{"document":{"slug":"rec-20260903-5241","title":"Comments of Old Dominion Electric Cooperative re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-03","accession":"20260903-5241","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Old Dominion Electric Cooperative","kind":"comments","file":"sources/filings/text/20260903-5241_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5241","tier":"record","sha256":"8bf33f8788442ac5d5e12febe2a4d55f065ee53210452bbf368533b068c90868","pages":11,"tokens":2943,"emptyPages":[],"textThemes":["registry","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":252,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \nCOMMENTS OF OLD DOMINION ELECTRIC COOPERATIVE \nI.\nINTRODUCTION \nOn August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) submitted revisions to the PJM \nOpen Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among \nLoad Serving Entities (“RAA”) for a proposed Interim Resource Adequacy Service (“IRAS”). \nIRAS, as described by PJM, is a “new supplemental capacity product”1 through which certain New \nLarge Loads may be directed to reduce their load when PJM determines necessary to address \npotential capacity emergencies or Interconnection Reliability Operating Limits (“IROL”) \nviolations. New Large Loads that do not have sufficient capacity of their own will qualify as \nEligible New Large Loads under IRAS.  \nThe IRAS filing also includes the following “foundational revisions”2 in order to facilitate \nIRAS: (1) clarification in the RAA that load serving entities (“LSEs”) are obligated to bring \nsufficient new capacity to cover New Large Loads or be subject to load reductions during \nEmergencies;3 (2) establishment of a Large Load Registry that PJM will maintain based on \ninformation to be provided by LSEs and Electric Distributors;4 and (3) revisions to the Tariff and \nRAA to include definitions for Large Load and New Large Load. Finally, PJM proposes, beginning \nwith the 2029/20230 Delivery Year, to exclude certain New Large Loads from the Variable \n1 PJM Transmittal Letter at 22. \n2 Id. at 3. \n3 Id. at 3-4. \n4 Id. at 3; 36-37."},{"page":2,"startToken":252,"endToken":541,"text":"2 \nResource Requirement (“VRR”) Curve in PJM’s Reliability Pricing Model (“RPM”) capacity \nmarket.5\nPJM requests that the Commission accept the IRAS filing effective October 12, 2026.6 In \norder to facilitate Commission acceptance as requested, PJM consents to the Commission’s \nexercise of authority to modify and/or sever any element of the proposed Tariff and RAA language \nto the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, \nLLC v. FERC,7 where such modification or severance is consistent with the objectives of PJM’s \nfiling.8\nODEC appreciates PJM’s efforts to address the impending reliability problem of \ninsufficient capacity as New Large Loads continue to connect to the PJM system. The IRAS filing \nis one component of PJM’s plan to address resource adequacy issues, that includes the recent \nReliability Backstop Procurement (“RBP”) proposal currently pending before the Commission in \nDocket No. ER26-3380-000. ODEC is generally supportive of the IRAS proposal. However, as \ndiscussed in these comments, certain elements of PJM’s IRAS proposal raise concerns for ODEC \n– namely certain aspects of the Large Load Registry and the IRAS load reduction proposal. Other \nelements of the IRAS proposal require further clarification or explanation, including the definition \nof New Large Load, compensation for IRAS load reductions, and the treatment of Bring Your \nOwn New Capacity (“BYONC”). \nPursuant to the Combined Notice of Filings #1 issued August 13, 2026, ODEC submits \nthese comments on PJM’s IRAS proposal. In support of its request for the Commission to direct \nPJM to address ODEC’s concerns, ODEC states as follows: \n5 Id. at 5. \n6 Id. at 8. \n7 Id. at 9, citing NRG Power Marketing, LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017). \n8 Id. at 9."},{"page":3,"startToken":541,"endToken":848,"text":"3 \nII.\nCOMMENTS \nA. PJM’s proposed Large Load Registry requires LSEs to provide information they \nmight not be able to obtain and might warrant enhanced confidentiality \nprotection.  \nPJM proposes to establish a Large Load Registry that will be used to facilitate \nimplementation of IRAS, among other purposes.9 The Large Load Registry is a key component of \nPJM’s IRAS proposal, since the Large Load Registry will be used by PJM “to determine the \nquantity of New Large Loads by zone/area and allocate IRAS responsibility to each zone/area \naccordingly . . .”10 ODEC agrees with the concept of a Large Load Registry to provide transparency \nand consistent, verified information regarding New Large Loads. ODEC also agrees that the Large \nLoad Registry is generally consistent with the Commission’s June 2026 Order to Show Cause \nregarding large loads, where the Commission determined that PJM’s Tariff appeared to be unjust \nand unreasonable absent provisions “that would require PJM and the Transmission Owners to \npublicly post and regularly update data that details (1) aggregate amounts of proposed large load \nadditions in PJM’s footprint. . .”11\nAs an initial matter, PJM should clarify whether its proposed RAA revisions would require \nLSEs to provide the Large Load Registry information. The IRAS transmittal letter states that “PJM \nis proposing that LSEs submit information to PJM about the Large Loads they serve”12 and that \nPJM may obtain information from Electric Distributors and Transmission Owners. PJM also states \nthat it proposes to hold LSEs primarily responsible for providing information for the Large Load \n9 See Proposed RAA Schedule 11, section B.3. (“The information provided . . . will be used . . . for purposes \nincluding but not limited to implementation of [IRAS] . . .”). \n10 PJM Transmittal Letter at 28-29. \n11 Id. at 48, citing PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 76 \n12 PJM Transmittal Letter at 36."