{"document":{"slug":"rec-20260918-5286","title":"Limited Protest of Entergy Services, LLC re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing","issued":"2026-09-18","accession":"20260918-5286","docket":"ER26-3650-000","group":"MISO interconnection reliability requirements for large loads","filer":"Entergy Services, LLC","kind":"protest","file":"sources/filings/text/20260918-5286_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5286","tier":"record","sha256":"1b2a5044bc1e148d718cffbdbe3908980572d00bd5550e933c9c038ec4f6869a","pages":58,"tokens":10965,"emptyPages":[21,22,23,24],"textThemes":["registry","study"]},"pages":[{"page":1,"startToken":0,"endToken":253,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nMidcontinent Independent System  \n) \n \n \nDocket No.  ER26-3650-000 \nOperator, Inc. \n \n \n) \n \n \n \nLIMITED PROTEST OF ENTERGY SERVICES, LLC \n \n \nPursuant to Rule 211 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.211, Entergy Services, LLC (“Entergy Services”), on behalf of the Entergy Operating \nCompanies (Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, \nEntergy New Orleans, LLC, and Entergy Texas, Inc.) (collectively, “Entergy”), files this Limited \nProtest in response to the August 28, 2026, filing of the Midcontinent Independent System \nOperator, Inc. (“MISO”).  In that filing, MISO proposes to revise its Open Access Transmission, \nEnergy and Operating Reserve Markets Tariff (“Tariff”) to establish interconnection reliability \nrequirements for Large Loads (the “Filing”).  \n \nEntergy supports adoption of requirements meant to ensure that Large Loads are reliably \nintegrated into the bulk electric system.  Indeed, Entergy has made significant and good faith \nefforts to work with MISO to identify reliability requirements for Large Loads.  Entergy is filing \nthis Limited Protest because, for certain reliability requirements, MISO proposes to include only \ngeneralized requirements in the Tariff, while relegating the operative technical requirements and \nkey numeric thresholds to an unfiled Business Practice Manual (“BPM”).  Specifically, for Large \nLoad forecast data requirements, Phasor Measurement Unit (“PMU”) requirements, Large Load \nride-through requirements, and Large Load ramp requirements, MISO improperly proposes to \ninclude in a BPM the specific requirements that a Transmission Customer serving a Large Load \nwill be required to meet.  Under the Commission’s “rule of reason” test, those requirements must"},{"page":2,"startToken":253,"endToken":578,"text":"2 \n \nbe included in the Tariff. The Commission thus should condition any acceptance of MISO’s \nfiling on a compliance filing as described in Part II.C below.  The Commission also should defer \nthe effective date of the Tariff provisions in the Filing until the compliance filing is accepted.   \nI. \nBACKGROUND \nThe Filing is one of a series MISO is making in response to the Commission’s June 18, \n2026, order instituting a proceeding under Section 206 of the Federal Power Act, directing MISO \nto show cause why its Tariff should not be found unjust and unreasonable for failing to \nadequately address the interconnection and reliable operation of Large Loads.1  The Commission \ngranted MISO a 90-day abeyance to develop its response through the stakeholder process.2  \nIn the Filing, MISO proposes to add a new Module B, Section 37A to the Tariff, \nestablishing interconnection reliability requirements for Large Loads.  New definitions are also \nset forth for “Large Load” (defined as load with demand of 50 MW or more at a single \nsubstation) and “Computational Load” (defined as a Large Load of 25 MW or more of \ninformation-technology demand, such as data centers).3  At the center of this Limited Protest are \nMISO’s proposed new categories of interconnection reliability requirements in the proposed new \nModule.  Those categories include Large Load forecast data requirements, PMU requirements, \nLarge Load ride-through requirements, and Large Load ramp requirements.  While MISO has \nfiled generic Tariff language mandating compliance, key provisions of the forecast data \nrequirements, PMU requirements, ride-through requirements, and ramp requirements are \ncompletely absent from the filing and according to MISO, will be contained in BPMs that in \n \n1 Filing Transmittal at 1; see also Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ \n61,212 at P 57 (“Show Cause Order”), errata notice, 196 FERC ¶ 61,123 (2026). \n2 Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,333 (2026). \n3 MISO Filing Tab A, Proposed Tariff Module B, §§ 1.C, 1.L."},{"page":3,"startToken":578,"endToken":848,"text":"3 \n \nmany cases have not yet been drafted.  At this time, the Entergy Operating Companies are \ninvolved in ongoing negotiations with Large Loads that may not satisfy MISO’s proposed \ngrandfathering criteria at all, or that may only qualify for limited exemptions from certain of the \nreliability requirements.  Others may be similarly situated because the grandfathering criteria are \nnot structured to fully exempt projects that are recently developed (and not yet in service) or in \nthe late stages of negotiations.  Without defined and clear reliability standards, however, Large \nLoads and Transmission Customers lack clarity on how to design data center architecture to \ncomply.       \nII. \n LIMITED PROTEST \nAt the outset, Entergy emphasizes that it supports transparent reliability requirements for \nLarge Loads.  Entergy also supports the ongoing efforts of the North American Electric \nReliability Corporation (“NERC”) to develop reliability standards for Large Loads under its \nauthority as the nation’s Electric Reliability Organization.  Importantly, NERC’s process will \nresult in standards that will apply uniformly across the country. As the Commission recognized \nin the Show Cause Order, large customer projects take significant resources to develop.4  \nEnsuring compliance with reliability requirements is a complex, technical process that may \ninvolve significant capital expenditure depending on the data center design. Yet, to date, MISO’s \nproposed Tariff language lacks essential technical and operational requirements. The undrafted \nBPMs will contain critical details on the specific requirements and how compliance can be \nachieved. Without this transparency, Transmission Customers and Large Loads cannot \nmeaningfully understand the obligations the Tariff would impose, nor evaluate their operational \nor financial impact. \n \n4 E.g., Show Cause Order, 195 FERC ¶ 61,212 at P 9."},{"page":4,"startToken":848,"endToken":1114,"text":"4 \n \n \nA. \nThe Rule of Reason Test \n \nSection 205(c) of the Federal Power Act requires a public utility to file not only its rates, \nbut the practices affecting those rates.5  When determining whether a practice affecting rates \nmust be included in a tariff or may be included in a BPM, the Commission applies a “rule of \nreason” standard.6  Under that standard, a tariff must include all practices that: (a) “significantly \naffect rates, terms, and conditions of service,” (b) are “readily susceptible of specification,” and \n(c) “are not so generally understood in any contractual arrangement as to render recitation \nsuperfluous.”7   \nOn the other hand, “items better classified as implementation details” may be included in \na BPM.8  As the Commission has explained, “[i]t is appropriate for Business Practice Manuals to \ncontain implementation details, such as instructions, guidelines, examples and charts, which \nguide internal operations and inform market participants of how [the RTO] conducts its \noperations under [its Tariff].”9  The information contained in a BPM “is meant to provide further \nexplanation of the [Transmission Provider’s] practices but not significantly affect any rates, \n \n5 16 U.S.C. § 824d(c). \n6 E.g., Southwest Power Pool, Inc., 169 FERC ¶ 61,048 at P 62 (2019) (citing Energy \nStorage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 at P 103 (2018)) (“SPP”). \n7 Id.  \n8 Energy Storage Assoc., 162 FERC ¶ 61,296 at P 103; see also SPP, 169 FERC ¶ 61,048 \nat P 62 (same).   \n9 California Indep. Sys. Operator Corp., 122 FERC ¶ 61,271 at P 16 (2008) (“CAISO”)."},{"page":5,"startToken":1114,"endToken":1407,"text":"5 \n \nterms, or conditions, consistent with the Commission’s ‘rule of reason.’”10  Thus, information \nthat is supplemental and secondary in nature may be included in a BPM. 11   \nThe rule of reason test “requires a case-by-case analysis, comparing what is in the . . . \ntariff against what is in the Business Practice Manuals.”12  A cross-reference cannot be used to \nrelegate to a BPM a rule that should be included a tariff.13 \nB. \nMISO’s Filing Contravenes the Commission’s Rule of Reason that Requires \nthe Operative Reliability Requirements to be Stated in the Filed Tariff, Not \nan Unfiled BPM \nAt the time of this filing, MISO has only provided draft BPM language for disturbance \nride-through and operational forecasting.  However, pending completion of BPMs, MISO has \nproposed other reliability requirements in other presentations or statements.  As Entergy will \nexplain, comparing MISO’s proposed Tariff language for Large Load forecast data requirements, \nPMU requirements, Large Load ride-through requirements, and Large Load ramp requirements \nto MISO’s draft BPM language or other recommendations makes clear that MISO’s filing fails \nthe rule of reason test for those requirements.  MISO improperly proposes to include in a BPM \nthe specific requirements that a Transmission Customer serving a Large Load will be required to \nmeet. \n1. \nLarge Load Forecast Data Requirements \nProposed Section 37A.4 of the Tariff establishes the Large Load forecast data \nrequirements. It comprises a total of two sentences.  First, the proposed Tariff language states \n \n10 California Indep. System Operator Corp., 116 FERC ¶ 61,274 at P 1358 (2006), reh’g \ngranted in part, 120 FERC ¶ 61,271 (2007). \n11  CAISO, 122 FERC ¶ 61,271 at P 104. \n12 California, 116 FERC ¶ 61,274 at P 1370. \n13 Midwest Indep. Transmission Sys. Operator, Inc., 136 FERC ¶ 61,038 at P 11 (2011)."