{"document":{"slug":"rec-20260921-5084","title":"Comments of Rowan Digital Infrastructure, LLC re the 08/28/2026 filing by Midcontinent Independent System Operator, Inc. proposing Interconnection…","issued":"2026-09-21","accession":"20260921-5084","docket":"ER26-3650-000","group":"MISO interconnection reliability requirements for large loads","filer":"Rowan Digital Infrastructure","kind":"comments","file":"sources/filings/text/20260921-5084_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260921-5084","tier":"record","sha256":"b67f1ad0fbd8e177e38976ada38cbd254b5756926405a3b76dc256cf95dbb8bd","pages":3,"tokens":1223,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":462,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent Independent System Operator, \nInc. \nDocket No. ER26-3650-000 \nCOMMENTS OF ROWAN DIGITAL INFRASTRUCTURE, LLC \n \nPursuant to Rule 211 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § \n385.211, Rowan Digital Infrastructure, LLC (\"Rowan\") files these Comments, Request for \nClarification, and Limited Protest, to the August 28, 2026 filing by the Midcontinent Independent \nSystem Operator, Inc. (\"MISO\") proposing Interconnection Reliability Requirements for Large Loads \n(the \"IRR Proposal\") in Docket No. ER26-3650-000. Rowan supports MISO's objective of reliably \nintegrating large loads and requests targeted revisions to ensure that the obligations are clear, \nworkable, and predictable, appropriately aligned with operational control, and supported by \ntransparent compliance standards. \nI.  COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL \nProposed Section 37A makes the Transmission Customer responsible for compliance. \nCompliance responsibility should be assigned to the entity that owns, operates, or controls the \nequipment, information, or operating function at issue. A Transmission Customer should not be held \nresponsible or subject to enforcement for a function controlled by MISO, a Transmission Owner, or \nanother entity, particularly where the Transmission Customer lacks the contractual or operational \nauthority necessary to perform that function. \nFor Phasor Measurement Unit (“PMU”) equipment, proposed Section 37A.5 requires \ninstallation by the Transmission Owner on its side of the Point of Withdrawal, at the Transmission \nCustomer’s expense; the equipment becomes part of the Transmission Owner’s interconnection \nfacilities, and the Transmission Owner provides the measurements to MISO. MISO should clarify that \nPMU siting, quantity, installation, testing, maintenance, operation, and data delivery are the \nTransmission Owner’s responsibilities, with cost responsibility addressed separately and any \nTransmission Customer costs limited to documented, reasonable costs directly attributable to the PMU \nfacilities necessary to serve the applicable Large Load. \nII.  MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS \nProposed Section 37A.2 requires verified electrical models and detailed Load profiles. MISO \nshould identify with specificity the required load-flow and stability models customarily provided \nthrough interconnection studies, any additional model types, and the scope, format, granularity, and \ntiming of any required detailed Load profiles, and should avoid duplicative submissions. The Tariff \nshould also identify the applicable validation standard and distinguish information reasonably available \nto the Transmission Customer from information controlled by customers, equipment manufacturers, or \nother third parties.  \nMISO should also define “material modifications,” using objective, reliability-based criteria, \nestablish specified and commercially reasonable review timelines, and limit prior approval to changes \nthat are reasonably expected to materially affect Transmission System reliability. Routine maintenance, \nlike-kind equipment replacement, and technology refreshes without such an effect should not be \ndelayed or subjected to prior approval. At a minimum, the Tariff should provide an expedited review \nprocess and require MISO to identify the specific reliability concern supporting any denial or request \nfor additional information."},{"page":2,"startToken":462,"endToken":988,"text":"2 \nIII.  FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION \nProposed Section 37A.4 requires day-ahead and real-time Load Forecasts by the later of the \nService Commencement Date or September 1, 2027. New and expanding facilities may lack \nrepresentative operating history, and profiles may depend on tenant deployment, customer controlled \noperating decisions, and phased energization. \nMISO should permit after-the-fact reporting where it satisfies the demonstrated reliability need. \nIf prospective forecasts are required, MISO should define the required forecast horizon, data format, \nsubmission and accuracy standards, provide reasonable safe harbors during commissioning and phased \nenergization, defer representative Load-profile requirements until sufficient operating history exists, \nand protect detailed operating data from unnecessary disclosure and limit its use to legitimate reliability \npurposes. Forecast accuracy should be evaluated in light of the information reasonably available to the \nTransmission Customer when the forecast is submitted, and good-faith forecast deviations should not \nconstitute a violation if the Transmission Customer used the applicable forecasting methodology and \nthe information reasonably available at the time. \nIV.  