{"document":{"slug":"rec-20260918-5364","title":"Motion For Leave to File Second Limited Answer and Second Limited Answer of East Kentucky Power Cooperative, Inc","issued":"2026-09-18","accession":"20260918-5364","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"East Kentucky Power Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20260918-5364_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5364","tier":"record","sha256":"273b34f2e918b91b431e50ed052c2915c1c744b9276e37b2900386fbc2fcc9e3","pages":35,"tokens":13254,"emptyPages":[],"textThemes":["credit","adequacy","cost","registry"]},"pages":[{"page":1,"startToken":0,"endToken":317,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n) \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-3380-000 \n \n \n \n \n \n \n) \n \n \nMOTION FOR LEAVE TO FILE LIMITED ANSWER,  \nAND LIMITED ANSWER, OF  \nEAST KENTUCKY POWER COOPERATIVE, INC. \n \nPursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure,1 East \nKentucky Power Cooperative, Inc. (“EKPC”) moves for leave to file this limited answer and \nanswers the September 10, 2026 answer submitted by PJM Interconnection, L.L.C. (“PJM”) in the \nabove-captioned proceeding.2 EKPC’s Protest opposed PJM’s proposed revisions to its Open \nAccess Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load \nServing Entities in the PJM Region (“RAA”) to establish the Reliability Backstop Procurement \n(“RBP”) because the RBP Proposal is unjust and unreasonable, unduly discriminatory, inconsistent \nwith the Commission’s cost-causation principles and the boundaries of federal and state \njurisdiction, and contrary to the Ratepayer Protection Pledge.3 PJM’s Answer does not resolve \nthose defects. For the reasons set forth herein and in the EKPC Protest, EKPC respectfully requests \nthat the Commission reject the RBP Proposal. \nEKPC also submits this Limited Answer to place PJM’s post-protest explanations and \nimplementation materials in their proper context. PJM’s Answer relies on clarifications, \n \n1 See 18 C.F.R. §§ 385.212, 385.213 (2026). \n2 PJM Interconnection, L.L.C., “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” Docket \nNo. ER26-3380-000 (filed Sept. 10, 2026) (“PJM Answer”). \n3 See PJM Interconnection, L.L.C., “Protest of East Kentucky Power Cooperative, Inc.,” at 11–14, 15–49, Docket No. \nER26-3380-000 (filed Aug. 21, 2026) (“EKPC Protest”); Affidavit of Adam Bednarczyk PP 7, 12, 14, 17, 27, 34, 38, \n42, 46, 59–70, Attachment 1 to EKPC Protest (“Bednarczyk Protest Aff.”); Affidavit of Carl F. Coscia PP 57–58, 72–\n80, 98, 109–121, 135–174, 175–210, Attachment 2 to EKPC Protest (“Coscia Protest Aff.”)."},{"page":2,"startToken":317,"endToken":770,"text":"2 \n \nconcessions, and implementation descriptions that were not fully reflected in the July 31 filing or \navailable for meaningful stakeholder review before protests were due.4 PJM itself characterizes its \nAnswer as providing post-filing clarifications and adjustments and cites post-Critical Issue Fast \nPath (“CIFP”) workshops and implementation materials.5 EKPC therefore addresses those \ndevelopments to assist the Commission in evaluating whether the RBP Proposal as filed—not as \nsubsequently explained or refined—satisfies PJM’s section 205 burden. \nI. \nMOTION FOR LEAVE TO FILE LIMITED ANSWER \nAlthough Rule 213(a)(2) generally prohibits answers to protests or answers absent \nCommission authorization, the Commission accepts otherwise-prohibited answers when they \nprovide information that assists its decision-making,6 and clarify the record.7 Good cause exists \nhere to justify the Commission’s granting this motion and accepting this Limited Answer. PJM’s \nAnswer misconstrues or does not address central issues raised in EKPC’s Protest and First Limited \nAnswer,8 including whether RBP costs and transmission owner exit fees bear a meaningful \nrelationship to cost causation, whether PJM treats Fixed Resource Requirement (“FRR”) entities \nand Reliability Pricing Model (“RPM”) self-supply load-serving entities (“LSEs”) comparably, \n \n4 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address \nResource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”). \n5 See PJM Answer at 8–10 & nn.31–32.  \n6 See PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting an answer that assisted with the \ndecision-making process); N.Y. State Pub. Serv. Comm’n v. N.Y. Indep. Sys. Operator, Inc., 158 FERC ¶ 61,137, at P \n29 (2017) (same), order granting in part and denying in part reh’g and clarification, 170 FERC ¶ 61,120, order on \nclarification, 171 FERC ¶ 61,114 (2020); Colonial Pipeline Co., 157 FERC ¶ 61,173, at P 23 (2016) (same). \n7 See, e.g., Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229, P 102 (2012) (accepting answer \nto an answer because it provided material evidence that corrected the record and informed the Commission’s decision-\nmaking process); High Island Offshore Sys., L.L.C., 113 FERC ¶ 61,202, P 8 (2005) (accepting an answer to a protest \nbecause it assisted the Commission with a more complete record); N.E. Utils. Servs. Co. v. NRG Energy, Inc., 101 \nFERC ¶ 61,327, P 17 (2002) (accepting answer to an answer because it helped clarify issues in the proceeding). \n8 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and \nLimited Answer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 4, 2026) (“EKPC First Limited Answer”) \n(supporting protests filed by transmission owners addressing PJM’s proposed Transmission Owner exit fee provisions \nof the RBP)."},{"page":3,"startToken":770,"endToken":1054,"text":"3 \n \nand whether the proposed credit and default provisions define, secure, and allocate the relevant \nexposures in a just and reasonable manner. PJM also supplies new explanations and proposed \nconcessions concerning severance of the buyer-side LSE credit rate, the timing and calculation of \ncollateral, Peak Market Activity, and default allocation.9 This Limited Answer responds only to \nthose matters and to PJM’s post-filing implementation explanations, will not prejudice any party \nor delay the proceeding, and will assist the Commission in evaluating whether PJM has carried its \nburden under section 205 of the Federal Power Act (“FPA”). The Commission should therefore \naccept this Limited Answer. \nII. \nBACKGROUND AND SUMMARY \nOn July 31, 2026, PJM filed proposed revisions to its Tariff and RAA to establish a RBP \nintended to address identified capacity shortfalls associated with forecast large-load growth. \nEKPC’s Protest explained that a legitimate reliability objective does not excuse a rate design that \nfails to make costs, credits, collateral obligations, and default risks transparent, traceable, \nadministrable, and reasonably tied to the entities that caused or benefit from the procurement.10 \nPJM’s proposed fallback allocation still spreads RBP costs to load without demonstrating that the \ncharged LSEs caused the procurement need or receive commensurate benefits. Its disparate \ntreatment of FRR entities and RPM self-supply LSEs remains unexplained. And severing one \ncredit-rate input leaves unresolved the nature, timing, quantity, release, and default treatment of \nthe exposure being collateralized.  \nPJM’s Answer does not cure those defects, and the allocation of the burden of proof \nmatters. This is PJM’s section 205 filing. PJM therefore must establish, by record evidence and \n \n9 See PJM Answer at 74–93, pts. I.J.1–I.J.6. \n10 See EKPC Protest at 11."},{"page":4,"startToken":1054,"endToken":1438,"text":"4 \n \nreasoned explanation, that the particular tariff rules it filed—not merely the reliability objective \nthey pursue—are just and reasonable and not unduly discriminatory or preferential.11 EKPC need \nnot design a superior replacement or disprove every possible justification that PJM might have \nsupplied. If PJM has not shown how its allocation, offset, collateral, and default provisions produce \nlawful outcomes, the statutory prerequisite to the Commission’s acceptance of the RBP Proposal \nis absent. The Commission therefore should reject the RBP Proposal or, at minimum, reject or set \nfor further procedures the unsupported provisions identified below.12 \nPJM’s evolving explanation of the buyer-side credit framework confirms that material \naspects of the RBP Proposal remained under development after the PJM RBP Filing. PJM now \noffers to remove Tariff language concerning Peak Market Activity, clarifies that collateral is not \ndue until 45 days before the first Delivery Year for which an LSE is responsible for RBP Charges, \nand consents to further procedures on the buyer-side credit rate.13 Whatever authority PJM has to \nmake a section 205 filing, the relevant point is that the credit design now being defended was not \nfully presented in the stakeholder process or, most importantly for purposes of the Commission’s \ndeliberation, in the filed tariff language presented in PJM’s RBP Filing. LSEs were asked to \nevaluate a proposal whose collateral mechanics, interaction with Peak Market Activity, timing, and \nexposure methodology were still being refined after protests were filed. That procedural history \n \n11 See 16 U.S.C. § 824d(a), (b), (e); Hecate Energy LLC v. FERC, 126 F.4th 660, 662 (D.C. Cir. 2025) (explaining that \nsection 205 requires the Commission to accept proposed changes only if they are just and reasonable and not unduly \ndiscriminatory); City of Winnfield v. FERC, 744 F.2d 871, 875 (D.C. Cir. 1984) (contrasting the filing utility’s burden \nunder section 205 with a complainant’s burden under section 206); see also 18 C.F.R. § 35.13(e) (2026) (requiring \nsupport for proposed rate changes). \n12 Failure in this Answer to specifically address a point raised by PJM should not be viewed as a concession by EKPC \nthat it is no longer challenging that aspect of the RBP.   \n13 See PJM Answer at 78 n.234, 86 n.259, 92–93 & nn.282–86."},{"page":5,"startToken":1438,"endToken":1778,"text":"5 \n \nreinforces—not replaces—EKPC’s substantive showing that the proposal lacks administrable tariff \nstandards. \nIII. \nLIMITED ANSWER \nA. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205. \nSection 205 places the burden squarely on PJM to show that the RBP is just and reasonable. \nAll jurisdictional rates and all rules and practices affecting them must be just and reasonable and \nnot unduly discriminatory or preferential, and when a public utility proposes a change, “the burden \nof proof to show that the increased rate or charge is just and reasonable shall be upon the public \nutility.”14 The Commission’s regulations accordingly require a filing utility to submit the \ninformation necessary to explain and support the proposed change.15 The distinction from section \n206 of the FPA is fundamental: PJM is not defending an existing rate presumed lawful against an \nEKPC complaint; PJM is asking the Commission to authorize new tariff provisions.16 PJM itself \nhas publicly described the governing rule the same way: a public utility making a section 205 filing \n“has the legal burden of demonstrating” that its proposed change is just and reasonable.17  \nTo satisfy this burden requires more than showing that a reliability problem exists or that \nPJM’s preferred mechanism is administratively convenient. PJM must connect the evidence to the \nspecific rate design for which it seeks approval. And the Commission must evaluate the proposal \nactually filed on the record before it, provide a reasoned explanation for its conclusion, and respond \n \n14 16 U.S.C. § 824d(a), (b), (e). \n15 See 18 C.F.R. §§ 35.12, 35.13 (2026)  (any public utility filing a rate change must submit detailed data and statements \nto “sustain the burden of proof under the Federal Power Act of establishing that the rate increase is just and \nreasonable”). \n16 See City of Winnfield, 744 F.2d at 875. \n17 PJM Interconnection, L.L.C., Federal Law Guides Changes in PJM Governing Documents 1 (2025), available at: \nhttps://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/federal-power-act-sections-205-and-\n206.pdf."