},{"page":6,"startToken":1407,"endToken":1656,"text":"6 \n \nthat, “[p]rior to the later of the Service Commencement Date of a Large Load or September 1, \n2027, a Transmission Customer taking Transmission Service on behalf of a Large Load must \nprovide day(s) ahead and real-time Load Forecasts for a Large Load directly to the Transmission \nProvider to support the Reliability Assessment Commitment (RAC) and Security Constrained \nEconomic Dispatch (SCED) processes, along with other reliability studies.”14  Second, the \nproposed Tariff language provides that the “Load Forecasts shall be updated to reflect the most \ncurrent information on the expected Demand, in accordance with the Business Practices Manual \nfor Large Load.”15  \nLacking from this provision are the basic requirements that establish the core, legally \nbinding terms and conditions for interconnection of large loads.  This section of MISO’s \nproposed Tariff identifies no forecast horizon, no update cadence, no accuracy standard, and no \nconsequence for inaccurate forecasts.16 MISO states only that a Transmission Customer must \nsubmit “day(s) ahead and real-time” forecasts while deferring the substance of every operative \ndetail to the BPM for Large Load. \nThe non-substantive character of MISO’s proposed Tariff in this regard is immediately \napparent when compared to the forecast requirements MISO has proposed in its draft BPM-025-\nr14 for Operational Forecasting, draft section 9 of BPM-032 for Large Loads, attached hereto as \nExhibits A, and B, respectively, and its Large Load Working Group presentation, made public on \n \n14 MISO Filing Tab A, Proposed Tariff Module B, § 37A.4. \n15 Id. \n16 Id."},{"page":7,"startToken":1656,"endToken":1996,"text":"7 \n \nAugust 27, 2026, one day prior to the Filing.17 Each of these documents include specific, \noperative requirements that a Transmission Customer serving a Large Load must satisfy.  For \ninstance, the draft BPM requirements include two mandatory forecasts, on fixed horizons and \ncadences with a delineated “Large Load Hourly Forecast” that must be provided on a minimum \n“168 Hours Out” time horizon and updated at least hourly “by a defined deadline,” and a “Large \nLoad 5-Minute Load Forecast” with a minimum horizon of “6 Hours Out,” which “must be sent \nand processed in MISO’s system at least 9 minutes prior to the start of” the applicable interval.18 \nNext, MISO’s draft BPM requires a specifically-defined forecast submission level, “at the \nCPNode,” with each Large Load “registered to its own dedicated CPNode . . . not [to] be \naggregated or netted across CPNodes,” and the submitted forecast “shall reflect the gross load of \nthe facility” without netting co-located or behind-the-meter generation.19 \nBeyond these clear operative and significantly impactful standards, MISO has proposed, \noutside of its Filing, defined accuracy metrics and a forecast-accuracy incentive that will in turn \nbe used to allocate associated costs.  As stated in its Large Load Working Group Presentation of \nAugust 27, 2026: “Cost-causation allocation can strengthen the incentive for Large Loads to \n \n17 See MISO, Large Load Operational Forecast Requirements (LLWG-2026-4A), Large \nLoad Working Group (Aug. 27, 2026)  available at \nhttps://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin\ng%20Requirements%20(LLWG-2026-4a)%20Presentation777222.pdf (last accessed Sept. 18, \n2026, attached hereto at Exh C); draft BPM-025-r14, Operational Forecasting § 3.2 available at \nhttps://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin\ng%20BPM-025-r14%20Draft%20(LLWG-2026-4A)777225.pdf (last accessed Sept. 18, 2026, \nattached hereto at Exh. A); draft BPM-032, Large Load § 9 available at \nhttps://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin\ng%20BPM-032%20LL%20Draft%20(LLWG-2026-4A)777226.pdf (last accessed Sept. 18, \n2026, attached hereto at Exh. B). \n18 See Operational Forecasting Business Practices Manual BPM-025-r13 at 21. \n19 Id."},{"page":8,"startToken":1996,"endToken":2251,"text":"8 \n \nsubmit accurate forecasts by assigning forecast-related costs to the errors that create them. The \nmain cost channels are hourly make-whole / commitment impacts, 5-minute balancing and \ncongestion impacts, and real-time energy price impacts.”20   \nThese requirements are not implementation details, set apart as instructions to an \nunderlying substantive Tariff provision, or secondary in nature to the Tariff.  Rather, they are the \nbasic, specific requirements that a Transmission Customer must meet in order to satisfy the \nLarge Load forecast data requirement, and they are key elements in MISO’s proposed reliability \nprogram.  \nA measure to determine the substantive versus secondary impact of MISO’s proposed \nforecasting requirements is to view them from the lens of potential cost of compliance.  Whether \na Transmission Customer must maintain a rolling 168-hour hourly forecast updated hourly and a \nrolling 6-hour, 5-minute forecast delivered at least 9 minutes ahead of each interval dictates the \nmetering equipment, associated software systems, and personnel staffing a Large Load must \nprocure to meet the requirement(s).  Additionally, because MISO proposes to enforce the \nforecasting requirements it sets forth through a cost-causation incentive that allocates make-\nwhole, commitment, balancing, congestion, and shortage-pricing charges commensurate with the \nforecast error (under a formula MISO dictates),21 the forecast requirements directly determine the \ncharges a Transmission Customer serving a Large Load will pay.  In short, MISO proposes to \nconvert forecast errors measured using its own criteria into costs charged to the Transmission \nCustomer through existing MISO settlement mechanisms.  \n \n20 MISO (LLWG-2026-4A) at 7 (Aug. 27, 2026). \n21 Id. at slides 7-8."},{"page":9,"startToken":2251,"endToken":2707,"text":"9 \n \nThe requirements currently included in the draft BPM and the Large Load Working \nGroup presentation thus affect rates and services significantly. 22  Moreover, as evidenced by the \nfact that they are included in MISO’s presentation and draft BPM, these numeric requirements \nare realistically susceptible of specification.  Finally, they are not so generally understood in any \ncontractual arrangement as to render recitation superfluous.  Absent specification, there would be \nno basis to know what the requirements are.23  Precedent makes clear that these types of \nnumerical requirements must be included in a tariff rather than a BPM.24   \n2. \nPMU Requirements \nUnder proposed section 37A.5 of the Tariff, a Transmission Customer taking service on \nbehalf of a Computational Load will be subject to PMU requirements.  That proposed section \nprovides (a) the date by which phasor measurement recording and communications equipment \nmust be installed by the Transmission Owner, (b) that the Transmission Customer is responsible \n \n22 Midcontinent Indep. Sys. Operator, Inc., 166 FERC ¶ 61,236 at P 71 (2019) (the term \n“maintenance margin” should be defined in the Tariff because it is the sole factor in determining \nwhether there is an “adequate projected margin” under the proposed Tariff revisions, which in turn \ndetermines whether certain Generator Planned Outages qualify for a safe harbor exemption or are \notherwise subject to a potential accreditation penalty); CAISO, 122 FERC ¶ 61,271 at P 23 (a \nformula used to calculate a rate significantly affects rates, terms, and conditions of service and \ntherefore should be included in the tariff) (“CAISO”); Midwest Indep. Transmission Sys. Operator, \nInc., 122 FERC ¶ 61,283 at P 342 (a key element in the development of a reliable program must \nbe included in the Tariff), order on reh’g, 125 FERC ¶ 61,061 (2008); see also City & Cnty. of \nSan Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (numerical threshold requirements are \nthe type that the “rule of reason” requires be stated in the Tariff).  \n23 Compare Hecate Energy Greene County LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. \n2023) (finding that provisions need not be included in a tariff because they are clearly implied by \nthe tariff's express terms). \n24 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (even \nif a 75 kW cap for the availability of secondary-voltage service is only a “guidepost,” “that kind \nof numerical threshold is the type of requirement that the ‘rule of reason’ requires be stated in the \nTariff”); SPP, 169 FERC ¶ 61,048 at P 62 (a 4-hour continuous run-time requirement must be \nincluded in the tariff because it determines whether a resource is eligible to be used to satisfy a \nresource adequacy requirement)."},{"page":10,"startToken":2707,"endToken":3001,"text":"10 \n \nfor the costs of the equipment, (c) where the equipment must be located, and (d) when existing \nequipment may be used.25  Beyond that, the proposed provision provides that the equipment must \nbe “capable, at a minimum, of gathering phasor measurements as specified in Business Practices \nManual for Large Load” and that “phasor measurements must be streamed in the format \nspecified in the Business Practices Manual for Large Load[.]”26   \nThe shortcomings of MISO’s proposal are evident when its proposed Tariff provision is \ncompared to its June 2026 presentation of a draft Technical Compendium entitled \n“Interconnection Reliability Requirements for Large Load.”27 That presentation includes the \nfollowing numeric thresholds and “Telemetry and PMU Requirements”:  \n▪ \n“Sampling Rate and Data Quality: High‑resolution sampling (e.g., PMU‑level \n>60 samples per second) is necessary to capture fast voltage, frequency, and \nreal/reactive power changes characteristic of power‑electronic large loads.”28  \nThe shortcomings of the draft Tariff language are further reinforced when the proposed \nBPM provisions addressing Telemetry and PMU requirements are considered.  