{"document":{"slug":"rec-20260923-5140","title":"Motion for Leave to Answer and Answer of American Transmission Company LLC to the Comments and Protests filed by Midcontinent Independent System Operator,…","issued":"2026-09-23","accession":"20260923-5140","docket":"ER26-3531-000","group":"ATC large-load planning revisions (Attachment FF-ATCLLC)","filer":"American Transmission Company LLC (ATC)","kind":"protest","file":"sources/filings/text/20260923-5140_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260923-5140","tier":"record","sha256":"8df4a6d529fbdc08a97ead70b06d9336332b8f854675d5c8f88c3b3f8a83f5d4","pages":17,"tokens":4945,"emptyPages":[],"textThemes":["cost","study","retail"]},"pages":[{"page":1,"startToken":0,"endToken":249,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nAmerican Transmission Company LLC \n \n \n          Docket No. ER26-3531-000 \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nAMERICAN TRANSMISSION COMPANY LLC \n \n \nPursuant to Sections 212 and 213 of the Commission’s Rules of Practice and Procedure,1 \nAmerican Transmission Company LLC  by its corporate manager, ATC Management Inc. \n(collectively, ATC) hereby files this Motion for Leave to Answer and Answer to the Comments \nand Protests filed by the Midcontinent Independent System Operator, Inc. (MISO) and Microsoft \nCorporation (Microsoft).2  On August 17, 2026, ATC filed its proposed revisions to Attachment \nFF-ATCLLC of MISO’s Open Access  Transmission, Energy and Operating Reserve Markets \nTariff (Tariff) in response to the Commission’s Show Cause Order.3  In this Answer, ATC (1) \nproposes modifications to its Attachment FF-ATCLLC in response to MISO’s operational \nconcerns, and (2) responds to other comments on ATC’s planning process, cost allocation and the \nproposed template large load agreements.  ATC’s proposed revisions address the immediate need \nfor large load integration in the ATC service territory and are just and reasonable and should be \naccepted by the Commission without hearing or settlement proceedings with an effective date of \nOctober 17, 2026.  \n \n1 18 C.F.R. § 385.212-213 (2026). \n2 Comments and Protest of the Midcontinent Independent System Operator, Inc. (MISO Protest) and \nProtest of Microsoft Corporation (Microsoft Protest).  \n3 Midcontinent Indep. System Op., Inc., Order Instituting Proceeding Under Section 206 of the Federal \nPower Act, 195 FERC ¶ 61,212 (2026) (Show Cause Order)."},{"page":2,"startToken":249,"endToken":532,"text":"2 \n \nI. \nSUMMARY OF ANSWER \nFor nearly two decades, ATC has operated under its own local planning rules that are \nincorporated in the MISO Tariff.  Among other things, Attachment FF-ATCLLC currently \ngoverns load interconnections to the ATC transmission system.  ATC studies load interconnection \nrequests, determines what facilities are needed and then feeds the study results and proposed \ntransmission facilities to MISO for evaluation in the regional planning process for inclusion in \nthe MISO Transmission Expansion Plan (MTEP) through the regular annual process or the \nExpedited Project Review (EPR) process.  ATC’s Commission-approved local planning process \nhas worked without issue since it was approved.  ATC’s proposed revisions to Attachment FF-\nATCLLC are intended to codify and reflect the processes that ATC follows today with respect to \nmanaging the challenges of large load interconnections and other revisions that reflect new, \nproposed practices to comply with the Show Cause Order.  \nSince the Commission approved ATC’s transmission planning process in Attachment FF-\nATCLLC under Order No. 890, ATC has revised that process to comply with Order No. 1000 and \nother transmission planning-related reforms issued by the Commission – all of which \ncomplement MISO’s regional planning process.  ATC’s proposed revisions in this docket are no \ndifferent: they update the local planning process per the Commission’s direction.  In ATC’s view, \nthe Show Cause Order builds on the Commission’s previously approved local planning \nframework by requiring updates to meet the specified requirements. \nATC began receiving requests in 2023 from the Local Distribution Companies (LDCs) \nconnected to its transmission system requesting studies for large load interconnections.  ATC \nresponded to concerns about cost allocation and transparency related to large loads by \ndeveloping the processes reflected in the proposed revisions to Attachment FF-ATCLLC.  