{"document":{"slug":"rec-20260903-5236","title":"Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim Resource Adequacy Service et al","issued":"2026-09-03","accession":"20260903-5236","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Advanced Energy United","kind":"comments","file":"sources/filings/text/20260903-5236_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5236","tier":"record","sha256":"b7406e043a5b4d5ae280955aa8b6a44d80fc8708adf611e900bb27a75fc8aba4","pages":13,"tokens":3636,"emptyPages":[],"textThemes":["flex","adequacy","registry","cost"]},"pages":[{"page":1,"startToken":0,"endToken":340,"text":"1 \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n) \nPJM Interconnection, L.L.C    \n \n) \n \nDocket No. ER26-3515-000   \n \n) \n \n  \n \n \n \n \n \n \n \n \n \n \nCOMMENTS OF ADVANCED ENERGY UNITED  \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) \nRules of Practice and Procedures,1 Advanced Energy United2 (“United”) submits these \ncomments in response to PJM Interconnection, L.L.C.’s (“PJM”) revisions to the PJM Open \nAccess Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load \nServing Entities (“RAA”) to establish the Interim Resource Adequacy Service (“IRAS”).3 United \nneither opposes nor supports PJM’s August 13, 2026, filing as a means to address the system \nreliability issues as New Large Loads connect to the PJM system faster than new supply can be \nbrought online. United recognizes and agrees with the rationale behind IRAS: New large loads \nthat are contributing to the region’s resource adequacy shortfall, i.e., those that do not bring their \nown new capacity, should be the first to face curtailment if and when load shed is needed. \nHowever, IRAS as proposed leaves several important questions unresolved, particularly with \nrespect to how a New Large Load’s efforts to reduce its own footprint and secure its own \ncapacity are actually credited against its curtailment exposure, and whether IRAS’s central \n \n1 18 C.F.R. § 385.211 \n2 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean, \nand affordable. Advanced Energy United is the only industry association in the United States that represents the full \nrange of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes \nenergy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. The \nviews expressed in these comments reflect the position of Advanced Energy United, but do not necessarily reflect \nthe views of any particular member with respect to any issue. \n3 PJM Interconnection, L.L.C. “Proposal to Establish Interim Resource Adequacy Service and a Large Load \nRegistry to Address System Reliability” Docket No. ER26-3515-000 (filed August 13, 2026) (“Transmittal Letter”)"},{"page":2,"startToken":340,"endToken":624,"text":"2 \nincentive, to induce new large loads to avoid curtailment by bringing new capacity, can be \ndelivered at all given PJM’s own acknowledged lack of authority over retail-level curtailment \nand compensation decisions. United’s comments below identify areas of uncertainty or concern \nand offer specific clarifications and commitments PJM and the Commission should require \nbefore this proposal takes effect. \nI. \nINTRODUCTION \n \nPJM is navigating a genuinely difficult situation, and IRAS reflects real effort to design a \nworkable response to New Large Loads connecting to the PJM system faster than new supply \ncan be brought online. United and its members have been active participants throughout the \nCritical Issue Fast Path (“CIFP”) stakeholder process leading to both the RBP and IRAS filings, \nand IRAS reflects meaningful refinement from the concepts PJM initially floated through that \nprocess.  \nHowever, the IRAS mechanism as proposed leaves important questions unresolved, \nparticularly with respect to how a New Large Load’s efforts to reduce its own footprint and \nsecure its own capacity are actually credited against its curtailment exposure, and how retail-\nlevel cost allocation and compensation will be implemented consistent with the Commission’s \njurisdictional limits. United urges the Commission to direct PJM to act on these issues promptly, \nboth to ensure IRAS functions as the fair, incentive-aligned mechanism it is meant to be, and to \navoid creating a gap between wholesale design and retail-level outcomes. \nUnited does not oppose the concept of a curtailment and BYONC mechanism as a \nnecessary tool to manage an urgent