{"document":{"slug":"rec-20260917-5316","title":"Answer of PJM Power Providers Group in response to PJM Interconnection, L.L.C.'s 09/10/2026 Motion for Leave to Answer and Answer","issued":"2026-09-17","accession":"20260917-5316","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"PJM Power Providers Group","kind":"answer","file":"sources/filings/text/20260917-5316_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260917-5316","tier":"record","sha256":"7e709f60ad3c63d17091f3a04eba402ef116b83465a60c6b989271e359ceb47c","pages":11,"tokens":3078,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":361,"text":"1 \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n) \n \nDocket No. ER26-3380-000 \n \n \n \n \nANSWER1 OF THE PJM POWER PROVIDERS GROUP \n \n \nThe PJM Power Providers Group2 (“P3”) submits these comments in response to a \nspecific response and justification offered by PJM Interconnection, L.L.C. (“PJM”) in its \nSeptember 10, 2026, Motion for Leave to Answer and Answer (“Answer”) in the above \nproceeding.3   On page 47 of its Answer, PJM attempts to justify Reliability Backstop \nProcurement (“RBP”) resources offering into capacity auctions as price-takers by arguing that \n \n1 This Answer is in response to PJM’s Motion for Leave to Answer and Answer filed last week on September 10, \n2026.  Although the Commission’s procedural rules do not provide for answers to answers as a matter of right, the \nCommission has allowed answers where, as here, the answer provides further explanation or otherwise helps ensure \na full and complete record. See, e.g., Empire Pipeline, Inc., 164 FERC ¶ 61,076 P 9 (2018), PJM Interconnection, \nL.L.C., 104 FERC ¶ 61,154, at P 14 (2003), on reh’g, 109 FERC ¶ 61,236 (2004); Williams Energy Mktg. & Trading \nCo. v. Southern Co. Servs., Inc., 104 FERC ¶61,141, at P 10 (2003); Ameren Servs. Co., 100 FERC ¶ 61,135, at P 15 \n(2002), on reh’g, 103 FERC ¶ 61,178 (2003). \n2 P3 is a non-profit organization dedicated to advancing federal, state and regional policies that promote properly \ndesigned and well-functioning electricity markets in the PJM Interconnection, L.L.C. (“PJM”) region. Combined, P3 \nmembers own over 108,000 MWs of generation assets and produce enough power to supply over 63 million homes \nin the PJM region covering 13 states and the District of Columbia. For more information on P3, visit \nwww.p3powergroup.com.  The comments contained herein represent the position of P3 as an organization, but not \nnecessarily the views of any particular member with respect to any issue.  On August 4, 2026, P3 filed a doc-less \nMotion to Intervene in this proceeding. \n3 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3380-000,  \nSeptember 10, 2026 (“PJM September 10, 2026 Answer”)."},{"page":2,"startToken":361,"endToken":671,"text":"2 \n \nFERC has “consistently rejected the position that requiring resources that are procured outside of \na capacity market to offer into the capacity market as price takers would unjustly and \nunreasonably distort or suppress capacity market clearing prices.”4 \nP3 is baffled by this logic.   PJM should know and understand that Reliability Must Run \n(“RMR”) contracts that are short term and only executed with the intention that they will go \naway as soon as possible are fundamentally different than RBP capacity commitments which will \nbe actively serving resources in the PJM region for at least 15 years and most likely beyond.   \nMoreover, PJM is asking FERC to buy into “two wrongs make a right” logic by asking the \nCommission to repeat a policy that is not part of a properly designed market and that PJM \nhistorically opposed (only changing positions recently).   This is not sound logic or reasoned \ndecision-making, and the Commission should specifically reject it or replace it with an \nalternative that is less damaging to the long-term health of the market and resource adequacy in \nthe region. \nThe Commission cannot turn a blind eye to the long-term implications of increasing the \nvolume of megawatts that PJM would require to offer into the auction at zero.   It only stands to \nreason that each additional MW that is required to participate as a price taker will only drive \nmore megawatts to demand out of market support or leave PJM as markets are increasingly \nundermined by regulatory interventions into a market that aspires to be competitive.  