{"document":{"slug":"rec-20260916-5131","title":"Motion for Leave to Answer and Answer of Josh Shapiro, Governor of the Commonwealth of Pennsylvania in Support of PJM Interconnection, LLC’s proposal to…","issued":"2026-09-16","accession":"20260916-5131","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Josh Shapiro, Governor of the Commonwealth of Pennsylvania","kind":"answer","file":"sources/filings/text/20260916-5131_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260916-5131","tier":"record","sha256":"8fb083bda2d922fe775aa6762e6d1e5e760d89a8cb411f4b1784745a8033a8b1","pages":26,"tokens":8559,"emptyPages":[],"textThemes":["flex","retail","adequacy","study"]},"pages":[{"page":1,"startToken":0,"endToken":308,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n) \nPJM Interconnection, LLC \n) \nDocket No. ER26-3515 \n) \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF PENNSYLVANIA \nGOVERNOR JOSH SHAPIRO IN SUPPORT OF PJM’S PROPOSAL TO \nESTABLISH INTERIM RESOURCE ADEQUACY SERVICE AND A LARGE \nLOAD REGISTRY  \n \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(Commission) Rules of Practice and Procedure,1 Pennsylvania Governor Josh Shapiro (Governor \nShapiro) respectfully submits this motion for leave to answer and answer in support of PJM \nInterconnection, LLC’s (PJM) proposal pursuant to Federal Power Act (FPA) Section 205 to \nestablish Interim Resource Adequacy Service (IRAS) and a Large Load Registry. The \nCommission should grant leave to answer to clarify certain issues and assist the Commission \nwith its decision-making. \nI. \nSUMMARY \nPJM faces a crisis: large load growth has overwhelmed the region’s ability to serve that \nnew demand in a reliable manner, driving skyrocketing costs and increasing the risk of reliability \nevents, which may require manual load shed to protect the bulk power system.2 In that serious \n \n1 18 C.F.R. §§ 385.211, 385.214. \n2 PJM Transmittal at 13 (“Year-over-year, the shortfall of capacity supply needed to meet \ndemand . . . has grown despite a net increase of 1,294.4 MW of Installed Capacity . . . the \naddition of new supply has not kept pace with rapid large load demand growth”); Opening \nremarks of Chair Swett, AD26-7 Transcript at 9 (July 23, 2026) (“PJM is the tip of the spear, it's \nthe laboratory of national and economic security on which our country may rise or fall”); \nOpening remarks of Deputy Sec. of Energy Danly, AD26-7 Transcript at 32-34 (“PJM is a mess . \n. . Two auctions in a row that failed to meet the capacity requirement. That is not a functioning \nmarket.”); Opening remarks of Senior Director of White House National Energy Dominance"},{"page":2,"startToken":308,"endToken":642,"text":"2 \ncontext, IRAS is a critical measure to protect the region’s reliability and its ratepayers, consistent \nwith the Governors’ and the Administration’s Statement of Principles3 and the Ratepayer \nProtection Pledge.4 The central thesis for those documents was that the data centers that are \npredominantly causing the present reliability crisis and spurring the need for new energy \ninfrastructure should bear its costs. Pennsylvania is doing its part to meet the moment, advancing \nsolutions to the current crisis within the Commonwealth—as described by the Pennsylvania \nPublic Utility Commission in its filing in this docket—but no state can address the looming \nreliability emergency singlehandedly. PJM’s proposed mandatory, region-wide pre-emergency \nIRAS program is a necessary short-term fix to protect Pennsylvania residents and business—as \nwell as PJM customers broadly—from the unjust and unreasonable harm of resource adequacy \nshortfall and related power outages.  \nOpponents raise three principal objections to PJM’s proposal, none of which warrant its \nrejection.5  \nFirst, protestors are wrong that PJM has veered beyond its jurisdiction. PJM is squarely in \nits lane to operate the bulk power system in order to maintain system reliability including, where \n \nCouncil Lake, AD26-7 Transcript at 45-46 (“PJM is clearly broken, multiple failed capacity \nmarkets, capacity auctions, sky high price increases.”). \n3 National Energy Dominance Council within the White House and Undersigned Governors, \nStatement of Principles Regarding PJM, https://www.energy.gov/documents/statement-\nprinciples-regarding-pjm.  \n4 The White House, President Trump’s Ratepayer Protection Pledge Secures American AI \nDominance, Protects Consumers (July 23, 2026), \nhttps://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayer-protection-pledge-\nsecures-american-ai-dominance-protects-consumers/.  \n5 The Governor Shapiro focuses on challenges to the core design features of IRAS raised in the \nprotests of the Data Coalition Center (DCC); Google; Vistra; Talen; Constellation; EPSA; and \nP3. Filers raise a host of other, less central, objections to IRAS. Because PJM has consented to \nmodifications of its proposal consistent with NRG, if the Commission finds any validity to such \nobjections, it may direct PJM to file tariff modifications sufficient to address them."},{"page":3,"startToken":642,"endToken":965,"text":"3 \nnecessary, directing the curtailment of load. Under its proposal, PJM properly leaves the task to \nthe retail authority to determine which individual retail customers face disruption of service due \nto changes in system-level operation. PJM has also appropriately provided solicitude to the states \nby granting retail authorities a direct role in determining whether to provide wholesale \ncompensation based on the curtailments directed under IRAS and, if so, how much compensation \nup to the cap proposed by PJM.  \nSecond, opponents incorrectly argue that IRAS unduly discriminates against new large \nloads6 and/or existing generators.7 The new large computational loads that are causing the \ncurrent strain on the region’s infrastructure are not similarly situated to other loads due to their \nunique features. Their addition is not organic load growth that might cause the need for rapid \nsystem expansion and new supply in the ordinary course. It is a new and distinct threat to \nreliability and affordability in the region. Treating these new loads as distinct matches reality. \nLikewise, it is not discriminatory to recognize the difference between a capacity resource that is \nalready committed to serve system needs and a resource that has not yet assumed such a \ncommitment. To the contrary, it is common sense to distinguish between new capacity that is \navailable to serve new large loads, and existing capacity that is not. This is wholly consistent \nwith designing a reliability construct that directs curtailment signals to zones/areas hosting new \nlarge loads that have not secured sufficient new capacity to meet their needs. \nThird, protestors’ remaining arguments are largely contradictory, revealing the weakness \nof those objections. For example, some argue that IRAS will not be effective in incenting new \nlarge loads to bring their own capacity because only retail authorities, not PJM, decide which \n \n6 DCC Protest at 26-30; Google Protest at 11-13; Constellation Protest at 30-37; Vistra Protest at \n11.  \n7 Constellation Protest at 37-40; Vistra Protest at 12-14."