{"document":{"slug":"rec-20260908-5340","title":"Comments and Protest of Midcontinent Independent System Operator Inc. in response to American Transmission Company LLC’s tariff filing","issued":"2026-09-08","accession":"20260908-5340","docket":"ER26-3531-000","group":"ATC large-load planning revisions (Attachment FF-ATCLLC)","filer":"Midcontinent Independent System Operator Inc.","kind":"protest","file":"sources/filings/text/20260908-5340_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5340","tier":"record","sha256":"3a3f1a71e476fb80c39f45146f570869ea28488de106a08a16da8f1696c179f5","pages":16,"tokens":4489,"emptyPages":[],"textThemes":["procedure","study","registry"]},"pages":[{"page":1,"startToken":0,"endToken":276,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nAmerican Transmission Company, LLC \n) \n) \n) \n \n \nDocket No. ER26-3531-000 \nCOMMENTS AND PROTEST OF THE  \nMIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC. \n \nThe Midcontinent Independent System Operator, Inc. (“MISO”) submits1 these comments \nand protest in response to the proposed revisions to Attachment FF-ATCLLC of MISO’s Open \nAccess Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) filed by MISO as \nthe Transmission Provider on behalf of American Transmission Company, LLC, by its corporate \nmanager, ATC Management Inc. (collectively, “ATC”).  MISO appreciates the steps taken by \nATC to expeditiously address the mandates of the Commission’s Order Instituting Proceeding \nUnder Section 206 of the Federal Power Act (“Show Cause Order”).2  MISO submits these \ncomments and protest because ATC proposes Tariff changes related to the interconnection and \noperation of large loads in the ATC footprint that conflict with MISO’s pending Interconnection \nReliability Requirements for Large Loads proposal (“IRR Proposal”).3  While MISO appreciates \nthat the sequence and timing of MISO and ATC’s filings may be the underlying cause of the \ndifferences in ATC’s proposal and MISO’s IRR Proposal, MISO is concerned that ATC’s \nproposal, if accepted, would establish a separate large load framework rather than complementing \n \n1  \nThis submission is made pursuant to Rules 211 and 212 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.211 and 385.212 (2026). \n2  \nMidcontinent Indep. System Op., Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”). \n3  \nLtr. To the Hon. Debbie-Anne Reese regarding the Midcontinent Independent System Operator, Inc.’s \nInterconnection Reliability Requirements for Large Loads, Docket No. ER26-3600 (Aug. 28, 2026)."},{"page":2,"startToken":276,"endToken":571,"text":"2 \na common MISO regional baseline consistent with ATC’s stated intent in its filing.4  Accordingly, \nMISO respectfully requests that the Commission direct ATC to revise Attachment FF-ATCLLC \neither to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with MISO’s large \nload rules and procedures, remove redundant processes, and explicitly provide that any \nrequirements imposed by Attachment FF-ATCLLC or ATC’s business practices on ATC Large \nLoad are additional to those applicable to Large Load under the MISO Tariff and that, in the event \nof a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as unjust, \nunreasonable, and unduly discriminatory for large loads taking Transmission Service under the \nMISO Tariff.  \nI. \nBACKGROUND \nMISO submits these comments and protest to resolve the mismatch in large load definitions \nand rules between MISO’s IRR Proposal and ATC’s proposed Tariff revisions.  This mismatch \ninvolves conflicting thresholds between the 100 MW large load threshold in ATC’s proposed \nTariff revisions and the 50 MW large load threshold in MISO’s pending IRR Proposal, separate \nstudy processes, and related downstream impacts.  This issue appears to be a matter of timing \nresulting from the time lag between the issuance of the Show Cause Order, MISO’s request to hold \nthose compliance directives in abeyance, ATC’s filing in this docket, and submission of MISO’s \nIRR Proposal.  \nThe Commission issued the Show Cause Order on June 18, 2026.5  The Show Cause Order \ndirected MISO and the Transmission Owners to either: (1) show cause as to why MISO’s Tariff \n \n4  \nLtr. To the Hon. Debbie-Anne Reese regarding the American Transmission Company LLC’s Proposed Revisions \nto Attachment FF-ATCLLC of the MISO Tariff in Response to Show Cause Order, Docket No. ER26-3531 (Aug. \n28, 2026) at p. 2. \n5  \nSee Show Cause Order."