These were \nposted publicly by MISO on September 4, 2026, a week after MISO submitted the Filing.  Draft \nsection 11.5.1 requires as follows: “All PMU data from Computational Loads must be streamed \n \n25 MISO Filing Tab A, Proposed Tariff Module B, § 37A.5. \n26 Id. \n27 Midcontinent Independent System Operator, Inc., “Interconnection Reliability \nRequirements for Large Load” Technical Compendium Draft (June 2026), available at \nhttps://cdn.misoenergy.org/20260610%20LLWG%20Item%2006%20MISO%20Large%20Load\n%20Interconnection%20Reliability%20Requirements_Technical%20Compendium%20Draft763\n427.pdf. Note that the August 2026 version of MISO’s Technical Compendium removed reference \nto the 2-4 seconds or faster threshold and MISO may be continuing to receive stakeholder feedback \non this and other topics.   \n28 Id. at 8."},{"page":11,"startToken":3001,"endToken":3290,"text":"11 \n \nto MISO in IEEE/IEC 60255 118-1-2018 format at a sampling rate of 60 samples per second,” \nand calibration accuracy requirements are further specified in draft section 11.5.2.29   \nThe requirements identified in MISO’s draft June 2026 technical compendium, recently \nposted BPM, or whatever requirements MISO ultimately proposes to adopt in those regards, are \nnot mere implementation details such as instructions, guidelines, examples and charts; do not \nserve as guides for internal operations; and are not supplemental or secondary in nature.  They \nare the basic, specific requirements that a Transmission Customer must meet in order to satisfy \nthe PMU reliability requirement and are key elements in MISO’s proposed reliability program. \nAs the proposed Tariff sets forth, the Transmission Customer will be responsible for the expense \nof installing the “phasor measurement recording and communications equipment . . . that is \ncapable, at a minimum, of gathering phasor measurements as specified in the Business Practice \nManual for Large Load.”30  The requisite PMU sampling rate and streaming format, GPS time \nsynchronization for intermediary phasor data concentrator (“PDC”), and latency from PMU to \nMISO PDC determines the type of hardware that the Transmission Owner or Transmission \nCustomer must procure and the continuous streaming requirement drives the costs of additional \nrequired equipment, including data system architecture and secure communications systems that \ncan handle the volume of data that will be required at a sampling and streaming rate that is \ndouble what Entergy currently uses.     \n \n29 \nDraft \nSection \n11 \nof \nBPM-032 \n(Large \nLoads), \navailable \nat \nhttps://cdn.misoenergy.org/20260909%20LLWG%20Item%2004%20BPM-\n032%20Large%20Load%20DRAFT%20-%20Section%2011%20PMU780059.pdf (last accessed \nSeptember 18, 2026, attached hereto as Exh. E). \n30 MISO Filing Tab A, Proposed Tariff Module B, §37A.5."},{"page":12,"startToken":3290,"endToken":3659,"text":"12 \n \nThe requirements currently included in the draft BPM thus affect rates and services \nsignificantly.31  Moreover, as evidenced by the fact that they are included in MISO’s presentation \nand draft BPM, these numeric requirements are realistically susceptible of specification.  Finally, \nthey are not so generally understood in any contractual arrangement as to render recitation \nsuperfluous.  Absent specification, there would be no basis to know what the requirements are.32  \nPrecedent makes clear that these types of numerical requirements must be included in a tariff \nrather than a BPM.33   \n3. \nLarge Load Ride-Through Requirements \nProposed Section 37A.6 includes Large Load ride-through requirements.  MISO’s \nproposed Tariff language states only that a Transmission Customer taking Transmission Service \non behalf of a Computational Load must “remain[] connected to the Transmission System and \ncontinue operation during voltage and frequency disturbances within the performance criteria \nestablished by the Transmission Provider in the Business Practices Manual for Large Load,” and \nthat ride-through requirements “may include evaluation, testing, modeling, monitoring, and other \ncompliance measures established by the Transmission Provider in the Business Practices Manual \n \n31 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, \n122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 \n(D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires \nbe stated in the Tariff). \n32 Compare Hecate Energy Greene County LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. \n2023) (finding that provisions need not be included in a tariff because they are clearly implied by \nthe tariff’s express terms). \n33 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (even \nif a 75 kW cap for the availability of secondary-voltage service is only a “guidepost,” “that kind \nof numerical threshold is the type of requirement that the ‘rule of reason’ requires be stated in the \nTariff”); SPP, 169 FERC ¶ 61,048 at P 62 (a 4-hour continuous run-time requirement must be \nincluded in the tariff because it determines whether a resource is eligible to be used to satisfy a \nresource adequacy requirement)."},{"page":13,"startToken":3659,"endToken":3970,"text":"13 \n \nfor Large Load.”34  The proposed Tariff language contains no voltage magnitudes, no frequency \nband, and no ride-through duration curve. \nIn comparison, MISO’s draft section 11 of BPM-032 specifies a voltage ride-through \nenvelope, measured as Root Mean Square (“RMS”)Voltage at the Point(s) of Withdrawal, \ndetailing RMS voltage ranges and corresponding minimum ride-through times; and it further \nrequires specific active-power recovery performance as follows: “After voltage recovers above \n0.90 p.u., restore at least 90% of pre-disturbance active power within two seconds (default).”35  \nDraft section 11 also specifies a frequency ride-through envelope, where minimum ride-through \ntimes are specified for corresponding system frequency levels (measured in Hz). \nAgain, these requirements or whatever requirements MISO ultimately proposes to adopt \nin those regards, are not mere implementation details, do not serve as guides for internal \noperations, and are not supplemental or secondary in nature.  They are the basic, specific \nrequirements that a Transmission Customer must meet in order to satisfy the Large Load ride-\nthrough requirement and are key elements in MISO’s proposed reliability program.  For \nexample, whether a data center must ride through a 0.50 p.u. dip for 0.15 seconds versus longer \nperiods, or recover 90% of its load within 2 seconds, dictates the electronic equipment and \ncontrols the Computational Load must install to achieve compliance.  The post-disturbance ride-\nthrough requirements related to post-disturbance performance and other criteria, if varied by only \nsmall measurements of time and permissible volume of load to be drawn from the grid, may \n \n34 MISO Filing Tab A, Proposed Tariff Module B, § 37A.6. \n35 MISO Business Practices Manual for Large Loads, Section 11 (BPM-032); See page 61 \nof 67, (posted August 27, 2026) available at \nhttps://cdn.misoenergy.org/20260827%20LLWG%20Item%2010%20BPM-\n032%20Large%20Load%20Ride-through%20Draft777237.pdf (last accessed Sept. 18, 2026, \nattached hereto at Exh. D)."},{"page":14,"startToken":3970,"endToken":4315,"text":"14 \n \ncreate unachievable technical standards.  And even if they are achievable, small changes in the \nrequirements can result in project-sized changes in costs (e.g., a $100 million project may need \nto spend another $100 million) to achieve compliance.  These are determinations that could \ndecide project viability.  They thus affect rates and services significantly.36    \nMoreover, as evidenced by the fact that they are included in draft BPM requirements, \nthese numeric requirements are realistically susceptible of specification.  Finally, they are not so \ngenerally understood in any contractual arrangement as to render recitation superfluous.  Absent \nspecification, there would be no basis to know what the requirements are.37  Precedent makes \nclear that these types of numerical requirements must be included in a tariff rather than a BPM.38   \n4. \nLarge Load Ramp Requirements \nProposed Section 37A.7 includes ramp requirements for Transmission Customers taking \nTransmission Service on behalf of Computational Loads.  Proposed Section 37A.7 includes \nlanguage regarding the measurement of ramp limits, and then provides that “Computational Load \nshall be subject to up-ramp and down-ramp limits established by the Transmission Provider \nconsistent with the process set forth in the Business Practices Manual for Large Load.”39  That \nsection also provides that “[t]he Computational Load must have an effective up and down ramp \nrate not exceeding the specified limit outlined in the Business Practices Manual for Large Load \nunless otherwise directed by the Balancing Authority, Reliability Coordinator, or Transmission \n \n36 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, \n122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 \n(D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires \nbe stated in the Tariff). \n37 Compare Hecate, 72 F.4th at 1314. \n38 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022); SPP, \n169 FERC ¶ 61,048 at P 62. \n39 MISO Filing Tab A, Proposed Tariff Module B, § 37A.7."},{"page":15,"startToken":4315,"endToken":4656,"text":"15 \n \nOperator.”40  MISO states in the Filing that it “is proposing initial up- and down-ramp limits of \n30MW/minute,” measured in aggregate across the applicable Points of Withdrawal during stable-\nstate transitions, while allowing eligible generation or other resources to provide “ramp \nsmoothing.”41  \nAs an initial matter, tariff provisions, not statements in a transmittal letter, are binding.42  \nAnd, once again, it is the specific ramp limits that a Transmission Customer will need to satisfy.  \nThe ramp limits themselves are not mere implementation details, do not serve as guides for \ninternal operations, and are not supplemental or secondary in nature.  