},{"page":4,"startToken":965,"endToken":1311,"text":"4 \nspecific retail customers are allocated a share of zonal load curtailment8 but at the same time \ninsist IRAS is too stringent, will disrupt expectations, and new large loads need a longer \ntransition period to be just and reasonable.9 Both allegations cannot be true.  \nRather, IRAS is just and reasonable because it will increase the incentive for new large \nloads to invest in new capacity in order to decrease the likelihood that they face curtailment of \ntheir operations. IRAS is also just and reasonable because a given zone only faces the planning \nhorizon risk of pre-emergency curtailment proportionate to the share of new large loads that fail \nto meet their own need for supply, which the zone has allowed to interconnect. The aspect of \ncurtailment that PJM controls, i.e., operation of the bulk power system and aggregate MW \nlimitations on service imposed at the zonal transmission system-level, is appropriate and \ncommensurate with the risks posed to the bulk power system. PJM is not responsible for, and \nIRAS cannot be deemed unjust and unreasonable due to, actions (i.e., allocation of zonal \ncurtailment to individual customers) that later may occur through the independent decision of a \nstate retail authority. \nProtestors also object to removal of new large loads that do not Bring Your Own New \nCapacity (BYONC) from the VRR Curve10; but that treatment is precisely the actual result of \nimplementing IRAS. In periods of capacity shortage when IRAS is in effect, new large loads will \nnot be served by system resources during periods of system strain. It is just and reasonable to \nisolate demand that is not being served by system capacity from being reflected in the demand \ncurve. Exclusion of such load is necessary to accurately reflect the needs that are expected to be \n \n8 Google Protest at 3 (“IRAS will not incentivize new large loads to bring their own capacity”). \n9 DCC Protest at 35 (requesting, if it does not reject IRAS, that the Commission direct PJM to \ninclude a “meaningful transition” that limits application of IRAS). \n10 Google Protest at 23-24."},{"page":5,"startToken":1311,"endToken":1610,"text":"5 \nserved by system resources, and to protect existing customers from costs that they did not \ncontribute to. Likewise, objections to PJM’s proposed order of curtailment are policy judgments \nthat do not render the design unjust and unreasonable. Rather, PJM’s design of IRAS to curtail \nzones/areas with large load growth not matched by new supply before calling on demand \nresponse products is an appropriate choice to protect existing customers because flipping that \norder would reduce available capacity to meet regional needs by deterring demand response \nregistration. \nIn addition to their legal flaws, many of these protests fly in the face of commitments the \nsame protestors already made in the Ratepayer Protection Pledge, and are essentially an \nargument that the new capacity needed to serve data centers must be paid for by all PJM \ncustomers through higher capacity market prices rather than by the actual cost-causers. IRAS is \nboth just and reasonable and critical to vindicate the shared commitment in the Governors’ and \nthe Administration’s Statement of Principles to “allocate costs to data centers . . . to load serving \nentities with new data centers that have not self-procured new capacity or agreed to be \ncurtailable.”  \nPJM’s proposal of IRAS is necessary and appropriate in response to the severe challenges \nfacing the region. Protestors’ intimations that PJM ignored better alternatives such as a state-led \ncurtailment regime is legally irrelevant, but also incorrect.11 PJM’s decision to implement a \nmandatory, pre-emergency, region-wide solution is necessary leadership and serves to protect \ncustomers in response to requests from many state entities for such a uniform regional approach. \nStates can, of course, independently implement actions within their jurisdictional authority to \nmitigate the challenges of large load growth, but they face the risk that such actions are not \n \n11 DCC Protest at 2-4; Google Protest at 23-25."},{"page":6,"startToken":1610,"endToken":2073,"text":"6 \ncompatible with or recognized under PJM’s tariff, or that other states fail to take commensurate \naction.12 Failure to implement a consistent approach throughout the region could lead to a \npatchwork strategy that could frustrate PJM’s real-time operations and fail to achieve the goals of \nthe implementing states.13 Given the urgency of this situation, only coordinated, region-wide \naction like IRAS can mitigate the severe cost and reliability challenges caused by large load \ngrowth imminently exceeding available supply. Governor Shapiro therefore urges the \nCommission to approve IRAS without delay, as timely implementation is critical to have IRAS \nin effect in time to avoid disruption of service for existing customers and to ensure its rate-\nprotective effects are in place before the next Base Residual Auction in December.   \n \n12 For example, in a recent Virginia State Corporation Commission proceeding to establish large \nload connection queue process standards Dominion asserted that it could not consider the \nimpacts of load flexibility to reduce impacts on the transmission system or resource adequacy in \nload interconnection studies because of PJM system planning requirements. Dominion asserted \nthat “PJM must first establish governing rules and analytical frameworks necessary to evaluate \nnon-firm or flexible load in both planning studies and system operations.” Similarly, Dominion \nasserted that “implementation of any fast-track or accelerated connection mechanism” for \nflexible loads “requires PJM rulemaking and FERC guidance.” Dominion, Rebuttal Testimony of \nJacqueline R. Vitiello, Exhibit No. 25, VA SCC Case No. PUR-2026-00011, at 15-17 (filed Apr. \n30, 2026), https://www.scc.virginia.gov/docketsearch/DOCS/8c2n01!.PDF; see also Dominion, \nRebuttal Testimony of R. Matthew Gardner, Exhibit No. 21, VA SCC Case No. PUR-2026-\n00011, at 7-8 (filed Apr. 30, 2026), \nhttps://www.scc.virginia.gov/docketsearch/DOCS/8c2j01!.PDF (“the Company needs FERC and \nPJM to take action on developing a formal framework for non-firm or flexible load planning and \nestablish rules around a customer bringing its own new generation before the Company can \nbegin to implement that framework.”). Dominion thus articulated the case for a coherent federal \nregulatory approach as proposed by PJM in IRAS. State regulators face barriers to know when \nthe potential for inconsistency with a federal jurisdictional scheme genuinely warrant delay, or \nwhen such concerns lack merit and are raised to delay costly or burdensome reforms. \n13 For example, PJM’s capacity shortage emergency procedures in Manual 13 for manual load \ndumps after EEA3 generally assign load shed requests to deficient zones. However, if the PJM \nMid-Atlantic Region (MAAC) is deficient, the load shed is further allocated by the load shed \nallocation table in Attachment E. As such, a state within MAAC could implement a voluntary \nstate IRAS program, and zones within that state could still face emergency EEA3 curtailments \nbased on actions of other states and zones within MAAC."