},{"page":3,"startToken":571,"endToken":899,"text":"3 \nremains just and reasonable without provisions addressing certain large load issues; or (2) explain \nwhat changes to the Tariff would address the Commission’s concerns, if the Commission were to \ndetermine that the Tariff has in fact become unjust and unreasonable.6  The Show Cause Order \nafforded MISO and the Transmission Owners 60 days to make their respective filing(s).7 \nOn August 3, 2026, MISO moved to hold all proceedings related to the Show Cause Order \nin abeyance for 90 days.8  The Abeyance Motion explained that MISO and the MISO Transmission \nOwners required additional time to continue the stakeholder process and submit FPA section 2059 \nfilings that address the concerns raised in the Show Cause Order.10  The Commission granted the \n90-day abeyance requested in the Abeyance Motion on August 14, 2026.11  ATC filed its proposed \nTariff revisions three days later, on August 17, 2026.  MISO, in turn, filed the IRR Proposal on \nAugust 28, 2026.  \nThe mismatch in large load definitions and rules is understandable when viewed against \nthis procedural backdrop.  At the time ATC filed its proposed Tariff revisions in this docket, the \nabeyance period had not expired, and MISO had yet to file its IRR Proposal and related large load \nthreshold.  MISO believes this outcome was unintentional; after all, ATC’s filing states that ATC’s \nproposal is intended to be “complementary to MISO’s future filings” and to “work together with \nMISO’s process ….”12  The ATC proposal, however, asks the Commission to act on separate a \n \n6  \nId. at P 3.  \n7  \nId. \n8  \nMotion of the Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners to Hold \nProceeding in Abeyance and Request for Shortened Comment Period and Expedited Treatment, Docket No. \nEL26-70-000 (Aug. 3, 2026) (“Abeyance Motion”).   \n9  \n16 U.S.C. § 824d.  \n10  Abeyance Motion at 2.  \n11  Midcontinent Independent System Operator, Inc., et. al., 196 FERC ¶ 61,133 (August 14, 2026) (“Abeyance \nOrder”). \n12  ATC Transmittal Letter at p. 2."},{"page":4,"startToken":899,"endToken":1180,"text":"4 \nseparate large load framework for ATC instead of supplementing a common MISO regional \nbaseline.  This raises practical and other challenges, including potential reliability impacts.  The \nappropriate solution in this instance is for the Commission to direct ATC to revise Attachment FF-\nATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or integrate with \nMISO’s large load rules and procedures, remove redundant processes, and explicitly provide that \nany requirements imposed by Attachment FF-ATCLLC or ATC’s business practices on ATC \nLarge Load are additional to those applicable to Large Load under the MISO Tariff and that, in \nthe event of a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as unjust, \nunreasonable, and unduly discriminatory for large loads taking Transmission Service under the \nMISO Tariff. \nII. \nCOMMENTS AND PROTEST \nA. \nATC’s Proposal Is Contrary to its Stated Goal of Complementing MISO’s \nLarge Load Framework. \n \nMISO appreciates that ATC’s goal is to provide a rule set that addresses concerns specific \nto large loads in the ATC footprint and that ATC intends for their proposal to complement MISO’s \nLarge Load filings.  As ATC stated at the outset of its filing: \nATC’s filing here is intended to establish requirements in its \nfootprint and be complementary to MISO’s future filings. As \ndescribed below, ATC’s proposed revisions to Attachment FF-\nATCLLC describe processes that are designed to work together with \nMISO’s process in the same way ATC’s local planning process in \nAttachment \nFF-ATCLLC \nworks \nwith \nthe \nannual \nMISO \nTransmission Expansion Plan (“MTEP”) process today. ATC also \nseeks approval for modifications to the local planning process that \nis utilized today in ATC’s footprint.13 \n \n \n13  ATC Transmittal Letter, at p. 2."},{"page":5,"startToken":1180,"endToken":1539,"text":"5 \nMISO supports ATC’s stated goal and has long acknowledged the importance of allowing its \nTransmission Owners to establish additional or supplemental requirements in its footprint that \nwork together with MISO’s Tariff rules.  Unfortunately, ATC’s proposed Tariff revisions may \nfrustrate this goal and lead to unjust or unexpected outcomes for Large Load connecting to the \nMISO Transmission System.  This is because ATC’s proposed Tariff revisions create a different \nprocess with requirements that supersede MISO’s Large Load and Computational Load definitions \nand baseline reliability requirements for loads in the ATC footprint.   \nProposed Section V.F provides that “ATCLLC Local Planning Criteria and requirements \nestablished by ATCLLC’s Business Practices, as described herein, shall govern in ATCLLC’s \nfootprint.”14  Taken together, these provisions create an entirely different rule set for large loads \nconnecting to ATC’s transmission facilities—which are part of the MISO Transmission System \nand take Transmission Service pursuant to MISO’s Tariff—and purport to make the definitions, \nrequirements, and studies that are or will be required by MISO’s Tariff for large loads inapplicable \nin the ATC footprint.  