{"document":{"slug":"rec-20260908-5321","title":"Motion to Intervene and Comments of MISO Transmission Owners in support of the 08/18/2026 filing by Midcontinent Independent System Operator, Inc","issued":"2026-09-08","accession":"20260908-5321","docket":"ER26-3552-000","group":"MISO zero-injection generator interconnection agreement","filer":"MISO Transmission Owners","kind":"comments","file":"sources/filings/text/20260908-5321_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5321","tier":"record","sha256":"00cb74bd35b72245112591e766b22297282453a5558fafac3c5c09dffe01945c","pages":13,"tokens":3127,"emptyPages":[],"textThemes":["study","colo","cost","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":316,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n ) \nMidcontinent Independent System   \n) \nDocket No. ER26-3552-000 \n \nOperator, Inc.  \n \n \n) \n) \n \nMOTION TO INTERVENE AND COMMENTS IN SUPPORT OF  \nTHE MISO TRANSMISSION OWNERS  \n \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 \nsubmit this motion to intervene and comments in support of the August 18, 2026 filing by \nMidcontinent Independent System Operator, Inc. (“MISO”) in which MISO proposes \nrevisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff \n \n1  \n18 C.F.R. §§ 385.212, 385.214.   \n2  \nFor purposes of this filing, the MISO Transmission Owners consist of Ameren \nServices Company, as agent for Union Electric Company d/b/a Ameren Missouri, \nAmeren Illinois Company d/b/a Ameren Illinois and Ameren Transmission \nCompany of Illinois; American Transmission Company LLC; Big Rivers Electric \nCorporation; Central Minnesota Municipal Power Agency; Citizens Electric \nCorporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; \nCooperative Energy; Dairyland Power Cooperative; Duke Energy Business \nServices, LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative, \nInc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural \nElectric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power \n& Light Company d/b/a AES Indiana; International Transmission Company d/b/a \nITCTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan \nElectric Transmission Company, LLC; MidAmerican Energy Company; \nMinnesota Power (and its subsidiary Superior Water, L&P); Missouri River Energy \nServices; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company \nLLC; Northern States Power Company, a Minnesota corporation, and Northern \nStates Power Company, a Wisconsin corporation, subsidiaries of Xcel Energy Inc.; \nNorthwestern Wisconsin Electric Company; Otter Tail Power Company; Prairie \nPower, Inc.; Southern Illinois Power Cooperative; Southern Indiana Gas & Electric \nCompany (d/b/a CenterPoint Energy Indiana South); Southern Minnesota \nMunicipal Power Agency; Wabash Valley Power Association, Inc.; and Wolverine \nPower Supply Cooperative, Inc."},{"page":2,"startToken":316,"endToken":544,"text":"2 \n(“Tariff”) to create a Zero Injection Generator Interconnection Agreement (“ZGIA”), \nrelated study process and operational requirements, and market and resource adequacy \nrules to interconnect resources that intend to serve load, including large and co-located \nloads, interconnected at the same substation and with the same voltage level as existing or \nproposed load, i.e., Zero-Injection Generation (“ZG”) Resources.3  As explained in the \nAugust 18 Filing and below, MISO’s proposal to create a new framework to accommodate \ninterconnection of ZG Resources will provide the region with another strategic and \noperational tool to help meet the rapidly growing demand of large and co-located loads by \noffering a streamlined interconnection pathway to resources that qualify, while also \nformalizing an already existing practice, addressing aspects of the Commission’s directives \nfrom its recent show cause order,4 and yielding independent benefits for the region’s \ninterconnection process.  For these reasons, the Commission should accept the August 18 \nFiling’s proposed Tariff revisions, effective October 18, 2026.   \n \n \n \n3  \nZero Injection Generator Interconnection Agreement of Midcontinent Independent \nSystem Operator, Inc., Docket No. ER26-3552-000 (Aug. 18, 2026) (“August 18 \nFiling”).  All capitalized terms in this pleading that are not otherwise defined herein \nhave the same meaning they are given in the current Tariff or the proposed Tariff \nrevisions of the August 18 Filing. \n4  \nMidcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause \nOrder”)."