},{"page":4,"startToken":848,"endToken":1238,"text":"4 \nRegistry beginning as early as next March.13 The proposed RAA would require that “[e]ach Party \nshall submit, or cause to be submitted” the information related to each Large Load Served by the \nParty.14 The RAA defines “Party” as “an entity bound by the terms of the Operating Agreement.”15\nThe PJM Operating Agreement is binding on entities that are Members,16 and Members are defined \nas those who satisfy the Membership Requirements at Operating Agreement section 11.6.17\nOperating Agreement section 11.6, in turn, provides, in part, that to qualify as a Member, an \nApplicant shall be a Transmission Owner, Generation Owner, an Other Supplier, an Electric \nDistributor, or an End-Use Customer.18 Thus, it is not clear that the IRAS provisions obligate LSEs \nto provide the Load Registry information. PJM should clarify the proposed RAA as necessary. \nNotwithstanding support for the concept of the Large Load Registry, ODEC is concerned \nthat PJM’s proposal will at least create obligations that LSEs cannot satisfy and could subject LSEs \nlike ODEC to enforcement actions. PJM states in its filing that “each piece of information is a \nnecessary component to the Large Load Registry . . .”19 The proposed RAA revisions obligate \nLSEs to provide the information, without any provision for an LSE to notify PJM if the LSE cannot \nobtain the information in the time period required or at all. ODEC has reviewed the list of \ninformation that PJM proposes to require from each LSE and ODEC has identified certain \ninformation that ODEC does not have access to at this time nor is ODEC certain it can obtain. \n13 PJM’s proposed RAA, Schedule 11, section B.2, requires that the Large Load Registry information be \nprovided by “[e]ach Party serving or contracted to serve a Large Load . . .” \n14 PJM’s proposed Tariff Attachment RAA, Schedule 11, section B.1(a). \n15 PJM RAA, Article 1 – Definitions. \n16 See Operating Agreement, section 17.1.3 (providing that the Operating Agreement “constitutes the legal, \nvalid and binding obligation” of Members who execute the Operating Agreement.). \n17 Id., Definitions M-N. \n18 PJM Operating Agreement, section 11.6(a)(i). Operating Agreement section 11.6(b) also provides that \n“[c]ertain Members that are Load Serving Entities are parties to the Reliability Assurance Agreement.” \n19 PJM Transmittal Letter at 37 (emphasis added)."},{"page":5,"startToken":1238,"endToken":1624,"text":"5 \nBelow is the list of information that PJM proposes to require LSEs to provide. 20 Information that \nODEC is uncertain that it will be able to obtain is indicated in bold font, with explanation as \nwarranted: \n1.\nDescription of Large Load; \n2.\nLocation(s) (Control Zone, Electric Distributor zone/area, where a zone/area is an \narea within a Zone for which the relevant Electric Distributor specifies a separate \nObligation Peak Load MW value. A zone/area is a service area of an Electric \nDistributor that is a separately identifiable, geographic area bounded by wholesale \nmetering) \n3.\nIn-service date for each increment of load; \n4.\nPeak shaving adjustment value pursuant to a state program codified in state law and \nwhether and how it meets the requirements of Tariff, Attachment DD-2; \n5.\nDelivery point / Point(s) of interconnection (include all if more than one); \n6.\nPeak load quantity (MW) and ramp schedule, if applicable; \n7.\nTelemetry specifications - ; \n8.\nBYONC quantity (MW) and ramp schedule, if applicable – As discussed above, \nODEC might not have timely information regarding the end-use customer and in \nthose instances, ODEC might not be able to obtain information regarding BYONC; \n9.\nAllocated RBP UCAP MW quantity (MW), if applicable - As discussed above, \nODEC might not have timely information regarding the end-use customer and in \nthose instances, ODEC might not be able to obtain information regarding allocated \nRBP UCAP MW quantities; \n10.\nBackup generation (MW), including fuel type and relevant permitting limitations; \n11.\nContracts or service agreements between the Large Load and the LSE – Large \nLoads as end-use customers will likely have contracts or service agreements with \nODEC’s member distribution cooperatives, not ODEC. Therefore, ODEC is \nuncertain that PJM or ODEC can require disclosure regarding these agreements; \n12.\nPoints of contact at the applicable Transmission Owner, Electric Distributor, and \nLoad Serving Entity;  \n13.