{"document":{"slug":"rec-20260911-5298","title":"Motion for Leave to File Comments Out-of-Time and Comments of CyrusOne, LP on the proposal of PJM Interconnection, L.L.C. to Establish Interim Resource…","issued":"2026-09-11","accession":"20260911-5298","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"CyrusOne LP","kind":"comments","file":"sources/filings/text/20260911-5298_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260911-5298","tier":"record","sha256":"d497a424eb9092cd430b14b4866bc9a63847be4d9310afcf748f17f3b0e3b372","pages":11,"tokens":2793,"emptyPages":[],"textThemes":["registry","retail"]},"pages":[{"page":1,"startToken":0,"endToken":286,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C.                                    )    \n \nDocket No. ER26-3515-000 \n \n \nMOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME AND \nCOMMENTS OF CYRUSONE, LP \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or the “Commission”)1, CyrusOne, LP (“CyrusOne”) \nrespectfully submits this motion for leave to file its comments out-of-time (the “Motion”), \ntogether with its accompanying comments, on the filing by PJM Interconnection, L.L.C. (“PJM”) \nto establish an Interim Resource Adequacy Service and a Large Load Registry, submitted on \nAugust 13, 2026 (the “IRAS Filing”). As grounds for the Motion, and in support of the \nComments, CyrusOne states as follows. \nI. MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME \nRule 214 authorizes the Commission to grant a late-filed motion to intervene, and the \nCommission has broad discretion under Rule 101(e) to waive or extend its procedural rules for \ngood cause where doing so serves the public interest and does not prejudice other parties.2 The \nCommission routinely accepts late-filed comments and protests in section 205 proceedings \nwhere acceptance would not disrupt the proceeding, would not prejudice other parties, and would \nassist the Commission in developing a complete and well-informed record.3  \n \n1 18 C.F.R. §§ 385.212, 385.213. \n2 18 C.F.R. §§ 385.214, 385.101(e). \n3 See, e.g., Southwest Power Pool, Inc., 193 FERC ¶ 61,244 at P 68 (2025) (accepting out-of-time comments); PJM \nInterconnection, L.L.C., et al., 190 FERC ¶ 61,115 at P 13 (2025) (accepting out-of-time comments and out-of-time \nprotest); PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 at P 83 (2024) (accepting out-of-time comments)."},{"page":2,"startToken":286,"endToken":556,"text":"2 \n \nGranting this Motion will not delay this proceeding or disrupt the Commission’s \nconsideration of the IRAS Filing. The Motion and the accompanying Comments are being filed \nonly a short time after the September 3, 2026 deadline due to administrative oversight, well in \nadvance of any Commission action on the IRAS Filing. Granting this Motion to submit \ncomments out of time will not disrupt these proceedings, prejudice existing parties, or create \nadditional burdens for existing parties. Acceptance of CyrusOne’s Comments will benefit the \nCommission by ensuring a more complete record. CyrusOne is a significant developer and \noperator of data center facilities within the PJM Region and, as such, brings a direct, practical \nperspective on the operational and commercial consequences of the IRAS Filing for New Large \nLoads, including with respect to the treatment of multi-phase data center campuses and the \ninteraction between the IRAS Filing’s proposed Large Load definitions and existing, previously \nnegotiated retail service arrangements.  \nFor these reasons, CyrusOne respectfully submits that good cause exists for the \nCommission to exercise its discretion under Rule 214 and Rule 101(e) to accept CyrusOne’s \nComments out-of-time. \nII. BACKGROUND \nCyrusOne has been developing data centers for over 25 years as a global developer, \nowner, and operator, including several multi-year, multi-phase campuses that may be subject to \nPJM’s Reliability Backstop Procurement (“RBP”) and IRAS proposals.  