As \nresources continue to be driven from PJM’s markets, resource adequacy issues will worsen in \nPJM, and consumers will pay more overall.  If the Commission is serious about having a \nfunctionally competitive market in PJM that will deliver on the vision of reliability at the least \n \n4 PJM September 10, 2026 Answer at page 47."},{"page":3,"startToken":671,"endToken":1042,"text":"3 \n \ncost to consumers, as P3 believes it is, it should send a message to PJM in this proceeding that \nout of market revenues from RBP-support should not be a vehicle to undermine the competitive \ncapacity market upon which 67 million consumers rely. \nP3 members have taken various positions on the underlying filing in this proceeding5; \nhowever, the organization wholly rejects the idea that because FERC approved certain RMRs as \nprice-takers in PJM that the Commission should require that RBP capacity resources must be \noffered into capacity auctions as price takers.  PJM’s argument relies on highly limited \nprecedent6, conflates fundamentally distinct reliability mechanisms, and ignores the severe, long-\nterm market degradation to ongoing resource adequacy that PJM’s proposal will inflict on the \nPJM footprint and the overall consumer cost impacts that it will have.     \n1. RMR Contracts Are Fundamentally Distinct from RBP Capacity \n \nImportantly, PJM misreads its own precedent.  For example, the case PJM cites on pages \n47 and 48 clearly limited the applicability of the RMR zero offer rule to only two BRAs.7  While, \nthat ruling was extended by two years to accommodate a known transmission issue, PJM’s \nsuggestion that all RMRs are required to offer as price takers for all time is simply not true based \non PJM’s tariff or FERC orders.   \n \nBut even if PJM’s preferred reading of FERC’s orders and its tariff were correct, its \nreliance on RMR precedent is misplaced because RMR contracts and RBP resources serve \n \n5 See Motion to Intervene and Request for Clarification of Talen Energy Corporation, Docket No. ER26-3380-000, \nAugust 21, 2026; See Limited Protest of the NRG Companies, Docket No. ER26-3380-000, August 21, 2026; See \nLimited Protest of Vistra Corp., Docket No. ER26-3380-000, August 21, 2026; See Limited Protest of Constellation \nEnergy Generation, LLC, See Motion to Intervene and Comments of CPV Power Holdings, Docket No. ER26-3380-\n000, August 21, 2026. \n6 PJM cites PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 50 (2025) for the proposition that RMR resources \nshould be included in capacity auctions as price takers, but does not mention that the Commission limited that price \ntaker participation to two auctions. \n7 PJM September 10, 2026 Answer at pages 47 and 48 (notes 136-138)."},{"page":4,"startToken":1042,"endToken":1330,"text":"4 \n \ncompletely different structural functions.  RMR resources are localized, short-term, stop-gap \nmeasures designed to keep retiring, uneconomic generators online temporarily to resolve \nimmediate transmission or operational reliability constraints.  RBP capacity is a multi-year, \nforward procurement mechanism involving long-term commitments (up to 15 years) intended to \nbring significant volumes of new generation online to satisfy steep, multi-gigawatt load growth \n(largely driven by data centers).    \nConflating short-term retention of legacy units to resolve transmission constraints with \nlong-term, multi-gigawatt new entry ignores the difference in scale and market impact.   RMR \ncontracts are designed to be short-term propositions for relatively small amounts of power (about \n2 GWs in the case of Brandon Shores and Wagner), RBP resources are not.   RBP resources are \ndesigned to be on-going and can be significantly larger, potentially over 6.8 GWs. Dumping \npotentially thousands of megawatts of long-term RBP capacity into RPM auctions as price takers \nwill severely distort market-clearing signals at a regional scale, far beyond the hyper-local \nimpact of a typical RMR contract – which is time bound and will result in the unit leaving the \nmarket.   Apples and oranges come to mind. \n2. \"Two Wrongs Don't Make a Right\":  RMR Precedent Is Limited and Should Not Be \nExpanded \nPJM’s primary defense for price-taker treatment rests on the Commission’s precedent \nregarding RMR resources. However, doubling down on a historically flawed policy does not \nmake it just and reasonable.   