As the"},{"page":3,"startToken":532,"endToken":809,"text":"3 \n \nCommission noted in the Show Cause Order, ATC’s Attachment FF-ATCLLC includes an \napproved distribution-to-transmission interconnection process and a load interconnection \nprocedure, but it does not have procedures specific to large loads.4  ATC’s proposed revisions in \nthis filing are intended to fill that gap and are tailored to work within the established Attachment \nFF-ATCLLC procedures.  In sum, ATC’s proposal here is intended to formalize what ATC is \nalready doing in its footprint to manage the challenges of large load integration and add new \npractices that build upon ATC’s long-standing local planning processes.  \nNevertheless, ATC recognizes MISO’s need for regional visibility into, and operational \nauthority over, loads of 50 MW or more.  As discussed below, ATC proposes targeted revisions to \nAttachment FF-ATCLLC to address MISO’s concerns and eliminate any perceived operational \ngaps.  ATC will modify its Large Load definition threshold to 50 MW as follows: \n• ATC’s large load criteria will apply within the ATC footprint.  Large loads over 50 \nMW connecting to ATC’s system will be required to comply with MISO’s IRR \nrequirements when they become effective if ATC does not have applicable criteria on \na given topic.   \n• ATC will modify Attachment FF-ATCLLC and any related business practices to \nensure that ATC’s large load planning and interconnection criteria will apply to all \nLarge Loads over 50 MW. \n• For Large Loads over 50 MW, ATC will distinguish between computational loads and \nother large loads for power factor and other requirements as deemed necessary by ATC. \nFor cost allocation purposes, ATC will maintain the 100 MW threshold for application of \nATC’s proposed Large Load Project Commitment Agreement (LLPCA) and Minimum \n \n4  Show Cause Order at P 21, n. 75."},{"page":4,"startToken":809,"endToken":1149,"text":"4 \n \nTransmission Charge Agreement (MTCA).  The 100 MW threshold is important for cost \nallocation purposes to coincide with the Public Service Commission of Wisconsin’s (PSCW) \nestablished 100 MW threshold for large load tariffs to avoid stranded costs to ATC’s \ninterconnected LDCs.  If ATC is required to lower its threshold to 50 MW for cost allocation \npurposes, LDCs with large load tariffs in ATC’s footprint will be unable to directly assign the \nlarge load upgrade costs to the particular large loads causing those costs to be incurred.  As a \nresult, any upgrade costs for large loads between 50 and 100 MW would be spread to the LDC’s \nother customers.  \nIf these modifications are acceptable, ATC requests that the Commission issue an order \naccepting the Attachment FF-ATCLLC filing on the condition that ATC submit a compliance \nfiling implementing the proposed changes above within 30 days.   \nThe remainder of ATC’s Attachment FF-ATCLLC revisions should be accepted as just \nand reasonable.  ATC’s template large load agreements (LLPCAs and MTCAs) will be posted on \nATC’s website.  While ATC is not requesting approval of these template agreements as pro forma \nagreements, they nevertheless provide consistency and allow flexibility for large load customers.  \nAs mentioned previously, Attachment FF-ATCLLC was developed and approved in a series of \nplanning orders, as meeting Order 890’s5 transmission planning process and Order 1000’s \nrequirements.6  ATC’s proposed changes are consistent with Order No. 890 principles.  Finally, \nthere are no material issues of fact that warrant hearing and settlement procedures \n \n5 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, FERC Stats. \n& Regs. ¶ 31,241, order on reh’g, Order No. 890-A, FERC Stats. & Regs. ¶ 31,261 (2007), order on \nreh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ \n61,228 (2009), order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009). \n6 Midwest Indep. Transmission Sys. Operator, Inc., 147 FERC ¶ 61,127 at P 76 (2014) (Order 1000 \nCompliance Rehearing Order); Midwest Indep. Transmission Sys. Operator, Inc., 130 FERC ¶ 61,232, at"},{"page":5,"startToken":1149,"endToken":1471,"text":"5 \n \nII. \nMOTION FOR LEAVE TO ANSWER \nTo the extent required, ATC respectfully requests leave to submit this Answer.  The \nCommission’s Rules of Practice and Procedure prohibit answers to protests unless otherwise \nauthorized.7  The Commission regularly allows answers for good cause shown, such as when the \nanswers help ensure a more accurate and complete record, clarify the issues, or provide useful \nand relevant information that will assist the Commission in its deliberative process.8  ATC’s \nAnswer will clarify the record and ensure a more accurate and complete record.  