{"document":{"slug":"rec-20260918-5119","title":"Motion to Intervene and Comments of North American Electric Reliability Corporation et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing","issued":"2026-09-18","accession":"20260918-5119","docket":"ER26-3650-000","group":"MISO interconnection reliability requirements for large loads","filer":"North American Electric Reliability CorporationMidwest Reliability OrganizationReliability First Corporation ,SERC Reliability Corporation ,","kind":"comments","file":"sources/filings/text/20260918-5119_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5119","tier":"record","sha256":"e5387b95b95581769dd1fd058c13c1eaf6e2fd4f2aacd9fe3f13f396b564464c","pages":10,"tokens":2563,"emptyPages":[],"textThemes":["registry"]},"pages":[{"page":1,"startToken":0,"endToken":273,"text":"1 \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent \nIndependent \nSystem \nOperator, Inc. \n) \n) \n) \nDocket No. ER26-3650 \nMOTION TO INTERVENE AND COMMENTS OF THE \nNORTH AMERICAN ELECTRIC RELIABILITY CORPORATION, MIDWEST \nRELIABILITY ORGANIZATION, RELIABILITY FIRST CORPORATION, AND SERC \nRELIABILITY CORPORATION \nOn August 28, 2026, the Midcontinent Independent System Operator, Inc. (“MISO”) filed \nproposed revisions to MISO’s Open Access Transmission, Energy and Operating Reserve Markets \nTariff (“Tariff”) with the Federal Energy Regulatory Commission (the “Commission” or “FERC”) \nto establish certain Interconnection Reliability Requirements for Large Loads (the “IRR \nProposal”).1  The IRR Proposal2 was MISO’s initial step responding to the Commission’s June \n2026 Order Instituting Proceeding Under Section 206 of the Federal Power Act directing MISO \nto examine tariff provisions to support the interconnection of large load with the Bulk-Power \nSystem (“BPS”).3  While acknowledging regional differences and market rules, the Commission \nhighlighted five categories of focus:  (i) efficient transmission service application and study; (ii) \npotential cost shifting; (iii) co-location arrangements; (iv) new transmission services for flexible \nlarge loads; and (v) a process to study generating facilities serving electrically proximate large \n1\n18 C.F.R. §§ 385.206, 385.212, and 385.214 (2026). \n2\nMidcontinent Independent System Operator, Inc.’s Interconnection Reliability Requirements for Large \nLoads, Docket No. ER26-3650 (Aug. 28, 2026) [hereinafter IRR Proposal]. \n3\nSee, e.g., Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section \n206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order” or “SCO”).  The Commission \nissued parallel orders tailored to five other regional transmission organizations/independent system operators \n(“RTOs/ISOs”), which are together referred to as the “Show Cause Orders.”"},{"page":2,"startToken":273,"endToken":683,"text":"2  \n \n \nloads and large co-located load.  MISO’s IRR Proposal stated that it intended to promote visibility, \nramp rate, and disturbance ride-through requirements applicable to large loads. \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure, the North American Electric Reliability \nCorporation (“NERC”), Midwest Reliability Organization (“MRO”), ReliabilityFirst Corporation \n(“RF”), and SERC Reliability Corporation (“SERC”) (collectively, “NERC and the Regional \nEntities”) move to intervene and comment on the IRR Proposal.4  NERC and all six Regional \nEntities (collectively, the “ERO Enterprise”) are dedicated to ensuring effective and efficient \nreduction of risks to the reliability and security of the grid, including supporting entities in \nidentifying and mitigating potential threats to BPS reliability.  \nNorth America is entering a period of unprecedented load growth, with NERC Long-Term \nReliability Assessments (“LTRAs”) noting that demand is higher than at any point in the last two \ndecades.5   This projected increase in North American electricity demand is largely driven by \ncomputational load, such as data centers for artificial intelligence and other uses underpinning the \ndigital economy, interconnecting with the BPS.6 MISO’s IRR Proposal states, for example, that, \n \n4  \nNERC accomplishes its mission with the support of the six Regional Entities who help NERC support \nreliability across various interconnections with differing needs and characteristics. The six Regional Entities are  \nMRO, Northeast Power Coordinating Council, Inc., RF, SERC, Texas Reliability Entity, Inc., and Western \nElectricity Coordinating Council. NERC’s relationship with the Regional Entities is governed by Regional \nDelegation Agreements or “RDAs” filed with the Commission every five years. 18 C.F.R. § 39.8.   \n5  \nNERC, 2025 Long-Term Reliability Assessment (Jan. 2026), https://www.nerc.com/globalassets/our-\nwork/assessments/nerc_ltra_2025.pdf [hereinafter 2025 LTRA]; NERC, 2024 Long- Term Reliability Assessment at \n8 (Dec. 2024, updated July 2025), \nhttps://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%20Term%20Reliability%20\nAssessment_2024.pdf. NERC develops the Long-Term Reliability Assessments annually in accordance with the \nNERC Rules of Procedure and Title 18, § 39.112 of the Code of Federal Regulations; this is also required by Section \n215(g) of the Federal Power Act, which instructs NERC to conduct periodic assessments of the North American \nBPS. \n6  \nId.  Please note, in using the term computational load, NERC references that term as used in its assessments \nand draft registry criteria and Reliability Standard work.  MISO’s IRR Proposal includes MISO’s definition of \ncomputational load which may have differences."},{"page":3,"startToken":683,"endToken":876,"text":"3  \n \n \n“[a]s NERC has observed [in the LTRA], the largest contributor to this accelerated demand growth \nis data center additions, with 18 GW of data center loads projected [in MISO] by 2035.”7   \nThe ERO Enterprise has been working urgently with stakeholders on clear and consistent \nmeasures to support the reliable interconnection of computational loads. As outlined in NERC’s \nlarge load action plan, these efforts include revisions to NERC registry criteria and Reliability \nStandards for submission to the Commission by year-end, and further efforts such as disturbance \nride-through performance requirements are underway with filing(s) to the Commission targeted in \n2027.  MRO, RF, and SERC are the NERC Regional Entities which support activities in the MISO \narea.  Therefore, NERC and the Regional Entities move to intervene and comment to provide \ninformation on the record regarding efforts to harmonize these activities with those being led by \nstakeholders, such as MISO, under parallel processes.8 \n \n7  \nIRR Proposal, at 5 (citing the 2025 LTRA, at 15). \n8  \nThese comments are focused only on matters as related to section 215 of the FPA, the ERO Enterprise \ndeclines to comment on matters outside of its purview."},{"page":4,"startToken":876,"endToken":1134,"text":"4  \n \n \nI. \nNOTICES AND COMMUNICATIONS \nNotices and communications with respect to this filing may be addressed to the following:9 \nCandice Castaneda*    \nSenior Counsel \nMarisa Hecht* \nNorth \nAmerican \nElectric \nReliability \nCorporation  \n1401 H Street, N.W., Suite 410  \nWashington, D.C. 20005  \n(202) 400-3000  \n(202) 644-8099 – facsimile  \ncandice.castaneda@nerc.net \nmarisa.hecht@nerc.net \n \nJulie Peterson* \nVice President General Counsel and Corporate \nSecretary \nMidwest Reliability Organization \n380 St. Peter Street Suite 800 \nSaint Paul, MN 55102 \nJulie.Peterson@mro.net \nNiki Schaefer* \nVice President and General Counsel \nReliabilityFirst Corporation \n3 Summit Park Drive, Suite 600 • Cleveland, \nOhio  44131 \nniki.schaefer@rfirst.org \n \nHolly Hawkins* \nVice President and General Counsel \nRebecca Poulsen* \nAssistant General Counsel \nSERC Reliability Corporation \n13320 Ballantyne Corporate Place, Suite 200 \nCharlotte, NC  28277 \n704-357-7372 \nhhawkins@serc1.org \nrpoulsen@serc1.org \n \nII. \nMOTION TO INTERVENE \nNERC and the Regional Entities have a substantial interest in this proceeding as the IRR \nProposal includes market rules which would complement their activities under section 215 of the \nFPA.10  By enacting the Energy Policy Act of 2005 and section 215 of the FPA,11 Congress \nentrusted the Commission with approving and enforcing rules to ensure the reliability of the BPS, \n \n9  \nPersons to be included on the Commission’s service list are identified by an asterisk. NERC respectfully \nrequests a waiver of the Commission’s rules 18 C.F.R. § 385.203 (2016) to allow the inclusion of more than two \npersons on the service list. \n10  \nSee, e.g., IRR Proposal, at 3. \n11  \n16 U.S.C. § 824o."},{"page":5,"startToken":1134,"endToken":1473,"text":"5  \n \n \nand with certifying an Electric Reliability Organization (“ERO”) charged with developing and \nenforcing mandatory Reliability Standards, subject to Commission approval. The Commission \ncertified NERC as the ERO in 2006.12 As the ERO, NERC’s mission is to ensure effective and \nefficient reduction of risks to the reliability and security of the grid.13  \nNERC is responsible for developing and enforcing mandatory Reliability Standards \napplicable to BPS entities on NERC’s compliance registry and conducting assessments of the \nreliability and adequacy of the BPS.14 NERC develops Reliability Standards in accordance with \nSection 300 (Reliability Standards Development) of the NERC Rules of Procedure (“ROP”) and \nthe NERC Standard Processes Manual.15 NERC’s compliance registry includes those entities \nwhich meet registry criteria under Section 500 and Appendix 5B of the ROP.  The ERO Enterprise \nis responsible for monitoring, assessing, and enforcing compliance with Reliability Standards in \nthe United States in accordance with Section 400 (Compliance Enforcement) of the ROP and the \nNERC Compliance Monitoring and Enforcement Program.16 \nSince 2024, the ERO Enterprise has been assessing how to address potential issues \nassociated with large levels of computational load interconnecting with the BPS.  