{"document":{"slug":"rec-20260908-5320","title":"Protest of Microsoft Corporation re American Transmission Company LLC's 08/17/2026 tariff filing","issued":"2026-09-08","accession":"20260908-5320","docket":"ER26-3531-000","group":"ATC large-load planning revisions (Attachment FF-ATCLLC)","filer":"Microsoft Corporation","kind":"protest","file":"sources/filings/text/20260908-5320_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5320","tier":"record","sha256":"3fc2c3cd0ae41f8e4dee85822733f9c755e6608b691ac4e9c6a583bcd5354d7f","pages":14,"tokens":3979,"emptyPages":[],"textThemes":["retail","study"]},"pages":[{"page":1,"startToken":0,"endToken":264,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nAmerican Transmission Company LLC; \nMidcontinent Independent System \nOperator, Inc. \n) \n) \n) \nDocket No. ER26-3531-000 \n \n \n \nPROTEST OF MICROSOFT CORPORATION \n \n \nPursuant to the Federal Energy Regulatory Commission’s (“Commission’s”) \nCombined Notice of Filings #1,1 Microsoft Corporation (“Microsoft”) respectfully submits \nfor the Commission’s consideration these comments on the August 17, 2026 filing of \nMidcontinent Independent System Operator, Inc. (“MISO”), on behalf of American \nTransmission Company LLC (“ATC”).2 ATC is one of two MISO utilities that retains local \ntransmission planning responsibilities, with those planning procedures set out in Attachment \nFF-ATCLLC of MISO’s Open Access Transmission, Energy and Operating Reserve Markets \nTariff (“Tariff”).3 ATC intends the proposed reforms in this docket to comply with the local \ntransmission planning obligations directed by the Commission in the MISO Show Cause \nOrder4 and to complement MISO’s to-be-filed tariff reforms in compliance with that order.5  \nMicrosoft supports transparent, durable, and nondiscriminatory local transmission \nplanning processes necessary for interconnection and reliable service to transmission \n \n1 Combined Notice of Filings #1, Docket No. ER26-3531-000 (Aug. 17, 2026). \n2 Am. Trans. Co. LLC, Proposed Revisions to Attachment FF-ATCLLC of the MISO Tariff in \nResponse to Show Cause Order, Docket No. ER26-3531-000 (Aug. 17, 2026) (“ATC Filing”). \n3 MISO performs local planning services for all but two of its transmission-owning members.  \n4 Midcontinent Indep. Sys. Op., Inc., Order Instituting Proceeding under Section 206 of the \nFederal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”). \n5 August 17 Filing at 1 (“ATC is proposing certain revisions . . . to fulfill obligations outlined \nin the Show Cause Order”)."},{"page":2,"startToken":264,"endToken":595,"text":"2 \n \ncustomers on behalf of their large retail loads. As Microsoft explained in a related ATC \nproceeding,6 as a signatory to the White House Ratepayer Protection Pledge, Microsoft is \nfully committed to “pay for all new power delivery infrastructure upgrades required to \nservice [] data centers, including adequate network upgrade costs to ensure that these \nexpenses are not passed on to the ordinary household.”7 In this case, however, Microsoft is \nconcerned that ATC’s proposed local planning reforms do not align with the longstanding \nplanning principles of Order No. 890 and fall short of reforms contemplated by the \nCommission in the Show Cause Order for three primary reasons: \n1. ATC’s proposed local planning reforms do not give stakeholders like Microsoft a \nmeaningful role, or even opportunity, to provide input into the planning process, even \nthough this process will determine the facilities, schedule, and cost for which the \napplicable large retail customer is ultimately liable.   \n \n2. The proposed local planning reforms expand ATC’s unilateral exercise of discretion \nwithout guardrails and may produce inconsistent and unduly preferential or \ndiscriminatory outcomes that have consequences under the Federal Power Act.   \n \n3. The proposed local planning reforms require ATC to enter into two different contracts \nwith its customers, but ATC has not filed these contracts as pro forma—nor has it \nexplained why not.8  \n \nIf ATC’s objective is to provide the same treatment to all transmission customers with large \nloads, ATC has not explained why it omitted pro forma contracts and will be instead \nnegotiating those agreements separately for each of its transmission customer’s new large \n \n6 Am. Trans. Co. LLC; Midcontinent Indep. Sys. Op., Inc., Protest and Motion for Hearing \nand Settlement Judge Procedures of Microsoft Corp. at 2, Docket No. ER26-3265-000 (filed Aug. 21, \n2026). \n7 Ratepayer Protection Pledge at P 2, available at \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ \n8 The contracts are not part of the record in this docket. ATC has not provided them, even for \ninformational purposes."},{"page":3,"startToken":595,"endToken":891,"text":"3 \n \nloads. Moreover, ATC has not shown its reforms to comply fully with the longstanding \nplanning principles of Order No. 890.9   \nAccess to reliable electric service is essential to expand the capacity of cloud \ncomputing and artificial intelligence data center sectors, and observance of longstanding, \nproven utility regulatory principles like open access support the competitive, responsible \ngrowth that is necessary for U.S. leadership in the computing industry. If the Commission \ndoes not reject the ATC Filing, Microsoft requests that the Commission initiate \nunconsolidated hearing and settlement judge procedures in this proceeding and in the Docket \nNo. ER26-3265-000 proceeding so that Microsoft and other interested stakeholders may \nwork with ATC to resolve deficiencies in its local transmission planning processes.       \nI. \nPROTEST \nA. \nATC’s local planning reforms to address large load interconnection and \nservice exclude participation by large retail customers like Microsoft.   \nAs noted above, ATC is one of two transmission-owning members of MISO that \nretain authority over local transmission planning instead of delegating that responsibility to \nthe grid operator. Accordingly, ATC performs local transmission planning pursuant to \nAttachment FF-ATCLLC of the MISO Tariff.10 As described in Attachment FF-ATCLLC, \nATC administers the process for distribution-transmission interconnection planning, which \ninvolves planning for interconnection and service to distribution utilities, among other local \n \n9 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, \n118 FERC ¶ 61,119 (Feb. 16, 2007) (“Order No. 890”); see also Midcontinent Indep. Sys. Op., Inc. \nand Am. Trans. Co. LLC., Revisions to Attachment FF-ATCLLC of the Midwest ISO Open Access \nTransmission and Energy Markets Tariff, Docket No. OA08-42-000 (filed Dec. 7, 2007).  \n10 ATC is not permitted by state law to delegate its local transmission planning authority to \nMISO or any other entity. See ATC Filing at 2, nn.7, 9."},{"page":4,"startToken":891,"endToken":1198,"text":"4 \n \nplanning responsibilities. The proposed large load-related changes include adding to \nAttachment FF-ATCLLC newly defined terms like ATCLLC Large Load, Large Load \nInterconnection Criteria Confirmation Form, Load Interconnection Request Form, and \nATCLLC Local Planning Criteria.11 The changes specifically address interconnection and \nservice to distribution utilities for loads that are equal to or exceed 100 MW, and by \nextension are intended to capture the new loads of large retail customers like Microsoft.   \nMicrosoft has been working collaboratively with ATC and Wisconsin Electric Power \nCompany, dba We Energies (“WEPCo”) to interconnect and serve Microsoft’s large data \ncenter campus in Racine County, Wisconsin. Microsoft appreciates ATC’s efforts to support \nthe reliable integration of large retail loads into the transmission system and recognizes that a \nlarge retail load like a data center may have a significant grid impact.  \nAs a retail customer, Microsoft also recognizes the degree of separation that exists \nbetween it and ATC; however, Microsoft respectfully submits that large retail customers are \nimportant stakeholders in ATC’s local transmission planning work. As the Commission \nrecognized in the Show Cause Order, stakeholder engagement is part of the tariff revision \nprocess.12  The most significant consequence of ATC developing these reforms without \nbroad stakeholder consultation is that the proposed local planning procedures appear to \nexclude the opportunity for participation by interested large retail customers like Microsoft. \nMicrosoft respectfully submits that local