\nEMS B1/B2/B3 name (for the applicable Transmission Owner, Electric \nDistributor); and \n14.\nAdditional details and contents as necessary, in accordance with the PJM \nManuals – ODEC and other LSEs should not be obligated to provide yet-to-be \ndetermined information, as part of the RAA. Instead, to the extent further \ninformation may be necessary, it should either be detailed in the RAA or, \nalternatively, requested on a “best efforts” basis through the Manuals. \n20 Proposed RAA Schedule 11, Section B.1.(a)."},{"page":6,"startToken":1624,"endToken":1979,"text":"6 \nIn addition to these requirements, PJM proposes to require LSEs to promptly inform PJM \nof any change in the above-mentioned information.21 Here again, LSEs may not receive such \nnotification and may not have ready access to changes in the required information. The obligation \nand risk imposed on LSEs by PJM’s proposal is significant. Not only does PJM place the \nresponsibility on LSEs to ensure aspects of PJM’s IRAS that are foundational to the success of \nIRAS,22 but PJM emphasizes in its filing that LSEs’ reporting of information for the Large Load \nRegistry subjects LSEs to the full extent of the Commission’s enforcement authority for the duty \nof candor and the prohibition against false or misleading statements.23 To the extent LSEs are \nacting in good faith and simply unable to provide information that they cannot obtain, LSEs should \nnot be subject to the threat of an enforcement action. While PJM’s need for complete and accurate \ninformation is justifiable, placing the full burden on LSEs to ensure access to information that they \nsimply may not be able to obtain, under threat of enforcement actions, is not. Instead, PJM should \nchange its RAA to (1) require LSEs to provide the information that they are able to obtain with \nreasonable efforts or due diligence; (2) require LSEs to promptly identify information that they are \nnot able to obtain; and (3) change the provisions regarding PJM’s possible coordination with \nTransmission Owners and Electric Distributors as needed.24\n21 Proposed RAA, Schedule 11, section B.2.(c). \n22 PJM Transmittal Letter at 43-44 (“The information provided in the Large Load Registry will form the \nfoundation for an accurate, complete, and reliable database that will inform, inter alia, decisions about the \nMW quantify of new Large Loads that is available to provide IRAS in a Delivery Year.”). \n23 PJM Transmittal Letter at 44-45. \n24 See PJM Transmittal Letter at 26-27 (“. . . the initial obligation to submit data to PJM is on the LSE \nserving the Large Load, but in order to increase the accuracy of the registry, PJM finds valuable—and \nneeded—the information available to the Electric Distributors.”)."},{"page":7,"startToken":1979,"endToken":2300,"text":"7 \nB. PJM should revise its IRAS load reduction framework. \nPJM proposes to require Electric Distributors to execute PJM’s directives to reduce load \nduring Interim Resource Adequacy Service Actions.25 PJM’s IRAS does not consider how the load \nreductions will need to be carried out.26 Electric Distributors may not have the necessary \nequipment on site with all New Large Loads in order to require the load reductions and/or verify \nthe load reductions are executed as directed. For example, where colocated loads are served behind \na generator’s point of interconnection. Therefore, while having the Electric Distributor responsible \nmight provide the necessary system stabilization, it will not be possible where the Electric \nDistributor does not have equipment to execute the load reduction. An alternative would be to \nrequire the assistance of Transmission Owners in executing IRAS load reductions. However, load \nreductions at the higher voltage levels (e.g., 230 kV) will result in larger MW reductions of load, \nwhich could destabilize the transmission system if multiple New Large Loads need to be reduced \nsimultaneously. \nAs a reasonable alternative to PJM’s proposal to hold Electric Distributors solely \nresponsible for executing New Large Load reductions for an Interim Resource Adequacy Service \nAction, PJM should consider its role and authority to initiate Interim Resource Adequacy Service \nActions, as such is “an ‘Operating Instruction, as defined by NERC.’”27 PJM should use its existing \nauthority as defined by NERC, as well as authority that may be developed as part of NERC’s \ncomputational loads/large loads standard in development, to determine PJM’s ability to coordinate \nwith Electric Distributors and/or relevant state entities (perhaps RERRAs) to execute Interim \n25 PJM Proposed Tariff Attachment DD-4, Section III. (a). \n26 See PJM Transmittal Letter at 75-76 (“The details as to how and when PJM may call an Interim Resource \nAdequacy Service Action will be set forth in PJM Manual 13.”) \n27 PJM Transmittal Lettera t 75 (citation omitted)."