Moreover, high-cost \nsolutions may be the only technically feasible options to meet these requirements.  The specific \nramp rates thus affect rates and services significantly.43  Moreover, as evidenced by the fact that \nMISO was able to easily describe the ramp limits in its Filing, these numeric requirements are \nrealistically susceptible of specification.  Finally, they are not so generally understood in any \ncontractual arrangement as to render recitation superfluous.  Absent specification, there would be \nno basis to know what the requirements are.44  Precedent makes clear that these types of \nnumerical requirements must be included in a tariff rather than a BPM.45   \n \n40 Id.   \n41 Filing Transmittal at 20.  \n42 E.g., Louisville Gas and Elec. Co., 137 FERC ¶ 61,195 at P 55 (2011) (finding that \nstatement in transmittal letter was not binding and directing applicant to include that statement in \nits tariff). \n43 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, \n122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 \n(D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires \nbe stated in the Tariff). \n44 Compare Hecate, 72 F.4th at 1314. \n45 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022); SPP, \n169 FERC ¶ 61,048 at P 62."},{"page":16,"startToken":4656,"endToken":4954,"text":"16 \n \nC. \nThe Commission Should Accept MISO’s Filing Subject to a Compliance \nFiling, With the Effective Date Deferred Until That Filing Is Accepted  \n \nEntergy recognizes that MISO and its Transmission Owners are under a Commission \ndirective to address Large Load reliability, and Entergy shares the goal of reliable integration of \nLarge Loads. Entergy’s interest is in a Tariff it can read, comply with, and plan for costs needed \nto implement it.  Indeed, that is what is required under the rule of reason test.  Core, statable, and \nspecific reliability requirements must be included in the filed Tariff.   \nConsistent with the rule of reason and precedent,46 the Commission should direct MISO, \nin a compliance filing, to include in the Tariff specific Large Load forecast data requirements, \nPMU requirements, Large Load ride-through requirements, and Large Load ramp requirements, \nconsistent with the rule of reason.  Among other things, the Tariff provisions should include \nspecific forecasting parameters (including the applicable time horizons and any requirements to \nupdate operational forecast data), ramp-rate limits, disturbance ride-through timing (including \napplicable voltage or frequency levels and duration criteria), post-fault active power recovery \ntiming requirements, and PMU sampling and streaming rates, data-quality, and retention \nthresholds.  These requirements will inform Transmission Customers serving Large Loads of the \nconditions that must be met for interconnection, and invoke precisely the kind of significant, \nspecifiable terms the rule of reason requires in the filed Tariff.  Entergy agrees that genuine \nimplementation details should be included in the BPM; the list above is narrowly tailored to the \nterms that meet the Commission’s rule of reason criteria.  \n \n46 E.g., Midcontinent Indep. Sys. Operator, Inc., 166 FERC ¶ 61,236 at P 71 (2019) \n(requiring MISO to move a rate-significant definition from a BPM into the Tariff by compliance \nfiling, rather than rejecting the filing)."},{"page":17,"startToken":4954,"endToken":5221,"text":"17 \n \nThe Commission also should defer the effective date of the Tariff provisions included \nwith the Filing until the compliance filing is accepted.  The Commission has deferred effective \ndates pending a curative compliance filing in comparable circumstances.47  Finally, the \nCommission should require MISO to attach the relevant BPM as part of its compliance filing, for \ninformational purposes.  This is an important step to provide an opportunity for parties to \ncompare language in the BPM and recommend, as appropriate, operative language to be included \nin the Tariff.48  As noted above, the rule of reason test “requires a case-by-case analysis, \ncomparing what is in the . . . tariff against what is in the Business Practice Manuals.”49   \nOverall, the Commission must ensure that any adopted reliability requirements are \ndetailed in the Tariff, technically vetted, and supported by a complete record—protecting both \nsystem reliability and stakeholder fairness. Absent this, MISO’s filing risks premature approval \nof undefined reliability standards that could hamper the development of data centers in MISO. \nCONCLUSION \nFor the foregoing reasons, Entergy respectfully requests that the Commission accept \nMISO’s filing subject to a compliance filing that requires MISO to include in its Tariff operative \ninterconnection reliability requirements in accordance with the Commission’s rule of reason.  \nThe Commission also should defer the effective date of the Tariff provisions until the \ncompliance filing is accepted.   \n \n \n47 Id.  \n48 Cf. Midwest, 122 FERC ¶ 61,283 at P 400 (stakeholders need to be able to review BPMs \nto have a complete understanding of their responsibilities and obligations under the resource \nadequacy proposal). \n49 CAISO, 122 FERC ¶ 61,271 at P 17."},{"page":18,"startToken":5221,"endToken":5301,"text":"18 \n \n \n \n \n \n \n \n \nRespectfully Submitted, \n \n \n/s/ Jeffrey Phillips \n \n \n \n \n \n \n \n \nJeffrey Phillips \nSenior Counsel \nEntergy Services, Inc. \n101 Constitution Avenue, NW \nSuite 200 East \nWashington, DC  20001 \n \n(202) 530-7312  \n \n \n \n \n \n \n \nJphil36@entergy.com \n \n \n \n \n \n \n \n \nAndrea Weinstein \nVice President, Deputy General Counsel \nEntergy Services, Inc. \n101 Constitution Avenue, NW \nSuite 200 East \nWashington, DC  20001 \n(202) 530-7342  \naweinst@entergy.com \n \n \n \n \n \n \n \n \nKaris Parnham \nAssistant General Counsel \nEntergy Services, Inc. \n101 Constitution Avenue, NW \nSuite 200 East \nWashington, DC  20001 \n \n(512) 487-3986  \n \n \n \n \n \n \n \nkparnha@entergy.com \n \n \n \n \n \n \nDated: September 18, 2026"},{"page":19,"startToken":5301,"endToken":5355,"text":"CERTIFICATE OF SERVICE \nI certify that I have this day served the foregoing document by email upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n/s/Jeffrey Phillips \nJeffrey Phillips \nEntergy Services, Inc. \n101 Constitution Avenue, NW \nSuite 200 East \nWashington, DC  20001 \n \n \nDated: September 18, 2026"},{"page":20,"startToken":5355,"endToken":5358,"text":"20 \n \nEXHIBIT A"},{"page":21,"startToken":5358,"endToken":5358,"text":""},{"page":22,"startToken":5358,"endToken":5358,"text":""},{"page":23,"startToken":5358,"endToken":5358,"text":""},{"page":24,"startToken":5358,"endToken":5358,"text":""},{"page":25,"startToken":5358,"endToken":5361,"text":"21 \n \nEXHIBIT B"},{"page":26,"startToken":5361,"endToken":5526,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 51 of 68 \nOPS-12 \nPublic \n9. Large Load Forecast Data Requirements  \n9.1 \nPurpose \nThis section establishes the obligation for Transmission Customers serving Large Loads to \nprovide day‑ahead and real‑time Load Forecasts directly to the Transmission Provider. These \nforecasts supply critical inputs to the Reliability Assessment Commitment (RAC), Security \nConstrained Economic Dispatch (SCED), and other reliability studies, enabling reliable \noperations and efficient market outcomes. To maintain situational awareness and accuracy, \nforecasts must reflect the most current expected Demand and be updated whenever material \nchanges occur; submission, granularity, and validation expectations are harmonized with \nMISO’s operational forecasting processes referenced in BPM‑025.  \n \n9.2 \nRequirement Applicability \nFor each Large Load(s) meeting the requirement applicability in Section 2, the Transmission \nCustomer must provide day(s) ahead and real-time Load Forecasts for Large Load directly to \nthe Transmission Provider in accordance with BPM-025 Operational Forecasting.  \n \n9.3 \nApplicable BPMs and Processes \n• \nBPM-025 Operational Forecasting"},{"page":27,"startToken":5526,"endToken":5529,"text":"22 \n \nEXHIBIT C"},{"page":28,"startToken":5529,"endToken":5550,"text":"Large Load Operational Forecast Requirements \n(LLWG-2026-4A)\nLarge Load Working Group (LLWG) \nAugust 27, 2026\n8/28/2026\nCorrection to slide 6"},{"page":29,"startToken":5550,"endToken":5689,"text":"Purpose & Key \nTakeaway\nKey Takeaways\nPurpose\nSummarize stakeholder feedback requested at the June 29th  Large Load \nWorking Group meeting, review the BPM-032 and BPM-025 language, discuss \nthe forecast incentive proposal, and introduce the forecasting submission \nsystem.\n2\n• MISO has incorporated stakeholders feedback into the Interconnection Reliability \nRequirements Tariff and BPM language, and is collaborating closely with stakeholders to \nrefine accuracy, compliance expectations, and implementation details. \n• Detailed forecast requirements, submission, validation, and compliance processes are \nformally defined in BPM-025 (Operational Forecasting) and BPM-032 (Large Load BPM). \n• Large Load forecasting requirements integrate directly with MISO’s existing mid-term and \nshort-term forecasting systems, using participant-submitted data to strengthen \noperational forecasting. \n• MISO proposes improved incentives, including make-whole payments for hourly forecasts \nand 5-minute settlements for short-interval forecasts. Transmission Customers remain \nresponsible for providing complete and accurate information to ensure compliance.