transmission planning processes should give large \nretail customers the option to participate—for instance, to test and validate local transmission \n \n11 The Large Load Interconnection Criteria Confirmation Form, Load Interconnection \nRequest Form, and ATCLLC Local Planning Criteria are not part of Attachment FF-ATCLLC. \nSection I.C addresses Microsoft’s concerns that certain agreements referenced in the local planning \nprocedures are not tariffed pro forma agreements. \n12 See, e.g., Show Cause Order at PP 37, 41, 53, 62, 71, 73-76, 84"},{"page":5,"startToken":1198,"endToken":1536,"text":"5 \n \nneeds, to explore solutions to challenges, to support the utility’s consideration of grid-\nenhancing technologies, or to coordinate on load ramp and in-service timelines. Retail \ncustomers’ participation in federally regulated electric matters is not a new concept at all, as \nthe Commission has previously found that end-use retail customers may participate in the \nformula rate protocol process.13 \nATC’s proposed reforms to its local planning process, however, do not contemplate \nthat approach. For example, ATC provides for an “annual process to re-evaluate the \nATCLLC Local Planning Criteria and requirements established by ATCLLC’s Business \nPractices to ensure the ATCLLC Local Planning Criteria and requirements established by \nATCLLC’s Business Practices appropriately meet all requirements described herein.”14 \nChanges coming out of that process would now become effective “immediately following” \nthe posting of the revisions (instead of 30 days after posting as the currently effective Order \nNo. 890-approved procedures provide).15 The tariff reforms do not contemplate the \nparticipation of large retail loads in the annual review process. In Microsoft’s view, ATC \nshould provide interested stakeholders with notice of the annual review process (such as by \n \n13 See, e.g., See Am. Elec. Power Serv. Corp., 153 FERC ¶ 61,167 at P 12 (2015) (“As \nexplained below, the Commission concludes that: (1) retail ratepayers may file complaints and protest \ntransmission rates and wholesale power sales rates before the Commission; and (2) allowing retail \ncustomers to challenge transmission and wholesale power sales rates does not violate principles of \nfederalism.”). See also id. at P 19 (“As the Commission found in PATH, indirect customers (e.g., \nretail customers) have a right to intervene and protest rates when some portion of those rates will be \nflowed through to their retail bill. Ms. Peine has, in fact, intervened in this matter and protested the \nSWEPCO/AEP Annual Update filings and, therefore, we see no reason to treat her participation any \ndifferently than the retail customers in PATH who similarly protested the formula rate updates, but \ndid not intervene.”). \n14 Attachment FF-ATCLLCA, § V.F. \n15Id."},{"page":6,"startToken":1536,"endToken":1824,"text":"6 \n \nposting on OASIS) and the tariff should provide a meaningful opportunity for large retail \ncustomers and other stakeholders to engage with ATC and stress-test proposed changes.  \nWith regard to ATC’s process for requesting transmission-distribution \ninterconnection to serve the large load of a distribution utility, such as WEPCo’s service to \nMicrosoft’s Racine County data center campus, the tariff procedures should permit the large \nretail customer to participate in Distribution Interconnection Planning Meetings and to access \ntransmission data and planning models. ATC holds distribution interconnection planning \nmeetings only with “individual owners of Distribution Facilities”; it does not include the \nretail customers even though the purpose of these meetings is to \nprovide an opportunity for [ATC] to obtain such other information, or to \nvalidate previously received information, and to discuss with such \nDistribution Facility owners whether the studies or assessments then being \nperformed or which are to be performed, are appropriate to meet their \nrespective needs, and to determine whether the study models or assessment \ntools are appropriate for the particular Distribution Interconnection or \nDistribution Facilities owner’s requirements.16 \nA large retail customer could contribute meaningfully to these planning discussions. At the \nbare minimum, the large retail customer should be provided with the “results of [ATC’s] \nstudy or assessment” and ATC should have the opportunity to receive the large retail \ncustomer’s comments on the study.17  \nIf ATC’s local planning procedures were reformed to provide a large retail customer \nwith the opportunity to participate, it would be reasonable to provide a large retail load \naccess to the same dispute resolution process available to ATC and its distribution utility. \nATC’s local planning procedures direct that any dispute in connection with a distribution \n \n16 Id. § VI.A.7. \n17Id. § VI.A.8."