Because this \ninformation will assist the Commission in its decision-making, ATC respectfully requests that the \nCommission accept this Answer for good cause shown. \nIII. \nANSWER \nA. \nATC’s Proposed Attachment FF-ATCLLC Revisions Address the Immediate \nNeed for Large Load Integration in ATC’s Footprint.  \n \nATC appreciates the potential complexity caused by the misalignment in the Show Cause \nOrder compliance schedules of ATC and MISO.  MISO’s compliance processes are working their \nway through the stakeholder process. Once filed, MISO’s proposed compliance filing could take \nmany months to finalize with follow-up compliance filings and potential challenges.  Given that \ntransmission owners in the MISO Region have their own local planning process (even though \nthey are not included in the MISO Tariff), existing practices may vary greatly across the region.  \n \nP 36, on reh’g, 132 FERC ¶ 61,119, PP 20-22 (2010); Midwest Indep. Transmission Sys. Operator, Inc., \n123 FERC ¶ 61,165 (2008), order on reh’g, 127 FERC ¶ 61,169 (2009).  \n7 18 C.F.R. § 385.213(a)(2). \n8 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 at P 24 (2025) (accepting answers \nto answers “because they have provided information that assisted us in our decision-making process”); \nTexas Eastern Transmission, LP, 122 FERC ¶ 61,205 at P 8 (2008) (accepting answer that completed the \nrecord); California Indep. Operator Corp., 105 FERC ¶ 61,284 at P 10 (2003) (accepting ISO’s answer \nthat clarified the issues)."},{"page":6,"startToken":1471,"endToken":1781,"text":"6 \n \nThus, any consensus proposal that MISO develops may necessarily be at a high level, with room \nfor individual variation.  It could be well into 2027 before any MISO-wide large load rules are in \neffect.  ATC’s proposed revisions provide an immediately implementable path forward, \nconsistent with ATC’s current practices, offering certainty for large-load projects already \nunderway in ATC’s footprint and establishing urgently needed protections against cost shifting.   \nATC has already committed to adjusting its processes, if necessary, through its Business \nPractices or otherwise, as MISO’s requirements develop through the stakeholder process.  MISO \nsuggests that ATC should defer its proposal because it may conflict with MISO’s future \ncompliance filing.  ATC is participating in the stakeholder process for developing MISO’s \nregion-wide Show Cause Order compliance filing and intends that ATC’s processes will continue \nto work with MISO’s planning processes similar to how ATC’s Attachment FF-ATCLLC works \nwith MISO’s Attachment FF today.  A direct conflict is even less likely after the changes ATC is \nproposing in Section C, below.  However, if a direct conflict arises, ATC will work with MISO to \nresolve it.  Implementing ATC’s revisions on October 17, 2026 will provide timely clarity and \ncertainty while advancing changes  that are independently just and reasonable and responsive to \nthe Show Cause Order.   \nB. \nUniform Rules Across the MISO Region May Be Unjust and Unreasonable if \nThey Impose Unnecessary Burdens or Conflict with State Requirements. \n \nConsistent with Wisconsin state law, local planning is a core function of ATC’s \noperations.  ATC’s own robust local planning process has worked collaboratively within MISO’s \nregional planning umbrella for nearly two decades.  Nothing in ATC’s proposed changes to \nAttachment FF-ATCLLC is intended to change that collaborative framework.  For nearly three \nyears, ATC’s studies and reliability analyses have determined that the appropriate threshold for \ncategorizing large loads in ATC’s footprint should be 200 MW.  That threshold has thus far not"},{"page":7,"startToken":1781,"endToken":2053,"text":"7 \n \nresulted in any reliability or instability issues to date.  In light of the current development efforts \nand the PSCW actions to date, ATC determined that 100 MW would strike the right balance \nbetween state cost allocation determinations and maintaining system reliability in ATC’s \nfootprint.   \nA single set of uniform rules for the entire MISO region9 will necessarily have to reflect a \nbroadly applicable regional baseline, which could impose unduly burdensome requirements in \nATC’s footprint.  Each new large load presents its own unique characteristics, and ATC’s system \nis uniquely situated among the Great Lakes and the Mississippi River.  Load interconnections are \ndynamic and reliability issues can be highly technical; a one-size-fits-all approach can result in \nunnecessarily onerous requirements and costly equipment specifications.  