},{"page":6,"startToken":1778,"endToken":2201,"text":"6 \n \nto material objections that cast doubt on the proposal’s lawfulness.18 The Commission therefore \ncannot presume answers that PJM did not supply, rely on conclusory assertions that the proposal \nis “tailored,”19 or treat unanswered cost-causation questions as EKPC’s failure of proof. A material \nevidentiary gap is PJM’s failure to carry its section 205 burden. \nB. PJM Failed to Address EKPC’s Cost Causation Arguments.  \nCost causation is not a subsidiary policy preference that the Commission may bypass once \nPJM identifies a regional shortfall. A rate must reflect, at least to some degree, the costs caused by \nthe customers required to pay it, and an allocation based on benefits must be at least roughly \ncommensurate with the benefits received.20 PJM’s own Answer invokes the same principle: costs \nshould be recovered from customers that use the facilities and cause the costs to be incurred.21 But \nPJM does not carry that principle through the RBP Proposal. \nPJM’s transmittal letter establishes a regional capacity shortfall and attributes much of the \nforecast growth to large loads.22 But PJM does not demonstrate each link necessary to justify the \nproposed charge. PJM does not identify how the forecast increment used to set the procurement \ntarget will be traced to the particular LSEs ultimately assessed RBP Charges, show that an Electric \nDistributor or state/Relevant Electric Retail Regulatory Authority (“RERRA”) allocation will \npreserve that causal link, require an offset or prudent existing supply to follow the LSE or load \n \n18 See Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983); PSEG Energy Res. & \nTrade LLC v. FERC, 665 F.3d 203, 208 (D.C. Cir. 2011). \n19 PJM Answer at 10 (the role of an Electric Distributor is “[a]ppropriately tailored”), 42 (the proposed gating criteria \nas “appropriately tailored”), 74 (the buyer-sider credit requirements are “appropriately tailored”).  \n20 See K N Energy, Inc., 968 F.2d 1295, 1300-01 (D.C. Cir. 1992) (“requiring that all approved rates reflect to some \ndegree the costs actually caused by the customer who must pay them.”); Midwest ISO Transmission Owners v. FERC, \n373 F.3d 1361, 1368-69 (D.C. Cir. 2004) (same); Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 476-77 (7th Cir. \n2009) (same); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-61 (D.C. Cir. 2018) (same). EKPC Protest at \n29–31; Bednarczyk Protest Aff. at PP 17–22, 27–40. \n21 PJM Answer at 61–63 & nn.182–92. \n22 See PJM RBP Filing at 1-2, 7."},{"page":7,"startToken":2201,"endToken":2529,"text":"7 \n \nthat provided it, explain why a Peak Load Contribution-based (“PLC”) fallback measures \ncausation by the identified large-load growth, or establish that a customer charged under the \nfallback measure will receive a benefit roughly commensurate with its assigned costs. Moreover, \nPJM’s proposed Tariff text likewise supplies no objective standard that answers those questions. \nDescribing the mechanics of a downstream allocation process is not evidence that the resulting \nallocation is just and reasonable.23 \nThese are not isolated objections. Mr. Bednarczyk explained that the RBP fails to maintain \na traceable link among incremental large-load responsibility, recognized mitigation, RBP \nObligations (“RBO”) MW, RBP Charges, and collateral obligations.24 Mr. Coscia then showed that \nthe credit construct compounds that defect because the collateral obligation is not derived from a \nmeasured exposure, is not tied to the timing of actual RBP settlement risk, and may itself create \nliquidity and default risk.25 PJM’s Answer addresses pieces of those critiques but does not supply \nthe missing tariff standards needed to make the RBP framework administrable and causation-\nbased. \nPJM cannot cure the deficiencies by assigning the missing analysis to Electric Distributors, \nstates, or RERRAs.26 Those entities may administer retail matters or choose how a valid wholesale \nobligation is recovered, but their later choices cannot supply the predicate showing PJM had to \nmake when it filed the wholesale rate.27 If PJM’s Tariff does not provide a causation-based \n \n23 See EKPC Protest at 15-21 (explaining that the PJM RBP Proposal is unjust and unreasonable because the resulting \nrate impact is uncertain).  \n24 Bednarczyk Protest Aff. at PP 12–22, 26–40, 47–58, 65–70. \n25 Coscia Protest Aff. at PP 57–58, 72–80, 98, 109–121, 135–174, 201–210. \n26 See EKPC Protest at 19-21, 37-38.  \n27 See 16 U.S.C. § 824d(c), (d); Atl. City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002) (“the power to initiate \nrate changes rests with the utility”)."},{"page":8,"startToken":2529,"endToken":2942,"text":"8 \n \nallocation rule, a state’s later decision cannot retroactively make the filed wholesale rate just and \nreasonable. \nNor may PJM’s Answer substitute new explanation for missing Tariff content. The \nCommission evaluates the filed rate as proposed, and regulated entities must be able to determine \ntheir obligations from the governing tariff rather than from post-filing assurances.28 Where PJM \nnow offers clarifications, concessions, or severance to answer protests, those responses confirm \nthat the as-filed provisions did not themselves resolve material uncertainties and issues of the \nproposed rated. \nFinally, the Commission may not save the RBP Filing by assembling a different proposal \nfrom stakeholder alternatives or by supplying its own reasoning to reinterpret filed tariff revisions \nthat PJM did not provide.29 The stakeholder-supported subscription alternative referenced by \nEKPC in its Protest is relevant because it demonstrates that causation-based approaches existed, \nnot because EKPC bears a burden to prove that alternative uniquely just and reasonable.30 EKPC \nfurther observes that PJM’s RBP Proposal inappropriately relies on downstream state/RERRA \naction. PJM could have adopted the stakeholder-supported proposal that relied on RERRA action \nat the outset of the backstop procurement process to ensure that LSEs serving Large Loads would \n \n28 See e.g., NRG Power Marketing, LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017) (holding that FPA section \n205 did not authorize the Commission to transform a utility’s proposal into an “entirely new rate scheme,” \nnotwithstanding the filing utility’s agreement to the Commission-imposed modifications); Western Resources, Inc. v. \nFERC, 9 F.3d 1568, 1578–79 (D.C. Cir. 1993) (distinguishing permissible conditions that leave the proposal’s essential \nstructure intact from modifications that exceed the Commission’s authority); KeySpan-Ravenswood, LLC v. FERC, \n474 F.3d 804, 811–12 (D.C. Cir. 2007) (vacating an order where the Commission permitted NYISO to use material \nconversion formulae not set forth in the filed tariff and the Commission failed adequately to explain why they need \nnot be filed). See also EKPC Protest at 15-21 (a filed rate must provide specificity and allow impacted customers to \nestimate the cost impact). \n29 See NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114-15 (D.C. Cir. 2017) (“Section 205 puts FERC in a ‘passive \nand reactive role.’” (quoting Advanced Energy Management Alliance v. FERC, 860 F.3d 656, 429 (D.C. Cir. June 20, \n2017)). \n30 EKPC Protest at 8-10; Bednarczyk Protest Aff. at P 44. PJM completely failed to address Mr. Bednarczyk’s affidavit \nin its Answer."},{"page":9,"startToken":2942,"endToken":3233,"text":"9 \n \nsubscribe to the auction to ensure that the capacity shortfall would be addressed through sufficient \nsubscription. PJM’s concern with the stakeholder-supported proposal is that the PJM Board did \nnot have confidence it addressed the capacity shortfall. However, reliance on states/RERRAs could \nhave addressed the capacity shortfall concern while also affording certainty as to which LSEs \nwould be receiving RBP allocations and be fully responsible for RBP costs and credit \nresponsibilities and being consistent with cost-causation principles. More importantly, reliance on \nstates/RERRAs at the start of a backstop procurement process would be consistent with \nestablishing a valid wholesale obligation that would appropriately align with the state’s/RERRA’s \nresponsibilities for retail rate determinations. \nC. EKPC’s Protest Is Consistent with the Ratepayer Protection Pledge. \nPJM suggests that EKPC’s execution of the Ratepayer Protection Pledge is inconsistent \nwith its opposition to the RBP.31 The opposite is true. EKPC supports the principle that new large \nloads should build, bring, or buy the resources needed to serve their demands and bear the full \nassociated costs. In fact, EKPC supported the Joint EDC & Data Center Coalition Reliability \nBackstop Procurement Proposal, which would have enabled states/RERRAs to act at the outset of \nan RBP process to ensure LSEs responsible to provide retail service to Large Loads subscribed to \nthe procurement process so the appropriate amount of capacity is procured.  As noted above, this \nwould have provided greater certainty, better aligned cost causation, and provided ratepayer \nprotection by ensuring the appropriate LSEs are charged the costs they were directly responsible \nfor incurring. EKPC protested the RBP because, as proposed, the RBP may shift those costs to \nLSEs and customers that prudently planned their portfolios and did not cause the residual \n \n31 PJM Answer at 59."},{"page":10,"startToken":3233,"endToken":3643,"text":"10 \n \nprocurement need.32 A mechanism that can impose RBP charges, collateral burdens, or mutualized \ndefault exposure on non-causers conflicts with—rather than implements—the Pledge’s ratepayer-\nprotection objective.33 \nPJM’s assertion that EKPC presently receives no direct RBP allocation does not answer \nEKPC’s fundamental objections to the RBP proposal.34 EKPC challenges the RBP Proposal, \nincluding its precedential and future effects, not merely its first illustrative assignment. \nAlthough PJM describes the RBP as a one-time process,35 the proposed Tariff and RAA language \ndoes not itself supply a clear one-time limitation, and PJM has publicly contemplated RBP or \nsimilar mechanisms in future reliability frameworks.36 The Commission must evaluate the filed \nprovisions as proposed. \nPJM’s reliance on the Ratepayer Protection Pledge to support its transmission-owner exit \nprovisions is similarly misplaced.37 Requiring entities that did not cause the RBP need to bear costs \nassociated with pseudo-tying generation back into PJM after a transmission owner exits would \n \n32 See EKPC Protest at 14 (“The PJM RBP Proposal creates unmitigable financial and reliability risk for LSEs that \nprudently planned for their load or otherwise did not cause the residual RBP procurement need.”), Bednarczyk Protest \nAff. at P 34 (“an LSE that has already planned prudently and secured adequate resources could nonetheless incur a \nsecond long-term obligation that provides little or no additional reliability benefit. That outcome weakens incentives \nfor proactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning LSE exposed to \nresidual charges, collateral obligations, and default-allocation risk.”). \n33 See EKPC Protest at 28, 39, 48-49 (explaining why the RBP Proposal is inconsistent with the Ratepayer Protection \nPledge).  \n34 PJM Answer at 67 n.205.  \n35 PJM similarly described the RPM price collar as a one-time, temporary measure but it has now been extended for \nmultiple, additional delivery years. See PJM Interconnection, L,L.C., 195 FERC ¶ 61,076 (2026).  \n36 See PJM Interconnection, L.L.C., Draft Memorandum of Understanding Framework Between States and PJM Re: \nReliability/Resource Adequacy (PJM “Commits to establish Reliability Backstop Procurements, or other similar \nmechanisms codified in Attachment DD of the PJM Open Access Transmission Tariff at the request of states and with \nthe approval of FERC, to allow for the procurement of additional capacity where shortfalls have been identified and \nrisk \nto \nsystem \nreliability \nis \ncredible”)  \nfound \nat: \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/mc/2026/20260819/20260819-item-08---2-memorandum-of-understanding-framework-between-\npjm-and-states.pdf \n37 See PJM Answer at 94."},{"page":11,"startToken":3643,"endToken":3997,"text":"11 \n \nreproduce the same cost-causation problem.38 PJM does not explain why those costs should follow \nnon-causing load rather than the transaction, entity, or circumstance that makes the pseudo-tie \nnecessary. \nD. PJM Does Not Justify Disparate Treatment of FRR Entities and RPM Self \nSupply LSEs. \n \nPJM fundamentally misunderstands EKPC’s argument with respect to treatment of FRR \nentities. Contrary to PJM’s assertion, EKPC does not argue that FRR entities should be subjected \nto the RBP.39 EKPC’s point is comparability.40 PJM recognizes an FRR entity’s existing portfolio \nand excludes its load and supply from RBP exposure, while an RPM self-supply LSE may receive \nno comparable recognition for resources it already owns or procured to serve its customers.41 Both \nentities may have taken materially similar planning actions to satisfy aggregate resource \nobligations. PJM does not identify a relevant operational or cost-causation distinction that justifies \ninsulating one portfolio while disregarding the other. \nThat unexplained asymmetry raises classic undue-discrimination concerns. FPA section \n205(b) prohibits an undue preference or advantage and any unreasonable difference in rates or \nservice among similarly situated customers.42 That FRR entities face a deficiency rate does not \ncure the problem, particularly where that rate is not yet effective for the relevant period.43 Nor \ndoes moving related FRR language to the IRAS docket establish that the RBP’s differential \n \n38 See EKPC First Limited Answer.    \n39 See PJM Answer at 55.  \n40 EKPC Protest at 45 (“PJM’s RBP Proposal’s treatment of FRR entities and the use of existing resources to satisfy \nFRR plans creates comparability concerns and unduly discriminates against RPM Capacity Market LSEs in several \nways.”). See also Bednarczyk Protest Aff. at PP 59-60 (“The RBP also treats FRR entities and RPM self-supply entities \ndifferently in ways that raise comparability concerns.”).  \n41 EKPC Protest at 45. \n42 16 U.S.C. § 824d(b); see Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 367 (D.C. Cir. 2002). \n43 See RAA, Schedule 8.1, Section D (7) (“For Delivery Years between the 2025/2026 Delivery Year through the \n2028/2029 Delivery Year, no FRR Commitment Insufficiency Charge shall be assessed.”)."},{"page":12,"startToken":3997,"endToken":4345,"text":"12 \n \ntreatment is just and reasonable.44 The Commission should require PJM to recognize comparable \nportfolio sufficiency or explain, with record evidence, why materially similar planning conduct \nwarrants materially different RBP treatment. \nE. PJM’s Proposed Credit-Rate Severance Does Not Cure the RBP’s Credit \nand Default Defects. \n \nAs detailed in the EKPC Protest, PJM’s proposed collateral requirements are unjust and \nunreasonable and should be rejected.45 If the Commission nevertheless accepts PJM’s proposal to \nsever the buyer-side LSE credit rate for further procedures, the numerical rate is only one \ncomponent of the defect.46 Any further proceeding must define the exposure being secured, the \nquantity to which the rate applies, the date on which the obligation arises, objective reduction and \nrelease standards, the interaction with Operating Agreement section 15.2.2, and the liquidity and \ndefault consequences created by the requirement. Severing one input cannot make the remainder \nof the RBP just and reasonable when the obligation’s basic operation remains uncertain. \nPJM’s Answer also contains unresolved inconsistencies. PJM states that EKPC would \nreceive no RBP cost allocation or reallocation under proposed section 18.9(a), yet PJM invokes \nOperating Agreement section 15.2.2—and the need to protect PJM Members from LSE default—\nto justify the collateral requirement.47 If section 18.9 fully contains an RBP default within the pool \nof LSEs assigned RBP Charges, PJM should state that limitation in the governing Tariff text. If \nresidual unpaid amounts may reach all PJM Members under Operating Agreement section 15.2.2, \nthen EKPC’s lack of a direct RBP allocation does not eliminate its exposure. PJM cannot rely on \n \n44 EKPC filed a limited protest in the IRAS proceeding and objected to the language at issue in that docket as well. \nSee PJM Interconnection, L.L.C., “Limited Protest of East Kentucky Power Cooperative, Inc.,” 35-36, Docket No. \nER26-3515-000 (filed Sept. 3, 2026).  \n45 EKPC Protest at 21–28; Coscia Protest Aff. at PP 61–121, 135–174, 201–210. \n46 See PJM Answer at 92–93. \n47 See PJM Answer at 67 n.205, 84 n. 252."},{"page":13,"startToken":4345,"endToken":4647,"text":"13 \n \nmutualized Member exposure to defend the credit design while denying that the same exposure \nreaches EKPC. \nPJM’s remaining clarifications likewise do not conform to the filed Tariff. First, PJM offers \nto delete the sentence stating that RBP settlement may be included in Peak Market Activity,48 but \ndoes not explain how an invoiced RBP billing item is excluded from Peak Market Activity or \nwhether Attachment Q requires a conforming revision. Second, PJM states that no LSE collateral \nis required until an RBP Resource is in service for the applicable Delivery Year,49 but proposed \nsection 18.8(b)(i)(A)—the buyer-side cumulative requirement—defines committed RBP UCAP \nMW without an express in-service limitation. Third, PJM states that collateral is based on \ncommitted MW,50 while section 18.8(b)(i)(B)(1) scales the LSE posting to the Final RBP Target. \nIf procurement clears below that target, the filed language does not specify which quantity controls \naggregate collateral. \nPJM’s credit-migration analysis does not cure those defects. PJM extrapolates S&P’s ten-\nyear transition study to fifteen years and reports an approximately 11 percent probability that a \nBBB obligor reaches default and 36.9 percent for a BB obligor.51 But that table measures migration \narising in the ordinary course; it does not measure what happens to an LSE’s financial condition \nwhen PJM imposes a collateral obligation of the magnitude proposed here.52 On PJM’s own \nallocation, the cooperative with the second-largest zonal assignment would post approximately \n114 percent of its total assets, roughly twice its equity, and about eight times its cash, while a 100-\n \n48 PJM Answer at 86, n.259.  \n49 PJM Answer at 78, n. 234. \n50 PJM Answer at 78, n. 234. \n51 PJM Answer at 81-82, Table 2.  \n52 Coscia Reply Affidavit at P 26."},{"page":14,"startToken":4647,"endToken":4968,"text":"14 \n \nbasis-point carrying cost would consume approximately 94 percent of one year’s operating \nmargins.53 That cooperative is investment grade and among the 24 LSEs PJM itself classified as \ninvestment grade.54 At this scale, the migration PJM invokes to defend a credit-blind rate may be \npartly a consequence of the rate itself. Additionally, PJM applies credit sensitivity to sellers while \ndeclining to do so for buyers, without adequately explaining that asymmetry.55 \nThe stakeholder record further confirms that credit-specific, causation-based alternatives \nexisted, including that buyer-side credit could be managed through existing processes. 56 The June \n30 Package Matrix also shows that the Joint EDC/Data Center Coalition proposed a pre-\nprocurement registry identifying which LSEs must support collateral and for how many \nmegawatts, with a gate preventing procurement for load whose responsible LSE or large-load \ncustomer could not post.57 PJM states that the filed LSE credit requirement has roots in the Joint \nEDC/ Data Center Coalition proposal,58 but the filed design adopts the assignment to LSEs without \nthe registry, gate, or exposure-funding mechanics that tied credit responsibility to the load being \nprocured for. This record reinforces that causation-based approaches existed on the precise credit \nissue; PJM did not justify discarding their limiting mechanics. \nThe economics also show why the gross payment stream is not a sufficient measure of \nRBP-specific exposure. For 6,000 MW with three years remaining, an RBP price of $555/MW-\nday, and an RPM price of $554/MW-day, the incremental contract-for-differences payment is only \n \n53 Coscia Reply Affidavit at P 27. \n54 Coscia Reply Affidavit at P 27. \n55 Coscia Reply Affidavit at P 28. \n56 Coscia Reply Affidavit at P 33. \n57 Coscia Reply Affidavit at P 34. The June 30 Package Matrix is available at: https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-cifp---reliability-backstop-procurement---\noptions-and-packages-matrix---updated.xls   \n58 Coscia Reply Affidavit at P 35; PJM RBP Filing at 22."},{"page":15,"startToken":4968,"endToken":5268,"text":"15 \n \n$2.19 million per year, or $6.57 million over three years.59 The $554/MW-day RPM component—\napproximately $3.64 billion over the same period—would settle through ordinary RPM billing \nand, absent the RBP, would be addressed through PJM’s existing credit processes.60 Thus, the gross \nthree-year amount on which PJM relies consists almost entirely of future RPM payments rather \nthan incremental RBP exposure.61 The filed provisions do not explain why, for example, a $1/MW-\nday contract-for-differences transforms the associated RPM stream into a separately collateralized \nlong-term obligation or establish an objective method for reducing and releasing collateral as the \ncontract-for-differences and remaining tenor decline. \nFinally, PJM states that no LSE collateral is due until 45 days before the first Delivery Year \nin which an LSE is responsible for RBP Charges.62 That clarification does not justify postponing \nresolution of the buyer-side credit framework until shortly before collateral is due. The credit \nframework affects the economics, financeability, risk allocation, and potential creditworthiness of \naffected LSEs from the moment RBP commitments become binding, which is currently proposed \nto occur in December 2026.63  \nAppropriate buyer-side credit provisions are essential for the PJM RBP Proposal to be just \nand reasonable, and  PJM’s proposed buyer-side credit provision clearly do not meet this standard.   \nShould the Commission decide to not reject PJM’s RBP Proposal outright, including the buyer-\nside credit provisions, it should require PJM to propose and obtain Commission approval of a \ncomplete, exposure-based buyer-side credit framework before RBP commitments become \n \n59 Coscia Reply Affidavit at P 59 and Table 1. \n60 Coscia Reply Affidavit at P 60. \n61 Coscia Reply Affidavit at P 60. \n62 PJM Answer at 78 n.234, 92–93 & n.285. \n63 Coscia Protest Aff. at PP 72–80, 135–152, 201–210."},{"page":16,"startToken":5268,"endToken":5557,"text":"16 \n \nbinding. At an absolute minimum, the Commission should establish a date certain that gives \naffected LSEs, states, RERRAs, and large loads a meaningful opportunity to evaluate, challenge, \nfinance, and implement any required credit support well before the first posting deadline. The \nurgency of securing capacity does not justify making long-term commitments (of a duration that \nis up to 15 years longer than any other PJM-administered market) first and resolving a fundamental \nallocation and credit issue years later.  \nF. The Commission Should Reject the Proposed Default Allocation. \n \nThe Commission should reject the default allocation because PJM has not demonstrated \nthat shifting an unpaid RBP Charge among the remaining LSEs preserves any relationship to \ncausation or benefits. The fact that the residual loss must be placed somewhere does not establish \nthat PJM’s chosen recipients caused it or receive commensurate benefits from assuming it. PJM \nmust support that choice under section 205 just as it must support the initial allocation. The \nCommission cannot infer a lawful nexus from the mere existence of default risk. At minimum, the \nCommission must require Tariff language confining RBP nonpayment to entities assigned RBP \nCharges and reasoning documented in the record as to why any reallocation among them remains \njust and reasonable. \nG. PJM’s Portfolio-Benefit Theory Underscores the Mismatch. \n \nPJM argues that one LSE’s actions can reduce other LSEs’ RBP obligations because pooled \nbenefits are inherent in an RTO.64 But PJM recognizes portfolio benefits when they reduce its \nprocurement target while denying comparable recognition to the owner or contracting LSE when \ndetermining offsets or exposure. In its Protest, EKPC explained that without a rule requiring offsets \nand existing-supply recognition to follow the responsible LSE or load, the RBP unfairly socializes \n \n64 PJM Answer at 73."},{"page":17,"startToken":5557,"endToken":5834,"text":"17 \n \nthe benefit of prudent resource planning while leaving those LSEs that adequately covered their \nload obligations exposed to potential charges and collateral requirements.65 PJM has not explained \nwhy portfolio effects count when they reduce the regional procurement need but not when they \ndemonstrate that a particular LSE prudently supplied its own load. That asymmetry is especially \ndifficult to justify if PJM later repeats or repurposes the RBP. \nIV. \nCONCLUSION \nFor the foregoing reasons, EKPC respectfully requests that the Commission accept this \nlimited answer and reject PJM’s RBP Proposal. PJM bears the section 205 burden, and neither its \ntransmittal letter, proposed Tariff language, supporting affidavits, nor Answer demonstrates that \nthe challenged cost-allocation, offset, collateral, credit, default, and transmission owner exit fee \nprovisions are just and reasonable and not unduly discriminatory or preferential. The Commission \ntherefore lacks a reasoned record basis to accept those provisions; it cannot sidestep EKPC’s \nmaterial cost-causation objections, presume facts PJM did not establish, or supply missing tariff \nstandards on PJM’s behalf. Should the Commission be inclined to accept PJM’s RBP Proposal and \naccept PJM’s suggestion for severing the buyer-side credit provisions, EKPC respectfully urges \nthe Commission to undertake additional administrative proceedings that would result in tariff \nlanguage that clearly defines, measures, and confines RBP credit and default exposure  before the \nRBP commitments would be established (currently proposed to be in December 2026).  It is \nimperative that buyer-side credit requirements be certain before RBP commitments become \nbinding, and that the buyer-side credit rules provide LSEs a meaningful opportunity to evaluate \nand arrange credit support well before any collateral posting obligation arises. \n \n65 EKPC Protest at 31; Bednarczyk Protest Aff. at PP 27, 34."},{"page":18,"startToken":5834,"endToken":5935,"text":"18 \n \n \nRespectfully submitted, \n \n \nDenise R. Foster Cronin \nChief Compliance Officer and Senior Vice \nPresident \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTel.: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \nOn Behalf of East Kentucky Power \nCooperative, Inc. \n \n/s/ Daniel E. Frank \n \n \nDaniel E. Frank \nAllison E. S. Salvia  \nKelly A. Cuthbertson \nAdriana J. Santana \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTel.: 202-383-0100 \nEmail: danielfrank@eversheds-sutherland.com \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \nanasantana@eversheds-sutherland.com \n \nCounsel for \nEast Kentucky Power Cooperative, Inc. \n \n \n \n \nDated: September 18, 2026"},{"page":19,"startToken":5935,"endToken":5943,"text":"Attachment 1 \nReply Affidavit of Carl F. Coscia"},{"page":20,"startToken":5943,"endToken":6418,"text":"1 \n \nREPLY AFFIDAVIT OF CARL F. COSCIA, Ph.D. \nOn behalf of East Kentucky Power Cooperative, Inc. \nPJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000 \n \nI. \nPURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS \n1. \nMy name is Carl F. Coscia. I am the Principal of Toller Energy. I submitted an affidavit in \nthis docket on August 21, 2026 (“Coscia Protest Affidavit”) in support of the protest of \nEast Kentucky Power Cooperative, Inc. (“EKPC”).  My qualifications, the basis for my \nopinions, and the materials I reviewed are set out at paragraphs 1 through 5 of that affidavit \nand are not repeated here. The opinions expressed in this reply are my own. No part of my \ncompensation is contingent on the outcome of this proceeding. \n2. \nSince submitting that affidavit I have reviewed PJM’s answer filed September 10, 2026 \n(“PJM Answer”);1 its Reliability Backstop Procurement Execution presentation of \nSeptember 14, 2026 (“September 14 Presentation”);2 and PJM’s written responses to \nquestions I submitted to PJM on August 12, August 14, August 31 and September 15, 2026. \nI have also reviewed PJM’s Credit & Securitization Overview of March 4, 2026 (“March \n4 Credit Overview”);3 its Reliability Backstop Procurement Design presentations of April \n16-17, 2026 (“April 17 Design Presentation”),4 May 27, 2026,5 and June 10-11, 2026 \n(“June Design Presentation”);6 its Stage 1 Proposal Status Update of May 5, 2026 (“May \n5 Status Update”);7 its Stage 4 proposal materials of June 30, 2026;8 and the CIFP-RBP \nOptions and Packages Matrix updated June 30, 2026 (“Package Matrix”).9 References to \nthe “July 31 Filing” are to PJM’s initial filing in this proceeding, including the proposed \n \n1 PJM Interconnection, L.L.C., “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” Docket \nNo. ER26-3380-000 (filed Sept. 10, 2026).  \n2 September 14 Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260914/20260914-item-01---reliability-backstop-procurement-execution---presentation.pdf \n3 \nMarch \n4 \nCredit \nOverview \navailable \nhere: \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm-\npresentation.pdf \n4 April 17 Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260417/20260417-item-05---pjm-reliability-backstop-procurement-design---pjm-presentation.pdf \n5 May 27 Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260527/20260527-item-05---reliability-backstop-procurement-design---pjm-presentation---updated.pdf \n6 June Design Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260610/20260610-item-04a---pjm-reliability-backstop-procurement-design-presentation.pdf \n7 May 5 Status Update Presentation available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260504/20260504-item-03---pjm-proposal-update.pdf \n8 Stage 4 proposal materials available here: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260630/20260630-item-02a---pjm-reliability-backstop-procurement-proposal---paper.pdf \n9 \nPackage \nMatrix \navailable \nhere: \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260630/20260630-cifp---reliability-backstop-procurement---options-and-packages-matrix---updated.xls"},{"page":21,"startToken":6418,"endToken":6945,"text":"2 \n \nTariff revisions submitted as Attachment A.10 Materials on which I rely are cited where \nused. \n3. \nThis reply addresses the new explanations, interpretations, and implementation positions \nPJM offered after EKPC’s protest. I do not repeat the analysis in my original affidavit \nexcept where needed to test those new positions. Where PJM has not answered an opinion \nin my original affidavit, that opinion stands as submitted, and I do not restate it. \n4. \nPosture. PJM now states that the buyer-side Load Serving Entity (“LSE”) Credit Rate need \nnot be effective for the Reliability Backstop Procurement (“RBP”) to proceed, and consents \nto additional procedures on that rate. A material element of the buyer-side credit design \ntherefore remains unresolved. If the Commission addresses that methodology through \nadditional procedures, the schedule for those procedures should account for the fact that \nmeasurable RBP exposure develops well before the filed collateral posting date. \n5. \nPJM’s proposed schedule separates the development of measurable RBP exposure from \nthe date on which buyer-side collateral is required. The procurement results and the \n2029/2030 Base Residual Auction will make the first two Delivery Years of contract-for-\ndifferences exposure measurable in December 2026. Buyer-side collateral would not be \ndue until approximately April 2028. Deferring the posting date does not defer the need for \na governing methodology. \n6. \nI also note what such procedures would need to reach. PJM’s Answer does not respond to \nmost of the analysis in my original affidavit, and where it does respond, it characterizes \nthat affidavit as addressing the stakeholder process rather than the merits. PJM Answer at \n74 n.220. The paragraphs cited for that proposition, paragraphs 182 through 184, appear in \nthe section addressing the stakeholder record for the seller-side requirement and were not \noffered as merits opinions. The matters set out at paragraphs 52 and 53 below, and the \nopinions at 7(a) through 7(i) and Sections III and VI through XI of my original affidavit, \nremain unaddressed. \n7. \nPrincipal opinion. The central issue is methodological. PJM has not identified the residual \nloss that the buyer-side collateral requirement is intended to secure. Until that loss, the \nparties that bear it, the quantity and timing of the exposure, and the standards for \nrecalculating and releasing collateral are defined, neither $1.5 million per MW nor a \nsubstitute figure can be evaluated in relation to the exposure secured. PJM’s Answer and \nimplementation materials provide additional explanation, but they do not establish that \nrelationship. \n8. \nPJM’s new positions leave five issues unresolved: the loss being secured, the support for a \nuniform Credit Rate, the development of the buyer-side methodology, the controlling \nmegawatt quantity and posting date, and the coordination of RBP collateral with ordinary \nRPM credit treatment. My conclusions on each follow. \n9. \nDefault exposure. PJM states that “in no event would EKPC be allocated any cost \nresponsibility,” and that EKPC would not receive a reallocation following another LSE’s \ndefault because section 18.9(a) reallocates only among LSEs already paying RBP Charges. \n \n10 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (“July 31 Filing”)."