{"document":{"slug":"rec-20260908-5364","title":"Joint Comments and Limited Protest of PJM Industrial Customer Coalition et al. to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing","issued":"2026-09-08","accession":"20260908-5364","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"PJMICC, IECA, AF&PA, and Amtrak","kind":"protest","file":"sources/filings/text/20260908-5364_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260908-5364","tier":"record","sha256":"55b796953a1d1edfd459e95ab8afa0835eb0c1bc3621fcc499abd8c49c6cd033","pages":12,"tokens":3433,"emptyPages":[],"textThemes":["colo","retail","study"]},"pages":[{"page":1,"startToken":0,"endToken":250,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n)\n \n \nDocket No. ER26-1479-000 \n \n \n      ER26-1479-001 \n \nJOINT COMMENTS AND LIMITED PROTEST OF \nINDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK \nTO PJM INTERCONNECTION, L.L.C.’S AUGUST 17, 2026, COMPLIANCE FILING \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC” or \n“Commission”) Rules of Practice and Procedure1 and the Combined Notice of Filings #1 issued \non August 18, 2026,2 the PJM Industrial Customer Coalition (“PJMICC”), the Industrial Energy \nConsumers of America (“IECA”), the American Forest and Paper Association (“AF&PA”) \n(collectively, “Industrials”), and the National Railroad Passenger Corporation (“Amtrak”) hereby \nfile these Joint Comments and Limited Protest in response to PJM Interconnection, L.L.C.’s \n(“PJM”) Compliance Filing of PJM Interconnection, L.L.C. in Response to Order on Rehearing, \nClarification, Compliance Filing, and Paper Hearing in Docket Nos. EL25-49-002, et al. (“August \nCompliance Filing”), which was filed on August 17, 2026, in the above-captioned docket.3  \nI. \nSUMMARY \nAs demonstrated herein, the Commission should find that certain material components of \nthe August Compliance Filing are not compliant with the June 18, 2026, Order (“June Order”) \nissued in Docket No. EL25-49, because they do not clarify that retail customers with Retail \n \n1 18 C.F.R. § 385.211. \n2 Combined Notice of Filings #1, PJM Interconnection, L.L.C., Docket No. ER26-1479-000. \n3 On February 24, 2026, the Industrials separately intervened in the above-captioned docket. On March 11, 2026, \nAmtrak intervened in the above-captioned docket."},{"page":2,"startToken":250,"endToken":646,"text":"2 \n \nBehind-the-Meter Generation (“BTMG”) will remain designated as having BTMG as opposed to \nbeing classified as Co-Located Load more generally. This ambiguity is of particular concern for \nretail customers with three-party Interconnection Service Agreements (“ISA”) who, for reasons of \nhistory and regulation, may make a basic level of sales of excess power and capacity into PJM’s \nmarketplace pursuant to market-based rates. Under PJM’s proposed tariff language, there is \nambiguity as to the obligations and status of these retail customers. Additionally, because PJM is \nmaking its compliance filings in two steps (with the second step yet to be filed), it is unclear if \nPJM’s proposed language will create issues for retail customers with BTMG to remain \ngrandfathered with respect to PJM’s Retail BTMG netting rules if they or their contractual \ncounterparty also possess an ISA. The Industrials/Amtrak respectfully request that the \nCommission order PJM to correct these errors, consistent with the June Order, as set forth below. \nII. \nBACKGROUND \nIn response to the Commission’s Order4 issued on December 18, 2026, in Docket EL25-\n49, PJM filed a 60-Day Compliance Filing on February 23, 2026.5 After a significant number of \nresponsive pleadings, PJM and other parties to the above-captioned proceeding have continued to \naddress, at the FERC, many issues connected to BTMG in PJM.  \nIn its June Order, the Commission partially accepted and partially rejected the 60-Day \nCompliance Filing. The Commission ordered PJM to submit a new compliance filing within 60 \n \n4 On December 18, 2025, the Commission issued the December Order, finding that the PJM Tariff is unjust and \nunreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and \ndirecting PJM to make several compliance and informational filings. PJM Interconnection, L.L.C., Order on Show \nCause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting In Part and Denying In \nPart Complaint, 193 FERC ¶ 61,217 (Dec. 18, 2025) (“December Order”). The Order also addressed PJM’s Retail \nBehind-the-Meter Generation (“BTMG”) rules, finding that “circumstances have changed since the Commission \napproved PJM’s retail BTMG rules such that these rules are no longer just and reasonable.” Id. at P 186. \n5 See PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access \nTransmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-1479-000 \n(Feb. 23, 2026)."