reliability challenge, but United’s support for the specific \napproach taken in IRAS is tempered by a fundamental issue: PJM’s proposal assumes a degree \nof control over retail-level curtailment outcomes that PJM itself does not actually have. As"},{"page":3,"startToken":624,"endToken":923,"text":"3 \ndiscussed further below, PJM can designate an aggregate megawatt figure for a zone or area, but \nit is states and Electric Distributors, not PJM, who determine which specific loads are ultimately \ncurtailed. United urges the Commission to treat that jurisdictional reality as central to evaluating \nIRAS, not as a detail to be resolved later at the retail level. \nII. \nCOMMENTS \n \nUnited respectfully identifies the following specific clarifications and commitments \nneeded to ensure IRAS achieves its intended purpose without creating unnecessary barriers to the \nvery loads and resources best positioned to help close PJM’s resource adequacy gap. \nA. Peak Shaving Adjustment Should Be Credited in the Eligible New Large \nLoad Amount Formula \nThe Large Load Registry tracks each load’s Peak Shaving Adjustment value, but the \nEligible New Large Load Amount formula that determines a load’s IRAS curtailment exposure \ncredits only BYONC and Allocated RBP UCAP MW.4 As a result, a load that has taken \nconcrete, state-sanctioned steps to reduce its own contribution to peak demand receives no \nreduction in its IRAS curtailment exposure, the same practical result as a load that has done \nnothing at all to address the shortfall it is helping to cause. \nPeak Shaving Adjustment is not a novel mechanism specific to this filing. It is an existing \ntool under Tariff, Attachment DD-2, available to any end-use customer whose load reduction is \nauthorized under a state-codified program, and it predates IRAS entirely.5 PJM’s decision to add \nPeak Shaving Adjustment as a tracked field in the Large Load Registry accordingly reflects \nPJM’s own judgment that this value is relevant to a New Large Load’s profile and its capacity \n \n4 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, \n2026); Transmittal Letter at 37. \n5 Transmittal Letter at 65."},{"page":4,"startToken":923,"endToken":1217,"text":"4 \nneeds. Having made that judgment, PJM should complete the logical next step and ensure the \nvalue it has chosen to track actually affects the calculation that matters most to the load: its \nexposure to curtailment. \nThis is the same gap United’s RBP comments identify with respect to the RBP peak-\nshaving opt-out, and United’s RBP comments recommend the Commission direct PJM to amend \nthe Eligible New Large Load Amount formula in this proceeding.6 This docket is where that \nrecommendation must be resolved. United requests that the Commission direct PJM to revise the \nEligible New Large Load Amount calculation to expressly deduct verified Peak Shaving \nAdjustment MW attributable to a New Large Load and comparable state-authorized reductions. \nPJM should apply the deduction only to Peak Shaving Adjustment MW attributable to a New \nLarge Load and not already reflected in the load forecast as of the IRAS tariff filing date (August \n13, 2026), or already reflected in the BYONC quantity, or another capacity adjustment.  \nUnited does not propose that PJM independently determine whether a Peak Shaving \nAdjustment or comparable demand reduction satisfies the requirements of the applicable state-\nauthorized program; consistent with the jurisdictional framework discussed further below, that \ndetermination appropriately rests with the relevant state and Electric Distributor administering \nthe program. PJM should, however, retain its existing role in determining the MW value of a \nqualifying Peak Shaving Adjustment. United therefore requests that PJM’s Tariff specify that the \ndeduction under this formula for a qualifying Peak Shaving Adjustment or comparable state-\nauthorized reduction shall equal the MW value calculated and verified by PJM pursuant to its \napplicable procedures. This approach would avoid duplicative qualification review by PJM while \n \n6 Comments of Advanced Energy United, Docket No. ER26-3380-000, at 7 (filed Aug. 21, 2026)."