{"document":{"slug":"rec-20260918-5413","title":"Motion for Leave to Answer and Answer of American Electric Power Service Corporation to PJM Interconnection, L.L.C.'s 09/10/2026 Answer","issued":"2026-09-18","accession":"20260918-5413","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"American Electric Power Service Corporation","kind":"answer","file":"sources/filings/text/20260918-5413_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260918-5413","tier":"record","sha256":"fdc0420a1ce5d22e50a6ac3d545c0560951e1e8eba7e76fc80b4765832e6ece2","pages":8,"tokens":2389,"emptyPages":[],"textThemes":["credit","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":304,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, LLC  \n \n \n)  \n \nDocket No. ER26-3380 \n \n \n \n \n \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF \nAMERICAN ELECTRIC POWER SERVICE CORPORATION \n \n \nPursuant to Rules 212 and 213, AEP hereby submits this motion for leave to answer and \nanswer (“Answer”) to the September 10 answer filed by PJM Interconnection, LLC (“PJM”) in \nthe captioned proceeding. 1  PJM’s Answer fails to meaningfully respond to significant flaws in \nthe proposed Reliability Backstop Procurement (“RBP”) exit provisions.  Most of these flaws \nemanate from the proposal that a departing member not just cover its load obligations for RBP \nCharges, but also hold third-party generators harmless through some combination of accelerated \npayments, pseudo-ties, or renegotiated contracts, depending on which generators PJM elects in its \nsole discretion to retain.  PJM suggests that these issues can be worked out in “extensive \nnegotiations” upon a member’s exit.2  This response from PJM exposes the problem well:  RTO \nmembership remains voluntary, and PJM governing documents have never required “extensive \nnegotiations” before a member can exercise its legal right to leave.  This lack of clear, \nadministrable standards renders the RBP exit provisions unjust and unreasonable.  PJM’s proposal \nto have unfettered discretion in those negotiations further renders this new exit fee unacceptable.   \n \n1  \nThis motion and answer is submitted pursuant to 18 C.F.R. §§ 385.212, 385.213 (2025). American Electric \nPower Service Corporation is filing on behalf of its affiliates Appalachian Power Company, Indiana Michigan Power \nCompany, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power \nCompany, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP \nKentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Company, \nInc. (collectively, “AEP”). \n2  \nAnswer of PJM Interconnection, LLC in Docket No. ER26-3380-000 at 96 (filed Sept. 10, 2026) (“PJM \nAnswer”)."},{"page":2,"startToken":304,"endToken":871,"text":"2 \n \nI. \nMOTION FOR LEAVE TO ANSWER \nWhile an answer to a protest or comment is generally not permitted under the \nCommission’s rules,3 AEP respectfully moves for leave to file this Answer and asks that the \nCommission consider this response.4  The Commission permits an answer when it provides useful \nand relevant information that will assist the Commission in its decision-making process or where \nthe answer will clarify the issues before the Commission.5  This Answer clarifies the issues and \nprovides critical responses to arguments presented in PJM’s Answer that will assist the \nCommission in its decision-making process in this proceeding. \nII. \nANSWER \nA. \nAEP’s Protest Provided Detailed Concerns Regarding the Proposed RBP \nExit Fee  \nAs AEP explained in its Protest to PJM’s proposal to impose an unprecedented exit fee on \ndeparting members, the proposed RBP exit terms lack the clarity and administrable standards \n \n3  \n18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, \nor a request for rehearing, unless otherwise ordered by the decisional authority.”). \n4  \nThe Commission permits answers that would otherwise be prohibited where the reply would assure a \ncomplete record in the proceeding or assists the Commission in its decision-making process; SunEnergy1, LLC, 176 \nFERC ¶ 61,004 at P 41 (2021) (“We accept SunEnergy’s answer because it has provided information that assisted us \nin our decision-making process.”); New Fortress Energy LLC, 174 FERC ¶ 61,207 at P 7 (“The Commission’s Rules \nof Practice and Procedure do not permit answers to protests or answers to answers; however, we find good cause to \nwaive our rules and accept the answers