{"document":{"slug":"rec-20260904-5013","title":"Protest, Request for Clarification, and Comments of Equinix Inc. on the Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy…","issued":"2026-09-04","accession":"20260904-5013","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"EQUINIX INC.","kind":"protest","file":"sources/filings/text/20260904-5013_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260904-5013","tier":"record","sha256":"6afd61af80b4d5871544cccdc0db063b913e44173e3257a2c664a3f60a410020","pages":3,"tokens":804,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":289,"text":"Equinix.com     © 2026 Equinix, Inc. \n  \nSeptember 3, 2026 \nThe Honorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E., Room 1A \nWashington, D.C. 20426 \nRe:  Submission 1788574 - Protest, Request for Clarification and Comments of EQUINIX INC. \nunder ER26-3515 \nDear Ms. Reese: \nAfter difficulties with interactions of our internal filing system and the FERC online system, I \nhave learned that I inadvertently uploaded and filed the original submission made by PJM \nInterconnection, L.L.C. (“PJM”) initiating Docket ER26-3515, instead of the “Protest, Request for \nClarification and Comments of EQUINIX INC. under ER26-3515.”   \nI only became aware of this issue when I received the attached notice from FERC Online \nSupport, requesting removal of the FERC watermark from the submission that I made at 4:20:02 PM \ntoday, as shown in the attached copy of the receipt of filing. I found this confusing, as I did not insert \nany watermarks on the document I had prepared, which has a time signature of 4:13 PM today, and \nas I saw none when I checked the document. I then looked at the online summary of filing, and \nrealized the file name was for the original PJM filing rather than our document. Clearly, after several \nfailed attempts to upload the correct document, I inadvertently attached the wrong document. \nI am filing a copy of this letter and its two attachments, along with the proper document \nwith the 4:13 PM time stamp. I hope that the original document can be accepted for the \nCommission’s consideration in this proceeding. \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n   /s/ Arthur Haubenstock \n \n \n \n \n \nArthur Haubenstock \n \n \n \n \n \nSr. Counsel, Global Regulatory \nEquinix Inc. \n700 “K” Street, N.W., Suite 600 \nWashington DC, 20001 \n(202) 322-9073 \nahaubenstock@equinix.com \nAttachments"},{"page":2,"startToken":289,"endToken":486,"text":"1 of 1\nCaution:\nCaution:\nCaution:\nCaution: This email is from an external source. Please take care when clicking links, scanning QR codes, or\nopening attachments. When in doubt, use the Report Button\nReport Button\nReport Button\nReport Button.\nThursday, September 3, 2026 at 9:12:07\nThursday, September 3, 2026 at 9:12:07\nThursday, September 3, 2026 at 9:12:07\nThursday, September 3, 2026 at 9:12:07 PM Eastern Daylight Time\nPM Eastern Daylight Time\nPM Eastern Daylight Time\nPM Eastern Daylight Time\nSubject:\nSubject:\nSubject:\nSubject: [EXTERNAL] SCTASK0170495 - Submission 1788574\nDate:\nDate:\nDate:\nDate:\nThursday, September 3, 2026 at 4:56:46 PM Eastern Daylight Time\nFrom:\nFrom:\nFrom:\nFrom:\nFERCOnlineSupport@ferc.gov\nTo:\nTo:\nTo:\nTo:\nArthur Haubenstock\nYou don't often get email from ferconlinesupport@ferc.gov. Learn why this is important\nGood afternoon\nWe are reaching out about Submission 1788574 - Protest, Request for Clarification and\nComments of EQUINIX INC. under ER26-3515. \nWe are requesting that you remove the FERC's watermarks and refile. Or attach a\ncover letter and refile your submission. \nOnce you have refiled, please reply with your new submission number \nThank you\nFERC Online Support \n \nRef:MSG2238124_hdVIK0RW32zK62uRPTkc"},{"page":3,"startToken":486,"endToken":804,"text":"1 of 1\nThursday, September 3, 2026 at 9:14:44\nThursday, September 3, 2026 at 9:14:44\nThursday, September 3, 2026 at 9:14:44\nThursday, September 3, 2026 at 9:14:44 PM Eastern Daylight Time\nPM Eastern Daylight Time\nPM Eastern Daylight Time\nPM Eastern Daylight Time\nSubject:\nSubject:\nSubject:\nSubject:\n[EXTERNAL] FERC Receipt of Filing in ER26-3515-000\nDate:\nDate:\nDate:\nDate:\nThursday, September 3, 2026 at 4:22:11 PM Eastern Daylight Time\nFrom:\nFrom:\nFrom:\nFrom:\neFiling@ferc.gov\nTo:\nTo:\nTo:\nTo:\nArthur Haubenstock, eﬁlingacceptance@ferc.gov\nPriority:\nPriority:\nPriority:\nPriority:\nHigh\nCategory:\nCategory:\nCategory:\nCategory: Red category\nCaution: This email is from an external source. Please take care when clicking links, scanning QR codes,\nor opening attachments. When in doubt, use the Report Button.\nConﬁrmation of Receipt\n-----------------------\nThis is to conﬁrm receipt by the FERC Ofﬁce of the Secretary of the following electronic submission:\n-Submission ID: 1788574\n-Docket(s) No.: ER26-3515-000\n-Filed By: EQUINIX INC.\n-Signed By: Arthur Haubenstock\n-Filing Desc: Protest, Request for Clariﬁcation and Comments of EQUINIX INC. under ER26-3515-000.\n-Submission Date/Time: 9/3/2026 4:20:02 PM\n-Projected Filed Date/Time: 9/3/2026 4:20:02 PM (Subject to Change based on OPM/FERC Closure)\nAdditional detail about your ﬁling is available via the following link:\nhttps://nam11.safelinks.protection.outlook.com/?\nurl=https%3A%2F%2Fferconline.ferc.gov%2FSubmissionStatus.aspx%3Fhashcode%3DPV4f5QQOUD7\nocDMSiLfdJA&data=05%7C02%7Cahaubenstock%40equinix.com%7C9e7abcf8368d4fa19a7008df09f9\n0616%7C72adb2712fc74afea5ee9de6a59f6bfb%7C0%7C0%7C639240637312358818%7CUnknown%7\nCTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIj\noiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=YBzm7Colmk4NsEeS%2FMmsk%2BlS\nmH%2FeORX83Qch8IG46l4%3D&reserved=0\nThank you for participating in the FERC Electronic Filing System.  If you have any questions, or if you\ndetect errors in your submission or the FERC-generated PDF, please contact FERC at:\nE-Mail: ferconlinesupport@ferc.gov mailto:ferconlinesupport@ferc.gov (do not send ﬁlings to this\naddress)\nVoice Mail: 866-208-3676."}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 3","method":"page range","endPage":3,"endAt":2182,"startToken":0,"endToken":804}]}