{"document":{"slug":"rec-20260922-5110","title":"Motion for Leave to Answer and Answer of Indicated PJM Transmission Owners to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. filed…","issued":"2026-09-22","accession":"20260922-5110","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"American Transmission Systems, Inc.Mid-Atlantic Interstate Transmission, LLCTrans-Allegheny Interstate Line Company ,Keystone Appalachian Transmission Company ,Jersey Central Power & Light ,Potomac Edison Company ,Duquesne Light Company ,Monongahela Power Company ,","kind":"answer","file":"sources/filings/text/20260922-5110_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260922-5110","tier":"record","sha256":"5dc0cd41282d1e5bf26d6fe3a1fc91f0d5d73abc08497673e40e9b82a4647138","pages":5,"tokens":1018,"emptyPages":[],"textThemes":["credit"]},"pages":[{"page":1,"startToken":0,"endToken":234,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n  \n \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \nDocket No. ER26-3380-000 \nINDICATED PJM TRANSMISSION OWNERS’ MOTION FOR LEAVE TO \nANSWER AND ANSWER TO THE ANSWER OF PJM INTERCONNECTION, \nL.L.C. \nPursuant to Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure,1 the \nIndicated PJM Transmission Owners2 respectfully move for leave to submit this answer in \nresponse to the answer of PJM Interconnection, L.L.C. (“PJM”) filed on September 10, 2026.3   \nThis proposed answer addresses a narrow but important issue:  whether it violates cost-\ncausation principles to impose new exit fees related to a generation/capacity product on a \ntransmission owner (“TO”) as opposed to a load-serving entity (“LSE”).  PJM’s answer does \nnot confront that issue or the arguments raised by the Indicated PJM Transmission Owners in \ntheir initial protest in the instant proceeding.  PJM does, however, concede that the cause of \n \n1 18 C.F.R. § 385.213(a)(2) (2026). \n2 The Indicated PJM Transmission Owners are American Transmission Systems, Inc., Mid-Atlantic \nInterstate Transmission, LLC, Trans-Allegheny Interstate Line Company, Keystone Appalachian \nTransmission Company, Jersey Central Power & Light Company, Monongahela Power Company, and \nThe Potomac Edison Company (collectively, “The FirstEnergy Transmission Companies”), and \nDuquesne Light Company.   \n3   See Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-\n3380-000 (Sept. 10, 2026) (“PJM Answer”)."},{"page":2,"startToken":234,"endToken":517,"text":"2 \nthe Reliability Backstop Procurement (“RBP”) is loads (served by LSEs).4  And, thus, any and \nall costs associated with the RBP must be borne by LSEs, and not TOs.   \nAccordingly, the Commission should not allow the RBP to go into effect without \nremoving its Exit Amendment that imposes exit fees on TOs. \nI. \nMOTION FOR LEAVE TO ANSWER \nJust as the Commission’s rules do not permit as of right PJM’s proposed answer to the \nvarious protests in this Docket, they do not permit as of right the Indicated PJM Transmission \nOwners’ proposed answer to PJM’s proposed answer.5  The Commission nonetheless retains \nauthority to permit such an answer in its discretion.  The Commission should do so here \nbecause the Indicated PJM Transmission Owners’ proposed answer highlights an important \nconcession in PJM’s proposed answer that bears on cost-causation principles that PJM \notherwise does not address. \nII. \nPROPOSED ANSWER \nThe Indicated PJM Transmission Owners’ protest explained that, under cost-causation \nprinciples and the Commission’s precedent applying them, RBP-related exit fees cannot be \nimposed on TOs as opposed to LSEs:  “The Commission has never allocated generation- and \ncapacity-related costs to TOs and, more specifically, the Exit Amendment [of the RBP] \nconflicts with highly relevant precedent in the Duquesne Light Co. proceeding where the \n \n4 PJM Answer at 86 (“Given that the RBP is to address the capacity shortfall from the 2027/2028 and \n2028/2029 RPM Auctions, which is primarily driven by the unprecedented addition of large loads (in \nthe form of Load Adjustments), the loads causing the RBP—through their LSEs—should bear the costs \nof the RBP Resources throughout the full term.”) (emphasis added). \n5   See 18 C.F.R. § 385.213(a)(2)."