{"document":{"slug":"rec-20260923-5148","title":"Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the comments and protests in response to the 08/18/2026 proposed…","issued":"2026-09-23","accession":"20260923-5148","docket":"ER26-3552-000","group":"MISO zero-injection generator interconnection agreement","filer":"Midcontinent Independent System Operator Inc.","kind":"protest","file":"sources/filings/text/20260923-5148_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260923-5148","tier":"record","sha256":"9bb7937a229f214d6ce9d3cb199116bab0650752fee8bb962fc94d274a7e5b79","pages":27,"tokens":7395,"emptyPages":[],"textThemes":["study","cost","retail","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":250,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nMidcontinent Independent System \n \nOperator, Inc., \n) \n) \n) \n) \n \nDocket No. ER26-3552-000 \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF THE  \nMIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC. \n \nThe Midcontinent Independent System Operator, Inc. (“MISO”) respectfully submits1 this \nMotion for Leave to Answer and Answer to the comments and protests filed in response to MISO’s \nAugust 18, 2026 filing proposing revisions to its Open Access Transmission, Energy and \nOperating Reserve Markets Tariff (“Tariff”) to establish Zero Generation Interconnection Service \n(“ZG Interconnection Service” or “ZIGS”), a corresponding Zero Generation Interconnection \nAgreement (“ZGIA”), and associated study, operational, market, and resource adequacy \nrequirements (“ZGIA Filing”).2 \nThe comments reflect substantial support for the fundamental design of the proposal in \nMISO’s ZGIA Filing.  The Organization of MISO States, Inc. (“OMS”) cautiously supports the \nZGIA Filing, but raises certain reliability and resource adequacy concerns of the states.3  The \nMISO Transmission Owners (“MISO TOs”) support the ZGIA construct as an additional tool to \naddress large-load growth and provide greater consistency and structure for interconnection \nrequests designed to serve specific loads.4  The Solar Energy Industries Association (“SEIA”) \n \n1  \nSee Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission \n(“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 213 (2026). \n2  \nMISO Transmittal at 1-2. \n3  \nMotion for Acceptance of Late-Filed Comments in Conditional Support of the Organization of MISO States, \nInc. (“OMS Comments”) at 1. \n4  \nMISO TOs Comments at 3-4, 7-9."},{"page":2,"startToken":250,"endToken":529,"text":"similarly supports the proposal and explains that its same-substation and load-following \nrequirements minimize Transmission System impacts and protect other interconnection customers \nfrom cost shifting.5 Google LLC (“Google”) describes the ZGIA as a “step in the right direction,” \nwhile advocating for additional reforms beyond those proposed here.6 Advanced Energy United \n(“United”) likewise supports the ZGIA subject to certain requested clarifications.7  \nThe remaining concerns do not demonstrate that MISO’s proposal is unjust or \nunreasonable.  The sole protest in this matter was filed by Community Organizations and Clean \nEnergy Advocates.8  Several comments and protests arise from a misunderstanding of the limited \nnature of ZGIS or concern broader large-load issues MISO expressly reserved for subsequent \nproposals.  ZGIS does not provide ERIS, NRIS, Transmission Service, or a general right to inject \nenergy onto the Transmission System.9  Instead, ZGIS is a limited form of Interconnection Service \nthat allows an Interconnection Customer to connect its Generating Facility for the limited purpose \nof delivering energy to designated ZG Associated Load, subject to the configuration, study, and \noperational requirements established by the Tariff and ZGIA.10 \nThe Commission should therefore accept the ZGIA Filing without delaying its \nimplementation or requiring MISO to expand this proceeding to resolve distinct large-load, \ntransmission-service, or generator-interconnection issues.11  Accordingly, MISO respectfully \n \n5  \nSEIA Comments at 3-6. \n6  \nGoogle Comments at 2-5. \n7  \nUnited Comments at 3-12. \n8  \nProtest of Community Organizations and Clean Energy Advocates (“Clean Energy”). \n9  \nMISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service. \n10  MISO Transmittal at 12-16; proposed Tariff, Module A, ZG Interconnection Service; proposed Attachment X §§ \n3.2.5, 3.10.1. \n11  MISO Transmittal at 2, 9-11."