},{"page":3,"startToken":646,"endToken":997,"text":"3 \n \ndays of the June Order. On August 14, 2026, the Commission granted PJM approval for a 90-day \nextension of time to comply with certain directives from the June Order. On August 17, 2026, PJM \nmade the partial compliance filing that is the subject of these Joint Comments and Limited Protest.6 \nA fuller procedural history is set forth in PJM’s August Compliance Filing.  \nIII. \nTHE INDUSTRIALS & AMTRAK \nThe Industrials include associations of leading American manufacturing companies, trade-\nexposed electricity users, institutional users, and other energy-intensive customers. Many of these \nare manufacturers that are energy intensive, operate 24/7, are price sensitive, and compete globally.  \nIndustries represented by the Industrials include chemicals, plastics, steel, iron ore, aluminum, \npaper, food processing, fertilizer, insulation, glass, industrial gases, pharmaceuticals, building \nproducts, automotive, independent oil refining, and cement, among others. Many of the Industrials’ \nmembers have constructed, maintained, and operate substantial retail BTMG units that are \ndesigned for operational efficiency and are deeply integrated into their industrial processes, \nincluding some Qualifying Facilities (“QF”) under the Public Utility Regulatory Policies Act of \n1978 (“PURPA”), currently set forth at 16 U.S.C. §§ 2601, et seq. The Industrials also comprise \nother institutional and service customers, such as universities and hospitals, some of which also \noperate retail BTMG. \nAmtrak is a corporation authorized by the Rail Passenger Service Act of 1970, currently \nset forth at 49 U.S.C. §§ 24101, et seq. Amtrak provides passenger rail service across the \ncontinental United States, including within the PJM footprint. Amtrak consumes substantial \n \n6 On January 20, 2026, PJMICC and IECA jointly filed a Request For Clarification or, in the Alternative, Rehearing \nof the Industrial Customer Coalitions (“December Order Rehearing Request”), in Docket No. EL25-49-000 and the \nother Consolidated Dockets. On July 20, 2026, the Industrials and Amtrak jointly filed a Request For Rehearing and \nClarification of the Industrial Customers/Amtrak (“June Order Rehearing Request”). Nothing herein should be \nconstrued to modify either Rehearing Request. The Requestors and the Industrials/Amtrak reserve their rights to \nsupplement or modify these Joint Comments and Limited Protest in response to any order on rehearing."},{"page":4,"startToken":997,"endToken":1311,"text":"4 \n \namounts of electricity in its operations and requires reliable electric service to support its \noperations.  For many years, Amtrak has harnessed retail BTMG within PJM to support its business \noperations and reliability imperatives. \nThe Industrials and Amtrak have, throughout this proceeding, continually sought to provide \nuseful information to PJM, PJM’s stakeholders, and the Commission about the unique \nconfigurations of industrial and institutional BTMG.7 Without this information, there is a danger \nthat new tariff language will be approved that has minimal effect on many users, yet is devastating \nto retail customers whose operations are deeply integrated with their BTMG and who, in some \ncases, rely on BTMG to remain economically viable. The Commission has acknowledged this \ncompelling interest by grandfathering existing contractual arrangements that reflect retail BTMG \nnetting. To ensure the Commission’s acknowledgement is effectuated, the Industrials and Amtrak \naddress a new concern raised by PJM’s August Compliance Filing. \nIV. \nCOMMENTS & LIMITED PROTEST \nThe Industrials and Amtrak write to direct the Commission’s attention to a key concern in \nthe August Compliance Filing—namely, that PJM’s proposed Tariff language creates potential \nambiguity for the Retail BTMG status of retail customers who obtained an ISA and may make \nlimited wholesale power sales. Similarly, there are existing long-standing commercial \narrangements with existing wholesale generators by which retail customers receive electricity \nservice that should qualify for grandfathered treatment, in compliance with the June Order. \n \n7 These traditional loads differ from most of today’s large-load entrants in both size and type. These traditional load \nconfigurations are neither the essential cause of the current changed circumstances on the grid, nor do they present the \nreliability risks posed by super-sized, inverter-based loads rapidly seeking to come online today. See Dauphinais \nAffidavit at PP 22-26, 32, 50, 65-69. The planning of new AI data centers, with speed-to-power demands, is also \ndistinct from more long-term, drawn-out planning by manufacturers examining facility additions."