{"document":{"slug":"rec-20260903-5243","title":"Protest of the Independent Market Monitor for PJM to the 08/13/2026 filing by PJM Interconnection, L.L.C. proposing to establish Interim Resource Adequacy…","issued":"2026-09-03","accession":"20260903-5243","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Monitoring Analytics, LLC","kind":"protest","file":"sources/filings/text/20260903-5243_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260903-5243","tier":"record","sha256":"aad0e9543eb2a2a6e769f0fb2e8172e89d665628edf0341875d045f1e70dc72a","pages":47,"tokens":15493,"emptyPages":[],"textThemes":["flex","adequacy","registry","retail"]},"pages":[{"page":1,"startToken":0,"endToken":228,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n \n \nDocket No. ER26-3515-000 \nPROTEST OF THE INDEPENDENT MARKET MONITOR FOR PJM \nPursuant to Rule 211 of the Commission’s Rules and Regulations1 Monitoring \nAnalytics, LLC, acting in its capacity as the Independent Market Monitor (“Market \nMonitor”) for PJM Interconnection, L.L.C. (“PJM”),2 submits this protest to the filing \nsubmitted by PJM Interconnection, L.L.C. (“PJM”) on August 13, 2026, proposing (at 1) “to \nestablish Interim Resource Adequacy Service (“IRAS”)—a service to be implemented by \nPJM solely during periods when there are insufficient resources to reliably meet demand in \nreal time operations” (“IRAS Filing”).3 \nThe IRAS Filing has not been supported as just and reasonable, and it should be \nrejected. The IRAS Filing is unjust and unreasonable, and attempting to implement it will \ndamage PJM markets and create unintended consequences. \nThere is broad agreement among policy makers, regulators, and developers, \ncaptured in the Ratepayer Protection Pledge and Principles, on the need to ensure that data \n \n1 \n18 CFR § 385.211 (2025). \n2 \nCapitalized terms used herein and not otherwise defined have the meaning used in the PJM Open \nAccess Transmission Tariff (“OATT”), the PJM Operating Agreement (“OA”) or the PJM Reliability \nAssurance Agreement (“RAA”). \n3  \nThe IRAS Filing is supported by an Affidavit of Christopher Pilong (Attachment C) (“Pilong \nAffidavit”)."},{"page":2,"startToken":228,"endToken":759,"text":"- 2 - \ncenters bring their own new generation and pay their own way and to prioritize the \nprotection of reliability and affordability for all the other customers.4 5 The Pledge affirms: \n“The Ratepayer Protection Pledge and the commitments embodied therein effectuate the \nnational policy of the United States.” The Commission has recognized the Pledge and \nPrinciples.6 The Pledge and Principles should guide the development of rules to support \n \n4 \nSee \nThe \nWhite \nHouse, \n“Ratepayer \nProtection \nPledge” \n(March \n4, \n2026), \n<https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/?utm_source=wh_social\n_share_button>, Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026) (“Today, pursuant to the \nRatepayer Protection Pledge, leading United States hyperscalers and AI companies guarantee that \ndata centers’ energy needs will not increase household electricity costs for American citizens. \nInstead, these companies will build, bring, or buy the new generation resources and electricity \nneeded to satisfy their energy demands, and pay for all new power delivery infrastructure \nupgrades to service their data centers. They will voluntarily negotiate new, separate rate structures \nwith their utilities and relevant State governments, and pay those rates, and for their infrastructure, \nwhether they use the electricity or not. They will also invest in local communities and coordinate \nwith grid operators to contribute to a more reliable grid.”) (“Pledge”). On July 23, 2026, over 200 \nadditional entities joined the pledge. See The White House, “President Trump’s Ratepayer \nProtection Pledge Secures American AI Dominance, Protects Consumers” (July 23, 2026), \n<https://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayer-protection-pledge-secures-\namerican-ai-dominance-protects-consumers/?utm_source=wh_social_share_button>. \n5  \nNational Energy Dominance Council, Statement of Principles Regarding PJM (January 16, 2026) \n<https://www.energy.gov/documents/statement-principles-regarding-pjm> (“Principles”). Two principles \napply to the contemplated procurement of new generation. First, the procurement should \n“[p]rovide 15-year price certainty for new capacity resources” [emphasis]. The statement notes that \nthis can be done in through a “Reliability Backstop Auction,” but does not require that this auction \nbe a centralized procurement by PJM or that PJM customers assume risks. Second, “PJM should \nallocate the cost of any new capacity through the aforementioned Reliability Backstop Auction to \nload serving entities (LSEs) with new data centers that have not self-procured new capacity or \nagreed to be curtailable.” The principles, agreed to by the Governors of PJM States Indiana, Ohio, \nMaryland Pennsylvania, Virginia, West Virginia, Delaware, Illinois, Michigan, New Jersey, \nTennessee, North Carolina and Kentucky, call for PJM to do the allocation and to match data \ncenters to the costs not excluding risks of new resources or commitments to curtail. Additional \nprinciples that going beyond the RBF Proposal, the Market Proposal, or potential alternatives, \ninclude: (i) extending the price collar for two additional RPM Base Residual Auctions, (ii) PJM \nimproving load forecasting, (iii) accelerating generator interconnections, i.e., the Reliability \nResource Initiative (RRI), and (iv) continued efforts to reform the capacity market. \n6  \nSee PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at PP 2, 5, 8, 32 & 69 (2026) (“Large Load Show \nCause Order”). The Large Loads Show Cause Order states (at P 66) (“We next preliminarily find \nthat PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to"},{"page":3,"startToken":759,"endToken":1203,"text":"- 3 - \nresource adequacy by procuring new capacity to serve data centers and ensuring that data \ncenters pay for that capacity and that those costs are not assigned, allocated or otherwise \npushed onto other customers. \nThe IRAS Filing does none of these things. The IRAS Filing is a convoluted, \ninconsistent, confusing proposal that PJM justifies based on a misreading of jurisdictional \nresponsibilities and under which PJM denies responsibility for reliability and assigns key \nundefined and inappropriate roles to the states. \nAccordingly, in addition to rejecting the IRAS Filing as not shown to be just and \nreasonable, an order should issue, finding that the existing rules relating to resource \nadequacy for serving data centers in the PJM Region are unjust and unreasonable under \nSection 206 of the Federal Power Act.7 The PJM rules do not explicitly provide a rule for \ncurtailing service to data centers that are connected to the grid but do not have capacity \neither through BYONG or through an allocation of RBP MW. Upon issuing a finding that \n \n \nmitigate the risk of cost shifting among transmission customers, which may result in unjust and \nunreasonable rates for transmission service. In particular, we are concerned about the apparent lack \nof: (1) transparency regarding the assignment of Network Upgrades, and their associated costs, that \nare needed to provide transmission service to Eligible Customers on behalf of large loads; and (2) a \npro forma cost recovery agreement between PJM, the relevant transmission owner, and the Eligible \nCustomer taking transmission service on behalf of large loads that help ensure that Eligible \nCustomers bear the risk and are ultimately responsible for costs incurred to provide transmission \nservice, including the cost of Network Upgrades.”). \n7  \nSee 16 U.S.C. § 824e(a); see also Large Loads Show Cause Order at P 49 (“[W]e today exercise our \nauthority to ensure that the process by which jurisdictional transmission providers and/or \ntransmission owners will study the provision of jurisdictional transmission service to Eligible \nCustomers on behalf of large loads interconnecting to the transmission system, including where, as \nallowed by state law or a public utility’s voluntary offer of such service, an end-use large load seeks \nunbundled retail transmission service, is just and reasonable and not unduly discriminatory or \npreferential. Pursuant to that authority, we find that PJM’s Tariff appears to be unjust and \nunreasonable or unduly discriminatory or preferential because it lacks sufficiently clear and \nconsistent provisions regarding the study process related to the provision of transmission service to \nEligible Customers on behalf of large loads. We need not comprehensively address the \nCommission’s jurisdiction over other aspects of the addition of large loads to the transmission \nsystem at this time.”)."},{"page":4,"startToken":1203,"endToken":1556,"text":"- 4 - \nthe current rules are unjust and unreasonable, the Commission can, on the basis of the \nexisting record, act without delay to direct PJM to immediately implement a remedy that \nwould require LSEs hosting data centers that are interconnected without having obtained \nnew capacity to require such data centers to contract with curtailment coordinators to \nprovide curtailments to PJM. Such an order should direct that PJM file rules for the PJM \nRegion establishing tariff defined curtailment obligations for wholesale service to data \ncenters during a defined, limited transition period that would allow data centers that \ninterconnect without new generation the time to contract for new generation. \nThese requirements meet the goals of the Pledge and Principles and can be \nimplemented immediately.  \nI. PROTEST \nA. The IRAS Filing Has Not Been Shown to be Just and Reasonable. \n1. The IRAS Filing is not a Coherent Proposal. \nThe most fundamental point about the IRAS Filing is that, despite its claims, it does \nnot effectively remove data center load from the VRR curve and the result of the IRAS \nFiling will continue to be to distort and unjustly and unreasonably inflate the prices of \nenergy and capacity in PJM. The IRAS Filing does not follow the Pledge and Principles. In \naddition, the IRAS Filing treats data center load unfairly and will create further uncertainty \nand confusion about how the markets will actually function. PJM needs to return to the \nfundamental market design that worked effectively for many years until the temptation to \nmicromanage results took precedence, starting with the Capacity Performance design. \nThere is a manageable way to ensure that data center load is served without imposing \nmassive costs on all customers. The Market Monitor has spelled that out in two proposals \nposted for the most recent CIFP process at PJM. The basic elements of the IRAS proposal are \nthat: PJM will allow the interconnection of new data center loads with no capacity; PJM will \ncharge these data centers for capacity; PJM will not include only these specific forecast new \ndata center loads in the VRR curve; PJM fails to define enforceable rules for the curtailment"},{"page":5,"startToken":1556,"endToken":1874,"text":"- 5 - \nof these data center loads; PJM will add these new data center loads back to the VRR curve, \nwith no requirement to bring new capacity, if the system is not short of capacity for three \nyears; the IRAS and the Bring Your Own New Capacity (“BYONC”) rules will never again \napply to these data center loads in any way if the system is not short of capacity for three \nyears; PJM will leave in place and not address the impact of previously forecast data center \nload on other customers. \nThe IRAS Filing is inconsistent with the RBP Filing in significant ways including the \nobligation to bring new capacity and the definition of acceptable new capacity.8 \nPJM recognizes that New Large Loads “constitute a separate, new class of load, and \nare therefore appropriately subject to different treatment,” but fails to implement rules that \nappropriately recognize that fact.9 \nA fundamental gap in the IRAS Filing is the failure to create rules that actually \nimpose curtailability on data center loads that interconnect with no new capacity. PJM \njustifies its failures on hand waving about cooperative federalism and a misunderstanding \nof jurisdictional rules. \nThe IRAS Filing creates incentives to not bring your own new capacity but to just \nwait until PJM acquires capacity and is no longer short. This is the exact opposite of what \nthe design should be. \nFor all these reasons, the IRAS Filing is not just and reasonable and should be \nrejected in its entirety. \n \n8  \nThe related Reliability Backstop Procurement (“RBP”) filing is currently pending in Docket No. \nER26-3880 (“RBP Filing”). The Market Monitor filed a protest on August 21, 2026, seeking rejection \nof the RBP Filing and the issuance of a remedial directive in that proceeding to ensure that LSEs \nshow the data centers they serve have made arrangements to obtain new resources sufficient to \nserve their load reliably. \n9  \nIRAS Filing at 95."