{"document":{"slug":"rec-20260918-5365","title":"Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the protests and comments of Buckeye Power, Inc., et al","issued":"2026-09-18","accession":"20260918-5365","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"New Jersey Board of Public Utilities","kind":"protest","file":"sources/filings/text/20260918-5365_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5365","tier":"record","sha256":"3fc0151882c04c04011924129674b6ae6ec40596b0c90fedd656ec601cd9a87b","pages":8,"tokens":1802,"emptyPages":[],"textThemes":["adequacy","flex","registry"]},"pages":[{"page":1,"startToken":0,"endToken":263,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, LLC  \n  \n) \n \n   \n                   \nDocket No. ER26-3515-000\n                                         \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nTHE NEW JERSEY BOARD OF PUBLIC UTILITIES \n \nOn August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) proposed revisions to the \nReliability Assurance Agreement Among Load Serving Entities (“RAA”) and the PJM Open \nAccess Transmission Tariff (“Tariff”) to establish Interim Resource Adequacy Service (“IRAS”).1  \nOn September 3, 2026, the New Jersey Board of Public Utilities (“Board”) submitted its \nSupportive Comments and Limited Protest of PJM’s Proposal.2   \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission” or “FERC”) Rules of Practice and Procedure,3 the Board respectfully moves for \nleave to answer and submits this Answer to the protests and comments of Buckeye Power, Inc. \n(“Buckeye Power”),4 Southern Maryland Electric Cooperative, Inc. (“SMECO”),5 East Kentucky \n \n1 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large \nLoad Registry to Address System Reliability, Docket No. ER26-3515 (Aug. 13, 2026) (“PJM IRAS \nProposal” or “Proposal”). \n2 PJM Interconnection, L.L.C., Supportive Comments and Limited Protest of the New Jersey Board of \nPublic Utilities, Docket No. ER26-3515 (Sept. 3, 2026) (“NJ BPU Comments”). \n3 18 C.F.R. §§ 385.212, 385.213 (2020). \n4 PJM Interconnection, L.L.C., Limited Comments of Buckeye Power, Inc., Docket No. ER26-3515 (Sept. \n3, 2026) (“Buckeye Power Comments”). \n5 PJM Interconnection, L.L.C., Comments and Limited Protest of Southern Maryland Electric \nCooperative, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“SMECO Comments”)."},{"page":2,"startToken":263,"endToken":615,"text":"2 \n \nPower Cooperative, Inc. (EKPC”),6 Voltus,7 Equinix Inc. (“Equinix”),8 Tesla, Inc. (“Tesla”),9 the \nChief Energy Officer for the Governor of Virginia,10 and Corporate Energy Buyers Association \n(“CEBA”).11  The Board submits this Answer to provide additional information and context that \nwill assist the Commission in its decision-making process.  \nI. \nMOTION FOR LEAVE TO ANSWER \nWhile Rule 213(a)(2) generally prohibits answers to protests and comments, good cause \njustifies the Commission’s granting this motion and accepting this answer because it provides \nuseful and relevant information that will assist the Commission in its decision-making process. \nII. \nANSWER \ni. \nIRAS Should Not Exceed Amount of New Large Load Demand in Real Time \nProtests and comments submitted by Buckeye Power, SMECO, and EKPC raise issue with \na specific component in PJM’s IRAS Proposal.  In its Proposal, PJM proposes to issue load \nreductions to electric distribution companies (“EDCs”) in an amount “up to, and capped at, the \npre-Delivery Year IRAS obligations they were assigned” when conducting an IRAS Action.12  \n \n6 PJM Interconnection, L.L.C., Limited Protest of East Kentucky Power Cooperative, Inc., Docket No. \nER26-3515 (Sept. 3, 2026) (“EKPC Protest”).  \n7 PJM Interconnection, L.L.C., Comments of Voltus, Docket No. ER26-3515 (Sept. 3, 2026) (“Voltus \nComments”). \n8 PJM Interconnection, L.L.C., Protest, Request for Clarification and Comments of Equinix Inc. on the \nProposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large \nLoad Registry to Adress System Reliability, Docket No. ER26-3515 (Sept. 3, 2026) (“Equinix \nComments”). \n9 PJM Interconnection, L.L.C., Comments of Tesla, Inc., Docket No. ER26-3515 (Sept. 3, 2026) (“Tesla \nComments”). \n10 PJM Interconnection, L.L.C., Comments of the Chief Energy Officer for the Governor of Virginia, \nDocket No. ER26-3515 (Sept. 3, 2026) (“Chief Energy Officer for the Governor of Virginia Comments”). \n11 PJM Interconnection, L.L.C., Motion to Intervene and Protest of Corporate Energy Buyers Association \n(“CEBA”), Docket No. ER26-3515 (Sept. 3, 2026) (“CEBA Protest”). \n12 PJM IRAS Proposal Attachment C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, \nL.L.C. at 42."