{"document":{"slug":"rec-20260908-5257","title":"Comments of the Solar Energy Industries Association in Support of Midcontinent Independent System Operator, Inc.’s filing proposing revisions to establish…","issued":"2026-09-08","accession":"20260908-5257","docket":"ER26-3552-000","group":"MISO zero-injection generator interconnection agreement","filer":"Solar Energy Industries Association","kind":"comments","file":"sources/filings/text/20260908-5257_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5257","tier":"record","sha256":"ecca38f59dd9a7e9da6ec0d50f18eb81f142a0b1a3abfd90c8989b135f31b427","pages":7,"tokens":1969,"emptyPages":[],"textThemes":["study","colo","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":240,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nMidcontinent Independent System Operator, \nInc. \n) \n) \n) \n \nDocket No. ER26-3552-000 \n \nCOMMENTS OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION \n \nPursuant to Rule 213 of the Federal Energy Regulatory Commission’s (Commission) \nRules of Practice and Procedure,1 the Solar Energy Industries Association (SEIA)2 submits these \ncomments supporting the Midcontinent Independent System Operator, Inc.’s (MISO) filing \nproposing revisions to establish the Zero Injection Generator Interconnection Agreement \n(ZGIA).3 In addition to establishing the ZGIA, MISO’s ZGIA Proposal would establish a study \nprocess and operational requirements, and market and resource adequacy rules to accommodate \nZero-Injection Generation Resources (ZG Resources) that intend to serve load interconnecting at \nthe same substation as the Generating Facility. MISO’s proposal represents a just and reasonable \nstep toward addressing the resource adequacy issues posed by the rapid addition of large loads. \nSEIA supports MISO’s ZGIA Proposal and urges the Commission to accept it.4 \n \n \n1 18 C.F.R. § 385.213 (2026). \n2 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar \nindustry, but do not necessarily reflect the views of any particular member with respect to any issue. \n3 Midcontinent Independent System Operator, Inc., Zero Injection Generator Interconnection Agreement, Docket \nNo. ER26-3552-000 (Aug. 18, 2026) (ZGIA Proposal). \n4 Capitalized terms not defined in these comments have the same meaning as in the Tariff or the ZGIA Proposal, as \napplicable."},{"page":2,"startToken":240,"endToken":586,"text":"2 \nI. \nINTRODUCTION \nThe MISO region faces unprecedented growth in energy demand, driven largely by data \ncenters, next-generation manufacturing, and electrification.5 The Commission recognized these \nchallenges in its Show Cause Order in Docket No. EL26-70-000, which raised concerns about, \namong other things, the absence of generator interconnection service and study processes \ntailored to generation serving co-located or electrically proximate large load.6 The ZGIA \nProposal is the first in a series of filings MISO intends to make to address those concerns.7 If \napproved, it would address generation serving co-located load at the same substation—the co-\nlocation subset of the Show Cause Order’s concerns—by establishing an expedited \ninterconnection pathway while preserving MISO’s interconnection queue and planning \nprocesses.8 As MISO has indicated, other issues, including transmission service for co-located \nand proximate loads and the integration of electrically proximate generation, would be addressed \nin subsequent filings.9 SEIA supports the ZGIA Proposal as a just and reasonable first step \ntoward addressing these co-location and large load interconnection challenges. \n \n \n5 See MISO, 2026 Reliability Imperative Report, at 2 (Feb. 2026), available at: \nhttps://cdn.misoenergy.org/2026%20Reliability%20Imperative%20Report744320.pdf. \n6 Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal \nPower Act, 195 FERC ¶ 61,212. PP 94, 97, 113 (2026) (Show Cause Order). \n7 See ZGIA Proposal, Transmittal Letter at 5–6 (explaining that “[t]he present filing represents the first of this \nseries” of filings MISO intends to submit to address the concerns raised in the Show Cause Order). \n8 See id. at 1–2 (explaining that MISO “submits proposed revisions to its [Tariff] to establish a Zero Injection \nGenerator Interconnection Agreement (‘ZGIA’), associated study process and operational requirements, and market \nand resource adequacy rules to accommodate [ZG Resources]”). \n9 See id. at 7, 10–11 (explaining that MISO “chose not to incorporate a ‘proximate’ load solution in this initial \nfiling” and that MISO “will continue to develop the LARS process through the LLWG” and “expects to submit the \nLARS filing by November 16, 2026, or earlier”)."