{"document":{"slug":"rec-20260904-5010","title":"Comments of Voltus, Inc. on PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish an…","issued":"2026-09-04","accession":"20260904-5010","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Voltus, Inc.","kind":"comments","file":"sources/filings/text/20260904-5010_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260904-5010","tier":"record","sha256":"a4c3d375116dbcd47bc9c61bb24491d72f5ab2c09168cf4bdc72591b17cd3b65","pages":41,"tokens":12540,"emptyPages":[],"textThemes":["adequacy","registry","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":106,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nProposal Of Pjm Interconnection, L.L.C. To \nEstablish Interim Resource Adequacy Service \nAnd A Large Load Registry To Address \nSystem Reliability  \n \n \n \nDocket No. RM26-3515-000 \n \nCOMMENTS OF VOLTUS \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC’s” or \n“Commission’s”) Rules of Practice and Procedure, and the August 13 “Combined Notice of \nFilings #2” setting a comment date of September 3, Voltus respectfully submits comments on \nPJM Interconnection LLC’s (“PJM’s”) Federal Power Act Section 205 filing requesting the \napproval of tariff amendments to establish an Interim Resource Adequacy Service (“IRAS”) and \nLarge Load Registry.\n \n1"},{"page":2,"startToken":106,"endToken":508,"text":"TABLE OF CONTENTS \nI. INTRODUCTION......................................................................................................................3 \nII. CLARIFYING THE BYONC CRITERIA FOR DEMAND-SIDE RESOURCES IS \nNECESSARY TO PREVENT UNDUE DISCRIMINATION, SUPPORT PRIVATE \nMARKET CONTRACTING, AND PROVIDE A JUST AND REASONABLE RATE......... 5 \nA. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support \nBYONC in the New Tariff Language As Drafted......................................................................6 \nB. New BTM Assets and Site Reactivations Are a Genuine and Substantial Potential Source \nof Additive System Capacity..................................................................................................... 9 \n1. New BTM assets at existing DR/DER sites increase system capacity much like new \nassets at existing generators/storage projects.......................................................................9 \n2. GW of capacity capability lie dormant at sites that once participated in DR................10 \nC. Excluding New BTM Assets and Site Reactivations is Undue Discrimination..................11 \n1. Treatment of new BTM assets at existing sites versus new capability at existing \ngenerators/storage projects.................................................................................................11 \n2. Treatment of DR/DER site reactivations versus generator repowering.........................12 \nD. In a Context in Which the Private Market Has Been Asked to Proceed Expeditiously with \nBilateral Negotiations Before Tariff Language Has Been Finalized, the Exclusion of New \nBTM Assets and DR/DER Site Reactivations Raises “Notice” Concerns.............................. 13 \n1. The exclusion of demand-side reactivations contravenes the alignment reached during \nthe CIFP process................................................................................................................ 13 \n2. Meanwhile, contracting parties made commercial decisions on a reasonable \nexpectation that reactivations would be included..............................................................14 \nE. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and \nReactivations as Eligible to Support BYONC DR/DER in Both the Upcoming and Any \nFuture IRAS Periods................................................................................................................15 \n1. This definition is designed to mirror the structure and specificity of the \ngeneration/storage eligibility criteria in VI(b)(i)............................................................... 16 \n2. Line item (2) within this definition straightforwardly covers new asset capacity.........17 \n3. Line item (3) employs the language and logic of the reactivation definition for FTM \ngeneration in VI(b)(i)(4).................................................................................................... 17 \nF. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable Resulting in a \nJust and Reasonable Definition of BYONC-Eligible DR/DER Reactivations........................17 \n1. What makes an effective deactivation test?...................................................................17 \n2. Voltus’s test delivers against the standards just described.............................................18 \n3. Voltus’s test solves for other potential concerns............................................................20 \n4. The test’s timeline matches the deactivation timeline on the generator side.................21 \nG. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is \nAdministratively Viable...............................................................................................................21 \nH. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations Eligible to \n2"},{"page":3,"startToken":508,"endToken":811,"text":"Reactivate for BYONC..........................................................................................................22 \nIII. PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE LARGE LOAD \nREGISTRY IS LAUDABLE, BUT TO ALIGN INCENTIVES, THE MECHANISM \nSHOULD ALSO BE CREDITED IN THE CALCULATION OF IRAS-ELIGIBLE LOAD \nAMOUNTS...................................................................................................................................23 \nIV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING \nTIMELINES AS TARIFFED WITH UNDERLYING INTENT.............................................24 \nA. Adjusting RPM Auctions that Capacity Can Have Cleared Prior to Becoming BYONC..24 \nB. Enabling PJM to Verify DER/DR BYONC........................................................................ 25 \n1. Extension of resource owner certification in VII(a)(ii) to apply to section VI, as well as \nthe existing VIII.................................................................................................................26 \n2. Enabling PJM review of DR/DER BYONC after registrations have been completed in \na Delivery Year.................................................................................................................. 26 \n3. Clarification that deficiency charges will apply under VIII(d), in the event that the \nreview finds the BYONC arrangement does not meet the requirements of VI(b).............26 \nV. CONCLUSION........................................................................................................................27 \n \nI.​\nINTRODUCTION \nVoltus, Inc., (“Voltus”) is a distributed energy resource (“DER”) aggregator operating in \nall nine North American wholesale electricity markets. Voltus is a registered curtailment service \nprovider (“CSP”) with PJM Interconnection, L.L.C., (“PJM”) aggregating the flexible attributes \nof retail load across the footprint and offering capacity, energy, and ancillary services products \ninto PJM markets. Relevant to the provision of capacity, Voltus has participated in all Reliability \nPricing Model (“RPM”) since the Base Residual Auction (“BRA”) for 2022/2023 (held in early \n2021) and has delivered its capacity commitments as Demand Resources in the associated \ndelivery years. Voltus also has experience transacting PJM-accredited capacity bilaterally, \nincluding to support “Bring Your Own Capacity\nTM” arrangements1. Voltus’s commercial \nexperience developing demand-side capacity resources closely informs these comments. \n1 See Voltus Blog, Voltus launches “Bring Your Own Capacity Product to Support Data Center Growth and Grid \nResiliency” (Sept. 30, 2025), https://www.voltus.co/press/bring-your-own-capacity-data-centers.  \n3"},{"page":4,"startToken":811,"endToken":1148,"text":"Voltus participated actively throughout the Critical Issue Fast Path (“CIFP”) RBP process \nand the Connect-and-Manage (“CAM” or “C&M”, IRAS’s predecessor) Senior Task Force \n(“CAMSTF”) as well as the merged “CIFP-RBP/CAM.”2 Voltus had earlier engaged in a limited \nmanner in the preceding CIFP on Large Load Additions (“CIFP-LLA”), which had introduced \nseveral of the concepts carried into the January 17 CIFP-LLA Board Decisional Letter and \nsame-day White House Energy Dominance Council and PJM State Governors’ Statement of \nPrinciples, which together set the goals and initial shape of the instant tariff filing and the sister \nRBP filing now before FERC. Voltus’s comments herein reflect a careful attention to the \nevolution of the IRAS (and RBP) frameworks; consideration of the intent of various design \nelements and their interactions; and a respect for the challenge of rapidly designing a complex \nsolution that meaningfully meets an unprecedented moment, while under intense political \nscrutiny, and on largely-untested jurisdictional grounds. Voltus’s consistent interest throughout \nthe stakeholder process has been to ensure a level playing-field for demand-side capacity, with \nrules designed to accommodate the differences between various resource classes without \narbitrarily or unnecessarily limiting the ability of distributed resources to address the resource \nadequacy shortfall. These comments pick up certain issues Voltus raised during the CIFP process \nand seek clarification on new questions raised by the proposed tariff language.  \nVoltus contends that incentivizing Bring Your Own New Capacity (“BYONC”) and \nrelated frameworks is generally more effective and efficient at developing new capacity than \ncentral procurement, and better protects non-cost-causers. Voltus approves the IRAS proposal as \na whole and supports PJM’s reintroduction of the RTO-wide CAM/IRAS incentive framework. \n2 See CIFP-RBP/CAM record at https://www.pjm.com/committees-and-groups/cifp-rbp, and CIFP-LLA record at \nhttps://www.pjm.com/committees-and-groups/cifp-lla; and Executive Summary and proposals filed by Voltus in \nCIFP-RBP/CAM Stage 4, including Voltus RBP/C&M Package Executive Summary (June 2026), available at \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02l---voltus---c\nm-and-rbp---executive-summary.pdf.  \n4"},{"page":5,"startToken":1148,"endToken":1437,"text":"Voltus \nfurther \nappreciates \nthat \nthe \nframework \nincludes \ndemand-side \ncapacity \nresources—Demand Resources (“DR”) and Distributed Energy Resource (“DER”) Capacity \nAggregation Resources—as eligible to support BYONC arrangements, and commends PJM for \nresponding to broad stakeholder support to include the demand side. Demand-side resource \nadditions minimize the risk of stranded assets in the face of an uncertain long-term load forecast, \nbring revenues directly to retail consumers to offset the increase in energy costs associated with \nlarge load growth, support grid resiliency, and promote the technological and operational \nmodernization of the grid for more efficient utilization of existing infrastructure, in turn driving \nlower system costs and improving affordability. Demand-side resources by definition increase \ndemand-side flexibility, crucial for absorbing the increasing renewables penetration that is a \npolicy preference and legislative requirement for many states within the PJM footprint.  \nVoltus’s primary concern herein is that by excluding certain critical categories of new, \ndurable demand-side capacity, the IRAS tariff is unjust and unreasonable because it \nunnecessarily limits the volumes of capacity available to ease system constraints and provide \nratepayer relief. This issue is addressed in Section II. Second, Voltus suggests an expansion of \nthe inclusion of the Peak Shaving Adjustment mechanism to incentivize large load funding of the \nsame (Section III). Third, Voltus offers minor redlines to clarify and align the required timelines \nfor reporting and verifying BYONC arrangements (Section IV). A complete set of suggested \nredlines is provided in Attachment A.  \nII.​\nCLARIFYING \nTHE \nBYONC \nCRITERIA \nFOR \nDEMAND-SIDE \nRESOURCES \nIS \nNECESSARY \nTO \nPREVENT \nUNDUE \nDISCRIMINATION, SUPPORT PRIVATE MARKET CONTRACTING, \nAND PROVIDE A JUST AND REASONABLE RATE \nThe inclusion of new capacity from Demand Resources and DER Capacity Aggregation \nResources naturally raises a question as to requirements on the sites underlying the aggregations. \n5"},{"page":6,"startToken":1437,"endToken":1740,"text":"Stakeholders and PJM staff devoted significant energy to this question during the CIFP process \nand discussed the inclusion of several categories: (1) the capacity of sites providing wholesale \ncapacity for the first time, (2) the added capacity associated with the installation of \nbehind-the-meter (“BTM”) assets (generation, storage) to support DR/DER participation, and (3) \nthe potential “reactivation” capacity of sites that supported a capacity resource at some point in \nthe past, under different conditions, but no longer participate. PJM’s last several proposals on \nBYONC eligibility included all three categories, consistent with the analogous allowance of \nnew-build, incremental, and repowered front-of-the-meter (“FTM”) generation and storage \ncapacity.   \nHowever, the proposed Tariff language on DR/DER resource eligibility only \nunambiguously includes the first category: sites providing wholesale capacity for the first time. \nVoltus understands—and there is evidence in the Tariff’s drafting—that excluding both \ncategories was not the intent: PJM intended preserve the eligibility of new capacity associated \nwith the installation of BTM generation/storage (“new asset capacity”), but chose to exclude the \n“reactivation” of any portion of a site’s capacity not associated with a new asset.3  \nGiven this understanding of intent, several of the following subsections focus specifically \non site reactivations rather than new asset capacity. Voltus contends that both categories must be \nadded back to the final tariff and provides a redline to effectuate this change in Section II.E.  \n3 FERC precedent strongly supports the non-discriminatory treatment of demand-side resources. See FERC Order \nNo. 2222: Fact Sheet (Sept. 28, 2020) (“FERC Order No. 2222 will help usher in the electric grid of the future and \npromote competition in electric markets by removing the barriers preventing distributed energy resources (DERs) \nfrom competing on a level playing field in the organized capacity, energy and ancillary services markets run by \nregional grid operators.”). \n6"},{"page":7,"startToken":1740,"endToken":2093,"text":"A.​ For DR/DER Resources, New Assets and Reactivations May Be Ineligible to \nSupport BYONC in the New Tariff Language As Drafted \nDR/DER resource eligibility is delineated in proposed Tariff, Attachment DD-4, section \nVI(b): \n(ii) For Demand Resources or DER Capacity Aggregation Resources, the resource \nmust qualify as a Planned Demand Resource or DER Capacity Aggregation \nResource, as described in the RAA, Schedule 6 and Schedule 6.2 and: \n(1) be composed of, or reliant on, any location not registered in or prior to \nthe 2026/2027 Delivery Year at which an incremental amount at that \nlocation is the result of the registration of new generation or storage assets \nat the location. However, to the extent three consecutive Delivery Years \nmeet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then \nwill be composed of, or reliant on, any location registered in the Delivery \nYear prior to the first Delivery Year for which the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii) are not met; and/or \n(2) be composed of, or reliant on, locations that were not previously \nsupported Capacity Resource, a Peak Shaving Adjustment, or Price \nResponsive Demand for or prior to the 2026/2027 Delivery Year. \nHowever, to the extent three consecutive Delivery Years meet the \nrequirements of Tariff, Attachment DD-4, section IV(b)(iii), then will be \ncomposed of, or reliant on, locations that were not previously supported a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive \nDemand for the Delivery Year prior to the first Delivery Year for which \nthe requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not \nmet. \n(The orange reflects text that was included in PJM’s redlined tariff in a different color \nthan the surrounding text, and may indicate late-stage edits.)  \nThe second sentences in both VI(b)(ii)(1) and VI(b)(ii)(2) above address the composition \nof eligible BYONC in a future state in which the system has left and then returned to the \nBYONC posture. Putting these aside for now, DR/DER BYONC resources for the IRAS period \nbeginning June 1, 2027, must  \n7"},{"page":8,"startToken":2093,"endToken":2499,"text":"be composed of, or reliant on, any location not registered in or prior to the \n2026/2027 Delivery Year at which an incremental amount at that location is the \nresult of the registration of new generation or storage assets . . . and/or . . . \nlocations that were not previously supported [sic] a Capacity Resource, a Peak \nShaving Adjustment, or Price Responsive Demand for or prior to the 2026/2027 \nDelivery Year. \nThe first clause allows new asset capacity but seemingly only at sites with no past \nDR/DER participation; the second allows new sites in general. Since sites supporting Capacity \nResources, Peak Shaving Adjustments, and Price Responsive Demand must all be registered in \nPJM’s Demand Response Hub database tool (“DR Hub”), the qualification in the second clause \nis likely coincident with “not registered” in the first. Additionally, since a new site’s capacity \nnomination will count whether or not tied to a new asset, and since the capacity nomination will \ninclude the new asset’s capability, the first clause is redundant to the second. Fundamentally, this \ndefinition counts as new all of (but only the) capacity of never-before-registered sites. \nAs to the future IRAS periods, as covered by the second sentences of VI(b)(ii)(1) and \nVI(b)(ii)(2), “to the extent three consecutive Delivery Years meet the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii),” DR/DER BYONC resources \nwill be composed of, or reliant on, any location registered in the Delivery Year \nprior to the first Delivery Year for which the requirements of Tariff, Attachment \nDD-4, section IV(b)(iii) are not met; and/or . . . locations that were not previously \nsupported a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive \nDemand for the Delivery Year prior to the first Delivery Year for which the \nrequirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met. \nOn a plain reading, the first clause above actually requires that a site was registered in the \nDelivery Year prior to the resumption of the IRAS posture (a requirement at odds with a plain \nmeaning of “new”), which seems to be the opposite of the intent. Conversely, the second clause \nrequires that the site was not supporting capacity (and therefore was not registered) in that same \nDelivery Year—a more plausible test of “new.” Reading these clauses literally would leave no \npath for any site to support BYONC in a future IRAS period. Voltus expects a simple drafting \n8"},{"page":9,"startToken":2499,"endToken":2811,"text":"error: the exclusion of “not” before “registered” in the first clause. On that assumption, the tariff \nis intended to allow reactivations for BYONC in a future IRAS posture, since the test is on \nregistration and/or support of a capacity product in the year prior to the resumption of IRAS \nonly.  \nThus the tariff drafting on plain reading allows only new sites today, and (assuming a \none-word addition to resolve the apparent contradiction) both new sites and reactivations toward \nBYONC in future IRAS iterations.  \nB.​ New BTM Assets and Site Reactivations Are a Genuine and Substantial \nPotential Source of Additive System Capacity \nIt is worth considering concretely the assets excluded by PJM’s current definition. First, \nwithout Tariff clarification, new “steel-in-the-ground” physical BTM generation and storage \ninvestments may not support BYONC unless sited at locations that have never before touched a \nwholesale capacity product. In parallel, sites that have ever touched a wholesale capacity product \nare ineligible. Both exclusions carve away very significant sources of new capacity, and \nincentivizing investment in the excluded categories is manifestly good policy, as the following \nexamples illustrate.  \n1.​ New BTM assets at existing DR/DER sites increase system capacity much \nlike new assets at existing generators/storage projects  \nConsider a site that has participated in demand response by changing air conditioning \nsetpoints, where air conditioning is only 5% of site load at a 20 MW large industrial facility. \nInstalling a battery on site, sized to meet 95-100% of the full site’s load, will increase the volume \nof potential site curtailment by 19 MW. The battery will also add the ability to participate in \nancillary services, the Energy market, and to avoid transmission and distribution system peaks. \nOr consider a site already curtailing its full load when PJM’s Emergency Load Response \nProgram (“ELRP”) is dispatched but with the square footage and appetite to install a solar and \n9"},{"page":10,"startToken":2811,"endToken":3125,"text":"storage system, fuel cell, etc. that could be reflected as injection capacity under the DER Model. \nIn both cases, the system gains durable physical infrastructure that is genuinely additive. New \nstorage and generation installed alongside existing sources of capacity—whether behind the \nmeter or in front—provide exactly the kind of efficient capacity expansion necessary to \ncounteract the reliability impacts of unprecedented load growth. \nThe BTM placement of new assets provides additional community benefits. BTM assets \nimprove local grid resiliency, may avoid network upgrades as compared to the generator case for \nthe same volume of new capacity, and send revenues directly to retail customers. BTM \ngeneration and storage also carry less stranded asset risk than FTM assets because the BTM \nassets may have additional use cases, such as providing back-up in the case of a blackout.   \n2.​ GW of capacity capability lie dormant at sites that once participated in DR  \nConsider next a location that once did DR but has gone dormant. Perhaps curtailment \nproved operationally more disruptive than anticipated, or the facility lost the on-site staff \nrequired to execute a manual reduction when called. As such, the opportunity cost in terms of \nproduction, throughput, or other foregone benefits (e.g. HVAC access) simply exceeded the \ncompensation the capacity market had to offer. In each case the underlying capability remains \nphysically present but is “locked out” in absence of a business case sufficient to bring the \ncapability to market. \nThe incentives related to BYONC allow aggregators to overcome these obstacles in \nseveral ways. The aggregator may invest in new systems and equipment—building controls, \nautomatic load control—that address operational infeasibility. Higher revenues may be sufficient \nin themselves to incent participation, and the extended term and revenue certainty associated \nwith BYONC arrangements may have independent value. In short, BYONC provides the \nfinancial incentive to make the participation of dormant sites feasible and economic.  \n10"},{"page":11,"startToken":3125,"endToken":3423,"text":"There are potentially GW of capacity at long-dormant sites. DR, which has been an \neligible RPM resource class since the first auction, in 2007, peaked at just shy of 11 GW \nInstalled Capacity (“ICAP”) registered Demand Resources in Delivery Year 2015/2016, but was \nonly 6.76 GW in 2024/20254 (with erosion due to increasing dispatch frequency and other \nfactors). The delta provides an indication of the volume of existing but “dormant” capability. \nAllowing the market to discover these missing GW and their appropriate price is good policy. \nNote also that site control upgrades and other investments that may be required to “unlock” the \ncapability of dormant sites may be accomplished much faster than utility-scale uprates, much \nlike BTM generation and storage development timelines are shorter than new generator or FTM \nstorage development timelines. “Modular” distributed investments offer a significant advantage \nin terms of Commercial Operation Date (“COD”). \nC.​ Excluding New BTM Assets and Site Reactivations is Undue Discrimination \nBecause an assessment of the differential treatment of DR/DER versus generation/storage \nresources for BYONC eligibility may be informed by consideration of RBP and Qualifying RBP \nOffset (“QRBPO”) criteria, this section notes the resource eligibility criteria for these other two \nproducts as defined in PJM’s companion RBP filing in Docket No. ER26-3380. The same \nunderlying resources should be able to support both BYONC and QRBPO if tied to load growth \nin the 2027/2028 and 2028/2029 Delivery Years; this alignment ensures that a zone may receive \nQRBPO credit for the capacity investments that are decreasing the zone’s Eligible Large Load \nAmount, thus avoiding double procurement.  \n4 See Monitoring Analytics, 2024 State of the Market Report for PJM, Table 5-12 (2025), available at \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm-sec5.pdf. \n11"},{"page":12,"startToken":3423,"endToken":3766,"text":"1.​ Treatment of new BTM assets at existing sites versus new capability at \nexisting generators/storage projects \n​\nUnlike the increase of capacity within an existing generation or storage facility, achieved \nin proposed Tariff, Attachment DD-4, section VI(a) through either an uprate, the utilization of \nadditional interconnection rights, or a change to fuel type, all of which are incremental capacity \nfor an existing physical asset, the addition of new BTM assets involves the addition of \ncompletely new physical assets at an existing site. For this reason, and for those outlined in \nsection B.1 supra, Voltus’ suggested wording for proposed Tariff, Attachment DD-4, section \nVI(b)(ii)(2) captures the capacity related to those new physical assets. \n2.​ Treatment of DR/DER site reactivations versus generator repowering \nWhile the \"repowering of a deactivated generation resource that deactivated prior to April \n10, 2026\" is eligible to back BYONC, QRBPO, and even sell offers into RBP itself, a site that \nhas ever participated as DR in the past is ineligible to support aggregations toward any of the \nthree products. The proposed Tariff language just quoted applies both to BYONC5 and QRBPO6 \nresource eligibility. The language on RBP resource eligibility is even more inclusive, allowing \n“repowering of a generation resource that had deactivated, or announced deactivation, on or \nbefore April 10, 2026” (emphasis added).7 Given the availability of tests to effectively identify \nwhat DR/DER should be considered eligible to reactivate as new, including the test suggested by \nVoltus later in these comments, there is no justification for this discriminatory treatment. \nThe exclusion discriminates unduly between rate classes and results in a perverse policy \noutcome: native load that constituted the vanguard of DR participation but was subsequently \nunable or uninterested in sustaining that participation are blocked from accessing the new large \nload incentives that would make market reentry feasible. This will disproportionately affect DR’s \n7 Proposed Tariff, Attachment DD, section 18.5(b) (RBP filing). \n6 Proposed Tariff, Attachment DD, section 18.2(b) (RBP filing). \n5 Proposed Tariff, Attachment DD-4, section VI(b). \n12"},{"page":13,"startToken":3766,"endToken":4089,"text":"traditional early adopters, namely commercial and industrial (“C&I”) customers previously \nconsidered “large loads.” Meanwhile, new load can meet its IRAS obligation using on-site load \nflexibility backed by storage and generation. The distinction siphons expected BYONC revenues \nfrom veteran to new large loads and promotes on-site asset build-out at data center complexes at \nthe expense of investment in the efficient utilization of dormant C&I capacity. Early DR adopters \nshould not be penalized for the long-ago capacity benefits they provided under different market \nconditions and DR program designs.   \nD.​ In a Context in Which the Private Market Has Been Asked to Proceed \nExpeditiously with Bilateral Negotiations Before Tariff Language Has Been \nFinalized, the Exclusion of New BTM Assets and DR/DER Site Reactivations \nRaises “Notice” Concerns \nThis section primarily traces the evolution of the CIFP conversation on DR/DER \nreactivation eligibility rather than new BTM asset eligibility, because this is the category that \nPJM excluded from both BYONC and QRBPO in its tariff filings. The apparent exclusion from \nBYONC of new BTM asset capacity may be a misreading on Voltus’s part or the result of a \ndrafting error. However, to the extent the category has been excluded, very similar notice \nconcerns as delineated below apply. \n1.​ The exclusion of demand-side reactivations contravenes the alignment \nreached during the CIFP process \nDuring the CIFP-RBP process and later CIFP-RBP/CAM,Voltus and other stakeholders \nadvocated that DR/DER site reactivations should be treated as new capacity equivalently with \nthe generation side. On the BYONC side, Staff included reactivations in its very first proposal \nthat specified what counted as new DR/DER, presented May 15, 2026.8 All versions of PJM’s \nStage 3 package included reactivations, and PJM staff verbally acknowledged the reasonableness \n8 Tim Horger, PJM, Connect and Manage PJM Proposal, at slide 8 (May 15, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/committees-groups/task-forces/camstf/2026/20260515/20260515-item-03a--\n-connect--manage-pjm-package---presentation.pdf. \n13"},{"page":14,"startToken":4089,"endToken":4401,"text":"of providing a market for dormant sites to reactivate as new on the basis of large load price \nincentives, given that existing incentives had proven insufficient for such sites. \nContemporaneously, BYONC was proposed as eligible to decrement the RBP procurement \ntarget, implying reactivations’ eligibility for this function as well. The tight linkage between \nBYONC and the RBP target was maintained until the day before the CIFP Stage 4 meeting.9 \n2.​ Meanwhile, contracting parties made commercial decisions on a \nreasonable expectation that reactivations would be included \nThus, for the final six weeks of the stakeholder process, and up until the RBP and IRAS \ntariff filings four to six weeks later, stakeholders expected that DR/DER reactivations would be \neligible both to reduce a large load’s IRAS exposure (the BYONC function) and to decrement the \nRBP procurement target (the QRBPO function). Given the very short timeframe to finalize \nbilaterals, especially for QRBPO purposes, the industry made investments based on the latest and \nbest understanding of resource eligibility. This meant reactivations on both the generation and \nDR sides.  \nPursuing, under conditions of regulatory uncertainty, both the large load bilaterals and the \ncontracts with the underlying sites that would serve those bilaterals aligned with the best interests \nof the system and the provided incentives. Political actors had expressed urgency, and PJM was \nactively matching potential buyers and sellers through RBP’s “matchmaking” service. \nBYONC arrangements with potentially very large companies as buyers imply complex \ncontracting for a product (IRAS protection) never before sold. Parties required time to develop \nshared understanding and design agreements addressing risk allocation for unknowns beyond \njust present regulatory uncertainty. With IRAS beginning in less than a year and large loads \n9 See PJM, CIFP - Reliability Backstop Procurement - Options and Packages Matrix - Updated (June 29, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-cifp---reliability-bac\nkstop-procurement---options-and-packages-matrix---updated.xls. \n14"},{"page":15,"startToken":4401,"endToken":4659,"text":"seeking to lock in protection, bilateral discussions needed to begin prior to final tariff approval, \nin October or later. PJM has requested effective dates for both 205 filings of just after tariff \napproval, to meet political urgency and accommodate interdependencies with the December \nBRA.  \nParties were thus encouraged, if not required, to make commercial investments and \npursue commercial arrangements on the basis of evidence-backed assessments as to the range of \nfinal tariff outcomes. As explained above, the DR/DER industry’s defensible expectation was \nthat site reactivations and new BTM assets would be eligible to supply BYONC.  \nPJM has publicly explained neither the reasoning behind the change from the CIFP \nconclusion nor the justification for discriminatory treatment compared to generators. Neither the \nBoard CIFP decisional letter10 nor the Board Executive Summaries on RBP11 and IRAS12 \nmentioned the specific definitions of new DR/DER, and there was no reference to a change in \nthese definitions or to considerations that would have led to such a change. \n \n12 PJM Board, CIFP Framework for Service During Periods of Insufficient Resource Adequacy Executive Summary \n(July 27, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-cifp-framework-f\nor-service-during-periods-of-insufficient-resource-adequacy-executive-summary.pdf  \n11 PJM Board, CIFP Reliability Backstop Procurement Executive Summary (July 27, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-cifp-reliability-ba\nckstop-procurement-pjm-board-decision.pdf  \n10 PJM Board, Board Decisional Letter on CIFP Reliability Backstop Procurement and Connect and Manage (July \n27, 2026), available at \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260727-board-decisional-\nletter-on-cifp-reliability-backstop-procurement-and-connect-and-manage.pdf  \n15"},{"page":16,"startToken":4659,"endToken":5072,"text":"E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and \nReactivations as Eligible to Support BYONC DR/DER in Both the Upcoming \nand Any Future IRAS Periods \nVoltus suggested language (in italics below) replaces proposed Tariff, Attachment DD-4, \nsections VI(b)(ii)(1)-(2): \n(ii) For Demand Resources or DER Capacity Aggregation Resources, the resource \nmust qualify as a Planned Demand Resource or DER Capacity Aggregation \nResource, as described in the RAA, Schedule 6 and Schedule 6.2, and must be \nsupported by any combination of the following: \n(1)​sites never previously registered nor otherwise previously supporting a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive \nDemand; \n(2)​new-build behind-the-meter generation or storage assets;  \n(3)​reactivations of locations previously registered or otherwise supporting a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive \nDemand that deactivated prior to, and were not registered in or since, the \n2025/2026 Delivery Year. \n1.​ This definition is designed to mirror the structure and specificity of the \ngeneration/storage eligibility criteria in VI(b)(i) \nThis recommended definition parallels the structure PJM has used to define resource \neligibility on the FTM generation/storage side: first providing for resources that are fully new to \nthe system, then accommodating new capacity tied to specific investments, and finally providing \nfor the repowering of dormant resources. Like the generation and storage criteria, the suggested \ndefinition handles the current and future IRAS periods together, collapsing the additional \nclauses.13 And, wherever possible, the above definition borrows the wording of the \n13 The urgent imperative is to define BYONC eligibility for the first IRAS period, beginning next June. This will \nprovide much-needed clarity for contracting. If the system moves out of and then back into an IRAS posture as \ncontemplated by proposed Tariff, Attachment DD-4, section IV(b) in combination with the proposed definition of \nNew Large Load tariff terms, at a possibly far-future date, it is likely that certain elements of Attachment DD-4 will \nneed to be revisited to account for changing conditions and lessons learned. PJM’s proposed BYONC-eligibility \nlanguage on the generation/storage side accomplishes the tariff’s goal of capturing the policy determinations hashed \nout in the stakeholder process as to the kinds of capabilities that should be incentivized by large load investments. \nVoltus’s amendments attempt to do the same on the DR/DER side. Further specifications needed to accommodate a \nfuture IRAS period, if not requiring tariff revisions, may be appropriately determined in the manuals. \n16"},{"page":17,"startToken":5072,"endToken":5355,"text":"generation/storage eligibility criteria. This consistency supports interpretive ease and \nunambiguously provides for non-discriminatory treatment of distributed demand-side capacity.  \nThe suggested language supplies fundamentally the same level of specificity as PJM's \nlanguage on the underlying sites that may contribute to an aggregation. Voltus does not propose \nthat the tariff resolve every question of measurement and verification for each category. Many \nsuch determinations are properly developed in the PJM manuals.  \n2.​ Line item (2) within this definition straightforwardly covers new asset \ncapacity \nThe capacity associated with a new investment and installation of a physical asset should \nbe included as new regardless of the history of the host site. There is no need to link the \nallowance of this type of capacity to only those locations that do not otherwise “host” eligible \nBYONC capacity. Doing so creates potential ambiguity as to whether new assets at new or \nreactivated sites may support BYONC.  \n3.​ Line item (3) employs the language and logic of the reactivation definition \nfor FTM generation in VI(b)(i)(4) \nOn the generation/storage side, PJM proposes that the “repowering of a deactivated \ngeneration resource that deactivated prior to April 10, 2026” may support a BYONC \narrangement.14 Voltus’s proposed allowance of DR/DER reactivations parallels this structure by \npermitting the reactivation of sites deactivated by a certain date. The primary test is on whether \nthe site has been registered in the Delivery Years since that date. A site could be registered, \nindicating availability, but never dispatched. Thus registration is a stricter and cleaner check than \na criteria based only on “support” of a capacity resource or \"participation\" in DR/DER.  \n14 Proposed Tariff, Attachment DD-4, section VI(b)(i)(4). \n17"},{"page":18,"startToken":5355,"endToken":5669,"text":"F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable \nResulting in a Just and Reasonable Definition of BYONC-Eligible DR/DER \nReactivations \n1.​ What makes an effective deactivation test? \nThe inclusion of new sites and new assets as providing new capacity is largely \nself-justifying. These resources are providing capacity incremental to the system’s total capacity \ntoday. On the other hand, reactivations—whether of generators and FTM storage or sites \nunderlying an aggregation—invite further consideration. It is not self-evident that a generator or \nsite that previously provided system capacity should be counted as new.  \nRather, reactivations provide additive capacity against the counterfactual that the relevant \nresource remains out of commission. If a large load incentivizes the resurrection of a resource \nthat would otherwise stay out of market, that large load may be legitimately credited for \noffsetting the impact of its addition. Thus dormant capacity may be considered new again, if the \nBYONC arrangement is the cause-in-fact of the repowering. This is the logic supporting \ngenerator repowerings is section VI(b)(i)(4).   \nThus the appropriate definition of DR/DER reactivations must assess whether a site now \nout of market would stay out in the normal course of business; in other words, whether it should \nbe considered actually deactivated rather than temporarily unavailable. A deactivated site is one \nthat is not out of market for exogenous, short-term reasons such as maintenance, but for reasons \nthat will hold for the foreseeable future unless there is a material change in market conditions \n(such as a sizable increase in available incentives to participate). An effective test will capture \ntrue deactivations as so defined without sweeping in false positives; at the same time, the \nline-drawing exercise should not arbitrarily exclude a subset of true deactivations in its efforts to \navoid false positives. Finally, the test should not be gameable. It should not allow for a site, by a \n18"},{"page":19,"startToken":5669,"endToken":5995,"text":"change in behavior, to intentionally preserve or create the ability to qualify for the BYONC \nincentive.   \n2.​ Voltus’s test delivers against the standards just described \nVoltus’s test meets the mark because it calibrates the start of the lookback period to the \nspecific market conditions of the pre-IRAS Delivery Years. BRAs for both 2025/2026 and \n2026/2027 cleared at the administratively-imposed price cap, resulting in unprecedented capacity \nvalue that aggregators could pass on to sites willing to register and perform in these Delivery \nYears. BRA results were known well in advance of registration decisions; a retail energy \ncustomer deciding not to participate for those Delivery Years did so with full knowledge of the \nhigh compensation on offer—substantially diminishing the possibility that could have been \nincentivized to reenter the market under the non-IRAS status quo. A retail customer with past \nexperience of DR but that registered in neither of these years has signalled that participation is \nuneconomic or otherwise infeasible absent significant changes at the site or with respect to \nmarket conditions. Simply put, if a site that once participated would have come back anyway \nabsent the BYONC incentive, it would have done so in 2025/2026 or 2026/2027.  \nIf a site is temporarily unavailable due to maintenance or other ordinary, temporary \nconditions, under high pricing conditions, customers and their aggregators are incentivized to \nresolve the condition and become available as quickly as possible. Thus, while a single-year \nlookback risks sweeping in locations that happened to be unavailable for an ordinary reason but \nthat would have returned the following year by default, checking for non-registration in \nconsecutive Delivery Years substantially avoids this risk: a location out for maintenance in \n2025/2026 would be expected to return in 2026/2027, and a location out in 2026/2027 would \nordinarily have participated in 2025/2026. Nonparticipation in both years despite the highest \npricing PJM’s capacity market has thus far produced is not readily explained by transient, \n19"},{"page":20,"startToken":5995,"endToken":6316,"text":"addressable circumstances, but instead indicates a permanent choice or necessity to “deactivate” \nthe site.  \nThe test is also immune to strategic behavior: when the registration decision for \n2025/2026 was made (in May 2025), the IRAS and BYONC frameworks did not exist and were \nnot reasonably foreseeable in their current form. No location would have withheld itself from the \nmarket in order to preserve or manufacture eligibility for a construct that had not yet been \nsocialized or developed. The suggested test identifies revealed preference under conditions that \ncould not have been influenced by the eligibility rule the Commission is now asked to approve. \nNote that pushing back the start of the lookback period does not improve the test but \ninstead disqualifies true deactivations from 2025/2026. A site whose departure from the market \nexactly coincided with a step-change in pricing—an order of magnitude—and which did not \nreturn the following year despite the 2025/2026 price signal and the equally high pricing realized \nand available for 2026/2027, should be considered intentionally dormant. Beginning the \nlookback with Delivery Year 2025/2026 is a well-justified rather than arbitrary choice. \n3.