because they provide information that has assisted in our decision-making \nprocess.” (citation omitted)), order on reh’g, 176 FERC ¶ 61,031 (2021), aff’d sub nom. New Fortress Energy Inc. v. \nFERC, 36 F.4th 1172 (D.C. Cir. 2022); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212 at P 2 n.6 (2018) (“[T]he \nCommission finds good cause to accept Saltville’s answer because it will not delay the proceeding, will assist the \nCommission in understanding the issues raised, and will ensure a complete record.”); provide information helpful to \nthe disposition of an issue; Columbia Gas Transmission, LLC, 146 FERC ¶ 61,232 at P 10 (2014) (“While the \nCommission’s Rules of Practice and Procedure generally prohibit answers to protests or answers, . . .  the Commission \nwill accept Columbia’s answer to aid in the disposition of the issues” (citation omitted)); or permit the issues to be \nnarrowed or clarified; Algonquin Gas Transmission, LLC, 166 FERC ¶ 61,012 at P 30 (2019) (“[W]e will accept \nAlgonquin’s answers because they clarify the concerns raised . . . .”). \n5  \nSee, e.g., PJM Interconnection, L.L.C., 176 FERC ¶ 61,003 at P 24 (2021) (“We accept the answers filed by \nPJM and the Market Monitor because they provide information that has assisted us in our decision-making process.”); \nAla. Gasline Dev. Corp., 171 FERC ¶ 61,134 at P 7 (2020) (“Although the Commission’s Rules of Practice and \nProcedure do not permit answers to protests, we will accept the answers herein because they clarify the concerns raised \nand provide information that has assisted in our decision making.” (citation omitted)), order on reh’g, 172 FERC ¶ \n61,214 (2020), aff’d sub nom. Ctr. for Biological Diversity & Sierra Club v. FERC, 67 F.4th 1176 (D.C. Cir. 2023)."},{"page":3,"startToken":871,"endToken":1210,"text":"3 \n \nnecessary to give a Transmission Owner adequate notice of its obligations upon exercising its \ncontractual right to exit PJM.6  The RBP exit fee would be based not on the RBP Charges allocated \nto it pursuant to PJM’s proposed cost allocation methodology, but would be determined \nsignificantly by where PJM happens to procure new RBP resources.  Moreover, the proposed exit \nfee would require a “negotiation” with PJM unbounded by governing principles, where no such \nrequirement exists today under the applicable governing documents.7  For example, section 18.7(a) \nof the RBP Tariff language would require a departing Transmission Owner to satisfy its exit \nobligations by entering into agreements with RBP Resource owners that “preserve the RBP \ncommitments,” but fails to provide any useful detail regarding what a satisfactory agreement \nwould contain.8  Should a departing Transmission Owner fail to enter into such an agreement, it \ncan elect to satisfy its exit obligations by pseudo-tying the RBP Resources into PJM, subject to \nPJM’s unfettered discretion over whether or not to retain the resource.  This decision to choose \nhow many and which resources to retain, left completely in PJM’s hands, could impose up to \nbillions of dollars of costs on a departing Transmission Owner’s customers. \nThe Commission has expressly rejected the notion that a Transmission Owner withdrawing \nfrom PJM should be required to pay an exit fee, and has reiterated that PJM’s Consolidated \nTransmission Owner’s Agreement does not contain such a requirement.9  PJM’s proposed RBP \nexit provisions are, in substance, precisely the kind of exit fee the Commission has previously \n \n6  \n See Limited Protest of Am. Elec. Power Svc. Corp., Docket No. ER26-3380-000, at 12-13 (filed Aug. 21, \n2026) (“AEP Limited Protest”). \n7  \nId. at 10-11.  \n8  \nId. at 12 (citing Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from \nNew Load Adjustments, Docket No. ER26-3380-000, Attachment B, Clean Tariff Records, Attachment DD, § \n18.7(a)). (filed July 31, 2026)).). \n9  \nMw. Indep. Transmission Sys. Operator, Inc., 124 FERC ¶ 61,219, at P 176 (2008) (“Duquesne II”)."},{"page":4,"startToken":1210,"endToken":1538,"text":"4 \n \ndeclined to impose.  As AEP explained in its Protest, PJM’s governing documents do not contain \nan exit fee, and Commission precedent in Duquesne I and Duquesne II confirms that a departing \nmember’s obligation with regard to generating capacity charges extends only through the last RPM \nauction in which that departing member’s load was included.10  The RBP exit fee, by contrast, \nwould go well beyond this approved framework.  