},{"page":3,"startToken":529,"endToken":809,"text":"requests the ZGIA Filing be accepted without modification and with an effective date of October \n18, 2026, as requested in the ZGIA Filing. \nI. \nMOTION FOR LEAVE TO ANSWER \nUnder Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure, answers to \nprotests are generally not permitted.12  Nonetheless, the Commission waives this requirement \nwhere an otherwise prohibited answer would clarify the issues under consideration, ensure \ncompleteness of the record, or assist the Commission in its decision-making.13  MISO respectfully \nsubmits that granting it leave to answer the comments and protests in this docket will assist the \nCommission in its decision-making and facilitate the expeditious resolution of this matter by \nclarifying the issues under consideration.  Accordingly, Rule 213(a)(2) should be waived for good \ncause shown.  \nII. \nANSWER \nA. \nThe ZGIA Is a Just and Reasonable Standalone Interconnection Service That \nNeed Not Await MISO’s Other Large-Load Reforms. \n \nWhile United supports acceptance of the ZGIA Tariff revisions, it asks the Commission to \ndelay implementation of ZGIS to permit further coordination with MISO’s forthcoming Load \nAddition Resource Study (“LARS”) proposal and seeks additional explanation concerning how \nthe two processes will operate together.14  Google, from a different perspective, urges MISO to \n \n12  See 18 C.F.R. § 385.213(a)(2) (2026). \n13  See, e.g., Southwest Power Pool, Inc., 143 FERC ¶ 61,018, at P 15 (2013) (accepting answer that assisted in the \ndecision-making process); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205, at P 8 (2008) (accepting answer \nthat completed the record); California Independent System Operator Corp., 105 FERC ¶ 61,284, at P 10 (2003) \n(accepting answer that clarified the issues). \n14  United Comments at 1, 3-5."},{"page":4,"startToken":809,"endToken":1093,"text":"expand ZGIS beyond the same-substation configuration to encompass generation serving \nelectrically proximate load.15  \nNeither request provides a basis to delay implementation of the ZGIA Filing.  MISO \ndeveloped the ZGIA as a standalone proposal addressing the generator-interconnection service and \nstudy framework applicable to generation serving ZG Associated Load connected at the same \nsubstation and voltage level.16  ZG Associated Load does not have to be a Large Load.  LARS, by \ncontrast, is intended to address distinct study issues associated with new generation and large load \nthat are electrically proximate by aligning the Transmission Service and Interconnection Service \nevaluations in order to provide coordinated study results on an accelerated basis .17  LARS will not \ngrant ZG Interconnection Service and MISO has not proposed that participation in LARS is a \nprerequisite to ZGIS.18  Neither the ZGIA nor LARS create a new Transmission Service product \nfor serving co-located or electrically proximate load.19  \nMISO therefore does not need LARS to implement the ZGIA.  They are two entirely \ndifferent, standalone processes with distinct use cases.  The ZGIA establishes a discrete form of \nInterconnection Service for generation serving load under the specific configuration and \n \n15  Google Comments at 3-4. \n16  MISO Transmittal at 2, 9-11. \n17  September 23, 2026 Large Load Working Group presentation, “Large Load Addition Resource Study (LARS),” \nand associated draft Tariff Sheets (Item No. 06) available at  Large Load Working Group (LLWG) - September \n23, 2026. \n18  MISO Transmittal at 9-10; Id. As currently envisioned and drafted, the generation portion of the LARS study will \nrequire Network Resource Interconnection Service and studies appropriate for such service.   \n19  Id. at 10. New Transmission Service products are being discussed with stakeholders for inclusion in a separate \n205 filing."},{"page":5,"startToken":1093,"endToken":1349,"text":"operational limitations established in the proposed Tariff.20.  Accordingly, MISO can implement \nthe ZGIA independently while continuing to develop other complementary large-load reforms.21  \nMISO’s decision to limit ZGIS to generation and load at the same substation and voltage \nlevel likewise is deliberate.22  MISO considered both a narrower same-POI approach and a broader \napproach encompassing electrically proximate generation and load, but determined that the \nbroader approach would introduce additional reliability and transmission-service questions, \nincluding potential retail-wheeling considerations.  