},{"page":22,"startToken":6945,"endToken":7564,"text":"3 \n \nPJM Answer at 67, n.205. PJM separately states that its approach “balances the protection \nof Members against the effects of LSE default,” citing Operating Agreement section 15.2.2. \nPJM Answer at 84, n.252. \n10. PJM addressed the same question during the stakeholder process and answered it. Its April \n2026 design presentation states, under the heading “Default Allocation,” that “[i]f a default \noccurs as a result of a nonpayment of a RBP charge, that amount would be handled as a \ndefault allocation assessment under the existing OA Section 15.2.2,” and adds that “[t]his \nis consistent with the RPM market today.” April 17 Design Presentation at 47. If unpaid \nRBP obligations can reach PJM Members under section 15.2.2, the absence of a direct RBP \nallocation does not establish that EKPC has no RBP-related default exposure. If section \n18.9(a) instead confines an RBP default to the LSEs assigned RBP Charges, PJM should \nclarify their interrelationship and identify the role section 15.2.2 plays in the exposure the \ncollateral requirement is intended to secure. The residual loss and the population that bears \nit are predicates to sizing the requirement, and the record does not presently establish either. \n11. The requirement and credit migration. PJM defends a uniform Credit Rate that does not \nvary with an obligor’s credit condition, relying in part on a credit migration table \nextrapolated from S&P Global’s ten-year corporate rating transition study. PJM Answer at \n82, Table 2. That table reports ordinary-course rating migration across the general \npopulation of rated United States corporate issuers. PJM does not explain why a \ngeneralized migration matrix is appropriate to the particular population at issue, which is \nthe LSEs in the PJM region. PJM does not reconcile the table with its own measurement \nof that population, presented to stakeholders on March 4, 2026, which identified 105 LSEs, \nof which 24 were investment grade and 81 sub-investment grade, reported that 46 percent \nheld tangible net worth below $5 million and 30 percent below $1 million, and stated that \nthose figures indicate limited financial flexibility. And PJM provides no analysis of \nwhether the collateral requirement it proposes would itself constitute a liquidity stress event \nthat degrades the credit quality of the population the requirement is intended to secure. A \nmigration study of ordinary-course outcomes does not answer that question, because the \nobligation in question is not an ordinary-course event for the entities on which it falls. \n12. Peak Market Activity and the development of the Credit Rate. PJM now states that \nPeak Market Activity is unsuitable because it measures short-term, backward-looking \nexposure rather than the long-term forward exposure created by the RBP. PJM identified \nthat limitation to stakeholders on March 4, 2026, when it presented that its credit policy “is \nprimarily built for short-term settlement cycle and one-year capacity obligations” and that \nthe construct “introduces 15-year contractual durations, which current PJM credit rules \nwere not designed to mitigate.” PJM nevertheless proposed managing buyer-side credit \nthrough existing credit processes, including Peak Market Activity recalculation, from April \n2026 through its Stage 4 proposal of June 30, 2026. The $1.5 million per MW requirement \nfirst appears in the July 31 filing. \n13. EKPC does not contend, and I do not opine, that Peak Market Activity is the appropriate \ncredit mitigant for the RBP obligation. PJM has offered two explanations at different times. \nThrough June 30 it proposed that buyer-side credit be managed through existing credit \nprocesses, including Peak Market Activity recalculation, which secures a rolling period of \nbilled activity. On July 31 it filed a fixed $1.5 million per MW rate derived from \napproximately one-half of the gross fifteen-year payment stream. Neither explanation"},{"page":23,"startToken":7564,"endToken":8117,"text":"4 \n \nestablishes the relationship between the collateral required and the residual loss the \nrequirement is intended to secure. \n14. Quantity. PJM states that “no collateral would be required for RBP Resources [that] are \nnot in service for that Delivery Year.” PJM Answer at 78 n.234. Proposed section \n18.8(b)(i)(A) defines the quantity to which the Credit Rate applies as “the amount of RBP \nUCAP MW that receives a commitment through the Reliability Backstop Procurement \nminus each commitment of RBP UCAP MW that is rescinded pursuant to Tariff, \nAttachment DD, section 18.6(e).” PJM’s implementation presentation of September 14, \n2026 describes the same term at slide 9 as “the level of RBP UCAP MW for which an LSE \nis allocated cost responsibility submitted for the buyer by the EDC,” and states in the same \nslide that “Committed MW is equal to the generation that is coming online for that delivery \nyear.” Those are not the same quantity. The in-service interpretation also does not resolve \nthe separate relationship between committed megawatts and the Final RBP Target, to \nwhich section 18.8(b)(i)(B)(1) scales each LSE’s posting. \n15. Timing. PJM states that no LSE collateral is required until forty-five days before the first \nDelivery Year in which an RBP Resource is in service. On PJM’s schedule the Reliability \nBackstop Procurement results and the 2029/2030 Base Residual Auction results will both \nbe known in December 2026. At that point the contract-for-differences amount for the first \ntwo Delivery Years of a fifteen-year commitment is determined rather than forecast. On \nthe collared caps for both Delivery Years, derived at paragraphs 52 and 53 below, the \ndetermined exposure for those two years is approximately $163,217 per MW, or \napproximately $979 million on an adjusted target of approximately 6,000 MW. No \ncollateral is required against that amount until approximately April 17, 2028. PJM states \nthat the collateral requirement exists to protect load from the consequences of an LSE \ndefault. During the interval in which the near-term exposure becomes known and remains \noutstanding, the filed provisions require no security against it. \n16. Peak Market Activity, the contract-for-differences, and release. PJM proposes to \nremove RBP settlement from Peak Market Activity while treating the Reliability Pricing \nModel (“RPM”) component of the RBP payment as part of a separately collateralized long-\nterm obligation. That separation raises a further question as the commitment runs off. If a \nBase Residual Auction clears near the RBP commitment price, the incremental contract-\nfor-differences amount approaches zero and substantially the entire payment occurs \nthrough ordinary RPM settlement, which PJM secures through its existing credit processes. \nThe RBP obligation would then be excluded from Peak Market Activity while continuing \nto carry a separate collateral requirement, although the economic difference between it and \nan ordinary capacity obligation had narrowed to the contract-for-differences amount. PJM \nstates that the Credit Rate may decline as remaining exposure declines. The filed provisions \ndo not establish when that occurs, by how much, or when collateral is released. \n17. In my opinion, these matters go to the methodology of the credit requirement rather than \nto the selection of a replacement figure. If the Commission establishes additional \nprocedures on the buyer-side Credit Rate, the elements identified in Section VIII below \nshould be resolved before a rate is set."},{"page":24,"startToken":8117,"endToken":8680,"text":"5 \n \nII. THE EXPOSURE THE REQUIREMENT SECURES HAS NOT BEEN \nIDENTIFIED \n18. A collateral requirement is sized to a loss. I addressed the RBP default provisions and the \nresidual exposure under Operating Agreement section 15.2.2 at paragraphs 40, 152, 155 \nand 168 through 169 of my original affidavit. PJM did not respond to that analysis. I \naddress here only PJM’s own characterization of the default consequence, which appears \ntwice in the Answer and differs between the two. \n19. Responding to the Kentucky Attorney General, PJM states that “in no event would EKPC \nbe allocated any cost responsibility,” and that EKPC “would not be allocated any cost \nresponsibility in the event of default by another LSE on paying RBP Charges, as PJM’s \nproposal would require such reallocation of cost responsibility among other LSEs already \npaying RBP Charges.” PJM Answer at 67 n.205. \n20. Defending the magnitude of the requirement, PJM states that its approach “balances the \nprotection of Members against the effects of LSE default,” citing Operating Agreement \nsection 15.2.2. PJM Answer at 84 & n.252. \n21. PJM therefore describes the consequence of an LSE default in two different ways without \nexplaining how the two operate together. The first describes a defaulted RBP Charge as \nreallocated within the LSEs assigned RBP Charges. The second invokes the protection of \nMembers, and Operating Agreement section 15.2.2, in support of the requirement. The two \nare not necessarily alternatives; they may describe successive levels of a default waterfall, \nand PJM should clarify their interrelationship. Operating Agreement section 15.2.2 \nallocates defaults, which could arise should any LSE from whom PJM seeks to collect RBP \ndefault payments be unable to pay, to the total number of Members with only a certain few \nexceptions. EKPC would be among those “total number of Members.” Section 18.9(a) \nstates what happens to a defaulted RBP Charge in the first instance. It does not state what \nhappens if the reallocated amounts are not collected, and it does not disclaim Operating \nAgreement section 15.2.2. The preamble to section 18.8 provides that “[n]othing in this \nTariff, Attachment DD, section 18 supersedes the provisions of Tariff, Attachment Q.” \n22. What remains after section 18.9(a) operates determines the amount. A requirement sized \nto protect the RBP-paying population from each other is a different calculation from one \nsized to protect the general membership from a residual loss. PJM has not stated which it \nreflects, and the derivation in the Kelly Affidavit, approximately one-half of gross \ncontractual value, corresponds to neither. \n23. It also determines who is protected. Collateral is posted only by LSEs allocated cost \nresponsibility under section 18.3. If the exposure extends to Members generally, the entities \nposting and the entities protected are different populations. Section 18.9(a) compounds this \nby providing that a reallocated amount “may be offset by the RBP Collateral posted by the \ndefaulting LSE.” Whether collateral is applied before or after mutualization determines the \nresidual that reaches any further tier. See Coscia Protest Affidavit ¶ 155. \n24. Opinion. Until PJM states what remains unpaid after section 18.9(a) operates, which \nparties bear that residual loss, and whether collateral is applied before reallocation and any \nmutualization under Operating Agreement section 15.2.2, the amount required cannot be \nderived from the exposure it is said to secure."