},{"page":6,"startToken":1874,"endToken":2196,"text":"- 6 - \n2. PJM’s Arguments on Jurisdiction Are Incorrect. \nPJM incorrectly relies on assertions about jurisdiction and cooperative federalism to \njustify the obvious flaws in the IRAS Filing. PJM asserts (at 85–93) that jurisdictional rules \nare the reason that PJM’s IRAS Filing fails to create rules that actually impose curtailability \non data center loads that interconnect with no new capacity. Instead of proposing any \nactual rules for curtailments and taking responsibility for reliability, PJM defers all of the \ncurtailment related issues to the individual states with vague and unhelpful and \ninconsistent suggestions about what states might do, including not curtailing these loads. \nPJM has not demonstrated that its proposal to leave the standard for determining \ncurtailments and payments for curtailments to the 14 jurisdictions that comprise the PJM \nRegion is required based on federal jurisdiction over wholesale power sales in interstate \ncommerce. The rules for resource adequacy in a multistate region are necessarily beyond \nthe jurisdiction of any PJM state and must be addressed at the federal level. The state by \nstate approach proposed in the IRAS Filing will create inconsistencies, conflicts and other \nadministrative obstacles that will burden PJM’s assurance of resource adequacy in the PJM \nRegion. The state by state approach will result in myriad unintended consequences \nincluding states unintentionally imposing costs on other states through inconsistent \ncurtailment rules. The state by state approach is not consistent with an efficient and \ncompetitive wholesale power market. State regulation that burdens interstate commerce is \nnot permissible.10 The IRAS Filing’s failure to include coherent rules for curtailment and \nrelated competition significantly burdens interstate commerce and is a deficiency of the \nIRAS Filing based on a misunderstanding of jurisdiction. \n \n10  \nSee Arkansas Power & Light Co. v. Federal Power Com., 368 F.2d 376, 384 (1966) (“state regulation \nof sales in interstate commerce constituted a direct burden on interstate commerce”), citing Public \nUtils. Comm'n v. Attleboro Steam & Elec. Co., 273 U.S. 83 (1927)."},{"page":7,"startToken":2196,"endToken":2594,"text":"- 7 - \nThe IRAS Filing continues PJM’s efforts from the RBP Filing to balkanize the PJM \ngrid into state entities rather than the interconnected market that is essential to the effective \nand efficient and competitive functioning of PJM markets. If states or zones wanted to be \nFixed Resource Requirement (“FRR”) entities solely responsible for their own reliability, \nthey would have made that choice.11 PJM’s efforts to force a form of FRR obligation on \nstates and EDCs is inappropriate, wrong and inconsistent with the basic rules of the RTO. \nPJM has apparently not considered the multiple unintended consequences of this effort to \nabandon their responsibility to grid reliability. There is no consideration or analysis of the \nimpacts on one state’s rules on another state. Under PJM’s IRAS approach, one state could \nrequire curtailments while another state did not. The result would be one state imposing its \ncosts and the associated reliability risks on other states. The result for the PJM Region \nwould be a market rules framework for resource adequacy even less efficient and coherent \nthan a situation where every state had an explicit FRR Plan. PJM’s proper role as an RTO is \nto provide a coherent plan for resource adequacy for the multistate PJM Region. \nPJM’s references to cooperative federalism (at 2, 87–89) do not excuse the \ndeficiencies in its proposal. PJM does not define cooperative federalism or explain how it \ncompels or justifies the division of responsibilities in the IRAS Filing. The Commission \nrecently explained that considerations of cooperative federalism come only after satisfaction \nof the fundamental requirements for the division of jurisdictional responsibility.12 The IRAS \nFiling fails this test. \n \n11  \nSee RAA Schedule 8.1. \n12  \nSee Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,157, 62082 (2025) (“[W]ith regard to \ncooperative federalism, Southern Regulators misconstrue EPSA. In EPSA, the Supreme Court did \nnot rely on the Commission's provision of state veto power over the inclusion of retail customers in \ndemand response programs in affirming that the Commission's Order No. 745 on demand response \nwas within its jurisdiction. Instead, the Court described the veto as a \"finishing blow . . . [that] \nremoves any conceivable doubt as to [the order's] compliance with [FPA section 201(b)]'s allocation \nof federal and state authority.\"[footnote omitted] As the Commission has explained, \"the Court \ntreated the state 'veto power' in [EPSA] as confirming the Commission's compliance with principles"},{"page":8,"startToken":2594,"endToken":2965,"text":"- 8 - \nThe IRAS Filing does not provide for cooperation with states, it is instead an \nabdication of PJM’s responsibility to set and implement the terms and conditions of \ncurtailments to ensure that curtailments protect resource adequacy in the PJM Region. If \nPJM determines to serve loads that it lacks adequate resources to serve and is willing to risk \nreliance on curtailments, PJM must take undivided responsibility for the administration of \nthat program and the potential consequences. PJM must ensure that it will have \ncurtailments available wherever on the regional system it needs them, and that curtailments \nwill be implemented when PJM calls for them. \nThe states have an important role to play in identifying data center loads, siting data \ncenters and the new resources that serve them and protecting affordability in their states. \nStates could prevent the interconnection of data centers without assurance that they have \nbrought new generation to serve their loads. Alternatives to the IRAS Filing, including the \nMarket Monitor’s proposal (Attachment A) are equally cooperative with states, but avoid \nassigning a role to the states that they have not asked for, that is outside of their jurisdiction \nand that is beyond their capability to perform.  \nCooperative federalism does not justify balkanizing the PJM Region and defeating \nthe purpose of the RTO. PJM has exclusive responsibility to ensure resource adequacy in \nthe multistate PJM Region. PJM’s proposed “Interim Resource Adequacy Service” is all \nabout rules related to resource adequacy. The Supreme Court in Hughes finds that the \nCommission has exclusive jurisdiction over the market rules related to resource adequacy.13 \n \n \nof cooperative federalism, having already discussed at length why the Commission, regulating \nwithin the areas of its jurisdiction, was not intruding on state prerogatives.\"), citing FERC v. Elec. \nPower Supply Ass’n, 577 U.S. 260 (2016). \n13  \nSee Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 163 (2016) (“We agree with the Fourth \nCircuit’s judgment that Maryland’s program sets an interstate wholesale rate, contravening the \nFPA’s division of authority between state and federal regulators. As earlier recounted, … the FPA \nallocates to FERC exclusive jurisdiction over ’rates and charges . . . received . . . for or in connection \nwith’ interstate wholesale sales. §824d(a). Exercising this authority, FERC has approved the PJM"},{"page":9,"startToken":2965,"endToken":3357,"text":"- 9 - \nThe IRAS Filing revises PJM’s resource adequacy rules. While states can identify large loads \nand determine the allocation of costs in retail rates, PJM needs to ensure that there is a \ncoherent resource adequacy program in the PJM Region and to administer that program \nefficiently and impartially. If PJM is going to permit a curtailment option, PJM must take \ndirect steps to create clear rules governing curtailments, to establish procedures to ensure \ntimely curtailments and verify compliance. These curtailments are terms and conditions of \nwholesale service, subject to FERC’s jurisdiction. \nPJM’s reliance on the model for state participation in demand response (i.e. \nRERRAs) and its interpretation of EPSA are misplaced.14 EPSA confirmed federal \njurisdiction over demand response even though it involves rules for participation of retail \ncustomers in the wholesale energy markets.15 Federal jurisdiction is also appropriately \nexercised over rules related to retail customers as they receive wholesale power service and \nrelated resource adequacy through Load Serving Entities (“LSE”) and Curtailment Service \n \n \ncapacity auction as the sole rate setting mechanism for sales of capacity to PJM, and has deemed \nthe clearing price per se just and reasonable”). \n14  \nSee IRAS Filing at 89–92, citing EPSA, 577 U.S. 260 (2016). \n15  \nSee id. at 677–78 (“Yet a FERC regulation does not run afoul of §824(b)’s proscription just because it \naffects—even substantially—the quantity or terms of retail sales. It is a fact of economic life that the \nwholesale and retail markets in electricity, as in every other known product, are not hermetically \nsealed from each other. To the contrary, transactions that occur on the wholesale market have \nnatural consequences at the retail level. And so too, of necessity, will FERC’s regulation of those \nwholesale matters. Cf. Oneok, Inc. v. Learjet, Inc., 575 U. S. 373, 387, 135 S. Ct. 1591, 194 L. Ed. 2d 511, \n523 (2015) (noting that in the similarly structured world of natural gas regulation, a “Platonic ideal” \nof strict separation between federal and state realms cannot exist). When FERC sets a wholesale \nrate, when it changes wholesale market rules, when it allocates electricity as between wholesale \npurchasers — in short, when it takes virtually any action respecting wholesale transactions — it has \nsome effect, in either the short or the long term, on retail rates. That is of no legal consequence.”)."},{"page":10,"startToken":3357,"endToken":3714,"text":"- 10 - \nProviders (“CSP”).16 PJM’s program for resource adequacy is necessary for the multistate \nPJM Region. Coherent administration of the resource adequacy rules is necessary. \nThe IRAS Filing represents bad policy choices that PJM has not shown to be \ncompelled by any jurisdictional requirement. Workable rules consistent with the actual \njurisdictional rules are available. The Market Monitor’s solution is a viable alternative that \nrelies on the same rules and logic as the current PJM rules for resource adequacy and \ndemand response.  \nB. The IRAS Filing Is Deficient, Unjust and Unreasonable. \n1. The IRAS Filing Requires IRAS Load to Pay for Capacity. \nAlthough the IRAS Filing never states this explicitly, the IRAS Filing requires that \ndata centers that do not bring new capacity must pay for capacity through the PJM capacity \nmarket cost allocation mechanism. The IRAS Filing requires that IRAS data centers must \npay for capacity even though they are added to the system when they do not bring their \nown new capacity and when the overall system is short of capacity and when IRAS load is \nnot included in the VRR curve in the capacity market. New Large Loads subject to IRAS \nwill pay the allocated capacity market cost, termed the Local Reliability Charge, which is \nequal to Daily UCAP Obligation times the Final Zonal Capacity Price, that all LSEs pay.17 \nThis is the only relevant fact about IRAS payments for capacity in the IRAS Filing. In \naddition to assigning to the states the problem of defining curtailment rules, PJM assigns \nthe definition and mechanics of any offsetting discounts or compensation for curtailment to \nthe states. PJM’s vague language does not create any rules or impose any obligations. Based \n \n16  \nSee id. at 281–82 (“When FERC regulates what takes place on the wholesale market, as part of \ncarrying out its charge to improve how that market runs, then no matter the effect on retail rates, \n§824(b) imposes no bar. And in setting rules for demand response, that is all FERC has done. The \nCommission’s Rule addresses—and addresses only—transactions occurring on the wholesale \nmarket.”). \n17  \nSee RAA Article 7, Section 7.2."},{"page":11,"startToken":3714,"endToken":4019,"text":"- 11 - \non the PJM IRAS Filing, the only thing that IRAS load can be sure of is that they will pay for \ncapacity. \n2. IRAS Load Is Not Effectively Removed from VRR Curve.  \nThe IRAS Filing purports to remove data center load from the VRR curve along with \nits attendant impacts on capacity market prices that has been extensively documented by \nthe Market Monitor.18 19 The IRAS Filing does not effectively remove data center load from \nthe VRR curve. Any impact on the VRR curve is short lived. \nSpecifically, the IRAS Filing proposes to remove New Large Load without RBP \nAllocation or without BYONC from the RTO and LDA VRR Curves. PJM’s proposal \nintroduced two new terms: Excluded RTO New Large Load Amount and Excluded LDA \nNew Large Load Amount. PJM defined Excluded RTO New Large Load Amount as the \nUCAP equivalent of forecasted New Large Load for the delivery year, minus the New \nLarge Load included in the 2028/2029 Delivery Year, minus New Large Load contracted \nwith BYONC or assigned Allocated RBP UCAP MW.20 PJM defined Excluded LDA New \nLarge Load Amount as the UCAP equivalent of forecasted New Large Load for the delivery \nyear, minus the New Large Load included in the 2028/2029 Delivery Year, minus New \nLarge Load contracted with BYONC located within the LDA or assigned Allocated RBP \nUCAP MW within the LDA.21 \nPJM argued that removing such New Large Loads is consistent with the Ratepayers \nProtection Pledge and would lower capacity market clearing prices for PJM customers. \n \n1818  \nSee Monitoring Analytics, LLC “Analysis of the 2027/2028 RPM Base Residual Auction – Part A,” \n(January 5, 2026). \n19  \nSee 2026 Quarterly State of the Market Report for PJM: January through June, Section 1 Introduction \n(August 13, 2026). \n20  \nIRAS Filing at 112. \n21  \nId. at 112."},{"page":12,"startToken":4019,"endToken":4347,"text":"- 12 - \nPJM’s proposal has very limited scope and would do very little to lower the prices for PJM \norganic customers.  \nPJM fails to address the ongoing impact of the previously forecast data center load \nthat inflated capacity market prices. PJM simply leaves that previously forecast data center \nload in the VRR curve despite its distortionary effects. In addition, the IRAS load returns to \nthe VRR curve after three consecutive years of no shortfall. A shortfall should not be the \ntrigger for excluding data center load from the VRR curve. Using a shortfall as the trigger \nwill continue to distort prices and to impose data center costs on other customers. Allowing \nIRAS load to be served with no obligation to bring their own new capacity will also inflate \nenergy prices as New Large Loads are added with no corresponding energy supply. The \nIRAS Filing also provides a strong incentive to not bring new capacity and to simply wait \nfor the IRAS condition to terminate well before the 10 year BYONC obligation. \nThe starting point of PJM’s IRAS Filing is to consider only the forecasted incremental \nincrease in the New Large Load for the future delivery years from the forecasted large load \nincluded in the 2028/2029 Delivery Year. The 2028/2029 BRA cleared with a 6,831.3 UCAP \nMW shortfall. Under PJM’s proposal, the VRR curves for the future delivery years would \ncontinue to include the forecasted New Large Load for the 2028/2029 Delivery Year \nincluding the large loads that were allowed to be interconnected to PJM’s grid with no \noffsetting capacity. These New Large Loads have substantially increased the cost of \ncapacity to PJM customers and under PJM’s IRAS proposal, they would continue to impose \nthis cost.22 \n \n22  \nThe addition of data center load has resulted in adding $29.4 billion to the cost of capacity. See 2026 \nQuarterly State of the Market Report for PJM: January through June, Section 1 Introduction (August 13, \n2026)."},{"page":13,"startToken":4347,"endToken":4698,"text":"- 13 - \n3. Failure to Require Locational Matching of IRAS Load and Offsetting \nCapacity Will Create Significant Unintended Consequences. \nUnder the proposed IRAS rules, New Large Loads would be allowed to avoid \npotential curtailment if the New Large Load contracts with new generation (BYONC). \nThere is no requirement that this generation be located within the same LDA. For example, \na New Large Load located in the DPL-SOUTH LDA would be allowed to avoid curtailment \nif the New Large Load contracts with BYONC in the COMED LDA. If the DPL-SOUTH \nLDA is a constrained LDA, meaning that there is a lack of sufficient transmission capacity \nto import capacity from outside the LDA, the contracted BYONC would not be able to meet \nthe reliability needs of the DPL-SOUTH LDA. Under PJM’s proposed rules, the New Large \nLoad would nonetheless be exempt from curtailment and treated like any other organic \nload in the DPL-SOUTH LDA. \nUnder the PJM’s proposed IRAS rules, the New Large Load would be removed from \nthe VRR curve of the LDA even if the contracted BYONC is located outside the LDA.23 In \nthe example where the New Large Load located in the DPL SOUTH LDA contracts with \nBYONC in the COMED LDA, the VRR Curve of the DPL SOUTH LDA would be reduced. \nThis reduction directly contradicts the fact that DPL-SOUTH LDA is less reliable as a result \nof the addition of data center load that is exempt from curtailment without any matching \nincrease in supply. \n \n4. PJM Fails to Explain How IRAS load Will Be Removed from LDA VRR \nCurves. \nPJM calculates each modeled LDA’s reliability requirement based on CETO/CETL \nanalysis. The need for capacity in each LDA is defined by the VRR curve for each LDA.  The \n \n23  \nExcluded LDA New Large Load Amounts include incremental large load minus “the total MW \nquantity of New Large Load that is added on or after the 2029/2030 Delivery Year and is (i) in an \narrangement with BYONC in the Locational Deliverability Area or (ii) assigned Allocated RBP \nUCAP MW in Locational Deliverability Area.” See Attachment A, Definitions E-F."},{"page":14,"startToken":4698,"endToken":5028,"text":"- 14 - \nneed for capacity in each LDA is met by a combination of internal capacity and imported \ncapacity from elsewhere in PJM. Capacity Emergency Transfer Objective (“CETO”) is the \namount of imports required by an LDA to meet the LDA’s reliability criterion of one loss of \nload event in every 25 years or equivalent unserved energy. The reliability requirement of \nan LDA is calculated as the sum of CETO and the UCAP MW of resources located within \nthe LDA. Under PJM’s IRAS Filing, New Large Loads without BYONC or RBP allocation \nwithin the LDA would have to be removed from the LDA’s VRR Curve in addition to the \nRTO VRR curve. PJM proposes to use an estimated impact factor to convert the large load \nMW to CETO equivalent UCAP MW. PJM did not provide any details on how this impact \nfactor would be estimated. \nTo calculate the CETO of an LDA, PJM simulates the availability of resources within \nthe LDA and load scenarios within the LDA, similar to the RTO wide resource adequacy \nsimulation.24 In every iteration, PJM calculates the amount of capacity required to be \nimported from outside the LDA to meet the load. CETO is the amount of capacity that \nprobabilistically satisfies the LDA’s reliability criterion.  \nThe CETO without the New Large Load subject to curtailment included in the load \nscenarios would be different from the CETO calculated by PJM with New Large Load and \npotentially very different. PJM approximates the magnitude of this difference through the \nestimated impact factor for which PJM did not provide any details.25 PJM asks the \nCommission to make an important determination that will affect capacity market clearing \nprices without providing an actual detailed proposal to evaluate. The Commission should \nreject the PJM IRAS Filing for this and other significant flaws that make effective review \nimpossible. \n \n24  \nSee PJM Manual 20A: Resource Adequacy Analysis, § 3 Capacity Emergency Transfer Objective \n(CETO) Study, Rev. 39, (June 24, 2026). \n25  \nIRAS Filing at 114."},{"page":15,"startToken":5028,"endToken":5424,"text":"- 15 - \n5. The Trigger for IRAS Unjustly Imposes Costs on Other Customers. \nPJM’s proposed IRAS rules are triggered by the existence of a capacity shortfall, \nmeaning that the capacity procured in the capacity auction is not adequate to meet the \nreliability requirement. If there is a shortfall in a delivery year, the MW of New Large Load \nwithout BYONC would be designated as IRAS. New Large Load without BYONC by the \ndefined deadline would be excluded from the VRR curve for that capacity auction.  \nIf the IRAS load is less than the shortfall, there would be no impact on the capacity \nmarket price and that price would remain at the maximum price. If the IRAS load is greater \nthan the shortfall, the capacity market price would be lower than the maximum price.26 \nThe PJM IRAS approach would reduce capacity payments by other customers both if \nthe price remains at the maximum and if the price is below the maximum. IRAS load would \nbe required to pay for capacity through the capacity cost allocation mechanism and those \npayments will reduce the capacity payments by other load by the amount of the IRAS MW \n(adjusted by the Final Zonal RPM Scaling Factor) multiplied by the zonal capacity price.27 28 \nThe PJM IRAS approach is very different than simply removing Eligible New Large \nLoad Amount from the VRR curve. The IRAS rules apply only when there is a shortfall in \nthe capacity market. If there is no shortfall for three years, all of the designated IRAS load is \npermanently converted to being load like existing organic load and is then treated like any \nother load and included in the VRR curve. In that case, New Large Load without BYONC \nwill be included in the VRR curve and will unjustly increase the price for other customers \n \n26  \nThis comparison is approximate. The actual quantity would be greater than the shortfall, using the \nVRR curve based on the Agreement between Governor Shapiro of Pennsylvania and PJM (See \nDocket Nos. ER25-1357-000 and ER26-1556-000.) For example, in the 2028/2029 BRA, the shortfall \nwas 6,831.3 MW. A leftward shift of the VRR curve by 8,385.3 MW would have reduced the \nclearing price below the VRR maximum price at point A. \n27  \nSee RAA Article 7.2 & Schedule 8. \n28  \nSee OATT Attachment DD § 5.14(e)&(f)."},{"page":16,"startToken":5424,"endToken":5783,"text":"- 16 - \nas a result. The effect will be to inflate capacity market prices as long as there is significant \nNew Large Load with no new capacity and there is not a shortfall. A new going forward \nIRAS designation would be implemented if the capacity market has a shortfall in a future \nyear that applies only to New Large Load included in the forecast for the first time, at that \npoint in the future. \nPJM should not include New Large Load in the VRR curve, regardless of shortfall \nconditions, unless it has new matching capacity to ensure that there is no impact on prices \nfor other customers. PJM’s IRAS approach will continue to permit New Large Load with no \nnew capacity to inflate capacity market prices for other customers when the IRAS status is \ncanceled after PJM is no longer short. The use of shortfall as a trigger for excluding non \ncapacity backed New Large Load from the VRR curve misses the point. New Large Load \nwith no new capacity can affect capacity market prices regardless of whether PJM is short, \nas the Market Monitor demonstrated for the 2025/2026 BRA.29 \nIn addition, after the IRAS status is terminated after three years, any new capacity \nthat had been brought in order to be exempt from IRAS status is now considered to be \navailable to export or to serve other new load and is no longer required to serve the New \nLarge Load that it was linked to. Not only is the IRAS load now considered to be organic \nload, but the capacity IRAS load brought in order to be exempt from IRAS rules is no longer \nconsidered to be required to serve that load. The PJM IRAS Filing would increase load and \nreduce supply after the three year period. \n6. It Is Not Just and Reasonable to Curtail IRAS Load Before Demand \nResponse Capacity Resources. \nPJM proposes that IRAS curtailments occur before deployment of Pre-Emergency \nLoad Management. PJM’s rationale is that New Large Load should be the first curtailed \n \n29  \nSee Monitoring Analytics, LLC “Analysis of the 2025/2026 RPM Base Residual Auction – Part G \nRevised,” (June 3, 2025)."