As discussed in \nNERC comments, as supplemented, on the Advanced Notice of Proposed Rulemaking on reforms \n \n12  \nN. Am. Elec. Reliability Corp., 116 FERC ¶ 61,062, order on reh’g and compliance, 117 FERC ¶ 61,126 \n(2006), order on compliance, 118 FERC ¶ 61,030, order on compliance, 118 FERC ¶ 61,190, order on reh’g, 119 \nFERC ¶ 61,046 (2007), aff’d sub nom. Alcoa Inc. v. FERC, 564 F.3d 1342 (D.C. Cir. 2009). \n13  \nNERC, Who We Are, https://www.nerc.com/who-we-are. \n14  \n16 U.S.C. § 824o(d)-(e), § 824o(g). \n15  \nThe NERC Rules of Procedure are available at https://www.nerc.com/globalassets/who-we-are/rules-of-\nprocedure/nerc-rop.pdf. The NERC Standard Processes Manual is available at \nhttps://www.nerc.com/globalassets/who-we-are/rules-of-procedure/Appendix-3A.pdf. \n16  \nThe NERC Compliance Monitoring and Enforcement Program is available at \nhttps://www.nerc.com/globalassets/who-we-are/rules-of-procedure/appendix-4c.pdf."},{"page":6,"startToken":1473,"endToken":1827,"text":"6  \n \n \nto ensure timely and orderly interconnection of large loads,17 NERC has been actively pursuing an \naccelerated action plan to develop (i) technical justification; (ii) registry criteria updates to the \nROP; and (iii) Reliability Standards to account for computational load.18  On July 16, 2026 (the \n“July 16th Order”), the Commission directed NERC to file registry criteria and Reliability \nStandards to address computational load by December 31, 2026.19  The Commission also directed \nNERC to file a work plan by March 1, 2027, detailing next steps for additional Reliability \nStandards pertaining to computational load integration.  As a result, no other party can adequately \nrepresent NERC and the Regional Entities’ interests in this proceeding. Therefore, the parties \nrequest that the Commission grant this motion to intervene and comment as within the public \ninterest.   \nIII. \nCOMMENTS \nConsistent with the July 16th Order, the ERO Enterprise has prioritized near-term measures, \nsuch as foundational Reliability Standards and registry criteria addressing computational loads, \nwhile preserving flexibility for subsequent refinements, such as plans to develop ride-through \nrequirements next year, as additional experience is gained with large load interconnections.20 The \nERO Enterprise is working as quickly as possible with stakeholders to advance integration of \ncomputational load in a manner that sustains continued reliability and resilience. Based on risk \n \n17  \nDepartment of Energy, Secretary of Energy’s Direction that FERC Initiate Rulemaking Procedures and \nProposal Regarding the Interconnection of Larg Loads Pursuant to the Secretary’s Authority Under Section 403 of \nthe Department of Energy Organization Act (Oct. 23, 2025) (“ANOPR”); Interconnection of Large Loads to the \nInterstate Transmission Sys., Notice Inviting Comments, Docket No. RM26-4-000 (Oct. 27, 2025).  \n18  \nComments of the North American Electric Reliability Corporation in Response to Notice Inviting \nComments, Docket No. RM26-4-000 at 1-2, 5-6 (Nov. 21, 2025) (“NERC ANOPR Comments”); NERC Additional \nComments on Large Loads ANOPR (March 20, 2026) (“Supplemental ANOPR Comments”). \n19  \nOrder Directing the North American Electric Corporation to File Reliability Standard(s) Pertaining to \nComputational Load Integration, 196 FERC ¶ 61,031 (2026) [hereinafter July 16th Order].  See also, 16 U.S.C. § \n824o(d)(5). \n20  \nJuly 16th Order at P 11."},{"page":7,"startToken":1827,"endToken":2096,"text":"7  \n \n \nprioritization, the ERO Enterprise and others are working towards foundational expectations to \nmitigate the immediate reliability risks associated with computational load.  MISO’s filing is an \nexample of contributions by those across the electric and computational load industries to advance \nreliability in the face of this change.  Due to the urgency of these near-term measures, the ERO \nEnterprise, MISO, and other stakeholders working to mitigate risk are acting in parallel rather than \nsequentially, creating potential for some differences. While all stakeholders collaborate to \nminimize these differences, different timelines and internal governance processes may yield \nslightly different outcomes.  \nRegardless of the parallel development, MISO’s IRR Proposal seems generally consistent \nwith pending Reliability Standards efforts.  The ERO Enterprise and RTO/ISO stakeholders, \nincluding MISO, have forums and groups established to continue ensuring consistency to the \nextent possible. For example, NERC’s Reliability and Security Technical Committee (“RSTC”) \nsubgroups, computational load drafting team Project 2026-02, the short-term advisory group for \nfoundational standards, and an ERO Enterprise and RTO/ISO computational load advisory group \nprovide crucial input to help synchronize and harmonize parallel efforts advance.  