ATC has confronted \nthe challenges posed by large loads, studied them, and developed workable, proven \nrequirements.  ATC engaged specialized power system consultants to study large loads, including \nflicker analyses, rotor-swing modes, generator-shaft studies to develop ramp-rate, oscillation, \nand voltage-ride-through requirements.  The Commission should give due weight to ATC’s \npreparedness and should not disadvantage ATC for advancing proven large load processes \ndeveloped over the past several years and submitting them within the Show Cause Order’s \noriginal timeframe. \nATC disagrees with MISO’s assertion that ATC’s large load processes would produce \n“unjust and unexpected outcomes” for large loads.  Rather, requiring ATC to alter its existing \npractices – particularly for large load projects already underway in its footprint – would itself \nproduce an unjust result.  This does not mean that ATC’s processes will remain static.  ATC has \ncontinually reassessed them and will continue to do so in light of MISO’s forthcoming \n \n9 MISO Protest at 6."},{"page":8,"startToken":2053,"endToken":2305,"text":"8 \n \ncompliance filing and the new NERC Reliability Standards under development.  No reliability \ngaps will arise because the NERC Reliability Standards will soon apply to all large loads, \nincluding those in ATC’s footprint. \nC. \nATC’s Proposed Modifications Will Address MISO’s Operational Concerns. \nMISO suggests there will be practical implementation problems if it is unclear how ATC's \nseparate application, study, and agreement processes would interface with MISO's own \ntransmission service and Large Load Section 205 filings currently in development.  MISO asks \nthe Commission to direct ATC to file revised tariff sheets that “adopt or integrate with” MISO’s \nlarge load rules and remove redundant processes.   \nATC recognizes MISO’s concerns and agrees to modify its Attachment FF-ATCLLC \nproposal in certain respects to eliminate any perceived operational gaps that could arise for loads \nbetween 50 and 100 MW.  ATC will agree to modify its Large Load definition threshold to 50 \nMW for certain operational processes as follows: \n• ATC’s large load criteria will apply within the ATC footprint.  Large loads over 50 \nMW connecting to ATC’s system will be required to comply with MISO’s IRR \nrequirements when they become effective if ATC does not have applicable criteria on \na given topic.  \n• ATC will modify Attachment FF-ATCLLC and any related business practices to \nensure that ATC’s large load planning and interconnection criteria will apply to all \nLarge Loads over 50 MW.  As described above and in the filing letter, ATC’s planning \nand interconnection criteria is study-based and tailored to ATC’s footprint.10  MISO’s \n \n10 Transmittal Letter at 4."},{"page":9,"startToken":2305,"endToken":2601,"text":"9 \n \nproposed 50 MW threshold is based on the threshold suggested in the Show Cause \nOrder and is not based on studies specific to the MISO region.  \n• For Large Loads over 50 MW, ATC will distinguish between computational loads and \nother large loads for power factor and other requirements as deemed necessary by \nATC. \nIf the Commission accepts these modifications, ATC requests that the Commission issue \nan order accepting the Attachment FF-ATCLLC filing on the condition that ATC submit a \ncompliance filing with revised tariff sheets implementing the proposed changes above within 30 \ndays.   \nATC’s proposed revisions to Attachment FF-ATCLLC describe processes that are \ndesigned to work together with MISO’s process in the same way ATC’s local planning process in \nAttachment FF-ATCLLC works with the annual MTEP process today.  ATC’s application process \nand studies of all distribution interconnections, including large load interconnections, \ncontemplates close coordination with MISO.  ATC works closely with MISO to provide it with \nall necessary information so that the interconnection can be integrated into the annual MTEP, \nwhich may include on an as needed basis, review and approval on an expedited timeline through \nMISO’s EPR process.  Moreover, NERC’s new large load Reliability Standards will soon be \napplicable to all large loads, including those in ATC’s footprint.  