{"document":{"slug":"rec-20260918-5391","title":"Comments of Verrus LLC in Support of Midcontinent Independent System Operator, Inc.'s proposed Interconnection Reliability Requirements for Large Loads","issued":"2026-09-18","accession":"20260918-5391","docket":"ER26-3650-000","group":"MISO interconnection reliability requirements for large loads","filer":"Verrus LLC","kind":"comments","file":"sources/filings/text/20260918-5391_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5391","tier":"record","sha256":"816a9da2c772e8ec5e9072d4902da8b477b9a112322e4e0852dcc68b9a2da92c","pages":21,"tokens":4082,"emptyPages":[],"textThemes":["flex"]},"pages":[{"page":1,"startToken":0,"endToken":357,"text":"UNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\nMidcontinent Independent System Operator, Inc.\n)\nInterconnection Reliability Requirements\n)  Docket No. ER26-3650-000\nfor Large Loads\n)\nCOMMENTS OF VERRUS, LLC IN SUPPORT OF MISO'S INTERCONNECTION\nRELIABILITY REQUIREMENTS FOR LARGE LOADS\nPursuant to Rule 213 of the Commission’s Rules of Practice and Procedure1, Verrus LLC2\n(\"Verrus\") respectfully submits these comments in support of the above-captioned filing by the\nMidcontinent Independent System Operator, Inc. (\"MISO\"), which proposes Interconnection\nReliability Requirements (\"IRR\") for Large Loads.3 Verrus generally supports MISO’s proposed\napproach and offers the comments below to underscore that advanced, flexible computational\nloads — such as those Verrus develops — can, and should, serve as active contributors to grid\nreliability, not merely as loads that must be accommodated.\nI.  BACKGROUND AND SUMMARY OF POSITION\nMISO’s filing responds to the Commission’s June 18, 2026 order directing MISO to show\ncause why its Tariff remains just and reasonable absent provisions addressing ongoing\noperational requirements for large loads, including visibility, ramp rate, and disturbance\nride-through.4 MISO’s IRR Proposal seeks to establish four categories of reliability requirements\n— data, modeling, telemetry, and forecasting requirements (together, “visibility”), phasor\nmeasurement unit (“PMU”) requirements, ramp requirements, and ride-through requirements —\n4Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (\"Show Cause Order\"); see also\nTransmittal Letter at 6, 8 (describing the Show Cause Order and MISO’s subsequent Abeyance Motion).\n3Midcontinent Independent System Operator, Inc., Interconnection Reliability Requirements for Large Loads,\nDocket No. ER26-3650-000, Transmittal Letter (Aug. 28, 2026) (\"Transmittal Letter\").\n2Verrus LLC (\"Verrus\") is a developer, owner, and operator of a first-of-its-kind fleet of purpose-built, load-flexible\ndata centers designed to function not only as digital infrastructure but also as active grid assets, capable of\ndynamically adjusting electricity consumption to support system reliability, efficiency, and affordability.  Verrus has\nbeen an active stakeholder participant in MISO’s Large Load Working Group (\"LLWG\") process addressing the\nInterconnection Reliability Requirements at issue in this filing, and has separately engaged before the Commission\non large-load interconnection issues, including in Docket Nos. EL26-70-000 and RM26-4-000.  Contemporaneously\nwith these comments, Verrus has filed a motion to intervene in this proceeding.\n1 18 C.F.R. § 385.213.\n1"},{"page":2,"startToken":357,"endToken":692,"text":"scaled to a newly defined “Computational Load” subset of “Large Load,” with the more intensive\nPMU, ramp, and ride-through obligations applied only to Computational Loads.5\nVerrus supports this framework.\nAs explained below, Verrus (A) supports MISO’s\nrisk-scaled approach to applicability; (B) supports MISO’s choice to establish core obligations in\nthe Tariff, while reserving implementation detail to the Business Practices Manual (“BPM”) and\nits ongoing stakeholder process; (C) offers its own facility design as an example demonstrating\nthat advanced computational loads are capable of actively supporting reliability, not merely\ncomplying with minimum standards; (D) urges the Commission to ensure that MISO’s\nTariff-based requirements remain harmonized with the ongoing NERC standard development\neffort; and (E) requests that MISO’s transition provisions continue to reasonably account for\nloads still progressing toward full interconnected capacity.