​ Voltus’s test solves for other potential concerns \nIn conversations with PJM, Voltus has heard another concern that may have informed the \nexclusion of reactivations: that Curtailment Service Providers routinely nominate more locations, \nand more UCAP, than is strictly necessary to fill a cleared RPM commitment, to build a \nperformance buffer into the portfolio. Individual locations may effectively cycle in and out of the \nresource from year to year or from dispatch to dispatch, such that a location's apparent absence in \na given period does not reflect genuine unavailability. PJM’s concern, as Voltus understands, is \nthat this “cycling” invites or enables gaming of the “reactivation” category. \nVoltus first observes that there is nothing undesirable about the performance buffer / \ncycling dynamic. Aggregators should be encouraged to build redundancy into their portfolios so \n20"},{"page":21,"startToken":6316,"endToken":6624,"text":"they may perform fully against their commitments. Reliable performance across the range of \nconditions during dispatch requires portfolio diversification as well as judgment about how to \nsequence and manage the participation of individual locations during an event. These activities \nare core to an aggregator’s function and comprise the layer converting distributed resources into \na product legible to and usable by the system operator: individually variable end-use customers \nmay function as a firm capacity resource. \nHowever, Voltus understands and agrees with the premise of the concern with “cycling” \nin the context of reactivation: a location that was available in a given year to contribute to any \ntest or dispatch, but for whatever reason did not end up doing so, has not deactivated and should \nnot be counted as new capacity. \nVoltus's recommended test addresses the concern by disqualifying sites that were in any \nway available to provide capacity: the test is on registrations, not just participation. Only a \nlocation registered by the start of the Delivery Year may have its actions measured and settled \ntoward DR/DER performance. Whether the CSP in fact calls upon such location in response to a \nPJM dispatch instruction is immaterial: the location was registered, and it therefore fails Voltus’s \nreactivation test. The test avoids any “cycling” concerns (as does, incidentally, PJM’s own \nproposed wording which defines DR/DER eligibility in terms of registration and/or support of a \ncapacity resource).  \n4.​ The test’s timeline matches the deactivation timeline on the generator side \nFinally, the proposed test neatly aligns DR/DER reactivation with generator/storage \nreactivation, defined as “repowering of a deactivated generation resource that deactivated prior \nto April 10, 2026.”15 The process to complete deactivation following the decision or \nannouncement takes time, perhaps about a year per Voltus’s understanding. Deactivation by \n15 Proposed Tariff, Attachment DD-4, section VI(b)(i)(4). \n21"},{"page":22,"startToken":6624,"endToken":6928,"text":"April 2026 implies a deactivation decision by sometime in 2025. Similarly, a site not registered \nin DY25/26 has made the “deactivation” decision by May 2025 at latest. \nG. The Proposed Test Provides a Concrete Delineation of Potential Reactivations \nand Is Administratively Viable \nCrucially, Voltus’s test is administratively workable. A time-limited lookback involves a \nstraightforward, well-defined, and efficient database search against the relevant years’ historical \nregistrations, with Electric Distribution Company (“EDC”) account number as the identifier. For \nPJM verification, lengthier lookback periods introduce data fidelity challenges, the complexity of \nchanges to the data model over time, and uncertainty as to stability of EDC account numbers: a \ngiven location’s account number may change for a variety of reasons, disrupting database history \nfor that site. On the customer/aggregator side, there may be insufficient information available to \ncheck eligibility against a longer lookback: a site’s residents, owners, and/or operators may have \nno recollection or knowledge of long-past DR participation, or may confuse participation in a \nutility DR program carrying no resource adequacy benefits with support of a wholesale capacity \nproduct. A discrete and limited lookback enables customers and aggregators to confidently \nassess whether a given site satisfies criteria, providing clarity for bilateral contracting purposes \nand greatly reducing the risk that a resource shows up to the Delivery Year partially \n“unavailable” for BYONC purposes due to site ineligibility discovered during registrations. In \nthis situation, large load MW avoided curtailment risk and have been added back to RPM on the \nbasis of capacity that PJM does not consider to be new. For internal coherence of the \nIRAS/BYONC framework, the reactivation test should provide high confidence to all parties as \nto a site’s eligibility, so that large loads contracted with DR/DER resources may bring to the \nsystem the expected volume of new capacity as defined.  \n22"},{"page":23,"startToken":6928,"endToken":7237,"text":"H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations \nEligible to Reactivate for BYONC \nNote that in comments in Docket No. ER26-3380, Voltus recommended a test of site \ndeactivation for purposes of Qualified Reliability Backstop Procurement Offset (“QRBPO”) \nDR/DER resource eligibility that was  linked to the 2026/2027 Delivery Year only. That \nrecommendation had reflected Voltus's supposition that an allowance of reactivations under a \none-year lookback may have been what PJM originally planned to file for BYONC eligibility \n(see section II.A supra, interpreting the tariff drafting). Voltus has no objection to a two-year test \nwhich aligns with the formulation PJM had advanced in the stakeholder process. Voltus's interest \nis in a defined and administrable lookback applied consistently across the QRBPO and BYONC \nconstructs and future IRAS iterations. \nVoltus welcomes feedback on its proposed test and is not averse to discussing further \ncriteria PJM or the Commission may propose to appropriately identify the set of DR/DER sites \neligible for BYONC reactivation. \nIII.​\nPJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE \nLARGE \nLOAD \nREGISTRY \nIS \nLAUDABLE, \nBUT \nTO \nALIGN \nINCENTIVES, THE MECHANISM SHOULD ALSO BE CREDITED IN \nTHE CALCULATION OF IRAS-ELIGIBLE LOAD AMOUNTS \nAs currently drafted, Peak Shaving Adjustment values are to be separately tracked in the \nLarge Load Registry for each New Large Load16 yet play no role in the calculation of the Eligible \nNew Large Load Amount as written,17 with the potential effect that a Peak Shaving Adjustment \ndoes not reduce a Large Load's exposure to IRAS curtailment. This could mean that a load that \ninvests in reducing demand could qualify its zone for an RBP opt-out and still be subject to \nIRAS curtailment. We support the points made by Advanced Energy United on this issue, that \n17 Proposed Tariff, Attachment DD-4, section VII(h). \n16 Proposed Tariff, Schedule 11, section B.1(a). \n23"},{"page":24,"startToken":7237,"endToken":7529,"text":"clear, unambiguous rules regarding PSA’s treatment are essential, to give those that do use a Peak \nShaving Adjustment the confidence they will not face unexpected curtailment exposure once \nIRAS is filed. We support United’s recommendation that the Commission direct PJM to amend \nthe Eligible New Large Load Amount formula to credit Peak Shaving Adjustment values on the \nsame basis as BYONC and Allocated RBP UCAP MW, or to explain on the record why a load \nmanaging its footprint through a state-sponsored peak shaving program should be treated \nidentically to one that has not. \nIV.​\nVOLTUS \nSUGGESTS \nMINOR \nREDLINES \nTO \nALIGN \nBYONC \nREPORTING TIMELINES AS TARIFFED WITH UNDERLYING INTENT \nA.​ Adjusting RPM Auctions that Capacity Can Have Cleared Prior to \nBecoming BYONC \nVoltus notes a minor inconsistency with the reporting timelines that must be met for \nBYONC to qualify and provide IRAS protection as recorded in the Large Load Registry. PJM’s \ntransmittal letter and tariff design describe three functions enabled by reporting the BYONC \narrangement to PJM, each with different timelines. At minimum, PJM needs to know about the \narrangement prior to the relevant Delivery Year (more precisely, prior to determining the \navailable IRAS amounts for each zone/area, as BYONC decreases these amounts). Additionally, \nPJM should be told about the arrangement prior to the commencement of the supply’s RPM \nparticipation, as insurance that the supply is coming online as a consequence of the BYONC \narrangement. Finally, given that Eligible Large Load Amounts will be removed from the load \nforecast for RPM purposes beginning with Delivery Year 2029/2030, PJM needs to verify the \nmatched load and supply amount prior to finalizing auction parameters for the auction in which \nthe underlying supply first intends to clear (consistent with its ten-year RPM obligation).  \n24"},{"page":25,"startToken":7529,"endToken":7867,"text":"Given the non-applicability of this last deadline for the first two IRAS years as well as \nthe interaction of tariff finalization with in-flight bilateral deals, the application of these \ndeadlines varies for different years. Hence the nuanced delineation of reporting timelines in \nproposed Tariff, Attachment DD-4, sections VII(b)-(d) (setting reporting deadlines for RPM \nparameter adjustments) and VI(a). Section VI(a)(iii) provides the general rule that clearing an \nRPM auction before reporting the BYONC arrangement is disqualifying, with the exception that \nclearing auctions listed in section VI(a)(i) is not. Logically, the exempted auctions should include \nthose that will have already cleared by the time the tariff is approved and which pertain to \nnear-term IRAS years such that supply may be assumed to have cleared in anticipation of a \nBYONC arrangement; these are BRAs 27/28 and 28/29. It is consistent with this logic to \nadditionally exempt the one near-term auction whose parameters will not be impacted by \nIRAS—the Third Incremental Auction (“3IA”) for 2027/2028—to allow parties additional time \nto finalize contracts given how recently the IRAS framework will have been finalized.  \nReflecting this logic but contradicting section VI(a)(i)’s current exemptions, section \nVII(b) sets a just-prior-to-Delivery Year reporting deadline for 27/28 and 28/29 BYONC. Thus, \nVoltus proposes replacing in section VI(a)(i) the reference to BRA 29/30 with a reference to 3IA \n27/28, to clarify that 27/28 BYONC need not be reported until April 1, 2027, (well after the 3IA \n27/28 auction), but that BYONC wishing to clear BRA 29/30 must obey the much earlier \ndeadline provided in VII(c), because PJM needs BYONC inputs in time to adjust auction \nparameters. Expected 29/30 BYONC not able to meet this very near-term deadline may use a \n29/30 Incremental Auction to satisfy the RPM obligation once the BYONC arrangement is \nfinalized and reported. The effectuating redline, at proposed Tariff, Attachment DD-4, section \nVI(a), is as follows: \n25"},{"page":26,"startToken":7867,"endToken":8165,"text":"(i)  Capacity Resources that cleared an RPM Auction for the first time in the Base \nResidual Auction for the 2027/2028, or 2028/2029, and 2029/2030 Delivery Years or \nthe Third Incremental Auction for the 2027/2028 Delivery Year may qualify as \nBYONC to the extent the underlying resource meets the criteria in subsection (b) \nbelow. \n[. . .] \nB.