P3 extensively protested PJM’s policy reversal to include RMR \nunits in capacity auctions as price takers.    As P3 offered at the time, “While P3 appreciates the \ndesire to address the concerns raised by state and consumer interests, if approved, the proposed \nchanges will further send PJM down a road that will only prolong the successful resolution of the"},{"page":5,"startToken":1330,"endToken":1646,"text":"5 \n \nissues that created the RMR in the first instance while unnecessarily compromising reliability.”8   \nP3 regrets this prognostication being accurate and fears that PJM is pushing the Commission \nfurther down this reliability-threatening and more costly path. \nPJM itself previously recognized the market-distorting impacts of injecting zero-priced \nRMR offers into the supply stack and the long-term resource adequacy and cost impacts that \nsuch an action could have.  Forcing out-of-market supported resources to offer as price takers \ncreates artificial supply at a $0 price point which will push existing resources out of PJM \nexacerbating the current resource adequacy shortfall and consumer cost issues.  Adopting this \napproach for RBP capacity expands a limited construct, compounding market disruption and \nundermining market efficiency and resource adequacy across the RTO.  As PJM offered prior to \nits policy reversal, “requiring participation of a deactivating unit in the capacity auction under the \nexisting RMR agreements could distort the price signal and fail to incent the new build …… \nsuppressing this price signal now is likely to result in greater reserve shortfalls in the future.  \nAdditionally, suppressing this price signal now could discourage other forms of resources, such \nas Demand Response and other resources that may be available on shorter notice from increasing \ntheir market participation precisely at the time they are most needed.”9    \nSince PJM is clearly aware of the damage that mandated price taking capacity has on the \nmarkets, resource adequacy and ultimately consumer costs, it is troubling that it is asking FERC \nto yet again endorse and significantly expand a policy that is antithetical to sound market design.   \nMoreover, and importantly, the Commission’s 2025 decision to require RMR units to participate \n \n8 See Comments and Request to Sever of the PJM Power Providers Group, Docket No. ER25-682-000, January 6, \n2025, at page 6.  \n9 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2024/20240919-pjm-board-\nresponse-consumer-advocates-letter-re-urgent-reforms-pjm-capacity-market-re-reliability-must-run-\nunits.ashx?_sp=0238a5f6-837e-4142-a86f-f8b8f54cd74a.1789491722754"},{"page":6,"startToken":1646,"endToken":1991,"text":"6 \n \nin capacity auctions as price takers was specifically time-limited to two auctions when it was \napproved so as to avoid sustained disruption to the market.10  The Commission and commenters \nrelied heavily on the fact that PJM was making a limited exception and not creating an ongoing \nexpectation that RMR resources would participate in auctions as price takers.  Yet, here, PJM is \nseeking to expand this limited exception to a full on market principle as significant amounts of \ncapacity could be offered into the auction for up to 15 years at zero – at the very time PJM is \nseeking to send price signals to encourage new entry.   This tortured logic must be rejected. \n4.  Long-Term Price Suppression Destroys Market Performance and Reliability \nP3 echoes and supports the arguments raised by NRG Energy and Constellation:  price-taker \ntreatment for out-of-market capacity destroys the long-term integrity and performance of the \ncapacity market; resource adequacy will suffer and costs will increase as a result.  \nWhen RBP supply is forced into RPM auctions at $0/MW-day, it artificially shifts the supply \ncurve to the right without a corresponding shift in auction demand, crashing RPM clearing \nprices.  The long-term ramifications of this artificial suppression are severe:  \n \nPremature Exits: Depressed clearing prices prevent existing, uncontracted merchant \ngenerators from recovering their avoidable costs, forcing premature retirements or exits \nof needed capacity.  \n \nDeterrence of Unsubsidized New Entry:  Investors will not commit merchant capital to \nnew supply if the capacity market signals are systematically suppressed by multi-\ngigawatt backstop procurements offered at zero.  \n \nPerpetual Backstop Dependence:  By chilling competitive investment and accelerating \nretirements, PJM creates a self-fulfilling crisis where the competitive market continually \nclears short, forcing PJM to rely indefinitely on administrative backstop procurements. \n \nResource Adequacy Issues in PJM will be Exacerbated:  Reliability will most \ncertainly be compromised as existing resources are incented to exit, and new capacity \n \n10 In FERC Docket no. ER25-682, the Commission required that PJM make changes in its compliance to clarify the \ntime-limited nature of RMR units participating in capacity auctions as price takers.  See Order at paragraph 54."},{"page":7,"startToken":1991,"endToken":2315,"text":"7 \n \nresources will struggle with the decision to participate in capacity auctions or backstop \nprocurements. \n \nConsumers will Pay more for Resource Adequacy.   Over the long term, reliance on \nout of market supported resources offering as price takers will drive overall prices higher \nas the ability to garner out of market support replaces efficiency as a capacity resource’s \nprimary motivation. \n \n5.   A Just and Reasonable Path Forward \nMost concerning, PJM is asking FERC to take a further step down what is an \nextraordinarily slippery slope.  Resources that are receiving out of market financial support need \nto be appropriately recognized in the capacity market if the capacity market is going to remain \nthe engine for reliability at the least cost for consumers in PJM.   This is the same challenge that \nwas presented in MOPR where the Commission had to wrestle with the question of state \nsubsidies distorting wholesale market pricing.  In the instant case, the question is how to handle \nthe participation of resources that PJM is procuring to meet system load outside of the capacity \nmarket. \nFortunately, unlike the MOPR, there are easy answers to this question.  For example, \nNRG and Constellation include proposed paths forward in their pleadings in this docket.  \nAnother simple to implement path forward would be to have RBP resources offer at their \ncontract prices.  Specifically, RBP resources will have an easily identified contracted price that is \nreflective of the capacity cost necessary to support the resource.  That price will also be at or \nbelow a price cap set by the Commission in this proceeding.  The Commission can maintain the \nfidelity of the market by having the capacity participate in the market at its contract price.11  The \nCommission could easily direct PJM to make this change as part of its compliance filing and in \n \n11 If the contracted RBP price happens to be above the BRA price cap, P3 would support the BRA price cap as the \nRBP offer price."},{"page":8,"startToken":2315,"endToken":2657,"text":"8 \n \ndoing so significantly reduce the long-term market damage that could be caused by resources \nwith significant capacity costs participating in the market as price takers.  \nIn the alternative, FERC could defer the question of RBP capacity participation in \nauctions to a future proceeding.  PJM and FERC will not know how much capacity is procured \nthrough the RBP process or the location of that capacity until later this year after the auction has \nbeen completed.  In addition, all RBP capacity can come online as late as June 1, 2032.  Finally, \nand importantly, the auction that will occur in December of this year is for the 29/30 delivery \nyear which is bound by both a cap and a floor and, by PJM’s own declaration, “...there will need \nto be substantial load reduction for the auction to clear at a price lower than the ‘collar cap.’”12  \nIn other words, if any RBP capacity participates in the December auction, that capacity is highly \nunlikely to impact the outcome.  