Rather than delay implementation of ZGIS \nwhile23 those broader issues are resolved, MISO proposed a configuration that can be studied and \nimplemented within the limited ZGIS framework.24  \nThe proposal therefore does not foreclose the broader reforms advocated by United or \nGoogle.  MISO expressly explained that the ZGIA addresses only some of the issues identified in \nthe Commission’s Show Cause Order and that other issues will be addressed through subsequent \nproposals.25  The Commission should accept the discrete ZGIA Filing before it without awaiting \nresolution of every related large-load issue.26  \nB. \nZGIS Is a Limited Zero-Injection Service, and the Transient Tolerance \nWindow Does Not Confer an Injection Right. \n \n \n20  MISO Transmittal at 11-16; proposed Attachment X §§ 3.2.5, 3.10.1. \n21  MISO Transmittal at 2, 9-11. \n22  MISO Transmittal at 7, 12-13; Keyser at 11-14, 19-20. \n23  MISO Transmittal at 7; Keyser at 11-14, 19-20. \n24  MISO Transmittal at 7, 12-15. \n25  MISO Transmittal at 2, 9-11; Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause \nOrder”). \n26  MISO Transmittal at 2."},{"page":6,"startToken":1349,"endToken":1634,"text":"Clean Energy contends that the proposal does not adequately ensure that “zero means \nzero,” emphasizing the possibility of injections during and outside the Transient Tolerance \nWindow and requesting additional penalties for unauthorized injections.27 \nThat argument conflates the scope of the Interconnection Service MISO proposes to \nprovide with the physical response of a Generating Facility following a transient event.  ZGIS \nprovides no general right to inject energy onto the Transmission System and does not convey \nTransmission Service.28  ZGIS permits the Generating Facility to operate only for the limited \npurpose of delivering energy to its designated ZG Associated Load.29 \nThe Transient Tolerance Window does not alter those service limitations.  The proposed \nTariff defines the Transient Tolerance Window as the period following a reduction or loss of ZG \nAssociated Load by the end of which the Generating Facility must reduce its injections to an \namount no greater than the Load of the ZG Associated Load.30  The Tariff limits that period to no \nmore than twenty seconds and subjects it to applicable Transmission Owner Local Planning \nCriteria.31  \nThe Transient Tolerance Window reflects the physical reality that a Generating Facility \ngenerally cannot respond instantaneously to a sudden reduction in associated load.32  Even where \ncommunications and other equipment link the Generating Facility and ZG Associated Load, the \nGenerating Facility may require a finite period to reduce its production following an abrupt \n \n27  Clean Energy Protest at 3-11. \n28  MISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service. \n29  MISO Transmittal at 12; proposed Tariff, Module A, ZG Interconnection Service. \n30  MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window. \n31  Id. \n32  MISO Transmittal at 21, 26; Keyser at 25-26."},{"page":7,"startToken":1634,"endToken":1924,"text":"reduction in demand.33  The Transient Tolerance Window allows MISO to account for that \ntransient response in the ZG Impact Assessment while requiring the Generating Facility to reduce \nits injections within the defined period.34 \nAn inadvertent transient flow therefore does not create an entitlement to inject energy onto \nthe Transmission System.35  Rather, MISO expressly studies injections occurring during the \nTransient Tolerance Window by modeling the loss of ZG Associated Load and evaluating the \nresulting stability and steady-state impacts.36  The ZG Impact Assessment must determine that no \nNetwork Upgrades beyond those specifically allow for ZGIS are required to maintain reliability \nunder those conditions.37  \nThe proposal also imposes specific operational requirements designed to enforce the ZGIS \nlimitation. A ZG Resource must install communications and monitoring equipment enabling it to \nmonitor demand of the ZG Associated Load.38 It also must install equipment enabling the \nGenerating Facility to reduce its injections to a