In particular, \nthe RTO/ISO computational load advisory group was developed and designed to foster \ncoordination on these issues, with a specific focus on the potential performance requirements for \ncomputational loads across interconnections.21   \n Through parallel processing, extensive and extraordinary stakeholder outreach, and \ncarefully organized comment periods, NERC is striving to rapidly advance reliability and \nconsistency as knowledge grows.  Despite the urgent and parallel actions, the ERO Enterprise has \n \n21  \nNERC’s large loads action plan webpage provides further examples of outreach and coordination, \nhttps://www.nerc.com/initiatives/large-loads-action-plan."},{"page":8,"startToken":2096,"endToken":2386,"text":"8  \n \n \nretained a transparent  stakeholder process with robust industry involvement, including \ncomputational load entities, that facilitates further harmonization across actions. At each step of \nthe pending project for foundational Reliability Standards, the ERO Enterprise expedited processes \nwhere feasible, while maintaining transparency and effective consensus-building through a \nconcerted effort to involve computational load entities in the standards development process.  At \nthe inception of the Reliability Standards development project, for example, NERC’s Standards \nCommittee appointed a drafting team based on diverse industry experts that included \ncomputational load entities, RTOs/ISOs, and members of NERC Standing Committees.  In light \nof the July 16th Order, the Standards Committee also granted waivers to permit shorter balloting \nand comment periods in the standards development process. Recently, the RSTC applied expedited \nprocessing for a computational load disturbance ride-through performance Standard Authorization \nRequest in anticipation of presenting the request to the Standards Committee in the fall of 2026.  \nThe RSTC meetings in September included multiple presentations on the work being done to study \nand respond to the needs associated with computational load.   \nThe ERO Enterprise anticipates that industry will continue to rapidly refine its \nunderstanding of what is needed to support reliable computational load integration.  As the ERO \nEnterprise and industry learn more about the needs associated with computational load, criteria \n(such as ride-through requirements) may need to be adjusted. Earlier in the year, the RSTC \napproved a roadmap of upcoming high-priority standards development projects – with the most \nurgent being the disturbance ride-through performance project mentioned above. To that end, the \nERO Enterprise requests that the Commission consider expedited evaluation of future efforts \nstating that they seek to harmonize with NERC Reliability Standard requirements.  NERC also \nplans to request expedited Commission review of NERC’s proposed registry criteria and"},{"page":9,"startToken":2386,"endToken":2483,"text":"9  \n \n \nReliability Standards filings later this year to support clear, consistent expectations and help ensure \nthat foundational requirements can begin to become effective before the end of next year. \nIV. \nCONCLUSION \nWHEREFORE, for the reasons stated above, NERC and the Regional Entities respectfully \nrequest that the Commission accept the comments herein. \nRespectfully submitted, \n/s/ Candice Castaneda \n \n \nCandice Castaneda \nSenior Counsel \nNorth American Electric Reliability \nCorporation  \n1401 H Street, N.W., Suite 410  \nWashington, D.C. 20005  \n(202) 400-3000  \n(202) 644-8099 – facsimile  \ncandice.castaneda@nerc.net \n \nCounsel for the North American Electric \nReliability Corporation \n \nDate: September 18, 2026"},{"page":10,"startToken":2483,"endToken":2563,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served a copy of this document upon all parties listed \non the official service list compiled by the Secretary in the above-captioned proceeding, in \naccordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and \nProcedure (18 C.F.R. § 385.2010).  \n \nDated at Washington, D.C., this 18th day of September, 2026.  \n \n \n \n \n \n \n \n \n/s/ Candice Castaneda \n \n \n \n \n \n \n \n \n \n \nCandice Castaneda \n \n \n \n \n \n \n \nCounsel for the North American Electric  \nReliability Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":8,"startToken":0,"endToken":877},{"p":4,"at":8,"title":"I. NOTICES AND COMMUNICATIONS","method":"printed heading","endPage":4,"endAt":1001,"startToken":877,"endToken":1010},{"p":4,"at":1001,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":6,"endAt":890,"startToken":1010,"endToken":1606},{"p":6,"at":890,"title":"III. COMMENTS","method":"printed heading","endPage":9,"endAt":204,"startToken":1606,"endToken":2415},{"p":9,"at":204,"title":"IV. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2415,"endToken":2483},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":563,"startToken":2483,"endToken":2563}]}