},{"page":3,"startToken":517,"endToken":839,"text":"3 \nCommission notably did not apply generation-related costs to an exiting TO in its capacity as \na TO,” but only in its capacity as an LSE.6 \nPJM’s answer does not address this argument or the relevant portion of Duquesne Light \nCompany.7  It does, however, concede that loads and LSEs are the causes of the RBP:  “Given \nthat the RBP is to address the capacity shortfall from the 2027/2028 and 2028/2029 RPM \nAuctions, which is primarily driven by the unprecedented addition of large loads (in the form \nof Load Adjustments), the loads causing the RBP—through their LSEs—should bear the costs \nof the RBP Resources throughout the full term.”8 (emphasis added).     \nPJM does not and cannot explain how it is consistent with Duquesne Light Company \nand cost-causation principles to impose RBP exit fees on a TO as opposed to an LSE.  At a \nminimum, therefore, even if all of the RBP’s other deficiencies could be overlooked, the \nCommission should strip out the exit fee provision before the RBP is allowed to go into effect.   \nIII. \nCONCLUSION \n \nFor the foregoing reasons, the Indicated PJM Transmission Owners respectfully \nrequest that the Commission accept this answer and reject PJM’s proposed Exit Amendment.  \nDated:  September 22, 2026 \nRespectfully submitted, \n/s/ Evan K. Dean \n \n \n \nEvan K. Dean \nManaging Counsel, Transmission Rates & \nServices \nFirstEnergy Service Company \n341 White Pond Drive \nAkron, Ohio 44320 \n/s/ Sanford I. Weisburst \n \n \nSanford I. Weisburst \nMatthew Meyer \nMadeleine Fleming \nQUINN EMANUEL URQUHART \n& SULLIVAN, LLP \n295 Fifth Avenue, Ninth Floor \n \n6   See Protest of the Indicated PJM Transmission Owners at 2 & n.3, Docket No. ER26-3380-000 (Aug. \n21, 2026) (citing Duquesne Light Co., 122 FERC ¶ 61,039 (2008)); see also id. at 8-10. \n7   See PJM Answer at 103-04 (referring interchangeably to an “LSE” and “Transmission Owner” and \nfailing to distinguish between the two for purposes of responsibility for generation/capacity-related \ncosts). \n8   PJM Answer at 86 (emphasis added)."},{"page":4,"startToken":839,"endToken":932,"text":"4 \nTelephone: 330-620-9585 \nedean@firstenergycorp.com \nNew York, New York 10016 \nTelephone: 212-849-7000 \nFacsimile: 212-849-7100 \nsandyweisburst@quinnemanuel.com \nmatthewmeyer@quinnemanuel.com \nmadeleinefleming@quinnemanuel.com \n \n/s/ Anthony Alden \n \n \n \nAnthony Alden \nQUINN EMANUEL URQUHART  \n & SULLIVAN, LLP  \n865 S Figueroa St, 10th Floor \nLos Angeles, CA 90017 \nTelephone: 213-443-3000 \nanthonyalden@quinnemanuel.com \nCounsel for the FirstEnergy Transmission Companies \n \n \n/s/ Michael Brechlin  \n \n \nMichael Brechlin  \nManager Asst GC - Regulatory Law State \nRegulatory \nDuquesne Light Company  \nNova Place \n100 South Commons, Suite 118 \nMail Drop OGC-L1 \nPittsburgh, PA 15212 \nTelephone: 412-393-6431 \nmbrechlin@duqlight.com \n \n \nCounsel for Duquesne Light Company"},{"page":5,"startToken":932,"endToken":1018,"text":"5 \nCERTIFICATE OF SERVICE \n \n \nI hereby certify that I have served the foregoing document upon all parties listed on the \nofficial service list for the captioned proceeding in accordance with Rule 2010 of the \nCommission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \nDated at New York, NY, this 22nd day of September, 2026. \n \n/s/ Sanford I. Weisburst \nSanford I. Weisburst \nQUINN EMANUEL URQUHART \n& SULLIVAN, LLP \n295 Fifth Avenue, Ninth Floor \nNew York, New York 10016 \nTelephone: 212-849-7000 \nFacsimile: 212-849-7100 \nsandyweisburst@quinnemanuel.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":310,"startToken":0,"endToken":287},{"p":2,"at":310,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":905,"startToken":287,"endToken":379},{"p":2,"at":905,"title":"II. PROPOSED ANSWER","method":"printed heading","endPage":3,"endAt":1030,"startToken":379,"endToken":696},{"p":3,"at":1030,"title":"III. CONCLUSION","method":"printed heading","endPage":5,"endAt":3,"startToken":696,"endToken":933},{"p":5,"at":3,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":5,"endAt":566,"startToken":933,"endToken":1018}]}