},{"page":17,"startToken":5783,"endToken":6135,"text":"- 17 - \nbecause it has not provided the capacity needed to support its demand and should not be \nable to simply rely on existing system resources. This argument is made without apparent \nirony despite the fact that PJM is proposing to allow IRAS load without corresponding \ncapacity, to leave IRAS load out of the VRR curve, and to require IRAS load to pay for \ncapacity. In PJM’s convoluted and unworkable IRAS proposal, IRAS load pays for capacity \nthat actually includes payments to Pre-Emergency Load Management resources, yet is \ncurtailed before those same Pre-Emergency Load Management resources. Pre-Emergency \nLoad Management resources are paid to curtail following rules in the PJM tariff. Despite \nmuch ultimately meaningless discussion of compensation for IRAS load, the proposed PJM \ntariff in the IRAS Filing provides for no compensation to IRAS load for being curtailable. \nPJM has the order of curtailment backwards based on its own proposed tariff language. \nPJM has not actually provided a supportable reason to justify giving IRAS priority over \nexisting compensated Demand Resources. If IRAS is triggered under conditions in which \nexisting Demand Resources could have provided the necessary reliability service, the \nproposal effectively substitutes a new nonmarket curtailment mechanism for an existing \nreliability resource and shifts the associated economic consequences to other customers. \nPJM fails to establish clear and objective criteria governing when IRAS may be triggered. \nThe proposed vague and unenforceable triggering conditions for IRAS would require PJM \nfirst to exhaust available economic supply needed to maintain operating reserves, requiring \nthe dispatch of increasingly costly resources and thereby increasing energy costs borne by \nexisting customers before IRAS reductions are deployed. This sequencing would result in \nhigher energy costs for existing customers, particularly where deploying existing Demand \nResources would be less costly than dispatching additional higher cost generation to \npreserve reserves prior to curtailing IRAS load. PJM’s proposed sequencing is \nunenforceable because it is intentionally not specific. The proposed sequencing does not \nestablish a fixed operating hierarchy. Although PJM proposes that IRAS curtailments occur \nbefore Pre-Emergency Load Management, PJM system operators retain discretion to \nimplement emergency procedures in whatever order is necessary to maintain system"},{"page":18,"startToken":6135,"endToken":6454,"text":"- 18 - \nreliability. Likewise, operators may exit emergency procedures in an order different from \nthe order in which they were implemented. Consequently, the nominal sequencing of IRAS \nahead of Pre-Emergency Load Management does not necessarily establish the actual \noperational priority of the two resources during the reliability event. This lack of actual \noperational rules further underscores the need for PJM to define the IRAS trigger and \noperating criteria with sufficient specificity to permit meaningful evaluation of the \nproposal's reliability and economic consequences. Without such safeguards, IRAS will \ndisplace existing Demand Resources when demand response is available and effective, \nwhile imposing higher energy and scarcity costs on existing customers. PJM has not \ndemonstrated that this outcome is consistent with the stated objective of protecting existing \nratepayers from the reliability and economic consequences associated with the New Large \nLoad. \n7. IRAS Filing Proposal Unjustly Allows Data Centers to Rely on Existing \nCapacity and Make the System Less Reliable for Other Customers. \nThe RBP Filing and IRAS Filing have inconsistent definitions of capacity that can be \nused to satisfy the requirements to meet the data center load. The IRAS Filing allows 10 \nyear contracts for BYONC that could terminate after three years, whereas the RBP auction \nwould require 15 year contracts but would also allow a five year bilateral contract to meet \nthe same obligation under the RPB offset option. The IRAS Filing creates strong incentives \nto provide inferior and shorter term capacity. The IRAS Filing creates strong incentives to \nclaim capacity that is not actually new capacity to meet data center demand. \nWhile PJM claims that the BYONC gating criteria “are designed to ensure the \ncapacity is actually new and not repackaged,” the proposed BYONC gating criteria allow \nexactly this repackaging of existing resources as new.30 The criteria for qualifying to be \nBYONC are defined in the PJM proposed Tariff in the IRAS Filing, Attachment DD-4, \n \n30  \nIRAS Filing at 23."},{"page":19,"startToken":6454,"endToken":6860,"text":"- 19 - \nsection VI. PJM’s proposed criteria include uprates; Demand Resources; DER aggregation \nresources; capacity that cleared an RPM auction for the first time in the 2027/2028 through \nthe 2029/2030 Delivery Years; and capacity that cleared an RPM auction for the first time \nstarting in the delivery year in which a shortfall exists after IRAS rules apply again \nfollowing a period of surplus. The goal should be to support new generation and to prevent \ngaming of the rules by reclassifying existing capacity resources as new. The definition \nshould ensure that all cleared capacity represents investment in new physical supply rather \nthan redefining existing resources. PJM’s proposed criteria fail to do this.  \nPJM fails to explain why capacity that previously cleared should count as new and \nqualify as BYONC. For example, suppose a 100 MW new resource cleared for the first time \nin the 2028/2029 BRA. The 2028/2029 BRA cleared 6,831.3 MW UCAP short of the reliability \nrequirement. If this 100 MW resource is then contracted as BYONC for the 2029/2030 \nDelivery Year and the New Large Load of 100 MW is included in the VRR curve, then the \n2029/2030 Delivery Year would be 100 MW shorter, all else equal. In other words, the \nreliability requirement would increase by the 100 MW of New Large Load, and the supply \nwould remain the same. The PJM proposal results in shifting the risk and costs to other \nLSEs and their customers compared to the case where the 100 MW resource were actually \nnew. The result of PJM’s proposal would be to make PJM less reliable as a result of allowing \ndata center load to cannibalize existing capacity. \nThe term of the BYONC arrangement could terminate after three consecutive \ndelivery years without a shortfall. While the proposed Tariff Attachment DD-4 Section \nVIII(b) states that “BYONC may not seek an exception to the capacity must-offer \nrequirement to provide an external sale, as available under Tariff, Attachment DD, section \n6.6(g) for a 10-year period starting with the first Delivery Year which the BYONC is in an \narrangement with the New Large Load,” the proposed Tariff Attachment DD-4 Section \nVIII(f) also states that if a shortfall does not exist for three consecutive delivery years, “then \nany existing BYONC are relieved of the obligations under this Tariff, Attachment DD-4, \nsection VIII.” As PJM explains in the Transmittal Letter at 58, “BYONC RPM participation"},{"page":20,"startToken":6860,"endToken":7197,"text":"- 20 - \nrequirements are extinguished if IRAS is not needed for three consecutive Delivery Years,” \nand that “they would be they would be free to meet the requirements for an exception \nbased on an external sale.” Therefore, a BYONC resource could export its capacity after \nthree years. PJM claims that the 10-year participation requirement is “designed to ensure \nthat this BYONC is real and lasting.”31 However, limiting the BYONC obligations to three \nyears does not support a lasting solution to the resource adequacy issues.  \nThe Accredited UCAP for BYONC would be set at the value for the RPM auction in \nwhich the BYONC resource cleared for the initial delivery year.32 If the actual accredited \nUCAP factor decreases during the term of the BYONC commitment, the result is shifting \nthe ELCC accreditation risk from resource owners to LSEs and their customers. \n8. The IRAS Filing Unjustly and Unreasonably Imposes Capacity \nAccreditation Risk on Other Customers. \nPJM proposes that BYONC capacity be guaranteed the current ELCC derating \npercentage despite the fact that PJM knows that will produce an incorrect result and assign \nrisk to others in the PJM markets. It is unjust and unreasonable to protect new generation \nfrom ELCC risk if PJM actually continues to believe that their ELCC approach should \ncontinue to be used.33 This provision would fix the accredited UCAP value for up to 15 \nyears so that it would reflect PJM’s calculation of the correct ELCC values for the \ntechnologies.  \nAs an illustration of how wrong PJM’s proposed fixed ELCC values actually are, \nPJM recently posted preliminary ELCC ratings for the 2028/2029 through 2042/2043 \n \n31  \nIRAS Filing at 56. \n32  \nId., PJM proposed Tariff, Attachment DD-4, Sections VII(i)(i)–(ii). \n33  \nPJM proposes that “the Accredited UCAP of any BYONC shall be the Accredited UCAP for the \nRPM Auction in which the BYONC cleared for the initial Delivery Year the BYONC is in an \narrangement with the New Large Load [fn. Filing, Attachment A – Market Tariff, Attachment DD-4 \nVIII (i)] .”"},{"page":21,"startToken":7197,"endToken":7392,"text":"- 21 - \nDelivery Years.34 PJM states that the preliminary ratings for the 2030/2031 through \n2042/2043 Delivery Years “are non-binding and are provided only for indicative purposes.” \nPJM calls the ratings “preliminary and indicative” yet RBP sellers are allowed to offer \nUCAP using an ELCC class rating as high as “120% of the resource type’s most recent \nmaximum Preliminary ELCC Class Ratings for 2028/2029 through the last posted Delivery \nYear.”35 \nFigure 1, Figure 2, and Figure 3 below show the ELCC ratings for selected \ntechnologies, beginning with current ELCC ratings for 2026/2027, the already posted ELCC \nratings for the 2027/2028 BRA and 2028/2029 BRA, and the preliminary ratings for the \n2030/2031 through 2042/2043 Delivery Years 36. \n \n34  \nPreliminary ELCC Class Ratings for Period DY28-DY42, PJM Interconnection, L.L.C. (August 31, \n2026). <https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/postings/preliminary-elcc-class-\nratings-for-period-dy28-dy42.pdf>. \n35  \nSee RBP Filing, Attachment A (Marked Tariff), Attachment DD § 18.5(e)(i). \n36  \nSee Preliminary ELCC Class Ratings for Period DY28-DY42, PJM Interconnection, L.L.C. (August \n31, 2026) <https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/postings/preliminary-elcc-\nclass-ratings-for-period-dy28-dy42.pdf>."},{"page":22,"startToken":7392,"endToken":7617,"text":"- 22 - \nFigure 1 ELCC Ratings for Intermittent Resources \n \nFigure 2 ELCC Ratings for Demand Response and \nStorage \n \nFigure 3 ELCC Ratings for Nuclear and Fossil Fuel \nResources \n \n \nThe ratings for intermittent, storage and Demand Resources all decrease over the \nperiod. The ratings for nuclear, coal and diesel generators decrease over the period. The \nratings for the three gas generator technologies decrease over the first few delivery years \nand then increase. Regardless of the technology, fixing the accredited UCAP at a single \nvalue over the period will misrepresent the actual UCAP. The discrepancies manifest in two \nways. The supply offers will not reflect an accurate UCAP value. The resultant UCAP value \ncould overstate or understate the actual capacity. As a result, PJM will overstate or \nunderstate reliability and fail to purchase the required level of capacity. The auction \nparameters will also be affected. The pool-wide accredited UCAP factor, used to calculate \n0%\n20%\n40%\n60%\n80%\n100%\n2026\n2028\n2030\n2032\n2034\n2036\n2038\n2040\n2042\nOnshore Wind\nOffshore Wind\nSolar Fixed\nSolar Tracking\n0%\n20%\n40%\n60%\n80%\n100%\n2026\n2028\n2030\n2032\n2034\n2036\n2038\n2040\n2042\n4-hr Storage\n6-hr Storage\n8-hr Storage\n10-hr Storage\nDemand Response\n0%\n20%\n40%\n60%\n80%\n100%\n2026\n2028\n2030\n2032\n2034\n2036\n2038\n2040\n2042\nNuclear\nCoal\nGas CC\nGas CT\nGas CT Dual Fuel\nDiesel Utility"},{"page":23,"startToken":7617,"endToken":7967,"text":"- 23 - \nthe reliability requirement, is the ratio of the sum of all accredited UCAP for capacity \nresources to the sum of corresponding ICAP values. For a BYONC resource, PJM does not \nexplain whether they will use the incorrect UCAP that results from the fixed ELCC values \nor make customers pay for the difference. \nIt is also not clear how this provision interacts with the MW offered for sale in the \nReliability Backstop Procurement (RBP). RBP Sellers are allowed to offer UCAP using an \nELCC class rating as high as “120% of the resource type’s most recent maximum \nPreliminary ELCC Class Ratings for 2028/2029 through the last posted Delivery Year.”37[ \nThis will misrepresent the accredited UCAP calculations going forward. For example, a gas \nCT resource’s maximum ELCC rating of 71 percent occurs in the final two years of the PJM \npreliminary ratings, 2041/2042 and 2042/2043 Delivery Years. If the generator’s installed \ncapacity is 100 MW, the RBP seller can offer 85.2 MW into the RBP. If the generator’s initial \nRPM clearing occurs in the 2030/2031 Delivery Year, its accredited UCAP, assuming a \nperformance adjustment factor of 1.0, is 56.0 MW, a reduction of 29.2 MW, or 34 percent. \nPJM does not clarify whether this means that a New Large Load in an “arrangement” with \nthe gas CT is subject to curtailment under IRAS for the 29.2 MW difference. \n9. The Fact That IRAS Curtailment Rules Are Unenforceable Suggestions \nMeans that the Entire IRAS mechanism Cannot Work and Is Not Just \nand Reasonable. \nPJM’s proposal improperly defers to the states and EDCs the critical determinations \nof which customers will be subject to IRAS curtailment, which customers will receive \ncompensation for such curtailments, the level of such compensation if any, and which \ncustomers will ultimately bear the associated costs. These determinations are central to the \neconomic incentives and reliability consequences of IRAS and should not be left to state \ndiscretion. PJM should instead establish clear, objective, and nondiscriminatory rules \n \n37  \nRBP Filing, Attachment A (Marked Tariff Records), Attachment DD § 18.5(e)(i)."