Upon Commission acceptance \nof these changes to Attachment FF-ATCLLC, ATC will continue to coordinate with MISO to \nensure all projects interconnecting to ATC’s system are included in MTEP either through the \nstandard planning process or the EPR process.11   \n \n11 Attachment FF-ATCLLC at  VI.C.10 (“Inclusion in the MTEP. ATCLLC shall, consistent with \nAppendix B of the ISO Agreement and in accordance with the provisions of the Attachment FF of this \nTariff, upon completion of the analysis of any proposed Transmission Facilities project, or upon the"},{"page":10,"startToken":2601,"endToken":2982,"text":"10 \n \nD. \nATC’s 100 MW Threshold for Cost Allocation is Driven By a State-\nDetermined Threshold and Should Be Accepted.   \n \nATC proposes to maintain its 100 MW threshold for large loads for cost allocation \npurposes.  ATC’s threshold aligns with the PSCW's determination in separate retail proceedings \nthat 100 MW is the appropriate threshold for large load cost-shifting protections at the retail \nlevel.12  The PSCW made a finding of fact that it would be reasonable to make the large load \ntariffs mandatory for all customers with an aggregate load forecast of 100 MW and therefore \nordered the large load tariff mandatory for all customers with an aggregated load forecast of over \n100 MW.13  If ATC is required to implement a 50 MW threshold for cost allocation purposes, \nthere will be a cost allocation gap at the state level.  LDCs with those large load tariffs in \nWisconsin will be unable to directly assign costs to the large loads between 50 and 100 MW that \ncause the network upgrade costs to be incurred.14  Thus, network upgrade costs regarding loads \nbetween 50 and 100 MW will be spread to the LDC’s other customers.   \n \ncompletion of the evaluation of its network adequacy, identify to the Transmission Provider those \nprovisional, proposed or planned projects that ATCLLC, in its judgment, has determined should be \nconstructed to meet the needs of its Interconnection Customers and Transmission Customers in order to \nfulfill ATCLLC’s obligation to provide interconnection service and open access transmission service for \nthe benefit of all users of its Transmission Facilities.”). \n12 See infra, n. 14, 15. \n13 See Public Service Commission of Wisconsin Order Docket 6630-TE-113 Final Decision (PSC REF# \n591873) (“PSCW Retail Tariff Order on Very Large Customer and Bespoke Resource Tariff\"). Id., \nFinding of Fact 3, Order Point 5; see also Public Service Commission of Wisconsin Order Docket 6680-\nTE-115 Final Decision (PSC REF# 594678) (“PSCW Individual Contract Order\"), Finding of Fact 3 \n(finding 100 MW to be the appropriate threshold to apply a new large load retail tariff). \n14 See Wisconsin Power and Light, Application for Approval of Large Load Power Service Tariff, Docket \nNo. 6680-TE-119; Application of Madison Gas and Electric Company, Docket 3270-TE-124 (PSC REF#: \n597709); see also Application of Northern State Power Company, Docket 4220-TE-119 (PSC REF#: \n594842)."},{"page":11,"startToken":2982,"endToken":3268,"text":"11 \n \nE. \nTemplate LLPCAs and MTCAs Posted on ATC’s Website Provide \nConsistency and Allow Flexibility.  \n \nATC’s proposes to apply the 100 MW threshold for cost allocation purposes by requiring \nthat all large loads interconnected to ATC’s system execute the LLPCA and MTCA agreements.15  \nThese agreements deliver two layers of protection.   \nFirst, during construction, the Amended LLPCAs require LDCs to (1) backstop the cost \nof the required network upgrades in case the large load project is cancelled before it goes into \nservice and (2) pay the carrying costs for Construction Work in Progress (CWIP) that ATC would \notherwise recover from all of its transmission customers through its Attachment O formula rate.  \nThese mechanisms protect against other ATC customers paying for stranded costs if the large \nload projects are canceled before entering service.   \nOnce the facilities are placed into service, the MTCA requires LDCs to pay a minimum \ncontribution to ATC’s transmission revenue requirement based on the amount of transmission \ncapacity that the LDC requested to serve the large load.  ATC proposes to roll-in the capital costs \nof the network upgrades for large loads rather than directly assign them to LDCs.  The MTCA \nwith its minimum transmission contribution will ensure the large load project costs are not \nunreasonably shifted to other transmission customers in the event the large load does not \nmaterialize to the extent requested.  Moreover, the total charges incurred under the MTCA will \nbe limited to the incremental revenue requirement of the required network upgrades so that the \nLDC does not overpay under the agreement.  