Given all these factors, the need to resolve the significant \nquestion of how best to reflect RBP capacity in capacity auctions going forward for potentially \ntwo decades can easily be addressed in a separate, more thoughtful, context. \nThe Commission should provide PJM guidance that RBP resources are not sufficiently \nsimilar to the limited RMR precedent that PJM cites and direct PJM as part of its holistic \nresource adequacy market review to consider the question of how RBP capacity participates in \ncapacity auctions in a way that reflects its capacity value and does not undermine the integrity of \nthe market for the resources that are not receiving out of market support.  If the Commission \ndoes not want to defer the question to that initiative, P3 would suggest that the question be \naddressed in a paper hearing that commences after the quantity and location of RBP capacity is \nknown and concludes before the BRA in May 2027 for the 29/30 delivery year. \n \n12 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260901-pjm-president-\nceo-response-to-md-office-of-peoples-counsel-letter-regarding-base-residual-auction-2029-2030.pdf"},{"page":9,"startToken":2657,"endToken":2925,"text":"9 \n \n6.   At Minimum, the Commission Must Reject PJM’s Logic \nIn the event that the Commission is inclined to accept PJM’s proposal to include RBP \ncapacity in the auction as price takers immediately, P3 urges the Commission to reject PJM’s \nassertion that the Commission is indifferent to the price suppression impacts and that RMR \ncontracts are the same as RBP contracts.   RMR contracts and RBP commitments are \nfundamentally different propositions and should not be subject to the same regulatory structures.   \nThe Commission recognized the importance of limiting mandated price taking capacity in 2025 – \nit should do so again here.    \nCONCLUSION \nThe Commission should not accept PJM’s attempt to justify zero-dollar price-taker \ntreatment for multi-gigawatt, 15-year Reliability Backstop Procurement commitments by hiding \nbehind short-term Reliability Must Run precedent that is explicitly very narrow and relies on \nfundamentally broken logic.  Conflating temporary legacy unit retention with long-term new \ngeneration entry is not justified; it completely ignores market fundamentals and threatens to \nentrench administrative price suppression across the entire regional footprint.  By systematically \ndepressing capacity clearing prices, this proposal will accelerate premature plant retirements, \nchill vital merchant investment, and trap the region in a self-fulfilling crisis of perpetual resource \nadequacy shortfalls, backstop dependence and increased overall costs.  Something the \nCommission should be highly motivated to avoid. \nThe Commission must reject PJM’s proposal to treat out-of-market backstop capacity as \nzero-priced supply and preserve the long-term integrity of the wholesale market.  At minimum, \nFERC should require RBP capacity as suggested by NRG or Constellation or to offer at its actual \ncontract price, sending a clear signal that out-of-market revenues cannot be leveraged to"},{"page":10,"startToken":2925,"endToken":3006,"text":"10 \n \ndismantle a competitive framework that 67 million consumers rely upon for cost-effective, \nreliable power.  P3 also supports deferring the question until more information is known about \nthe quantity, timing and location of any RBP capacity so such a significant question can be \nresolved more thoughtfully. \n  \nRespectfully submitted,  \n \nOn behalf of The PJM Power Providers Group  \n \nBy:  /s/ Glen Thomas \nGlen Thomas \nGT Power Group  \n101 Lindenwood Drive, Suite 225  \nMalvern, PA 19355  \ngthomas@gtpowergroup.com  \n \n \n \n \n \n \n610-768-8080 \n \n \n \n Dated: September 17, 2026"},{"page":11,"startToken":3006,"endToken":3078,"text":"11 \n \n   \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the Official Service List compiled by the Secretary in this proceeding.   \n \nDated at Washington, D.C., this 17th day of September, 2026. \n \n \nOn behalf of the PJM Power Providers Group \n \n \n \n \nBy:  /s/ Diane Slifer \nDiane Slifer \nGT Power Group  \n101 Lindenwood Drive, Suite 225  \nMalvern, PA 19355  \ngthomas@gtpowergroup.com  \n \n \n \n \n \n \n610-768-8080"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":9,"endAt":644,"startToken":0,"endToken":2756},{"p":9,"at":644,"title":"CONCLUSION","method":"printed heading","endPage":11,"endAt":14,"startToken":2756,"endToken":3007},{"p":11,"at":14,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":494,"startToken":3007,"endToken":3078}]}