CyrusOne is a leading \nglobal data center developer and operator, providing mission-critical infrastructure for cloud \nproviders, enterprises, and hyperscale customers. CyrusOne’s leading global platform of hybrid-\ncloud and multi-cloud deployments offers customers colocation, hyperscale and build-to-suit \nenvironments, which help enhance the strategic connections of their essential data infrastructure"},{"page":3,"startToken":556,"endToken":832,"text":"3 \n \nand support the achievement of sustainability goals. CyrusOne’s operations rely on dependable, \nrobust, and economical electricity to support high-density computing environments that enable \ndigital transformation across industries.  CyrusOne is a signatory to the Ratepayer Protection \nPledge. \nCyrusOne frequently develops multiple, separately contracted facilities in phases over a \nperiod of years, at times including facilities located within close proximity to one another but \nbuilt for different customers, on different timelines, and under separate service arrangements. \nCyrusOne would be a “New Large Load” within the meaning of the IRAS Filing with respect to \nqualifying load, and its facilities and expansion plans would be directly affected by the proposed \nLarge Load and New Large Load definitions, the Large Load Registry, and the resulting IRAS \ncurtailment framework. CyrusOne has made significant investment and construction decisions in \nseveral states within PJM. Our existing sites should not be seen or classified as “new” and have \nundergone years of studies, development, long lead equipment purchases, and include tenant \ncontracts for capacity for years extending beyond 2026. Implementation of IRAS poses \nuncertainty and risk to projects that have been under development for several years. \nI. \nCOMMENTS OF CYRUSONE \nCyrusOne submits these Comments to identify and recommend specific, targeted changes \nto the IRAS Filing’s proposed tariff language that, as written, creates unnecessary uncertainty for \nNew Large Loads seeking to procure new capacity and comply with the proposed framework in \ngood faith. For example, while CyrusOne often develops our sites to include backup emergency \ngeneration, the intention is to use that resource for testing and emergency purposes only. It is \nCyrusOne’s position that these resources should be utilized in a manner consistent with state and"},{"page":4,"startToken":832,"endToken":1164,"text":"4 \n \nfederal laws. If the Commission accepts the IRAS Filing, CyrusOne respectfully requests that the \nCommission direct PJM to clarify or modify the provisions identified below. \nA. \nThe Definition of “Large Load” Should be Revised to Eliminate the One Mile \nRadius Requirement, or in the Alternative be Revised to Make a Rebuttable \nPresumption that Projects within a One-Mile Radius are Independent. \n \nThe IRAS Filing defines “Large Load” to mean end-use customer load with a cumulative \npeak load of 50 MW or greater at a single electrical site, and provides that, for configurations \ninvolving multiple affiliated load facilities or points of interconnection, all affiliated load \nfacilities within a one-mile radius will be considered a single electrical site.4 PJM states that this \none-mile radius rule is adapted from the Commission’s Qualifying Facility siting rules under \nOrder No. 872.5 \nCyrusOne is concerned that this rule, as proposed, does not account for the way data \ncenter campuses are actually developed and financed. CyrusOne, like other data center \ndevelopers, frequently constructs multiple, separately contracted facilities within a one-mile \nradius of one another and of existing operating facilities, on different timelines, for different \ncustomers, and under separate service and financing arrangements. Aggregating such facilities \ninto a single electrical site based on proximity alone, without regard to whether they are \ncommercially, contractually, or electrically independent, risks two specific consequences that \nCyrusOne believes the Commission did not intend. First, it could potentially cause an existing, \nalready-operational facility to become newly subject to IRAS curtailment risk solely because a \nlater, unrelated facility happens to be developed nearby, even though the existing facility’s \ncapacity needs were accounted for and arranged years earlier. Second, it could cause multiple \n \n4 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load. \n5 IRAS Filing at 33 & n.95 (citing Qualifying Facility Rates and Requirements Implementation Issues Under the \nPublic Utility Regulatory Policies Act of 1978, Order No. 872, 172 FERC ¶ 61,041, order on reh’g, Order No. 872-\nA, 173 FERC ¶ 61,158 (2020))."