},{"page":7,"startToken":2073,"endToken":2377,"text":"7 \nII. \nANSWER IN SUPPORT OF IRAS \nA. \nIRAS properly targets wholesale sales and reliable operation of the bulk \npower system. \nProtestors variously characterize IRAS as “aim[ing] to interrupt retail service”; \n“compel[ing] states . . . to conform their retail curtailment frameworks to PJM tariff \nrequirements”;14 “target[ing] retail customers . . . by mak[ing] the characteristics of the retail \ncustomer . . . the basis for a curtailment obligation”15; and failing to “directly affect wholesale \nrates.”16 None of these descriptions match the basic facts of PJM’s proposal. As PJM explains \nIRAS is a “supplemental capacity product” that may be called upon during “an Interim Resource \nAdequacy Service Action,” an action PJM anticipates will occur when it “is no longer able to \nmaintain reserves within the RTO or zone” or “there are insufficient resources to keep \n[Interconnection Reliability Operating Limits] within defined operating limits in order to prevent \ninstability, uncontrolled separation, or cascading outages that adversely impact the reliability of \nthe interconnection.”17 PJM’s proposal is manifestly aimed at provision of a wholesale product or \nservice, and at ensuring reliable operation of the bulk power system; each is clearly within its \njurisdiction. Indeed, actions that would be possible under IRAS are no different from other \nactions (or “Operating Instructions,” as defined by NERC) that PJM has long been authorized to \ntake as the region’s Reliability Coordinator, Transmission Operator, and Balancing Authority.18 \nThe Operating Agreement already expressly grants PJM the authority to coordinate curtailment \n \n14 DCC Protest at 3. \n15 Google Protest at 8-9. \n16 Constellation Protest at 26-27. \n17 PJM Transmittal at 75. \n18 Id. at 81 (“Under the terms of the Operating Agreement and as the Reliability Coordinator, \nTransmission Operator, and Balancing Authority, PJM has the authority and flexibility to initiate \nEmergency Procedures as it sees fit to maintain the reliability of the PJM Region”)."},{"page":8,"startToken":2377,"endToken":2735,"text":"8 \nof load19; where PJM determines the aggregate amount of MW load reduction required to be \ncurtailed in a zone or area and the Transmission Owner or Electric Distributor determines the \nend-use entities that are ultimately curtailed. IRAS differs in only two ways, each of which is just \nand reasonable and neither of which matters for PJM’s jurisdiction: (1) the implementation of \ncurtailment signals prior to an EEA 1, and (2) the means by which PJM will determine the \naggregate MW of load reduction directed within a zone or area. Implementing IRAS on a pre-\nemergency basis prior to a NERC EEA 1 will avoid escalating emergency procedures that \ninclude but are not limited to shortage pricing and public calls for conservation, which would \nrepresent socialization of costs, both financial and reliability related, being imposed by non-\ncapacity backed new large loads upon all customers. For target MW reductions, PJM proposes to \nlimit the total MWs of load reduction in a zone or area based on the share of new large loads \n(which PJM terms “Eligible New Large Loads”) that have failed to meet their capacity needs \nthrough BYONC or capacity procured pursuant to Reliability Backstop Procurement (RBP) \nrules.20 However, PJM does not direct the curtailment of these loads, rather it uses these criteria \nto set the aggregate MW reduction amount. It remains up to the retail authority to work with \nentities within their jurisdiction to implement the retail end-user curtailment priority. PJM’s \nfocus on non-capacity backed new large loads to determine the MW reduction target in each \nzone or area is appropriate, since these entities are precipitating the reliability emergency. Duly \ntargeting load reductions in zones or areas with non-capacity backed new large loads as a means \nto potentially avoid emergency procedures is a just and reasonable method for avoiding unjust \n \n19 PJM, OA Schedule 1 Sec 1.6, OA Schedule 1 Sec 1.6 Office of the Interconnection (3.1.0), § \n1.6.2 (v) and (vii) (“The Office of the Interconnection shall . . . Determine and declare than an \nEmergency is expected to exist . . . . Coordinate the curtailment of shedding of load. . . .”).  \n20 PJM Transmittal at 86-87."},{"page":9,"startToken":2735,"endToken":3096,"text":"9 \nand unreasonable outcomes of shortage pricing and potential curtailment for existing PJM \ncustomers who have paid for the embedded costs of the existing system and have not contributed \nto the resource adequacy shortfall. Furthermore, the focus on zones or areas projected to have \ncapacity shortfalls in real-time—through the existence of non-capacity backed large loads in the \nplanning horizon—is consistent with PJM’s Operating Agreement Schedule 1, Section 1.7.11 \nwhich states that in an emergency “the Office of the Interconnection may not order a manual \nload dump in a Control Zone solely to address capacity deficiencies in another Control Zone.”21 \nIn other words, PJM is appropriately aligning IRAS with existing practices that generally limit \ncurtailment signals to zones with real-time capacity shortfalls.  \nIn short, PJM is asserting no new novel authority in proposing IRAS, but rather is \nenhancing its deployment of existing tools to better ensure bulk system reliability (directing \nloadshed to areas with concentrations of non-capacity backed new large loads) and equitable \nwholesale market rates (more fairly allocating the risk of curtailment to zones or areas of the grid \nthat have most contributed to the problem). \nProtestors acknowledge that PJM does not propose to direct the curtailment of any \nspecific retail customer.22 In fact, PJM’s inability (and its disavowal of any attempt to do so) to \ncontrol the curtailment priority among individual retail customers is simultaneously a point of \ncontention for protestors.23 But protestors cannot logically claim both that PJM’s proposal \n \n21 PJM, OA, OA Schedule 1 Sec 1.7, OA Schedule 1 Sec 1.7 General. (21.1.0), § 1.7.11. \n22 DCC Protest at 11 (“it will not curtail specific end-use customers directly, but will direct \nElectric Distributors to curtail these customers’ demand”); Constellation Protest at 20 (PJM \n“leav[es] to the state regulatory sphere the choice of which particular identifiable retail \ncustomers will be subject to curtailment under IRAS”). \n23 See Google Protest at 1-2 (calling PJM’s inability to direct curtailment of individual retail \ncustomers the “fundamental flaw”, “basic misalignment”, and “regulatory disconnect” of the \nIRAS proposal); Vistra Protest at 4 (calling IRAS an “illusory construct” because “there is no"},{"page":10,"startToken":3096,"endToken":3418,"text":"10 \nunlawfully “targets retail customers” and that PJM’s proposal is fatally flawed because it cannot \nguarantee which individual retail customers are curtailed. Both cannot be true.  \nStripped of embellishment, the facts are straightforward: under IRAS, PJM can only \ndirect “a MW quantity of load reduction to the relevant Electric Distributer zone(s)/area(s)”24—it \nneither targets nor directs specific retail customers to be subject to curtailment, nor compels or \nrestricts the authority of the retail authority to prioritize among the retail customers that must be \ncurtailed in order to meet the required MW quantity of bulk load reduction and safeguard the \nreliability of the grid. This is what PJM and other balancing authorities have long existed to do. \nProtestors also make much of the fact that PJM’s determination of the MW quantity of \nbulk load reduction is based upon the characteristics of retail customers in the relevant Electric \nDistributer’s zone or area—i.e., that PJM proposes to base its curtailment of wholesale customers \non whether the load growth in that zone or area is comprised of new Large Loads (i.e., a large \nand concentrated addition of 50 MW or more at the same electrical location) and whether such \nnew Large Load additions have been matched by addition of commensurate new supply (new \ncapacity in the form of BYONC or allocated RBP resources).  \nProtestors’ position appears to be that PJM must blind itself—that it is legally barred \nfrom acting on information about the characteristics of load growth in a zone or area, even if that \ninformation is directly relevant to reliable operation of the bulk power system and enables PJM \nto provide a just and reasonable wholesale product or service. There is no merit to this position. \n \nassurance that new large loads will receive the purported benefit of BYONC because it is up to \nstates and EDCs to decide curtailment orders and priorities”). \n24 PJM Transmittal at 86."},{"page":11,"startToken":3418,"endToken":3723,"text":"11 \nThe caselaw on jurisdiction under the FPA has never drawn such rigid and restrictive \nboundaries on the information that is plainly relevant to setting a wholesale rate.25 The \ncharacteristics of retail loads and generation, both matters that reflect state regulation, are highly \nrelevant and essential to inform a wholesale rate. Taking this information into account in \ndesigning the wholesale rate does not constitute regulation of those matters. It rather merely \nconstitutes prudent regulation of wholesale rates in light of the “fact . . . that the wholesale and \nretail markets in electricity, as in every other known product, are not hermetically sealed from \neach other.”26 \n \nIf adopted by the Commission, the protestors’ position would bar PJM from taking into \nconsideration information about generating facilities—ramp rates, minimum run times, outage \nrates, and so on—because neither the Commission nor PJM have authority to directly regulate \ngeneration. This jurisdictional rule would be absurd and unworkable if applied to generating \nfacilities in the context of running a wholesale energy or capacity market, and it is equally so if \napplied to retail loads. PJM is not barred from seeking information about the nature of the load \ngrowth in a zone, even if those matters are subject to retail jurisdiction, and using that \ninformation to shape wholesale market rates. \n \n25 FERC v. EPSA, 577 U.S. 260, 281-282 (2016) (“When FERC regulates what takes place on \nthe wholesale market, as part of carrying out its charge to improve how that market runs, then no \nmatter the effect on retail rates, § 824(b) imposes no bar.” (emphasis added)); see also Oneok, \nInc. v. Learjet, Inc., 575 U.S. 373, 387–88 (2015) (rejecting the “Platonic ideal” that there should \nbe a clear division between areas of state and federal authority).  \n26 FERC v. EPSA, 577 U.S. 260, 281 (2016)."},{"page":12,"startToken":3723,"endToken":4063,"text":"12 \nB. \nPJM’s proposed compensation framework provides appropriate solicitude to \nthe states and is jurisdictionally sound. \nProtestors separately challenge PJM’s provision of an opportunity for wholesale \ncompensation for loads that provide IRAS as prescribing a retail rate.27 A number of state \nregulators who have not otherwise challenged IRAS raise questions and concerns about the \nproposed compensation structure, and some request that PJM or the Commission clarify that the \nwholesale compensation proposal is not aimed at or a limitation on state authority to regulate the \nretail rate.28 While Governor Shapiro is sympathetic to states’ requests to clarify these \nprovisions, so clarified, the proposal is jurisdictionally sound. Rather than target or set retail \nrates, PJM’s proposal appropriately recognizes the states’ interests and affords states a unique, \nbut not unprecedented, role in implementing the wholesale market rate. Under established \nCommission precedent upheld by the Supreme Court, availability of a wholesale rate may \ndepend on retail conditions, as PJM proposes here.  \nGovernor Shapiro understands the confusion that has resulted from PJM’s provision of \nwholesale compensation for a wholesale service because it envisions making that wholesale \ncompensation level subject to change by the relevant retail authority. Providing such solicitude \nto the state regulatory authority to exert circumscribed authority over aspects of a wholesale rate \nhas precedent, in the context of matters like wholesale demand response and wholesale \nparticipation of distributed energy resources where both federal jurisdiction and state jurisdiction \nexist over the same nexus of activities (e.g., a demand reduction can be sold as part of a \n \n27 DCC Protest at 12 (“PJM’s tariff revisions seek to prescribe the amount paid to retail \ncustomers through their retail rates for service interruptions implemented at PJM’s direction”).  \n28 See e.g., Comments, Request for Clarification, and, in the alternative, Request to Sever of \nOPSI (“OPSI Comment”) at 8 (generally supporting key design elements of IRAS but requesting \nclarification that “retail regulators can set the IRAS rate itself at retail” and whether it is New \nLarge Loads that determine the compensation level or retail regulators)."},{"page":13,"startToken":4063,"endToken":4408,"text":"13 \nwholesale demand response product or contribute to a retail demand response program). Indeed, \nin Order No. 719, in solicitude to the states’ retail authority over retail customers, the \nCommission granted the relevant electric retail regulatory authority (RERRA) a veto over that \nexistence of the wholesale transaction entirely. 29 Accordingly, the Commission required \nRTO/ISOs to amend their market rules to permit demand response aggregators to bid in demand \nresponse into wholesale markets, unless the RERRA’s laws or regulations do not permit such \nparticipation.30 To this day, Order No. 719’s provision for a state opt-out limits demand response \nparticipation in wholesale markets.  \nHere, PJM has proposed an even more circumscribed role for the retail regulatory \nauthority over the wholesale rate than that provided by the Commission under Order No. 719. \nWhereas under Order No. 719, a retail authority has a dispositive role in determining whether the \nwholesale transaction may occur at all, PJM proposes in IRAS only to allow retail authority to \ndetermine, from a range of just and reasonable compensation levels, which just and reasonable \ncompensation level to select. Specifically, by proposing a wholesale market compensation rate \nfrom zero dollars up to a cap of 50% of the Non-Performance Charge Rate, PJM is setting a \ndefault wholesale rate of 50% of the Non-Performance Charge Rate that will, absent other action \nby the retail authority, pass through to retail rates. Only if the retail authority acts to change that \ndefault rate to another just and reasonable compensation level, including potentially to zero, \nwould that alternative wholesale compensation level apply and flow through to retail rates.31 As \nin Order No. 719, providing such a role for the retail authority does not render the wholesale rate \n \n29 See Order No. 719, 125 FERC ¶ 61,071, at P 154 (2008). \n30 Id.; see also PJM Transmittal at 108 (citing Orders No. 719 125 FERC ¶ 61,071, at P 154 \n(2008) & Order No. 719-B, 129 FERC ¶ 61,252 at P 5). \n31 PJM Transmittal at 102 (“the wholesale IRAS rate is flexible and can be further reduced”)."