{"document":{"slug":"rec-20260908-5328","title":"Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing","issued":"2026-09-08","accession":"20260908-5328","docket":"ER26-1479-002","group":"PJM co-location compliance","filer":"American Municipal Power, Inc.","kind":"protest","file":"sources/filings/text/20260908-5328_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5328","tier":"record","sha256":"cf7017db03f9e8b0e59149faa7fbf283318c372d2f3572dd2c72642d9f0d4982","pages":9,"tokens":2362,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":318,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-1479-002 \nLIMITED PROTEST OF \nAMERICAN MUNICIPAL POWER, INC. \nAmerican Municipal Power, Inc. (“AMP”) hereby protests the August 17, 2026 \ncompliance filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1\nin which PJM proposes revisions to its Open Access Transmission Tariff (“Tariff”) to \ncomply with directives in the Federal Energy Regulatory Commission’s (“Commission” or \n“FERC”) June 18, 2026 order in Docket Nos. EL25-49-002, et al.2 As discussed below, \nAMP’s protest is limited to one aspect of the PJM Filing: the proposed definition for Eligible \nGenerating Facility is too narrow.3\nI. \nBACKGROUND AND INTRODUCTION \nHistorically, the PJM Tariff allowed load served by Behind the Meter Generation \n(“BTMG”) to be netted from daily load under sections 34.2 and 34.3 of the PJM Tariff for \npurposes of calculating charges for Network Integration Transmission Service and other \nPJM charges.4 AMP and AMP’s load-serving utility members own and operate generating \n1\nPJM, Compliance Filing in Response to Order on Rehearing, Clarification, Compliance Filing, and Paper \nHearing in Docket Nos. EL25-49-002, et al., Docket No. ER26-1479-002 (Aug. 17, 2026) (“PJM Filing”). \n2\nPJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 18 Order”).  \n3\nSee PJM Filing, Transmittal Letter at 13; id. at Attachment A, proposed Tariff, Part I, section 1 \n(Definitions E – F). \n4\nSee generally, PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 7 (2025) (“December 18 \nOrder”).The definition of BTMG, as previously proposed by PJM, is as follows (pending new language \nunderlined): \n“Behind The Meter Generation” shall mean either Retail Behind the Meter \nGeneration or Non-Retail Behind The Meter Generation and refers to a generation \nunit that delivers energy to load without using the Transmission System or any \ndistribution facilities (unless the entity that owns or leases the distribution facilities"},{"page":2,"startToken":318,"endToken":772,"text":"2 \nunits in the PJM region that qualified (and continue to qualify) as “Non-Retail BTMG” – a \ndistinct category of BTMG subject to certain specific conditions and limitations.5\nIn the December 18 Order,6 the Commission drew a distinction between “retail” \nBTMG and Non-Retail BTMG, and concluded that PJM’s rules allowing netting of retail \nBTMG were no longer just and reasonable.7 The Commission directed PJM to revise the \nTariff provisions addressing certain generating units that are classified as retail BTMG.8\nThe Commission made clear, however, that it was not directing PJM to make any changes \nto its rules for Non-Retail BTMG.9 PJM’s February 23, 2026 compliance filing proposed \nnumerous Tariff changes in response to these directives, including, inter alia, the new \ndefined term “Retail Behind The Meter Generation.”10\nhas consented to such use of the distribution facilities and such consent has been \ndemonstrated to the satisfaction of the Office of the Interconnection); provided, \nhowever, that Behind The Meter Generation does not include (i) at any time, any \nportion of such generating unit’s capacity that is designated as a Generation \nCapacity Resource or DER Capacity Aggregation Resource; or (ii) in an hour, any \nportion of the output of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM Interchange Energy \nMarket. \nPJM Filing, Attachment A (proposed Tariff, Part I, section 1 (Definitions A – B). \n5  Non-Retail Behind the Meter Generation is defined in the Tariff as “Behind the Meter Generation that is \nused by municipal electric systems, electric cooperatives, or electric distribution companies to serve \nload.” Tariff, Part I, section 1 (Definitions L – M – N); see also PJM Filing, Attachment A, proposed Tariff, \nsection 34.3. \n6  193 FERC ¶ 61,217. \n7\nSee id. PP 179, 186. \n8\nId. PP 186, 221-224. Specifically, the Commission directed PJM to “propose a new [megawatt] threshold \nfor the amount of load at a particular electrical location that Network Customers may net by using \nBTMG.” Id. P 221. Recognizing that customers may have relied on the existing BTMG rules, however, \nthe Commission required PJM to maintain the current BTMG rules for customers that fall below the new \nmegawatt threshold level. See id. P 179. The Commission also adopted a transition process for “retail \nBTMG,” including a three-year transition period and grandfathering of certain parties with existing \ncontracts. See id. \n9\nSee id. P 222.  \n10  PJM proposed defining Retail Behind The Meter Generation as: “Behind The Meter Generation that is \nused to serve a retail load served by a Network Customer located at the same electrical location (not \nincluding back-up generation at the same electrical location as the retail load that can only be used to"},{"page":3,"startToken":772,"endToken":1048,"text":"3 \nIn the June 18 Order, the Commission set aside the December 18 Order, in part, \nconcluding that “the Tariff is unjust and unreasonable because it does not include \ntransmission services that reflect that Eligible Customers taking transmission service on \nbehalf of load with BTMG are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.”11 The Commission indicated that it would \nbe unjust and unreasonable to require Eligible Customers taking transmission service on \nbehalf of load with BTMG to take Network Integration Transmission Service (“NITS”), \nwithout the option to instead take the alternative transmission services that FERC \nadopted in the December 18 Order for Eligible Customers taking transmission service on \nbehalf of Co-Located Load.12\nTo address these concerns, the Commission introduced the term “Eligible Load,” \nand specified that the term “refer[s] to Co-Located Load and/or load with BTMG.”13 The \nCommission directed PJM to file “a definition for Eligible Load, or other comparable Tariff \nrevisions to implement” FERC’s directives.14 Further, the Commission specified that PJM \nmust “revise its definition of BTMG to allow Eligible Customers taking transmission \nservice on behalf of load with BTMG that are willing and able to limit their energy \nwithdrawals from the transmission system under certain conditions to take the new \ntransmission services, consistent with this order.”15\nserve such retail load during conditions that may threaten the integrity or reliability of the PJM Region \nor the regional power system).” PJM Filing, Attachment A (proposed Tariff, Part I, section 1 (Definitions \nR – S). \n11  June 18 Order at P 91. \n12 See id. \n13 Id. (footnotes omitted).  \n14 Id. \n15 Id."},{"page":4,"startToken":1048,"endToken":1325,"text":"4 \nIn response to these directives, PJM proposes to amend the Tariff to add Eligible \nLoad as a defined term.16 PJM also proposes to add the term “Eligible Generating \nFacility,” which PJM says would “encompass both a Co-Located Generating Facility or \nRetail BTMG.”17 Further, PJM offers a number of other conforming changes to the Tariff \nto reflect the adoption of these new definitions.18\nAMP supports the Commission’s decision to extend eligibility for the new \ntransmission services to Eligible Customers taking transmission service on behalf of load \nwith BTMG. AMP is concerned, however, that PJM’s proposed Tariff provisions – \nparticularly the proposed definition of “Eligible Generating Facility” and related conforming \nchanges could limit eligibility for the new transmission services in contravention of the \nCommission’s June 18 Order. \nII. \nPROTEST \nA. \nThe Commission should direct PJM to revise the proposed definition \nof Eligible Generating Facility because it could exclude otherwise \neligible Non-Retail BTMG from taking new transmission services. \nThe PJM Filing proposes to define Eligible Load as “Co-Located Load or load \nconnected to Behind the Meter Generation.”19 This definition appears to comply with the \nCommission’s directives in the June 18 Order inasmuch as it would encompass all “load \n16 See PJM Filing, Transmittal Letter at 13 (citing proposed Tariff, Part I, section 1 (Definitions E - F)).  \n17 Id.\n18 See id. at 13-14. Separately, the PJM Filing removes PJM’s proposed changes to the definition of Non-\nRetail BTMG that the Commission rejected in the June 18 Order. See June 18 Order at P 314; see also \nPJM Filing, Transmittal Letter at 22. \n19  PJM Filing, Attachment A, proposed Tariff, Part I, section 1 (Definitions E - F)."},{"page":5,"startToken":1325,"endToken":1616,"text":"5 \nwith BTMG,”20 because the Tariff defines BTMG to include both Retail and Non-Retail \nBTMG.21\nPJM’s proposed definition of Eligible Generating Facility, however, excludes \ngenerators serving as Non-Retail BTMG: “‘Eligible Generating Facility’ shall mean a Co-\nLocated Generating Facility or Retail Behind the Meter Generation.”22 PJM’s Transmittal \nLetter does not explain why an Eligible Generating Facility is defined only with reference \nto Retail BTMG, rather than to all BTMG (including Non-Retail BTMG), or how such a \nlimitation complies with the directives in the June 18 Order. The Commission was clear \nthat the new transmission services should be available to “Eligible Customers taking \ntransmission service on behalf of load with BTMG.”23 The Commission did not distinguish \nbetween Retail and Non-Retail BTMG, and specifically cited to the general definition of \nBTMG in the Tariff.24 Indeed, the Commission did not require PJM to adopt a definition of \nEligible Generating Facility at all; it directed PJM “to revise its definition of BTMG to allow \nEligible Customers taking transmission service on behalf of load with BTMG” to take the \nnew transmission services.25 Even if PJM had the latitude to add a new definition for \n20 See June 18 Order at P 91. \n21 See Tariff, Part I, section 1 (Definitions A - B) (specifying in part that “‘Behind The Meter Generation’ \nshall mean either Retail Behind the Meter Generation or Non-Retail Behind The Meter Generation . . .”); \nsee also supra note 4. \n22  PJM Filing, Attachment A, proposed Tariff, Part I, section 1 (Definitions E - F) (emphasis added). \n23  June 18 Order at P 91.  \n24 See id. P 91 n.217 (cross-referencing footnote 4 of the June 18 Order which quoted the general definition \nof BTMG). \n25 Id. P 91 (emphasis added)."