},{"page":24,"startToken":7967,"endToken":8297,"text":"- 24 - \ngoverning the application and economic consequences of IRAS throughout the PJM \nfootprint. Leaving these determinations to the states will produce materially inconsistent \ntreatment of similarly situated New Large Loads across PJM. \nPJM fails to include any enforceable curtailment rules for IRAS load despite the \nessential and required link between the load that is interconnected without matching new \ncapacity and the need to curtail that load to ensure reliability.  \nUnder the IRAS Filing, PJM would provide a single aggregate MWh curtailment \nquantity to an EDC rather than identify the individual New Large Loads that must curtail. \nEDCs are expected to reduce load by this MWh quantity. The EDC, consistent with \napplicable state processes, would determine which customers provide the reduction. EDCs \nare not required to implement the request in any specific way and are not required to \ncurtail the IRAS load that is the source of the issue. The IRAS Filing proposes to delegate \nthe distribution of this MWh quantity among the constituent LSEs to the individual EDCs, \nand those LSEs may subsequently need to distribute the MWh quantity down to individual \nlarge loads.  \nThe Pilong Affidavit states (at 9): \nPJM will not direct specific New Large Loads to reduce load, even \nthough Electric Distributors—in coordination, where applicable, \nwith relevant states, Load Serving Entities, and New Large \nLoads—may issue more specific directives to specific retail \ncustomers. PJM will only direct load reduction of an aggregate \nMW IRAS within the zone or area. \nThe resulting MWh quantity reduction may not satisfy PJM’s objective. PJM \noperators would have to make assumptions on how EDCs would pass on this directive to \ntheir constituent LSEs. As a result, PJM operators cannot rely on expectations of specific \nlocational curtailments when PJM issues a curtailment directive. \nThe IRAS Filing’s approach is unworkable for locational issues and specifically the \ncontrol of Interconnection Reliability Operating Limits (“IROL”) conditions because the \neffectiveness of a load reduction depends not only on the amount of load curtailed, but also"},{"page":25,"startToken":8297,"endToken":8728,"text":"- 25 - \non its electrical location relative to the constrained facility or interface. The IRAS Filing fails \nto provide any mechanism to ensure that the load reductions selected through the state or \nEDC processes will provide the specific transmission relief required to address an IROL or \nother locational reliability constraint. Under the IRAS Filing, PJM should not count IRAS as \na reliability resource for locational issues including an IROL condition. PJM will not have \nthe ability or the authority to ensure that the resulting reductions are locationally effective, \nmeasurable, and capable of being delivered when needed. This concern is heightened \nbecause PJM proposes to deploy IRAS before Pre-Emergency Load Management. \nThe exact load to be curtailed matters to PJM operators especially when curtailable \nIRAS load is used to control power flows on IROL interfaces. For example, consider the \noverloading of the AP SOUTH IROL Reactive Interface. Suppose PJM needs 90 MWh relief \nfor this IROL constraint from Dominion EDC. For simplicity, suppose there are only two \nNew Large Loads in Dominion EDC. New Large Load A located in the LSE I has 50 percent \ndistribution factor (DFAX-I) to the IROL interface and New Large Load B located in LSE II \nhas 25 percent distribution factor (DFAX-II) to the IROL interface. If PJM anticipated that \nDominion EDC would request LSE-I and LSE-II to reduce by the identical MWh amount, \nthe directive issued to Dominion EDC would have specified a 240 MWh reduction.38 But, if \nthe Dominion EDC actually requested LSE I to reduce 60 MWh and LSE II to reduce the \n \n38  \nPJM needs to calculate the expected relief to the IROL constraint. The relief would depend on the \ndistribution factors (DFAX) of the New Large Loads to the constraint. In this context, DFAX is the \nMWh quantity of the relief to the constraint for every 1 MWh of load reduction. In the example \nwhere PJM assumes same MWh quantity of load reduction from both LSEs, PJM’s problem is to \nfind a solution to the equation: 0.5*DFAX-I*(Aggregate Load Reduction)+0.5*DFAX-II*(Aggregate \nLoad Reduction) = 90 MWh. DFAX-I (0.5) represents the relief per 1 MWh of reduction from the \nlarge load located in LSE I and DFAX-II(0.25) represents the relief per 1 MWh of reduction from \nlarge load located in LSE II. The solution is 240 MWh. Both LSE I and LSE II would reduce their \nload by 120 MWh. Under this assumption, LSE I would provide 60 MWh (120*0.5) of relief and LSE \nII would provide 30 MWh (120*0.25) of relief."},{"page":26,"startToken":8728,"endToken":9091,"text":"- 26 - \nremaining 180 MWh, the total relief received by PJM would be 75 MWh (60*0.5 + 180*0.25), \nor 15 MWh below the needed relief.  \nThe magnitude of this discrepancy would only increase with the size of the EDC and \nthe number of large loads located within the EDC. To further complicate PJM’s operational \ndecision making, if the directive to issue aggregate load reductions includes multiple EDCs \nand if there were multiple ways to achieve the same reduction, it is unclear which criteria \nwould be used to fairly allocate load reduction MWh. In addition, PJM did not describe \nhow the operators would account for possible noncompliance or delayed response from \nLSEs or the large loads. \nIt is essential to have clear, transparent rules and performance measurement for \ncurtailability because PJM is relying on curtailments to maintain reliability under stressed \nconditions. PJM does not define compliance with the load reduction directive. PJM does not \nspecify the time needed for the entities to achieve the directed load reduction. PJM also \ndoes not acknowledge the possibility of noncompliance or delayed response.  \nPJM’s complete failure to specify curtailment rules will create unintended \nconsequences for reliability and for costs to other customers. The consequences can range \nfrom high scarcity prices or violated transmission constraints to invoking emergency \nactions. Customers will ultimately bear the burden. \nPJM’s IRAS Filing will force other customers to bear economic and reliability \nconsequences that should be borne by the IRAS loads directly. PJM’s IRAS Filing fails to \nassign the costs and risks to the New Large Loads that are responsible for creating those \ncosts and risks. Under the PJM proposal, existing customers could be required to pay \ncompensation to IRAS data centers for curtailments or be curtailed rather than curtailing \nthe New Large Load that created the problem. PJM’s IRAS Filing fails to create the required \nconnection between the costs and risks imposed by New Large Load and the payment for \nthose costs and risks. This result is not consistent with the Ratepayer Protection Pledge.  \nThe problem is even broader. If the identity of the customers curtailed and \ncompensated and the level of compensation vary based on the existence or absence of"},{"page":27,"startToken":9091,"endToken":9415,"text":"- 27 - \nseparate state rules, the actual impact of IRAS on PJM’s markets will vary across the system. \nThis will erode the linkage between PJM’s IRAS rules and their impact on energy, capacity, \nand scarcity outcomes, including during emergency conditions. PJM’s IRAS Filing pretends \nto establish a market wide reliability mechanism while leaving the fundamental economic \nand operational consequences of that mechanism to an unknown range of divergent state \ndecisions.  \nThe Commission should require PJM to establish tariff provisions that ensure that \nthe economic and reliability consequences of IRAS are born solely by the New Large Loads \nwhose incremental demand creates the need for the service. \n10. Telemetry and Performance Measurement Should Be Required. \nThe Commission should require PJM to distinguish between providing telemetry \ninformation as part of the Large Load Registry and establishing a PJM telemetry \nrequirement for the operation and measurement of an IRAS reduction. The former provides \nPJM with information about a New Large Load. It does not by itself establish that PJM will \nreceive real-time telemetry sufficient to monitor the load during an IRAS event, or to \ndetermine whether the required reduction action actually occurred. This distinction is \nimportant because PJM proposes to rely on IRAS reductions as a reliability resource in \naggregate and to control flows on IROL constraints, and to deploy IRAS generally before \nPre-Emergency Load Management. PJM must be able to determine accurately how much \nload actually responded to an IRAS instruction and whether the reduction was attributable \nto that instruction. PJM should therefore require mandatory real time telemetry and \nperformance measurement for loads subject to IRAS, sufficient to verify the actual MW \nreduction delivered in response to an IRAS Action. Absent such requirements, PJM would \nbe unable to verify that IRAS produced the MW reduction on which its reliability \nassessment and any associated compensation depend.  \nThe Market Monitor recommends that the Commission require PJM to supplement \nthe New Large Load Registry’s telemetry information with mandatory, enforceable, real-"},{"page":28,"startToken":9415,"endToken":9709,"text":"- 28 - \ntime telemetry and performance measurement requirements applicable to all loads \nproviding IRAS reductions. This is particularly important if IRAS reductions are to be \ntreated as an operational reliability resource rather than merely as a forecasted or \nadministrative load adjustment. \n11. PJM’s IRAS Filing Undermines the Incentive to Bring New Capacity. \nPJM has not demonstrated that the proposed compensation framework for IRAS \nprovides appropriate incentives for New Large Loads to obtain actual capacity rather than \nrely on curtailment as an alternative. PJM proposes to compensate IRAS reductions at 50 \npercent of the Non-Performance Charge Rate for Performance Assessment Intervals \n(“PAIs”) while also providing that IRAS performance is not subject to nonperformance \npenalties. PJM does not, however, provide sufficient analysis demonstrating that this \ncombination of compensation and performance consequences will incent a New Large Load \nto prefer bringing new capacity over relying on IRAS. The economic comparison is central \nto whether the proposal is just and reasonable. A New Large Load that can avoid procuring \ncapacity by accepting the possibility of IRAS curtailment will compare the cost of obtaining \ncapacity with the expected cost of being curtailed. If the expected frequency and duration of \nIRAS events are sufficiently low, and the consequences of nonperformance are limited \nbecause no nonperformance penalty applies, IRAS becomes an economically attractive \nsubstitute for procuring actual capacity. In that circumstance the proposed framework \nundermines PJM’s stated objective that New Large Loads bear responsibility for the \nincremental capacity requirements associated with their demand.39 PJM must be required to \nquantitatively justify the proposed 50 percent compensation rate and absence of \nnonperformance penalties as providing sufficient economic incentive to bring new capacity. \nAbsent such an analysis, PJM fails to demonstrate that IRAS will function as a reliability \n \n39  \nIRAS Filing at 4–5."