},{"page":25,"startToken":8680,"endToken":9228,"text":"6 \n \nIII. PJM’S CREDIT MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM \nRATE \n25. PJM defends a Credit Rate that does not vary with an obligor’s credit condition by \nreference to credit migration. It extrapolated S&P Global’s ten-year corporate rating \ntransition study to a fifteen-year period and presents the result as Table 2 of its Answer. \nPJM Answer at 82. PJM reasons that under “an alternative, specific-LSE-driven credit \napproach … such declining creditworthiness would require PJM to request more and more \ncollateral from such entities in order to compensate for the increasing default risk,” and \nthat its methodology “is based on the committed obligation itself and avoids having the \nadequacy of the credit protection depend upon long-range predictions about individual \nLSE’s financials.” PJM Answer at 81, 83. \n26. Table 2 reports ordinary-course rating migration across the general population of rated \nUnited States corporate issuers. It does not measure what happens to an obligor’s credit \ncondition when the party imposing the requirement requires collateral comparable to or \nexceeding that obligor’s balance sheet. A requirement of that size can consume liquidity, \nencumber assets, absorb credit-facility capacity, or impose a recurring carrying cost. Those \neffects cannot simply be assumed to be independent of the future credit condition the \nmigration analysis is used to address. \n27. The illustration in my original affidavit gives the magnitude. On PJM’s figures, the \nNOVEC zone carries an initial allocation of 1,302.6 RBP UCAP MW and a collateral \nobligation of approximately $1.954 billion. Against the cooperative’s certified FY2025 \nreport, that is approximately 114 percent of total assets of $1.716 billion, approximately \ntwice total margins and equities of $920 million, and roughly eight times cash and \ntemporary investments. The carrying cost at 100 basis points is approximately $19.5 \nmillion, or approximately 94 percent of the cooperative’s patronage capital and operating \nmargins for the year. That cooperative is investment grade and is among the 24 LSEs PJM \nclassified as investment grade on March 4, 2026, when it also reported that 81 of 105 LSEs \nwere sub-investment grade, that 46 percent held tangible net worth below $5 million and \n30 percent below $1 million, and that those figures indicate “limited financial flexibility.” \nMarch 4 Credit Overview at 7. \n28. PJM applied a different approach to sellers. The seller requirement is twenty percent of the \ncommitment price, the rate at which a non-performing seller is charged under section \n18.6(d), applied over three years, discounted at 9.5 percent, and reduced as the commitment \nruns off “while taking into account the credit quality of the Market Participant.” April 17 \nDesign Presentation at 43-45. The buyer requirement is approximately one-half of the gross \nfifteen-year contractual value, undiscounted, without the seller-side methodology’s express \ntenor-sensitive calculation or credit-quality adjustment. \n29. On the same megawatt at the same $555.00/MW-day price, the seller posts $121,545 and \nthe buyer posts $1,500,000. PJM cites the difficulty of predicting buyer credit quality over \nfifteen years as its reason for a uniform buyer rate. A requirement that discounts and \ndeclines with remaining tenor, as the seller requirement does, does not require that \nprediction. \n30. Opinion. Table 2 establishes that credit quality varies over a fifteen-year horizon. That \nsupports measuring and adjusting the requirement over that horizon. It does not support"},{"page":26,"startToken":9228,"endToken":9803,"text":"7 \n \nfixing a single, uniform amount at the outset, applied without regard to the obligor, in a \nmagnitude large enough to affect the liquidity and financial condition of the obligors the \nrequirement is intended to secure. \nIV. THE FILED REQUIREMENT IS NOT THE BUYER-SIDE DESIGN PJM \nPRESENTED TO STAKEHOLDERS \n31. PJM’s Answer states that Peak Market Activity is not an adequate credit tool for RBP \nCharges, describing it as a backward-looking measure of short-term transactional exposure \nthat does not prospectively collateralize the RPM component of the obligation. \n32. PJM knew the RBP was long-dated from the outset and demonstrated an ability to model \nthe resulting exposure. On March 4, 2026, it presented that its credit policy “is primarily \nbuilt for short-term settlement cycle and one-year capacity obligations” and that the \nconstruct “introduces 15-year contractual durations, which current PJM credit rules were \nnot designed to mitigate.” March 4 Credit Overview at 3. In the same presentation it \nmodeled the procurement as a fixed-for-float swap and produced a potential future \nexposure (“PFE”) profile across the fifteen-year term. Id. at 12. \n33. PJM nevertheless proposed to secure the buyer-side obligation through existing credit \nprocesses. In April it stated that “[c]redit and collateral requirements for EDCs are expected \nto be managed by the current credit processes, which include but are not limited to credit \nevaluation, PMA and use of other mitigation tools, such as posting of credit support and/or \nUCRs.” April 17 Design Presentation at 46. In June it stated the same for LSEs: “Upon \nnotification by the Load Serving Entity (LSE) of the known changes to its load, credit, and \ncollateral requirements for LSEs are expected to be managed by the current credit \nprocesses. These processes include, but are not limited to, credit evaluation, PMA \nrecalculation and use of other mitigation tools, such as posting of credit support and/or \nUCRs.” June Design Presentation at 35. PJM carried that position into its Stage 4 proposal \nof June 30, 2026 and its entry at design component 22. June 30 Options and Packages \nMatrix. Over the same period, PJM recorded stakeholder feedback on the size of the \nrequirement. Its status update of May 5, 2026 summarizes the Stage 1 meeting feedback \nunder the heading “Credit” as “[c]ollateral requirements may be too high – are they \ncompetitive?”, and under the heading “Role of EDC” as “EDCs don’t want to wear the risk \n– this may result in targets of 0.” May 5 Status Update at 2. PJM applied to sellers the term-\nsensitive methodology described at paragraph 28 above. \n34. An alternative buyer-side design was also before PJM. At the same design component of \nthe Package Matrix, the package proposed by the Joint Electric Distribution Companies \nand the Data Center Coalition provided that “[p]rior to the procurement, the LSE-Large \nLoad registry will indicate the LSEs who must hold collateral and for what amount of \nMW,” that “[i]f an LSE-Large Load cannot post collateral, the load is not procured for \nthrough the backstop,” and that the collateral held “must ensure that any emerging buyer \ndefault exposure is recognized early, funded continuously, and contained entirely within \nthe buyer over time.” That package was the only one of the thirteen voted at the close of \nStage 4 to receive greater than two-thirds sector-weighted member support. It identified \nthe obligated entity and its megawatt quantity before the procurement, conditioned the \nprocurement on the ability to post, and measured exposure as it emerged."},{"page":27,"startToken":9803,"endToken":10348,"text":"8 \n \n35. The July 31 filing established a separate RBP Credit Requirement at a Credit Rate of $1.5 \nmillion per MW, a figure that appears in none of the stakeholder materials I have reviewed. \nPJM states that the Board “adopted various concepts from the Coalition RBP Proposal that \nreceived a sector-weighted majority of stakeholder support,” and identifies the “credit \nrequirement for Load Serving Entities” as among those with “roots in the Coalition RBP \nProposal.” July 31 Filing at 22. The filed construct incorporates the assignment of the \nobligation to LSEs. It does not incorporate the registry, the identification of the obligated \nentity before the procurement, the requirement to post before the obligation attaches, or the \ncontinuous funding of exposure as it emerges. \n36. Opinion. PJM is not obliged to adopt a stakeholder proposal, and it may reasonably have \nconcluded that Peak Market Activity alone was insufficient for a fifteen-year obligation. \nWhat the Answer supplies is an explanation of why PJM now considers Peak Market \nActivity inadequate. What it does not supply is the analytical bridge from the approaches \nPJM had before it, its own March exposure modeling, the existing credit processes it \nproposed through June 30, and the Coalition’s exposure-based design, to a rate initially \napproximating one-half of the gross fifteen-year payment stream. \nV. \nTHE QUANTITY ON WHICH COLLATERAL IS REQUIRED IS NOT DEFINED \n37. An LSE cannot calculate its posting unless the tariff identifies the controlling megawatt \nquantity. Proposed Tariff, Attachment DD, section 18.8(b)(i)(A) requires collateral equal \nto the RBP Credit Rate multiplied by “RBP UCAP MW committed.” The amount of the \nrequirement therefore depends entirely on that quantity. PJM’s Answer and its \nimplementation materials leave three questions about it unresolved: whether the megawatts \nmust be in service; whether an individual LSE’s posting follows the megawatts its Electric \nDistributor assigns or is scaled to the Final RBP Target; and what quantity applies, if any, \nwhere the Electric Distributor reports nothing. \nA. Whether the megawatts must be in service \n38. PJM’s Answer states that “no collateral would be required for RBP Resources [that] are \nnot in service for that Delivery Year.” PJM Answer at 78 n.234. \n39. That in-service limitation does not appear in section 18.8(b)(i)(A). That provision defines \nthe quantity as “the amount of RBP UCAP MW that receives a commitment through the \nReliability Backstop Procurement minus each commitment of RBP UCAP MW that is \nrescinded pursuant to Tariff, Attachment DD, section 18.6(e).” Commitments received, \nless rescissions. There is no in-service condition, and PJM has proposed no revision to that \nprovision. \n40. Rescission under section 18.6(e) occurs only “where RBP UCAP MW fail to come online \nfor three Delivery Years beginning with the first Delivery Year in which the RBP Resource \nwas committed.” A resource that has not achieved commercial operation therefore remains \nwithin the quantity for up to three Delivery Years. PJM’s transmittal describes the same \nmechanic and identifies rescission as the operative event: the input “will change as \ncommitted resources fail to follow through on their commitment and do not achieve \ncommercial operation,” and it is the rescinded commitment that “is subtracted from the \ninput used to determine the uniform RBP credit requirement.” July 31 Filing at 116."