ATC’s proposed approach generally follows the \n \n15 ATC recently filed executed LLPCAs and an MTCA with Wisconsin Electric Power Company in \nDocket No. ER26-3265, which is pending a Commission order."},{"page":12,"startToken":3268,"endToken":3584,"text":"12 \n \nTransmission Security Agreement framework the Commission has already accepted in other \nproceedings without a hearing.16 \nATC has a series of template agreements that will assist with large load interconnections.  \nFirst, ATC already employs standardized Distribution-Transmission Interconnection agreements \n(D-TIAs) that are posted publicly and filed with the Commission when executed, serving the \nsame transparency function.  In addition, proposed section VI.12.B of Attachment FF-ATCLLC \nrequires that LLPCA and MTCA templates17 be posted on ATC's public website and filed with \nFERC for acceptance upon execution.  These template agreements achieve comparable \ntransparency and consistency to a pro forma agreement without foreclosing project-specific \nadjustments that may be needed given the individualized nature of large load projects.  Any \nunreasonable variations in these agreements can be brought to the Commission’s attention via the \nfiling of an unexecuted agreement.  \nF. \nATC’s Proposed Changes are Consistent with Order No. 890 Principles. \nATC is the only transmission owner in MISO that codifies its local planning process in \nthe MISO Tariff and has received specific findings that those local processes are compliant with \nOrders Nos. 890 and 2000.  ATC’s planning processes are structured to include all interested \nparties and treat all similarly situated interconnected customers the same.  ATC's planning \nprocess is open, collaborative, and stakeholder driven.  \n \n16 See e.g., PECO Energy Co., 195 FERC ¶ 61,074 (2026); Commonwealth Edison Co., 194 FERC ¶ \n61,183 (2026); see also Show Cause Order at P 83. \n17 The LLPCA protects transmission customers from the financing costs of construction and other costs \narising if a large load project is canceled before completion. The MTCA, with its Minimum Transmission \nCharge, protects other transmission customers after the project is placed into service in the event the full \namount of the requested load does not materialize.  Combined, the agreements protect other transmission \ncustomers from unjust and unreasonable cost shifts that could occur if the large load fails to materialize."},{"page":13,"startToken":3584,"endToken":3929,"text":"13 \n \nHowever, under Wisconsin law ATC's direct contractual and Tariff relationship is with \nLDCs, not end-use retail customers.  Because ATC is prohibited from providing transmission \nservice directly to retail customers, the local planning process necessarily is focused on the needs \nof entities, such as LDCs, with distribution facilities connected to ATC’s system.18  ATC does not \nshare information regarding interconnection requests from LDCs with third parties for \nconfidentiality reasons, much like in the generator interconnection context.  It is up to the LDC \nmaking an interconnection request to determine what information to share with its retail customer.   \nATC agrees with Microsoft’s contention that stakeholders should have the option to \nparticipate in the local planning process, such as to test and validate local transmission needs, \nexplore solutions to challenges and support consideration of GETs.19  Given the confidentiality \nconcerns mentioned above, such stakeholder participation does not occur in connection with a \nparticular interconnection request, but otherwise stakeholders have an ability to participate.  \nATC’s network adequacy planning process is open to stakeholder engagement.  As provided in \nAttachment FF-ATC, ATC conducts an annual Ten-Year Assessment (TYA) “of the need to \nmodify, extend or construct new Transmission Facilities to provide, safe, reliable, \nInterconnection Service and transmission Service and to ensure that its Transmission Facilities \nare capable of providing and have the Physical Capacity and operating Capability to reliably \nprovide adequate transmission Service to meet the needs of all uses of its Transmission Facilities \n \n18 Attachment FF-ATCLLC at VI.A.1:  “Any entity that owns or operates Distribution Facilities shall be \nentitled to make a request to modify any existing Distribution Interconnection or to propose a new \nDistribution Interconnection, including a Distribution Interconnection to support an ATCLLC Large \nLoad.”  Except for the underlined portion of that sentence, which is proposed in this filing, the concept of \nATC planning for Distribution Facilities is already included in Attachment FF-ATCLLC.  