},{"page":8,"startToken":2300,"endToken":2583,"text":"8 \nResource Adequacy Service Action load reductions. The entirety of this obligation should not be \nleft to Electric Distributors. \nFurther, PJM’s filing addresses the reliability and other benefits of load reductions. \nHowever, PJM has not addressed how Interim Resource Adequacy Service Action load reductions \nwill be assessed and executed in a manner to minimize or avoid adverse transmission or \ndistribution system conditions. PJM should provide clarification regarding how voltage stability \nimpacts will be evaluated and which entity will be ultimately responsible for ensuring that Interim \nResource Adequacy Service Action load reductions do not create adverse transmission or \ndistribution system conditions. \nC. PJM should provide additional clarifications regarding its proposed IRAS. \nIn addition to the changes discussed above, certain elements of PJM’s IRAS should be \nfurther clarified so that the Commission can ensure the proposal is just and reasonable, and so that \nmarket participants have certainty regarding the IRAS.  \nFirst, the definition of Large Load should be clarified. PJM proposes to define Large Load \nas follows: \nend-use customer(s) load that has a cumulative peak load of 50 megawatts or \ngreater at a single electrical site behind one or more points of interconnection, \nwhere for configurations involving multiple affiliated load facilities or multiple \npoints of interconnection with affiliated load facilities behind them, all affiliated \nload facilities within a one-mile radius will be considered a single electrical site as \nfurther described in the PJM Manuals. \nODEC agrees that the definition should include affiliated load facilities. However, PJM’s \nfiling does not provide how affiliation will be determined for purposes of the one-mile radius \nmeasurement. For example, where facilities are owned by separate legal entities within the same \ncorporate family, does common control deem the entities affiliates?"},{"page":9,"startToken":2583,"endToken":2859,"text":"9 \nSecond, PJM’s Tariff provisions for IRAS compensation should clarify that such \ncompensation will be limited to Eligible New Large Loads that are incurring capacity costs. PJM \nexplains that its IRAS compensation will be implemented by Electric Distributors, in conjunction \nwith applicable state authorities and New Large Loads.28 PJM further explains that “the IRAS rate \nis intended to be conjoined with retail rates and ultimately paid to Eligible New Large Loads that \nreflect a discount on capacity costs commensurate with the impact of Interim Resource Adequacy \nService on addressing resource adequacy issues.”29 The proposed Tariff provisions, however, do \nnot explicitly state this condition that compensation will only be paid to Eligible New Large Loads \nthat are charged capacity costs. PJM should provide such clarification in its Tariff provisions. \nThird, PJM’s proposal for BYONC appears to allow a New Large Load in one zone to be \nsupported by BYONC located in another zone. However, PJM has not explained how BYONC \nwill impact RPM locational deliverability and market modeling assumptions, including CETL, \nCETO, LDA demand curves or capacity price separation. PJM should provide such clarification. \nIII.\nCONCLUSION \nWHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider \nthese comments in its determination of the PJM IRAS proposal and if the Commission accepts \nPJM’s filing, direct PJM to (1) modify the Large Load Registry as provided in section II.A. above; \n(2) modify the IRAS load reduction framework as discussed in section II.B. above, and (3) clarify \nthe definition of Large Load, IRAS compensation and treatment of BYONC, as discussed in \nsection II.C. above.  \n28 PJM Transmittal Letter at 104 (emphasis added). \n29 Id."},{"page":10,"startToken":2859,"endToken":2901,"text":"10 \nRespectfully submitted, \n /s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C. 20006-1167 \n(202) 585-6900 \n(202) 585-6969 (fax) \naclair@thompsoncoburn.com  \nAttorney for Old Dominion Electric \nCooperative \nDated: September 3, 2026"},{"page":11,"startToken":2901,"endToken":2943,"text":"CERTIFICATE OF SERVICE \nI hereby certify that on this 3rd day of September 2026, I have caused a copy of the \nforegoing to be served upon each party designated on the Commission’s Official Service List for \nthis proceeding. \n /s/Adrienne E. Clair"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":184,"startToken":0,"endToken":25},{"p":1,"at":184,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":3,"startToken":25,"endToken":542},{"p":3,"at":3,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":17,"startToken":542,"endToken":544},{"p":3,"at":17,"title":"A. PJM’s proposed Large Load Registry requires LSEs to provide information they","method":"printed heading","endPage":7,"endAt":3,"startToken":544,"endToken":1980},{"p":7,"at":3,"title":"B. PJM should revise its IRAS load reduction framework.","method":"printed heading","endPage":8,"endAt":721,"startToken":1980,"endToken":2400},{"p":8,"at":721,"title":"C. PJM should provide additional clarifications regarding its proposed IRAS.","method":"printed heading","endPage":9,"endAt":1225,"startToken":2400,"endToken":2768},{"p":9,"at":1225,"title":"III. CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":2768,"endToken":2901},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":246,"startToken":2901,"endToken":2943}]}