level that does not exceed demand of the ZG \nAssociated Load within the Transient Tolerance Window.39  \nThe equipment used to satisfy those requirements must be identified in Appendix A of the \nZGIA, and MISO verifies through the interconnection process that the ZG Resource can limit \n \n33  MISO Transmittal at 26; Keyser at 25-26. \n34  MISO Transmittal at 21-22, 26, 28; Keyser at 25-28. \n35  MISO Transmittal at 16, 21-22, 42-43; proposed Tariff, Module A, ZG Interconnection Service and Transient \nTolerance Window; proposed ZGIA Art. 9.7.4.7. \n36  MISO Transmittal at 15, 28; Keyser at 28. \n37  MISO Transmittal at 28; proposed Attachment X § 3.2.5.2. \n38  MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(a). \n39  MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(b)."},{"page":8,"startToken":1924,"endToken":2297,"text":"injections as proposed.40 The required equipment and configuration are then documented in \nAppendix A and become enforceable terms of the ZGIA.41 \nThe Commission should not require MISO to characterize unauthorized ZGIS injections \nas unreserved use. The existing unreserved-use provisions address Transmission Service and are \nnot the enforcement mechanism MISO proposes for ZGIS.42 MISO instead proposes to address \nZGIS compliance directly through the technical, operational, study, and contractual requirements \napplicable to the ZG Resource.43  A  potential for injection above an established interconnection \nservice limit is hardly unique to the ZGIA. Any Generating Facility, especially one with capacity \nabove its Interconnection Service level, has a similar potential.  The Commission explored this \nissue in Order No. 845 and found that existing GIA mechanisms were sufficient to address \nunauthorized injections without establishing penalties.44  Should MISO determine in the future that \npenalties have become necessary or appropriate for enforcing interconnection service limits, MISO \nexpects that it would explore potential penalty frameworks for application generally to all \ninterconnection agreements that have such a potential rather than singling out only some \ngenerating facilities or service types for penalties.  This docket, however, is not the appropriate \nvehicle for considering such proposals.  \nC. \nMISO Appropriately Establishes Performance-Based System Protection \nRequirements Rather Than Mandating a Single Technical Configuration. \n \n40  MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7. \n41  MISO Transmittal at 43; proposed ZGIA App. A § 2. \n42   Tariff, Module B at Sections 13.7, 14.5, 27A.1.6 and/ 27A.2.4. \n43  MISO Transmittal at 21-22, 26-28, 42-43; proposed ZGIA Art. 9.7.4.7. \n44  Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 FERC ¶ 61,043 (2018), \norder on reh'g and clarification, Order No. 845-A, 166 FERC ¶ 61,137 (2019), order on reh'g, Order No. 845-B, \n168 FERC ¶ 61,092 (2019)at P 416 (“Based on these facts, we decline to generically adopt into the pro forma \nLGIP any additional financial penalties for exceeding the limitations for interconnection service established in \nthe interconnection agreements”) and P 417 (“Because of these existing provisions, and the fact that no other \nconsequences currently apply in the analogous situations described above, we see no need to devise new penalties \nat this time.”)."},{"page":9,"startToken":2297,"endToken":2565,"text":"Clean Energy argues that the Tariff should specify a minimum configuration of System \nProtection Facilities, require automatic corrective action, and prescribe specific testing and \ninspection intervals.45  \nMISO’s proposal instead establishes the required performance and permits the particular \nequipment and configuration to be tailored to the ZG Resource, ZG Associated Load, Point of \nInterconnection, and applicable Transmission Owner system.46 The ZG Resource must identify the \nequipment it proposes to use to satisfy the injection limitations, and MISO must verify that the ZG \nResource can limit injections as proposed.47 MISO then documents the required equipment and \nconfiguration in Appendix A of the ZGIA, making those requirements enforceable terms of \nZGIS.48  \nThis performance-based approach permits the technical solution to reflect the actual \nconfiguration rather than assuming that a single prescribed technology is appropriate for every ZG \nResource.49 MISO and the applicable Transmission Owner remain involved in evaluating the \nproposed configuration, and a project cannot proceed under ZGIS if the safeguards are insufficient \nto satisfy the applicable study and operating requirements.50 By focusing on the required result, \nthis approach avoids limiting Interconnection Customers to certain types of equipment or \nconfigurations that may be incomplete or rapidly obsolesce.  \n \n45  Clean Energy Protest at 6-11. \n46  MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7. \n47  MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7. \n48  MISO Transmittal at 43; proposed ZGIA App. A § 2. \n49  MISO Transmittal at 42-43. \n50  MISO Transmittal at 13, 28, 42-43; proposed Attachment X §§ 3.2.5.2, 3.10.1; proposed ZGIA Art. 9.7.4.7."},{"page":10,"startToken":2565,"endToken":2833,"text":"Clean Energy’s testing concern similarly overlooks requirements already contained in \nMISO’s pro forma ZGIA. Section 6.1 addresses pre-Commercial Operation Date testing and \nmodifications, including testing of control equipment used to limit injections at the Point of \nInterconnection to the level of Interconnection Service specified in Appendix A and testing \nnecessary to ensure safe and reliable operation of the Interconnection Customer’s Interconnection \nFacilities.51 Section 6.1 also provides for similar testing after initial operation where appropriate.52 \nSection 6.2 separately establishes post-Commercial Operation Date testing and modification \nrequirements.53  \nThe absence of a separate ZGIS-specific inspection interval therefore does not mean that \nthe control and protection equipment is exempt from testing.54 The MISO TOs likewise recognize \nthat the ZGIA provides a framework for addressing the control and protection systems necessary \nto limit injections from generation serving associated load.55  \nD. \nThe Twenty-Second Maximum Transient Tolerance Window Has a \nReasonable Engineering Basis. \n \nClean Energy asks MISO to provide additional engineering support for the twenty-second \nmaximum Transient Tolerance Window and argues that the standards governing a shorter window \nshould appear in the Tariff rather than the Business Practices Manual.56  \nThe twenty-second maximum is tied to MISO’s existing planning methodology. MISO’s \ndynamic simulations analyze transient response over a zero-to-twenty-second study period.57 The \n \n51  Pro Forma ZGIA § 6.1. \n52  Pro Forma ZGIA § 6.1. \n53  Pro Forma ZGIA § 6.2. \n54  Pro Forma ZGIA §§ 6.1-6.2; proposed ZGIA Art. 9.7.4.7. \n55  MISO TOs Comments at 8-9. \n56  Clean Energy Protest at 12-14. \n57  MISO Planning Modeling Manual § 5.4; Keyser at 25-26."},{"page":11,"startToken":2833,"endToken":3112,"text":"twenty-second maximum therefore permits MISO to evaluate the ZG Resource’s response during \nthe same period in which transient stability impacts are analyzed.58 If the study identifies a \nreliability issue requiring a Network Upgrade that is incompatible with ZGIS, the project cannot \nproceed through the ZGIA process.59  \nThe proposed Tariff itself establishes the controlling outer limit. The Transient Tolerance \nWindow “shall be no greater than 20 seconds” and is subject to applicable Transmission Owner \nLocal Planning Criteria.60 Thus, the Business Practices Manual cannot expand the permitted period \nbeyond twenty seconds.61 Rather, the BPM will identify the circumstances in which a shorter \ninterval applies.62 This is a reasonable balance between certainty and flexibility because there may \nbe circumstances where shorter Transient Tolerance Window is appropriate for reliability based \non situation-specific factors that are likely to be technical in nature.  Requiring MISO to specify \nthese rules in in the Business Practices Manual ensures ZG Interconnection Customers are treated \nconsistently.  \nThe ZG Impact Assessment also includes the ZG Associated Load and simulates a scenario \nin which that load trips offline.63 The resulting analyses evaluate injections occurring during the \nTransient Tolerance Window and help validate the protection scheme necessary for the particular \nZGIA project.64  \n \n58  MISO Planning Modeling Manual § 5.4; Keyser at 25-26. \n59  MISO Transmittal at 13, 28; proposed Attachment X §§ 3.2.5.1-.2. \n60  MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window. \n61  MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window. \n62  MISO Transmittal at 21-22 & n.53. \n63  MISO Transmittal at 15, 28; Keyser at 28. \n64  MISO Transmittal at 15, 28; Keyser at 28."