},{"page":14,"startToken":4408,"endToken":4814,"text":"14 \nactually a retail rate, nor does it violate the FPA’s jurisdictional provision because the service \nremains at the wholesale level and the state role would be authorized and defined in a federal \ntariff. To be more precise, the retail authority does not set the wholesale rate, rather the \nwholesale rate is setting conditions under which that rate applies (i.e., absent state action, rate x \napplies; under conditions of state action y, rate z applies).  \nPJM’s transmittal and proposed tariff revision arguably could be clearer in describing the \nrespective jurisdictional roles of PJM, as the public utility subject to federal jurisdiction that has \npower to propose a change to wholesale rates, and the retail authority, which has no authority to \nchange that wholesale rate once it is established, but has authority pursuant to state law to \ndetermine how to allocate that charge among retail customers. At times, PJM confusingly \nappears to be speaking about compensation that would be provided to individual retail \ncustomers, which can only be provided via retail, not wholesale bills.32 But PJM is also clear that \ncurtailment during an IRAS event is directed only as a MW quantity of load curtailment, i.e., \nbulk load, to a particular Electric Distributer’s zone or area,33 and wholesale compensation will \ntherefore accrue (presumably as a credit) on a wholesale bill to the wholesale customers based on \nthat total MW quantity of load curtailment. PJM acknowledges repeatedly in its filing that which \nindividual retail customers receive that compensation is beyond its control.34 Cleaning up PJM’s \n \n32 See PJM Transmittal at 104 (“The net result is a reduced capacity charge for Eligible New \nLarge Loads, and thus a ‘practice . . . in which operators of wholesale markets pay electricity \nconsumers for commitments not to use power at certain times’ and thus ‘directly’ affects \nwholesale capacity rates assessed.”) (emphasis added). \n33 PJM Transmittal at 86 (PJM identifies for each zone/area the Eligible New Large Load \nAmounts—i.e., the MW quantity to be called upon to reduce load under IRAS. “Directing an \nElectric Distributor, rather than a specific end-use customer, to reduce a quantity of load is in \nkeeping with PJM’s longstanding practice and reflects and respects the allocation of jurisdiction \nbetween the federal and state levels”). \n34 PJM Transmittal at 104 (“the entities to be paid the rate and the loads to be charged to support \nsuch compensation must be determined at the state level”)."},{"page":15,"startToken":4814,"endToken":5156,"text":"15 \nproposed tariff provision pertaining to IRAS compensation35 to remove all references to \n“Eligible New Large Loads,” entities that PJM will not directly interface with in implementing \nthe wholesale rate, would helpfully clarify that PJM is setting a wholesale rate (in which retail \nauthority is permitted a role in implementation) rather than dictating terms of compensation to \nspecific retail customers. Similarly, PJM’s proposed tariff would benefit from clarification to \nspecify that provision of particular levels of compensation depend on certain conditions at retail. \nIn other words, just as eligibility to participate as wholesale demand response depends on \npermission under the relevant state laws and regulations, wholesale compensation for IRAS at a \nreduced level depends on RERRA action specifying such an alternate compensation level within \nthe acceptable, just and reasonable range. Such a reformulation would clarify that the retail \nauthority is not setting the wholesale rate, but rather that conditions in the retail context inform \nthe implementation of and are an input into the wholesale rate. Given PJM’s agreement to \nalterations of its proposal consistent with NRG, we understand such clarifications of PJM’s \ncompensation structure to be permissible as they leave intact PJM’s core rate design (the \nwholesale curtailments remain subject to wholesale compensation within the same just and \nreasonable range as the initial proposal). \nC. \nIRAS is not unduly discriminatory.  \nProtestors contend that IRAS is unduly discriminatory in its treatment of new large loads, \nexisting capacity resources, or both.36 But it is not unduly discriminatory to distinguish between \n \n35 See PJM Transmittal Attachment A, Redlined Proposed Tariff Provisions, Attachment DD-4 \nSection X (“Compensation for Providing Interim Resource Adequacy Service”). \n36 DCC Protest at 27-30 (arguing PJM treatment under IRAS is arbitrary based on timing of \nwhen the load is placed in service); Google Protest at 11-12 (undue discrimination because “the \nonly differences between EDs that receive curtailment orders and those that do not are the \ncharacteristics of their retail customers”); Constellation Protest at 29 (PJM’s proposal unduly \ndiscriminates against “certain load, based on load size and in-service date” and “against certain"},{"page":16,"startToken":5156,"endToken":5458,"text":"16 \nnovel forms of load (very fast paced, very large peak demand additions that are concentrated in a \nsingle electrical location) that threaten the reliability of the grid and traditional forms of load that \ndo not (load growth that is demonstrably slower-paced, occurring over many years, that is \ncomprised of smaller and more distributed retail loads). As discussed herein, the Commission \nitself recognized the need for distinct treatment of large computational loads in recent orders. \nAnd likewise, it is common sense that existing capacity that has already been committed to \nprovide services to the transmission system, and where existing consumers have contributed to \nembedded costs, is not similarly situated to newly available capacity (including new capacity that \nis not associated with a wholly new build generating facility, such as uprates of existing \ngenerating facilities) that does not face such commitments and is therefore available to serve the \nparticular capacity needs of new large loads. Moreover, distinguishing between such differently \nsituated resources is inherently needed to prevent cross-subsidization. Existing capacity has been \ncommitted—through wholesale markets and rates—to serving existing loads, where these \nexisting loads have contributed to embedded costs in the form of capacity market payments. \nAllowing existing capacity to now contract with new large loads (e.g., as BYONC) would allow \nthese new large loads to benefit from existing consumer embedded cost contributions, and more \nimportantly, would worsen the reliability shortfall by shifting existing capacity to new loads, \nleaving existing consumers with reliability shortfalls. This is a form of unwilling consumer \ncross-subsidization of new large loads—both in terms of rates and reliability—that can only be \naddressed by providing for reasonable distinct treatment. \n \ngeneration, based on resource vintage”); Vistra Protest at 3 (objecting that inability for new large \nloads to contract with existing capacity resources is “textbook undue discrimination”)."