},{"page":3,"startToken":586,"endToken":994,"text":"3 \nII. \nCOMMENTS \nA. \nThe ZGIA Proposal Appropriately Limits Zero Injection Generation \nInterconnection Service to Co-Located Configurations, Addressing \nDeliverability Concerns. \n \nUnder MISO’s existing interconnection framework, a resource that injects power onto the \nTransmission System must demonstrate deliverability through the Definitive Planning Phase \n(DPP). Deliverability is a prerequisite to receiving full capacity accreditation and marketable \nZonal Resource Credits.10 However, under the ZGIA proposal, a project developed under a \nZGIA would not grant deliverability rights. The ZGIA Proposal limits Zero Injection Generation \nInterconnection Service (ZG Interconnection Service) to co-located configurations in which ZG \nResources and the Zero Injection Generation Associated Load (ZG Associated Load) would be \nlocated at the same substation and voltage level, with no injection beyond the interconnecting \nsubstation. Because the ZG Resource would not inject onto the broader Transmission System, \nthe co-location design would avoid the need for a deliverability analysis.11 Under the ZGIA \nProposal, ZG Interconnection Service would not grant injection rights or deliverability, and \nMISO would require that no Network Upgrades be needed beyond the interconnecting substation \n(except limited System Protection Facilities).12 A ZG Resource that would trigger broader \nNetwork Upgrades would not qualify and would instead need to proceed through the DPP.13 The \n \n10 See MISO Tariff, Module E-1, Section 69A (establishing accreditation and capacity credit framework for \nPlanning Resources); see also Show Cause Order at PP 94, 113 (discussing the need for generator interconnection \nservice tailored to generation serving co-located load and recognizing that limited or no injection may reduce the \nneed for Network Upgrades).   \n11 See ZGIA Proposal, Transmittal Letter at 26 (explaining that “[i]t is not necessary to include this limited product \nin DPP studies because its lack of injection prevents it from having impacts on the broader Transmission System”). \n12 See ZGIA Proposal, Proposed Tariff, Attachment X, Section 3.2.5.1 (establishing ZG Interconnection Service \nrequirements including same-substation and same-voltage-level limitations); see also id., Transmittal Letter at 25–\n27 (explaining that limiting injection onto the broader Transmission System is the foundational feature of ZG \nInterconnection Service and that the requirement that no Network Upgrades be needed beyond the interconnecting \nsubstation acts as a key guardrail). \n13 See ZGIA Proposal, Transmittal Letter at 26 (explaining that if Network Upgrades were needed beyond the \ninterconnecting substation, “that would both call into question the lack of injection and raise cost-shifting risk for \nother Interconnection Customers”); see also id. at 31 (“Interconnection Requests with such impacts are better"},{"page":4,"startToken":994,"endToken":1407,"text":"4 \nco-location requirement, coupled with the strict load-following obligation, would confine the \nZGIA to arrangements with minimal Transmission System impact—generation would be \nphysically co-located with the load it would serve and would reduce output in real time if that \nload decreased,14 ensuring that the ZG Resource does not inject onto the Transmission System.15 \nThese guardrails prevent ZG Resources from bypassing the deliverability requirements that \napply to all other interconnecting generation, avoiding potential cost-shifting to other \nInterconnection Customers and preserving the integrity of the DPP queue.16 \nThe ZGIA Proposal’s resource adequacy provisions would further address related \nconcerns by limiting ZG Resource accreditation to the lesser of each resource’s applicable \naccreditation or the ZG Associated Load’s requirement and by requiring associated Zonal \nResource Credits (ZRCs) to be used with the ZG Associated Load in the applicable Load Serving \nEntity’s Fixed Resource Adequacy Plan or Reliability Based Demand Curve Opt-Out.17 For \nSEIA, these limitations are important because they would maintain a level playing field by \nensuring ZG Resources receive capacity credit only for the load they actually serve, rather than \ncompeting with fully deliverable Planning Resources for transferable capacity value. \n \nprocessed through the DPP where they can study in a cluster with other Interconnection Requests with potential \nimpacts on the broader Transmission System”). \n14 See ZGIA Proposal, Transmittal Letter at 26 (explaining that “if there is a decrease in the ZG Associated Load’s \ndemand, it is important to correspondingly reduce the output of the ZG Resource to prevent power from flowing out \nonto the Transmission System”). \n15 See id. at 12–15, 18–20, 25–29 (describing the same-substation and same-voltage limitations, injection \nrestrictions, resource adequacy guardrails, and DPP treatment, and explaining that the “limited distance over which \nenergy would need to be—and is permitted to—flow allows for a more targeted study”). \n16 See SEIA’s Comments in Response to MISO’s Updated ZGIA Proposal (Mar. 23, 2026), available at: \nhttps://www.misoenergy.org/engage/stakeholder-feedback/2026/pac-zgia-proposal-framework-pac-2024-4-\n20260225/. \n17 See SEIA’s Comments in Response to MISO’s Updated ZGIA Proposal (Mar. 23, 2026) (urging MISO to “create \nguardrails by making clear that any ZRCs associated with a ZGIA resource are non-transferable”), available at: \nhttps://www.misoenergy.org/engage/stakeholder-feedback/2026/pac-zgia-proposal-framework-pac-2024-4-\n20260225/; see also Clean Grid Alliance Comments Submitted by David Sapper (May 5, 2026) (raising concerns \nregarding accreditation impacts of adding ZGIA resources to direct loss of load modeling), available at: \nhttps://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-zgia-proposal-framework-pac-2024-4b-\n20260420/."