\nBPM: Business Practice Manual"},{"page":30,"startToken":5689,"endToken":5838,"text":"The forecast requirement progressed from Tariff obligation to detailed \nrequirements, and currently focuses on BPM writing process and \nincentives design\nDiscussed Forecast \nRequirements\n• Proposed what Transmission \nCustomers submit: CP node level, \nHourly (168-hour horizon) and 5-\nminute (6-hour horizon)\n• Introduced the error measurement \nbasis (absolute error vs. actual) and \nsubmission monitoring\nReview SH feedback, \nBPM redlines, and \nincentives proposal\n• Review stakeholder feedback from \nthe 6/29th LLWG meeting\n• Introduce BPM-032 (Large Load) and \nBPM-025 (Forecast) redlines\n• Define forecast error measurement \nand initial considerations for accuracy \nincentives proposal\n• Illustrate forecasting submission \nsystem\nIllustrate Forecast \nSystems & Processes to \nIncorporate Large Loads\n• Further details on forecast accuracy \nincentive proposal based on \nstakeholder feedback\n• Software build and implementation \nfor forecasting submission system\n• Software build and implementation \nfor DART system integration\nCPNode: Commercial Pricing Node | LLWG: Large Load Working Group | BPM: Business Practice Manual | DART: Day-ahead and Real-time \nLast LLWG\nToday\nNext Steps \n3"},{"page":31,"startToken":5838,"endToken":6020,"text":"4\nStakeholders feedback reflect general support of the forecast \nrequirements and seek clarification on design and implementation details \nDetailed Stakeholder feedback and MISO responses are available in LLWG Large Load Operational Forecast Requirements \nResponse (LLWG-2026-4A)774944.pdf\nStakeholder Feedback Theme\nMISO Response\nForecast Design & Integration: Stakeholders \nquestion the need for 5-minute forecasts and its \noverlap with existing hourly/telemetry.\n5-minute forecast submissions provide forward-looking \noperational data to manage intra-hour variability for Unit Dispatch \nSystem (UDS) and Look-Ahead Commitment (LAC).\nAccuracy, Applicability & Accountability: \nStakeholders seek clarity on accuracy metrics, and \nresponsibility for submissions.\nAccuracy and incentives will be defined in collaboration with \nstakeholders in the upcoming LLWG meetings.\nTransmission Customers are accountable for meeting the \nforecasting requirements, as specified in MISO’s Interconnection \nReliability Requirements Tariff. \nImplementation, Transition & Regulatory Basis: \nStakeholders request clearer transition rules, \nimplementation details, and justification for \nrequirements.\nForecast requirements stem from FERC’s Show Cause Order and \nfollow MISO’s Interconnection Reliability Requirements. Large \nLoads already in service are exempt unless changes occur, as \ndescribed in MISO’s Interconnection Reliability Requirement Tariff.  \nSubmission mechanics and timelines will be detailed in BPM/LLWG \ndiscussions."},{"page":32,"startToken":6020,"endToken":6163,"text":"MISO’s forecast requirements are kept unchanged and stakeholders \nfeedback on design and implementation details are incorporated into BPM \nlanguage\n• Forecasts are submitted at the Commercial Pricing (CP) node level, consistent with the Large Load participation \nmodel; MISO maps submissions into the network model for congestion and contingency analysis\nResponsibility: Transmission Customers are accountable for meeting the forecasting requirements\nTransition: Prior to the later of the Service Commencement Date of a Large Load or September 1, 2027.\nBPM: Business Practice Manual | LAC: Look-ahead Commitment | RAC: Reliability Assessment Commitment | UDS: Unit Dispatch System\nRequirements in BPM (unchanged)\nRequirements in Tariff (updated)\nForecast\nWindow and update cadence\nMISO process supported\nStatus\nHourly\nNext hour through +168 hours; updated \nhourly\nMulti-Day, Next-Day and Intraday RACs \n(reliability commitment)\nNew\n5-minute\nNext 6 hours (72 intervals); updated \nevery 5 minutes\nLAC (look-ahead commitment) and UDS \n(real-time dispatch)\nNew\n5"},{"page":33,"startToken":6163,"endToken":6295,"text":"6\nChanges in BPM-025 and new contents in BPM-032 incorporate detailed \nLarge Load forecasting requirements\n• BPM-025-r14 (2026) (Operational Forecasting) establishes the baseline for operational forecasting\n• BPM-032 (Large Load) introduces updates focused on Large Load Interconnection Reliability Requirements.\nCP: Commercial Pricing | LBA: Local Balancing Authority | BPM: Business Practice Manual | DART: Day-ahead and Real-time \nProposed changes to BPM-025 (Operational Forecast)\n•\nLarge Load hourly forecasts for the next 168 hours.\n•\nLarge Load 5-minute forecasts for the next 72 intervals.\n•\nForecasts at CPNode level as gross load, not netted. Telemetry-based actuals for \nperformance review.\n•\nMISO validates & integrates submitted forecasts into existing DART processes.\n•\nLarge Load forecast submissions are treated as confidential information and are not \nposted publicly. Submitted forecast data is reflected only within the aggregate LBA \nand MISO market footprint forecast information that MISO posts."},{"page":34,"startToken":6295,"endToken":6309,"text":"Forecast incentives\n7\nMeasure\nforecast error\nApply\ntolerance band\nAllocate costs\nusing cost causation"},{"page":35,"startToken":6309,"endToken":6532,"text":"Forecast errors matter because they can affect commitment efficiency, \nbalancing reliability outcomes, and real-time energy prices\n• Cost-causation allocation can strengthen the incentive for Large Loads to submit accurate forecasts by assigning \nforecast-related costs to the errors that create them.\n• The main cost channels are hourly make-whole / commitment impacts, 5-minute balancing and congestion impacts, \nand real-time energy price impacts.\nHourly forecast and commitment \nefficiency\nMake-whole and commitment \ncost allocation*, including:\n•\nDay-ahead Deviation and \nHeadroom Charge (DDC)\n•\nConstraint Management \nCharge (CMC)\n• Large Load forecast errors can \ndistort RAC and real-time \nscheduling: over-forecast can lead \nto unnecessary commitment; \nunder-forecast can require late \ncommitment with fewer available \nresource options\n5-minute forecast and real-time \nbalancing/congestion\nRT balancing actions and congestion \nimpacts\n• 5-minute forecast misses can \nincrease balancing needs and change \nhow reserves are carried and \ndeployed\n• Congestion impacts may justify a \ntargeted mechanism; Uninstructed \nDeviation Enhancement (UDE) \nconstruct provides a precedent for \nlinking harmful deviations to \ncongestion impacts\nSettlement intervals and \nshortage pricing\nReal-time energy prices during tight \nintervals\n• Forecast errors can contribute to \nconditions that produce large five-\nminute energy-price movements and \nshortage pricing.\n• Aligning settlement intervals \nallows prices to more closely reflect \nreal-time system conditions and \nsupports efficient market outcomes.\n*MISO BPM-005 Market Settlements, Market Settlements 5-Minute Calculation Guide, D.14.2 (Constraint Management Charge) and D.14.6 (Day-ahead Deviation and Headroom Charge)\n8"},{"page":36,"startToken":6532,"endToken":6733,"text":"Large Load forecasts are submitted and measured at each individual Large \nLoad CP node\nWhere forecasts are submitted and measured\n• Large Load forecasts are submitted at the applicable CP node\n• Forecast accuracy is measured against metered load at that same \nCP node\n• Hourly forecast values use integrated load; 5-minute values use \nRT interval meter data\nPerformance metrics at individual CP nodes\n• Mean Absolute Error (MAE) at each CP node measures the average \nmagnitude of forecast error in the applicable load units\n• Mean Absolute Percentage Error (MAPE) at each CP node \nmeasures forecast error relative to actual load, expressed as a \npercentage\nHourly MTLF measurement at the CP node*\nDA\nNDRAC\n14:30\nNotification\nDeadline (NTD) 4-\nHA\nRT actual\n| DA − NDRAC |\n| NDRAC − NTD|\n| NTD − RT actual |\n| NDRAC (14:30) − RT actual |\n5-minute STLF at the CP node\n9 Min\nAhead\nRT\nmeter\n| 9 Min Ahead − RT interval meter |\n• Measured at the same CP node using \nRT interval meter data\n| NTD 4HA − RT actual |\n*Note: MISO DDC/CMC already measure deviations across DA to NTD and NTD to RT as part of RT RSG First Pass allocation \n(MISO BPM-005, Market Settlements 5-Minute Calculation Guide, D.14.2 and D.14.6.)\n9"},{"page":37,"startToken":6733,"endToken":6834,"text":"MISO evaluates forecast accuracy similarly using MAE, MAPE, and \nunbiasedness\nMAE\n• Measures the average magnitude of \nforecast error in load units\n• Captures error volume directly\nMAPE\n• Measures forecast error relative to \nactual load in percentage terms\n• Normalizes forecast error for \ndifferences in load size\nUnbiasedness\n• Measures whether forecast errors are \ncentered around zero over time\n• Identifies persistent over- or under-\nforecasting\nExamples of MISO forecast-performance reporting\nHistorical MAE distributions by forecast horizon\nCurrent-period operational MAE reporting by horizon and region\n• Operational reporting tracks forecast error at specific horizons \nand by geography.\n• Historical reporting provides an empirical benchmark for current \nperformance.\n10"},{"page":38,"startToken":6834,"endToken":6929,"text":"Open design questions remain for the Large Load forecast accuracy \nincentives\nMISO will work with stakeholders to further develop these design elements.\nMeasure\nforecast error\nApply\ntolerance band\nAllocate costs\nusing cost causation\nTolerance and metrics\n• What should the tolerance band be: comparable MISO error, Large Load group typical error, a minimum MW floor, or a combination?\n• Should the same tolerance band apply to all Large Loads, or should computational Large Loads have a different tolerance?\nMonitoring and rollout\n• Is a monitoring period needed before implementation, and if so for how long?