RAMP REQUIREMENTS NEED A CLEAR BASIS AND SHOULD RECOGNIZE NET RAMP-\nSMOOTHING \nProposed Section 37A.7 applies ramp limits during stable-state transitions, measured in \naggregate across applicable Points of Withdrawal, and allows eligible generation or other resources to \nprovide ramp smoothing. MISO proposes initial limits of 30 MW per minute. \nMISO should provide the technical and reliability basis for the proposed ramp limits and specify \nthe applicable measurement methodology, including the measurement interval, treatment of \nmeasurement error, aggregation methodology, the circumstances constituting a stable state transition, \nand how local planning criteria will be considered. MISO should also confirm that onsite battery energy \nstorage and other qualifying resources may provide ramp smoothing and that compliance will be \nassessed on a net basis at the applicable Points of Withdrawal. Any site-specific limit should be based \non documented system conditions, provided to the affected Transmission Customer with the supporting \nbasis before it becomes enforceable, and accompanied by a reasonable implementation period. \nV.  RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES \nProposed Section 37A.6 requires Computational Load to remain connected during voltage and \nfrequency disturbances within criteria established in the Business Practice Manual. MISO should place \nall material and operative performance criteria, measurement standards, exceptions, and compliance \npathways in the Tariff or otherwise subject them to Commission review before they become \nenforceable. The Tariff should not permit a Business Practice Manual to create or materially expand a \nTransmission Customer's substantive compliance obligations. \nMISO should explain how ride-through requirements will coordinate with approved under-\nvoltage and under-frequency load-shedding schemes, equipment protection settings, Transmission \nOwner requirements, and other applicable reliability obligations. The framework should not require a \nComputational Load to remain connected when shedding under an applicable protection scheme is the \nreliability-supporting response, and compliance with an approved or required protection scheme should \nnot constitute a violation of Section 37A.6. \nVI.  TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE \nThe proposal fully exempts the portion of a Large Load with a Service Commencement Date \non or before December 4, 2026. Loads meeting the MISO Transmission Expansion Plan/Expedited \nProject Review (“MTEP/EPR”) Condition remain subject to Sections 37A.1 through 37A.5 and 37A.8"},{"page":3,"startToken":988,"endToken":1223,"text":"3 \nbut are exempt from Sections 37A.6 and 37A.7. Certain projects submitted for Expedited Project \nReview from June 19 through October 31, 2026, may receive a waiver from Section 37A.6. \nTransition relief should also account for objective evidence of project maturity, reasonable \nreliance, and binding commitments made before the Tariff’s effective date, including executed \ninterconnection, energy service, or transmission service agreements, material equipment procurement \ncommitments, completed engineering, and construction activities. Eligibility should not turn solely on \nmilestones controlled by a utility, MISO, or transmission provider, or on the timing of a third party's \nprocessing or approval. The Tariff should identify the required waiver documentation, an objective \nstandard for approval, commercially reasonable review timelines, and written decision criteria. MISO \nshould also provide relief where compliance would require material redesign, replacement of \npreviously procured equipment, or impairment of binding pre-effective date commitments without a \ndemonstrated reliability necessity. \nVII.  CONCLUSION \nRowan respectfully requests that the Commission accept the IRR Proposal only subject to the \ntargeted revisions described above, including revisions necessary to align compliance responsibility \nwith operational control, establish objective and transparent compliance standards, coordinate \npotentially conflicting reliability requirements, and provide reasonable transition relief for projects \nundertaken in reliance on the existing framework. \n \nRespectfully submitted, \nROWAN DIGITAL INFRASTRUCTURE, LLC \n/s/ Tyler Petersen  \nTyler Petersen  \nDirector, Regulatory Affairs and Public Policy \n1400 16th Street, Suite 330 \nDenver, Colorado 80202 \ntpetersen@rowan.digital \nDated: September 18, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":898,"startToken":0,"endToken":119},{"p":1,"at":898,"title":"I. COMPLIANCE RESPONSIBILITY SHOULD ALIGN WITH OPERATIONAL CONTROL","method":"printed heading","endPage":1,"endAt":2213,"startToken":119,"endToken":293},{"p":1,"at":2213,"title":"II. MISO SHOULD CLARIFY MODELING AND MODIFICATION REQUIREMENTS","method":"printed heading","endPage":2,"endAt":3,"startToken":293,"endToken":463},{"p":2,"at":3,"title":"III. FORECASTING REQUIREMENTS SHOULD REFLECT AVAILABLE OPERATING INFORMATION","method":"printed heading","endPage":2,"endAt":1283,"startToken":463,"endToken":627},{"p":2,"at":1283,"title":"IV. RAMP REQUIREMENTS NEED A CLEAR BASIS AND SHOULD RECOGNIZE NET RAMP-","method":"printed heading","endPage":2,"endAt":2425,"startToken":627,"endToken":786},{"p":2,"at":2425,"title":"V. RIDE-THROUGH REQUIREMENTS SHOULD COORDINATE WITH EXISTING PROTECTION SCHEMES","method":"printed heading","endPage":2,"endAt":3588,"startToken":786,"endToken":934},{"p":2,"at":3588,"title":"VI. TRANSITION RELIEF SHOULD REFLECT ACTUAL PROJECT RELIANCE","method":"printed heading","endPage":3,"endAt":1116,"startToken":934,"endToken":1136},{"p":3,"at":1116,"title":"VII. CONCLUSION","method":"printed heading","endPage":3,"endAt":1832,"startToken":1136,"endToken":1223}]}