​ Enabling PJM to Verify DER/DR BYONC \nAs discussed above, sections VII(b)-(d) set out the timeframes for when BYONC \narrangements need to be provided to PJM for verification. Following the initial two years, \narrangements need to be provided prior to the commencement of the underlying supply’s RPM \nparticipation and, from Delivery Year 2029/2030, prior to finalizing auction parameters for the \nauction in which the underlying supply first intends to clear. Given that site-level registrations \nfor DR/DER occur immediately prior to the start of a Delivery Year, Voltus proposes three \namendments to ensure that this sequence enables DR/DER BYONC in practice. They are: \n1.​ Extension of resource owner certification in VII(a)(ii) to apply to section \nVI, as well as the existing VIII \nThe process for BYONC to be in an arrangement with a New Large Load anticipates two \nkey stages: (1) reporting of the arrangement; and (2) certification from the resource owner or \ncontractual authority to PJM attesting to the arrangement and that the capacity will follow the \nrequirements of section VIII. With this process occurring well ahead of the time at which \nDR/DER sites will be registered, it will not be possible to provide the level of detail needed to \ndetermine satisfaction of the section VI requirements. To address this, Voltus is suggesting to add \nto section VII the supplier’s certification that the capacity will follow the requirements of section \nVI.  \n26"},{"page":27,"startToken":8165,"endToken":8457,"text":"2.​ Enabling PJM review of DR/DER BYONC after registrations have been \ncompleted in a Delivery Year \nAs PJM verification of BYONC occurs prior to registration and the provision of site level \ninformation, Voltus is suggesting including an ability for PJM to review DR/DER BYONC after \nregistrations have been completed. This enables a practical check of ensuring capacity brought \nfor the purposes of IRAS is ‘new’, while also allowing for the sequence of BYONC verification \nprior to load forecast. \n3.​ Clarification that deficiency charges will apply under VIII(d), in the event \nthat the review finds the BYONC arrangement does not meet the \nrequirements of VI(b)  \nMirroring the existing consequence if a resource supporting a BYONC is unavailable, \nVoltus is suggesting that, should PJM find through their review, or at any time after verification, \nthat BYONC does not meet the requirements of section VI, the deficiency charges process under \nTariff, Attachment DD will apply. This clarifies the outcome generally and links into the specific \nprocess created by the amendments for certification and review suggested in Sections IV.B.1-2, \nsupra. Redlines for all three amendments discussed in this subsection IV.B are provided in \nAttachment A.  \nV.​\nCONCLUSION \nThese comments have highlighted first and foremost the need for non-discriminatory \ntreatment of DR and DER resources: it is unjust and unreasonable to determine whole categories \nof BTM resources, and gigawatts of potential capacity, ineligible to alleviate the growing \nresource adequacy shortfall through the BYONC construct given that “new” DR/DER can be \ndefined just as effectively as “new” utility-scale generation and storage. The remedy is a \ndefinition of BYONC resource eligibility that includes site reactivations and new BTM asset \ncapacity. These comments have also suggested minor modifications to rationalize BYONC \n27"},{"page":28,"startToken":8457,"endToken":8567,"text":"reporting and verification processes in order to ease administrative burden and provide \ncommercial clarity. Reflecting Voltus’s several suggested changes to the Tariff as proposed, a \nredlined copy of Tariff, Attachment DD-4 is appended to these comments (Attachment A). \nVoltus respectfully recommends that the Commission direct PJM to adopt the suggested or \nsimilar amendments.  \nVoltus deeply appreciates PJM’s and PJM stakeholders’ significant and ongoing efforts to \ndesign an effective and workable solution, and thanks FERC for this opportunity to comment.  \n \n \n \nRespectfully submitted, \n \n/s/ Kimaya Abreu \nKimaya Abreu \nSr. Manager, Regulatory Affairs \nVoltus, Inc. \n2443 Fillmore St. \nSan Francisco, CA 94115 \n609.994.7686 \nkabreu@voltus.co \n \nDated: September 3, 2026 \n28"},{"page":29,"startToken":8567,"endToken":8580,"text":"ATTACHMENT A \nSUGGESTED REDLINES TO PROPOSED TARIFF, ATTACHMENT DD-4:  \nINTERIM RESOURCE ADEQUACY SERVICE"},{"page":30,"startToken":8580,"endToken":8829,"text":"I.​\nINTRODUCTION \n \nThis Attachment DD-4 sets forth the terms and conditions governing the provision of Interim \nResource Adequacy Service. As more fully set forth in this Attachment and the PJM Manuals, \nand in conjunction with the Reliability Assurance Agreement: \n \n(a)​\nInterim Resource Adequacy Service is a load reduction service, effective starting \nwith the 2027/2028 Delivery Year, through which Eligible New Large Loads may be \ncompensated for providing load reductions requested by the Office of the Interconnection to \nmaintain system reliability for the purpose of supporting the integration of New Large Loads to \nthe PJM Region that are not in arrangements with new capacity additions to the PJM Region; \n \n(b)​\nStarting with the 2027/2028 Delivery Year, the Office of the Interconnection may, \nin accordance with the Manuals, instruct the implementation of an Interim Resource Adequacy \nService Action prior to calling on Pre-Emergency Load Management Reductions Actions after \ndetermining that available economic real-time supply may not be sufficient to maintain reserves \nto meet applicable Reserve Requirements and/or Interconnection Reliability Operating Limits \nwithin prescribed limits and prevent cascading outages; \n \n(c)​\nThe Large Load Registry maintained by the Office of the Interconnection, \npursuant to the Reliability Assurance Agreement, shall inform which New Large Loads are \neligible to be called on to provide Interim Resource Adequacy Service; and \n \n(d)​\nThe Office of the Interconnection shall coordinate with Electric Distributors, and \nother Members as appropriate, on the provision of Interim Resource Adequacy Service and the \ncompensation for providing Interim Resource Adequacy Service."},{"page":31,"startToken":8829,"endToken":8942,"text":"II.​\nRESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION \n \nThe Office of the Interconnection shall: \n \n(a)​\nmaintain the Large Load Registry, pursuant to Reliability Assurance Agreement, \nSchedule 11; \n \n(b)​\nidentify Eligible New Large Loads; \n \n(c)​\ndetermine the megawatt quantity of New Large Loads eligible to provide Interim \nResource Adequacy Service in each Electric Distributor zone/area for a given \nDelivery Year; \n \n(d)​\nstarting with the 2027/2028 Delivery Year, issue an Interim Resource Adequacy \nService Action based on system conditions; and \n \n(e)​\nrequest Electric Distributors to direct that a quantity of Eligible New Large Load \nAmounts in their respective zone(s)/area(s) be reduced in accordance with an \nInterim Resource Adequacy Service Action."},{"page":32,"startToken":8942,"endToken":9119,"text":"III.​\nRESPONSBILITIES OF ELECTRIC DISTRIBUTORS \n \nElectric Distributors shall: \n \n(a)​\nexecute the Office of the Interconnection’s directives to implement Interim \nResource Adequacy Service Actions among the Eligible New Large Loads in the \nElectric Distributor’s zone/area, which is an area within a Zone for which the \nrelevant Electric Distributor specifies a separate Obligation Peak Load MW value \nand is a service area of an Electric Distributor that is a separately identifiable, \ngeographic area bounded by wholesale metering; \n \n(b)​\ncoordinate with the Office of the Interconnection in developing and maintaining \nthe Large Load Registry by providing the Office of the Interconnection any \ninformation or data the Electric Distributor believes appropriate to facilitate an \naccurate Large Load Registry, including applicable state or RERRA retail tariff or \ncontractual obligations; \n \n(c)​\ncoordinate, as appropriate, with the relevant state(s) or RERRA(s), individual \nLoad Serving Entities, and customers served by the Load Serving Entities in its \nzone/area to support transparent, effective, and orderly deployment of Interim \nResource Adequacy Service; and \n \n(d)​\nimplement compensation program consistent with Tariff, Attachment DD-4, \nsection X."},{"page":33,"startToken":9119,"endToken":9617,"text":"IV.​\nDETERMINATION OF MAXIMUM INTERIM RESOURCE ADEQUACY \nSERVICE EACH ELIGIBLE NEW LARGE LOAD MAY PROVIDE IN A \nDELIVERY YEAR \n \n(a)​\nAll Eligible New Large Loads shall be available to be requested to provide Interim \nResource Adequacy Service by the Office of the Interconnection. \n \n(b)​\nThe amount of Interim Resource Adequacy Service available to the Office of the \nInterconnection may change for each Delivery Year depending on the relationship of the amount \nof Capacity Resources committed, through Tariff, Attachment DD, for a given Delivery Year, \nand the Eligible New Large Load Amounts. \n \n(i)​\nIn the event ([the amount of Capacity Resources committed for a given Delivery \nYear (as determined after the Third Incremental Auction) is less than the PJM \nRegion Reliability Requirement determined prior to the Third Incremental \nAuction] divided by the Pool-wide Accredited UCAP Factor) by an amount \ngreater than the sum (in MW) of all Eligible New Large Load Amounts, then all \nEligible New Large Load Amounts is needed by the Office of the Interconnection \nto be available to provide Interim Resource Adequacy Service for that Delivery \nYear; \n \n(ii)​\nIn the event ([the amount of Capacity Resources committed for a given Delivery \nYear (as determined after the Third Incremental Auction) is less than the PJM \nRegion Reliability Requirement determined prior to the Third Incremental \nAuction] divided by the Pool-wide Accredited UCAP Factor) by an amount less \nthan the sum (in MW) of all Eligible New Large Load Amounts, then the \ndifference (in MW) shall be the cumulative amount (in MW) of Eligible New \nLarge Load Amounts that the Office of the Interconnection needs to be available \nto provide Interim Resource Adequacy Service for that Delivery Year; and \n \n(iii)​\nIn the event ([the amount of Capacity Resources committed for a given Delivery \nYear (as determined after the Third Incremental Auction) equals or exceeds the \nPJM Region Reliability Requirement determined prior to the Third Incremental \nAuction] divided by the Pool-wide Accredited UCAP Factor), then the Office of \nthe Interconnection does not need any Eligible New Large Loads to be available \nto provide Interim Resource Adequacy Service for that Delivery Year. \n \n(c)​\nFor each Delivery Year that meets the requirements of Tariff, Attachment DD-4, sections \nIV(b)(i) or IV(b)(ii), the Office of the Interconnection shall determine: \n \n(i)​\nthe total amount of Interim Resource Adequacy Service (in MW) needed to be \navailable on a daily basis across the PJM Region for the Delivery Year; and \n \n(ii)​\nthe total amount of Interim Resource Adequacy Service (in MW) needed to be \navailable on a daily basis in each Electric Distributor zone/area for the Delivery \nYear, which shall be equal to the product of the sum of all Eligible New Large \nLoad Amounts needed in the PJM Region pursuant to Attachment DD-4, section \nIV(b) multiplied by the quotient of [(the sum of all Eligible New Large Load \nAmounts in the Electric Distributor’s zone/area) divided by (the sum of all \nEligible New Large Load Amounts in the PJM Region)]."