},{"page":5,"startToken":1164,"endToken":1476,"text":"5 \n \nfacilities that individually fall below the 50 MW Large Load threshold to be aggregated and \nthereby newly subjected to IRAS, based solely on their geographic proximity rather than any \nshared electrical or commercial relationship. \nCyrusOne’s concerns in this respect are consistent with, and reinforced by, the comments \nfiled by Equinix Inc. in this docket. Equinix has documented, through concrete examples from its \nown facilities in Northern Virginia’s Data Center Alley, that the same 100 megawatts of \nincremental load can be treated as 0 megawatts, 60 megawatts, or 100 megawatts of IRAS-\neligible load depending solely on how that load happens to be geographically distributed among \naffiliated facilities, with no relationship to the actual resource adequacy risk presented.6 Equinix \nhas requested that the Commission either eliminate the one-mile aggregation rule or, in the \nalternative, direct PJM to treat it as a rebuttable presumption, allowing an affected customer to \ndemonstrate that affiliated facilities are properly treated as separate electrical sites based on \nfactors such as separate service arrangements, separate points of interconnection, separate \nownership and control, development history, and electrical and operational independence.7 \nCyrusOne agrees that the one-mile aggregation rule should be eliminated. With respect to \nan alternative to elimination, CyrusOne believes that the presumption should be that the facilities \nwithin a one-mile radius are independent and not aggregated for purposes applying the Large \nLoad definition. Placing the burden on PJM, rather than on the affected customer, is the more \njust and reasonable allocation because PJM, not the customer, is the party proposing to depart \nfrom the ordinary rule that each electrical site is evaluated on its own. The one-mile radius rule \nwas not developed through the stakeholder process but was instead imported from the \n \n6 Protest, Request for Clarification and Comments of Equinix Inc., Docket No. ER26-3515-000 at 13-14 (Sept. 3, \n2026) (“Equinix Comments”). \n7 Equinix Comments at 3, 14."},{"page":6,"startToken":1476,"endToken":1772,"text":"6 \n \nCommission’s Qualifying Facility siting rules, which govern generation siting for an entirely \ndifferent purpose, and applied to data center campuses without any reasoned account of why data \ncenters, which cluster for latency, interconnection, and other commercial reasons entirely \nunrelated to energy, should be treated the same as generating facilities for aggregation \npurposes.   \nRequiring PJM to identify and prove those same facts as a threshold matter, before \naggregating facilities that would otherwise be treated as independent, ensures the rule is applied \nonly where PJM can affirmatively demonstrate that the facilities function as a single integrated \nsite, rather than sweeping in longstanding, independently developed campuses by default.  Such \na demonstration could include, for example, confirming the presence of a contract or utility \nagreement showing that the facilities share a common point of interconnection, common \nownership or control, or another arrangement establishing that the facilities are electrically or \ncontractually connected, rather than merely located near one another. For these reasons, \nCyrusOne’s preferred outcome is elimination of the one-mile aggregation rule altogether. Should \nthe Commission nonetheless decline to eliminate the rule, CyrusOne requests that the \nCommission direct PJM to adopt a rebuttable presumption that affiliated facilities within a one-\nmile radius are separate electrical sites, with PJM bearing the burden of demonstrating that \nspecific facilities are sufficiently integrated to warrant aggregation. \nB. \nIRAS Should Not Apply to Incremental Load Added Before June 1, 2027 or Load \nServed Under Pre-Existing Binding Retail Service Agreements. \nThe IRAS Filing defines “New Large Load” to include, among other things, incremental \nload in service after June 1, 2027 that increases existing end-use customer load at a site that did \nnot previously meet the Large Load definition.8 PJM’s transmittal letter indicates that the Large \n \n8 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load."