},{"page":29,"startToken":9709,"endToken":10027,"text":"- 29 - \nbackstop rather than as a lower cost substitute for capacity. The Commission must require \nPJM to establish that the compensation and performance framework is calibrated so that \nreliance on IRAS is materially less attractive than securing the capacity necessary to support \nthe new load. \nThe IRAS compensation framework should be structured to provide a sufficiently \nstrong economic incentive for New Large Loads to procure qualifying capacity rather than \nrely on IRAS curtailments as a lower cost alternative. The compensation and associated \ncurtailment consequences should reflect the full economic value and reliability cost of the \ncapacity obligation being avoided, be sufficiently predictable to allow a New Large Load to \ncompare the expected cost of IRAS exposure with the cost of procuring capacity, and \nincrease appropriately with the frequency, duration or magnitude of IRAS curtailments. \nThe framework should also ensure that a load cannot obtain an economic advantage by \naccepting IRAS in lieu of procuring capacity while shifting the resulting energy and \nreliability costs to existing customers in violation of the Pledge and Principles. PJM must \ndemonstrate that the expected cost of IRAS participation is high enough, relative to the cost \nof qualifying capacity, to provide a meaningful incentive for New Large Loads to procure \ncapacity and that the compensation does not create an economically attractive substitute for \nthe capacity obligation. \n12. PJM’s Data Center Size Definition is Not Just and Reasonable. \nPJM’s 50 MW data center size cut off is too small and will exclude a significant \nnumber of data centers. PJM fails to provide any actual factual support for its definition of \nNew Large Loads in the IRAS Filing:  \n‘Large Load’ shall mean end-use customer(s) load that has a \ncumulative peak load of 50 megawatts or greater at a single \nelectrical site behind one or more points of interconnection, where \nfor configurations involving multiple affiliated load facilities or \nmultiple points of interconnection with affiliated load facilities"},{"page":30,"startToken":10027,"endToken":10314,"text":"- 30 - \nbehind them, all affiliated load facilities within a one-mile radius \nwill be considered a single electrical site as further described in \nthe PJM Manuals.40 \nPJM argues that the definition is “in line with” the Commission’s Show Cause Order \non Large Loads.41 42 The order states that “it appears that it would be reasonable to define a \nlarge load as a new, commercial or industrial customer, located at a single site behind one \nor more points of interconnection, and that has a peak load of 50 MW or greater, \ninterconnects to the transmission system at a voltage level of greater than 69 [kilovolts \n(“kV”)], and is not part of a co-location arrangement.”43 \nThe one-mile radius requirement in PJM Large Load definition “is intended to avoid \na scenario where, for example, a data center owner is not categorized as Large Load simply \nbecause the owner has elected to site a number of smaller data centers, each with peak \nloads below 50 MW, close together.”44 PJM notes that the “Commission has explicitly \nadopted a one-mile test in other situations to determine whether facilities are “at the same \nsite” to be a Qualifying Facility.”45 \nPJM does not provide any details regarding the implementation of the one-mile \nradius rule. There would need to be some kind of optimizing criteria to uniformly and \nfairly apply such a rule. For instance if there are five affiliated data centers in an area, there \nare many possibilities for grouping the data centers under a one-mile radius rule. \n \n40  \nIRAS Filing, Attachment A (Market Tariff) RAA Art. 1. \n41  \nIRAS Filing at 31. \n42  \nSee 195 FERC ¶ 61,211 at P 58. \n43  \nId. \n44  \nIRAS Filing at 33. \n45  \nId."},{"page":31,"startToken":10314,"endToken":10707,"text":"- 31 - \nTable 1 shows the number of data centers and expected peak load by size for data \ncenters that are expected to be operating in PJM by June 1, 2031. The table includes \nindividual data centers and data center campuses. A data center campus includes multiple \ndata centers and the data centers may or may not grouped together under PJM’s one-mile \nradius rule. PJM’s size cut off of 50 MW will exclude a significant number of data centers.  \nTable 1 Embedded and Forecast Data Centers in the PJM Footprint46 47 \n \nData centers with peak loads less than 50 MW account for 26.8 GW or 28.5 percent of \nthe total data center peak load. Data center campuses with peak loads less than 50 MW \naccount for 6.5 GW or 6.9 percent of the total data center peak load.48 Data centers with \npeak loads at or above 50 MW account for 67.2 GW or 71.5 percent of the total data center \npeak load. Data center campuses with peak loads at or above 50 MW account for 87.4 GW \nor 93.1 percent of the total data center peak load.  \n13. The IRAS Filing Is Not Just and Reasonable Because it Will Raise \nEnergy Prices as an Unintended Consequence Not Referenced in the \nFiling. \nMost of the focus has been on meeting the increasing peak demand in PJM and the \nassociated impact on the capacity market prices. In comparison, the impact on the energy \nmarket has received less attention. The mostly flat load profile of a data center means that \n \n46  \nUnderlying data provided by SynMax Intelligence–Vulcan / IIR Energy. \n47  \nIncludes data centers in the PJM footprint currently operating or scheduled to be operating prior to \nJune 1, 2031.  \n48  \nA plant is a single data center facility on a site. A campus is a multi-building data center \ndevelopment on the same site. \nCounts\nTotal MW\nCounts\nTotal MW\nPeak Load Less than 10 MW\n286\n1,030.1\n193\n551.3\nPeak Load Greater than or equal to 10 MW, Less than 50 MW\n876\n25,724.8\n230\n5,927.7\nPeak Load Greater than or equal to 50 MW\n743\n67,161.4\n360\n87,437.3\nTotal Peak Load\n1,905\n93,916.3\n783\n93,916.3\nData Centers\nData Center Campuses"},{"page":32,"startToken":10707,"endToken":11050,"text":"- 32 - \nunlike residential or commercial load, energy consumption of the data centers during the \npeak periods is not significantly different from the energy consumption during the off peak \nperiods.49 This means that PJM’s load during the normal off peak periods tend to be higher \nwith higher concentration of data centers in PJM’s footprint. Typically, PJM’s energy \ndispatch relies on cheaper base load generators during the off peak periods and expensive \npeakers during morning and evening ramp hours. With higher energy consumption from \ndata centers during all periods: peak and off peak, PJM would need to dispatch expensive \ngeneration even during off peak periods. In PJM, the reliance on expensive generation \nduring the off peak periods would be unavoidable given that there has been limited supply \nof new base load generation in the recent years.50 This would result in higher LMPs in PJM \nas energy prices are set by the offers of the marginal generators following an optimal \ndispatch.  \nThe proposed IRAS would compound the impact of data centers because under this \nproposal, data centers with no offsetting generation would be allowed to consume energy \nfrom PJM’s grid for almost all hours but for the few hours when PJM is expected to direct \nEDCs to curtail load. During all the remaining hours, the new data centers that were \nallowed to connect to the grid without offsetting generation would be consuming energy, \nresulting in PJM dispatching expensive generation to meet the load and higher prices for \nPJM’s regular rate payers. PJM did not propose to remove large load subject to curtailment \nfrom the day-ahead or real-time energy market clearing engines. \n \n49  \n“Notably, annual load rises much faster than summer peak demand. Data centers run at flat 24/7 \nutilization, lifting overnight and shoulder hours by a larger percent increase relative to the summer \nafternoon peak.” See Modo Energy, “Data centers define PJM's 2046 load forecast” \n<https://modoenergy.com/research/en/pjm-load-forecast-data-centers-2046>. \n50  \nSee Generation Capacity Resource Changes, “Analysis of the 2027/2028 RPM Base Residual Auction \n– Part B,” (July 9, 2026) at 47."},{"page":33,"startToken":11050,"endToken":11410,"text":"- 33 - \nPJM has been adding data center load since 2019. The large scale additions have \nincreased since 2023.51 The energy market data from these years provide an opportunity to \nassess the impact of increasing data center load on the energy market prices. The trends \nunmistakably show higher prices not only during the peak periods, but also during most \noff peak periods. \nTable 2 shows the actual and forecasted data center load in PJM. The actual data \ncenter load for a given year is measured as the peak data center load in July of that year. \nThe data center load measured as peak load in July increased by 62 percent from 5,036.9 \nMW in 2023 to 7,735 in 2025. PJM is projecting a substantial and rapid increase in the data \ncenter load in the coming years. During the same period, the real-time load in PJM has \nincreased. Table 2 shows the date, hour and peak load excluding exports for every year \nfrom 2009 to July 2026. From 2009 through 2024, the summer peak load excluding exports \nin PJM averaged 144,802 MW. The summer peak load in PJM did not exceed 150,000 MW in \nany year from 2014 through 2024. During this period, the summer peak load in PJM \naveraged 144,493 MW. The highest peak load, 156,256 MW, since 2009 was reached on July \n2, 2026. \nIn addition to the increase in the peak load, owing to the flat profile of the data \ncenter load, PJM’s load increased across all hours. In 2023, PJM’s real-time load was \nbetween 90 GWh and 120 GWh during 31 percent of hours. In 2025, PJM’s real-time load \nwas between 90 GWh and 120 GWh during 46 percent of hours. PJM has also seen an \nincrease in LMPs during this period. There were substantially more hours where the PJM \nreal-time load-weighted LMP was above $40 per MWh in 2025 than in 2023. In 2023, PJM’s \nreal-time load-weighted LMP was above $40 per MWh during 15 percent of hours. In 2025, \n \n51  \nSee PJM, “Data Center Accuracy Report,” <https://www.pjm.com/-/media/DotCom/planning/res-\nadeq/load-forecast/2026-accuracy-report.xlsx>."},{"page":34,"startToken":11410,"endToken":11717,"text":"- 34 - \nPJM’s real-time load-weighted LMP was above $40 per MWh during 41 percent of hours, \nnearly a threefold increase.  \nThe average real-time load-weighted average LMP increased with the load. This is a \ndirect result of PJM’s least cost dispatch and marginal pricing principles used in the Real-\nTime Energy Market. For example, in 2025, the average real-time load-weighted average \nLMP when the real-time load was between 110 GWh and 120 GWh was $63.28, or 25 \npercent higher than when the real-time load was between 100 GWh and 110 GWh.  \nThe higher load could also contribute to increased use of transmission network \nleading to increased transmission constraint violations. In PJM, when a transmission \nconstraint is limiting and there are no generation alternatives, PJM dispatchers may allow \nthe flow on the transmission constraint to exceed its limit. This is called a transmission \nconstraint violation. When this occurs, the shadow price and LMPs are set by the \nTransmission Constraint Penalty Factor. PJM uses $2,000 per MWh as the default \nTransmission Constraint Penalty Factor. For the first time in the first six months of 2026, the \nTransmission Constraint Penalty Factor contribution to the LMP was its highest, 20.3 \npercent of the real-time load-weighted average LMP.52 This was largely due to increased \n500 kV constraint violations. In 2025, on average, there were twelve 500 kV constraint \nviolation intervals when PJM’s real-time load was between 140 GWh and 150 GWh. This \nhistorical data show that PJM experienced a higher number of 500 kV violations as the load \nincreased. With higher load following the implementation of IRAS, PJM is likely to \nexperience higher frequency of 500 kV violations, and higher prices due to Transmission \nConstraint Penalty Factors. \n \n52  \nSee 2026 Quarterly State of the Market Report for PJM: January through June, Section 3 Energy Market at \nDemand, (August 13, 2026)."