\nII.  COMMENTS\nA. MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That\nPresent Reliability Risk\nVerrus supports MISO’s determination to apply the full suite of PMU, ramp, and\nride-through requirements only to the Computational Load subset of Large Load, while applying\nvisibility requirements more broadly.6 This approach appropriately recognizes that not all large\nloads\nexhibit\nthe\nrapid,\npower-electronic-driven\ndemand\nchanges\nthat\nmotivated\nthe\nCommission’s concerns,7\nand avoids imposing requirements on loads that do not present the\nreliability risk those requirements are designed to address.\nB.\nVerrus Supports Establishing Core Obligations in the Tariff While Reserving\nImplementation Detail to the BPM and Stakeholder Process\nVerrus also generally supports MISO’s approach of codifying the core visibility, PMU,\nramp, and ride-through obligations in the Tariff while leaving technical details — communication\nprotocols, specific thresholds, and testing and demonstration procedures — to the BPM for Large\n7Show Cause Order at P 64.\n6Transmittal Letter at 11, 15-22 (explaining that all Large Loads are subject to applicable visibility requirements,\nwhile the Computational Load component of a Large Load is separately subject to PMU, ramp, and ride-through\nrequirements).\n5Transmittal Letter at 3-4, 9-10, 22 (describing the categories of proposed reliability requirements and the Large\nLoad / Computational Load definitions).\n2"},{"page":3,"startToken":692,"endToken":1102,"text":"Load, which is being refined in the the continuing LLWG process.8 That approach strikes an\nappropriate balance: it gives the Commission and stakeholders a clear, enforceable Tariff\nframework, while preserving the flexibility MISO and stakeholders need to refine technical\nrequirements in a rapidly evolving area as operating experience increases.\nC.  Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability\nVerrus’ own facility design illustrates that computational loads that would be subject to\nMISO’s proposed requirements are not merely able to comply with them, but can affirmatively\nsupport system reliability. Verrus data centers employ behind-the-meter battery energy storage\nsystems (“BESS”) and proprietary coordinated controls — which Verrus refers to as its\nStabiliGrid™architecture — that function as a buffer layer between the point of interconnection\nand IT load, managing ramp behavior and providing sub-second ride-through support during\nvoltage and frequency disturbances.9 Testing and modeling of this architecture, conducted jointly\nwith\nthe\nNational\nLaboratory\nof\nthe\nRockies,\ndemonstrates\nmaterially\nreduced\npoint-of-interconnection power deviation during severe grid disturbances relative to the\nconventional design baseline modeled in the study.10 Verrus offers this experience to illustrate\nthat the Commission and MISO should continue their efforts to ensure that computational loads\nfunction as grid assets.\nD.\nFERC Action on MISO’s Reliability Requirements Should Be Harmonized with the\nParallel NERC Standards Effort\nMISO’s own filing recognizes that its proposed ramp, PMU, and ride-through\nrequirements are being developed ahead of, but in alignment with, NERC’s emerging\nComputational Load definition and the ongoing work of NERC’s Load Modeling Task Force.11\nNERC is separately developing large-load-related reliability requirements of its own, including\nthrough its Large Loads Task Force, Large Loads Working Group, and Project 2026-02\n11Transmittal Letter at 28 (noting that MISO clarified that Tariff applicability for the ramp, PMU, and ride-through\nrequirements aligns with NERC’s emerging definition of Computational Loads and the technical discussions of\nNERC’s Load Modeling Task Force).\n10Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated Control Strategy Using Verrus™\nStabiliGrid™ Architecture, Technical Report NLR/TP-2C00-98424 (Feb. 2026),\nhttps://docs.nlr.gov/docs/fy26osti/98424.pdf, appended as Attachment A (\"StabiliGrid Report\").