},{"page":34,"startToken":9617,"endToken":9895,"text":"V.​\nDETERMINATION OF NEW LARGE LOADS ELIGIBILITY TO PROVIDE \nINTERIM RESOURCE ADEQUACY SERVICE \n \n(a)​\nAll New Large Loads shall be Eligible New Large Loads to the extent that the sum of a \nNew Large Load’s Eligible New Large Load Amount is lessgreater than the New Large Load’s \nregistered peak load (in MW)zero, as provided in the Large Load Registry. New Large Loads \nwith a cumulative installed capacity equivalent of their BYONC arrangements and assigned \nAllocated RBP UCAP MW that equals or exceeds the New Large Load’s registered peak load, as \nprovided in the Large Load Registry, shall not be Eligible New Large Loads. New Large Loads \nthat are located within an FRR Service Area cannot be Eligible New Large Loads. \n \n(b)​\nA New Large Load’s Eligible New Large Load Amount shall be determined as follows: \n \n(New Large Load’s registered peak load (in MW), as provided in the Large Load \nRegistry) minus (the sum of all BYONC arrangements with the New Large Load \nin accordance with Tariff, Attachment DD-4, section VII divided by the Forecast \nPool Requirement for the first Delivery Year in which the BYONC cleared an \nRPM Auction, plus Allocated RBP UCAP MW assigned to the New Large Load, \nin accordance with Tariff, Attachment DD-4, section IX divided by the Forecast \nPool Requirement for the first Delivery Year in which the Allocated RBP UCAP \nMW cleared an RPM Auction, plus the value of any Peak Shaving Adjustment \nattributed to the Large Load in the Large Load Registry). \n \n(c)​\nFor purposes of removing its eligibility to provide Interim Resource Adequacy Service, a \nNew Large Load may enter into arrangements with BYONC supported by one or more resources."},{"page":35,"startToken":9895,"endToken":10290,"text":"VI.​\nBRING YOUR OWN NEW CAPACITY CRITERIA \n \n(a)​\n(i)  Capacity Resources that cleared an RPM Auction for the first time in the Base \nResidual Auction for the 2027/2028, or 2028/2029, and 2029/2030 Delivery Years or the \nThird Incremental Auction for the 2027/2028 Delivery Year may qualify as BYONC to \nthe extent the underlying resource meets the criteria in subsection (b) below. \n \n(ii)​\nMegawatts of Unforced Capacity that have not cleared an RPM Auction, other \nthan those specified in subsection (a)(i) above, may qualify as BYONC to the extent the \nunderlying resource meets the criteria in subsection (b) below. To the extent three \nconsecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section \nIV(b)(iii), then megawatts of Unforced Capacity may qualify as BYONC to the extent the \nunderlying resource meets the criteria in subsection (b) below and such megawatts (1) \nhave not cleared in an RPM Auction conducted for a Delivery Year prior to the first \nDelivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) \nare not met and (2) meet the eligibility criteria set forth in Tariff, Attachment DD-4, \nsection VI. \n \n(iii)​\nWith the exception of the RPM Auctions listed in subsection (a)(i) above, to the \nextent megawatts of Unforced Capacity that have cleared an RPM Auction before any \narrangement with a New Large Load based on such megawatts was reported to the Office \nof the Interconnection, then such megawatts of Unforced Capacity cannot qualify as \nBYONC even if the underlying resource meets the criteria in subsection (b) below. \n \n(b)​\nTo qualify as Bring Your Own New Capacity, resources must meet the following \neligibility requirements: \n \n(i)​\nFor generation and storage resources, the resource must be supported by one of \nthe following: \n \n(1)​\na new-build generation resource including new resources that obtain \nCapacity Interconnection Rights transferred from deactivated resources or \nresources that have announced deactivation as of April 10, 2026; \n \n(2)​\nthe incremental capacity created by an uprate of Existing Generation \nCapacity Resources, but only to the extent such incremental capacity is \ncreated through an increase in such Generation Capacity Resource’s \ninstalled capacity and increase in Capacity Interconnection Rights \nassociated with that Generation Capacity Resource; \n \n(3)​\nthe incremental capacity created by the utilization of Surplus \nInterconnection Service; \n \n(4)​\nrepowering of a deactivated generation resource that deactivated prior to \nApril 10, 2026; or"},{"page":36,"startToken":10290,"endToken":10632,"text":"(5)​\nincremental capacity, whether due to greater Unforced Capacity or a \nhigher level of Capacity Interconnection Rights, created by an Existing \nGeneration Capacity Resource’s changing fuel type to a more efficient fuel \ntype. \n \n(ii)​\nFor Demand Resources or DER Capacity Aggregation Resources, the resource \nmust qualify as a Planned Demand Resource or DER Capacity Aggregation Resource, as \ndescribed in the RAA, Schedule 6 and Schedule 6.2 and must be supported by any \ncombination of the following: \n \n(1)​sites never previously registered nor otherwise previously supporting a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive \nDemand; \n(2)​new-build behind-the-meter generation or storage assets;  \n(3)​reactivations of locations previously registered or otherwise supporting a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand \nthat deactivated prior to, and were not registered in or since, the 2025/2026 \nDelivery Year. \n(1) be composed of, or reliant on, any location not registered in or prior to the \n2026/2027 Delivery Year at which an incremental amount at that location is the \nresult of the registration of new generation or storage assets at the location. \nHowever, to the extent three consecutive Delivery Years meet the requirements of \nTariff, Attachment DD-4, section IV(b)(iii), then will be composed of, or reliant \non, any location registered in the Delivery Year prior to the first Delivery Year for \nwhich the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met; \nand/or \n \n(2) be composed of, or reliant on, locations that were not previously supported a \nCapacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for \nor prior to the 2026/2027 Delivery Year. However, to the extent three consecutive \nDelivery Years meet the requirements of Tariff, Attachment DD-4, section \nIV(b)(iii), then will be composed of, or reliant on, locations that were not \npreviously supported a Capacity Resource, a Peak Shaving Adjustment, or Price \nResponsive Demand for the Delivery Year prior to the first Delivery Year for \nwhich the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met."},{"page":37,"startToken":10632,"endToken":11136,"text":"VII.​\nBRING YOUR OWN NEW CAPACITY ARRANGEMENTS WITH NEW LARGE \nLOADS \n \n(a)​\nFor any BYONC to be in an arrangement with a New Large Load, \n \n(i)​\nthe Load Serving Entity serving the New Large Load or the applicable Electric \nDistributor shall report the BYONC in an arrangement with the New Large Load, in \naccordance with the PJM Manuals. The Office of the Interconnection may also accept \ninformation to the extent interconnection customers, Large Loads, Transmission Owners, \nor other entities voluntarily report any BYONC that may be in an arrangement with a \nNew Large Load; and \n \n(ii)​\nthe resource owner or entity with contractual authority to enter into a BYONC \narrangement must certify to the Office of Interconnection, in accordance with the PJM \nManuals, attesting to the arrangement with the New Large Load and that the BYONC \nwill follow the requirements of Tariff, Attachment DD-4, sections VI and VIII. \n \n(b)​\nFor an arrangement between a New Large Load and BYONC to be effective for the \n2027/2028 or 2028/2029 Delivery Years, for any BYONC arrangement to be considered, the \nrequirements of Tariff, Attachment DD-4, section VII(a) must be met by April 1 for the first \nDelivery Year such arrangement is to result in a reduction in the New Large Load’s Eligible New \nLarge Load Amount. By April 15, the Office of the Interconnection shall update the Large Load \nRegistry to reflect any verified arrangements between New Large Loads and BYONC. \n \n(c)​\nFor an arrangement between a New Large Load and BYONC to be effective for the \n2029/2030 Delivery Year, for any BYONC arrangement to be considered, the requirements of \nTariff, Attachment DD-4, section VII(a) must be reported to the Office of the Interconnection no \nlater than by 50 days prior to the commencement of the 2029/2030 Base Residual Auction or by \n30 days prior to the posting of the planning parameters for the Incremental Auctions arrangement \nfor the 2029/2030 Delivery Year. The Office of the Interconnection shall update the Large Load \nRegistry to reflect any verified arrangements between New Large Loads and BYONC after the \nrelevant RPM Auction. \n \n(d)​\nFor an arrangement between a New Large Load and BYONC to be effective for the \n2030/2031 Delivery Year and subsequent Delivery Years, the requirements of Tariff, Attachment \nDD-4, section VII(a) must be reported to the Office of the Interconnection no later than by 30 \ndays prior to the posting of the planning parameters for the relevant RPM Auction for the initial \nDelivery Year the BYONC enters into an arrangement with the New Large Load. The Office of \nthe Interconnection shall update the Large Load Registry to reflect any verified arrangements \nbetween New Large Loads and BYONC after the relevant RPM Auction. \n \n(e)​\nBYONC that is in an arrangement with a New Large Load must remain in such \narrangement with that New Large Load unless and until the New Large Load is permanently \nout-of-service. \n \n(f)​\nA physical resource may support multiple BYONC, each of which may be in an"},{"page":38,"startToken":11136,"endToken":11398,"text":"arrangement with different New Large Loads, as long as no BYONC is in an arrangement with \nmore than one New Large Load. \n \n(g)​\nA New Large Load may enter into an arrangement with discrete BYONC supported by \ndifferent physical resources. \n \n(h)​\nA New Large Load may enter into an arrangement with BYONC in excess of its current \nEligible Large Load Amount, e.g., to allow for expected growth in the New Large Load, and the \nfull megawatt quantity of such BYONC shall be offered in the first RPM Auction for which the \nNew Large Load is included in the Variable Resource Requirement Curve. \n \n(i)​\n(i)   For any generation or storage resource, the Accredited UCAP of any BYONC shall \nbe the Accredited UCAP for the RPM Auction in which the BYONC cleared for the \ninitial Delivery Year the BYONC is in an arrangement with the New Large Load. \n \n(ii)  For Demand Resources or DER Capacity Aggregation Resources, the Accredited \nUCAP shall be the Accredited UCAP for the RPM Auction in which the BYONC cleared \nfor the initial Delivery Year the BYONC is in an arrangement with the New Large Load \nand must be demonstrated each year for a 10-year period using the Demand Response or \nDER Capacity Aggregation Resources installed capacity for the first Delivery Year after \nthe BYONC is in an arrangement with the New Large Load. For Demand Resources or \nDER Capacity Aggregation Resources that are also the actual New Large Load, there is \nno demonstration required for the initial Delivery Year only to not be an Eligible New \nLarge Load."