},{"page":28,"startToken":10348,"endToken":10942,"text":"9 \n \n41. The September 14 Presentation states the Answer’s position on one slide and applies the \ntariff definition on another. Slide 9 defines the quantity as “the level of RBP UCAP MW \nfor which an LSE is allocated cost responsibility submitted for the buyer by the EDC,” and \nadds in a note that “Committed MW is equal to the generation that is coming online for \nthat delivery year.” \n42. Example #4 at slide 57 of the September 14 Presentation does the opposite. It addresses a \nunit that “does not come online for Delivery Year.” The example carries Committed MW \n(UCAP) of 50 throughout, assesses the RBP Shortfall Charge on all 50 committed \nmegawatts under section 18.6(d), and computes RBP Credits on Daily Owned MW of zero. \nThe commitment remains at 50 megawatts and settlement occurs on that quantity even \nthough the resource is not in service. That is the filed definition, applied. \n43. The two formulas use different quantities. RBP Credits, and therefore the RBP Charges \nassessed to load, are computed on Daily Owned MW, which is why the charge is zero in \nExample #4. The collateral requirement in section 18.8(b)(i)(A) is computed on RBP \nUCAP MW committed, which in the same example remains 50. The absence of a charge \nin a Delivery Year is a result of the credit formula. It does not change the quantity to which \nthe Credit Rate applies. \nB. Whether the posting follows assigned megawatts or the Final RBP Target \n44. Section 18.8(b)(i)(A) sets the cumulative RBP credit requirement for all LSEs as the Credit \nRate multiplied by committed megawatts. Section 18.8(b)(i)(B)(1) sets each individual \nLSE’s posting as $1.5 million multiplied by the RBP Obligation MW its Electric \nDistributor submits, “scaled, as necessary, in the event that the RBP Obligation MW values \nuploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the \nzone/area.” \n45. Those provisions use different quantities, and PJM states the procurement may clear short \nof the Final RBP Target. Where it does, committed megawatts are fewer than the Target. \nThe individual postings scaled to the Target under (B)(1) would then sum to more than the \ncumulative requirement calculated on committed megawatts under (A). Because the Credit \nRate is $1.5 million per megawatt, each 100 megawatts of difference between the two \nquantities changes the aggregate amount posted by $150 million. \n46. PJM has identified each quantity as governing. Footnote 234 states that the amount “would \nbe based on the RBP UCAP MW committed for that Delivery Year.” PJM’s written \nresponse of August 14, 2026 stated that the Final RBP Target governs. \nC. What applies where the Electric Distributor reports nothing \n47. Section 18.8(b)(i)(B)(2) provides that where no RBP Obligations are reported for an \nElectric Distributor zone or area, LSEs serving load there “may be required to post” \ncollateral calculated on “the [LSE’s] pro-rata share of the Daily Unforced Capacity \nObligation for the zone/area as determined in RAA, Schedule 8.” The September 14 \nPresentation states that measure at slide 70, while a footnote to the example at slide 69 \ndescribes the same fallback as a Peak Load Contribution allocation. \n48. The provision is permissive, and PJM confirmed in writing on September 15, 2026 that it \nadmits more than one outcome. An LSE may be required to post at the Credit Rate, may \npost at the Credit Rate and additionally be assessed under the Unreasonable Credit Risk"},{"page":29,"startToken":10942,"endToken":11530,"text":"10 \n \nprovisions of Attachment Q, Section II, or may not be required to post at the Credit Rate \nbut be subject to an unreasonable credit risk assessment. The provision states that an LSE \n“may be required to post.” It does not state that a Credit Rate posting is required in every \ncase in which no RBP Obligations are reported. \n49. The quantity also changes basis. Under (B)(1) an LSE posts on megawatts attributed to it \nthrough the allocation process. Under (B)(2) it posts on its share of total load. An entity \nwith no RBP Obligation under section 18.3 has no requirement under (B)(1) and a \nrequirement measured by its entire load under (B)(2). \n50. Subsection (B)(2) is also difficult to square with PJM’s defense of the uniform rate. PJM \nstates that its methodology “is based on the committed obligation itself and avoids having \nthe adequacy of the credit protection depend upon long-range predictions about individual \nLSE’s financials.” PJM Answer at 82. The Unreasonable Credit Risk provisions of \nAttachment Q, Section II are an individualized assessment of a participant’s financial \ncondition. Section 18.8(b)(i)(B)(2) routes directly into them, and PJM has confirmed that \nan assessment may be made in place of, or in addition to, a Credit Rate posting. PJM has \ntherefore built individualized credit evaluation into the construct. It applies where an \nElectric Distributor fails to report, and not where the Electric Distributor reports. \nD. Timing \n51. Section 18.3(b)(iii) requires the initial allocation to be reported no later than sixty days \nbefore the Delivery Year, and collateral is due prior to forty-five days before. An LSE \nwould have approximately fifteen days between learning which subsection applies to it, \nand on what quantity, and funding the requirement. \n52. The timing differs from the forward-exposure rationale. PJM relies on the long-dated \ncharacter of the obligation to distinguish it from Peak Market Activity, while requiring no \nsecurity until shortly before the first applicable Delivery Year. The near-term exposure is \ndetermined well before then. \n53. Both of the first two Delivery Years are subject to the price collar PJM extended through \n2029/2030. The collar is expressed in installed capacity terms and converted to unforced \ncapacity by the Effective Load Carrying Capability rating of the reference resource. The \n2028/2029 Base Residual Auction cleared at the collared cap of $325.00/MW-day UCAP \nat a Gas CT Dual Fuel rating of 79 percent, and the 2027/2028 auction cleared at its collared \ncap of $333.44/MW-day at a rating of 77 percent. Both imply the same basis of \n$256.75/MW-day ICAP. PJM endorsed a Gas CT Dual Fuel rating of 76 percent for \n2029/2030 on August 19, 2026, which places the collared cap for that Delivery Year at \n$337.83/MW-day UCAP and the floor at $181.91/MW-day UCAP. \n54. At the $555.00/MW-day maximum willingness to pay, the differential is therefore \n$230.00/MW-day for 2028/2029 and $217.17/MW-day for 2029/2030, or $83,950 and \n$79,267 per MW respectively. The two-year total is $163,217 per MW, which on an \nadjusted target of approximately 6,000 MW is approximately $979 million, and \napproximately $1.115 billion on the full Initial RBP Target of 6,831.3 MW. These figures \nreplace the $333.44 proxy I used at paragraph 92 of my original affidavit, the 2029/2030 \nparameters not having been endorsed when that affidavit was prepared. The amount is"},{"page":30,"startToken":11530,"endToken":11992,"text":"11 \n \ndetermined once the 2029/2030 auction clears in December 2026, and no collateral is \nrequired against it until approximately April 17, 2028. \n55. Opinion. An LSE cannot determine from the filed rate the quantity on which it must post. \nThe tariff, the Answer, and the implementation presentation give different answers to \nwhether the megawatts must be in service, and PJM’s own settlement example applies the \ntariff definition rather than the Answer’s. PJM has identified both committed megawatts \nand the Final RBP Target as governing an individual posting. And where an Electric \nDistributor reports nothing, whether an entity posts at all, on what quantity, and whether it \nis additionally assessed for unreasonable credit risk are matters the filed provisions leave \nto discretion. If PJM intends collateral to follow in-service megawatts, or the Final RBP \nTarget, those are changes to section 18.8(b)(i) and should be made in the tariff. \nVI. THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY \nRPM ACTIVITY \nA. Coordination with Attachment Q \n56. PJM proposes to delete the sentence providing that settlement of cleared RBP positions \n“may be included, as appropriate, in Peak Market Activity,” on the basis that it could cause \nconfusion that RBP Charges may be captured in that calculation. \n57. Removal of the clause does not establish how an invoiced RBP billing line item is excluded \nfrom the Peak Market Activity calculation in Attachment Q, section VII.A, and PJM has \nproposed no conforming revision to Attachment Q. Three provisions are unaffected by the \ndeletion and bear on the coordination question. Nothing in section 18 supersedes \nAttachment Q. The RBP requirements are separate from and additional to credit \nrequirements arising under Attachment Q. And under sections 18.8(b)(i)(B)(1) and (B)(2), \nPJM may evaluate an LSE for unreasonable credit risk under Attachment Q, Section II and \nrequire additional RBP Collateral, which as set out at paragraph 47 above may be done in \naddition to, or in place of, a Credit Rate posting. \n58. PJM explains the separate requirement as securing the forward RPM component of the \nobligation together with the contract-for-differences amount, on the ground that Peak \nMarket Activity does not prospectively collateralize the RPM component over the term. \nThe RBP settles economically through RPM and a contract-for-differences: load pays the \nRPM clearing price through ordinary capacity billing and pays or receives the difference \nthrough the new billing line item. \n59. To examine how that explanation operates, I apply it to a period in which three Delivery \nYears remain, at an RBP commitment price of $555.00/MW-day on 6,000 MW. I take a \nBase Residual Auction clearing price of $554.00/MW-day, at which the contract-for-\ndifferences is nearly extinguished. The result is set out in Table 1."