{"document":{"slug":"rec-20260904-5056","title":"Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc. in support of Protest filed by American Electric Power…","issued":"2026-09-04","accession":"20260904-5056","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"East Kentucky Power Cooperative, Inc.","kind":"protest","file":"sources/filings/text/20260904-5056_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260904-5056","tier":"record","sha256":"c41adf4b4b3691a49274eac1f7e4e4084c3e20778cf494e14a81da9641d4ac07","pages":9,"tokens":2441,"emptyPages":[],"textThemes":["adequacy","credit"]},"pages":[{"page":1,"startToken":0,"endToken":282,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n \n) \n \nDocket No. ER26-3380-000 \n \nMOTION FOR LEAVE TO FILE LIMITED ANSWER, \nAND LIMITED ANSWER, OF \nEAST KENTUCKY POWER COOPERATIVE, INC. \nPursuant to Rule 212 and 213 of the Commission’s Rules of Practice and Procedure,1 East \nKentucky Power Cooperative, Inc. (“EKPC”) moves for leave to answer and answers in support \nof the protests of American Electric Power Service Corporation (“AEP”),2 Indicated PJM \nTransmission Owners (“Indicated TOs”),3 and PPL Electric Utilities Corporation4 (“PPL Electric” \ntogether with AEP and Indicated TOs, “RBP Protestors”) in the above-captioned proceeding. As \nexplained further below, EKPC supports the RBP Protestors with respect to the arguments made \nconcerning PJM Interconnection, L.L.C.’s (“PJM”) proposed treatment of Reliability Backstop \nProcurement (“RBP”) commitments in the event that a Transmission Owner (“TO”) exits from \nPJM during the RBP commitment period. \nI. \nMOTION FOR LEAVE TO ANSWER \nRule 213(a)(2) of the Commission’s Rules of Practice and Procedure generally prohibits \nanswers to answers or protests unless otherwise ordered by the decisional authority. Here, good \ncause justifies the Commission’s granting this motion and accepting this Limited Answer because \n \n1 18 C.F.R. §§ 385.212, 385.213 (2026). \n2 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Limited Protest of American Electric Power Service \nCorporation” (filed Apr. 3, 2026) (“AEP Protest”). \n3 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Protest of the Indicated PJM Transmission Owners” \n(filed Aug. 21, 2026) (“Indicated TOs Protest”). \n4 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for to Intervene, Limited Protest, and Request \nfor Clarification of PPL Electric Utilities Corporation” (filed Aug. 21, 2026) (“PPL Electric Protest”)."},{"page":2,"startToken":282,"endToken":671,"text":"2 \nit provides information that may assist the Commission in its decision-making process.5 For these \nreasons, the Commission should accept this Limited Answer. \nII. \nLIMITED ANSWER \nThis proceeding concerns PJM’s July 31, 2026 filing6 proposing revisions to the PJM Open \nAccess Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving \nEntities (“RAA”) to establish the RBP to address previously identified resource adequacy \nchallenges that have arisen as a result of insufficient capacity commitments in the 2027/2028 and \n2028/2029 Reliability Pricing Model (“RPM”) Capacity Market Auctions (“RBP Proposal”). \nEKPC filed a protest to PJM’s RBP Proposal.7 \nAs explained in the RBP Protests, PJM proposed new rules that “set forth the \nresponsibilities of various parties in the event a Transmission Owner exits from PJM”8 (“TO Exit \nProvisions”) and that would impose new financial obligations on any TO that exits PJM during \nthe fifteen-year term of the RBP commitment.9 For example, the TO Exit Provisions would require \nan exiting TO with net load to pay, on an accelerated basis, all future RBP charges it would have \nowed, or enter into a binding agreement with the owners of the RBP resources to preserve the RBP \ncommitments.10 Or, if the exiting TO leaves with net generation, the TO must ensure that the RBP-\n \n5 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,110, P 22 (2024) (accepting answers to protests and answers \nbecause they assisted the Commission in its decision-making process); PJM Interconnection, L.L.C., 181 FERC ¶ \n61,162, P 29 (2022). Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229, P 102 (2012) \n(accepting answer to an answer because it provided material evidence that corrected the record and informed the \nCommission’s decision-making process); N.E. Utils. Servs. Co. v. NRG Energy, Inc., 101 FERC ¶ 61,327, P 17 \n(2002) (accepting answer to an answer because it helped clarify issues in the proceeding). \n6 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource \nAdequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”). \n7 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Protest of East Kentucky Power Cooperative, Inc.” (filed \nAug. 21, 2026) (“EKPC Protest”). \n8 PJM RBP Filing at 90. \n9 See Proposed Tariff, Attachment DD, § 18.7. \n10 PJM RBP Filing at 94-95."},{"page":3,"startToken":671,"endToken":1068,"text":"3 \ncontracted generation continues to serve PJM through a pseudo-tie, pay the remaining RBP \nobligations in full on an accelerated basis, or execute an agreement to maintain the RBP \ncommitments, essentially stepping into PJM’s role with respect to RBP.11 \nAs PJM did not place any locational limitations on capacity resources offering into the \nRBP, it is possible that selected resources could locate within EKPC’s service territory even though \nPJM is not intending to solicit RBP resources to serve EKPC load. EKPC has not submitted any \nLarge Load Adjustments to PJM, which PJM assumes to be in the RBP Procurement Target, and \ndoes not anticipate receiving a direct assignment of RBP Costs. As a result, potentially allocating \nto EKPC any costs related to RBP selected resources should, at some point over the next 15 years, \nEKPC contemplate exit from PJM is completely divorced from cost causation and not just and \nreasonable. \nHaving been introduced at the very end of the stakeholder process, PJM’s TO Exit \nProvisions were not discussed among stakeholders. Understandably PJM desires clear and \nenforceable commitments; however, its proposal goes too far and imposes obligations on exiting \nTOs unbounded by the cost causation principle. As a result, it should be rejected. EKPC agrees \nwith the arguments set forth by AEP, the Indicated TOs, and PPL Electric: PJM’s proposal unfairly \nexpands the negotiated terms of exit embedded in the Consolidated Transmission Owner’s \nAgreement (“CTOA”), Operating Agreement (“OA”), and RAA.12 Therefore, any imposition of \n \n11 PJM RBP Filing at 92-94. \n12 Each TO has a contractual right to leave a Regional Transmission Organization (“RTO”), and the Commission, \nunder its Federal Power Act (“FPA”) section 205 authority, ensures that the departing utility satisfies its “contractual \nobligations” applicable to it under its RTO’s governing documents upon withdrawal. See AEP Protest at 21. In PJM’s \ncase, these requirements are clear. Section 3.4 of the CTOA requires payment of Regional Transmission Expansion \nPlan fees; however, the CTOA does not require an exit fee. See AEP Protest at 25. Section 5.1.1 of the RAA requires \npayment of capacity PJM acquired on the Load Serving Entity’s (“LSE”) behalf, up to and including the last capacity \nauction in which the LSE’s load forecast was included. See id. at 26. And new provision to RAA – Section 7.2A \nrequires payment of all section 202(c) charges allocated to it. See id."},{"page":4,"startToken":1068,"endToken":1430,"text":"4 \nan exit fee that obligates departing load to pay for charges that are unrelated to its fair allocation \nof RBP commitments because they exceed or are not based not on the RBP Charges allocated to \nan Electric Distributor zone/area is not just and reasonable. \nA. The TO Exit Provisions Violate the Cost Causation Principle. \nEKPC agrees with the RBP Protestors that the TO Exit Provisions violate the cost causation \nprinciple. The Commission’s cost causation principle requires that “all approved rates reflect to \nsome degree the costs actually caused by the customer who must pay them,” in order to be found \njust and reasonable and not unduly discriminatory or preferential under FPA section 205.13 Here, \nthe TO Exit Provisions impose costs that do not align with an exiting TO’s obligations under the \nRBP Proposal.14 \nIn its Protest, AEP highlights the disconnect between the potential financial obligations an \nexiting TO may be responsible for relative to the RBP Charges it would pay if it remained in PJM, \nassuming the Commission accepted the RBP Proposal cost allocation methodology and the costs \nthat would be imposed if it exited PJM.15 The exit fee requires the TO to take on costs driven by \n“where PJM happens to procure or locate new RBP resources.”16 EKPC echoes AEP’s