{"document":{"slug":"rec-20260923-5060","title":"Motion for Leave to Answer and Limited Answer of FirstEnergy Service Company to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.…","issued":"2026-09-23","accession":"20260923-5060","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"FirstEnergy Service Company","kind":"answer","file":"sources/filings/text/20260923-5060_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260923-5060","tier":"record","sha256":"166116e587d028a9c22b2085763af4af1373d03cf338e09a50ebbe8c9ce63f5d","pages":4,"tokens":756,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":386,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION  \n \nPJM Interconnection, L.L.C.  \n \n) \n \nDocket No. ER26-3380-000 \n \n \nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF  \nFIRSTENERGY SERVICE COMPANY \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 FirstEnergy Service Company \n(“FirstEnergy”) respectfully files this Limited Answer in response to the answer to comments and \nprotests submitted by PJM Interconnection, L.L.C. (“PJM”) on September 10, 2026 (the \n“September 10 PJM Answer”), in this proceeding on PJM’s proposal to establish a Reliability \nBackstop Procurement (“RBP”) mechanism.2 \nI. \nAnswer \nAlthough the September 10 PJM Answer purports to respond to the points made in the \nAugust 21 FirstEnergy Comments and Protest,3 PJM fails to advance facts or law that satisfy its \nburden of proof under section 205 of the Federal Power Act (the “FPA”) to demonstrate that the \nJuly 31 RBP Proposal is just and reasonable.4  As explained in the August 21 FirstEnergy \n \n1  \n18 C.F.R. §§ 385.212, 385.213. \n2  \nPJM Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large \nLoads, Docket No. ER26-3380-000 (the “July 31 RBP Proposal”).  On August 20, 2026 FirstEnergy filed, as agent \nfor its franchised public utility and transmission-owning public utility affiliates, a motion to intervene in this \nproceeding.  On August 21, 2026, FirstEnergy filed comments and a protest regarding the July 31 RBP Proposal (the \n“August 21 FirstEnergy Comments and Protest”). \nFirstEnergy respectfully requests waiver of Rule 213(a)(2), 18 C.F.R. § 385.213(a)(2), to permit it to file this \nLimited Answer to the September 10 PJM Answer.  Good cause for the waiver exists because this limited answer will \naid the Commission in understanding the issues in the proceeding, inform the Commission in its decision-making \nprocess, and help to ensure a complete and accurate record in the case.  See, e.g., PJM Interconnection, L.L.C., 187 \nFERC ¶ 61,173, at P 25 (2024); Constellation Mystic Power, LLC, 185 FERC ¶ 61,016, at P 14 (2023); ISO New Eng. \nInc., 175 FERC ¶ 61,172, at P 15 (2021). \n3  \nSee September 10 PJM Answer at 59, 63-67, 74-76, 79-82, 88, 89 n.271. \n4  \nSee August 21 FirstEnergy Comments and Protest at 1-2."},{"page":2,"startToken":386,"endToken":600,"text":"2 \nComments and Protest, there are a number of ways in which PJM has not met its burden of proof.5  \nThe September 10 PJM Answer does not repair those defects.  Among other deficiencies, PJM’s \nanswer fails to explain or address how its proposal could possibly be just and reasonable if it does \nnot actually allocate RBP-related costs to the new data centers driving the need for such capacity, \nin accordance with the NEDC/PJM Governors’ Statement of Principles that underlies the RBP \nproposal.6 \nAccordingly, FirstEnergy reiterates that the Commission grant the relief requested in the \nAugust 21 FirstEnergy Comments and Protest:  the Commission should reject the July 31 RBP \nProposal, institute a proceeding under section 206 of the FPA, and establish settlement \nproceedings.7  Alternatively, even if the Commission were to accept the July 31 RBP Proposal for \nfiling, such acceptance should be conditioned on PJM submitting a subsequent compliance filing \nthat addresses the issues raised in the August 21 FirstEnergy Comments and Protest. \n \n \n \n \n \n \n \n \n \n5  \nId. at 2-22. \n6  \nSeptember 10 PJM Answer at 63-65 (arguing that it is “fallacious” to suggest that a just and reasonable cost \nallocation must be targeted to the new data centers driving the need for the RBP).  \n7  \nAugust 21 FirstEnergy Comments and Protest at 22."},{"page":3,"startToken":600,"endToken":689,"text":"3 \nII. \nConclusion \nFor the foregoing reasons and the reasons explained in the August 21 FirstEnergy \nComments and Protest, FirstEnergy respectfully requests that the Commission grant the relief \nrequested herein. \n \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \n \n \n/s/ Michael Kunselman \nMorgan E. Parke \n \n \n \n \nMichael Kunselman \nVice President, Associate General Counsel  \nBradley Miliauskas \nFirstEnergy Service Company \n \n \nDavis Wright Tremaine LLP  \n \n341 White Pond Drive \n \n \n \n1301 K Street, NW \nAkron, OH 44320 \n \n \n \n \nSuite 500 East \nTel: (330) 620-9585  \n \n \n \nWashington, DC 20005 \nmparke@firstenergycorp.com \n \n \nTel: (202) 973-4295 \n \n \n \n \n \n \n \nmichaelkunselman@dwt.com  \n \n \n \n \n \n \n \nbradleymiliauskas@dwt.com \n   \n  \nSeptember 23, 2026"},{"page":4,"startToken":689,"endToken":756,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day served the foregoing documents upon each person \ndesignated on the official service lists compiled by the Secretary in the above-captioned \nproceeding. \nDated at Washington, DC this 23rd day of September, 2026. \n/s/ Deiman Flores  \nDeiman Flores \nDavis Wright Tremaine LLP \n1301 K Street, NW \nSuite 500 East \nWashington, DC 20005 \n212.402.4037 \ndeimanflores@dwt.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":721,"startToken":0,"endToken":104},{"p":1,"at":721,"title":"I. Answer","method":"printed heading","endPage":3,"endAt":3,"startToken":104,"endToken":601},{"p":3,"at":3,"title":"II. Conclusion","method":"printed heading","endPage":4,"endAt":0,"startToken":601,"endToken":689},{"p":4,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":4,"endAt":426,"startToken":689,"endToken":756}]}