},{"page":31,"startToken":11992,"endToken":12471,"text":"12 \n \nTable 1. Illustrative RBP exposure and collateral, three Delivery Years remaining \nMeasure \nAmount \nContract-for-differences rate \n$1.00/MW-day \nAnnual contract-for-differences amount \n$2.19 million \nRemaining contract-for-differences obligation $6.57 million \nFour weeks of RPM payments \n$93.1 million \nRemaining gross payment stream at $555.00 \n$3.646 billion \nCollateral at $1.5 million per MW \n$9.0 billion \n  \n60. The discontinuity is in the treatment of the RPM component. At an RPM clearing price of \n$554.00, an LSE carrying an ordinary capacity obligation of that size would be subject to \nPJM’s ordinary Attachment Q credit processes. The same entity carrying the same RPM \nobligation, plus a contract-for-differences of $1.00/MW-day, has that RPM stream treated \nas part of a multi-year forward obligation supporting a separate collateral requirement. An \nincremental obligation of $2.19 million a year changes the credit treatment of \napproximately $1.2 billion a year of ordinary RPM payments. \n61. Opinion. PJM has not explained why the existence of an RBP commitment changes the \ncredit treatment of the forward RPM payment stream, or how that separate treatment should \nconverge with ordinary RPM credit treatment as the contract-for-differences amount and \nthe remaining term decline. \nVII. PJM’S ILLUSTRATION OF THE REDUCTION PROVISION \n62. I addressed the absence of a defined reduction and release standard at opinion 7(f) and \nparagraphs 47 and 155 of my original affidavit, including the comparison with Attachment \nQ, Section V.A and Section VI.B.3 and with the seller-side release in section 18.8(a). I do \nnot repeat that analysis. PJM has since explained how the provision is intended to operate, \nand I address that explanation. \n63. PJM states in its Answer that the Credit Rate can decline where previously required \ncollateral exceeds the remaining expected payment exposure, and acknowledges that use \nof the actual weighted-average RBP price may be appropriate. PJM Answer at 80 & n.240. \n64. The September 14 Presentation illustrates the result. Slide 69 sets out a roll-off schedule \nfor a 100 MW RBP Obligation at the $1.5 million Credit Rate, assuming a $555.00/MW-\nday commitment price, an annual payment obligation of $20,257,500, and no change to \ncommitted megawatts over the fifteen-year term. Collateral of $150,000,000 is held \nwithout change for the first eight Delivery Years. The first reduction occurs in 2036/2037, \nthe ninth Delivery Year, and PJM explains it in a note: “Credit requirement/collateral is \nreduced due to payment obligation is smaller than collateral held.” The requirement then \ntracks the remaining gross payment obligation to $20,257,500 in the final year. \n65. The requirement does not decline for more than half the term. Over the first eight Delivery \nYears the remaining gross payment obligation falls from $303,862,500 to $162,060,000, a \nreduction of approximately forty-seven percent, while the collateral held remains at"},{"page":32,"startToken":12471,"endToken":13031,"text":"13 \n \n$150,000,000. PJM has separately modeled exposure on this construct. In the March 4 \nCredit Overview at 12 it modeled the procurement as a fixed-for-float swap and produced \na potential future exposure profile that begins at zero, rises through the early Delivery \nYears, reaches a maximum within roughly the first third of the term, and declines to zero \nat expiry, stating that “[t]he value uncertainty goes higher deeper into the future, while \nquantity exposure decreases as time goes by. This makes PFE peaks at 1/3 of life.” Potential \nfuture exposure and remaining gross payments are different measures, and I do not suggest \nthe schedule should replicate the March profile. What PJM has not explained is why the \nbuyer-side requirement follows remaining gross payments rather than a profile sensitive to \nthe exposure it is said to secure, when PJM has modeled that exposure itself. \n66. The reduction, when it occurs, tracks the remaining gross payment obligation rather than \nthe exposure. The schedule is built from the $555.00/MW-day commitment price applied \nto full committed megawatts; the annual figure of $20,257,500 is that price multiplied by \n365 days and 100 MW. It contains no RPM clearing price and therefore no contract-for-\ndifferences input. \n67. The schedule is an illustration rather than a rule. It appears in a presentation, it assumes \ncommitted megawatts do not change over the term, and nothing in section 18.8(b)(i)(A) \nrequires PJM to follow it or establishes its frequency or inputs. \n68. Opinion. PJM’s illustration shows collateral held flat for eight of fifteen Delivery Years \nand reducing thereafter on the remaining gross payment obligation, on an assumption the \ntariff does not require, under a provision that is permissive throughout. The illustrated \nrequirement therefore does not respond to the contract-for-differences amount or observed \nRPM clearing prices, and it does not decline with remaining tenor during the first eight \nDelivery Years. \nVIII. RECOMMENDATIONS FOR ADDITIONAL PROCEEDINGS \n69. PJM has consented to the Commission resolving the buyer-side Credit Rate through \nadditional procedures, and states that the buyer-side rules need not be effective for the \nReliability Backstop Procurement to be conducted. The matters set out below should be \nresolved on a schedule that reflects when the underlying exposure becomes measurable, \nwhich, as set out in paragraph 5, is well before the filed posting date. \n70. In my opinion, any additional procedures should define the exposure the requirement is \nintended to secure and the quantity and timing of that exposure before a replacement Credit \nRate is selected. That includes the relationship among the RPM component of the payment, \nthe contract-for-differences amount created by the RBP, the reallocation provided by \nsection 18.9(a), and any residual exposure under Operating Agreement section 15.2.2. It \nalso requires a defined meaning of “RBP UCAP MW committed” and its relationship to \nmegawatts in service, megawatts allocated to an LSE, RBP Obligation MW reported by an \nElectric Distributor, and the Final RBP Target. The procedures should also establish when \nthe resulting exposure arises and when collateral is required in relation to it. \n71. The methodology should then provide objective standards for recalculating and releasing \ncollateral as the relevant conditions change, including the RBP commitment price, \nobserved RPM clearing prices and resulting contract-for-differences amounts, remaining \ntenor, committed quantity, and participant credit condition. It should also establish the"},{"page":33,"startToken":13031,"endToken":13169,"text":"14 \n \norder in which collateral, the reallocation under section 18.9(a), and any mutualization \nunder Operating Agreement section 15.2.2 apply, so that the residual loss the collateral is \nintended to secure can be identified. \n72. PJM’s Answer and implementation materials supply explanations that were not available \nwhen I submitted my original affidavit. They do not establish the relationship between the \ncollateral required and the exposure secured. \n73. The question presented by the buyer-side credit requirement is therefore not whether $1.5 \nmillion per MW is too high or too low. It is whether the amount, the quantity, the timing, \nthe recalculation, the release, and the default treatment of collateral bear a defined \nrelationship to the exposure the requirement is intended to secure. On the present record \nthey do not. \n74. This concludes my reply affidavit."},{"page":34,"startToken":13169,"endToken":13204,"text":"VERIFICATION OF AFFIDAVIT\nPursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the \nforegoing Affidavit is true and correct.\nExecuted September 18, 2026.\nBy: _____________________________\n       Carl F. Coscia"},{"page":35,"startToken":13204,"endToken":13254,"text":"Certificate of Service \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC this 18th day of September, 2026. \n \n/s/ Allison E. S. Salvia  \nAllison E. S. Salvia"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":558,"startToken":0,"endToken":394},{"p":2,"at":558,"title":"I. MOTION FOR LEAVE TO FILE LIMITED ANSWER","method":"printed heading","endPage":3,"endAt":709,"startToken":394,"endToken":874},{"p":3,"at":709,"title":"II. BACKGROUND AND SUMMARY","method":"printed heading","endPage":5,"endAt":114,"startToken":874,"endToken":1452},{"p":5,"at":114,"title":"III. LIMITED ANSWER","method":"printed heading","endPage":5,"endAt":136,"startToken":1452,"endToken":1455},{"p":5,"at":136,"title":"A. PJM Has Not Carried Its Affirmative Burden Under FPA Section 205.","method":"printed heading","endPage":6,"endAt":368,"startToken":1455,"endToken":1834},{"p":6,"at":368,"title":"B. PJM Failed to Address EKPC’s Cost Causation Arguments.","method":"printed heading","endPage":9,"endAt":819,"startToken":1834,"endToken":3056},{"p":9,"at":819,"title":"C. EKPC’s Protest Is Consistent with the Ratepayer Protection Pledge.","method":"printed heading","endPage":11,"endAt":212,"startToken":3056,"endToken":3673},{"p":11,"at":212,"title":"D. PJM Does Not Justify Disparate Treatment of FRR Entities and RPM Self","method":"printed heading","endPage":12,"endAt":244,"startToken":3673,"endToken":4029},{"p":12,"at":244,"title":"E. PJM’s Proposed Credit-Rate Severance Does Not Cure the RBP’s Credit","method":"printed heading","endPage":16,"endAt":530,"startToken":4029,"endToken":5346},{"p":16,"at":530,"title":"F. The Commission Should Reject the Proposed Default Allocation.","method":"printed heading","endPage":16,"endAt":1370,"startToken":5346,"endToken":5473},{"p":16,"at":1370,"title":"G. PJM’s Portfolio-Benefit Theory Underscores the Mismatch.","method":"printed heading","endPage":17,"endAt":460,"startToken":5473,"endToken":5626},{"p":17,"at":460,"title":"IV. CONCLUSION","method":"printed heading","endPage":20,"endAt":161,"startToken":5626,"endToken":5969},{"p":20,"at":161,"title":"I. PURPOSE, POSTURE, AND PRINCIPAL CONCLUSIONS","method":"printed heading","endPage":24,"endAt":5,"startToken":5969,"endToken":8118},{"p":24,"at":5,"title":"II. THE EXPOSURE THE REQUIREMENT SECURES HAS NOT BEEN","method":"printed heading","endPage":25,"endAt":5,"startToken":8118,"endToken":8681},{"p":25,"at":5,"title":"III. PJM’S CREDIT MIGRATION ANALYSIS DOES NOT SUPPORT A UNIFORM","method":"printed heading","endPage":26,"endAt":225,"startToken":8681,"endToken":9264},{"p":26,"at":225,"title":"IV. THE FILED REQUIREMENT IS NOT THE BUYER-SIDE DESIGN PJM","method":"printed heading","endPage":27,"endAt":1384,"startToken":9264,"endToken":10017},{"p":27,"at":1384,"title":"V. THE QUANTITY ON WHICH COLLATERAL IS REQUIRED IS NOT DEFINED","method":"printed heading","endPage":27,"endAt":2121,"startToken":10017,"endToken":10129},{"p":27,"at":2121,"title":"A. Whether the megawatts must be in service","method":"printed heading","endPage":28,"endAt":1364,"startToken":10129,"endToken":10587},{"p":28,"at":1364,"title":"B. Whether the posting follows assigned megawatts or the Final RBP Target","method":"printed heading","endPage":28,"endAt":2655,"startToken":10587,"endToken":10802},{"p":28,"at":2655,"title":"C. What applies where the Electric Distributor reports nothing","method":"printed heading","endPage":29,"endAt":1459,"startToken":10802,"endToken":11186},{"p":29,"at":1459,"title":"D. Timing","method":"printed heading","endPage":30,"endAt":953,"startToken":11186,"endToken":11681},{"p":30,"at":953,"title":"VI. THE EXPOSURE THE REQUIREMENT SECURES IS LARGELY ORDINARY","method":"printed heading","endPage":30,"endAt":1029,"startToken":11681,"endToken":11692},{"p":30,"at":1029,"title":"A. Coordination with Attachment Q","method":"printed heading","endPage":31,"endAt":1309,"startToken":11692,"endToken":12190},{"p":31,"at":1309,"title":"VII. PJM’S ILLUSTRATION OF THE REDUCTION PROVISION","method":"printed heading","endPage":32,"endAt":2001,"startToken":12190,"endToken":12792},{"p":32,"at":2001,"title":"VIII. RECOMMENDATIONS FOR ADDITIONAL PROCEEDINGS","method":"printed heading","endPage":35,"endAt":0,"startToken":12792,"endToken":13204},{"p":35,"at":0,"title":"Certificate of Service","method":"printed heading","endPage":35,"endAt":305,"startToken":13204,"endToken":13254}]}