\nIncentive Framework\n11"},{"page":39,"startToken":6929,"endToken":6934,"text":"Large Load forecast submission\n12"},{"page":40,"startToken":6934,"endToken":6998,"text":"Establishes externally-facing Application \nProgramming Interface (API) to accept \nthe Large Load forecast (5-minute short-\nterm load forecast (STLF) and 60-minute \nmid-term load forecast (MTLF)*\n13\nAccepting Large Load forecasts will focus on submission and integration \nwith existing systems\n*7-days out. | **Similar to how Local Balancing Authorities (LBAs) submit data today. \nVerifies that the \nsubmitted forecast \nmeets requirements \n(format, tables, time, \nvalues, etc…)\nMP/TC"},{"page":41,"startToken":6998,"endToken":7021,"text":"Next Steps\n14\n• Develop additional forecast incentive framework details\n• Expand forecast submission systems and DART integration\n• Present the updates at upcoming LLWG meetings"},{"page":42,"startToken":7021,"endToken":7067,"text":"Stakeholder Feedback Request\n15\n• MISO requests feedback on the Large Load Large Load Operational Forecast BPM \nlanguage and Incentives Proposal by Monday, September 10th, 2026\n• Feedback requests and responses are managed through the Feedback Tool on the \nMISO website at: https://www.misoenergy.org/engage/stakeholder-feedback/"},{"page":43,"startToken":7067,"endToken":7076,"text":"Send questions or comments to:\nLargeLoadProgram@misoenergy.org \n16"},{"page":44,"startToken":7076,"endToken":7079,"text":"23 \n \nEXHIBIT D"},{"page":45,"startToken":7079,"endToken":7459,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 59 of 67 \nOPS-12 \nPublic \n11. \nLarge Load Ride-Through Requirements   \n11.1 Purpose \nThe purpose of the ride-through requirements is to reduce the risk of unnecessary \ndisconnection or rapid changes in Demand associated with Computational Load during voltage \nand frequency disturbances and to support predictable disturbance performance during credible \nTransmission System events. \nAs Computational Loads increasingly incorporate power-electronic interfaces, fast controls, and \ndynamic operating behavior, their response to Transmission System disturbances may \nmaterially affect system performance, operational reliability, and post-contingency recovery. \nRide-through requirements establish minimum performance expectations for maintaining \nconnection and stable operation during voltage and frequency disturbances and for recovering \nactive power following disturbance clearance. \nConsistent with Section 37A.6 of the Tariff, Computational Load subject to this Section shall \nremain connected to the Transmission System and continue operation during voltage and \nfrequency disturbances within the applicable performance criteria specified in this Section. \n11.2 General Ride-Through Requirements \nRide-through requirements shall apply at the applicable Point(s) of Withdrawal (“PoW(s)”) of a \nLarge Load and shall be evaluated based on voltage and frequency conditions measured at the \nPoW(s). \nWhen system conditions remain within the applicable ride-through performance limits specified \nin Sections 11.3 and 11.4, the Computational Load shall remain connected to the Transmission \nSystem and maintain stable operation. \nProtection systems, converter protections, transfer schemes, facility controls, and other Large \nLoad Equipment shall be coordinated to avoid unnecessary tripping, interruption of service, or \nunstable operation during disturbances within the applicable ride-through limits. \nFollowing disturbance clearance, the Computational Load shall recover toward its pre-\ndisturbance operating condition in accordance with the applicable performance requirements of \nthis Section. \n \n11.3  Voltage Ride-Through Requirements \nComputational Load shall remain connected to the Transmission System and maintain stable \noperation during voltage disturbances when voltage measured at the applicable PoW(s) \nremains within the voltage ride-through requirements specified in this Section. \nProtection systems and facility controls shall be coordinated to avoid unnecessary \ndisconnection and to support stable operation during and following voltage disturbances. \n11.3.1 Voltage Ride-Through Envelope \nVoltage ride-through performance shall be determined based on the root-mean-square voltage \nmagnitude measured at the applicable PoW(s) and the duration of the voltage excursion. \nTable 11-1. Voltage Ride-Through Requirements at PoW"},{"page":46,"startToken":7459,"endToken":7776,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 60 of 67 \nOPS-12 \nPublic \nRoot Mean Square Voltage  \n(p.u. of nominal) \nMinimum ride-through time (s) \nV > 1.20 \nMay ride-through or trip \n1.10 < V ≤ 1.20 \n0.50 \n0.90 ≤ V ≤ 1.10 \nContinuous \n0.80 ≤ V < 0.90 \n2.00 \n0.50 ≤ V < 0.80 \n0.50 \nV < 0.50 \n0.15 \n \nWithin the voltage-duration limits defined by the ride-through envelope, the Computational \nLoads shall remain connected to the Transmission System and maintain stable operation \nconsistent with established performance expectations. Disconnection shall not occur unless \nvoltage conditions exceed the ride-through envelope or otherwise permitted under applicable \nride-through provisions. \nThe ride-through envelope establishes the expected no-trip region for Computational Loads and \nis intended to support predictable disturbance performance during credible voltage events and \nreliable operation of the Transmission System. \nComputational Loads shall be capable of remaining connected during at least six voltage \ndisturbance events occurring within any 90-second period, including disturbances associated \nwith automatic reclosing, provided the voltage magnitude and duration of each individual \ndisturbance remain within the applicable ride-through envelope specified in Table 11-1. \n11.3.2 Performance During Voltage Disturbances \nWhile operating within the voltage ride-through envelope, the Computational Load shall satisfy \nthe following active power performance requirements: \n• \nVoltage between 0.90 pu and 1.20 pu: \no The Computational Loads shall remain connected to the Transmission System \nand maintain pre-disturbance active power consumption. \no Temporary reduction of active power shall not occur. \no Protection systems, converter protections, and control logic shall not initiate \nunnecessary tripping, interruption of service, or curtailment. \n• \nVoltage between 0.50 pu and 0.90 pu: \no The Computational Loads shall remain connected to the Transmission System \nwithin the ride-through envelope. \no Temporary reduction of active power may occur in proportion to the voltage \nreduction to support continued operation during the disturbance. \n• \nVoltage below 0.50 pu:"},{"page":47,"startToken":7776,"endToken":8189,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 61 of 67 \nOPS-12 \nPublic \no The Computational Loads shall remain connected to the Transmission System \nwithin the ride-through envelope. \no Temporary reduction of active power may occur as necessary to maintain \nconnection and support ride-through performance during the disturbance. \nProtection systems, converter protections, and control logic shall be coordinated to avoid \nunnecessary disconnection during voltage disturbances occurring within the ride-through \nenvelope. Control systems shall maintain stable operation during and following disturbances \nand shall avoid oscillatory or unstable behavior that could adversely affect reliable operation of \nthe Transmission System. \n11.3.3 Active Power Recovery \nFollowing recovery of system voltage above 0.90 pu, Computational Load shall restore at least \n90% of its pre-disturbance active power within two seconds. This shall be the default active \npower recovery requirement. \nMISO may establish an alternative active power recovery time or recovery trajectory where \napplicable planning studies demonstrate that a slower or otherwise modified recovery is \nnecessary to maintain Transmission System reliability. Such an alternative may be established, \nfor example, in electrically weak systems or where planning assessments identify potential \nadverse impacts associated with active power recovery, including oscillatory behavior or voltage \ninstability. \n11.3.4  Transient Overvoltage Ride-Through \nComputational Load shall remain connected to the Transmission System and avoid \nunnecessary disconnection during short-duration transient overvoltage conditions associated \nwith credible Transmission System events, including faults, transmission energization, switching \noperations, or other credible system disturbances. \nProtection systems, converter protections, and facility controls shall be coordinated to avoid \nunnecessary interruption of service resulting from instantaneous or short-duration transient \nvoltage excursions that do not represent sustained abnormal system conditions. These \nrequirements are intended to support predictable disturbance performance and reduce the risk \nof unnecessary changes in large load demand during credible transmission events. \n11.3.5 Phase Jump Ride-Through \nComputational Load shall remain connected to the Transmission System and maintain stable \noperation during instantaneous positive-sequence voltage phase angle changes of up to 25 \nelectrical degrees resulting from non-fault switching events on the Transmission System, \nprovided system voltage remains within the voltage ride-through limits specified in Table 11-1. \nProtection systems, converter protections, and facility controls shall be coordinated to avoid \nunnecessary disconnection or unstable operation resulting from allowable phase angle changes \nduring credible transmission system events. \n11.3.6 Volts per Hz (V/Hz) Ride-Through \nComputational Load shall remain connected to the Transmission System and maintain stable \noperation during abnormal voltage-frequency conditions, provided the Volts per Hertz (V/Hz)"},{"page":48,"startToken":8189,"endToken":8505,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 62 of 67 \nOPS-12 \nPublic \nmeasured at the Point(s) of Withdrawal (PoW(s)) does not exceed 1.10 per unit for more than \n45 seconds or exceed 1.18 per unit for more than 2 seconds. \nProtection systems, converter protections, and facility controls shall be coordinated to avoid \nunnecessary disconnection during V/Hz excursions within these limits and support stable \noperation during and following transmission disturbances. \n11.3.7 Exception Process \nTo be developed. \n \n11.4 Frequency Ride-Through Requirements \nComputational Load shall remain connected to the Transmission System and maintain stable \noperation during frequency disturbances when system frequency measured at the applicable \nPoW(s) remains within the frequency