},{"page":6,"startToken":1616,"endToken":1956,"text":"6 \nEligible Generating Facility in its compliance filing,26 PJM has not adequately explained \nwhy the term excludes Non-Retail BTMG.  \nAs noted above, AMP and AMP’s load-serving utility members own and operate \ngenerating units in the PJM region that qualify as Non-Retail BTMG. It is not clear – and \nPJM does not explain – why such units should be categorically excluded from taking \nadvantage of the benefits that may be available to co-located generation (subject to the \nassociated requirements), which appears to be the result under PJM’s proposal. \nAMP recognizes that an Eligible Customer taking service on behalf of load with \nNon-Retail BTMG may have little incentive to utilize one of the three new types of \ntransmission service to the extent that all or a portion of a municipal, cooperative, or \nelectric distribution company generator is engaged in netting under the existing Non-\nRetail BTMG Tariff provisions. There may be circumstances, however, in which a \ngenerating facility that qualifies as Non-Retail BTMG might wish to utilize one of the new \ntransmission services. For example, section 34.3 of the PJM Tariff caps the total amount \nof Non-Retail BTMG in the PJM Region eligible for netting in any specific year, and sets \na maximum ceiling of 3,000 MW (unless increased through a section 205 filing).27 If and \nwhen the netting cap is reached, there may be a greater incentive for generators that \nqualify as Non-Retail BTMG to consider one of the new transmission services. Excluding \nNon-Retail BTMG from this opportunity would frustrate the Commission’s objective of \nmaking the new transmission service options available to load with BTMG.28\n26 See, e.g., PJM Interconnection, L.L.C., 173 FERC ¶ 61,244, at P 50 (2020) (explaining that \n“[c]ompliance filings must be limited to the specific directives ordered by the Commission,” and directing \nPJM to remove certain proposed Tariff provisions included in a compliance filing). \n27 See PJM Filing, Attachment A, proposed Tariff, section 34.3; see also December 18 Order at P 222. \n28  June 18 Order at P 91."},{"page":7,"startToken":1956,"endToken":2198,"text":"7 \nAssuming the Commission otherwise accepts PJM’s proposal to add a definition \nof Eligible Generating Facility, AMP proposes the following revised definition in lieu of \nPJM’s proposal to address the concerns described above: \n“Eligible Generating Facility” shall mean a Co-Located \nGenerating Facility or Retail Behind the Meter Generation. \nDirecting PJM to revise the definition of Eligible Generating Facility is well within \nthe Commission’s authority. PJM submitted its filing in this docket pursuant to section 206 \nof the Federal Power Act (“FPA”) for the purpose of establishing a just and reasonable \nreplacement rate given the Commission’s finding that certain aspects of the existing PJM \nTariff were unjust, unreasonable, and unduly discriminatory or preferential. The \nCommission has the obligation to fix the just and reasonable replacement rate,29 and it is \nnot restricted to accepting or rejecting PJM’s compliance proposal submitted under FPA \nsection 206.30\n29 See, e.g., 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. \n2017) (citation modified) (“When the Commission changes an existing filed rate under section 206, it is \nthe Commission’s burden to prove the reasonableness of its change in methodology.”). \n30 See, e.g., Bldg. for the Future Through Elec. Reg’l Transmission Planning and Cost Allocation, Order \nNo. 1920-B, 191 FERC ¶ 61,026, at PP 46-51 (2025) (rejecting arguments that compliance filings in a \nFPA section 206 proceeding implicate public utilities’ FPA section 205 filing rights)."},{"page":8,"startToken":2198,"endToken":2298,"text":"8 \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, American Municipal Power, Inc. \nrespectfully requests that the Commission direct PJM to revise its proposed definition of \nEligible Generating Facility as described herein. \nRespectfully submitted, \n/s/ John McCaffrey             \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com \nDATED: September 8, 2026 \n/s/ Gerit F. Hull                   \nLisa G. McAlister                                                  \nSenior Vice President & General Counsel  \nGerit F. Hull                                                          \nDeputy General Counsel for Regulatory Affairs   \nAmerican Municipal Power, Inc.                           \n1111 Schrock Road, Suite 100  \nColumbus, OH 43229                                     \n(614) 540-1111 \nlmcalister@amppartners.org \nghull@amppartners.org"},{"page":9,"startToken":2298,"endToken":2362,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, D.C., this 8th day of September, 2026. \n/s/ John McCaffrey              \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":741,"startToken":0,"endToken":111},{"p":1,"at":741,"title":"I. BACKGROUND AND INTRODUCTION","method":"printed heading","endPage":4,"endAt":852,"startToken":111,"endToken":1176},{"p":4,"at":852,"title":"II. PROTEST","method":"printed heading","endPage":4,"endAt":866,"startToken":1176,"endToken":1178},{"p":4,"at":866,"title":"A. The Commission should direct PJM to revise the proposed definition","method":"printed heading","endPage":8,"endAt":3,"startToken":1178,"endToken":2199},{"p":8,"at":3,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2199,"endToken":2298},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":429,"startToken":2298,"endToken":2362}]}