},{"page":17,"startToken":5458,"endToken":5776,"text":"17 \n1. \nIt is not undue discrimination to determine IRAS exposure based on \nthe kind of load growth in a zone that is causing the region’s reliability and \naffordability impacts. \nPJM aptly points out that the Commission has already determined that large loads may \nconstitute a “separate category of load” that require distinct treatment to ensure just and \nreasonable and not unduly discriminatory rates.37 The Commission explained that, “integrating \nlarge loads poses specific challenges to transmission system operation given their size, \noperational behavior, and unique potential to impact the transmission system.”38 The \nCommission also recently credited the position of the North American Electric Reliability \nCorporation (NERC) that large loads are “substantially larger and constructed more quickly than \nprior loads using the [Bulk-Power System]” and pose unique challenges, in an Order directing \nNERC to take “urgent” action to establish Reliability Standards that will “assure that \ncomputational loads are reliably integrated into the operation of the Bulk-Power System.”39 The \nCommission has thus already recognized that the characteristics of retail customer loads may \ndirectly affect the provision of transmission service to Eligible Customers on behalf of large \nloads and reliable operation of the bulk power system, such that these features are relevant to \nCommission-jurisdictional rates. The same “unique operational challenges” and “unique \noperational impacts on the transmission system” of providing transmission service to Eligible \nCustomers on behalf of large loads recognized by the Commission support PJM’s proposed \ndistinct treatment of Electric Distributers who seek transmission service on behalf of such large \nloads.40  \n \n37 PJM Transmittal at 96 (citing the June 2026 Order to Show Cause, 195 FERC ¶ 61,211 \n(2026)). \n38 June 2026 Order to Show Cause, 195 FERC ¶ 61,211 at P 58. \n39 Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031, at \nPP 9-10 (July 16, 2026). \n40 June 2026 Order to Show Cause, 195 FERC ¶ 61,211 at PP 50-58."},{"page":18,"startToken":5776,"endToken":6184,"text":"18 \nPJM’s proposal is not unduly discriminatory because it focuses on distinctions among \ncustomers that are relevant to ensuring just and reasonable rates and reliable operation of the \nbulk power system. Large load customers that today drive completely novel degrees of load \ngrowth pose unique operational challenges to the transmission system. \nProtestors’ effort to characterize IRAS as undue discrimination because it will apply only \non a forward-looking basis to new large loads after its acceptance also fails.41 The Commission \nregularly accepts that new rules apply only to new entrants, and when needed grandfathers \nexisting entities under prior rules without such treatment constituting undue discrimination.42 \nThe Commission could not conduct its statutorily mandated task of ensuring just and reasonable \nand not unduly discriminatory rates if approving new rates on a prospective basis constituted \nundue discrimination. Rather than treating the imposition of new requirements as prohibited \nundue discrimination, the Commission considers instead whether the disruption of settled \nexpectations due to the new rules is significant enough to warrant a transition period to mitigate \nthe harm to settled expectations.43  \n \n41 See e.g., DCC Protest at 29 (arguing PJM has not demonstrated that “the timing on when load \ncomes online” is a legitimate basis for discrimination). \n42 See e.g., MISO, 150 FERC ¶ 61,180 at P 21 (2015) (rejecting arguments that differing \ntreatment between interconnection customers constitutes undue preference, where that difference \nis due to the fact that certain interconnection customers are subject to generator interconnection \nprocedures and agreements that pre-date new reforms); ISO-NE, 162 FERC ¶ 61,205 at P 47 \n(2018) (rejecting protestors’ arguments that ISO-NE’s inclusion of a cut-off date in the definition \nof resource types to which a particular capacity market rule would apply constitutes undue \ndiscrimination); PJM, 193 FERC ¶ 61,217 at P 224 (2025) (“To the extent an entity is a party to \nan existing contract for such a purpose, we find that it is appropriate to grandfather such entity so \nthat it may continue using BTMG for the current term remaining under the existing contract”). \n43 See e.g., Order No. 2023, Improvements to Generator Interconnection Procedures and \nAgreements, 184 FERC ¶ 61,054 at P 856 (2023) (“We further find that the transition process, as \nadopted herein, appropriately balances the need to move expeditiously to the new cluster study \nprocess with the need to respect the investments and expectations of interconnection customers \nat an advanced stage in the existing interconnection process”)."},{"page":19,"startToken":6184,"endToken":6495,"text":"19 \n2. \nIt is not undue discrimination to treat capacity resources that are \nalready committed to serve system needs in a different manner from \nresources that have not yet assumed any such commitment. \nProtestors’ argument that PJM’s proposal unduly discriminates against existing capacity \nresources is also meritless. IRAS seeks to mitigate unique impacts to the grid from rapid \nadditions of very large quantities of load in a single electrical location without commensurate \naddition of capacity. For that purpose, existing capacity resources, which cannot serve those new \nlarge loads because they are already committed to provide capacity to the system, and new \ncapacity (including new capacity that is created at existing generating facilities or at deactivated \ngenerating facilities), which is capable of serving the needs of new large loads and therefore can \nreduce the transmission system impacts of such additions, must be distinguished. The question is \nnot whether resources that qualify new large loads to avoid curtailment under the IRAS scheme \n(as BYONC or via allocated RBP UCAP) and existing capacity resources are capable of \nproviding the same “capacity, energy, and ancillary services products” in PJM’s wholesale \nmarkets.44 Rather the question is whether existing capacity resources can solve the specific and \nunique operational challenges caused by large load additions that PJM aims to solve with IRAS. \nThe unqualified and commonsense answer is no. Resources that are already being counted upon \nto meet existing system needs do not have the same ability to address new large loads’ \nincremental capacity needs.  \nAllowing existing resources to meet the needs of new large loads—as BYONC or RBP—\nwould only be allowing for a rent-seeking shell game, as new large loads would seek out \navailable capacity resources made cheaper by years of ratepayer compensation, and existing \ncapacity resources would seek to lock-in long-term contracts with new large loads. This would \n \n44 Constellation Protest at 37."