{"document":{"slug":"rec-20260903-5240","title":"Comments of Microsoft Corporation to the proposal of PJM Interconnection, L.L.C. to establish Interim Resource Adequacy Service and Large Load Registry","issued":"2026-09-03","accession":"20260903-5240","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Microsoft Corporation","kind":"comments","file":"sources/filings/text/20260903-5240_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5240","tier":"record","sha256":"6d4055d798782ef5ab61c95fc4acee16d6beab1b88e9f4d3f3bd95413420d501","pages":11,"tokens":2434,"emptyPages":[],"textThemes":["retail","registry","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":227,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n \nDocket No. ER26-3515-000 \n \nCOMMENTS OF MICROSOFT CORPORATION \n \nPursuant to the Federal Energy Regulatory Commission’s (“Commission’s”) notices \nin this proceeding,1 Microsoft Corporation (“Microsoft”) respectfully submits these \ncomments regarding PJM Interconnection, L.L.C.’s (“PJM’s”) proposal to establish Interim \nResource Adequacy Service (“IRAS”) and a Large Load Registry.2 Microsoft, an original \nsignatory of the Ratepayer Protection Pledge,3 supports measures to promote reliability and \nfair cost allocation, but urges the Commission to modify IRAS to align capacity charges with \nreliability benefits, recognize and protect existing retail utility contracts and project load \nramp schedules, provide transparent project-level information and correction rights, and \npreserve accurate investment signals and workable pathways for large retail customers like \n \n1 PJM Interconnection L.L.C., Notice Denying Extension of Time, Docket Nos. ER26-3515-\n000 (Sept. 2, 2026); PJM Interconnection L.L.C., Combined Notice of Filings #1, Docket Nos. ER26-\n3515-000 et al. (Aug. 14, 2026); PJM Interconnection L.L.C., Combined Notice of Filings # 2, \nDocket Nos. ER26-3515-000 et al. (Aug. 13, 2026).   \n2 PJM Interconnection, L.L.C., FPA Section 205 Filing of PJM Interconnection, L.L.C., \nDocket No. ER26-3515 (Aug. 13, 2026) (“IRAS Filing”).   \n3 See Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/."},{"page":2,"startToken":227,"endToken":498,"text":"2 \nMicrosoft to procure new resources. Microsoft supports the Protest filed by the Data Center \nCoalition in this docket.4 \nThe U.S. economy increasingly depends on an electric grid capable of serving the \ngrowing requirements of the digital economy, advanced manufacturing, and the expansion of \nelectrification across domestic transportation, heating/cooling, and industrial sectors. As set \nout in Microsoft’s Community First AI Infrastructure Investment Principles,5 Microsoft \nrecognizes that the expansion of datacenters performing cloud storage, cloud computing, and \nartificial intelligence operations requires significant investment in electric transmission and \ngeneration capacity, support for domestic supply chains, and innovative new tools and \ntechnologies that optimize grid operations. Microsoft itself is investing substantially in the \nelectric power sector. For example, Microsoft has entered into a 20-year power purchase \nagreement with Constellation Energy for the Crane Clean Energy Center, which is expected \nto deliver more than 800MWs of new carbon-free capacity and energy to the PJM grid.6 \nMicrosoft supports regulatory and tariff reforms that facilitate timely infrastructure \n \n4 PJM Interconnection, L.L.C., Motion to Intervene and Protest of the Data Center Coalition, \nDocket No. ER26-3515 (Sept. 3, 2026).  \n5 See Brad Smith, Building Community-First AI Infrastructure, MICROSOFT ON THE ISSUES \n(Jan. 13, 2026), https://blogs.microsoft.com/on-the-issues/2026/01/13/community-first-ai-\ninfrastructure/.  \n6 Bobby Hollis, Accelerating the addition of carbon-free energy: An update on \nprogress, MICROSOFT (Sept. 20, 2024), https://www.microsoft.com/en-us/microsoft-\ncloud/blog/2024/09/20/accelerating-the-addition-of-carbon-free-energy-an-update-on-progress/  \n(linking Constellation to Launch Crane Clean Energy Center, Restoring Jobs and \nCarbon-Free Power to the Grid, CONSTELLATION (Sept. 20, 2024), \nhttps://www.constellationenergy.com/news/2024/Constellation-to-Launch-Crane-Clean-Energy-\nCenter-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html)."},{"page":3,"startToken":498,"endToken":752,"text":"3 \ndevelopment, improve coordination, and provide durable and transparent market signals to \nenable new supply to meet the growing demand within the PJM region. \nMicrosoft commends PJM’s efforts to address ongoing resource adequacy challenges \nin the region. Microsoft also supports reforms that promote efficient investment, advance the \ndevelopment of new generation and transmission infrastructure, and allocate costs consistent \nwith cost-causation principles. Microsoft recognizes that improved coordination among PJM, \nelectric distribution companies, load-serving entities, state regulators, and large retail \ncustomers is a necessary first step as the region works to enhance load forecasting \ntransparency and accommodate projected load growth. \nI. \nCOMMENTS \nMicrosoft submits these comments to highlight concerns with several aspects of \nPJM’s IRAS proposal and to encourage the Commission to consider modifications that better \nadvance regional objectives.  