},{"page":7,"startToken":1772,"endToken":2091,"text":"7 \n \nLoad Registry is intended to track the in-service date of each increment of load, together with a \nfacility’s peak load and ramp schedule, in order to determine which increments are properly \ntreated as New Large Load. CyrusOne notes that this June 1, 2027 cutoff does not operate in \nisolation from one-mile radius aggregation rule discussed above.  Because the one-mile \naggregation rule can cause otherwise independent, previously developed facilities to be \ncombined into a single electrical site, that aggregation can in turn cause a facility to newly cross \nthe Large Load threshold and subject unrelated, previously arranged load to New Large Load \ntreatment based on its in-service date. These two provisions are therefore problematic in \ncombination, and CyrusOne requests that the Commission consider and address their interaction \ntogether, not solely as separate issues.9 \nThe proposed tariff language does not clearly implement PJM’s stated intent for the \nLarge Load Registry to track in-service dates and ramp schedules to determine which increments \nare New Large Load. The New Large Load definition appears to capture only the specific \nincrement that causes a previously smaller site to first cross the 50 megawatt Large Load \nthreshold.  It does not clearly address subsequent increments at a site that already qualifies as a \nLarge Load.  It also does not state whether the resulting New Large Load designation applies \nonly to the qualifying increment or to the entire registered peak load of the site.10 This ambiguity \nis directly relevant to CyrusOne’s facilities, many of which will be coming into service over a \nmulti-year ramp that will continue after June 1, 2027, and are or will be energized in phases. To \nthe extent the Commission determines that multi-year, multi-phase existing projects such as \nCyrusOne's should nonetheless be included within the New Large Load definition, CyrusOne \n \n9 IRAS Filing at 36-45. \n10 IRAS Filing, Proposed Reliability Assurance Agreement, Definitions – Large Load; see also Equinix Comments \nat 8."},{"page":8,"startToken":2091,"endToken":2405,"text":"8 \n \nrequests that the Commission direct PJM to provide a reasonable transition mechanism for such \nprojects, such as a phase-in period or grandfathering of load increments tied to service \narrangements or construction commitments made before the IRAS Filing, to avoid disrupting \nprojects that have been under development for years in reliance on the pre-existing regulatory \nframework. \nCyrusOne accordingly requests that the Commission direct PJM to: (1) clarify that only \nthe incremental load added after June 1, 2027 that itself causes a site to newly cross the Large \nLoad threshold, or that is added at a site already so qualified, is treated as New Large Load, \nrather than the entirety of an existing facility’s registered peak load; and (2) exclude from the \nNew Large Load definition any load, including its contractual ramp, that is already covered by a \nbinding retail service agreement executed before the date of the IRAS Filing.11 Absent such \nclarification, New Large Loads like CyrusOne cannot determine with confidence the amount of \nBring Your Own New Capacity (“BYONC”) they would need to procure to avoid IRAS \nexposure, which undermines the very objective the IRAS Filing is intended to serve. \nC. \nPJM Should Further Explain the Basis for Excluding New Large Loads from \nthe VRR Curve Beginning with the 2029/2030 Delivery Year. \nThe IRAS Filing proposes, beginning with the 2029/2030 Delivery Year, to exclude New \nLarge Loads that lack sufficient BYONC or Allocated RBP Unforced Capacity (“UCAP”) \nmegawatts from the Variable Resource Requirement (“VRR”) Curve used in the Reliability \nPricing Model auctions, in order to protect existing customers from capacity price increases \nattributable to those loads.12 CyrusOne understands and does not dispute PJM’s stated ratepayer-\nprotection rationale for this exclusion. CyrusOne notes, however, that other commenters have \n \n11 This request is consistent with the relief requested by Equinix. See Equinix Comments at 3, 17. \n12 IRAS Filing at 5-6."