{"document":{"slug":"rec-20260908-5326","title":"Limited Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing","issued":"2026-09-08","accession":"20260908-5326","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"protest","file":"sources/filings/text/20260908-5326_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5326","tier":"record","sha256":"7e427e4752eb0f83d5d07e7e8ac27bebd1914198ae1e905ef33dadc9559cd41e","pages":11,"tokens":2974,"emptyPages":[],"textThemes":["study","colo","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":198,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al. \n \n \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n \n) \n) \n) \n \n) \n) \n) \n) \n) \n) \n) \n \n) \n) \n) \n \n \n \nDocket Nos. EL25-49-002 \nEL25-49-000 \n \n \n \nDocket No. AD24-11-001 \n \n \n \nDocket No. EL25-20-001 \n(consolidated) \n \n \n \n \n \n \nDocket No. ER26-1479-000 \nER26-1479-002 \nLIMITED PROTEST AND COMMENTS OF  \nCONSTELLATION ENERGY GENERATION, LLC  \nConstellation1 submits this limited protest and comments in response to the PJM \nCompliance Filing.2 Two aspects of the PJM Compliance Filing are non-compliant with the \nJune 2026 Co-Location Order.3 First, PJM has not shown that its proposal to delay the availability \nof Interim Network Integration Transmission Service (“Interim NITS”) until July 1, 2028, is just \n \n1 Constellation Energy Generation, LLC (“Constellation”) files this limited protest and comments pursuant to Rule 211 \nof the Commission’s Rules of Practice and Procedure. 18 C.F.R. § 385.211 (2026). \n2 Compliance Filing of PJM Interconnection, L.L.C. in Response to Order on Rehearing, Clarification, Compliance \nFiling and Paper Hearing in Docket No. EL25-49-002, et al. (Aug. 17, 2026) (“PJM Compliance Filing”). \n3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Co-Location Order”)."},{"page":2,"startToken":198,"endToken":503,"text":"2 \n \nand reasonable.4 PJM has not explained with any specificity why it will take nearly two more years \nto implement the service the Commission ordered in December 2025. Second, PJM has not \nadequately explained the Necessary Study process for Interconnection Customers with existing or \nongoing Necessary Studies, as the Commission directed.5 PJM should be required to confirm that \ncustomers can rely on the results of prior Necessary Studies where the scope has not changed.   \nThree areas of the PJM Compliance Filing require clarification or further Commission \ndirection. First, PJM should clarify the meaning of “partial NITS” and its ability to immediately \nprovide that service. Second, PJM has added as a prerequisite for Interim NITS the “satisfaction \nof any technical requirements identified by the applicable Transmission Owner(s).”6 This \ncondition requires reasonable limitations to prevent further Transmission Owner-driven delays in \nproviding service. Finally, the Commission should clarify that Interim NITS service cannot be \nconditioned on resource adequacy considerations outside of real-time operational necessities.7 \nPROTEST \nI. \nPJM’s Proposal to Delay the Availability of Interim NITS to July 1, 2028, Is Not Just \nand Reasonable \nThe Commission should reject PJM’s proposal to delay Interim NITS Service until July 1, \n2028, as PJM has not established that such a prolonged implementation period is just and \nreasonable. First, PJM fails to “provide[] sufficient information” for the Commission to find such \n \n4 Id. P 597. \n5 Id. P 283. \n6 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.4. \n7 See, e.g., June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597 (“[W]hile PJM will procure generation capacity \nin forward capacity auctions to serve Eligible Customers taking FCD transmission service based on the contract \ndemand level, PJM will not consider Interim NITS or NFCD transmission service in its resource adequacy \nplanning.”)."},{"page":3,"startToken":503,"endToken":837,"text":"3 \n \na delay to be just and reasonable.8 The Commission directed that PJM give “serious consideration” \nto the proposed effective date given the “urgent” nature of large load interconnections.9 Yet PJM \njustifies its July 1, 2028 implementation date in one conclusory sentence: “PJM Operations \npersonnel will need to implement additional tools and processes before they will be able to monitor \nand curtail, as needed, the new non-firm Interim NITS product proposed in Tariff, Part XI.”10 That \nis wholly inadequate. PJM still has not adequately considered “whether Interim NITS … can be \nmade effective at an earlier date,” as the Commission ordered it to do.11 As the June 2026 Co-\nLocation Order explains, the Commission “requires more support for the timeliness of a proposed \neffective date.”12 \nSecond, PJM’s vague claim that its Operations personnel will need until July 1, 2028, to \n“implement additional tools and processes” for Interim NITS is hard to square with PJM’s \nassertion that it can implement Interim Resource Adequacy Service (“IRAS”) by June 1, 2027, \nless than 10 months after being proposed.13 PJM fails to show that implementing Interim NITS \nwould be any more challenging than implementing IRAS. To implement IRAS, PJM must \nestablish a Large Load Registry, a new “database of information pertaining to Large Loads that \nwill be established and maintained by PJM.”14 PJM will use the Large Load Registry to “identify, \n \n8 Id. \n9 Id. \n10 PJM Compliance Filing at 23.  \n11 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597. \n12 Id.; see also id. (“[W]e agree with Vistra and Joint Co-Location Developers that PJM’s proposal lacks specificity. \nIn particular, we find that the implementation details for the software updates necessary for PJM’s economic dispatch \nsoftware and dispatch tools lack specificity.”) (emphasis added). \n13 Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load \nRegistry to Address System Reliability, Docket No. ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”). \n14 Id. at 5."},{"page":4,"startToken":837,"endToken":1117,"text":"4 \n \nfor each zone/area, the Eligible New Large Load Amounts, i.e., MW quantities that are eligible to \nbe called upon to reduce load.”15 During emergency conditions, “PJM will instruct Electric \nDistributors to reduce load by a MW quantity equal to or less than the Electric Distributor’s \nEligible New Large Load Amount.”16 In addition, the Electric Distributors must “coordinate, as \nappropriate, with the relevant state(s) or RERRA(s), individual Load Serving Entities, and \ncustomers ... to support transparent, effective, and orderly deployment of [IRAS].”17 PJM does not \nexplain how long that coordination process will take or what it will entail. Nonetheless, PJM \nproposes to implement IRAS by June 1, 2027, so that “coordination” process must be completed \nin a matter of months.  \nThese IRAS requirements appear comparable to, if not more complicated (given the \ninvolvement of numerous entities other than PJM) than what PJM claims is necessary for Interim \nNITS: establishing additional tools and processes to monitor and curtail the service. For IRAS, \nthose tools and processes include the Large Load Registry and determination of each Electric \nDistributor’s Eligible New Large Load Amount. And IRAS may in fact be more complicated \nbecause it also requires the coordination process between the Electric Distributors, thirteen states \nand others to determine “under their own laws, policies, and definition of what constitutes ‘large \nload’—which resources will be called on to reduce load.”18 \nIn the interest of efficiency, the Commission should exercise its authority under \nSection 206 of the Federal Power Act to fix a replacement rate and direct PJM to (i) adopt June 1, \n \n15 Id. at 86. \n16 Id.  \n17 Id. at 27. \n18 Id. at 87."},{"page":5,"startToken":1117,"endToken":1426,"text":"5 \n \n2027, as the date for implementing Interim NITS or (ii) demonstrate that it cannot meet that date \nand propose the earliest possible date that it can meet. Implementing Interim NITS by June 1, \n2027, is just and reasonable as it would remedy an unlawful rate within approximately 18 months \nof the Commission’s finding. If PJM elects the latter, PJM should provide specific and detailed \ncomments explaining why June 1, 2027, is not feasible and identify all work streams PJM is \nadvancing before the availability of Interim NITS. \nII. \nPJM Fails to Specify the Process for Interconnection Customers with Existing or \nOngoing Necessary Studies \nPJM fails to address the Commission’s finding that “PJM’s proposed revisions lack clarity \nwith respect to how they apply to Interconnection Customers that have already executed Necessary \nStudy Agreements.”19 As the June 2026 Co-Location Order found, the “scope” of the Necessary \nStudies “has not changed.”20 And PJM has not “otherwise demonstrate[d]” why “Interconnection \nCustomers seeking to serve Co-Located Load cannot rely on the results of Necessary Studies that \nhave already been performed if the scope of the study has not changed.”21 \nThe Commission should specifically order PJM to clarify that Necessary Studies need not \nbe repeated where their scope is the same as previously conducted Necessary Studies. The \nNecessary Studies process can take years.22 Requiring duplicative studies without justification \nwould unnecessarily delay the interconnection of large loads and cannot be just and reasonable. \n \n19 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 283. \n20 Id. \n21 Id. \n22 Under ideal conditions, PJM identifies a Necessary Study process of 270 days, but the process can take much longer. \nSee Limited Request for Rehearing and Clarification of Constellation Energy Generation, LLC, Docket No. EL25-\n49-000, et al., at 7 (“Constellation has been waiting years for Necessary Studies for multiple projects ….”)."