ride-through requirements specified in this Section. \nProtection systems and facility controls shall be coordinated to avoid unnecessary \ndisconnection during frequency disturbances within the specified limits. \n11.4.1 Frequency Ride-Through Envelope \nComputational Loads shall remain connected to the Transmission System and maintain stable \noperation when system frequency remains within the continuous operating range of 58.8–61.2 \nHz. For frequency deviations outside this range, Computational Loads shall remain connected \nfor the minimum durations specified in Table 11-2. Disconnection may occur when frequency \nexcursions exceed the applicable limits of the ride-through envelope. \nSystem frequency shall be measured at the applicable PoW(s) over a period of time, typically \nthree to six cycles. The specified durations of the no-trip regions in Table 11-2 shall be \ncumulative over one or more disturbance events occurring within any 10-minute period. \n \nTable 11-2. Frequency Ride-Through Requirements at PoW  \nSystem Frequency (Hz) \nMinimum Ride Through Time (Seconds) \nf > 61.8 \nMay Trip \n61.2 < f ≤ 61.8 \n299 \n58.8 ≤ f ≤ 61.2 \nContinuous \n57.0 ≤ f< 58.8 \n299 \nf< 57.0 \nMay trip \n \n11.4.2 Performance During Frequency Excursions \nDuring frequency deviations within the ride-through envelope, Computational Loads shall:"},{"page":49,"startToken":8505,"endToken":8947,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 63 of 67 \nOPS-12 \nPublic \n• \nRemain connected to the Transmission System; and \n• \nMaintain stable operation consistent with established performance expectations. \nComputational Loads shall maintain pre-disturbance active power consumption while system \nfrequency remains within the continuous operating range of 58.8 Hz to 61.2 Hz. \nFor frequency excursions outside the continuous operating range but within 57.0 Hz to 58.8 Hz \nor 61.2 Hz to 61.8 Hz, Computational Loads shall remain connected and maintain active power \nconsumption within ±10% of pre-disturbance levels while maintaining stable operation. \n11.4.3  Rate-of-Change-of-Frequency Ride-Through \nComputational Loads shall remain connected to the Transmission System and maintain stable \noperation during frequency excursions within the ride-through limits specified in Table 11-2, \nprovided the absolute Rate of Change of Frequency (RoCoF) measured at the Point(s) of \nWithdrawal (PoW(s)) does not exceed 5.0 Hz/s. \nFor purposes of evaluating ride-through performance, RoCoF shall be calculated as the average \nrate of change of multiple calculated system frequency measurements over a time interval \ngreater than or equal to 0.1 second. Consistent with North American Electric Reliability \nCorporation (NERC) PRC-029 guidance, RoCoF shall not be calculated during fault occurrence \nor fault clearance. \nAny RoCoF protection installed shall be coordinated with applicable Transmission System \nreliability requirements and configured to avoid unnecessary disconnection during credible \nfrequency disturbances. Protection settings and control behavior shall support ride-through \nperformance during transient system conditions while avoiding inappropriate operation resulting \nfrom temporary fault-induced frequency measurement behavior. \n11.5  Demonstration and Verification Requirements  \nThe Transmission Customer shall demonstrate that each Computational Load subject to the \nride-through requirements of this Section is capable of satisfying the applicable requirements in \nSection 11. \nDemonstration and verification may include applicable planning studies, verified electrical \nmodels, equipment and control documentation, protection settings, commissioning or equipment \ntest information, PMU and disturbance monitoring data, operational event records, or other \ninformation reasonably required by MISO to evaluate ride-through capability and performance. \nThe Transmission Customer shall provide, upon request, information necessary to evaluate the \nbehavior of equipment or controls that may affect ride-through performance, including power-\nelectronic equipment, uninterruptible power supply systems, protection systems, transfer \nschemes, backup generation, energy storage, facility controls, and active power recovery \ncharacteristics. \nThe models and supporting information used to demonstrate compliance shall reflect the \nconfiguration and operating characteristics expected to exist as of the Service Commencement \nDate and shall be updated consistent with the modeling requirements of this BPM. \n11.5.1 Planning Demonstration \nPrior to the Service Commencement Date, the Transmission Customer shall demonstrate that \nthe Computational Load is capable of meeting the applicable ride-through requirements"},{"page":50,"startToken":8947,"endToken":9257,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 64 of 67 \nOPS-12 \nPublic \nspecified in this Section. The demonstration shall be based on applicable planning studies, \nmodel quality and performance testing, protection and control coordination, equipment \ndocumentation, or other technical information, as appropriate for the applicable requirement. \nThe planning demonstration shall address, as applicable to the facility design, equipment, \nprotection systems, controls, and models: \n• \nVoltage ride-through performance and active power response during voltage \ndisturbances; \n• \nActive power recovery following voltage recovery; \n• \nFrequency ride-through performance and active power response during frequency \nexcursions; \n• \nConsecutive disturbance ride-through capability; \n• \nTransient overvoltage and phase-jump ride-through capability; \n• \nRoCoF ride-through capability; and \n• \nV/Hz ride-through capability. \nNot all ride-through requirements require a separate simulation test. MISO may determine the \nappropriate method of demonstration based on the nature of the requirement and the capability \nof the applicable models. Demonstration may include simulation results, protection-setting \nreview and coordination, equipment or manufacturer documentation, control-setting verification, \nor other supporting technical information acceptable to MISO. \nThe applicable dynamic models shall represent protection, control, disconnection, active power \nreduction, and active power recovery behavior to the extent necessary to evaluate the \napplicable ride-through performance requirements. \nWhere MISO determines that positive-sequence dynamic simulation is insufficient to evaluate \napplicable ride-through behavior, MISO may require EMT analysis using the applicable EMT \nmodels submitted pursuant to the modeling requirements of this BPM. \n11.5.2 Operational Performance Verification \nMISO may verify actual ride-through performance using available operational and disturbance \ndata, including PMU data, SCADA data, disturbance monitoring records, event records, or other \nrelevant measurements associated with the applicable PoW(s). \nOperational performance may be compared with the applicable ride-through requirements and \nsubmitted models to support post-event analysis and model validation. \nDetailed operational performance verification procedures will be established through a future \nrevision of this BPM. \n11.6 Corrective Actions \nSee Corrective Actions in Section 13.4."},{"page":51,"startToken":9257,"endToken":9260,"text":"24 \n \nEXHIBIT E"},{"page":52,"startToken":9260,"endToken":9294,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 55 of 83 \nOPS-12 \nPublic \n \n11. \nLarge Load Phasor Measurement Unit (PMU) Requirements  \n \nIRR for Large Loads, dated August 28, 2026 (for reference)"},{"page":53,"startToken":9294,"endToken":9683,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 56 of 83 \nOPS-12 \nPublic \n11.1 Purpose \nThe purpose of this section is to establish the technical, operational, installation, \ncommunication, and naming requirements for phasor measurement units (PMUs) or \nequivalent synchronized measurement devices required for Computational Loads. These \nrequirements ensure that high‑resolution, time‑synchronized phasor data is available to \nsupport real‑time situational awareness, oscillation detection, performance monitoring, \nincluding ride‑through requirement validation, after‑the‑fact event analysis, and dynamic \nmodel validation across the MISO footprint. \nThis section defines the minimum functional capabilities, data quality criteria, measurement \ntypes, and streaming expectations necessary for PMUs installed at Points of Withdrawal, \nand outlines roles and responsibilities for ensuring compliance with Tariff §37A \nInterconnection Reliability Requirements. Together, these requirements provide a \nconsistent, reliable standard for PMU observability of Computational Loads and ensure \nalignment with applicable IEEE/IEC synchrophasor measurement and communication \nstandards.  \n11.2 PMU Definition \nA phasor measurement unit (PMU) is a device which measures the electrical voltage and \ncurrent waveforms on a power grid that are synchronized to a common time source. Time \nsynchronization allows monitoring of synchronized real-time measurements of multiple \nremote measurement points on the grid. A PMU can be a dedicated device, or the PMU \nfunction can be incorporated into a protective relay, digital fault recorder (DFR), dynamic \ndisturbance recorder (DDR), or other devices that can meet the below requirements and \nadditional requirements specified in the later sections of this document. \n• \nMeasurements need to be synchronized with a high accuracy satellite clock (e.g. \nGPS/IRIG-B)  \n• \nData needs to be recorded at least at 60 samples per second and support continuous \nstreaming of data to MISO. \n• \nThe device must be capable of sampling and/or calculating all signals specified in 11.10 \nmeeting minimum accuracy limits defined in the standard IEC/IEEE 60255-118-1:2018 \nfor the P-Class PMU. \n11.3  Applicability and Scope \nPMU requirements defined in this section apply to all Computational Loads as defined under \nthe MISO Tariff Interconnection Reliability Requirements. PMU-capable equipment must be \ninstalled prior to the later of the Service Commencement Date of the Computational Load, or \nSeptember 1, 2027. \nComputational Loads are required to have PMU’s to support oscillation detection, wide area \nmonitoring, performance monitoring including ride through requirement validation, after-the-\nfact event analysis and dynamic model validation."