},{"page":3,"startToken":544,"endToken":785,"text":"3 \nI. \nCOMMENTS IN SUPPORT  \nA. \nZG Interconnection Service Will Provide the MISO Region With \nAnother Efficient, Effective, and Tailored Tool to Address the Region’s \nLarge Load Growth \nThe MISO Transmission Owners support MISO’s proposed ZG Interconnection \nService construct as a just and reasonable framework that provides a limited, streamlined \ninterconnection path for a ZG Resource, i.e., a planned generator seeking to connect at the \nsame substation and with the same voltage level as existing or planned load, including large \nloads and co-located loads.5  The proposed streamlined ZGIA framework, which is \nspecifically designed to complement MISO’s standard Interconnection Queue process, the \nDefinitive Planning Phase (“DPP”),6 establishes a targeted 90-day study process for \ngeneration resources seeking a more limited interconnection service than Energy Resource \nInterconnection Service (i.e., ERIS), which grants “as available” access to the full MISO \nTransmission System.7  The ZGIA interconnection study process recognizes “the limited \ndistance over which energy would need to be—and is permitted to—flow,” allowing for a \nmore targeted and efficient study process.8  Load customers, including large load \ncustomers, also will benefit from ZGIA interconnection studies that recognize on-site \ngeneration, potentially reducing network upgrade requirements to interconnect.  As MISO \n \n5  \nSee August 18 Filing at 7. \n6  \nSee id. at 14. \n7  \nSee id. at 25; id., Tab C (Prepared Direct Testimony of Marc Keyser, Director, \nCentral Region—External Affairs) at 7-8 (“Keyser Test.”). \n8  \nAugust 18 Filing at 25."},{"page":4,"startToken":785,"endToken":1100,"text":"4 \nstates, this framework “enables a pathway for certain large load configurations to achieve \nspeed to reliable power while maintaining system reliability.”9 \nWith its ZGIA proposal, MISO adds another tool to the region’s growing toolbox \nfor addressing the urgent and exponential load growth across the region.  Specifically, the \nZGIA will complement MISO’s other recent strategic initiatives, including:  the Expedited \nResource Addition Study, which provides a temporary accelerated interconnection process \ntailored to generators needed within the region to serve important, near-term new load; \nMISO’s improved Expedited Project Review (“EPR”) process, part of the MISO \nTransmission Expansion Plan (“MTEP”), which expeditiously studies network upgrades \nnecessary for new large loads; and the MISO-Southwest Power Pool, Inc. (“SPP”) Joint \nTargeted Interconnection Queue Study, which provides a pathway to build network \nupgrades at the MISO-SPP seams. \nThe crux of the proposed ZGIA framework is the new limited product, ZG \nInterconnection Service,10 available for a Generating Facility that will only serve ZG \nAssociated Load,11 i.e., a designated load either at the same POI or has a POW12 on the \n \n9  \nId. at 10. \n10  \nSee id., Tab A (Marked Tariff Sheets) at Definitions – Z (“Marked ZGIA Tariff \nSheets”) (defining ZG Interconnection Service). \n11  \nSee id. at Definition – Z (defining ZG Associated Load as “[a] source of electrical \nload that has a Point of Withdrawal [(“POW”)] that is at the same substation as the \nPoint of Interconnection [(“POI”)] to the Transmission System (i.e., same voltage \nlevel at the interconnecting substation) as the Generating Facility with ZG \nInterconnection Service that will serve it”). \n12  \nPOW is a new term proposed to be defined as “the point(s) where a non-\ntransmission facility that is used to withdraw Energy from the Transmission System \nto serve Load connects to the Transmission System.”  Id. at Attachment X.  Put \nanother way, POW is the “point that a Load interconnects to the Transmission"},{"page":5,"startToken":1100,"endToken":1422,"text":"5 \nsame voltage side of the same substation at the same voltage level, as identified in its \nInterconnection Request.13  The ZG Interconnection study process, i.e., the ZG Impact \nAssessment, will occur on an accelerated timeline, within ninety Calendar Days, at the end \nof which MISO will issue a ZGIA to the parties.  