},{"page":6,"startToken":1426,"endToken":1698,"text":"6 \n \nCLARIFICATION \nI. \nPJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation \nOn compliance, PJM states that “[a]t present, PJM can provide partial NITS, i.e., NITS in \nan amount less than requested and/or for a term shorter than requested, to Co-Located Load \nthrough the Necessary Study process and therefore is proposing an October 17, 2026 effective \ndate for the bulk of the revisions proposed in this filing.”23 The Commission should require PJM \nto clarify several aspects of this proposal. \nFirst, PJM should clarify what “partial NITS” is, whether it is a new or existing \ntransmission service, and which revisions are included in “the bulk.” \nSecond, PJM should clarify its reference to the Necessary Study process, as it is unclear \nhow that process applies to PJM’s provision of “partial NITS” or Interim NITS. As the \nCommission explained, “the studies applicable to a transmission service request … are distinct \nfrom the Necessary Study process, which studies the modification of a generator \ninterconnection.”24 In addition to explaining what it means, PJM also should clarify that the \nNecessary Study process can proceed at the same time as the study process for NITS and Interim \nNITS conducted by PJM. This is particularly appropriate when the co-location arrangement \nsubject to the Necessary Study is one that will use NITS and Interim NITS services, which will \nnot require delisting of the generator. This in turn will make it much less likely that the results \nwould identify additions, modifications, or replacements to the Transmission System necessary \n \n23 PJM Compliance Filing at 23. \n24 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 286."},{"page":7,"startToken":1698,"endToken":2037,"text":"7 \n \nto maintain system reliability.25 Interim NITS is an entirely front-of-the-meter service where \nPJM will ultimately serve the entire load when standard NITS can be provided.  \nConstellation emphasizes that even under ideal conditions, PJM’s Necessary Study \nprocess takes 270 days,26 and in practice, the process often takes much longer.27 Conditioning the \nprovision of Interim NITS on the Necessary Studies could cause significant delay, making it \neven more important that the implementation date be June 1, 2027. \nII. \nTransmission Owner Technical Requirements Should Be Subject to Reasonable \nLimitations \nPJM’s proposed Section 702.4 adds “satisfaction of any technical requirements identified \nby the applicable Transmission Owner(s)” as a “Technical Requirement[] Prior to Commencement \nof Service.”28 This requirement was not included in PJM’s Initial Brief,29 nor did the June 2026 \nCo-Location Order require PJM to add it.30 \nWhile Transmission Owners have a role in determining whether Interim NITS can be \nreliably provided, reasonable processes and limitations on Transmission Owner-imposed technical \nrequirements are necessary to ensure that Eligible Customers taking Interim NITS are not subject \n \n25 PJM Compliance Filing, Att. A, at Part VIII, Subpart A, § 401.H.3.c (“Transmission Provider shall assess the impact \nof the reduction in Capacity Interconnection Rights associated with the planned Eligible Load and Eligible \nGenerating Facility ….”). \n26 Tariff, Part IX, Subpart G, § 15 (Form of Necessary Studies Agreement) (“Transmission Provider’s good faith \nestimate for the time of completion of the Necessary Studies is within 270 days of the date Transmission Provider \napproves the dynamic model and data submitted by Project Developer ….”). \n27 Supra note 22. \n28 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.4. \n29 See PJM Initial Brief, Att. A, at Part XI, Subpart A, § 702.4 (listing six technical requirements, not including the \nrequirement for “satisfaction of any technical requirements identified by the applicable Transmission Owner(s)”). \n30 See generally June 2026 Co-Location Order, 195 FERC ¶ 61,209 at PP 571-578 (discussing the Commission’s \ndetermination on the terms and conditions of Interim NITS)."},{"page":8,"startToken":2037,"endToken":2410,"text":"8 \n \nto undue delay or burden. Absent such limitations, a Transmission Owner could raise a technical \nrequirement late in the process, further delaying the availability of Interim NITS. Reasonable \nlimitations should include requiring Transmission Owners to identify applicable technical \nrequirements at the time they provide feedback on transmission studies, requiring all Transmission \nOwner technical requirements to be on file with the Commission,31 and prohibiting Transmission \nOwners from imposing technical requirements that are duplicative of PJM’s technical \nrequirements where redundancy is not justified.32 \nIII. \nPJM May Not Condition the Availability of Interim NITS on Resource Adequacy \nConsiderations \nConstellation is concerned that PJM’s proposed tariff revisions will allow for anticipated \nresource adequacy concerns to form a basis for denying or limiting Interim NITS requests. That \nwould be contrary to the Commission’s intent. As the Commission explained, “PJM will not \nconsider Interim NITS … in its resource adequacy planning.”33 The Commission recognized that \n“increasing amounts of new Co-Located Load seeking to be served by an Eligible Customer faster \nthan equivalent generation can come online may create resource adequacy problems,”34 but found \n \n31 See also Response Brief of Constellation Energy Generation, LLC at 12 (Apr. 24, 2026) (“[T]he Commission should \nrequire PJM’s and Transmission Owners’ standards, requirements, guidance, and practices on Co-Location \nArrangements to be on file with the Commission on a standalone basis or reflected in PJM’s Tariff. Rules for Co-\nLocation Arrangements must be clearly stated and available as they ‘significantly affect rates, terms and conditions’ \nof service and can be ‘readily susceptible to specification.’”) (citation