},{"page":54,"startToken":9683,"endToken":10049,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 57 of 83 \nOPS-12 \nPublic \n11.4 Installation Requirements \nFor a Computational Load, the Transmission Owner (TO) is required to install PMU (as \ndefined in Section 11.2) at each Point of Withdrawal (POW) on the Transmission Owner’s \nside of the POW. The PMU shall provide real-time data output to MISO and adhere to the \nstandards listed below. \n• \nIEEE/IEC 60255-118-1-2018 – Measurement requirements for synchrophasors, \nfrequency and rate of change of frequency \n• \nIEEE C37.118.2-2024 – Communication requirements for real-time communication \nbetween PMU’s, PDC and other applications \n• \nExisting PMU’s shall comply to the earlier revisions of these standards including IEEE \nC37.118.1-2011 for measurement and IEEE C37.118.2-2011 for communication  \nUse of a phasor data concentrator (PDC) on the TO side is preferred to consolidate multiple \nPMU streams into a single stream. This simplifies integration with MISO’s system and \nreduces connection complexity, eases data quality management. \n11.4.1 Hardware Requirements \n• \nPMU shall be set to have an output reporting rate of at least 60 samples per second \n• \nPMU shall have timing accuracy of 3µs \n• \nAll data recorded will be in Coordinated Universal Time (UTC) \n• \nPMU shall have GPS (UTC) synchronization function either through an internal or \nexternal GPS receiver \n• \nThe PMU data stream shall indicate whether it is using GPS clock or local clock \n• \nGPS clock shall report time and time quality compatible to IEEE/IEC 60255-118-1-2018 \n• \nAny intermediary PDC shall have GPS (UTC) synchronization function either through an \ninternal or external GPS receiver \n11.4.2 Communication Requirements \n• \nInterface to PDC through private IP networks \n• \nReceive and send real-time data through TCP/UDP ports, user configurable (each port \nindividually configurable). \n• \nNetwork communication between PMU and PDC is defined by Member \n• \nLatency from PMU to MISO PDC shall be no more than 0.50 seconds. \n \n11.5 Operational Requirements \n11.5.1 Streaming requirements \nAll PMU data from Computational Loads must be streamed to MISO in IEEE/IEC 60255-\n118-1-2018 format at a sampling rate of 60 samples per second. \n11.5.2 Calibration Requirements \n• \nIEEE/IEC 60255-118-1-2018 Accuracy: \no Total Vector Error (TVE): ≤ 1% \no Frequency Error (FE): ≤ 0.005 Hz"},{"page":55,"startToken":10049,"endToken":10328,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 58 of 83 \nOPS-12 \nPublic \no ROCOF Error (RFE): ≤ 0.4 Hz/s \n• \nLaboratory Accuracy: \no 0.5% Measurement Accuracy \n▪ \nCalibration signals/measurement devices retain 0.05% to 0.1% Accuracy \n• \nField Testing Accuracy: \no GPS Receiver Response \n▪ \nCompatibility with IRIG-B Time Standard  \n▪ \nResponds correctly to loss of GPS signal within 1 minute \n• \nIndicated by status code \n▪ \nMonitor GPS signal loss over a 24-hour period to ensure solid \nconnectivity to Satellites \no Phasor Magnitudes \n▪ \nVoltage \n• \nEnsure voltage readings are within range of PT accuracy  \n• \nConfirm readings from testing tools are within 0.5 % of PMU \nreading values \n▪ \nCurrent \n• \nEnsure current readings are within range of CT accuracy  \no If Current magnitude is low (Under 20% of rated current), \nthen allow for extra amps of acceptable error (up to 50 A) \nin magnitude test \n• \nConfirm readings from testing tools are within 0.5 % of PMU \nreading values \no Phasor Angles \n▪ \nVoltage \n• \nConfirm readings from testing tools are within 1 degree of \ncorresponding signal angle differences \n▪ \nCurrent \n• \nConfirm readings from testing tools are within 1 degree of \ncorresponding signal angle differences \no Low current magnitudes will cause extra error here \no Analog Readings \n▪ \nEnsure PMU readings agree to other measuring devices in the substation \nwithin 5% \no Digital Readings \n▪ \nConfirm digital readings report correct Boolean state \n• \nControl Center Accuracy: \no Time Stamp and Server Accuracy \n▪ \nConfirm time stamp of received data matches local time to within 500 milli \nseconds \no Communication Errors and Data Loss \n▪ \nConfirm undesirable data loss is kept below 0.1% over a 24 hour period \n \no SCADA Comparisons \n▪ \nVoltage \n• \nWithin 1% magnitude of comparable locations \n▪ \nCurrent"},{"page":56,"startToken":10328,"endToken":10635,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 59 of 83 \nOPS-12 \nPublic \n• \nWithin 3% magnitude of comparable locations \n▪ \nFrequency \n• \nWithin 0.003 Hz over a 5-minute rolling window \n \n11.6 Support/Manageability Requirements \nTransmission Customer agrees to comply with any and all NERC Standards applicable \nto the PMU/PDC data stream in the event NERC or the MISO determines any of the \nNERC Standards apply to the PMU/PDC data stream and/or any associated \nhardware. \n11.7 Data Retention \nCurrent MISO data retention for synchrophasor data is as below: \n• \nFull resolution for A, B and C phase data is retained for 6 months; and all other data is \nretained for 1 year. \n• \nDown sampled data to one sample per second is retained for 2 years. \n• \nMISO PMU data retention does not replace any local storage requirements including \nobligations that come from existing and future NERC standards. \n11.8  Required PMU Measurements \nPMU’s at the Computational Loads must be able to sample and/or calculate the following \nsignals: \n11.8.1  Substation Measurements \n• \nFrequency - calculated from positive sequence voltage angle  \n• \nRate of Change of Frequency (ROCOF) \n• \nQuality \n11.8.2  Point of Withdrawal (POW) Measurements \n• \nPhase A: voltage magnitude and angle \n• \nPhase B: voltage magnitude and angle \n• \nPhase C: voltage magnitude and angle \n• \nPhase A: current magnitude and angle \n• \nPhase B: current magnitude and angle \n• \nPhase C: current magnitude and angle \n• \nPositive sequence for voltage magnitude and angle \n• \nPositive sequence for current magnitude and angle \n• \nQuality \n11.9  PMU Signal Naming Requirements \n• \nThe fields streamed from the PMU should conform to the naming standards set forth \nbelow to provide a standard set of information about the measurement within the \nmeasurement name. Each field allows space for 16 characters (bytes).  \n• \nStation Name – Name given to each phasor measurement unit: \no 4 bytes: Company Identifier"},{"page":57,"startToken":10635,"endToken":10934,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 60 of 83 \nOPS-12 \nPublic \n▪ \nUse MISO EMS Model Control Area Name \no 10 bytes: Station name \n▪ \nUse MISO EMS Model Station Name \no 2 bytes: Device ID Within Station \n▪ \nAllows for uniqueness when there is more than 1 PMU at a station \n▪ \nAlign the Device ID to measured equipment identifier where possible. Ex: \nif there are PMU’s at 2 large loads (L1,L2) in the substation, use 01 for L1 \nand 02 for L2. \n▪ \nEx. MISOPMU  01 \no Unused bytes should be left as blank spaces. \n• \nChannel Name – Name given to each individual Phasor measurement signal: \no 1 byte: Measurement Identifier \n▪ \nB = Phasor on Bus Side including loads \n▪ \nL = Phasor on Line Side \n▪ \nT = Phasor on Transformer \n▪ \nG = Phasor on Generator \n▪ \nR = Phasor on Reactor \n▪ \nC = Phasor on Capacitor \n▪ \nS = Phasor on Static Var Compensator \n▪ \nD = Digital \n▪ \nA = Non-phasor Analog (Including Frequency, ROCOF) \no 3 bytes: Nominal Voltage \n▪ \nFill from right (‘069’, ‘345’,’161’, etc.) \n▪ \nFor voltages with decimals such as 13.8, round to a whole number. \no 9 bytes:  \n▪ \nMISO EMS Model Device name for measurement location \n▪ \nUse Spaces after name to fill to 9 characters \n• \nEx: L345QWERTY 1V1 \n▪ \nFor all frequency and ROCOF measurements, use “FREQ”. \no 1 byte: \n▪ \n1= First Device, 2= Second Device, 3= Third Device, etc. \no 2 bytes: Measurement Identifier \n▪ \nVx = Voltage Phasor (x = 1, 0, A, B, C, N) \n▪ \nIx = Current Phasor (x = 1, 0, A, B, C, N) \n▪ \nPx = Real Power (x = 1, 0, A, B, C, N) \n▪ \nQx = Reactive Power (x = 1, 0, A, B, C, N) \n▪ \nDC = Digital channel \n▪ \nAC = Analog channel \n▪ \nFR = Frequency \n▪ \nDF = ROCOF \no Unused bytes should be left as blank spaces. \n11.10 Corrective Actions \nSee Corrective Actions in Section 14.4."},{"page":58,"startToken":10934,"endToken":10965,"text":"Business Practices Manual for Large Loads \nBPM-032 \nEffective Date: Dec-04-2026 \n \n \n \n \nPage 61 of 83 \nOPS-12 \nPublic \n11.11 Applicable BPMs and Processes \n• \nBPM-010 Network and Commercial Model \n• \nBPM-031 ICCP Data Requirements"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":295,"startToken":0,"endToken":301},{"p":2,"at":295,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":691,"startToken":301,"endToken":680},{"p":3,"at":691,"title":"II. LIMITED PROTEST","method":"printed heading","endPage":4,"endAt":7,"startToken":680,"endToken":849},{"p":4,"at":7,"title":"A. The Rule of Reason Test","method":"printed heading","endPage":5,"endAt":429,"startToken":849,"endToken":1185},{"p":5,"at":429,"title":"B. MISO’s Filing Contravenes the Commission’s Rule of Reason that Requires","method":"printed heading","endPage":16,"endAt":6,"startToken":1185,"endToken":4657},{"p":16,"at":6,"title":"C. The Commission Should Accept MISO’s Filing Subject to a Compliance","method":"printed heading","endPage":17,"endAt":1123,"startToken":4657,"endToken":5120},{"p":17,"at":1123,"title":"CONCLUSION","method":"printed heading","endPage":19,"endAt":0,"startToken":5120,"endToken":5301},{"p":19,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":58,"endAt":231,"startToken":5301,"endToken":10965}]}