With an interconnection agreement, the \nZGIA Resource can then be modeled as an input to the subsequent MTEP (or MTEP EPR) \nload study for its ZG Associated Load, potentially reducing the network upgrades needed \nto integrate the new load.14 \nMISO proposes requirements for eligibility of ZG Interconnection Service similar \nto the requirements for standard Interconnection Service through its DPP process, but \nincludes additional requirements to allow MISO to study the generation in connection with \nthe ZG Associated Load and verify the ability of proposed configurations and control \nequipment to limit injections, as required.15  Specifically, as MISO explains, the criteria \nfor a resource to qualify and proceed through the ZG Interconnection study process \ndeviates from MISO’s usual criteria for interconnection requests in five key ways:16  \n(1) The Interconnection Customer must demonstrate a documented relationship \nwith the planned or anticipated load to be connected at the same voltage \nside of the same substation, i.e., ZG Associated Load, and affirm the ZG \n \nSystem . . . the Load analog to the generation-specific term ‘Point of \nInterconnection’.”  Keyser Test. at 23. \n13  \nAugust 18 Filing at 12. \n14  \nSee id. at 8. \n15  \nKeyser Test. at 27-28. \n16  \nAugust 18 Filing at 12-13, Keyser Test. at 9-10.  In addition to the five listed, the \nZGIA Interconnection Request process will use a serial “first-come, first-served” \napproach and will group ZGIA projects per cycle capping the number of requests \nper cycle to the first ten requests.  Keyser Test. at 24.  MISO proposes this deviation \nfrom the DPP process to prevent disruptions to the DPP process and ensure MISO \nmaintains appropriate staffing levels.  Id."},{"page":6,"startToken":1422,"endToken":1753,"text":"6 \nAssociated Load’s intention to take service from the Interconnection \nCustomer’s Generation Facility, i.e., the ZG Resource,17 using a ZGIA;   \n(2) The Interconnection Customer requesting ZG Interconnection Service is not \nlimited in the quantity of nameplate capacity of generation to be built, but \nis limited to receive only ZG Interconnection Service at a level that will not \nexceed peak demand of the ZG Associated Load, ensuring the maximum \nexpected energy generated by the ZG Resource does not exceed maximum \ndemand by the ZG Associated Load;18  \n(3) When studying the Interconnection Request for ZG Interconnection \nService, MISO will model the ZG Associated Load and confirm the \nproposed equipment sufficiently limits injections, which means MISO will \nstudy the load and generation together;19  \n(4) The ZG Resource must interconnect at the same substation and voltage level \nas the POWs where the ZG Resource will serve the ZG Associated Load;20 \nand  \n(5) Study of the ZG Interconnection Service must find that the ZG Resource \ndoes not require Network Upgrades beyond the substation except for system \nprotection facilities at adjacent substations.21   \nThese enhanced requirements ensure that others on the Transmission System are not \nnegatively impacted by a ZG Resource.   \nMoreover, a ZG Resource with an executed ZGIA will be subject to MISO’s \nregional planning process and the specific local planning criteria of its appropriate \nTransmission Owner.22  It also may participate in the replacement process for like resources \n(i.e., replacing another Generating Facility that has ZG Interconnection Service in the same \n \n17  \nSee August 18 Filing at 12; Keyser Test. at 9; see also Marked ZGIA Tariff Sheets \nat Definitions – Z (defining ZG Resource). \n18  \nSee August 18 Filing at 13; Keyser Test. at 9-10. \n19  \nSee August 18 Filing at 13; Keyser Test. at 10 \n20  \nSee August 18 Filing at 13; Keyser Test. at 10 \n21  \nSee August 18 Filing at 13; Keyser Test. at 10. \n22  \nSee August 18 Filing at 13; Keyser Test. at 35."},{"page":7,"startToken":1753,"endToken":1989,"text":"7 \nlocation), MISO’s resource adequacy construct, and the energy and operating reserve \nmarkets.23   \nBy proposing a new ZG Interconnection Service process that echoes MISO’s \nstandard interconnection process with slight variations, the ZG Interconnection Service \nprocess adds consistency, transparency, and structure around these distinctive \ninterconnection requests to meet specific load needs.  Through its proposed ZGIA \nframework, MISO will have a uniform process to account for actual impacts of these \nresources with limited injections; ensure these Interconnection Customers pay for only the \nnecessary upgrades of their limited impacts; confirm the Interconnection Customer’s \nproposed means for limiting injections; and memorialize and enforce the Interconnection \nCustomer’s commitments, including the control equipment and operational limitations, via \na binding ZGIA.24  \nB. \nZG Interconnection Service Will Address the Show Cause Order’s \nConcern With Co-Located Load \nWhen discussing MISO’s lack of Tariff provisions regarding interconnection \nservice for generation serving co-located load, the Commission’s Show Cause Order \nhighlighted MISO’s development of a zero-injection generator interconnection process and \narticulated a concern that such a process and its studies were not part of the Tariff.25  \nMISO’s proposal here, the culmination of that stakeholder-driven development, addresses \nthat concern.  