First, PJM’s proposal requires certain large retail customers to \npay for capacity while exposing them to curtailment before compensated capacity resources \nare called upon to perform. Second, the proposal interferes with service expectations \nunderlying binding utility agreements and may substantially impair investments made under \nexisting retail and wholesale rules. Third, large retail customers currently lack sufficient \nvisibility into the load forecasts and project-level assumptions necessary for PJM to \ndetermine their exposure under IRAS and the Reliability Backstop Procurement (RBP). \nMicrosoft therefore urges the Commission to direct modifications that preserve the \nconnection between customer capacity payments and associated reliability benefits, protect \nexisting binding agreements for new load that has yet to ramp to the contracted-for capacity, \nand provide transparent and verifiable treatment of affected large retail loads. Additionally,"},{"page":4,"startToken":752,"endToken":1007,"text":"4 \nMicrosoft respectfully requests that PJM, the Commission, or both explain if RBP Unforced \nCapacity (UCAP) Offset MW under RBP can also serve a Bring Your Own New Capacity \n(BYONC) under IRAS. \nA. \nLarge Retail Customers Paying for Capacity Should Receive Reliability \nBenefits \nMicrosoft supports the principle that large retail customers benefiting from grid \nreliability should contribute appropriately to the costs of maintaining that reliability. \nMicrosoft also supports mechanisms that align growing demand with new resource \ndevelopment and provide large retail customers meaningful pathways to support the addition \nof new supply. Those principles must operate consistently in both the rates customers pay \nand the service they receive. \nPJM’s proposal requires Eligible New Large Loads to be curtailed before PJM \ninitiates certain load-management actions, including dispatch of Demand Response \nResources that have been compensated through the capacity market to reduce load when \nneeded.7 At the same time, the proposal does not clearly provide a corresponding reduction \nin the capacity-related charges paid by large retail customers subject to IRAS. Instead, PJM \nrelies on a separate IRAS compensation mechanism, the implementation of which is largely \nleft to Electric Distributors and state authorities. This creates a fundamental mismatch \nbetween cost and benefit: large retail customers may be required to pay for capacity while \nbeing interrupted before that capacity is used to preserve their service.  PJM has not \ndemonstrated why some retail customers that contracted for firm service should be \ninvoluntarily converted to a materially different service construct. Where a customer remains \n \n7 See IRAS Filing, at 100–01."},{"page":5,"startToken":1007,"endToken":1278,"text":"5 \nresponsible for capacity-related costs and transmission network service charges, the \nCommission should ensure that a load curtailment obligation is supported by an appropriate \ncustomer election, compensation mechanism, or corresponding adjustment in service rights \nand charges. \nMicrosoft is concerned that PJM has not demonstrated that IRAS is consistent with \ncost-causation principles and charges large retail customers for reliability benefits they will \nnot receive. Further, PJM has not explained how capacity charges, IRAS credits, and any \nstate-administered compensation will interact—information that is necessary for large retail \ncustomers to evaluate the full cost and reliability implications of the proposal. \nB. \nThe Proposal Upends Retail Contractual Commitments and Large Retail \nCustomers’ Reliance Interests on Those Arrangements.  \nMicrosoft is concerned with how IRAS changes the retail service framework \napplicable to projects where sponsors have already entered into binding utility arrangements \nand made substantial investment commitments. Large-load projects like Microsoft’s \ninvestments require years of planning and involve substantial commitments for land, \nconstruction, network infrastructure, electric facilities, generation procurement, and long-\nterm utility service. IRAS imposes requirements that could not reasonably have been \nanticipated when a large retail customer and utility entered into their agreement, causing \nabrupt, substantial impairment to the value of these long-lead time projects.  \nMany large load projects also ramp up over time rather than entering service at their \nfull contract demand. IRAS upsets existing commitments when some portion of its \ncontracted load ramps after the PJM-proposed cutoff date; The cut-off date is completely \narbitrary as to any particular phase of the large load project. Applying IRAS to later \nincrements of a phased project already covered by an executed agreement could divide a"},{"page":6,"startToken":1278,"endToken":1529,"text":"6 \nsingle facility into different service categories, further undermining settled commercial \nexpectations and imposing new retail service requirements that could not reasonably have \nbeen anticipated when the large retail customer and utility entered into their agreement. \nIf the Commission decides to proceed with IRAS, Microsoft requests that the \nCommission direct changes that provide a clear and effective transition mechanism that \nprotects large retail customers that executed binding utility agreements or made other \nsubstantial, demonstrable commitments they relied upon before PJM proposed IRAS. PJM's \nown proposed Large Load Registry recognizes that large load projects may have phased \nramp schedules and requires reporting of each increment's in-service date, peak load and \nramp schedule, and applicable contracts or service agreements.  The transition should \nrecognize the full contracted load and reasonable ramp schedule associated with an eligible \nproject, rather than protecting only the load energized before a single, arbitrary cutoff date \nwithout assessment of commercial implications. This approach would preserve legitimate \nreliance interests while maintaining appropriate obligations for genuinely new and \nunsupported load. \nC. \nTransparent, Project-level Information Is Necessary for Retail Customers \nTo Assess Their IRAS Exposure.  \nIRAS depends heavily on the load forecasts used to establish the relevant baseline \nand identify incremental load.8 Large retail customers, however, have limited visibility into \nhow electric distribution companies incorporate individual projects, contract quantities, and \nramp schedules into the forecasts underlying PJM’s proposal. Without that information, these \ncustomers are unable to assess which portions of their retail load may be considered \n \n8 See id., at 112–113."},{"page":7,"startToken":1529,"endToken":1810,"text":"7 \nincremental, whether contracted demand was fully reflected in the rolled-up load forecast, or \nwhat actions may be needed to limit curtailment and cost exposure. \nThis uncertainty is particularly consequential where utility forecasts appear to include \nless load than a large retail customer has committed to under an executed service agreement \nwith commercial obligations and firm commitments. A large retail customer should not face \ncurtailment or new capacity obligations because of forecasting practices of others that it was \nnever given the opportunity to verify or correct. Nor should large retail customers ever be \nrequired to make resource-procurement decisions without clear information regarding the \ndelivery years, megawatt quantities, and facilities potentially subject to IRAS. \nBefore IRAS is implemented, each potentially affected customer must be provided \nwith sufficient project-level information to verify how its load is represented in the \napplicable load forecast and Large Load Registry, including both load reflected in executed \nservice agreements and any additional forecasted load, and how any associated supply \narrangement will be credited. PJM must put into place a process to identify and correct \nforecasting and registry errors. PJM must also clearly distinguish among Qualifying \nReliability Backstop Procurement (“RBP”) Offset Unforced Capacity (“UCAP”) MW, \nallocated RBP UCAP MW, and Bring Your Own New Capacity (“BYONC”). These retail \ncustomer-specific determinations must be made sufficiently in advance of each Delivery \nYear so that affected large retail customers have a meaningful opportunity to procure \nqualifying supply, challenge errors, or adjust project plans before incurring curtailment risk.   \nAdditionally, PJM must explain whether and how the same resource may receive \nrecognition under both frameworks, the extent to which each designation reduces customer-\nspecific cost or curtailment exposure, and how resources with future commercial-operation"},{"page":8,"startToken":1810,"endToken":2089,"text":"8 \ndates will be treated during earlier Delivery Years.  For example, it is unclear from PJM’s \nsubmissions whether a resource that is used as Qualifying RBP Offset UCAP MW under \nRBP can also be used as BYONC under IRAS, assuming it meets all of the relevant criteria.9  \nThis is a critically important point of clarification as Microsoft and other large load \ncustomers look to make business decisions in the coming months.  Microsoft respectfully \nrequests that PJM and the Commission confirm that a resource may qualify and participate in \nboth programs.  