See also \nexisting Section VI.A.2. “ATCLLC maintains a queue of Distribution Interconnection requests made by \nthose entities owning Distribution Facilities that are interconnected to ATCLLC’s Transmission \nFacilities.” \n19 Microsoft Protest at 4-5."},{"page":14,"startToken":3929,"endToken":4275,"text":"14 \n \nand to fulfill all Public Policy Requirements.”20  For purposes of the TYA, each year ATC solicits \ninformation (by letter and by posting on its website) “from all Interconnection Customers, \nTransmission Customers and the owners of all Distribution Facilities that are interconnected to \nATCLLC’s Transmission System, and other stakeholders, specifically including information \nrelated to Public Policy Requirements.”21  Following the information gathering and verification, \nATC holds meetings with customers and stakeholders to discuss the assumptions and the models \nthat will be used to perform the TYA.22   \nATC agrees with Microsoft that large retail customers are important stakeholders in \nATC’s transmission planning work.23  That is why as noted above, ATC’s planning process \nincludes entities like Microsoft and has been approved by the Commission as compliant with \nOrder No. 890.24  Microsoft even acknowledges that it “has been working collaboratively with \nATC to interconnect and serve Microsoft’s large data center campus in Racine County, \nWisconsin.”25 \nATC disagrees with Microsoft’s assertion that the reforms give ATC unreasonable \ndiscretion in the planning process.26  More than half of Microsoft’s cited examples that \n \n20 Attachment FF-ATCLLC at VI.C.1. \n21 Id. at VI.C.2. \n22 Id. at VI.C.4 (“Any interconnection customer, Transmission Customer, owner of Distribution Facilities \nor Transmission Facilities, as well as any other stakeholder, including state regulators, local, state and \nfederal governmental officials, and members of interested community organizations shall be entitled to \nparticipate in such meeting or meetings held to discuss assumptions and models, specifically including a \ndiscussion of ATCLLC’s decision to include in, or exclude from, its proposed models any transmission \nneeds driven by Public Policy Requirements.”) (emphasis added). \n23 Microsoft Protest at 4. \n24 Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,165 at P 15 (2008) (Order on ATC’s \nOrder No. 890 compliance filing, stating that [w]e find that American Transmission Company’s \nAttachment FF-ATCLLC provides an opportunity for all affected parties to participate in the transmission \nplanning process.”), order on reh’g, 127 FERC ¶ 61,169 (2009). \n25 Microsoft Protest at 4. \n26 Id. at 7."},{"page":15,"startToken":4275,"endToken":4627,"text":"15 \n \npurportedly give ATC broad discretion are provisions that were previously approved and are not \nproposed to be changed.27  The changes proposed in Section V.F. are designed to allow criteria to \nbe updated at ATC's discretion in response to new conditions, safety concerns, operational issues, \ncustomer requests, and regulatory developments — same as it works today.  The discretion built \ninto these processes reflects existing, longstanding business practices rather than new or \nexpanded authority.  The planning processes have been developed collaboratively with \nstakeholder input over time and are intended to preserve existing commercial arrangements and \nin-flight projects rather than introduce new inconsistency.  \nG. \nThere are No Material Issues of Fact that Warrant Hearing and Settlement \nProcedures. \n \n \nThe Commission has discretion to direct an evidentiary hearing where there are genuine \nissues of material fact that cannot be resolved on the written record.28  Although protests \nroutinely identify disagreements in Section 205 proceedings, it is well established that “mere \nconjecture does not create a genuine issue of material fact warranting a hearing.” 29  Any factual \ndispute presented here—although none appears to exist—can be resolved on the written record.  \n \nATC has already agreed to modify the large load threshold regarding the operational \nissues that MISO identified.  ATC has also agreed to continue working with MISO to ensure that \nits planning process works seamlessly with MISO’s processes as it does today.  In addition, \n \n27 Id. at 7-9.  \n28 Southwest Power Pool, Inc. 195 FERC ¶ 61,134 at P 53 (2026), citing Cajun Elec. Power Co-op., Inc. \nv. FERC, 28 F.3d 173, 177 (D.C. Cir. 1994) (“Mere allegations of disputed fact are insufficient to mandate \na hearing—a petitioner must make an adequate evidentiary proffer to support the existence of such \ndisputes.”).   \n29 Interstate Power & Light Co., 127 FERC 61,043 at P 44, n. 49 (2009) (finding that a protestor has a \nburden to do more than make mere unsubstantiated allegations to warrant a hearing);  Tenneco Oil Co. 25 \nFERC ¶ 61,234 (1983); Tilden Mining Co. L.C., v. Midcontinent Indep. System Op., Inc., 153 FERC ¶ \n61,248 at P 22 (2015)."},{"page":16,"startToken":4627,"endToken":4860,"text":"16 \n \nATC’s proposed approach for cost allocation with the MTCA follows the Transmission Security \nAgreement framework the Commission has already accepted in other proceedings without a \nhearing.30  Hearing and settlement proceedings would serve no apparent purpose other than \npotentially preventing proper cost allocation that protects other ratepayers from paying for \nupgrades to ATC’s system caused by new large loads.  \nIV. \nCONCLUSION \nFor the foregoing reasons, ATC’s proposed revisions to Attachment FF-ATCLLC are just \nand reasonable and will provide greater clarity and transparency for the immediate and reliable \ninterconnection of large loads in ATC’s footprint.  ATC respectfully requests that the \nCommission grant leave to answer, accept this Answer, deny the requests for hearing and \nsettlement judge procedures, and accept the Amended LLPCAs and the MTCA as just and \nreasonable, effective October 17, 2026 (60 days from the date of filing).  \nRespectfully submitted,  \n \n \n \n \n \n \n \n \n \n/s/  Linda Walsh    \nEllen Nowak, Vice President, State  \n \n \nLinda Walsh \nand Federal Affairs  \n \n \n \n \nHusch Blackwell LLP \nStephanie Nietzel, Senior Counsel  \n \n \n1801 Pennsylvania Ave., NW \nATC Management Inc., corporate manager of \n \nSuite 1000 \nAmerican Transmission Company LLC  \n \nWashington, DC 20006 \nP.O. Box 47 \n \n \n \n \n \nTel: (202) 378-2308 \nWaukesha WI 53187-0047 \n \n \n \nlinda.walsh@huschblackwell.com \nTel: (262) 506-6170 \n \n \n \n \n \n \n \nsneitzel@atcllc.com \n \n \n \n \n \n \n \n \n \nDated: September 23, 2026  \n \n \n30 See e.g., PECO Energy Co., 195 FERC 61,074 (2026); Commonwealth Edison Co., 194 FERC 1,183 \n(2026); see also Show Cause Order at P 83."},{"page":17,"startToken":4860,"endToken":4945,"text":"17 \n \nCERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated at Washington, D.C. this 23rd day of September 2026. \n \n \n/s/ Emily Starobin \n \nEmily Starobin   \nHusch Blackwell LLP  \n1801 Pennsylvania Ave. NW, Suite 1000  \nWashington, D.C. 20006 \nTel: (202) 378-5784  \nemily.starobin@huschblackwell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":250},{"p":2,"at":5,"title":"I. SUMMARY OF ANSWER","method":"printed heading","endPage":5,"endAt":5,"startToken":250,"endToken":1150},{"p":5,"at":5,"title":"II. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":5,"endAt":746,"startToken":1150,"endToken":1261},{"p":5,"at":746,"title":"III. ANSWER","method":"printed heading","endPage":5,"endAt":760,"startToken":1261,"endToken":1263},{"p":5,"at":760,"title":"A. ATC’s Proposed Attachment FF-ATCLLC Revisions Address the Immediate","method":"printed heading","endPage":6,"endAt":1438,"startToken":1263,"endToken":1680},{"p":6,"at":1438,"title":"B. Uniform Rules Across the MISO Region May Be Unjust and Unreasonable if","method":"printed heading","endPage":8,"endAt":227,"startToken":1680,"endToken":2086},{"p":8,"at":227,"title":"C. ATC’s Proposed Modifications Will Address MISO’s Operational Concerns.","method":"printed heading","endPage":10,"endAt":6,"startToken":2086,"endToken":2602},{"p":10,"at":6,"title":"D. ATC’s 100 MW Threshold for Cost Allocation is Driven By a State-","method":"printed heading","endPage":11,"endAt":6,"startToken":2602,"endToken":2983},{"p":11,"at":6,"title":"E. Template LLPCAs and MTCAs Posted on ATC’s Website Provide","method":"printed heading","endPage":12,"endAt":993,"startToken":2983,"endToken":3403},{"p":12,"at":993,"title":"F. ATC’s Proposed Changes are Consistent with Order No. 890 Principles.","method":"printed heading","endPage":15,"endAt":732,"startToken":3403,"endToken":4377},{"p":15,"at":732,"title":"G. There are No Material Issues of Fact that Warrant Hearing and Settlement","method":"printed heading","endPage":16,"endAt":426,"startToken":4377,"endToken":4687},{"p":16,"at":426,"title":"IV. CONCLUSION","method":"printed heading","endPage":17,"endAt":6,"startToken":4687,"endToken":4861},{"p":17,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":17,"endAt":559,"startToken":4861,"endToken":4945}]}