},{"page":35,"startToken":11717,"endToken":11940,"text":"- 35 - \nTable 2 PJM Data Center Load (Measured by Peak Load in July)53 \n \n \n53  \nSee PJM, “Data Center Accuracy Report,” https://www.pjm.com/-/media/DotCom/planning/res-\nadeq/load-forecast/2026-accuracy-report.xlsx. \nZone\nForecast\nActual Forecast\nActual Forecast\nActual Forecast\nActual Forecast\nActual Forecast\nActual\nRTO\n3,894.0\n    \n5,036.9\n    \n5,968.3\n    \n6,135.6\n    \n7,735.0\n    \n8,167.2\n    \n11,479.0\n  \n15,866.0\n  \n21,290.0\n  \nAEP\n89.9\n          \n485.5\n       \n889.2\n       \n839.4\n       \n1,761.0\n    \n1,726.1\n    \n2,699.0\n    \n4,191.0\n    \n5,496.0\n    \nAPS\n1.2\n            \n73.4\n          \n8.0\n            \n165.0\n       \n276.0\n       \n319.0\n       \nATSI\n56.0\n          \n132.0\n       \n165.0\n       \n299.0\n       \nBGE\n12.0\n          \n18.0\n          \n25.0\n          \n43.0\n          \nCOMED\n396.9\n       \n497.0\n       \n546.0\n       \n622.7\n       \n885.0\n       \n1,275.0\n    \n2,058.0\n    \nDAYTON\n144.0\n       \n277.0\n       \nDOM\n3,802.9\n    \n3,908.1\n    \n4,712.3\n    \n4,534.0\n    \n4,970.0\n    \n5,563.2\n    \n7,066.0\n    \n8,925.0\n    \n10,615.0\n  \nDQE\nJCPL\nMETED\nPECO\n17.0\n          \n88.0\n          \n281.0\n       \nPEPCO\nPL\n93.0\n          \n189.0\n       \n394.0\n       \n1,274.0\n    \nPS\n246.4\n       \n293.5\n       \n265.3\n       \n289.0\n       \n255.2\n       \n308.0\n       \n383.0\n       \n628.0\n       \n2023\n2024\n2025\n2026\n2027\n2028"},{"page":36,"startToken":11940,"endToken":12206,"text":"- 36 - \nTable 3 PJM Peak Load between 2009 and January through June, 202654 \n \nC. Rejecting the IRAS Filing Would Allow the Commission to Direct an \nAppropriate Remedy. \n1. The Current Rules Are Inadequate to Address Prevailing Market \nConditions. \nThe Market Monitor has extensively documented the fact that the application of the \ncurrent tariff is unjust and unreasonable and produces results that are not competitive.55 56 \n57 \n \n54  \nSee 2026 Quarterly State of the Market Report for PJM: January through June, Section 3 Energy Market at \nDemand (August 13, 2026).  \n55  \nSee Monitoring Analytics, LLC “Analysis of the 2027/2028 RPM Base Residual Auction – Part A,” \n(January 5, 2026). \n56  \nSee Monitoring Analytics, LLC, 2026 Quarterly State of the Market Report for PJM: January through June \n(August 13, 2026) Section 1: Introduction. \nDate\nHour Ending (EPT)\nPJM Load (MWh)\n2009\nMon, August 10\n17\n123,900\n2010\nTue, July 06\n17\n133,297\n2011\nThu, July 21\n17\n154,095\n2012\nTue, July 17\n17\n150,879\n2013\nThu, July 18\n17\n153,790\n2014\nTue, June 17\n18\n138,448\n2015\nTue, July 28\n17\n140,266\n2016\nThu, August 11\n16\n148,577\n2017\nWed, July 19\n18\n142,387\n2018\nTue, August 28\n17\n147,042\n2019\nFri, July 19\n18\n148,228\n2020\nMon, July 20\n17\n141,449\n2021\nTue, August 24\n17\n145,563\n2022\nWed, July 20\n18\n144,356\n2023\nThu, July 27\n18\n144,215\n2024\nTue, July 16\n18\n148,890\n2025\nMon, June 23\n18\n156,256\n2026 (Jan-Jul)\nThu, July 02\n18\n158,005"},{"page":37,"startToken":12206,"endToken":12515,"text":"- 37 - \n2. The Record Provides Sufficient Information for the Commission to \nImmediately Issue a Remedial Directive that Protects Reliability and \nAffordability. \nUpon issuing a finding that the current rules are unjust and unreasonable, the \nCommission can, on the basis of the existing record, direct PJM to implement a remedy \n(“Remedial Directive”). The Remedial Directive is based on the Market Monitor Proposal \n(Attachment A). \nThe Remedial Directive should direct that PJM file, within two weeks, rules and \nprocedures establishing curtailment obligations for wholesale service to data centers that do \nnot yet have new capacity resources or plans to obtain new capacity resources, during a \ndefined transition period that would allow all data centers the time to contract for new \ngeneration capacity. LSEs would require data centers without new capacity to provide \ncurtailment service through a contract with a curtailment coordinator for up to three years \nor other reasonable defined limit.58 PJM would determine penalties for noncompliance with \ncurtailment directives and other requirements as necessary or appropriate to maintain \nresource adequacy. LSEs would require data centers to contract directly with curtailment \ncoordinators to provide curtailments, including terms assigning compliance related costs \nand risks among themselves and holding harmless other LSEs’ customers. \nThe Market Monitor recommends that the Remedial Directive be issued in \nconjunction with a remedial directive in Docket No. ER26-3380, the RBP Filing. The Market \nMonitor recommends that the Commission consolidate the proceedings or otherwise \n \n \n57  \nSee id., Section 5: Capacity Market. \n58  \nAs further explained in the Market Monitor proposal (Attachment A at 3), LSEs could either \nestablish themselves as curtailment coordinators or sign up with a curtailment coordinator if they \nprefer not to join PJM and become a wholesale market participant. The curtailment coordinator \nwould receive a curtailment directive from PJM and the curtailment coordinator would send a \ncorresponding directive to the data center needing to curtail."},{"page":38,"startToken":12515,"endToken":12918,"text":"- 38 - \nresolve the issues raised here and in the RBP Filing in conjunction. If orders establishing \nhearings issue, the Market Monitor moves that this docket and ER26-3380 be formally \nconsolidated. \nThe Remedial Directive can be implemented immediately and can be relied upon to \nmeet the goals of the Pledge and Principles. \nThe Commission has exclusive jurisdiction over the terms and conditions of \nwholesale power sales and the bulk power grid.59 The capacity obligation of LSEs to \nsupport resource adequacy is a term and condition of wholesale power sales subject to the \nCommission’s exclusive jurisdiction.60 61 The Remedial Directive applies to LSEs and the \nterms and conditions necessary to meet capacity obligations to PJM, and these terms cannot \nbe changed by states.62 The Supreme Court has determined that federal regulation in this \nfield preempts state regulation.63 The Remedial Directive does not regulate retail power \n \n59  \nSee 16 U.S.C. § 824. \n60  \nSee Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 163 (2016) (“We agree with the Fourth \nCircuit’s judgment that Maryland’s program sets an interstate wholesale rate, contravening the \nFPA’s division of authority between state and federal regulators. As earlier recounted, … the FPA \nallocates to FERC exclusive jurisdiction over ’rates and charges . . . received . . . for or in connection \nwith’ interstate wholesale sales. §824d(a). Exercising this authority, FERC has approved the PJM \ncapacity auction as the sole rate setting mechanism for sales of capacity to PJM, and has deemed \nthe clearing price per se just and reasonable”). \n61  \nRAA Article 7. \n62  \nSee Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 972 (1986) (“[I]n formulating rates \nover which it has exclusive jurisdiction, FERC ruled that the NFA and AA should be treated as \nallocating 22.5% of the entitlement power of the Tapoco-Nantahala system to Nantahala's \ncustomers and 77.5% of that power to Tapoco's customer. That allocation, reflected as it is in a filed \nrate, must be respected by NCUC. If, as a result, Nantahala needs to purchase additional power \nfrom some nonentitlement source, that need is a reasonable one.’). \n63  \nSee id (state action targeting rates for capacity preempted by federal occupation of the field), citing \nEPSA, 577 U.S. 260, 288 (2016) (“The FPA leaves no room either for direct state regulation of the \nprices of interstate wholesales or for regulation that would indirectly achieve the same result.” \n(internal quotation marks omitted”)."},{"page":39,"startToken":12918,"endToken":13355,"text":"- 39 - \nsales. The Commission’s jurisdiction to determine whether LSEs have met capacity \nobligations related to resource adequacy does not intrude on the jurisdiction over \ngeneration reserved to the States.64 The Commission initiated a proceeding to address \nmatching costs of new transmission network upgrades to data centers.65 A similar and \ncomplementary proceeding is needed to match the costs of new resources to support \nresource adequacy to data centers and to provide for limited interim arrangements to \naddress the period between the start of wholesale electric service to data centers and start of \ncapacity arrangements needed to support such service. The Remedial Directive is within the \nCommission’s jurisdiction based on the Commission’s exclusive jurisdiction over resource \nadequacy.66 The Remedial Directive provides an alternative means for LSEs to demonstrate \nthat the data center loads that they host have satisfied the terms and conditions related to \nthe receipt of wholesale electric service in the PJM Region.  \nThe Remedial Directive provides terms and conditions for wholesale energy service \nto support resource adequacy that define the rules for curtailment obligations, similar, in so \nfar as the Commission’s jurisdiction is concerned, to the Commission’s jurisdiction over \n \n64  \nSee id. at 164 (“That Maryland was attempting to encourage construction of new in-state generation \ndoes not save its program. States, of course, may regulate within the domain Congress assigned to \nthem even when their laws incidentally affect areas within FERC’s domain. See Oneok, Inc. v. \nLearjet, Inc., 575 U. S. 373, 385, 135 S. Ct. 1591, 191 L. Ed. 2d 511, 528 (2015) (whether the Natural \nGas Act (NGA) preempts a particular state law turns on “the target at which the state law \naims”).[citation omitted] But States may not seek to achieve ends, however legitimate, through \nregulatory means that intrude on FERC’s authority over interstate wholesale rates, as Maryland has \ndone here.”); see also Conn. Dep't of Pub. Util. Control v. FERC, 569 F.3d 477, 481 (2009). \n65  \nSee Large Loads Show Cause Order. \n66  \nSee Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 163 (2016) (“We agree with the Fourth \nCircuit’s judgment that Maryland’s program sets an interstate wholesale rate, contravening the \nFPA’s division of authority between state and federal regulators. As earlier recounted, … the FPA \nallocates to FERC exclusive jurisdiction over ’rates and charges . . . received . . . for or in connection \nwith’ interstate wholesale sales. §824d(a). Exercising this authority, FERC has approved the PJM \ncapacity auction as the sole rate setting mechanism for sales of capacity to PJM, and has deemed \nthe clearing price per se just and reasonable.”); see also EPSA, 577 U.S. at 281–282."},{"page":40,"startToken":13355,"endToken":13591,"text":"- 40 - \ndemand response and the role of Curtailment Service Providers within the framework of \nthe demand response rules.67 \nThe reason why the IRAS Filing should be rejected, and the Remedial Directive \nshould issue instead, is the broadly recognized need to protect reliability and affordability \nin the PJM Region. The IRAS Filing fails to address reliability. The IRAS Filing does not \npropose coherent rules, and instead defers to the development of state by state rules that do \nnot provide coherent or consistent rules for the curtailment of service to data centers that do \nnot bring their own capacity. Contrary to the fundamental goals of the Pledge and \nPrinciples, PJM proposes to shift the costs and risks of data center developers who have \ncreated and continue to create the extraordinary and immediate need for new resources to \nexisting customers even though the data centers are ready and willing to assume the costs \nand risks they create. The Remedial Directive can fully and timely implement the goals of \nthe Pledge and Principles. \nII. CONCLUSION \nThe Market Monitor respectfully requests that the Commission afford due \nconsideration to this pleading as the Commission resolves the issues raised in this \nproceeding. \n \nJoseph E. Bowring \nIndependent Market Monitor for PJM \nPresident \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \n \nRespectfully submitted, \n \nJeffrey W. Mayes \n \nGeneral Counsel \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \n \n67  \nSee 577 U.S. 260."