},{"page":7,"startToken":1824,"endToken":2173,"text":"7 \n \ninterconnection request “shall be handled” in accordance with the process specified in a \nDistribution-Transmission Interconnection Agreement between ATC and the distribution \nutility.18 Although a large retail customer is ultimately responsible for the costs of facilities \ndeveloped during the local planning process,19 even with the large load reforms proposed by \nATC in this docket there is not yet an opportunity for that customer to resolve concerns \nquickly and efficiently through a tariffed alternative dispute resolution process such as the \nprocess directed under Order No. 890’s dispute resolution planning principle.20 Instead, the \nonly option available to a large retail customer is to file a section 206 complaint with the \nCommission. To the extent the Commission intended its Show Cause Order reforms to \nprovide large retail customers with the opportunity for direct engagement, the local planning \nreforms proposed in this docket do not achieve that objective. \nB. \nATC’s local planning reforms provide ATC with substantial discretion \nand creates risk of undue discrimination and preferential treatment to \nsimilarly situated transmission customers.  \nOrder No. 890 required transmission providers to adopt transmission planning \nprocesses that are coordinated, open, transparent, and comparable because planning decisions \ncan materially affect access to transmission service, project timing, facility requirements, and \n \n18 Id. § VII.C (disputes arising in connection with distribution interconnection requests). \n19 E.g., Am. Trans. Co. LLC, Comments of the Public Service Commission of Wisconsin at 5, \nDocket No. ER26-3265-000 (Aug. 14, 2026). \n20 Nothing in Order No. 890 suggests that the alternative dispute resolution process may \nforeclose participation of a large retail customer. To the contrary, FERC “encourage[d] transmission \nproviders, customers, and other stakeholders” to utilize Commission resources in developing a \ntariffed dispute resolution processes. Order No. 890 at P 503; see id. at PP 496-503. See also Order \nNo. 890-A, 121 FERC ¶ 61,297 at PP 217-21 (Dec. 28, 2007); see id. at P 220 (“Any stakeholder that \nhas concerns regarding the dispute resolution mechanism proposed by a transmission provider, or any \nother aspect of the compliance filing, may bring them to the Commission’s attention on review of the \nproposal.”)."},{"page":8,"startToken":2173,"endToken":2487,"text":"8 \n \ncost.21 The Commission further recognized in that rulemaking that transmission customers \nand other stakeholders must have a meaningful opportunity to participate in the planning \nprocess and that planning standards must be sufficiently transparent to permit customers to \nunderstand and evaluate planning outcomes.  \nSince its Order No. 890 compliance docket more than two decades ago, ATC’s local \nplanning procedures have remained largely unchanged.22 Here, however, ATC wants to \nloosen practices with new grants of discretion, undefined readiness requirements, extra-tariff \ncriteria and business practices, discretionary access to its planning models, and to determine \nwhat studies, facilities, and upgrades are “necessary” or “appropriate.”23 Nowhere in \nAttachment FF-ATCLLC are readiness requirements actually specified, even though a \ndistribution customer’s ability to “meet” or “complete” “all applicable readiness \nrequirements” is required to proceed through the local planning process.24 These deficiencies \nweaken the coordinated, open and transparent transmission planning framework developed \nunder Order No. 