},{"page":5,"startToken":1311,"endToken":1651,"text":"5 \n \nHowever, because PJM is completing its compliance obligations in two steps, it is unclear what \nimpact PJM’s proposed language will have on grandfathering treatment. \nTo avoid confusion, PJM’s proposed Tariff language should clarify that: the mere existence \nof an ISA (1) does not foreclose a cogeneration QF or any grandfathered arrangements from being \nable to qualify for retail netting, (2) does not remove such QF or grandfathered arrangement from \n“Retail BTMG” status, and (3) does not obligate such QF or grandfathered arrangement to \ncomplete Necessary Studies or other studies simply to continue existing BTMG operations. \nUnfortunately, the current drafting allows for ambiguity, which could have massive implications \nfor several large PJM-region manufacturers or transportation companies if the language were to \nbe approved as proposed. \nBy way of background, the primary proposed definitions in the August Compliance Filing \nthat are relevant to this issue are as follows:  \n Co-Located Generating Facility: “Co-Located Generating Facility” shall mean \nan existing Customer Facility that is physically connected to a Co-Located Load. \nAny Interconnection Customer with an effective Interconnection Service \nAgreement that plans to use a Customer Facility to serve Co-Located Load must \nprovide Transmission Provider and Interconnected Transmission Owner with \nadvance written notice to begin the Necessary Studies process provided in ISA, \nAppendix 2, section 3.1 and Tariff, Part VIII, Subpart A, section 401(H)(3)(b). \n \n Co-Located Load: “Co-Located Load” shall mean a configuration that refers to \nend-use customer load that is physically connected to the facilities of an existing or \nplanned Customer Facility8 on the Interconnection Customer’s side of the Point of \nInterconnection to the Transmission Provider’s Transmission System. \n \n Eligible Load: “Eligible Load” shall mean Co-Located Load or load connected to \nBehind the Meter Generation. \n \n Eligible Generating Facility: “Eligible Generating Facility” shall mean a Co-\nLocated Generating Facility or Retail Behind the Meter Generation. \n \n8 Customer Facility is defined in the PJM Tariff as: “‘Customer Facility’ shall mean Generation Facilities or Merchant \nTransmission Facilities interconnected with or added to the Transmission System pursuant to an Interconnection \nRequest under Tariff, Part IV.”"},{"page":6,"startToken":1651,"endToken":2053,"text":"6 \n \n \n Retail Behind the Meter Generation (BTMG): “Retail Behind The Meter \nGeneration” shall refer to Behind The Meter Generation that is used to serve a retail \nload served by a Network Customer located at the same electrical location (not \nincluding back-up generation at the same electrical location as the retail load that \ncan only be used to serve such retail load during conditions that may threaten the \nintegrity or reliability of the PJM Region or the regional power system). \n \nA central concern is that PJM’s proposed language could create some interpretative \nambiguity as to the Retail BTMG status of certain facilities. The term Co-Located Load, at least \nin some cases, could be interpreted as applying to Retail BTMG facilities as well—particularly in \nthe situations (1) where the Retail BTMG is a QF that makes wholesale sales of excess generation, \nor (2) where there are commercial arrangements that otherwise would qualify for grandfathering.  \nThis issue often arises in the context of cogeneration QFs (explained more fully in the \nDauphinais Affidavit filed in this docket).9 Cogeneration facilities are highly efficient facilities \nthat produce both electricity and heat from the same fuel source, making use of the “waste heat” \nin the manufacturing, heating, or cooling process.10 Many cogeneration QFs are sized to meet the \nmanufacturer’s thermal or steam needs at their facility (such as to provide heating, operate chillers, \nor make productive use of steam.) As stated in the Dauphinais Affidavit, \n[T]he thermal energy needs of the retail customer typically dictate how much \nelectric power must be produced by the Cogeneration Facility. For example, if an \nindustrial retail customer has a very high steam need for its processes relative to its \nelectrical needs, the Cogeneration Facility serving that customer will likely have to \nproduce electric power well in excess of that retail customer’s needs for its \nelectrical load.11 \n  \n \n9 For a fuller explanation of the unique issues facing cogeneration QFs and cogeneration facilities more generally, see \nJoint Protest and Comments of Industrial Customer Organizations and Amtrak, Docket No. ER26-1479-000 (Mar. 16, \n2026), Exhibit IA-1, Affidavit of James R. Dauphinais (“Dauphinais Affidavit”). \n10 Dauphinais Affidavit at P 11. As explained by Mr. Dauphinais, “Cogeneration Facilities can achieve efficiencies in \nexcess of 80%, by using waste heat and avoiding electrical losses, compared to the efficiency of approximately 50% \nfor conventional electricity generation with a steam boiler.” Id. \n11 Id. at P 15."