concerns \nthat if PJM acquired new RBP resources in the exiting TO’s zone, the exiting TO would be required \nto pay for such RBP resources regardless of whether such RBP resources are tied to that TO.17 To \nrequire TOs to pay more than their obligation would be inconsistent with the Commission’s cost \n \n13 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992). \n14 In its Protest, EKPC raised concerns regarding the cost allocation and rate impact of the RBP Proposal. See EKPC \nProtest at 15-21 (the RBP Proposal is unjust and unreasonable because the resulting rate impact is uncertain) and 28-\n31 (PJM’s proposals with respect to decrementing and use of offsets are unjust and unreasonable because they ignore \nthe Commission’s cost causation principles). \n15 AEP Protest at 17-20. \n16 AEP Protest at 11. \n17 AEP Protest at 18."},{"page":5,"startToken":1430,"endToken":1724,"text":"5 \ncausation policy. PJM cannot penalize a TO for exercising its contractual rights to leave PJM by \nimposing an exit fee greater than the RBP Charges that it would otherwise be allocated.18 \nFurther, EKPC agrees with the Indicated TOs that the TO Exit Provisions violate cost \ncausation principles “by allocating generation- and capacity-related costs to TOs, which neither \ncaused nor will benefit from these costs.”19 An exiting TO should not be responsible for the RBP \ncommitments of generation resources and load within its zone where such costs cannot be \nconstrued as transmission-related costs properly allocated to the TO. The costs of procuring \ngeneration capacity under the RBP Proposal are driven by Load Serving Entities (“LSEs”) and \ntheir customers, not TOs. \nB. The TO Exit Provisions Lack the Required Clarity and Specificity to be \nFound Just and Reasonable. \n \nAs proposed, the TO Exit Provisions lack the clarity and specificity required for a TO to \ndetermine its obligations upon withdrawal from PJM. EKPC agrees with PPL Electric that any exit \nprovision should not run afoul of the Commission’s requirement that rates be “clear and \nspecifically set forth.”20 PPL Electric identifies language, such as “all costs” and “all forward \nobligations,” that exemplifies the financial uncertainty created by the TO Exit Provisions.21 The \nproposal does not include definitions for such costs nor include a limiting principle associated with \nthe costs sufficient to provide certainty for the exiting TO. \nSimilarly, EKPC agrees with AEP that any RBP exit provisions must provide “a \ntransparent and reasonably calculable measure of the financial consequences of withdrawal” in \n \n18 AEP Protest at 18. \n19 Indicated TOs Protest at 10. \n20 PPL Electric Protest at 11 (citing 18 C.F.R. § 35.1(a)). \n21 PPL Electric Protest at 11."},{"page":6,"startToken":1724,"endToken":2055,"text":"6 \norder to make informed decisions.22 As explained in EKPC’s Protest, a rate that is impermissibly \nvague such that customers cannot determine their cost burden is unjust and unreasonable.23 The \nTO Exit Provisions do not have sufficient specificity to allow a TO to calculate the costs it will \nface should it choose to leave PJM, and therefore the Commission should find that they are not \njust and reasonable. \nMoreover, any exit obligation related to the RBP Proposal should be limited to that which \nis necessary to prevent RBP charges from being shifted to remaining load.24 Should the \nCommission accept PJM’s RBP Proposal,25 EKPC urges the Commission to be clear that its \ndetermination in this proceeding is confined to the specific proposed Tariff language governing \nRBP Charges and does not disturb the Commission’s existing precedent regarding other PJM \ncontractual exit commitments.26 Notwithstanding that PJM’s RBP Proposal makes it challenging \nto determine the RBP Charges with certainty,27 EKPC concurs with AEP’s request that the \nCommission should “expressly reaffirm that any expansion of a Transmission Owner’s \nresponsibility for charges upon withdrawal accepted in this proceeding is limited to RBP charges \nand does not otherwise expand to a departing TO’s obligations under the TO Agreement, RAA, or \nPJM Tariff.”28 \n \n22 AEP Protest at 19-20. See also Tri-State Generation & Transmission Ass’n, 175 FERC ¶ 61,229, P 12 (2021) \n(finding the proposed Contract Termination Payment (“CTP”) to be “impermissibly vague because it lack[ed] detailed \nprocedures governing when and how a utility member may obtain a CTP methodology calculation” and “utility \nmembers [could not] estimate their own CTP payments or reasonably predict the impacts of a membership \nwithdrawal” since the calculation relied on proprietary information). \n23 EKPC Protest at 15-16. \n24 See AEP Protest at 27. \n25 As noted, EKPC protested the PJM RBP Filing and requested that the Commission reject the RBP Proposal. \n26 AEP Protest at 27. \n27 See EKPC Protest at 15. \n28 AEP Protest at 28."