890 and increase the likelihood of unduly preferential and discriminatory \ntreatment of transmission customers and, as follows, their large retail customers. For \ninstance:     \n• Any interested party may request, in writing, copies of the models developed using \nthe assessment tools employed by ATCLLC in performing any planning function or \nassociated analysis or assessment, and ATCLLC may, in its discretion provide copies \n \n21 See, e.g., Order No. 890 at PP 451-54, 460, 471-79; see also id. at P 488 (“The \ntransmission planning required by this Final Rule is intended to provide transmission customers and \nother stakeholders a meaningful opportunity to engage in planning along with their transmission \nproviders.”). \n22 See generally Docket No. OA08-42-000 et al. \n23 E.g., Attachment FF-ATCLLC, §§ III, V.E─V.G., VI.A.2, VI.A.6─VI.A.7, \nVI.A.10─VI.A.12, VI.B.3─VI.B.4, VI.B.7, VI.C.2, VI.C.4─VI.V.5. \n24Id. § VI.A.4."},{"page":9,"startToken":2487,"endToken":2806,"text":"9 \n \nof such models under appropriate confidentiality agreements, subject to the rules and \nregulations of the FERC.”25 \n• “Distribution –Transmission Interconnection Requests are studied or assessed by \nATCLLC primarily upon a first come, first served basis upon completion of any \napplicable readiness requirements.”26 “Each request is studied in the order in which \nsuch request meets applicable readiness requirements, unless in ATCLLC’s judgment \nand determination, require that a later received request should be studied prior to \nearlier received requests.”27 \n• “The terms and conditions of the Distribution – Transmission Interconnection \nAgreement published on ATCLLC’s website may be changed, modified or revised \nby ATCLLC in its judgment and determination….”28 \n• “The ATCLLC Local Planning Criteria and requirements established by ATCLLC’s \nBusiness Practices may be revised from time to time in response to changes in \nindustry standards, new system conditions, new technologies and new operating \nprocedures, as appropriate and subject to change at any time at ATC’s discretion.”29  \n• “Change, modification, supplement, or revision to the ATCLLC Local Planning \nCriteria and/or requirements established by ATCLLC’s Business Practices shall \nbecome applicable immediately following the posting by ATCLLC of such revised \ncriteria to the ATCLLC website.”30 \n• “ATCLLC shall reflect such modifications to existing Distribution Interconnections \nor proposed new Distribution Interconnections . . . and the Transmission Facilities \nthat are determined to be necessary as a result of such study or studies or other \nassessment shall be incorporated into such other planning functions . . . to the extent \nnecessary or appropriate to reflect the effect of such request or the Transmission \nFacilities determined necessary”31  \n• “To the extent necessary and appropriate, ATCLLC shall incorporate the results of \nthe studies or assessments performed for any and all Distribution – Transmission \nInterconnection Requests in its network assessment.”32   \n \n25 Attachment FF-ATCLLCA, § V.G. \n26 Id. § VI.A.2. \n27Id. \n28 Id. § IV (definition of Distribution – Transmission Interconnection Agreement). \n29 Id. § V.F. \n30 Id. \n31 Id. § VI.A.11. \n32 Id."},{"page":10,"startToken":2806,"endToken":3076,"text":"10 \n \nMicrosoft recognizes that transmission providers and transmission owners must \nconfront challenges today that are very different from those that existed when Order No. 890 \nwas issued nearly two decades ago. Microsoft also appreciates ATC’s work to reform its \nlocal transmission planning process to address the growing demand associated with large \nretail loads while maintaining system reliability and preventing inappropriate cost shifts to \nother customers. As the Commission evaluates ATC’s proposed revisions to Attachment FF-\nATCLLC, however, Microsoft respectfully requests that it consider not only whether the \nproposal addresses the operational challenges posed by large-load interconnections, but also \nwhether the proposal preserves the fundamental structural safeguards of open access \ntransmission service.  \nC. \nATC’s local planning reforms exclude pro forma agreements although \nATC requires the parties to execute these contracts, further \nexacerbating the risk of undue discrimination and preferential \ntreatment. \nATC’s proposal contemplates that transmission customers requesting transmission \nservice for an ATCLLC Large Load will be required to enter into a Minimum Transmission \nCharge Agreement (“MTCA”) and one or more Large Load Project Commitment \nAgreements (“LLPCAs”). Microsoft protested these agreements for its Racine County data \ncenter campus submitted by ATC in currently pending Docket No. ER26-3265 because as-\nfiled, those agreements contained blatant errors and deficiencies, and raised cost-of-service \nand open access red flags. As in this proceeding, the agreements at issue in Docket No. \nER26-3265 were negotiated without any input or participation from Microsoft, and the \nconsequences of this fact are axiomatic in their structural shortcomings.   \nMicrosoft understands that ATC’s preference is that its transmission customers \nremain subject to the same terms and conditions. Yet Microsoft cannot reconcile this stated"},{"page":11,"startToken":3076,"endToken":3381,"text":"11 \n \npreference with ATC’s decision to omit the MTCA and the LLPCA as pro forma contracts in \nAttachment FF-ATCLLC. These agreements establish the substantive rights and obligations \nthat will govern the planning, construction, financing, and operation of facilities necessary to \nserve large loads, and ultimately their terms will flow through to the large load retail \ncustomer. Their absence from the Tariff is significant. By requiring customers to enter into \nagreements that are not part of a generally applicable Tariff in order to receive electric \nservice, ATC introduces a level of discretion that creates a substantial risk that similarly \nsituated customers may be offered materially different terms and conditions. The danger is \nparticularly acute when the agreements are negotiated exclusively between ATC and its \naffiliates (like WEPCo) without any input from the applicable large load customer, as is the \ncase for the agreements currently pending in Docket No. ER26-3265. The Commission \nrecognizes that pro forma contracts have a role in ensuring that transmission providers \nadminister jurisdictional services on a transparent, consistent, and non-discriminatory basis. \nRecently, in PJM Interconnection, L.L.C., the Commission explained that where specific \ncontractual provisions provide benefits to interconnection customers, those benefits should \nbe made available through a pro forma agreement “to ensure that all similarly situated \ninterconnection customers are treated on a consistent and fair basis.”33 Likewise, in \nSouthwest Power Pool, Inc., the Commission reminded the grid operator that if it elects to \noffer a particular form of service, the applicable terms and benefits should be memorialized \nin a pro forma agreement “to ensure that all similarly-situated interconnection customers are \ntreated on a consistent and fair basis.”34 These precedents  recognize the concerns here—\n \n33 PJM Interconnection, L.L.C., 191 FERC ¶ 61,025, at P25 (2025). \n34 Sw. Power Pool Inc., 128 FERC ¶ 61,191, at P 21 (2009)."},{"page":12,"startToken":3381,"endToken":3697,"text":"12 \n \ntransparency and comparability are undermined when contracts for a tariff service are \nnegotiated outside of a generally applicable tariff framework. Because ATC intends the \nMTCA and the LLPCA to become a standard feature of local transmission planning and \nservice, the terms governing those arrangements should be set in Commission-approved pro \nforma agreements rather than through individualized negotiations or website-posted contracts \nthat may change over time. \nThe Commission reached a similar conclusion in MidAmerican Energy Co., where it \nrejected non-conforming provisions in an interconnection agreement, explaining that the \ninsurance requirements the transmission provider wished to adopt for one interconnection \ncustomer should instead be incorporated into the pro forma Large Generator Interconnection \nAgreement.35 The Commission emphasized there that pro forma agreements are necessary to \nensure that all similarly situated customers are “treated on a consistent and fair basis.”36 That \nsafeguard is particularly relevant here because the agreements contemplated by ATC will \ngovern matters that may ultimately determine a large retail customer’s financial exposure, \nproject development obligations, termination rights, security requirements, and long-term \nservice costs. Without Commission-approved pro forma agreements, large retail customers \nhave no assurance that these provisions will be applied consistently from one large project to \nthe next.   \n \n35 MidAmerican Energy Co., 116 FERC ¶ 61,018, at P 12 (2006) (“Indeed, MidAmerican’s \nproposed insurance requirements are tailored to more closely match the need for insurance with the \nexposure to liabilities by not requiring the full insurance coverage until construction commences.  \nHowever, these benefits should be made available to all interconnection customers in a transparent, \nnon-discriminatory manner so that MidAmerican cannot favor Pomeroy Wind over the rest of \nMidAmerican’s customers.”). \n36 Id.; See also Sw. Power Pool, Inc., 129 FERC ¶ 61,121, at P 13 (2009) (stating that “[t]he \nuse of pro forma documents ensures that interconnection customers receive non-discriminatory \nservice and that all interconnection customers are treated on a consistent and fair basis.”)."},{"page":13,"startToken":3697,"endToken":3913,"text":"13 \n \nATC has not explained why it did not propose a pro forma MTCA and LLPCA to \ncomply with the Show Cause Order, when pro forma contracts are consistent with \nlongstanding Commission policy and precedent. Permitting ATC to require execution of non-\ntariffed agreements while reserving discretion over their contents only exacerbates concerns \nregarding transparency, comparability, and the potential for inconsistent treatment by ATC \namong its customers. \nII. \nCONCLUSION \nMicrosoft respectfully requests that the Commission initiate hearing and settlement \njudge procedures in this proceeding to allow Microsoft and other interested stakeholders to \nwork with ATC to develop robust local planning procures. In the alternative, Microsoft \nrespectfully requests that the Commission reject the proposed tariff changes without prejudice \nto be refiled. \nRespectfully submitted, \n \nJeffery Riles \nSr. Director of Energy Markets, America \nJordan Weiszhaar \nSr. Manager of Energy Regulatory Strategy, \nAmericas \nMicrosoft Corporation  \nOne Microsoft Way  \nRedmond, WA 98052 \nTel: 425.882.8080 \njeffriles@microsoft.com \njordanw@microsoft.com \n \n/s/ Kimberly Frank     \nKimberly B. Frank \nThomas S. DeVita \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006 \nTel: 202.778.9064 \nkimberly.frank@klgates.com \nthomas.devita@klgates.com \n \n \nColeman Wheeler \nK&L Gates LLP \n17 North Second Street, 18th Floor \nHarrisburg, PA 17101 \nTel: 717.231.4820 \ncoleman.wheeler@klgates.com \n \n \n \nSeptember 8, 2026"},{"page":14,"startToken":3913,"endToken":3979,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day of September 8, 2026 served the foregoing \ndocument upon each person designated on the official service list compiled by the Secretary \nin this proceeding. \n \n \nRespectfully submitted, \n/s/ Kimberly Frank  \nKimberly B. Frank \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006 \nTel: 202.778.9064 \nkimberly.frank@klgates.com \n \nSeptember 8, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":841,"startToken":0,"endToken":715},{"p":3,"at":841,"title":"I. PROTEST","method":"printed heading","endPage":3,"endAt":854,"startToken":715,"endToken":717},{"p":3,"at":854,"title":"A. ATC’s local planning reforms to address large load interconnection and","method":"printed heading","endPage":7,"endAt":988,"startToken":717,"endToken":1971},{"p":7,"at":988,"title":"B. ATC’s local planning reforms provide ATC with substantial discretion","method":"printed heading","endPage":10,"endAt":830,"startToken":1971,"endToken":2917},{"p":10,"at":830,"title":"C. ATC’s local planning reforms exclude pro forma agreements although","method":"printed heading","endPage":13,"endAt":460,"startToken":2917,"endToken":3764},{"p":13,"at":460,"title":"II. CONCLUSION","method":"printed heading","endPage":14,"endAt":0,"startToken":3764,"endToken":3913},{"p":14,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":414,"startToken":3913,"endToken":3979}]}