omitted). \n32 See, e.g., id. at 13-18 (explaining requiring double protection schemes by default is “unsupported” and “unduly \ndiscriminatory”). \n33 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 597. \n34 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 236 (2025); id. P 201 (“Regarding broader resource \nadequacy and reliability concerns associated with maintaining sufficient generation to serve Co-Located Load, we \nreiterate that load growth generally involves resource adequacy and reliability considerations, regardless of whether \nthe new load is Co-Located Load.”); see also id. P 243 (finding “there is not sufficient evidence to conclude that \nadditional Tariff changes regarding Interconnection Customers electing to use their generation facilities to serve Co-"},{"page":9,"startToken":2410,"endToken":2707,"text":"9 \n \nthat Eligible Customers should be able to take service on behalf of Co-Located Loads that are \n“willing and able to limit their energy withdrawals from the transmission system under certain \nconditions.”35 The solution was not to bar Co-Located Loads from being timely served but to allow \nInterim NITS and other interruptible services and curtail when circumstances required. \nNevertheless, two tariff provisions raise this concern that PJM may attempt to condition \nInterim NITS on anticipated resource adequacy shortfalls. Section 702.3 provides that PJM will \ndetermine the amount of Interim NITS that “can be provided reliably … while maintaining the \nreliability of the Transmission System” based on study procedures in “Tariff, Part XI, Subpart A, \nSection 704”36—yet that section in turn states only that PJM will determine whether “additional \nstudies are needed” and if so, PJM will inform the “Eligible Customer of those studies as soon as \npracticable.”37 Section 705.1 provides that PJM may “curtail Interim NITS for capacity or reserve \nshortages as further set forth in the PJM Manuals”38 but does not identify the particular Manual or \nspecify that it is referring to real-time capacity or reserve shortages. The Commission should \nconfirm that a projection of resource adequacy is not a prerequisite for finding that PJM can \nreliably provide Interim NITS. \nCONCLUSION \nFor the foregoing reasons, Constellation requests that the Commission require PJM to: \n(1) make Interim NITS available by June 1, 2027, or explain why it cannot and propose the earliest \n \nLocated Load are needed with respect to capacity market rules, reliability, and resource adequacy to ensure that the \nPJM Tariff remains just and reasonable”). \n35 Id. P 160. \n36 PJM Compliance Filing, Att. A, at Part XI, Subpart A, § 702.3. \n37 Id. § 704.1. \n38 Id. § 705.1."},{"page":10,"startToken":2707,"endToken":2891,"text":"10 \n \nfeasible date; (2) clarify that Necessary Studies need not be repeated where existing or ongoing \nNecessary Studies sufficiently cover the circumstance; (3) clarify the meaning of “partial NITS” \nand its proposal to provide that service immediately; (4) impose reasonable limitations on \nTransmission Owner technical requirements; and (5) implement its proposed tariff in a manner \nthat does not use resource adequacy as a basis for denying or limiting Interim NITS requests. \n \n \n \nRespectfully submitted, \n     \n \n \n \n \n \n \n      /s/ Seth T. Lucia  \n \n \nSeptember 8, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \n \nChristopher A. Wilson \nVice President, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \nseth.lucia@constellation.com \n  \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n202-799-4538 \ncarolyn.clarkin@us.dlapiper.com  \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":11,"startToken":2891,"endToken":2974,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 8th day of September, 2026, caused to be served a copy \nof the foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2026). \n/s/ Carolyn E. Clarkin  \n \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n202-799-4538 \ncarolyn.clarkin@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1153,"startToken":0,"endToken":365},{"p":2,"at":1153,"title":"I. PJM’s Proposal to Delay the Availability of Interim NITS to July 1, 2028, Is Not Just","method":"printed heading","endPage":5,"endAt":537,"startToken":365,"endToken":1205},{"p":5,"at":537,"title":"II. PJM Fails to Specify the Process for Interconnection Customers with Existing or","method":"printed heading","endPage":6,"endAt":20,"startToken":1205,"endToken":1428},{"p":6,"at":20,"title":"I. PJM’s Comment That It Can Provide “Partial NITS” Requires Further Explanation","method":"printed heading","endPage":7,"endAt":523,"startToken":1428,"endToken":1777},{"p":7,"at":523,"title":"II. Transmission Owner Technical Requirements Should Be Subject to Reasonable","method":"printed heading","endPage":8,"endAt":621,"startToken":1777,"endToken":2121},{"p":8,"at":621,"title":"III. PJM May Not Condition the Availability of Interim NITS on Resource Adequacy","method":"printed heading","endPage":9,"endAt":1380,"startToken":2121,"endToken":2627},{"p":9,"at":1380,"title":"CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":2627,"endToken":2891},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":484,"startToken":2891,"endToken":2974}]}