\n9Verrus May 2026 LLWG Reliability Comments at 1 (describing Verrus’s use of a behind-the-meter battery energy\nstorage system and proprietary control system as a “buffer layer” between the point of interconnection and IT load).\n8Transmittal Letter at 21-27 (describing proposed Tariff Sections 37A.1 through 37A.8 and MISO’s corresponding\nBusiness Practices Manual for Large Load implementation).\n3"},{"page":4,"startToken":1102,"endToken":1346,"text":"(Computational Load).12\nBecause the MISO and NERC are advancing large-load reliability\nrequirements in parallel (but not in fully synchronized processes), Verrus urges the Commission,\nin acting on this filing, to make clear that MISO’s Tariff-based requirements and any eventual\nNERC Reliability Standard(s) addressing the same operational characteristics should be\nharmonized — so that large loads such as Verrus, as well as utilities and other stakeholders, are\nnot left navigating duplicative, inconsistent, or conflicting obligations.\nE.\nMISO’s\nTransition Provisions Should Continue to Accommodate Loads Still\nProgressing Toward Full Capacity\nVerrus supports MISO’s proposed transition provisions, which appropriately distinguish\nbetween loads with a Service Commencement Date before the proposed effective date and those\nstill progressing through interconnection.13\nConsistent with comments Verrus has previously\noffered in the LLWG process, Verrus encourages MISO to clarify that the ramp-up process for\nstandards implementation accounts for the buildout period of a large load campus (which\nfrequently extends over several years), rather than binding at a level calibrated to initial, partial\nenergization.14\n14Verrus May 2026 LLWG Comments at 1-2 (recommending that MISO clarify the load level at which the ramp\nrequirement becomes binding during a phased site energization).\n13Transmittal Letter at 13-14 (describing transition provisions applicable based on Service Commencement Date and\nMTEP/EPR status).\n12Transmittal Letter at 7 & n.21 (citing NERC Large Loads Task Force and Large Loads Working Group\nwhitepapers and alerts, and Project 2026-02 (Computational Load), a NERC Reliability Standard currently under\ndevelopment).\n4"},{"page":5,"startToken":1346,"endToken":1466,"text":"III.  CONCLUSION\nFor the foregoing reasons, Verrus respectfully requests that the Commission accept\nMISO’s filing in Docket No. ER26-3650-000, and approve MISO’s requested effective date of\nDecember 4, 2026.15 Verrus looks forward to continuing to participate in MISO’s Large Load\nWorking Group as further implementation details are developed.\nRespectfully submitted,\n/s/ Gabe Tabak\nGabe Tabak\nHead of Energy Policy\nVerrus LLC\ngabe@verrusdata.com\n/s/ Jeff Bladen\nJeff Bladen\nHead of Energy\nVerrus LLC\nbladen@verrusdata.com\nDated:  September 18, 2026\nAttachment A:  Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated\nControl Strategy Using Verrus™ StabiliGrid™ Architecture (Feb. 2026) [to be appended].\n15Transmittal Letter at 30 (requesting an effective date of December 4, 2026).\n5"},{"page":6,"startToken":1466,"endToken":1566,"text":"The National Laboratory of the Rockies is a national \nlaboratory of the U.S. Department of Energy,  \nOffice of Critical Minerals and Energy Innovation, \noperated under Contract No. DE-AC36-08GO28308. \nThis report is available at no cost from the National Laboratory \nof the Rockies (NLR) at www.nlr.gov/publications. \n \n \n \n \nTechnical Report  \nNLR/TP-2C00-98424 \nFebruary 2026  \nMitigating Data Center Impact on Grid \nStability: A Coordinated Control \nStrategy Using Verrus™ StabiliGrid™ \nArchitecture \nSaurav Talukdar,1 Shilpa Marti,1 Ben Wheeler,1 Jeff \nBladen,1 Deepthi Vaidhynathan,2 Kumaraguru Prabakar,2 \nand Steven Hammond2 \n1 Verrus LLC \n2 National Laboratory of the Rockies"},{"page":7,"startToken":1566,"endToken":1732,"text":"The National Laboratory of the Rockies is a national \nlaboratory of the U.S. Department of Energy,  \nOffice of Critical Minerals and Energy Innovation, \noperated under Contract