},{"page":3,"startToken":615,"endToken":967,"text":"3 \n \nThese obligations are pre-determined and correspond to the peak load reported by the New Large \nLoad in PJM’s proposed Large Load Registry.  However, Buckeye Power, SMECO, and EKPC \nidentify an important concern, which is that this pre-determined amount may not match the actual \nNew Large Load demand being used in real-time.13  SMECO’s Comments highlight that this is not \nmerely a hypothetical scenario, as IRAS amounts are set at a pre-Delivery Year MW quantity, yet \nan EDC’s assigned New Large Loads may not be yet energized, or may have only just begun a \nramp or testing period that is below its expected draw when PJM issues an IRAS Action.14  If this \nis the case and PJM directs an amount of IRAS that corresponds to the peak load reported by the \nNew Large Load, and this obligation is higher than the real-time demand of large loads in that \nzone, it is unclear whether EDCs will be required to reduce other customers in addition to New \nLarge Load customers in order to meet the required IRAS MW amount.  Buckeye Power, SMECO, \nand EKPC properly point out that this is clearly not PJM’s intent,15 with Buckeye Power’s \nComments highlighting that “PJM’s goal of ‘prevent[ing] Manual Load Dump’ properly \nrecognizes that keeping existing customers, particularly residential loads, online is the primary \ngoal in the event of a grid emergency.”16  Ultimately, however, PJM’s IRAS Proposal does not \nprovide the clarity needed for EDCs’ IRAS obligations in real-time.  To this end, the Board requests \nclarification on how PJM will use real-time demand from New Large Loads to inform curtailment \ndirectives, either through a more dynamic database in PJM’s proposed Large Load Registry, or \nthrough the development and maintenance of a different system entirely to assist in this process.  \nFurthermore, both Buckeye Power and SMECO seek clarification that EDCs will not be required \n \n13 Buckeye Power Comments at 5; EKPC Protest at 12.  \n14 SMECO Comments at 8-9. \n15 Buckeye Power Comments at 6; SMECO Comments at 9; EKPC Protest at 12. \n16 Buckeye Power Comments at 3 (quoting PJM IRAS Proposal at 81)."},{"page":4,"startToken":967,"endToken":1283,"text":"4 \n \nto shed more load than what is being used by New Large Loads in real-time, which the Board \nsupports.17  \nii. \nPJM Should Clarify How IRAS Directives Interact with Peak Shaving Adjustments  \nThe Board appreciates PJM’s consideration of state policies when it added a Peak Shaving \nAdjustment (“PSA”) provision in its Reliability Backstop Procurement Proposal (“RBP”) that \nwould decrement a zone’s RBP obligation commensurate with its PSA arrangements.18  This \nprovision recognizes the reliability benefits PSA programs provide to the region, and the Board \nsubmitted Comments in appreciation of this component that compliments the newly passed Data \nCenter Fair Share Act in New Jersey.19  However, while PSA arrangements reduce RBP \nobligations, PJM has not explained how they will interact with Bring Your Own New Capacity \n(“BYONC”) obligations or IRAS obligations.  Several commentators have raised concerns about \nthis ambiguity.20  The Board likewise seeks clarity regarding how PSA arrangements interact with \nIRAS.   \nThe Board thinks that New Large Loads with PSA agreements must be accounted for \nexplicitly in PJM’s IRAS operations with real-time information regarding whether New Large \nLoads have already reduced their load due to PSA directives.  In a scenario in which a New Large \nLoad has already offset its load due to a PSA directive, it cannot reduce its total registered load \namount in the event the EDC requires it during an IRAS Action.  As discussed in reference to \n \n17 Buckeye Power Comments at 7; SMECO Comments at 9-10.  \n18 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy \nConcerns Stemming from New Large Load Adjustments, Docket No. ER26-3380 (July. 31, 2026). \n19 PJM Interconnection, L.L.C., Comments of the New Jersey Board of Public Utilities, Docket No. \nER26-3380 (Aug. 21, 2026).  \n20 See e.g., Tesla Comments at 4-5; Voltus Comments at 23-24; CEBA Protest at 8-11; Chief Energy \nOfficer for the Governor of Virgina Comments at 2-3."},{"page":5,"startToken":1283,"endToken":1584,"text":"5 \n \nBuckeye Power’s Comments, it is unclear whether EDCs will face penalties for not curtailing the \nentire amount of the registered peak New Large Load amount directed by PJM, or if EDCs must \ncurtail other customers in order to meet this IRAS obligation.  \nThe Board recommends that PJM clarify that EDCs will not be required to curtail more \nthan their New Large Load demand in real time, after accounting for any real-time load reductions \nachieved through programs such as PSA.  Furthermore, the Board recommends that a more \ndynamic data-sharing method is developed for PJM, states, utilities, and New Large Loads to \nlocate and utilize real-time New Large Load demand, IRAS, and PSA dispatch information for \nbetter information-sharing and accountability.  In addition, the Board agrees with Equinix that the \nLarge Load Registry should account for New Large Loads that are sponsoring PSAs at another site \nin the same zone in addition to PSAs associated with the load itself, which is not something PJM’s \nProposal appears to do currently.21   \nIII. \nCONCLUSION \nThe Board reiterates that it strongly supports PJM’s decision to propose a PJM-led resource \nadequacy service for New Large Loads that do not offset their registered peak load with sufficient \ncapacity arrangements, and thinks its Proposal is largely workable.  However, the Board \nunderscores concerns other entities have raised and seeks clarity on specific elements that currently \nprovide confusion and challenges in implementing IRAS.  The Board is hopeful that this \nclarification will provide entities in New Jersey with the information they need to effectuate PSA \nprograms, and that clarification pertaining to the IRAS MW amount will provide EDCs with the \nconfirmation that they are not expected to curtail other customers during an IRAS Action.  The \nBoard thinks these elements can be addressed without fundamentally altering PJM’s IRAS \n \n21 Equinix Comments at 16."},{"page":6,"startToken":1584,"endToken":1602,"text":"6 \n \nProposal, and the Board thinks it and other entities have proposed workable solutions to these \nchallenges.   \n \nRespectfully,"},{"page":7,"startToken":1602,"endToken":1726,"text":"7 \n \nNEW JERSEY BOARD OF PUBLIC \nUTILITIES \n \nBy: /s/ Paul Youchak \n \nIan Oxenham \nAlex Cary \nAmanda Lescano \nTimothy Randazzo \nMahala Lahvis \nAiri Kogishi \nNew Jersey Board of Public Utilities  \n44 South Clinton Ave. \nTrenton NJ 08609 \nPaul.youchak@bpu.nj.gov \nIan.oxenham@bpu.nj.gov \nAlexander.Cary@bpu.nj.gov \nAmanda.lescano@bpu.nj.gov \nTimothy.randazzo@bpu.nj.gov \nMahala.lahvis@bpu.nj.gov \nAiri.kogishi@bpu.nj.gov \nMICHAEL L. ZUCKERMAN \nACTING ATTORNEY GENERAL  \nOF NEW JERSEY \n \nBy: /s/ Steven Chaplar \n \nDeputy Attorney General \nDepartment of Law and Public Safety \nDivision of Law \nP.O. Box 112 \nTrenton, NJ 08625 \nSteven.chaplar@law.njoag.gov \n \nAttorneys for the New Jersey Board of \nPublic Utilities \n \n \n \nDated: September 18, 2026  \n \n \nTrenton, New Jersey"},{"page":8,"startToken":1726,"endToken":1802,"text":"8 \n \nCERTIFICATE OF SERVICE \nI hereby certify that, on this 18th day of September 2026, I have caused the foregoing \ndocument to be served upon each party designated on the official service list compiled by the \nSecretary in this proceeding, by email. \nBy: /s/ Steven Chaplar \nSteven Chaplar \n \n \n \n \n \n \nDeputy Attorney General \n \n   \n \n \n \n \nNew Jersey Office of the Attorney General \nDepartment of Law & Public Safety  \nP.O. Box 112  \nTrenton, New Jersey 08625  \nSteven.chaplar@law.njoag.gov"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":354,"startToken":0,"endToken":316},{"p":2,"at":354,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":665,"startToken":316,"endToken":362},{"p":2,"at":665,"title":"II. ANSWER","method":"printed heading","endPage":5,"endAt":1054,"startToken":362,"endToken":1451},{"p":5,"at":1054,"title":"III. CONCLUSION","method":"printed heading","endPage":8,"endAt":5,"startToken":1451,"endToken":1727},{"p":8,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":494,"startToken":1727,"endToken":1802}]}