The proposed ZGIA framework is an adaptation of standard interconnection \nservice that aligns with directives of the Show Cause Order.  Specifically, MISO’s proposal \n \n23  \nSee August 18 Filing at 13; Keyser Test. at 36-39. \n24  \nSee Keyser Test. at 8-9. \n25  \nShow Cause Order at P 97."},{"page":8,"startToken":1989,"endToken":2215,"text":"8 \nprovides a solution to an aspect of the Commission’s concern about the lack of clarity and \nconsistency as to the rates, terms, and conditions of service that apply to interconnection \ncustomers serving load that is geographically and electrically close, including co-located \nload.26   \nWhile MISO’s proposal slightly expands the definition of “co-location” envisioned \nby the Show Cause Order,27 MISO reasonably determined, after extensive stakeholder \nfeedback,28 including from developers (such as developers of established or planned large \nloads in the region),29 Transmission Owners, and other interested parties in the region, that \nthis broader scope, encompassing arrangements of load and generation not just at the same \nPOI, but generally located at the same substation with the same voltage level, better met \nthe region’s needs30 and struck an appropriate balance, offering a limited product with \nlimited impact on other projects and an accelerated study process.31  In addition to aligning \nwith stakeholder feedback, MISO found that defining a ZG Resource as serving load at the \nsame substation with the same voltage level would be “electrically indistinguishable”32 \n \n26  \nId. at PP 94-98. \n27  \nId. at P 91. \n28  \nSee Keyser Test. at 39-42 (describing the stakeholder process culminating in the \nAugust 18 Filing). \n29  \nSee id. at 12. \n30  \nAugust 18 Filing at 6 n.30. \n31  \nId. at 12. \n32  \nKeyser Test. at 12."},{"page":9,"startToken":2215,"endToken":2495,"text":"9 \nfrom requiring interconnection for a resource only serving load that is “electrically \nproximate,” or “co-located” behind the same POI, as described by the Show Cause Order.33   \nAdditionally, the Commission in the Show Cause Order highlighted the absence of \nTariff provisions that address the potential need for control equipment and protection \nsystems to ensure that an interconnection customer’s commitment to limit its generating \nfacility’s output to match the forecast of an electrically proximate large load or large co-\nlocated load.34  MISO’s proposal includes strict limits on injections to the Transmission \nSystem, which will limit the potential impacts to the Transmission System and need for \nNetwork Upgrades,35 as well as requirements for control equipment and protection systems \nas part of the proposed ZGIA.36   \nMISO’s filing does not establish new rules regarding transmission service.  As such \nthe ZG Associated Load must obtain transmission service to be served using the \nTransmission System, which, for load served by a Load Serving Entity in MISO, is usually \nNetwork Integration Transmission Service.37  Relatedly, MISO’s ZGIA filing does not \nallow netting of load and generation for transmission service or market settlement \npurposes.38  However, as described by MISO and highlighted in the request for abeyance \nof the Show Cause Order’s deadlines by MISO and the MISO Transmission Owners,39 the \n \n33  \nShow Cause Order at PP 113, 116. \n34  \nId. at P 113. \n35  \nSee August 18 Filing at 7. \n36  \nSee Keyser Test. at 8, 26. \n37  \nAugust 18 Filing at 8 n.32. \n38  \nId. at 8. \n39  \nMotion of the Midcontinent Independent System Operator, Inc. and the MISO \nTransmission Owners to Hold Proceeding in Abeyance and Request for Shortened"},{"page":10,"startToken":2495,"endToken":2766,"text":"10 \nproposed ZGIA framework is only one piece of MISO’s work plan for addressing all \naspects of the Show Cause Order and resolving the issues posed by the dramatic large load \ngrowth in the region.40   \nMISO’s proposed ZGIA framework would establish a uniform and tailored \ninterconnection service that will provide regional benefits to generation and load with \nsafeguards to avoid disruptions to the Transmission System and MISO’s current \ninterconnection process.  