Rather than obligating a departing member to \npay costs for capacity PJM procures on its behalf, the RBP exit provisions would extend that \nobligation to establish a formal exit fee, potentially including costs for capacity procured to satisfy \nanother zone’s RBP obligation.  PJM’s proposed exit provisions would create, for the first time, a \nlong-term financial obligation that a departing Transmission Owner must satisfy as a condition of \nwithdrawal—an obligation that could extend up to 15 years and could amount to billions of dollars.   \nB. \nPJM’s Answer Does Not Provide a Basis for the Commission to Approve \nPJM’s Unfettered Discretion Over the Calculation of the RBP Exit Fee \n PJM’s Answer is unresponsive to AEP’s arguments regarding the new exit fee and thus \nprovides an inadequate basis for the Commission to approve this portion of the RBP Proposal.  \nBecause the proposed RBP exit fee goes well beyond the financial obligation allocated to departing \nload for its RBP Charges, the single largest variable in PJM’s calculation of the exit fee is the \ntreatment of RBP Resources in the departing member’s zone.  PJM’s proposal insists that PJM \nretain sole discretion over this critical input to the exit fee.  Specifically, PJM seeks complete \ndiscretion over whether to retain an RBP Resource via pseudo-tie upon a Transmission Owner’s \ndeparture without any objective, predetermined criteria governing which RBP Resources to retain \nand which to release.   \n \n10  \nAEP Limited Protest at 21-27 (citing Duquesne Light Co., 122 FERC ¶ 61,039, at P 92 (2008) (“Duquesne \nI”) and Duquesne II, 124 FERC ¶ 61,219 at P 176)."},{"page":5,"startToken":1538,"endToken":1847,"text":"5 \n \nPJM first asks the Commission to disregard these concerns by AEP and others on the \ngrounds that they can be addressed later in the “extensive negotiations” that should happen upon \na transmission withdrawal.11  This answer illustrates AEP’s point.  The current PJM governing \ndocuments do not require a Transmission Owner to negotiate its way out of PJM.  As long as it \nsatisfies its contractual obligations, it may leave.  PJM’s plan to use the RBP to impose a brand \nnew exit fee based on an “extensive negotiation” allows PJM unconstrained leverage to effect its \npreferred outcome in any such negotiation.  It is inadequate to simply state, as PJM does, that “it \nmust retain” that discretion to ensure reliability and resource adequacy.12  Without governing \nprinciples, the RBP exit provisions would ultimately afford PJM considerable discretion over a \nTransmission Owner’s ability to withdraw.  Indeed, PJM could either elect not to keep RBP \nResources and require the departing Transmission Owners to make them whole, or it could elect \nto keep more resources than it needs and force the departing Transmission Owner to facilitate \nexpensive and needless pseudo-ties.  PJM’s related argument that a departing member has \n“flexibility” in exit terms is also an overstatement.  This optionality would only apply after PJM \nhas exercised its discretion to decide which RBP Resources to retain.    \nFinally, PJM’s reliance on the Ratepayer Protection Pledge to justify this portion of its \nproposal is misplaced.  Utilities’ pledge to protect customers from hyperscaler costs has nothing \nto do with PJM’s exit fee.  In any event, this argument supports AEP as much as PJM.  When a \nmember departs PJM for alternative arrangements, it would do so to better serve its customers.  \nBurdening departing load with costs well in excess of its RBP Charges is flatly contrary to the \nRatepayer Protection Pledge.       \n \n11   \nPJM Answer at 96. \n \n12  \nId. at 97."},{"page":6,"startToken":1847,"endToken":2145,"text":"6 \n \nC. \nThe RBP Exit Provisions Represent a Fundamental Change to the \nFramework for Withdrawal from PJM that PJM Has Not Justified  \nThe proposed provisions would materially alter the financial calculus of RTO withdrawal \nin a manner that is untested and unprecedented.  As described in AEP’s Protest, the current terms \nfor withdrawing from PJM are clear and well-established.13  They provide notice to members \nelecting to withdraw from PJM regarding what to expect upon withdrawal and do not:  (1) contain \nan exit fee; (2) mandate PJM’s negotiation of said exit fee with the withdrawing party; (3) provide \nPJM with discretion how or whether to provide departing Transmission Owners with an \nopportunity to mitigate the exit fee; or (4) require that the Commission determine the final sum of \nthe exit fee.   \nPJM’s proposed RBP exit terms ask the Commission to approve each of these elements, \nwhich would implement a new, wholly unvetted and untested framework in PJM and subject \ndeparting Transmission Owners to PJM’s choice as to what exit fee to assign a departing \nTransmission Owner.  Given the magnitude and novelty of the proposed RBP exit provisions, the \nCommission should carefully consider whether this proceeding—a one-time, expedited backstop \nprocurement designed to address a near-term capacity shortfall—is the appropriate vehicle through \nwhich to fundamentally alter the terms of Transmission Owner departure from PJM.  The RBP \nwas developed under an extraordinarily compressed timeline, driven by the urgent need to procure \ncapacity for the 2028/2029 Delivery Year.  The exit provisions, however, would create financial \nobligations extending through the 2042/2043 Delivery Year and would establish a precedent with \nimplications far beyond this one-time procurement.  The Commission should not allow an \nexpedited, one-time filing to serve as the mechanism for establishing new long-term exit \n \n13   \nAEP Limited Protest at 21-26."},{"page":7,"startToken":2145,"endToken":2326,"text":"7 \n \nobligations that could materially constrain Transmission Owners’ ability to exercise their \ncontractual right to leave PJM.  The Commission should either:  (1) sever and reject the \nTransmission Owner exit provisions proposed in PJM’s RBP Proposal; or (2) direct that PJM \nmodify those provisions as outlined in AEP’s Protest.14 \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, AEP respectfully requests that the Commission \ngrant this motion for leave to answer, accept this Answer, and grant the relief requested herein.  \n \n \n \n \n \n \n \n \nRespectfully submitted,  \n \n \n \n/s/Tim Mastrogiacomo \nTim Mastrogiacomo \nSenior Vice President \nFERC Legal and RTO Policy \nAmerican Electric Power Service \nCorporation  \n701 Pennsylvania Avenue \nSuite 900 \nWashington, DC 20004 \n(202) 383-3430 \n \n/s/ John C. Crespo \nJohn C. Crespo \nSenior Legal Advisor \nAmerican Electric Power Service \nCorporation \n1 Riverside Plaza \nColumbus, Ohio 43215 \n(614) 716-3727 \n \n \n \n \nSubmitted September 18, 2026 \n \n \n/s/ Christopher R. Jones \nChristopher R. Jones \nEmily Beard \nTROUTMAN PEPPER LOCKE LLP \n401 9th Street, NW, Suite 1000 \nWashington, DC 20004 \n(202) 274-2886 \nchris.jones@troutman.com \nemily.beard@troutman.com \n \n \n \n \n \n \n \nCounsel to American Electric Power Service \nCorporation \n \n \n \n \n \n \n \n \n \n \n \n \n14  \n See AEP Limited Protest at 11-12."},{"page":8,"startToken":2326,"endToken":2389,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that, on this 18th day of September, 2026, I have served a copy of the \nforegoing document on the official service list compiled by the Office of the Secretary for the \ncaptioned proceedings.  \n \n \n \n \n \n \n \n/s/ Emily Beard \n \n \n \n \n \n \n \nEmily Beard  \n \n \n \n \n \n \n \nTROUTMAN PEPPER LOCKE LLP \n \n \n \n \n \n \n \n401 9th Street, NW, Suite 1000 \n \n \n \n \n \n \n \nWashington, DC 20004 \n \n \n \n \n \n \n \n(202) 220-1298 \n \n \n \n \n \n \n \nemily.beard@troutman.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":305},{"p":2,"at":5,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":651,"startToken":305,"endToken":406},{"p":2,"at":651,"title":"II. ANSWER","method":"printed heading","endPage":2,"endAt":664,"startToken":406,"endToken":408},{"p":2,"at":664,"title":"A. AEP’s Protest Provided Detailed Concerns Regarding the Proposed RBP","method":"printed heading","endPage":4,"endAt":982,"startToken":408,"endToken":1363},{"p":4,"at":982,"title":"B. PJM’s Answer Does Not Provide a Basis for the Commission to Approve","method":"printed heading","endPage":6,"endAt":5,"startToken":1363,"endToken":1848},{"p":6,"at":5,"title":"C. The RBP Exit Provisions Represent a Fundamental Change to the","method":"printed heading","endPage":7,"endAt":335,"startToken":1848,"endToken":2194},{"p":7,"at":335,"title":"III. CONCLUSION","method":"printed heading","endPage":8,"endAt":0,"startToken":2194,"endToken":2326},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":489,"startToken":2326,"endToken":2389}]}