If the large load connects to the Transmission System through distribution \nfacilities, including those built to support a large load, then ATC further proposes that its own cost \nallocation, study processes, readiness requirements, and forms of agreement will govern and that \nthe requests for such interconnections will be processed by ATC rather than by MISO.15  Given \n \n14  Proposed Revisions to Attachment FF-ATCLLC at Section V.F.  These include: (1) Steady State Criteria \n(including steady state voltage criteria); (2) Dynamic Stability Assessments; (3)  Resource Facility Requirements \n(including Voltage, Reactive Power, and Power Factor Control); (4) ATC Large Load Interconnection \nRequirements  (including Active Power Oscillations, Ramp Rate Limits, Voltage Ride Through, Load Power \nFactor)l and; (5) Large Load data monitoring, data retention, forecasting, and design criteria.  See, Proposed \nRevisions to Attachment FF-ATCLLC at Section V.E \n15  Proposed Revisions to Attachment FF-ATCLLC at Sections VI.A.1-VI.A12. Because ATC proposes to include \nmany details of its rules in its business practice manuals, there is also a risk that new conflicts between ATC’s \nand MISO’s rules could arise as the rule sets develop."},{"page":6,"startToken":1539,"endToken":1922,"text":"6 \nthe broad sweep of these proposed rules, it is unclear what parts of MISO’s Large Load rules will \nstill apply in ATC’s footprint and how conflicting requirements can be reconciled. \n \nMISO does not object to ATC developing supplemental rules and procedures needed to \nimplement the rules contained in MISO’s Tariff in ATC’s footprint or to supplement MISO’s \nTariff rules for Large Loads to the extent that ATC needs to impose additional reliability or \noperations requirements on ATC Large Load.  MISO welcomes ATC’s feedback on whether \nadjustments or additional flexibility is needed for individual requirements either included in the \nIRR Proposal or currently being developed in the Large Load Federal Power Act Section 205 \nfilings described in MISO’s Abeyance Request.  However, MISO is concerned that even with \nATC’s good intentions to develop complementary processes, the proposed Tariff language \ndescribes an entirely separate rule set and creates a high risk of discordant rates, terms, and \nconditions for Transmission Service under the MISO Tariff for ATC Large Loads as opposed to \nthose connecting to other parts of the MISO Transmission System.16  \nB. \nATC’s Proposal Is Impractical Because It Would Require ATC to Integrate \nATC-Specific Requirements with MISO’s Broader Process. \n \ni. \nA uniform Large Load framework for the MISO Transmission \nSystem is necessary to establish a common regional reliability \nbaseline. \n \nMISO’s Large Load reliability framework submitted in the IRR Proposal includes \ndefinitions, basic facility data, modeling, telemetry, forecasting, Phasor Measurement Unit (PMU), \n \n16  A similar concern applies to ATC proposal to maintain its own study process—the Generating Facilities \nModification Notification (“GFMN”) Process separate from MISO’s Interconnection Procedures. See, ATC \nTransmittal Letter at p. 18.  As defined in ATC’s Tariff sheets, this process covers “modifications, retirements, \nsuspensions, testing results, model updates, or other changes associated with a generating facility.”  See, Proposed \nRevisions to Attachment FF-ATCLLC at Section IV (Definitions)—Generating Facility Modification \nNotification.  Unlike the Large Load provisions, ATC’s GFMN revisions do indicate that customers may also be \nsubject to study processes under the Transmission Provider’s Tariff.  However, this still requires customers to \nundergo two separate study processes and it is not clear how conflicts would be resolved if ATC’s GFMN process \nreaches different conclusions regarding permissible changes or assigns different costs than those identified \nthrough MISO’s generating facility retirement, replacement, or material modification rules."},{"page":7,"startToken":1922,"endToken":2219,"text":"7 \nramp and ride-through requirements, as well as distinguishes Large Loads and Computational \nLoads with targeted requirements reflecting their specific reliability risks.  This is intended to \nprovide a common regional reliability baseline and rule set that facilitates comparable treatment \nfor Large Loads seeking to connect to all parts of the MISO Transmission System.  