No. DE-AC36-08GO28308. \nThis report is available at no cost from the National Laboratory \nof the Rockies (NLR) at www.nlr.gov/publications. \n \n \nNational Laboratory of the Rockies \n15013 Denver West Parkway \nGolden, CO 80401 \n303-275-3000 • www.nlr.gov \nTechnical Report  \nNLR/TP-2C00-98424 \nFebruary 2026  \nMitigating Data Center Impact on Grid \nStability: A Coordinated Control \nStrategy Using Verrus StabiliGrid \nArchitecture \nSaurav Talukdar,1 Shilpa Marti,1 Ben Wheeler,1 Jeff \nBladen,1 Deepthi Vaidhynathan,2 Kumaraguru Prabakar,2 \nand Steven Hammond2 \n1 Verrus LLC \n2 National Laboratory of the Rockies \nSuggested Citation \nTalukdar, Saurav, Shilpa Marti, Ben Wheeler, Jeff Bladen, Deepthi Vaidhynathan, \nKumaraguru Prabakar, and Steven Hammond. 2026. Mitigating Data Center Impact on \nGrid Stability: A Coordinated Control Strategy Using Verrus StabiliGrid Architecture. \nGolden, CO: National Laboratory of the Rockies. NLR/TP-2C00-98424. \nhttps://www.nlr.gov/docs/fy26osti/98424.pdf."},{"page":8,"startToken":1732,"endToken":1913,"text":"NOTICE \nThis work was authored in part by the National Laboratory of the Rockies for the U.S. Department of Energy (DOE), \noperated under Contract No. DE-AC36-08GO28308. Support for the work was provided by Verrus LLC under \nTSA2431261. This work was also supported by the Laboratory Directed Research and Development (LDRD) \nProgram at the National Laboratory of the Rockies. The views expressed herein do not necessarily represent the \nviews of the DOE or the U.S. Government. \nThis report is available at no cost from the National Laboratory  \nof the Rockies (NLR) at www.nlr.gov/publications. \nU.S. Department of Energy (DOE) reports produced after 1991 \nand a growing number of pre-1991 documents are available  \nfree via www.OSTI.gov. \nCover photos (clockwise from left): Josh Bauer, National Laboratory of the Rockies 61725; Visualization from National Laboratory of the \nRockies Insight Center; Getty-181828180; Agata Bogucka, National Laboratory of the Rockies 91683; Dennis Schroeder, National Laboratory \nof the Rockies 51331; Werner Slocum, National Laboratory of the Rockies 67842. \nThe National Laboratory of the Rockies prints on paper that contains recycled content."},{"page":9,"startToken":1913,"endToken":1957,"text":"iii \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nTable of Contents \nBackground ................................................................................................................................................. 1 \nJuly 10, 2024: Large Load Loss Incident ............................................................................................... 1 \nCurrent State ............................................................................................................................................... 3 \nInnovation .................................................................................................................................................... 4 \nResults ......................................................................................................................................................... 5 \nConclusion ................................................................................................................................................. 10 \nReferences ................................................................................................................................................. 11"},{"page":10,"startToken":1957,"endToken":2040,"text":"iv \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nList of Figures \nFigure 1. Grid voltage faults at Station C ..................................................................................................... 2 \nFigure 2. Aggregate grid load ....................................................................................................................... 3 \nFigure 3. Coordinated response of a BESS-enabled data center during repeated undervoltage events ............ 7 \nFigure 4. Coordinated response of a BESS-enabled data center during an overvoltage event ......................... 