},{"page":5,"startToken":1217,"endToken":1533,"text":"5 \nensuring that the amount of the deduction is based on the same PJM-determined and \nperformance-adjusted MW value used to reflect the program in the load forecast. \nB. Opportunities for DR/DER Aggregation as BYONC Should be Clarified and \nExpanded \ni. PJM Should Clarify or Revise what counts as “New” DR/DER \nBYONC \nPlanned Demand Resource and Planned DER Capacity Aggregation Resources are \neligible as BYONC, an important recognition of demand-side value.7 These resources are among \nthe most affordable and fastest to deploy, making them well situated to meet the speed-to-power \nimperative facing the PJM region. However, this eligibility is limited by the failure of the \nBYONC framework to clarify what qualifies as “new” capacity for purposes of satisfying the \nBYONC requirement. As proposed, DR/DER BYONC eligibility is limited to sites not registered \nin or before the 2026/2027 Delivery year, or to incremental capacity tied to newly registered \ngeneration or storage assets.8 This registration-based text excludes a site that has previously \nparticipated, went dormant, and is now capable of providing the same incremental value. In \ncontrast, generation and storage can satisfy BYONC through Capacity Interconnection Rights \ntransferred from a deactivated resource or through repowering a generator that retired before \nApril 10, 2026.9 This provision is, appropriately, intended to allow new capacity from new \ngeneration and storage assets at existing sites; this pathway to bring on new capacity at existing \nsites has no demand-side counterpart. The treatment of future IRAS periods in PJM’s proposed \ntariff revisions similarly lacks clarity. PJM has proposed a separate eligibility test for DR/DER \n \n7 Proposed Tariff, Attachment DD-4, §§ VI(b)(ii)(1)-(2); Transmittal Letter at 54-55. \n8 Tariff Attachment DD-4, Revisions to the PJM Open Access Transmission Tariff and Resource Adequacy \nAgreement (Marked/Redline Format), Docket No. ER26-3515, at § VI(b)(ii)(1)-(2) (Aug. 13, 2026).  \n9 Tariff Attachment DD-4, at § VI(b)(i)."},{"page":6,"startToken":1533,"endToken":1837,"text":"6 \nBYONC once the system exits and later re-enters an IRAS posture,10 but this eligibility test \nappears inconsistent; on plain reading the language precludes any site, new or reactivated, from \nqualifying at all in a future IRAS period. PJM should clarify that DR/DER BYONC eligibility, \nlike generation BYONC eligibility, turns on incremental capacity value provided to the system \nrather than solely on a site’s registration history, consistent with the incremental capability \nstandard discussed below. \nIn summary, United requests that PJM create a clear mechanism for reactivated DR/DER \nsites to be considered “new” for BYONC, comparable to reactivated generation, without \ncategorically excluding aggregations that participated before the 2026/2027 Delivery Year. \nii. PJM Should Clarify that Demand-Side DER can Substitute \nIndividual Sites or Customers \n \nUnited additionally requests affirmative clarification that demand-side BYONC should \nhave the option to substitute a departing site or customer for an equivalent new one.11 PJM \nrequires the Accredited UCAP value of a Demand Resource or DER Capacity Aggregation \nResource to “be demonstrated each year for a 10-year period” using the installed capacity the \nresource had in its first Delivery Year.12 This requirement should not preclude a DER \nAggregator whose portfolio loses a site to ordinary customer turnover, relocation, sale, or non-\nrenewal from replacing that site and preserving its arrangement, such that its portfolio would \ncontinue to reflect the same installed capacity it started with.  \nThe absence of a substitution mechanism would force a DER Aggregator to either hold a \nshrinking, non-compliant portfolio as sites depart, or exit the arrangement altogether. This \nconsequence would fall with particular force on residential DER aggregators, since their \n \n10 Attachment DD-4, at § VI(b)(ii)(1)–(2). \n11 Proposed Tariff, Attachment DD-4, § VIII(a)-(b); Transmittal Letter at 55-56. \n12 Proposed Tariff, Attachment DD-4, § VIII(c); Transmittal Letter at 66-67."},{"page":7,"startToken":1837,"endToken":2113,"text":"7 \nportfolios consist of hundreds or thousands of individually enrolled households rather than a \nhandful of commercial or industrial facilities, and they experience predictable, ongoing customer \nturnover as a structural feature of the business, not an edge case a one-off substitution request \ncould address.13 Aggregators are eminently capable of managing this turnover by bringing in \nnew customers if given a mechanism to do so.  \nUnited therefore requests that PJM confirm that annual compliance will be measured at \nthe aggregation level, rather than requiring the same individual customer locations to remain \nenrolled for ten years. Residential DER portfolios experience routine customer additions and \ndepartures. That turnover does not reduce reliability when the aggregator maintains the required \naggregate capacity and performance. FERC should ensure PJM expressly permits a DER \nAggregator to add, remove, or substitute Component DERs during the commitment term without \nlosing BYONC status or jeopardizing its annual demonstration obligation. Substitutions should \nremain subject to applicable registration, distribution-system review, measurement, and anti-\ndouble-counting requirements. This clarification would preserve the ten-year capacity \ncommitment without converting it into an impractical ten-year commitment by each household. \niii. IRAS Must Accommodate DER Aggregations as Aggregations  \nIRAS should expressly recognize DER Aggregation Resources participating under PJM’s \nCommission-approved Order No. 2222 framework, consistent with the aggregation level \ntreatment requested above. PJM should provide a transition path for Planned DER Capacity \nAggregation Resources that begin under the IRAS framework and later enter PJM’s Order No. \n2222 participation model. That transition should not terminate BYONC eligibility if the \naggregation maintains its committed capacity and satisfies the applicable market requirements. \n \n13 Comments of Advanced Energy United, Docket No. ER26-3380-000, at 20-21 (filed Aug. 21, 2026)."},{"page":8,"startToken":2113,"endToken":2382,"text":"8 \niv. PJM Should Create Additional DR Products to Expand the Role of \nDR in Addressing the Region’s Capacity Shortfall \n \nSome customers—including New Large Loads—may have the ability and willingness to \nparticipate as DR if given additional options to do so, specifically limited duration DR products \nthat would carry more manageable curtailment risk given their particular customer profile. \nOutside of this proceeding, United recommends that PJM separately develop additional DR \nproduct options, calibrated to a capped number of event hours per year, that would expand \navailable DR in the PJM region, including allowing a New Large Load to self-provide a \nmeaningful share of its BYONC obligation through its own demonstrated ability to curtail or \nshift load during those hours. \nA capped-hours structure of this kind would expand the types of customers willing and \nable to participate as DR and would give New Large Loads a lower-cost, faster-to-implement \noption for satisfying part of their BYONC obligation, particularly during the multi-year window \nbefore new generation or storage can realistically come online, without requiring the load to \ncurtail an unlimited or unpredictable number of hours annually.  \nThis ask sits outside the instant proceeding but would meaningfully contribute to PJM’s \nability to address its resource adequacy shortfall, and would give New Large Loads another tool \nto support that goal. \nC. IRAS Includes Important Elements That Should Be Maintained  \nUnited supports several elements of IRAS that will promote fair outcomes and recognize \nthe standing value of demand-side and alternative capacity solutions and urges that these \nelements be maintained in IRAS or any successor curtailment and Bring Your Own New \nCapacity (\"BYONC\") framework."},{"page":9,"startToken":2382,"endToken":2715,"text":"9 \nFirst, BYONC's gating criteria explicitly recognizes incremental capacity created through \nthe utilization of Surplus Interconnection Service as qualifying new capacity,14 a more \npermissive approach than PJM's own RBP proposal, which excludes SIS-based resources from \nselling into the RBP. United’s comments in the RBP proceeding also identified several critical \nbarriers to full utilization of SIS that should be addressed separate from these two proceedings.15 \nSecond, PJM should likewise be commended for locking a BYONC arrangement's \nAccredited UCAP value at whatever the resource clears in the RPM Auction for the first \nDelivery Year of the arrangement, fixed for the full 10-year term, rather than subject to ongoing \nre-accreditation.16  This is the right design choice, and stands in useful contrast to RBP, where \nresources remain exposed