This uniformity \nboth promotes fairness and will better expedite the development of large loads by promoting \ncommercial certainty to Large Loads. \nPermitting ATC to implement different large load thresholds and accompanying rules for \nlarge loads interconnecting within the ATC footprint versus those interconnecting in the rest of the \nMISO region will create confusion and divergent reliability requirements within the MISO region.  \nUltimately, accepting ATC’s proposal as filed would fragment the MISO region and create an \nunlevel playing field for similarly situated loads seeking to interconnect to the MISO Transmission \nSystem as ATC’s proposed revisions to Attachment FF-ATCLLC extend beyond establishing local \nplanning criteria resulting in disparate operational and economic treatment of loads interconnected \nto the MISO Transmission System.  ATC would impose a lower burden on Computational Loads, \nwhich—together with the higher threshold for load classification as a large load, could result in \nthose loads realizing lower compliance costs than Large Loads in the rest of the MISO region by \navoiding reliability requirements. \nii. \nGranting ATC’s requested relief would create reliability \ncoverage gaps. \n \nLarge Loads could face a reliability coverage gap if ATC’s Large Load framework \nreplaces, rather than supplements, MISO’s framework.  As noted, MISO defines Large Loads by \napplying a 50 MW threshold, whereas ATC Large Load applies a 100 MW threshold.  As such, \nLoads ranging from 50 MW to 100 MW in ATC’s footprint would be excluded from requirements \napplicable to comparable loads elsewhere in MISO.  This gap has significant  downstream impacts."},{"page":8,"startToken":2219,"endToken":2479,"text":"8 \nMISO’s IRR Proposal explains that the 50 MW threshold defining Large Load is based on \nindustry precedent and the need for a clear and administratively workable means of identifying \nsignificant, concentrated loads that warrant additional reliability visibility.17  A load of 50 MW is \nsufficiently large that its characteristics and behavior can be relevant to transmission planning and \nsystem operations.18  Because Large Loads above 50 MW increasingly exhibit dynamic operating \ncharacteristics and concentrated demand and utilize sophisticated power-electronic equipment and \ncontrols, additional facility information, telemetry, and modeling detail may be necessary to \nevaluate reliability impacts under both normal and contingency conditions.19  The data and \nmodeling requirements in the IRR Proposal are intended to support reliable operation of the entire \nMISO Transmission System by improving the accuracy of planning assumptions, strengthening \noperational awareness, supporting disturbance analysis and model validation, and enabling more \nconsistent evaluation of system performance associated with Large Load integration.20  As such, \nallowing ATC to apply the definition of ATC Large Load in the ATC footprint will have wide \nranging impacts on reliability, system planning and operational awareness.  \nATC’s proposed 100 MW Large Load threshold would exempt 50–99 MW facilities—\nincluding both traditional industrial loads and Computational Loads—from MISO’s day-ahead and \nreal-time forecasting requirements.  These forecasts are essential inputs to MISO’s Reliability \nAssessment Commitment (RAC), Security Constrained Economic Dispatch (SCED), Look-Ahead \nCommitment (LAC), and real-time dispatch processes. \n \n17  IRR Proposal, Testimony of B. Li, p. 12 (Aug. 28, 2026) (“Li Testimony”). \n18  Id. at p. 14. \n19  Id. at p. 24. \n20  Id."},{"page":9,"startToken":2479,"endToken":2825,"text":"9 \nIf ATC’s threshold replaces MISO’s 50 MW baseline in ATC’s footprint, a 75 MW load \nwould provide no Large Load forecast submissions.  Because this data is needed for real time \nprocesses, MISO needs the ability to require this information directly from the Large Load in real \ntime in order to anticipate demand swings, commit generation reliably, maintain reserve \nsufficiency, and manage real time system balance.  \nMISO’s concern does not end at the 100 MW threshold.  Because ATC proposes to \nsupersede MISO’s requirements, even a 100+ MW Large load connected through ATC \ntransmission facilities would still be excused from MISO’s requirements, including the \nrequirement to provide data to MISO in real time.21 \nIf the ATC Large Load definition is accepted, neither MISO’s nor ATC’s requirements \nwould apply to a 75 MW Computational Load.  This load source could fall outside MISO’s \ntargeted the Phasor Measurement Unit / high-resolution measurement requirements.  