{"document":{"slug":"rec-20260908-5266","title":"Comments of Google LLC on Midcontinent Independent System Operator Inc.’s Zero Injection Generator Interconnection Agreement proposal","issued":"2026-09-08","accession":"20260908-5266","docket":"ER26-3552-000","group":"MISO zero-injection generator interconnection agreement","filer":"Google LLC","kind":"comments","file":"sources/filings/text/20260908-5266_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5266","tier":"record","sha256":"ac9329da980b2107ca55834c7362ef3202de13f8b9493605b1a1612ad9ed63e7","pages":7,"tokens":1815,"emptyPages":[],"textThemes":["study","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":236,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nMidcontinent Independent System Operator, \nInc. \n \n) \n) \n) \n) \n) \n \nDocket No. ER26-3552-000 \n \nCOMMENTS OF GOOGLE LLC \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Google LLC (“Google”) submits these comments on \nthe Midcontinent Independent System Operator Inc.’s (“MISO”) Zero Injection Generator \nInterconnection Agreement (“ZGIA”) proposal.  The ZGIA proposal is a step forward.  Google \napplauds MISO for working constructively with stakeholders to develop the proposal, which will \nhelp facilitate the timely and efficient interconnection of badly needed new generation capacity.   \nGoogle has consistently supported efforts to accelerate the pace at which new generation \nfacilities are interconnected to the transmission system.  Those efforts are particularly important \nnow given the rapid load growth experienced throughout much of the country, including in MISO.  \nThe best way to ensure the reliability and affordability of our electricity system under those \nconditions is to enable the development of more generation capacity.   \nThat goal—the development of new capacity—is as much an infrastructure problem as it \nis anything else.2  Aging, over-burdened transmission facilities are the primary barrier to supply \nto keeping pace with demand.   Accordingly, building out the nation’s power grid with new \n \n1 18 C.F.R. § 385.211 (2026). \n2 Interconnection of Large Loads to the Transmission System, Comments of Google LLC, Docket No. RM26-4-\n000, at 2-3 (filed Nov. 21, 2025)."},{"page":2,"startToken":236,"endToken":608,"text":"-2- \ntransmission facilities and advanced transmission technologies is one of the most critical steps we \ncan take to ensure the reliability and affordability of the nation’s electricity system.   \n Google also recognizes that building new energy infrastructure, especially electric \ntransmission, takes an exceedingly long time.  And while Google supports efforts to accelerate \nthose processes, time is not a luxury that the electricity sector has.  For that reason, Google has \nalso strongly supported “reforms that will expedite the interconnection of facilities that maximize \nthe use of existing infrastructure and minimize strain on the grid.”3  Locating electric generating \nfacilities close to the loads they will serve is one of the most efficient means of doing so.   As a \nmatter of engineering, economics, and basic physics, generation sited near the load it serves puts \nless strain on the grid and requires less investment in new or upgraded transmission infrastructure.  \nSolutions that capitalize on that fact by facilitating efforts to site generation near paired load \ntherefore minimize the network upgrades needed to interconnect new resources and, in turn, \naccelerate the pace at which new generation comes online.     \n   \nThe ZGIA proposal is a step in that direction.  It recognizes the importance of accounting \nfor how a generator will operate in practice when studying generator interconnection requests, \nincluding the reality that generators serving electrically proximate loads can “minimize the impact \non the transmission system.”4  Specifically, the ZGIA would create a “study process tailored to the \noperational characteristics of generation serving co-located load, including a study process that \n \n3 Id. at 5-6.  \n4 Midcontinent Indep. Sys. Operator, Inc., Zero Injection Generator Interconnection Agreement, Docket No. \nER26-3552-000, at 13-14 (filed Aug. 18, 2026) (“Transmittal”); see also Midcontinent Indep. Sys. Operator, Inc., 195 \nFERC ¶ 61,212, at P 113 (2026) (“Large Load Show Cause Order”) (“Where a generating facility’s output is matched \nto the demand of the electrically proximate large load or large co-located load or if the generating facility’s output is \nlimited to ensure no new injection, the impacts to the transmission system of interconnecting the generating facility to \nserve that electrically proximate large load or large co-located load may be limited, thereby potentially reducing the \nneed for Network Upgrades, which can accelerate the generator interconnection process.” (footnote omitted))."},{"page":3,"startToken":608,"endToken":913,"text":"-3- \nrecognizes the potentially reduced Transmission System impacts where generation is limited to \nserving its associated load.”5  That is a major advancement beyond how transmission providers \ntypically study requests to interconnect to the grid—i.e., based on the assumption the generator \nmust be able to deliver its full output to the grid at all times—and crucial to adding as much \ncapacity to the existing transmission system as quickly as possible.  On the latter point, MISO \nsuggests “the ZGIA process can take place quickly, with the ZG Impact Assessment completed \nwithin 90 Calendar Days,”6 much faster than the multi-year timelines that can apply to generator \ninterconnection applications.   \n \nThe ZGIA is, however, only a step in the right direction.  That is because the ZG \nInterconnection Service can be used only to serve designated load that is either at the same Point \nof Interconnection as the paired generator or has a Point of Withdrawal on the same voltage side \nof the same substation as the paired generator.7  That limitation is considerably more restrictive in \npractice than the reforms that the Commission proposed to require MISO to adopt in the Large \nLoad Show Cause Order.8  In that proceeding, the Commission described electrically proximate \nload and generation as those that are no more than two substations apart.9  Similarly, SPP’s High \nImpact Large Load Generation Assessment (“HILLGA”) process, which offers an expedited 90-\nday interconnection study and a limited, provisional form of transmission service, is also available \nto generators that are located within two substations of the large load they will serve.10   \n \n5 Transmittal at 8. \n6 Id. \n7 Id. at 12. \n8 Large Load Show Cause Order, 195 FERC ¶ 61,212, at PP 113-119. \n9 Id. P 112. \n10 Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 25, 28 (2026)."},{"page":4,"startToken":913,"endToken":1222,"text":"-4- \nAs MISO develops its response to the directives in the Large Load Show Cause Order, \nGoogle urges it to expand the principles established in the ZGIA to apply to circumstances at least \nas broad as the within-two-substations configuration contemplated in the Large Load Show Cause \nOrder and permitted under HILLGA.  By including more potential load and generation \nconfigurations, MISO can unlock more new generation on an expedited basis.  That is particularly \nso because the distinction between being at the same point of interconnection and within two \nsubstations is a meaningful difference in practice.  For example, a major energy park that includes \nsignificant networked load and generation is exactly the type of facility for which a ZGIA \nframework would make sense.  But if, as is common in these configurations, that energy park has \nmultiple substations with the generation and associated load interconnecting through different \nsubstations, the ZGIA avenue may be unavailable, leading to costly delays and unnecessary \nexpense in bringing the new generation online.   \n \nAt the same time, although Google urges MISO to make the most out of approaches like \nZGIA, MISO cannot lose sight of the importance of accelerating its principal interconnection \nprocess:  the Definitive Planning Process (“DPP”).  As noted, it can take several years to move an \ninterconnection request through the DPP process.11  That timeline creates an understandable urge \nto pursue short-term solutions to accelerate the interconnection of a limited subset of generator—\nmost notably, the Expedited Resource Addition Study (“ERAS”).  Nevertheless, Google believes \nthat fixing the sluggish timelines in the DPP is a more durable and lasting solution to MISO \ninterconnection challenges than an endless series of shortcuts, even if some of those shortcuts are \nmerited for the foreseeable future.   \n \n11 MISO, Interconnection Process Working Group, DPP Study Schedule Updates (July 21, 2026), \nhttps://cdn.misoenergy.org/20260721%20IPWG%20Item%2003b%20DPP%20Study%20Schedule769072.pdf ."},{"page":5,"startToken":1222,"endToken":1509,"text":"-5- \n \nMISO appears to agree.  In its ERAS filing, MISO stated that it “remains committed to \nreducing its general interconnection review period to one year,” with a goal of doing so by 2028.12  \nThis proceeding provides one window into how it might achieve that goal.  Drawing on the idea \nunderpinning the ZGIA, MISO should amend the DPP study process to ensure that it is studying \ngenerators as they actually intend to operate and based on the effects they can realistically be \nexpected to have on the system, which will avoid saddling generators with unnecessary network \nupgrades that are required only to manage extreme circumstances.  At the end of the day, MISO \nneeds a single, well-functioning generator interconnection process that can facilitate the timely \nentry of new resources onto the system.  Otherwise, the region’s supply of generation will \nperpetually lag behind future increases in demand.   \nIn addition, Google strongly supports continued efforts to integrate transmission planning \nand generator interconnection.   MISO’s MTEP has been one of the country’s leading examples of \nforward-looking transmission planning, particularly its Long-Range Transmission Plan.  Holistic \ntransmission planning, that considers generator interconnection needs, among other drivers, helps \navoid the piece-meal, inefficient development of the transmission system while simultaneously \nreducing the risk that interconnection customers will be forced to shoulder enormous network \nupgrade costs that can stymie the development of new generation facilities and create considerable \nuncertainty for other generators through restudies.  “No power plant can obtain financing when the \ntransmission costs are either unknown or subject to significant revision based on ‘that next \n \n12 Midcontinent Indep. Sys. Operator, Inc., Revisions to the Open Access Transmission, Energy and Operating \nReserve Tariff  Expedited Resource Addition Study Filing, Docket No. ER25-2454-000, at 7 (filed June 6, 2025)."},{"page":6,"startToken":1509,"endToken":1756,"text":"-6- \nstudy.’”13  The end result of which is a further delay in developing badly needed generation \ncapacity. \nThis type of proactive transmission planning is also important for policy priorities like the \nRatepayer Protection Pledge, to which Google is a signatory,14 as well as broader efforts to \nincentivize customers to bring their own new capacity.  Those policies and efforts, which are \nconsistent with Google’s longstanding energy procurement philosophy and essential to ensuring \nreliable service and affordable rates for residential customers and other existing commercial \ncustomers, simply will not succeed if new generation cannot get through the interconnection \nqueue.  By expediting the interconnection of electrically proximate load and generation, ZGIA is \na step forward in that regard.  But it is just a step.  Many more are needed to win the race.   \n \n \nRespectfully submitted, \n \n \n \n/s/ Brian George \nBrian George \nSr. Lead, US Energy Markets \nStephen Lindeman \nLead, Energy Market Development \nGoogle LLC \n655 New York Ave., NW \nWashington, DC 20001 \n(202) 999-0990 \nbriangeorge@google.com \nlindemans@google.com  \n \n \nMatt Christiansen \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nmchristiansen@wsgr.com  \nbshpall@wsgr.com \n \nCounsel for Google LLC \nDated:  Sep 8, 2026 \n \n13 Sw. Power Pool, Inc., 194 FERC ¶ 61,192 (2026) (Rosner, Comm’r, concurring at P 4). \n14 Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google’s Approach for \nResponsible Energy Growth, Google: The Keyword (Mar. 4, 2026), https://blog.google/innovation-and-\nai/infrastructure-and-cloud/global-network/affordability-pledge-responsible-energy-growth/."},{"page":7,"startToken":1756,"endToken":1815,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated:  September 8, 2026 \nWashington, D.C. \n \n \n/s/ Bryan Shpall \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":7,"endAt":0,"startToken":0,"endToken":1756},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":389,"startToken":1756,"endToken":1815}]}