},{"page":41,"startToken":13591,"endToken":13710,"text":"- 41 - \nEagleville, Pennsylvania 19403 \n(610) 271‐8051 \njoseph.bowring@monitoringanalytics.com \nEagleville, Pennsylvania 19403 \n(610) 271‐8053 \njeffrey.mayes@monitoringanalytics.com \nPaul G. Scheidecker \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \npaul.scheidecker@monitoringanalytics.com  \nAlexandra Salaneck \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \nalexandra.salaneck@monitoringanalytics.com  \nJohn Hyatt \nSenior Economist \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \njohn.hyatt@monitoringanalytics.com \nDevendra R. Canchi \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \ndevendra.canchi@monitoringanalytics.com  \n \n \nDated: September 3, 2026"},{"page":42,"startToken":13710,"endToken":13715,"text":"ATTACHMENT A \nMarket Monitor Proposal"},{"page":43,"startToken":13715,"endToken":14211,"text":"© Monitoring Analytics 2026 | www.monitoringanalytics.com \nDATE: \nJune 30, 2026, Meeting Date \nTO: \nCIFP: Connect and Manage  \nFROM: \nIMM \nSUBJECT: \nProposed Limited Curtailment Alternative V2 \nThe preferred option for data centers adding load to the PJM system is that LSEs serving data \ncenters require such data centers to bring their own new generation via a bilateral contract \nbetween the load and the generation based on the addition of such LSE requirement to the \nRAA.1 For LSEs with data centers that did not bring their own new generation, the IMM \nproposes that PJM run a reliability backstop auction that would facilitate data centers’ \nprocurement of the new generation resources needed to satisfy the LSEs’ requirements. The \nreliability backstop auction is designed to allow data centers to purchase generation capacity \nwith the intent to sign bilateral contracts with generation resources that offer in the auction. \nThe data centers would, in consultation with the LSE, identify the amount and location of the \ncapacity they need. This reliability backstop auction would include associated rules for an \ninterconnection process for large new data center loads that bring their own new generation \nwith locational and temporal characteristics reasonably matched to their load profile. The IMM \naddresses the requirements for new generation brought by data centers and relied on by the \nLSEs serving such data centers in the IMM’s reliability backstop auction design proposal.  \nThe IMM defines an additional part of a comprehensive approach to reliably serving data \ncenter load while ensuring that data centers pay all of their own costs, which the IMM terms \nthe limited curtailment alternative. The limited curtailment alternative would obligate LSEs \nserving data centers that do not bring their own new generation, either directly through \nbilateral contracts or through the reliability backstop auction, to require that such data centers \nhave agreed as a condition of service from the LSE to be curtailable under defined conditions. \nThis limited curtailment alternative is not the same as the pretense that the data centers are \nproviding demand response for which they should be paid.2 Data centers do not want to be \ncurtailable. Data centers are already critical loads in many applications because they are \nembedded in the workings of the economy and society. Given the level of data center load \ngrowth, this limited curtailability alternative, if correctly designed and enforced for each \nindividual data center served, would provide an incentive for data centers to bring new \ngeneration to the market either through bilateral contracts or through the reliability backstop \nauction. As the curtailment alternative is to serve its intended goal as only a bridge allowing \n \n1  \nSee RAA § 5.2, referencing OA § 15.1. The RAA can be amended only by action of the PJM Board \nand FERC approval, per RAA § 16.4. \n2  \nThe Supreme Court has recognized FERC jurisdictional “wholesale demand response,” involving \n“consumers … commitments [through LSEs] to curtail their use of power, so as to … prevent grid \nbreakdowns.” EPSA v. FERC, 577 U.S. 260, 270 (2016)."},{"page":44,"startToken":14211,"endToken":14730,"text":"© Monitoring Analytics 2026 | www.monitoringanalytics.com \n2 \ndata centers that LSEs cannot serve reliably to receive service while waiting to buy or build \nnew capacity, there must be a strong incentive to not remain under the limited curtailment \nalternative for any longer than necessary. If an LSE does not show that its data center load \nbrings new generation, the LSE must show that the data center load is curtailable if that load \ncomes on line. The IMM proposes that there be a maximum term of three years on the ability \nof the LSE and the data center to rely on the limited curtailment alternative instead of bringing \ntheir own new generation.  \nUnder the proposed associated RAA revisions, LSEs would bear only the risk that they fail to \nrequire data centers to use one of the two available options: bring your own new generation \nand enter into a bilateral; or participate in the reliability backstop auction and enter into a \nbilateral. The risk for the LSE is as currently defined in the RAA.3 LSEs do not bear any risk \nassociated with the bilateral contracts or with the failure of a data center to curtail when \ndirected. The bilateral contract risks are entirely between the two parties to the contract. \nPJM’s modified (June 18, 2026) connect and manage proposal includes the fundamental and \nfatal flaw that there is no clear link between identifying the data centers that do not have \ncapacity and curtailment rules and mechanisms. PJM appropriately removed its prior proposal \nthat relied on PJM’s broad authority to request curtailments to manage extreme conditions \nincluding blackouts. Under that approach, PJM did not have the authority or the ability to \ncurtail specific customers. There was no clearly established link between the behavior (no \ncapacity) and the consequence (curtailment). There are no clear PJM rules governing detailed \ncurtailment priorities and order by customer. This type of curtailments are managed by \nTOs/EDCs. That broad brush approach cannot be targeted in the manner necessary to \nimplement curtailments of specific data centers that have not met the LSE requirement to bring \nyour own new generation and that are subject to the curtailment alternative.  \nHowever, PJM’s latest change to its connect and manage proposal (June 18, 2026) is to disclaim \nresponsibility and simply impose the risk and responsibility for curtailing load on the states. \nPJM will allow significant amounts of new data center load to interconnect to the grid without \ndoing transmission and capacity reliability studies. The unavoidable consequence of that will \nbe that the new loads, without matching new generation, will result in curtailments of load at \nunpredictable times and for unpredictable durations. Without curtailment rules that are clear \nand transparent ahead of time, data centers cannot make economic decisions. Without rules \nthat are clear and transparent ahead of time, the risk and cost of curtailments and load shedding \nmay fall on other customers. This is another example of PJM’s approach running counter to the \n \n3  \nSee RAA § 5.2, referencing OA § 15.1. The RAA can be amended only by action of the PJM Board \nand FERC approval, per RAA § 16.4."},{"page":45,"startToken":14730,"endToken":15254,"text":"© Monitoring Analytics 2026 | www.monitoringanalytics.com \n3 \nPrinciples and imposing risk and uncertainty on other customers. It is not reasonable for PJM \nto simply ignore this issue which is fundamental to the reliable operation of the PJM markets. \nThe IMM proposes to use the existing model for curtailing retail customers, the CSP model, \ncurrently used for demand resources. The CSP model has successfully been used to resolve the \nwholesale/retail jurisdictional issue, allowing PJM to direct curtailments of retail customers \nthrough the intermediary CSP. The purpose of the IMM proposal, like the CSP model, is the \nprotection of system reliability, which is a matter subject to federal jurisdiction.4 Because the \nIMM limited  curtailment alternative proposal is a condition of service and the curtailments do \nnot result in a product or sale of any kind, the curtailments do not involve a product or sale \nthat could be subject to state regulation.5 \nThe IMM’s proposal falls squarely within federal jurisdiction over wholesale sales of power \nand the terms and conditions for such sales. LSEs would be obligated, as a condition of service, \nin the RAA, to require that all data centers that an LSE serves must have a bilateral contract \nwith a new source of generation that meets the requirements to be exempt from curtailment, or \nto either establish themselves as curtailment coordinators (CCs) or sign up with a curtailment \ncoordinator if they prefer not to join PJM and become wholesale market participants. The CC \nwould receive a curtailment directive from PJM and the CC would send a corresponding \ndirective to the data centers under the limited curtailment alternative. Curtailment would \napply to each data center load individually. The behavior of the CC and its customers would \nbe directly monitored. Appropriate penalties would be imposed for nonperformance. \nThe IMM’s proposal is that all data center load that was not online on June 1, 2026, would be \nrequired by their LSE to participate in the reliability backstop auction or to commit to the \nBYONG option. LSEs would have the option to show that the data centers they serve have \ncommitted to a specific future BYONG plan and not be included in the auction. If LSEs cannot \nshow that such data center load brings new generation either through the BYONG option or \nthe reliability backstop auction, the LSE would have to show that the data center load would \nbe curtailable under the CC model if that load comes online. In general, LSEs must show that \ndata center load without new generation at the beginning of a delivery year would instead be \nsubject to curtailment.  \nLSEs would have to show that data centers have agreed that the trigger for curtailment of \ncurtailable data center load would be that, in the implementation of PJM procedures, data \ncenter curtailment would be prior to any PJM EEA1 declaration and prior to curtailment of pre-\nemergency or emergency demand response resources. LSEs would show that data centers \n \n4  \nSee 577 U.S. at 270. \n5  \nSee, e.g., In re Erving Indus., Inc., 432 B.R. 354 (Bankr. D. Mass. 2010) (court concludes electricity is a \ngood rather than a service)."},{"page":46,"startToken":15254,"endToken":15428,"text":"© Monitoring Analytics 2026 | www.monitoringanalytics.com \n4 \nwould also be subject to curtailment outside of emergency procedures at PJM’s discretion, if \nsuch curtailment would contribute to addressing an identified reliability issue. Curtailment \nwould last for the full duration of the emergency procedure or the amount of time necessary to \nresolve the identified reliability issues.  \nPJM would direct the curtailment of data center load on a pro rata basis if the total curtailment \nMW needed by PJM is less than the total data center load on the system that is under the limited \ncurtailment alternative. \nThe limited curtailment alternative is intended as an incentive to bring new generation either \ndirectly or through the reliability backstop auction in a timely manner. The duration of service \nunder the limited curtailment alternative would be limited to three years. The data centers \nwould pay the full cost of capacity to reflect the incentive nature of the limited curtailment \nalternative and to reflect the fact that the data centers would be using system capacity for most \nhours of the year."},{"page":47,"startToken":15428,"endToken":15493,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated at Eagleville, Pennsylvania, \nthis 3rd day of September, 2026. \n \nJeffrey W. Mayes \nGeneral Counsel \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610)271‐8053 \njeffrey.mayes@monitoringanalytics.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":809,"startToken":0,"endToken":1324},{"p":4,"at":809,"title":"I. PROTEST","method":"printed heading","endPage":4,"endAt":821,"startToken":1324,"endToken":1326},{"p":4,"at":821,"title":"A. The IRAS Filing Has Not Been Shown to be Just and Reasonable.","method":"printed heading","endPage":10,"endAt":546,"startToken":1326,"endToken":3438},{"p":10,"at":546,"title":"B. The IRAS Filing Is Deficient, Unjust and Unreasonable.","method":"printed heading","endPage":36,"endAt":79,"startToken":3438,"endToken":11953},{"p":36,"at":79,"title":"C. Rejecting the IRAS Filing Would Allow the Commission to Direct an","method":"printed heading","endPage":40,"endAt":1055,"startToken":11953,"endToken":13525},{"p":40,"at":1055,"title":"II. CONCLUSION","method":"printed heading","endPage":42,"endAt":0,"startToken":13525,"endToken":13710},{"p":42,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":47,"endAt":0,"startToken":13710,"endToken":15428},{"p":47,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":47,"endAt":449,"startToken":15428,"endToken":15493}]}