If an \noscillation occurs in the area with the 75 MW load, failure to apply large load data monitoring and \ncommunication rules would prevent MISO from performing the synchronized measurements \nneeded to determine whether the load is the source, contributing to the oscillation, or responding \nto it.  This makes source identification and mitigation more difficult, impacting Transmission \nSystem reliability. \nThis problem is compounded for Computational Loads.  MISO applies targeted modeling \nand PMU requirements to Computational Loads to address their distinct dynamic and oscillatory \nrisks.  ATC does not appear to establish an equivalent separate classification, potentially resulting \n \n21  Many of MISO’s Large Load rules focus on facilitating real-time visibility into how large loads are operating in \norder to gauge system-wide effects and potential responses. Even if ATC is correct that 100 MW is an appropriate \nthreshold for their facilities, the concern remains that their proposal would leave an ATC-shaped hole in MISO’s \nreal-time view of Large Loads on the MISO Transmission System. ATC may ultimately require reporting from \nthe large load to ATC.  But even good collaboration and data sharing between ATC and MISO cannot fully \nsubstitute for instantaneous communications directly between the large load and MISO’s systems."},{"page":10,"startToken":2825,"endToken":3159,"text":"10 \nin different requirements for similar loads based on where they interconnect.  This disconnect \nimposes challenges because Computational Loads often exhibit highly coordinated, rapid demand \nswings and power-electronic dynamics that can impact the entire MISO Transmission System.22  \nIf MISO cannot apply its Large Load data and visibility requirements and Computational Load \nclassification to loads connecting through ATC transmission facilities, this would further inhibit \nMISO’s ability to anticipate demand swings, commit generation reliably, maintain reserve \nsufficiency, and manage real time system balance to account for loads whose impact shifts \ndefinitionally can be sudden and significant given their size.  \nATC’s proposal raises broader reliability concerns that extend throughout the MISO \nregion.  Load loss, ride-through/recovery, and oscillatory behavior do not remain confined within \nATC’s footprint; they can affect frequency, voltage, nearby generation, and system stability across \nMISO.  ATC’s transmission facilities are part of the larger MISO Transmission System, and the \nelectrical impacts of discordant rules cannot be limited to just ATC’s facilities. \niii. \nImplementing ATC’s Proposal would Create Gaps and \nMisalignments with Downstream MISO Processes.  \n \nIn addition to different definitions, thresholds, and recipients of large load data, ATC \nproposes to formalize certain business practices “containing policies, practices, and requirements \ndirected specifically at large loads” that are identified on its website without a discussion of how \n \n22  MISO’s IRR Proposal includes a definition of Computational Load to distinguish a subset of Large Loads that \nmay exhibit operational characteristics different from more traditional loads, including rapid changes in demand, \nhighly coordinated control behavior, and power-electronic responses during system disturbances.  This distinction \nallows MISO to apply certain incremental requirements—such as ramp, PMU, and ride-through requirements—\nonly where those characteristics warrant additional reliability consideration to preserve reliable operations beyond \nthe ATC footprint. Events involving ramp and ride-through requirements can impact the entire MISO \nTransmission System. Defining Computational Load therefore supports a more targeted and risk-informed \napproach, rather than applying the same requirements to all Large Loads regardless of facility type or operating \nbehavior.  Li Testimony at p. 13."},{"page":11,"startToken":3159,"endToken":3551,"text":"11 \nthey will complement MISO’s business practices manuals.23  These include a form of application \nspecific to large loads connecting to the MISO Transmission System through ATC transmission \nfacilities, their own study procedures, and their own transmission service agreement. 24  Allowing \nthese separate processes creates disconnects with other downstream processes that MISO is \ncharged with implementing.   \nFor example, MISO is charged with providing Transmission Service under a single Tariff.25  \nAs the Commission acknowledged in the Show Cause Order, many of the rules and procedures \nneeded to accommodate large loads will be made applicable through transmission service \nprocesses imposing obligations on an Eligible Customer taking service to provide energy to the \nlarge load.26  MISO currently is developing revisions to Tariff rules governing transmission service \nprocesses and products responsive to the Show Cause Order through its Large Load 205 filings.  \nLeaving aside any fairness implications of granting the same transmission services to Eligible \nCustomers with divergent study and operational requirements, it is unclear from a practical and \nprocedural prospective, how these rules would be implemented if MISO is not the entity that \nreceives the application or operational assumptions that underlie transmission service options may \nnot apply to the large load.  MISO does not object to ATC’s implementation of large load \nrequirements in addition to the baseline established in MISO’s IRR Proposal e.g., if ATC were to \n \n23  ATC Transmittal Letter, at p. 5. \n24  ATC Transmittal Letter, at p. 14.  Transmission Owners Agreement, Appendix I, Section 7.1.  \n25  See Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent System Operator, \nInc.. (“Transmission Owners Agreement”) Appendix I, Section 7.1 (Service under the Tariff. Customers will \nreceive transmission service under a single Tariff which will apply to transmission service over the entire MISO \nRegion (including the ITC), subject to changes to the Tariff accepted by FERC that the ITC may propose pursuant \nto this Appendix I. Customers will apply for service on the MISO OASIS. MISO will execute the agreements \nwith the customers for service and studies. The ITC shall make all decisions on rate discounts for ITC-only \ntransactions.). \n26  Show Cause Order at PP 1(noting the distinction between large loads and Eligible Customers) and 13 (discussing \nthe “…need for clear and consistent tariff provisions regarding the provision of transmission service to Eligible \nCustomers on behalf of large loads”)."},{"page":12,"startToken":3551,"endToken":3888,"text":"12 \npropose to use the 100 MW load threshold as a trigger for additional requirements in its footprint, \nbut that is not the proposed Tariff languages does.  Rather the point is that a uniform baseline \nprocess is needed both to create space for complementary ATC-specific planning criteria and \nensure that any required processes appropriately connect with downstream MISO processes. \nC. \nGranting This Protest Is Consistent with ATC’s Stated Intent.  \n \nGranting this limited protest would align with ATC’s statements in its filing.  ATC states \nthat ATC’s proposal is intended to be “complementary to MISO’s future filings” and “designed to \nwork together with MISO’s process in the same way ATC’s local planning process in Attachment \nFF-ATCLLC works with the annual MISO Transmission Expansion Plan (“MTEP”) process \ntoday.”27  ATC’s proposed Tariff redlines, however, state that ATC requirements “shall govern” \nin its footprint and indicates ATC may selectively defer requirements to MISO.28  This provides \ntoo much uncertainty to Large Loads and results in inconsistent Large Load requirements.   \nMISO is willing to work with ATC to establish incremental criteria in the ATC region that \nwill complement MISO’s baseline reliability framework.  MISO also understands that ATC made \nits filing in response to the Show Cause Order, in advance of the submission of MISO’s IRR \nProposal, and without time to fully coordinate its proposed framework with MISO.  Now that both \nparties have filed their respective proposals, there is time for the parties to work together to address \nthe needs of the region while acknowledging that ATC may need to impose requirements on large \nloads that are in addition to the baseline reliability requirements established in the IRR Proposal. \nMISO is sensitive to the challenges that ATC faces in filing supplemental requirements \nthat are responsive to needs in the ATC footprint while aligning with MISO processes that are still \n \n27  ATC Transmittal Letter at p. 2.   \n28  ATC Tariff Redlines at p. 21 (“The ATCLLC Local Planning Criteria and requirements established by ATCLLC’s \nBusiness Practices, as described herein, shall govern in ATCLLC’s footprint.”)."},{"page":13,"startToken":3888,"endToken":4140,"text":"13 \nin development.  This is a difficult task and both MISO and ATC are working to develop new rules \non accelerated schedules.  To address this issue and better facilitate coordination, MISO suggests \nthat the Commission require ATC to make a future compliance filing no earlier than the date by \nwhich MISO will make its Large Load 205 filings---i.e., November 16, 2026, or the date on which \nthe Commission acts on MISO’s IRR filing, whichever is later.  Such a compliance period would \nalign MISO and ATC’s development schedules and allow ATC to see (and participate in \ndeveloping) the base rule set before it files supplemental requirements.  