to unhedgeable ELCC risk in revenue settlement for the life of the \nterm, an issue United's RBP comments raise directly.17 \nThird, BYONC's inclusion of Planned Demand Resource and Planned DER Capacity \nAggregation Resources as eligible new capacity is likewise an important recognition of demand-\nside value,18 though additional clarity and flexibility is needed, as discussed above. Likewise, the \nLarge Load Registry's tracking of Peak Shaving Adjustment values is a positive concept,19 \nthough it is currently undermined by the Eligible New Large Load Amount formula, as discussed \nabove. \nIII. \nRETAIL COST ALLOCATION AND STATE COORDINATION \nAs stated above, United supports the goal of IRAS: to incentivize new large loads to \nbring their own new capacity, and to ensure that those that do not, and that thus contribute to the \n \n14 Proposed Tariff, Attachment DD-4, § VI(b)(i)(3); Transmittal Letter at 54. \n15 See Comments of Advanced Energy United, Docket No. ER26-3380-000, at 4 (filed Aug. 21, 2026). \n16 Proposed Tariff, Attachment DD-4, § VII(d); Transmittal Letter at 65-66. \n17 See Comments of Advanced Energy United, Docket No. ER26-3380-000, at 7-11 (filed Aug. 21, 2026). \n18 Proposed Tariff, Attachment DD-4, §§ VI(b)(ii)(1)-(2); Transmittal Letter at 54-55. \n19 Transmittal Letter at 37."},{"page":10,"startToken":2715,"endToken":3048,"text":"10 \nregion’s resource adequacy shortfall, should be the first to face curtailment if and when load shed \nis needed. But United is concerned that the entire incentive structure of IRAS rests on a premise \nthat PJM’s own filing does not itself deliver: that a New Large Load bringing sufficient BYONC \nwill actually be protected from curtailment. Eliminating or tightening the gap between PJM \nimplementation and state curtailment will be critical to success of IRAS. Specifically, PJM \ndesignates only an aggregate megawatt figure for each Electric Distributor zone or area. This is \nexplicit in the filing, in which PJM says that it “will identify only aggregate MW values that \nneed to be reduced,” while “Electric Distributors, in coordination with the appropriate states \nand/or RERRAs, LSEs, and LSE customers will determine which loads should ultimately reduce \nsubject to IRAS.”20 PJM does not direct curtailment of a specific retail customer. That authority \nbelongs to the states and the Electric Distributors that operate under state jurisdiction, consistent \nwith the FPA’s traditional divide between wholesale and retail regulation. \nThis is not a peripheral detail, it is the lynchpin of whether IRAS functions as designed. \nA New Large Load that invests in BYONC does so because PJM’s Eligible New Large Load \nAmount formula promises that investment will reduce its exposure to curtailment. But PJM has \nno mechanism to ensure that promise is honored once an actual Interim Resource Adequacy \nAlert is called. Nothing in the proposed Tariff or RAA obligates an Electric Distributor, or the \nstate authority directing it, to actually exempt a load with sufficient BYONC from curtailment, or \nto curtail non-BYONC load first, when the Electric Distributor makes its own retail-level \ndetermination of which customers to reduce. But PJM has no mechanism, and by its own account \nno authority, to ensure that promise is honored once an actual Interim Resource Adequacy Alert \nis called.  A load could do everything IRAS asks of it and still have no assurance that the entity \n \n20 Id at 26."},{"page":11,"startToken":3048,"endToken":3363,"text":"11 \nactually flipping the switch will honor that effort. The compensation side of IRAS has the \nidentical structure: PJM sets a wholesale rate and Electric Distributors implement it “in \nconjunction with applicable state authorities and New Large Loads,”21 leaving open the same \nquestion of whether the load that reduced its exposure through BYONC is the load that actually \nreceives the benefit of that effort, whether measured in reduced curtailment or in compensation \nfor load actually reduced. \nThis same gap, wholesale design assuming an outcome only retail-level action can \nactually deliver, is one that United’s RBP comments already raise with respect to cost allocation, \nand United’s RBP comments state that this concern “applies with equal force to ensuring \nconsistency between RBP's cost-allocation and opt-out provisions and IRAS's curtailment \nmechanics.”22 But unlike cost