},{"page":9,"startToken":2405,"endToken":2653,"text":"9 \n \nraised a related question that CyrusOne believes warrants further explanation: because the \nexclusion removes certain New Large Load demand from the auction, it may also reduce the \nprice signal that would otherwise encourage new generation investment to serve that same load.13 \nCyrusOne respectfully requests that PJM clarify how the VRR Curve exclusion is intended to \ninteract with, rather than undermine, the incentive for New Large Loads and capacity suppliers to \nbring new supply to the PJM Region. \nII. \nCONCLUSION \nFor the foregoing reasons, CyrusOne respectfully requests that the Commission (1) grant \nthe Motion and accept these Comments for consideration in this proceeding, and (2) if the \nCommission accepts the IRAS Filing, direct PJM to: (a) adopt a rebuttable presumption for the \none-mile aggregation rule as applied to independently developed facilities, with PJM bearing the \nburden of demonstrating sufficient affiliation to trigger the New Large Load designation; (b) \nclarify the treatment of incremental load and ramp schedules under the New Large Load \ndefinition, exclude load under pre-existing binding retail service agreements, and address the \ncompounding interaction between the one-mile aggregation rule and the June 1, 2027 cutoff; (c) \nprovide a reasonable transition mechanism for multi-year, multi-phase existing projects if such \nprojects are included within the New Large Load definition; and (d) further explain the basis for, \nand intended interaction of, the proposed VRR Curve exclusion with incentives for new \ngeneration investment. \n \n \n \n \n13 See, e.g., Comments of Microsoft Corporation, Docket No. ER26-3515-000 at 9 (Sept. 3, 2026)."},{"page":10,"startToken":2653,"endToken":2708,"text":"10 \n \n \n \n \n \n \n \n \n/s/ Michael Blackwell_____ \nKevin Marquardt \n \n \n \nMichael Blackwell \nCyrusOne, LP  \n \n \n \nLinda Walsh \n2850 N Harwood Street, Suite 2200  \nHusch Blackwell LLP  \nDallas, TX 75201 \n \n \n \n1801 Pennsylvania Ave., NW, Suite 1000 \n \nkmarquardt@cyrusone.com  \n \nWashington, DC  20006 \n \n \n \n \n \n \nTel: (202) 378-2300 \n \n \n \n \n \n \nmichael.blackwell@huschblackwell.com \n \n \n \n \n \n \nlinda.walsh@huschblackwell.com \n \n \n \n \n \n \nCounsel to CyrusOne LP \n \nDated: September 11, 2026"},{"page":11,"startToken":2708,"endToken":2793,"text":"11 \n \nCERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated at Washington, D.C. this 11th day of September 2026. \n \n \n/s/ Emily Starobin \n \nEmily Starobin \nHusch Blackwell LLP  \n1801 Pennsylvania Ave. NW, Suite 1000  \nWashington, D.C. 20006 \nTel: (202) 378-2319 \nemily.starobin@huschblackwell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":838,"startToken":0,"endToken":120},{"p":1,"at":838,"title":"I. MOTION FOR LEAVE TO FILE COMMENTS OUT-OF-TIME","method":"printed heading","endPage":2,"endAt":1254,"startToken":120,"endToken":471},{"p":2,"at":1254,"title":"II. BACKGROUND","method":"printed heading","endPage":3,"endAt":1327,"startToken":471,"endToken":743},{"p":3,"at":1327,"title":"I. COMMENTS OF CYRUSONE","method":"printed heading","endPage":4,"endAt":180,"startToken":743,"endToken":858},{"p":4,"at":180,"title":"A. The Definition of “Large Load” Should be Revised to Eliminate the One Mile","method":"printed heading","endPage":6,"endAt":1587,"startToken":858,"endToken":1694},{"p":6,"at":1587,"title":"B. IRAS Should Not Apply to Incremental Load Added Before June 1, 2027 or Load","method":"printed heading","endPage":8,"endAt":1219,"startToken":1694,"endToken":2283},{"p":8,"at":1219,"title":"C. PJM Should Further Explain the Basis for Excluding New Large Loads from","method":"printed heading","endPage":9,"endAt":513,"startToken":2283,"endToken":2484},{"p":9,"at":513,"title":"II. CONCLUSION","method":"printed heading","endPage":11,"endAt":6,"startToken":2484,"endToken":2709},{"p":11,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":556,"startToken":2709,"endToken":2793}]}