The rules must ensure that large retail customers procuring qualifying new \ncapacity are not subject to duplicative charges. \nD. \nMicrosoft Supports Competitive Market Rules that Achieve Reliability \nwithout Undermining Signals for New Capacity Investment \nMicrosoft supports reforms that maintain reliability while facilitating the \ndevelopment of the generation and transmission infrastructure needed to serve growing \ndemand. A durable regulatory framework should create transparent pathways for customers \nto support new supply, recognize bilateral procurement and other qualifying resource \ncommitments, and facilitate competitive market signals that encourage timely resource entry. \nAny exclusion of new load from capacity-market demand should be carefully \nevaluated to ensure that market outcomes correctly signal the region’s actual long-term need \nfor capacity.  In Microsoft’s view, reliability reforms should align customer obligations, \nresource qualification rules, and capacity-market signals in a manner that supports both near-\nterm operational reliability and long-term supply development.  PJM has not yet cogently \nexplained why its proposal to exclude projected load from auction demand does not \nunderstate the region’s future capacity needs and mask signals necessary to attract new \n \n9 See Proposed Tariff, Attachment DD, Section 18.2; Proposed Tariff, Attachment DD-4, \nSection VI."},{"page":9,"startToken":2089,"endToken":2304,"text":"9 \ngeneration investment. Because the stated purpose of IRAS is to address resource adequacy \nconcerns associated with load growth, PJM should demonstrate how removing that same load \nfrom capacity-market demand is consistent with encouraging the supply additions needed to \nmaintain resource adequacy and reliability across the system over time.  \nII. \nCONCLUSION \nMicrosoft fully supports PJM’s objective of maintaining system reliability and agrees \nthat large retail customers should pay their fair share of the grid costs incurred to serve them. \nThe Commission should not, however, approve a tariff framework—and more generally, \nestablish regulatory precedents—that disconnect customer payments from reliability benefits, \ndisrupts binding utility arrangements and substantial investments made under existing rules, \nor determines large retail customer obligations through forecasts that customers cannot \nverify. \nFor these reasons, Microsoft respectfully requests that the Commission direct \nmodifications to (1) align curtailment priority and capacity charges with the reliability \nbenefits customers receive; (2) establish a meaningful transition to protect existing \ncontractual commitments and project ramp schedules; (3) provide transparent, project-level \ninformation and correction rights regarding IRAS exposure; and (4) preserve accurate market \nsignals and workable pathways for customers to support new resource development.   \nAdditionally, Microsoft respectfully requests that PJM, the Commission, or both explain if \nRBP UCAP Offset MW under RBP can also serve a BYONC under IRAS."},{"page":10,"startToken":2304,"endToken":2378,"text":"10 \nRespectfully submitted, \n \nDallas Harris \nPrinciple Corporate Counsel \nMicrosoft Corporation \nRedmond, WA 98052 \nEmail: dallasharris@microsoft.com \nTel: (909) 575-7320 \n \nJohn Greene \nSenior Program Manager, Energy \nRegulatory Affairs \nMicrosoft \n901 K St NW, Washington, DC 20001 \nEmail: john.greene@microsoft.com \nTel: (603) 620-0654 \n \n \n/s/ Jeffery Riles  \nJeffery Riles \nSenior Director of Energy Markets, Americas  \nMicrosoft Corporation \nOne Microsoft Way \nRedmond, WA 98052 \nEmail: jeffriles@microsoft.com \nTel: (425) 882-8080 \n \n \n \n \nDated: September 3, 2026"},{"page":11,"startToken":2378,"endToken":2434,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \n \nRespectfully submitted, \n/s/ Dallas Harris  \nDallas Harris \nPrinciple Corporate Counsel \nMicrosoft Corporation \nRedmond, WA 98052 \nEmail: dallasharris@microsoft.com \nTel: 909-575-7320 \n \n \n \nDated: September 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":755,"startToken":0,"endToken":596},{"p":3,"at":755,"title":"I. COMMENTS","method":"printed heading","endPage":4,"endAt":197,"startToken":596,"endToken":784},{"p":4,"at":197,"title":"A. Large Retail Customers Paying for Capacity Should Receive Reliability","method":"printed heading","endPage":5,"endAt":731,"startToken":784,"endToken":1105},{"p":5,"at":731,"title":"B. The Proposal Upends Retail Contractual Commitments and Large Retail","method":"printed heading","endPage":6,"endAt":1259,"startToken":1105,"endToken":1447},{"p":6,"at":1259,"title":"C. Transparent, Project-level Information Is Necessary for Retail Customers","method":"printed heading","endPage":8,"endAt":686,"startToken":1447,"endToken":1919},{"p":8,"at":686,"title":"D. Microsoft Supports Competitive Market Rules that Achieve Reliability","method":"printed heading","endPage":9,"endAt":349,"startToken":1919,"endToken":2138},{"p":9,"at":349,"title":"II. CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":2138,"endToken":2378},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":416,"startToken":2378,"endToken":2434}]}