},{"page":7,"startToken":2053,"endToken":2353,"text":"7 \n \nIn PJMICC’s experience, this situation often occurs with large manufacturing facilities that \nrequire substantial use of steam or other thermal output—particularly with chemical processes \nfound in paper products production, pharmaceutical manufacturing, and other related industries. \nThe sizing of cogeneration to meet thermal needs at the plant can result in production of more \nenergy than may be required to serve the manufacturer’s electricity requirements, resulting in \nexcess power. For example, a manufacturer in full production may require 60 MW of electric \npower consumption, but to produce sufficient steam for its industrial process, it may need its \ncogeneration facility to generate 70 MW of electric power. That excess 10 MW not needed by the \ncogeneration facility can then be sold to a third party. \nPURPA generally requires local utilities to purchase this excess energy (“must-purchase \nobligation”).12 However, the law permits the Commission to deem certain QFs as having sufficient \nmarket access that the applicable utility is excused from its must-purchase obligation.13 In these \ncases, where local utilities (who QFs would sell their excess power to by default) have been \nexcused from their must-purchase obligation, the retail customer has often obtained an ISA. The \nISA may be structured to allow the manufacturer to sell the excess energy and capacity to the PJM \nmarketplace.  \nThese small sales under an ISA, while conducted through PJM’s marketplace and \nstructures, are a secondary effect of utilities being excused from their must-purchase obligations. \nThey do not change the fundamental nature of the site and do not change the essential character of \nthe customer as retail. The facilities functioning in this way are first and foremost retail \ncustomers—they are manufacturers and/or institutional facilities providing goods and services, \n \n12 See 16 U.S.C. § 824a-3(a)(2). \n13 16 U.S.C § 824a-3(m)."},{"page":8,"startToken":2353,"endToken":2688,"text":"8 \n \ntypically generating power as the result of their industrial process, not as a primary function. \nConsequently, possession of an ISA does not (and should not) change the character of a location \nfrom a retail customer with BTMG to a Co-Location Arrangement. \nAdditionally, there are retail customers with BTMG that are not QFs but who have existing \ncontracts to sell excess power to third parties for historic and operational reasons. Pursuant to the \nJune Order, these contracts should qualify such BTMG units for grandfathered treatment, \nconsistent with “the directive to revise its Tariff to grandfather entities with existing contracts that \neffectuate a BTMG arrangement for the current term remaining under the existing contract.”14 \nAmtrak, a retail customer, has a contractual arrangement for retail BTMG to support its Northeast \nCorridor operations. As a legacy of the buildout of the Northeast Corridor, Amtrak requires service \nat 25 Hertz (“Hz”), which it receives, at least for some of its requirements, through a contractual \narrangement with a third-party generator that is neither a small power production QF nor a \ncogeneration QF. This arrangement provides the only black-start capability for Amtrak’s south \nend of its Northeast Corridor traction power system if the 60 Hz power grid goes out of service. \nUnfortunately, the language proposed by PJM in the August Compliance site creates \nadditional ambiguity by placing obligations based, in part on, the possession of an ISA, that could \nbe interpreted to apply to retail BTMG customers such as those described above. Yet, possession \nof an ISA should not, without more, limit the ability of retail customers with cogeneration facilities \nto avail themselves of retail BTMG netting for energy production behind the retail meter; nor \nshould it limit the ability of retail customers with other configurations to be eligible for \ngrandfathering. Namely, making basic sales of power into the PJM wholesale marketplace should \n \n14 June Order at P 233. The Commission approved PJM’s grandfathering approach in its 60-Day Compliance Filing, \nwhich was drafted broadly in favor of grandfathering existing contracts."},{"page":9,"startToken":2688,"endToken":3110,"text":"9 \n \nnot result in Retail BTMG facilities: (1) being classified into a non-Retail BTMG (Co-Location \nArrangement) status, (2) losing access to Retail BTMG netting when taking Network Integration \nTransmission Service (“NITS”) or purchasing capacity; or (3) being subject to additional \nrequirements applicable to Co-Located Generating Facilities, such as undergoing a Necessary \nStudy process.15  \nThe FERC reviews compliance filings for whether the public utility has complied with the \nrequirements of the underlying order.16 Consequently, the principles that should guide the ultimate \nselection of a Retail Threshold are set forth in the December Order and June Order themselves. In \nthese Orders, the FERC has been clear about its intent to allow retail electric customers with NITS \nto continue to benefit from netting (for NITS and Capacity purposes) up to 50 MW of load. The \nCommission has also been clear about its endorsement of broad grandfathering rules for existing \n \n15 For example, the August Compliance Filing proposes the following language:  \nAny Interconnection Customer or Generation Project Developer with an effective interconnection \nService Agreement or Generation Interconnection Agreement that plans to use an existing Customer \nFacility or Generating Facility to serve Eligible Load must provide Transmission Provider and \nTransmission Owner with advance written notice to begin the Necessary Studies process provided \nin Tariff, Part VIII, Subpart A, section 401(H)(3)(b). An Interconnection Customer or Generation \nProject Developer with an effective Interconnection Service Agreement or Generation \nInterconnection Agreement is prohibited from serving Eligible Load from its Customer Facility or \nGenerating Facility until all the complete scope of work required in their Interconnection Service \nAgreement or Generation Interconnection Agreement, as revised following the Necessary Studies, \nis completed. \nAugust Compliance Filing, Attachment A. Additionally, the August Compliance Filing states: \nAn Interconnection Customer or Generation Project Developer with an Interconnection Service \nAgreement or Generation Interconnection Agreement effective prior to December 18, 2025 that \nserves or plans to serve Co-Located Load with the Customer Facility or Generating Facility subject \nto such agreement must submit electronically through PJM’s website in accordance with PJM’s \nManuals notice of that fact and the identity of the Eligible Customer that will take transmission \nservice on behalf of that Co-Located Load. Transmission Provider will post the information \nconcerning the Co-Located Load and Eligible Customer on its website. \nAugust Compliance Filing, Attachment A. \n16 See, e.g., Southwest Power Pool, Inc., Order on Compliance, 194 FERC ¶ 61,047 at P 1, available at \nhttps://www.spp.org/documents/75765/20260122_order_order%20nos.%202023%20and%202023-\na%20second%20compliance%20filing_er24-2026-001%2C%20002.pdf."},{"page":10,"startToken":3110,"endToken":3268,"text":"10 \n \ncontracts.17 It is critically important that large retail customers who rely on this not be excluded on \na technicality. While Retail BTMG customers are (pursuant to the June Order) able to access the \nnew transmission services, simply having that right does not make them Co-Location \nArrangements. The Commission’s directed treatment of Retail BTMG customers remains intact, \nand PJM’s compliance obligations are to remain within those directives. \nBottom line, it is imperative that Retail BTMG customers not be at risk of losing BTMG \nstatus because of having active ISAs, which were essentially a necessity because of the \nabandonment of the must-purchase obligation by utilities; nor should it threaten the grandfathered \nstatus of existing contracts (including ISAs) between retail customers and existing generators. The \nIndustrials and Amtrak respectfully request that the Commission require PJM to modify its \nproposed tariff language accordingly. \n \n \n \n17 See, e.g., June Order at PP 137, 145, 233; December Order at P 179, 224."},{"page":11,"startToken":3268,"endToken":3372,"text":"11 \n \nV. \nCONCLUSION & REQUEST FOR RELIEF \nThe Industrials and Amtrak respectfully request that the Commission direct PJM to modify \nits August Compliance Filing, consistent with the Industrials and Amtrak’s Joint Comments and \nLimited Protest. \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition, \nthe Industrial Energy Consumers of America, the \nAmerican Forest and Paper Association, and the \nNational Railroad Passenger Corporation (Amtrak) \n \nDated:  September 8, 2026"},{"page":12,"startToken":3372,"endToken":3433,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via electronic transmission the foregoing upon \neach person designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 8th day of September, 2026.  \n \n \n     /s/ Matthew L. Garber \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nFax:  717-237-5433 \nE-mail: mgarber@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1159,"startToken":0,"endToken":162},{"p":1,"at":1159,"title":"I. SUMMARY","method":"printed heading","endPage":2,"endAt":1044,"startToken":162,"endToken":407},{"p":2,"at":1044,"title":"II. BACKGROUND","method":"printed heading","endPage":3,"endAt":377,"startToken":407,"endToken":710},{"p":3,"at":377,"title":"III. THE INDUSTRIALS & AMTRAK","method":"printed heading","endPage":4,"endAt":1057,"startToken":710,"endToken":1147},{"p":4,"at":1057,"title":"IV. COMMENTS & LIMITED PROTEST","method":"printed heading","endPage":11,"endAt":6,"startToken":1147,"endToken":3269},{"p":11,"at":6,"title":"V. CONCLUSION & REQUEST FOR RELIEF","method":"printed heading","endPage":12,"endAt":0,"startToken":3269,"endToken":3372},{"p":12,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":12,"endAt":422,"startToken":3372,"endToken":3433}]}