It also addresses the Show Cause Order’s concerns regarding \ngenerator interconnection service and the study of generation serving co-located load.  \nAccordingly, the Commission should accept MISO’s proposed ZGIA framework as just \nand reasonable. \nII. \nMOTION TO INTERVENE \nThis proceeding involves revisions to MISO’s Tariff to establish an entirely new \ninterconnection agreement, the ZGIA, the related processes and requirements for ZG \nResources, and provisions to integrate such resources as part of MISO’s market and \nresource adequacy.  As Transmission Owners within MISO that are subject to the Tariff, \neach of the MISO Transmission Owners will be affected by whatever action the \nCommission takes in this proceeding because the Tariff and its interconnection procedures \nimpact the MISO Transmission Owners’ transmission facilities.  Additionally, the MISO \nTransmission Owners have a vested interest in the MISO region’s ability to meet the need \nfor speed to power while maintaining resource adequacy and reliability as well as \n \nComment Period and Expedited Treatment, Docket No. EL26-70-000 (Aug. 3, \n2026). \n40  \nAugust 18 Filing at 6, 10 (“The ZGIA framework represents an initial step in a \nbroader set of solutions to address the concerns expressed in the Show Cause Order \nand to meet the evolving needs of the MISO region.”)."},{"page":11,"startToken":2766,"endToken":2971,"text":"11 \naddressing aspects of the Show Cause Order’s directives, all of which the August 18 \nFiling’s proposals do.  Consequently, each of the MISO Transmission Owners has a direct, \nunique, and substantial interest in this case that is not and cannot be adequately represented \nby any other party.41  Therefore, the Commission should allow the intervention of each \nMISO Transmission Owner listed supra in note 2.   \nThe MISO Transmission Owners also request that the Commission place the \nfollowing individuals on the official service list42 for this proceeding: \nWendy N. Reed \nAnna Fernandez \nAbraham F. Johns III \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC 20005-3898 \n(202) 393-1200 \nreed@wrightlaw.com \nfernandez@wrightlaw.com \njohns@wrightlaw.com \n \n41  \n18 C.F.R. § 385.214(b)(2)(ii) (stating that a motion to intervene must demonstrate \nthat “[t]he movant has . . . an interest which may be directly affected by the \noutcome of the proceeding”). \n42  \nTo the extent necessary, the MISO Transmission Owners request waiver of Rule \n203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.203(b)(3), to permit all of the persons listed to be placed on the official \nservice list for this proceeding."},{"page":12,"startToken":2971,"endToken":3053,"text":"12 \nIII. \nCONCLUSION \n \nFor these reasons, the MISO Transmission Owners request that the Commission \ngrant this motion to intervene and accept the August 18 Filing as just and reasonable, \neffective October 18, 2026.   \nRespectfully submitted, \n /s/ Abraham F. Johns III   \nWendy N. Reed \nAnna Fernandez \nAbraham F. Johns III \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005-3898 \n(202) 393-1200 \nreed@wrightlaw.com \nfernandez@wrightlaw.com \njohns@wrightlaw.com \nAttorneys for the \nMISO Transmission Owners \n \nSeptember 8, 2026"},{"page":13,"startToken":3053,"endToken":3127,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Washington, DC, this 8th day of September 2026. \n \n /s/ Abraham F. Johns III    \nAbraham F. Johns III \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005-3898 \n(202) 393-1200 \njohns@wrightlaw.com \n \nAttorney for the \nMISO Transmission Owners"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":3,"startToken":0,"endToken":545},{"p":3,"at":3,"title":"I. COMMENTS IN SUPPORT","method":"printed heading","endPage":3,"endAt":29,"startToken":545,"endToken":549},{"p":3,"at":29,"title":"A. ZG Interconnection Service Will Provide the MISO Region With","method":"printed heading","endPage":7,"endAt":887,"startToken":549,"endToken":1869},{"p":7,"at":887,"title":"B. ZG Interconnection Service Will Address the Show Cause Order’s","method":"printed heading","endPage":10,"endAt":718,"startToken":1869,"endToken":2599},{"p":10,"at":718,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":12,"endAt":4,"startToken":2599,"endToken":2972},{"p":12,"at":4,"title":"III. CONCLUSION","method":"printed heading","endPage":13,"endAt":0,"startToken":2972,"endToken":3053},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":479,"startToken":3053,"endToken":3127}]}