},{"page":39,"startToken":11398,"endToken":11878,"text":"VIII.​ BRING YOUR OWN NEW CAPACITY PARTICIPATION IN THE \nRELIABILITY PRICING MODEL \n \n(a)​\nAll BYONC in an arrangement with a New Large Load must meet the requirements in \nTariff, Attachment DD, section 5.5A and become Capacity Resources eligible to participate in \nRPM Auctions. \n \n(b)​\nAll BYONC in an arrangement with a New Large Load must be offered into the RPM \nAuctions as Capacity Resources consistent with and pursuant to the capacity must-offer \nrequirements and exceptions set forth in Tariff, Attachment DD, sections 6.6 and 6.6A. BYONC \nmay not seek an exception to the capacity must-offer requirement to provide an external sale, as \navailable under Tariff, Attachment DD, section 6.6(g) for a 10-year period starting with the first \nDelivery Year which the BYONC is in an arrangement with the New Large Load. \n \n(c)​\nAll BYONC in an arrangement with a New Large Load and committed through RPM \nAuctions will be subject to all capacity market rules, as set forth in Tariff, Attachments DD and \nDD-1. \n \n(d)​\nTo the extent the resource supporting a BYONC arrangement:  \n \n​\n(i) is reviewed by PJM immediately prior to the start of a Delivery Year, or at any other \ntime, and does not meet the requirements of Tariff, Attachment DD-4, section VI(b); or  \n \n​\n(ii) is otherwise unavailable in a given Delivery Year,  \n \nthe seller of such resource will be subject to all relevant deficiency charges under Tariff, \nAttachment DD.   \n \n(e)​\nAll BYONC in an arrangement with a New Large Load and not qualifying for an \nexception pursuant to Tariff, Attachment DD, section 6.6(g), must be offered into the applicable \nRPM Auctions as price takers, i.e., $0/MW-day UCAP for a 10-year period starting with the first \nDelivery Year which the BYONC is in an arrangement with the New Large Load. To the extent \nthe resource is a Demand Resource or DER Capacity Aggregation Resource, the BYONC shall \nparticipate in RPM Auctions for ten (10) consecutive Delivery Years as an Annual Demand \nResource or DER Capacity Aggregation Resource, as applicable; provided, however, the seller of \nsuch Demand Resource or DER Capacity Aggregation Resource may, in accordance with Tariff, \nAttachment DD-4, section VII(a)(i) report to the Office of the Interconnection BYONC that \nreplaces such BYONC, where such replacement shall be for the remainder of the replaced \nBYONC’s ten-year RPM Auction participation commitment and the replaced BYONC (and its \nsupporting registrations) may no longer provide BYONC. In such event, the replacement \nBYONC would need to be supported by the certification required by Tariff, Attachment DD-4, \nsection VII(a)(ii), and such replacement arrangement must be effective coincident with the initial \nBYONC releasing its arrangement. \n \n(f)​\nTo the extent three consecutive Delivery Years meet the requirements of Tariff, \nAttachment DD-4, section IV(b)(iii), then any existing BYONC are relieved of the obligations \nunder this Tariff, Attachment DD-4, section VIII."},{"page":40,"startToken":11878,"endToken":12063,"text":"IX.​\nALLOCATION OF RBP UCAP MW \n \n(a)​\nEach Electric Distributor zone/area allocated RBP Charges pursuant to Tariff, Attachment \nDD, section 18.3(a) shall be allocated RBP UCAP MW on a pro-rata basis using the Electric \nDistributor zone/area’s assigned share of the total Final RBP Target MW across all zone/areas. \n \n(b)​\nEach New Large Load’s Allocated RBP UCAP MW shall be determined as follows: \n \n(i)​\nEach Electric Distributor allocated RBP UCAP MW shall inform the Office of the \nInterconnection how such RBP UCAP MW should be further allocated among the New \nLarge Loads located in the Electric Distributor’s zone/area; or \n \n(ii)​\nIn the event the Electric Distributor has not informed the Office of the \nInterconnection how its RBP UCAP MW should be further allocated by April 1 before a \ngiven Delivery Year, the Office of the Interconnection shall allocate such RBP UCAP \nMW to the Electric Distributor’s zone/area pro-rata among all New Large Loads located \nin the zone/area. \n \n(c)​\nThe Office of the Interconnection shall list in the Large Load Registry each New Large \nLoad’s Allocated RBP UCAP MW."},{"page":41,"startToken":12063,"endToken":12540,"text":"X.​\nCOMPENSATION FOR PROVIDING INTERIM RESOURCE ADEQUACY \nSERVICE \n \n(a)​\nThe rate for the provision of Interim Resource Adequacy Service shall be 50% of the \nNon-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any \nEligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the \nNon-Performance Charge Rate as compensation for the provision of wholesale Interim Resource \nAdequacy Service, or (ii) waive receipt in its retail rates any compensation for the provision of \nwholesale Interim Resource Adequacy Service as contemplated by Tariff, Attachment DD-4, \nsection X(c). If any Eligible New Large Load so elects to accept less than 50% of the \nNon-Performance Charge Rate or waives in its entirety receipt of compensation for the provision \nof wholesale Interim Resource Adequacy Service, the wholesale rate for the provision of Interim \nResource Adequacy Service shall reflect the accepted sum less than 50% of the \nNon-Performance Charge Rate or if compensation is waived entirely, the rate shall be zero \ndollars. \n \n(b)​\n(i) Following an Interim Resource Adequacy Event, unless the Electric Distributor \ninforms the Office of the Interconnection otherwise in accordance with Tariff, \nAttachment DD-4, section X(b)(ii), the Electric Distributor shall be responsible for \ncompensating all Eligible New Large Loads that provided Interim Resource Adequacy \nService for up to the amount of such service provided. The Electric Distributor shall be \nresponsible for charging customers in its zone/area to fund any such compensation. \n \n(ii)​\nThe Electric Distributor may request the Office of the Interconnection to \ncompensate certain Members for the provision of Interim Resource Adequacy Service \nand to assess charges on certain Load Serving Entities within the Electric Distributor’s \nzone/area to fund such compensation. In support of such request, as further set forth in \nthe PJM Manuals, the Electric Distributor shall (1) identify each Member to be \ncompensated and provide the level of compensation and (2) identify each Load Serving \nEntity to be charged and the level of charge. \n \n(iii)​\nThe Office of the Interconnection, PJMSettlement, and the Members will not \nassume financial responsibility for the failure of a party to pay any amounts owed to \nanother party under this section. In the event the Electric Distributor requests the Office \nof the Interconnection facilitate the billing associated with an Interim Resource Adequacy \nEvent, such billing shall be considered a bilateral transaction between the Electric \nDistributor and the identified Members and PJMSettlement shall not be a contracting \nparty to the settlement. \n \n(c)​\nNothing in this Tariff, Attachment DD-4, section X shall interfere with any Eligible New \nLarge Load’s election to (i) accept in its retail rates a sum less than 50% of the Non-Performance \nCharge Rate as compensation for the provision of wholesale Interim Resource Adequacy \nService, or (ii) waive receipt in its retail rates any compensation for the provision of wholesale \nInterim Resource Adequacy Service."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":0,"startToken":0,"endToken":106},{"p":2,"at":0,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":2,"endAt":155,"startToken":106,"endToken":112},{"p":2,"at":155,"title":"II. CLARIFYING THE BYONC CRITERIA FOR DEMAND-SIDE RESOURCES IS","method":"printed heading","endPage":2,"endAt":350,"startToken":112,"endToken":138},{"p":2,"at":350,"title":"A. For DR/DER Resources, New Assets and Reactivations May Be Ineligible to Support","method":"printed heading","endPage":2,"endAt":550,"startToken":138,"endToken":161},{"p":2,"at":550,"title":"B. New BTM Assets and Site Reactivations Are a Genuine and Substantial Potential Source","method":"printed heading","endPage":2,"endAt":1478,"startToken":161,"endToken":258},{"p":2,"at":1478,"title":"D. In a Context in Which the Private Market Has Been Asked to Proceed Expeditiously with","method":"printed heading","endPage":2,"endAt":2168,"startToken":258,"endToken":329},{"p":2,"at":2168,"title":"E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and","method":"printed heading","endPage":2,"endAt":2976,"startToken":329,"endToken":417},{"p":2,"at":2976,"title":"F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable Resulting in a","method":"printed heading","endPage":2,"endAt":3605,"startToken":417,"endToken":480},{"p":2,"at":3605,"title":"G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations and Is","method":"printed heading","endPage":2,"endAt":3831,"startToken":480,"endToken":496},{"p":2,"at":3831,"title":"H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations Eligible to","method":"printed heading","endPage":3,"endAt":130,"startToken":496,"endToken":512},{"p":3,"at":130,"title":"III. PJM’S INCLUSION OF PEAK SHAVING ADJUSTMENTS IN THE LARGE LOAD","method":"printed heading","endPage":3,"endAt":468,"startToken":512,"endToken":544},{"p":3,"at":468,"title":"IV. VOLTUS SUGGESTS MINOR REDLINES TO ALIGN BYONC REPORTING","method":"printed heading","endPage":3,"endAt":1593,"startToken":544,"endToken":656},{"p":3,"at":1593,"title":"INTRODUCTION","method":"printed heading","endPage":16,"endAt":0,"startToken":656,"endToken":4659},{"p":16,"at":0,"title":"E. Voltus Suggests a Redline to Plainly and Consistently Include New Assets and","method":"printed heading","endPage":18,"endAt":0,"startToken":4659,"endToken":5355},{"p":18,"at":0,"title":"F. Voltus’s Test of Site “Deactivation” is Non-Arbitrary and Non-Gameable","method":"printed heading","endPage":22,"endAt":170,"startToken":5355,"endToken":6652},{"p":22,"at":170,"title":"G. The Proposed Test Provides a Concrete Delineation of Potential Reactivations","method":"printed heading","endPage":23,"endAt":0,"startToken":6652,"endToken":6928},{"p":23,"at":0,"title":"H. Voltus Welcomes Other Reasonable Proposals to Identify Deactivations","method":"printed heading","endPage":27,"endAt":1259,"startToken":6928,"endToken":8364},{"p":27,"at":1259,"title":"CONCLUSION","method":"printed heading","endPage":29,"endAt":0,"startToken":8364,"endToken":8567},{"p":29,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":30,"endAt":4,"startToken":8567,"endToken":8581},{"p":30,"at":4,"title":"INTRODUCTION","method":"printed heading","endPage":41,"endAt":3129,"startToken":8581,"endToken":12540}]}