allocation, which the states are well positioned to address, and \nwhich does not ultimately impact the outcomes of PJM’s implementation of RBP, here PJM is \ndelegating elements that are foundational to the function and impact of IRAS. This outcome \ncould have been avoided had PJM taken responsibility for curtailment of New Large Loads that \ndo not BYONC through adjustments to its own emergency procedures—while still allowing \nflexibility for states to take additional action to more precisely target curtailment at the retail \nlevel. \nIf the Commission approves IRAS as currently structured, United recommends that PJM \ncommit to monitoring and reporting on the extent to which states and Electric Distributors have \nadopted mechanisms, whether through the Virginia State Corporation Commission and Data \nCenter Coalition model-tariff process23 or comparable state-level efforts, that actually tie \n \n21 Id at 104. \n22 See Comments of Advanced Energy United, Docket No. ER26-3380-000, at 28 (filed Aug. 21, 2026). \n23 Letter from Chair Kelsey Bagot, Virginia State Corporation Commission, and Josh Levi, Data Center Coalition, to \nPaula Conboy and David Mills, PJM Interconnection, L.L.C. (June 30, 2026)."},{"page":12,"startToken":3363,"endToken":3594,"text":"12 \ncurtailment selection and compensation to BYONC status, so that there is no gap between the \ntreatment IRAS promises to a load that has committed to BYONC and the treatment that load \nactually receives, simply because the latter falls outside the Commission’s direct jurisdiction. \nAbsent that assurance, IRAS risks functioning as an incentive PJM has designed but cannot \nguarantee, with New Large Loads bearing the cost and effort of BYONC on the strength of a \nprotection no PJM-jurisdictional rule actually secures.  \n \nIV. \nCONCLUSION \n \nUnited recognizes the unfortunate reality that curtailment of new large loads may be \nnecessary to ensure reliability for existing customers in PJM as demand rises faster than supply \nand conceptually supports introduction of a mechanism to ensure that curtailment impacts those \ncustomers contributing to the resource adequacy shortfall through their own failure to bring new \ncapacity to the system. The clarifications and commitments identified in these comments are \noffered as opportunities to ensure IRAS achieves its intended purpose. United appreciates the \nCommission’s consideration of these comments and looks forward to continuing to work with \nPJM and other stakeholders as this proceeding moves forward. \nRespectfully submitted, \n \n \n \n \n \n \n \n/s/   Mike Haugh                             \n \n \n  \nCaitlin Marquis, Managing Director   \nMike Haugh, Director  \nJon Gordon, Senior Director \nKelsey Koenig, Associate \nAdvanced Energy United   \n1801 Pennsylvania Ave. N.W., Suite 410    \nWashington, D.C. 20006    \ncmarquis@advancedenergyunited.org   \nmhaugh@advancedenergyunited.org \njgordon@advancedenergyunited.org  \nkkoenig@advancedenergyunited.org"},{"page":13,"startToken":3594,"endToken":3636,"text":"13 \n \nCERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated this 3rd day of September, 2026. \n \n \n \n \n \n \n \n \n/s/ Mike Haugh"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":409,"startToken":0,"endToken":398},{"p":2,"at":409,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":367,"startToken":398,"endToken":683},{"p":3,"at":367,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":653,"startToken":683,"endToken":721},{"p":3,"at":653,"title":"A. Peak Shaving Adjustment Should Be Credited in the Eligible New Large","method":"printed heading","endPage":5,"endAt":167,"startToken":721,"endToken":1244},{"p":5,"at":167,"title":"B. Opportunities for DR/DER Aggregation as BYONC Should be Clarified and","method":"printed heading","endPage":8,"endAt":1434,"startToken":1244,"endToken":2330},{"p":8,"at":1434,"title":"C. IRAS Includes Important Elements That Should Be Maintained","method":"printed heading","endPage":9,"endAt":1450,"startToken":2330,"endToken":2599},{"p":9,"at":1450,"title":"III. RETAIL COST ALLOCATION AND STATE COORDINATION","method":"printed heading","endPage":12,"endAt":528,"startToken":2599,"endToken":3444},{"p":12,"at":528,"title":"IV. CONCLUSION","method":"printed heading","endPage":13,"endAt":6,"startToken":3444,"endToken":3595},{"p":13,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":281,"startToken":3595,"endToken":3636}]}