},{"page":20,"startToken":6495,"endToken":6871,"text":"20 \nleave existing ratepayers as suddenly second-class customers in the system they have long paid \nto maintain, leaving them particularly vulnerable to reliability events from resource adequacy \nshortfalls and higher bills to support development of costly and slow new capacity. \nD. \nIRAS is just and reasonable because it will encourage investment in new \ncapacity while protecting other customers from reliability and affordability impacts \ncaused by large load growth. \nFinally, protestors’ remaining objections to IRAS have no merit.45 Governor Shapiro \nfocuses on claims that target the core design of IRAS, none of which warrant rejection of IRAS. \nTo the extent that the Commission determines that modifications of IRAS are necessary to \nresolve other, less central concerns about its design, PJM has granted its consent to the \nCommission to modify its proposal consistent with NRG and the Commission can accordingly \ndirect changes to PJM’s tariff proposal to address such concerns.46 Given the pressing need for \ntimely solutions to PJM’s supply shortage, Governor Shapiro urges the Commission to accept \nIRAS by the statutory deadline to enable PJM to rapidly turn to more detailed implementation of \nthe construct, with any necessary modifications.    \nFirst, protestors are wrong that IRAS cannot achieve its core objective and is unjust and \nunreasonable because PJM does not have jurisdiction over retail customers, and therefore cannot \nguarantee that the right retail customers will be curtailed and, to the extent that the wholesale \ncompensation is set above zero, compensated for such curtailment. IRAS is just and reasonable \n \n45 See, e.g., DCC Protest at 6, 35; Google Protest at 2, 14; Vistra Protest at 1.  \n46 For example, Governor Shapiro takes no position on concerns that IRAS should provide for a \nlonger transition period before it becomes effective; or that modifications to the transmission \nservices or capacity charges to new large loads subject to IRAS are necessary to be consistent \nwith cost causation. To the extent the Commission finds merit in concerns about the details of \nimplementation of IRAS, it should approve the proposal and direct modification of the proposal \nto address those concerns on further compliance, in order to move the PJM region forward with \nthe only real solution it has to timely address the near-term reliability and affordability impacts \nof large load additions."},{"page":21,"startToken":6871,"endToken":7224,"text":"21 \nbecause it appropriately places the potential risk of being subject to curtailment on the \ntransmission zone or area serving a new non-capacity backed large load, and on the planning \nhorizon that potential risk is proportionate to the quantity of new large load additions that are not \nmatched with new capacity supply and therefore which pose unique risks to the transmission \nsystem in that operational horizon. PJM, and the Commission via oversight of jurisdictional \nrates, have no responsibility to ensure that that risk of curtailment falls incident to particular \nretail customers; that is beyond the scope of ensuring that the wholesale rate is just and \nreasonable and is a matter for retail ratemaking. Likewise, wholesale compensation need only be \nprovided to the appropriate wholesale customer (in this case, the transmission customer \nproviding service on behalf of the large loads) to be just and reasonable under the FPA; PJM \nneed not and cannot address the subsequent allocation of such wholesale compensation among \nretail customers. But the jurisdictional division of labor does not require PJM or the Commission \nto sit idly by while large load additions not backed by new capacity erode reliability and \naffordability. PJM’s proposal reasonably aims to address the real challenges that large load \ngrowth presents while respecting the jurisdictional divide established by Congress. \nMoreover, protestors’ arguments that IRAS will fail to incentivize new large loads to \ninvest in new capacity in order to reduce the likelihood that they are subject to curtailment is \nunconvincing,47 and is contradicted by arguments that IRAS is too harsh and must be mitigated \nby a more generous transition period.48 PJM proposes to identify the total MW quantity of load \nsubject to IRAS in a zone or area based on new large loads that have not addressed their capacity \nneeds within that zone/area, and to leave the actual curtailment directions being made to end-use \n \n47 Google Protest at 2 (arguing IRAS would result in “less investment in capacity in PJM”). \n48 DCC Protest at 35 (arguing that if the Commission is inclined to accept IRAS, at minimum it \nmust adopt a meaningful transition mechanism)."},{"page":22,"startToken":7224,"endToken":7664,"text":"22 \nretail load to the Electric Distributer. As a result, individual large loads materially decrease their \nlikelihood of being subject to curtailment by investing in new capacity. Such individual retail \ncustomers that invest in new capacity consistent with IRAS will also have, because of the federal \ntariff, a good argument to retail authorities that they should not be subject to curtailment, or \nshould receive priority above other large loads in allocation of curtailment quantities during \nIRAS events. The Large Load Registry that PJM proposes to establish will provide information \nto enable retail regulators and retail load customers to understand the basis for PJM’s \ndetermination of the MW quantity of load subject to curtailment in a zone or area during an \nIRAS event. Ultimately, PJM’s proposal sufficiently aligns incentives to constitute a just and \nreasonable rate that must be accepted by the Commission.49  \nSecond, protestors are wrong that it is not just and reasonable to remove new large loads \nthat are subject to IRAS from the VRR Curve.50 PJM is not ignoring demand fundamentals; it is \nrespecting supply realities. Specifically, due to supply project development constraints51 \n \n49 Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1017 (D.C. Cir. 2022) (“The \nstatutory requirement that rates be ‘just and reasonable’ is obviously incapable of precise judicial \ndefinition, affording the Commission leeway in its ratemaking decisions”) (internal quotation \nand citation omitted); Long Island Power Auth. v. FERC, 27 F.4th 705, 714 (D.C. Cir. 2022) \n(Commission is not held to the standard of “exacting precision” in ratemaking) (internal \nquotation and citation omitted). \n50 DCC Protest at 6 (“PJM proposes to undermine the ability of the capacity market to send price \nsignals for the development of new capacity by excluding Eligible New Large Loads from the \ncalculation of the Variable Resource Requirement curve”); Google Protest at 14 (arguing PJM’s \nproposal “break[s] supply and demand fundamentals by ignoring the demand that PJM itself \nexpects to materialize”); Constellation Protest at 46 (arguing aspect of the proposal will “harm \nlong-term resource adequacy, the capacity market, and customers’ pocketbooks by muting the \nprice signals that are necessary to encourage new entry and retain existing resources.); Vistra \nProtest at 16 (this aspect of the proposal “meddle[s] with capacity market fundamentals”). \n51 PJM, “2027/2028 Base Residual Auction Reserve Target Shortfall Report” at 5-9 (Feb. 