},{"page":7,"startToken":2055,"endToken":2262,"text":"7 \nC. The TO Exit Provisions “Unnecessarily Constrain Future Decision-Making.” \nPJM concedes that a TO withdrawing is a “remote” possibility yet proposes rigid \nobligations that very likely would need to be revisited if a TO sought to withdraw over the 15-year \nRBP commitment period. EKPC agrees with PPL Electric that the proposed TO Exit Provisions \nwould “unnecessarily constrain” the parties involved in effectuating a TO’s withdrawal from PJM, \nincluding the Commission and state regulatory authorities.29 Any withdrawal would require \nextensive negotiations and communications amongst the parties taking into account the specific \nfacts and circumstances at that time.30 Additionally, any withdrawal would already need to comply \nwith the CTOA provisions, which require Commission authorization of the withdrawal.31 As PPL \nElectric argued, “preemptively mandating how the costs and contractual arrangements of \ngeneration resources and load within an exiting Transmission Owner’s zone must be treated” is \nnot necessary and likely will need to be revisited when the actual, specific circumstances are \nconsidered.32 Accordingly, EKPC urges the Commission to reject PJM’s proposed TO Exit \nProvisions. \n \n29 PPL Electric Protest at 9-10. \n30 PPL Electric Protest at 9-10. \n31 PPL Electric Protest at 9-10 (citing CTOA, Section 3.2). \n32 PPL Electric Protest at 10 (emphasis in original)."},{"page":8,"startToken":2262,"endToken":2395,"text":"8 \nIII. \nCONCLUSION \nWherefore, EKPC respectfully requests that the Commission accept this answer, consider \nthe arguments set forth herein, and take such action as requested herein and in the EKPC Protest. \n \nRespectfully submitted, \n \n \nDenise R. Foster Cronin \nChief Compliance Officer and SVP \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \n701 N.E. 7th \nWinchester, KY 40392-0707 \nTel: (859) 745-9615 \ndenise.cronin@ekpc.coop \n \n \nOn behalf of East Kentucky Power Cooperative, \nInc. \n \n \n \n \n \n/s/ Daniel E. Frank \n \n \nDaniel E. Frank \nAllison E. S. Salvia \nKelly A. Cuthbertson \nAdriana J. Santana \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 2001-3980 \nTel: (202) 383-0100 \ndanielfrank@eversheds-sutherland.com  \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \nanasantana@eversheds-sutherland.com \n \nCounsel \nfor \nEast \nKentucky \nPower \nCooperative, Inc. \n \n \n \nDated: September 4, 2026"},{"page":9,"startToken":2395,"endToken":2441,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have served the foregoing document upon each person listed on the \nofficial service list compiled by the Secretary in this proceeding. \nDated at Washington, DC, this 4th day of September, 2026. \n \n \n \n \n \n \n \n \n/s/Kelly A. Cuthbertson \n \n \n \n \n \n \n \nKelly A. Cuthbertson"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1024,"startToken":0,"endToken":148},{"p":1,"at":1024,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":162,"startToken":148,"endToken":306},{"p":2,"at":162,"title":"II. LIMITED ANSWER","method":"printed heading","endPage":4,"endAt":263,"startToken":306,"endToken":1114},{"p":4,"at":263,"title":"A. The TO Exit Provisions Violate the Cost Causation Principle.","method":"printed heading","endPage":5,"endAt":777,"startToken":1114,"endToken":1552},{"p":5,"at":777,"title":"B. The TO Exit Provisions Lack the Required Clarity and Specificity to be","method":"printed heading","endPage":7,"endAt":3,"startToken":1552,"endToken":2056},{"p":7,"at":3,"title":"C. The TO Exit Provisions “Unnecessarily Constrain Future Decision-Making.”","method":"printed heading","endPage":8,"endAt":3,"startToken":2056,"endToken":2263},{"p":8,"at":3,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2263,"endToken":2395},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":318,"startToken":2395,"endToken":2441}]}