Such alignment will have \nlong term benefits for ATC and MISO’s large load customers by avoiding rule conflicts, process \nredundancies, or unduly disparate treatment of large loads. \nIII. \nCOMMUNICATIONS \nMISO requests waiver of Rule 203(b)(3)29 of the Commission’s Rules of Practice and \nProcedure to the extent necessary to permit the designation of more than two persons for service \non behalf of MISO in this proceeding and requests all communications related to this filing be \ndirected to: \nChristopher D. Supino \nManaging Senior Corporate Counsel \nMichael Kessler  \nManaging Assistant General Counsel \nMidcontinent Independent System  \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 249-5400 \ncsupino@misoenergy.org \nmkessler@misoenergy.org \n \nJames C. Holsclaw \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com  \n \n \n29  18 C.F.R. § 385.203(b)(3) (2026)."},{"page":14,"startToken":4140,"endToken":4369,"text":"14 \nIV. \nNOTICE AND SERVICE \nMISO has served a copy of this filing electronically, including attachments, upon each \nperson designated on the official service list compiled by the Secretary as well as on all Tariff \ncustomers, MISO Members, Member representatives of transmission owners and non-\ntransmission owners, as well as all state commissions within the MISO Region and the \nOrganization of MISO States.  The filing has been posted electronically on MISO’s website at \nhttps://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter. \nV. \nCONCLUSION \nWHEREFORE, MISO respectfully requests that the Commission direct ATC to revise \nAttachment FF-ATCLLC either to: (1) require ATC to submit revised Tariff sheets that adopt or \nintegrate with MISO’s large load rules and procedures, remove redundant processes, and explicitly \nprovide that any requirements imposed by Attachment FF-ATCLLC or ATC’s business practices \non ATC Large Load are additional to those applicable to Large Load under the MISO Tariff and \nthat, in the event of a conflict, the more restrictive rule governs; or (2) reject ATC’s proposal as \nunjust, unreasonable, and unduly discriminatory for large loads taking Transmission Service under \nthe MISO Tariff. \nRespectfully submitted, \n/s/ Christopher D. Supino \n \nChristopher D. Supino \nManaging Senior Corporate Counsel \nMichael Kessler  \nManaging Assistant General Counsel \nMidcontinent Independent System  \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 249-5400 \nmkessler@misoenergy.org \ncsupino@misoenergy.org"},{"page":15,"startToken":4369,"endToken":4404,"text":"15 \n \nJames C. Holsclaw \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com   \n \nAttorneys for the Midcontinent Independent \nSystem Operator, Inc. \n \n \nDATED: September 8, 2026"},{"page":16,"startToken":4404,"endToken":4489,"text":"16 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day e-served a copy of this document upon all parties listed \non the official service list compiled by the Secretary in the above-captioned proceeding, in \naccordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and \nProcedure (18 C.F.R. § 385.2010). \n \nDated this 8th day of September 2026, in Carmel, Indiana. \n/s/ Julie Bunn \nJulie Bunn  \nMidcontinent Independent  \nSystem Operator, Inc.  \n720 City Center Drive  \nCarmel, IN 46032  \n317-249-5400"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":770,"startToken":0,"endToken":392},{"p":2,"at":770,"title":"I. BACKGROUND","method":"printed heading","endPage":4,"endAt":875,"startToken":392,"endToken":1030},{"p":4,"at":875,"title":"II. COMMENTS AND PROTEST","method":"printed heading","endPage":4,"endAt":902,"startToken":1030,"endToken":1034},{"p":4,"at":902,"title":"A. ATC’s Proposal Is Contrary to its Stated Goal of Complementing MISO’s","method":"printed heading","endPage":6,"endAt":1171,"startToken":1034,"endToken":1719},{"p":6,"at":1171,"title":"B. ATC’s Proposal Is Impractical Because It Would Require ATC to Integrate","method":"printed heading","endPage":12,"endAt":386,"startToken":1719,"endToken":3610},{"p":12,"at":386,"title":"C. Granting This Protest Is Consistent with ATC’s Stated Intent.","method":"printed heading","endPage":13,"endAt":832,"startToken":3610,"endToken":4022},{"p":13,"at":832,"title":"III. COMMUNICATIONS","method":"printed heading","endPage":14,"endAt":4,"startToken":4022,"endToken":4141},{"p":14,"at":4,"title":"IV. NOTICE AND SERVICE","method":"printed heading","endPage":14,"endAt":569,"startToken":4141,"endToken":4226},{"p":14,"at":569,"title":"V. CONCLUSION","method":"printed heading","endPage":16,"endAt":4,"startToken":4226,"endToken":4405},{"p":16,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":538,"startToken":4405,"endToken":4489}]}