9 \n \nList of Tables \nTable 1. Undervoltage Grid Contingency Event ........................................................................................... 5 \nTable 2. Overvoltage Grid Contingency Event ............................................................................................. 8"},{"page":11,"startToken":2040,"endToken":2324,"text":"1 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nBackground \nJuly 10, 2024: Large Load Loss Incident \nOn July 10, 2024 (NERC 2025), the fragility of modern load dynamics was exposed when a \nlightning strike in Northern Virginia caused a transmission-level fault, lasting less than 100 \nmilliseconds (ms), which triggered the cascading disconnection of approximately 1,500 \nmegawatts (MW) of data center load (see Figure 1). Despite the grid fault clearing in roughly 50 \nms, sensitive internal protection schemes across dozens of facilities interpreted the voltage sag as \na valid outage, transitioning information technology (IT) loads to backup power and severing \ngrid connection. The resulting sudden drop in demand caused a voltage swell to 1.07 p.u., \nrequiring manual operator intervention to stabilize the area. \nCrucially, although the facilities in Northern Virginia effectively operated within the voltage \nimmunity bounds of the Information Technology Industry Council (ITIC) curve, the event \nexposed a fundamental misalignment: The ITIC standard is designed to protect individual server \nhardware, not to maintain macro-grid stability. This resulted in the grid losing several hundred \nmegawatts of load almost instantaneously, creating overvoltage and oscillation. \nThis “near miss” has become a primary case study for North American Electric Reliability \nCorporation and Institute of Electrical and Electronics Engineers (IEEE) working groups, driving \nnew regulatory frameworks that treat data centers not just as passive customers, but as large, \ndynamic loads that must possess robust voltage ride-through capabilities, adaptive protection, \nand coordinated control strategies. The Electric Reliability Council of Texas recently released its \nride-through requirements (ERCOT 2025) for large electronic loads (which includes data \ncenters), particularly to address these types of massive load disconnection concerns."},{"page":12,"startToken":2324,"endToken":2354,"text":"2 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \n \nFigure 1. Grid voltage faults at Station C (NERC 2025)"},{"page":13,"startToken":2354,"endToken":2598,"text":"3 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nCurrent State \nIn practice, many data centers use disturbance-count protection that locks out after three \nundervoltage events (below ~0.7–0.8 p.u.) within 60 seconds (s), transferring loads to backup \npower until a manual reset is performed. In the July 10 event shown in Figure 1, the third \nundervoltage (NERC 2025) triggered widespread lockouts, disconnecting approximately 1.5 \ngigawatts of data center load and amplifying grid instability as seen in Figure 2. \n \nFigure 2. Aggregate grid load (NERC 2025) \nRecently, some new data centers (Vaidhynathan et al. 2025) have incorporated commercial \nbattery energy storage systems (BESS) units that typically include fault ride-through and \nundervoltage ride-through capabilities, as mandated by IEEE 1547 standards. However, these \nresponses are typically self-contained and uncoordinated with data center protection logic or \nuninterruptible power supply (UPS) operation to provide a “plant-level” ride-through response. \nAs a result, although the BESS remains connected during short faults, it is not synchronized to \nprovide grid load recovery/ride-through behavior with UPS load transfer or point of \ninterconnection (POI) protection timing. This results in delayed power restoration and short-term \ngrid instability following voltage recovery persisting with conventional BESS. \nThis observation highlights a key gap: Existing BESS operate effectively at the device level but \nlack integrated control with other critical data center assets needed for a grid-supportive response \nduring and after “successive” undervoltage events."