2026), \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-\n2028-bra-reserve-target-shortfall-report.pdf (“Even if every viable project were to clear the \ninterconnection process today, developers face a rigid physical barrier that prevents immediate \nconstruction. As detailed in PJM’s recent Periodic Review of Variable Resource Requirement"},{"page":23,"startToken":7664,"endToken":8050,"text":"23 \nsufficient new capacity is not and perhaps cannot come online as fast as new large load demand, \nat any price. In the face of this reality, PJM is crafting a deliberate market design during resource \nadequacy shortfall crisis in which the capacity market is not aiming to procure supply for certain \nnew large loads because they will be subject to curtailment and not served by system resources \nduring times of system strain. PJM’s proposal thus ensures the capacity market is accurately \nseeking to procure capacity sufficient to serve the transmission system needs during the periods \nwhen IRAS applies. Market design that recognizes IRAS new large loads are not capacity backed \nis appropriate and beneficially prevents distorted price signals that are incapable of materializing \nnew supply. Lastly, the exclusion of this demand from the VRR Curve is not permanent, such \ntreatment only lasts while IRAS is active, and Eligible New Large Loads are subject to potential \ncurtailment during IRAS actions. Once PJM achieves capacity sufficiency for the requisite three-\nyear period and IRAS goes dormant, the load that was previously subject to IRAS no longer falls \nunder the definition of Eligible New Large Loads and would be incorporated back into the \ndemand curve. Again, this matches both demand and supply fundamentals because when IRAS is \nnot in effect—meaning when demand and supply are balanced—the capacity market is expected \nto procure sufficient resources to serve all loads.  \nProtestors appear to recognize that PJM’s decision to exclude demand from large loads \nthat is not matched with commensurate new supply from the VRR Curve is necessary to ensure \n \n(VRR) Parameters, the industry has hit a supply chain wall that has a project schedule timeline of \nthe Reference Resource technology longer than the three-year-forward market.”); see also \nSynapse Energy Economics et al., “Assessing Electricity Resource Adequacy in Pennsylvania \nand PJM”, prepared on behalf of the Pennsylvania Public Utility Commission (Sept 14, 2026), \nhttps://www.puc.pa.gov/media/4044/2026_assessing_electricity_resource_adequacy_in_pa_and_\npjm.pdf (finding PJM’s Loss of Load Expectation planning criterion is not met by 2027, and is \nworse than that criterion by a factor of six by 2030, under the Reference Case that factors in \nPJM’s interconnection queue reforms, including the Reliability Resource Initiative and \nExpedited Interconnection Track, and PJM’s RBP)."},{"page":24,"startToken":8050,"endToken":8381,"text":"24 \nthat residential and existing commercial customers’ capacity rates do not increase as large loads \nconnecting to the grid continue to accelerate.52 But Protestors reveal their paper-thin adherence \nto the Ratepayer Protection Pledge, as they nevertheless argue that PJM’s only option is to \nprocure supply for all new large loads through the capacity market, driving capacity market \nprices in PJM even higher and worsening the affordability crisis in the region. Fortunately for the \nregion, PJM’s hands are not tied as the Protestors insist. PJM has proposed a just and reasonable \nwholesale market scheme that, on an interim basis during times of sustained capacity shortage, \nprovides for more limited service in return for the potential for wholesale compensation to the \ntypes of new large load additions that would otherwise pose unique and serious operational \nchallenges to the transmission system. PJM’s proposal is a just and reasonable approach to \naddressing the severe challenges faced by the region.     \nPJM’s proposal to curtail Eligible New Large Loads prior to calling on Pre-Emergency \nLoad Management is likewise critical to mitigate existing customers’ exposure to curtailment \nrisk and increased capacity costs caused by large loads that do not bring their own capacity, and \nis a just and reasonable rate. If demand response were called prior to curtailment of Eligible New \nLarge Loads, demand response would be called upon more frequently due to the growing \ncapacity shortage in PJM and the need to serve non-capacity backed new large loads. This in turn \nwould result in existing customers sharing the increased cost of calling on the demand response \nthat is due to large load growth, diluting the incentive for new large loads to procure their own \ncapacity. Moreover, if called upon too frequently, demand response resources will be less likely \nto register over time, reducing the capacity available to serve the region at a time when every \nresource that can be quickly brought online is needed. Again, PJM’s proposal to expose the new \n \n52 Google Protest at 14."},{"page":25,"startToken":8381,"endToken":8499,"text":"25 \nlarge loads that are causing the operational risks to the system to bear those risks directly, where \nthe hypothetical alternative of driving capacity prices ever higher could not actually produce new \nsupply fast enough to avoid operational risks, is a just and reasonable choice. \nIII. \nCONCLUSION \nFor the foregoing reasons, Governor Shapiro respectfully requests the Commission to \naccept PJM’s proposal, subject to modification consistent with NRG as necessary to ensure its \nimplementation as soon as possible. \n \n \nRespectfully submitted, \n/s/ Kim Smaczniak \nKim Smaczniak \nMiles Farmer \nAvi Zevin \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nkim.smaczniak@rosellellp.com \nmiles.farmer@rosellellp.com \navi.zevin@rosellellp.com \nnathan.lobel@rosellellp.com"},{"page":26,"startToken":8499,"endToken":8559,"text":"26 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: September 16, 2026 \n/s/ Nathan Lobel \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nnathan.lobel@rosellellp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":882,"startToken":0,"endToken":126},{"p":1,"at":882,"title":"I. SUMMARY","method":"printed heading","endPage":7,"endAt":3,"startToken":126,"endToken":2074},{"p":7,"at":3,"title":"II. ANSWER IN SUPPORT OF IRAS","method":"printed heading","endPage":7,"endAt":35,"startToken":2074,"endToken":2080},{"p":7,"at":35,"title":"A. IRAS properly targets wholesale sales and reliable operation of the bulk","method":"printed heading","endPage":12,"endAt":4,"startToken":2080,"endToken":3724},{"p":12,"at":4,"title":"B. PJM’s proposed compensation framework provides appropriate solicitude to","method":"printed heading","endPage":15,"endAt":1470,"startToken":3724,"endToken":5028},{"p":15,"at":1470,"title":"C. IRAS is not unduly discriminatory.","method":"printed heading","endPage":20,"endAt":281,"startToken":5028,"endToken":6535},{"p":20,"at":281,"title":"D. IRAS is just and reasonable because it will encourage investment in new","method":"printed heading","endPage":25,"endAt":287,"startToken":6535,"endToken":8426},{"p":25,"at":287,"title":"III. CONCLUSION","method":"printed heading","endPage":26,"endAt":4,"startToken":8426,"endToken":8500},{"p":26,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":26,"endAt":380,"startToken":8500,"endToken":8559}]}