},{"page":5,"startToken":1407,"endToken":1792,"text":"5 \n \nB. \nThe ZGIA Proposal Supports Speed to Reliable Power While Preserving \nSystem Integrity. \n \nUnder the ZGIA Proposal, ZG Interconnection Service would be available only where the \nGenerating Facility and the ZG Associated Load are at the same substation and voltage level.18 \nMISO considered and rejected broader scopes, including electrically proximate configurations, \nbased on stakeholder concerns about injection control, unconstrained power flows, and potential \nstate retail service conflicts.19 By drawing the boundary at the substation level, MISO would \nlimit ZG Interconnection Service to configurations where injection controls can be effectively \nverified,20 and the expedited 90-day study process would be well-suited to these limited \nconfigurations.21 \nA critical feature of this process is that MISO has designed the ZGIA study track to \noperate independently of the DPP.22 As MISO indicates, ZGIA studies would use a separate \nmodel base that does not include pending DPP interconnection requests,23 and ZGIA approvals \nwould not be added to ongoing DPP studies. MISO would reconcile both sets of results in the \nnext MISO Transmission Expansion Plan (MTEP) base case.24 This structural separation \n \n18 ZGIA Proposal, Proposed Tariff, Attachment X, Section 3.2.5.1. \n19 ZGIA Proposal, Transmittal Letter at 7. \n20 See id. at 28 (explaining that “an examination of the electrical connection between the Generating Facility, ZG \nAssociated Load, and the Transmission system, and the proposed control equipment becomes a critical aspect of the \nstudy”). \n21 See id. at 14 (“[A] separate, expedited study process and corresponding form of Interconnection Service is both \nfeasible and responsive to the Commission’s directive to address the needs of certain loads, including large loads \nassociated with data centers.”). \n22 See id. at 15 (“[T]his insulates existing DPP projects from negative impacts or cost shifts due to the existence of \nthe ZGIA process.”). \n23 See id. (explaining that “[b]efore every ZGIA cycle, all Interconnection Requests with a GIA approved since the \nlast base case was created will be added to the base case for the ZGIA cycle but will not be added in any ongoing \nDPP studies” and that ZGIA studies will not use available transmission capacity in DPP studies or adversely affect \nDPP projects). \n24 See id. (explaining that ZGIA studies will not use available transmission capacity in DPP studies or adversely \naffect DPP projects)."},{"page":6,"startToken":1792,"endToken":1923,"text":"6 \nsupports ZG Resources proceeding on a 90-day study timeline without consuming transmission \ncapacity reserved for DPP projects or increasing costs for projects already in the queue.25 \n \nIII. \nCONCLUSION \nMISO’s ZGIA proposal represents a just and reasonable step toward addressing the \nresource adequacy issues posed by the rapid addition of large loads. SEIA respectfully urges the \nCommission to accept MISO’s ZGIA Proposal.  \nRespectfully submitted, \n \n \n \n/s/ Melissa Alfano \n \nMelissa Alfano  \nSenior Director of Energy Markets and Counsel  \nSolar Energy Industries Association  \n1425 K St NW Ste. 1000  \nWashington, DC 20005  \n(202) 566-2873  \nmalfano@seia.org   \n \n \nDated: September 8, 2026 \n \n \n25 See id. (“[T]he standing MISO DPP three phase and ERAS processes will not be impacted by ZGIA, as ZGIA will \nnot be utilizing any available transmission capacity in those studies.”)."},{"page":7,"startToken":1923,"endToken":1969,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC, this 8th day of September, 2026. \n \n \n \n/s/ Melissa Alfano \n \nMelissa Alfano"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":241},{"p":2,"at":3,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":3,"startToken":241,"endToken":587},{"p":3,"at":3,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":18,"startToken":587,"endToken":589},{"p":3,"at":18,"title":"A. The ZGIA Proposal Appropriately Limits Zero Injection Generation","method":"printed heading","endPage":5,"endAt":5,"startToken":589,"endToken":1408},{"p":5,"at":5,"title":"B. The ZGIA Proposal Supports Speed to Reliable Power While Preserving","method":"printed heading","endPage":6,"endAt":190,"startToken":1408,"endToken":1820},{"p":6,"at":190,"title":"III. CONCLUSION","method":"printed heading","endPage":7,"endAt":0,"startToken":1820,"endToken":1923},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":300,"startToken":1923,"endToken":1969}]}