},{"page":14,"startToken":2598,"endToken":2834,"text":"4 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nInnovation \nAs data centers represent a larger percentage of overall grid load, it is increasingly critical that \nthey stay connected and assist the grid during short-duration grid contingencies (<~5-s) to avoid \ncausing wide-area outages. This is accomplished by intelligent control algorithms and/or \nparameter settings for controllable assets in a data center such as IT load, cooling load, UPS, \nprotection settings, and distributed energy sources such as BESS and generators. \nThe Verrus™ StabiliGrid™ data center architecture involves four steps for data center response \nthat improve grid resilience: \n1. Grid contingency event detection. Uses high-resolution power quality monitoring to \ndetect grid state (during events such as undervoltage, overvoltage, underfrequency, and \noverfrequency). \n2. Grid-resilient protection settings. POI settings that allow extended ride-through/grid-\nconnected operation of the data center during the grid contingency, reducing the \nprobability of an islanding event. \n3. Control of assets. Depending on detection of grid event, enables grid-state-driven \nautonomous dispatch of the asset to improve grid resiliency (for example, reduce power \ndraw from the grid during an undervoltage event or absorb more power from the grid \nduring an overvoltage event). \n4. Post-grid event response. Post-grid recovery and following a grid contingency event, \ncoordinates data center assets to present firm load to the grid more quickly, similar to the \nlevels before the grid contingency event."},{"page":15,"startToken":2834,"endToken":3275,"text":"5 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nResults \nVerrus explored the real-life incident shown in Figure 1 in its controller hardware in the loop (C-\nHIL) setup at the National Laboratory of the Rockies (NLR) to demonstrate the effectiveness of \nour data center design with large-scale BESS and Verrus StabiliGrid (applicable features \ndescribed previously) in responding to the cascaded grid undervoltage events. The C-HIL setup \nis developed in the Advanced Research on Integrated Energy Systems virtual emulation \nenvironment at NLR and is based on a digital real-time simulation platform (Vaidhynathan et al. \n2025). \nNote although we present results from undervoltage events, the Verrus StabiliGrid design can \ncontribute to grid resilience during other types of short-duration grid contingencies such as \novervoltage, overfrequency, and underfrequency. Our work with NLR instantiates the previous \nfour-step strategy for data centers to ride through short-duration grid contingencies (~ seconds) \nand provide grid support. Controllable assets used are BESS and UPS. Results from the \nundervoltage grid contingency event of Figure 1 are presented in Table 1. \nTable 1. Undervoltage Grid Contingency Event \n1 \nGrid contingency event \ndetection \nHigh-resolution power quality monitoring is used to rapidly detect the \ngrid’s state (e.g., undervoltage, overfrequency). \nUse of protection relays and/or advanced power quality monitoring \ncapable of millisecond resolution sampling with communication \ncapabilities such as IEC61850. \nProvides the necessary “fast” input signal for controllable assets such \nas the BESS and UPS to initiate a response. \nIn Figure 3a, the system simulates cascaded undervoltage events, \neach dropping below 0.7 p.u., and initiates automatic mitigation \nthrough Verrus StabiliGrid. \n2 \nGrid-resilient protection \nsettings \nImplementing POI protection settings aligned with standards such as \nIEEE 1547 to enable “plant” ride-through response. \nThis crucial step changes the data center’s default behavior from \nimmediate disconnection (islanding) during a short fault to extended \nride-through/grid-connected operation, allowing a grid-resilience-\nimproving response to function. \nUnlike conventional disturbance-count schemes that trigger lockout \nafter three undervoltage events, the adaptive logic within Verrus \nStabiliGrid dynamically evaluates voltage magnitude, recovery rate, \nand event duration to prevent premature disconnection during both \nundervoltage and overvoltage transients. \n3 \nControl of assets (during \nundervoltage grid \ncontingency) \nAs shown in Figure 3b, the total power drawn from the grid is \nmomentarily reduced during the undervoltage events, stabilizing grid \nloading. \nThe BESS discharges in volt-watt mode, supplying power to \ncompensate for voltage sags and offset the drop in utility import. \nSimultaneously, UPS maintains continuous support for IT loads, \nensuring operational integrity as grid voltage fluctuates. \nThis controlled BESS discharge during undervoltage event minimizes \nthe net power imbalance seen by the grid and prevents cascading \ninstability."},{"page":16,"startToken":3275,"endToken":3413,"text":"6 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \n4 \nPost-grid event response \nBESS controls are modified to have UPS awareness. \nAs soon as grid voltage returns to a nominal state, the BESS begins \ncharging and continues until the IT load is no longer relying on the \nUPS. \nIn Figure 3d, the data center’s total grid import returns to pre-fault \nlevels within 100 milliseconds of voltage normalization. \nThis immediate restoration of firm load prevents secondary \novervoltage or oscillation events and supports grid recovery \ndynamics. \n \nNext, we show the four-step framework also enables ride-through capabilities for overvoltage \nevents. Because of the lack of real-life overvoltage events, we look at a synthetic case of \novervoltage to 1.1 p.u. in the grid for 1-second duration (see Table 2)."},{"page":17,"startToken":3413,"endToken":3544,"text":"7 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \n \n(a) \n \n(b) \n \n(c) \n \n(d) \nFigure 3. Coordinated response of a BESS-enabled data center during repeated undervoltage events \n(a; top) Grid voltage: Undervoltage events, each dropping below 0.7 p.u., detected within a 60-s window; (b) Utility \npower import: Controlled reduction in grid power draw during undervoltages and rapid (<100-ms) restoration to pre-\nfault levels once voltage normalizes; (c) BESS output power: BESS operating in volt-watt mode discharges to offset \ngrid voltage dips, then transitions to controlled charging post-recovery in coordination with UPS hand-back; (d;) Data \ncenter UPS load: UPS provides transient support for IT loads during grid disturbances, maintaining uninterrupted \noperation and enabling seamless load transfer back to grid power."},{"page":18,"startToken":3544,"endToken":3723,"text":"8 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nTable 2. Overvoltage Grid Contingency Event \n1 \nGrid contingency event \ndetection \nAs shown in Figure 4a, illustrates the overvoltage scenario reaching \n1.1 p.u. for a sustained 1-s period. \nUpon detection, Verrus StabiliGrid activates the grid voltage support \nsequence, commanding the BESS to absorb excess grid energy to \nrestore nominal voltage levels. \n2 \nGrid-resilient protection \nsettings \nThe POI settings prevent unnecessary islanding during “short” \novervoltage peaks. \nBy allowing ride-through, the data center remains grid-connected \nlong enough for StabiliGrid to stabilize the voltage. \n3 \nControl of assets (during \nundervoltage grid \ncontingency) \nFigure 4b and 4c illustrate the overvoltage response, where the \nBESS transitions into power absorption mode, drawing controlled \npower from the grid to support the voltage rise on the grid. \nThe UPS supports the IT loads during the overvoltage event with no \ninterruption or power quality degradation. \n4 \nPost-grid event \nresponse \nFigure 4b shows a similar smooth recovery following the overvoltage \nevent with no secondary oscillations or overshoot."},{"page":19,"startToken":3723,"endToken":3868,"text":"9 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \n \n \n(a) \n \n(b) \n \n(c) \n \n(d) \nFigure 4. Coordinated response of a BESS-enabled data center during an overvoltage event \n(a; top) Grid voltage: A transient overvoltage reaching approximately 1.1 p.u., sustained for ~1 s before returning to \nnominal levels; (b) Utility power draw: The BESS operating in volt-watt mode charges to offset grid overvoltage, then \ntransitions to controlled charging post-recovery in coordination with UPS hand-back; (c) BESS output power: The \nBESS transitions to absorption mode (negative power), dynamically drawing excess energy from the grid in \nproportion to the voltage deviation and gradually tapering as the voltage normalizes; (d; bottom) Data center UPS \nload: UPS provides transient support for IT loads during grid disturbances, maintaining uninterrupted operation and \nenabling seamless load transfer back to grid power."},{"page":20,"startToken":3868,"endToken":3954,"text":"10 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nConclusion \nThrough this coordinated strategy implemented in Verrus StabiliGrid, the data center achieves \nfault ride-through and rapid recovery for both undervoltage and overvoltage conditions without \ntriggering protection lockouts. The digital real-time simulations demonstrate by synchronizing \nBESS, UPS, and protection logic behavior, the data center transitions from being a disturbance-\nsensitive load to an active, grid-supporting participant—a key requirement for future grid-\nintegrated data center operations."},{"page":21,"startToken":3954,"endToken":4082,"text":"11 \nThis report is available at no cost from the National Laboratory of the Rockies at www.nlr.gov/publications. \nReferences \nElectric Reliability Council of Texas (ERCOT). 2025. “Large Electronic Load Ride-Through \nRequirements. www.ercot.com/files/docs/2025/12/01/6.2-NOGRR282-Large-Electronic-Load-\nRide-Through-Requirements-and-NPRR1308.pdf. Austin, Texas.   \nNorth American Electric Reliability Corporation (NERC). 2025. “Incident Review: Considering \nSimultaneous Voltage-Sensitive Load Reductions.” Washington, D.C. \nwww.nerc.com/globalassets/our-work/reports/event-\nreports/incident_review_large_load_loss.pdf.  \nVaidhynathan, Deepthi, Kumaraguru Prabakar, Gregory Martin, Anand Ramesh, Ben Wheeler, \nChristopher Coco, Jimmy Clidaras, Matthieu Monsch, Sangsun Kim, Saurav Talukdar, and \nShilpa Marti. 2025. Vulcan Test Platform: Demonstrating the Data Center as a Flexible Grid \nAsset. Golden, Colorado: National Laboratory of the Rockies. \ndocs.nlr.gov/docs/fy25osti/94844.pdf."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":919,"startToken":0,"endToken":122},{"p":1,"at":919,"title":"I. BACKGROUND AND SUMMARY OF POSITION","method":"printed heading","endPage":2,"endAt":958,"startToken":122,"endToken":488},{"p":2,"at":958,"title":"II. COMMENTS","method":"printed heading","endPage":2,"endAt":972,"startToken":488,"endToken":490},{"p":2,"at":972,"title":"A. MISO’s Risk-Scaled Framework Reasonably Targets Requirements at the Loads That","method":"printed heading","endPage":2,"endAt":1583,"startToken":490,"endToken":575},{"p":2,"at":1583,"title":"B. Verrus Supports Establishing Core Obligations in the Tariff While Reserving","method":"printed heading","endPage":3,"endAt":347,"startToken":575,"endToken":742},{"p":3,"at":347,"title":"C. Advanced Computational Loads Are Capable of Actively Supporting Grid Reliability","method":"printed heading","endPage":3,"endAt":1460,"startToken":742,"endToken":893},{"p":3,"at":1460,"title":"D. FERC Action on MISO’s Reliability Requirements Should Be Harmonized with the","method":"printed heading","endPage":4,"endAt":539,"startToken":893,"endToken":1177},{"p":4,"at":539,"title":"E. MISO’s","method":"printed heading","endPage":5,"endAt":0,"startToken":1177,"endToken":1346},{"p":5,"at":0,"title":"III. CONCLUSION","method":"printed heading","endPage":5,"endAt":550,"startToken":1346,"endToken":1428},{"p":5,"at":550,"title":"Attachment A: Talukdar et al., Mitigating Data Center Impact on Grid Stability: A Coordinated","method":"printed heading","endPage":9,"endAt":115,"startToken":1428,"endToken":1933},{"p":9,"at":115,"title":"Table of Contents","method":"printed heading","endPage":11,"endAt":113,"startToken":1933,"endToken":2060},{"p":11,"at":113,"title":"Background","method":"printed heading","endPage":20,"endAt":114,"startToken":2060,"endToken":3888},{"p":20,"at":114,"title":"Conclusion","method":"printed heading","endPage":21,"endAt":986,"startToken":3888,"endToken":4082}]}