},{"page":12,"startToken":3112,"endToken":3396,"text":"The twenty-second limit therefore is not an authorization for every ZG Resource to inject \nfor twenty seconds.65 It is the maximum response interval within which a project must satisfy the \napplicable study and operating requirements, subject to a shorter interval where Transmission \nOwner Local Planning Criteria or the BPM so require.66  \nE. \nThe ZGIA Provides Appropriate Operational Visibility and Verification. \n \nUnited requests clarification concerning MISO’s ongoing visibility into coordination \nbetween the ZG Resource and ZG Associated Load after execution of the ZGIA and how \ncompliance with the Transient Tolerance Window and associated equipment requirements will be \nmonitored and verified.67  \nThe proposal includes multiple mechanisms that provide operational visibility and \nfacilitate verification. First, each ZG Resource must install communications and monitoring \nequipment enabling it to monitor demand of the ZG Associated Load.68  The Resource must install \nequipment enabling it to reduce injections to no greater than the demand of the ZG Associated \nLoad within the Transient Tolerance Window.69  \nSecond, an Interconnection Customer receiving ZGIS must install metering for the \nGenerating Facility that is separate from the metering used for the ZG Associated Load.70 This \nrequirement allows the generation and associated load to be measured separately rather than netted \nbehind a common meter.71  \n \n65  MISO Transmittal at 21-22, 26-28; proposed Tariff, Module A, Transient Tolerance Window. \n66  MISO Transmittal at 21-22 & n.53; proposed Tariff, Module A, Transient Tolerance Window. \n67  United Comments at 11-12. \n68  MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(a). \n69  MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(b). \n70  MISO Transmittal at 41; proposed ZGIA Art. 7.1. \n71  MISO Transmittal at 41; Keyser at 38."},{"page":13,"startToken":3396,"endToken":3700,"text":"Third, a ZG Resource greater than 5 MW must register as a Generation Resource, Energy \nStorage Resource, or Dispatchable Intermittent Resource, as applicable, and maintain the \nregistration required by the Tariff.72 MISO explained that the registration requirement provides \nvisibility of the ZG Resource and allows MISO to account for the gross amount of ZG Associated \nLoad.73  \nFourth, the equipment and configuration used to satisfy the injection limitations are \nmemorialized in Appendix A of the ZGIA and therefore remain enforceable requirements after the \ninitial study is complete.74 Changes to the studied configuration that could affect the impacts of \nZGIS are subject to MISO’s applicable modification rules.75  \nTaken together, the communication, monitoring, metering, registration, testing, and \ncontractual requirements provide continuing mechanisms for observing and enforcing the \noperational limitations applicable to ZGIS.76  \nF. \nMISO’s Study and Model-Reconciliation Processes Protect Existing DPP \nCustomers and Address the Asserted Cost-Shifting Concerns. \n \nClean Energy and United raise related questions concerning interactions among the ZGIA, \nDPP, and MTEP study processes. Clean Energy contends that differences in study timing may \nshift Network Upgrade costs to load and argues that a ZG Resource could use ZGIS as a pathway \nto later obtain ERIS or NRIS.77 United requests additional clarification concerning base-case \nreconciliation and cost responsibility for constraints identified through MTEP.78  \n \n72  MISO Transmittal at 18, 41; proposed Tariff § 38.2.2; proposed ZGIA Art. 7.1.1. \n73  MISO Transmittal at 18; Keyser at 38. \n74  MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7; proposed ZGIA App. A § 2. \n75  MISO Transmittal at 43; proposed ZGIA App. A §§ 1-2. \n76  MISO Transmittal at 18, 41-43; Pro Forma GIA §§ 6.1-6.2; proposed ZGIA Arts. 7.1, 7.1.1, 9.7.4.7. \n77  Clean Energy Protest at 18-26. \n78  United Comments at 7-10."},{"page":14,"startToken":3700,"endToken":3975,"text":"MISO’s filing already explains how the ZGIA and DPP models interact. ZGIA studies do \nnot include Interconnection Requests remaining in the generator interconnection queue that do not \nyet have a GIA.79 Before each ZGIA cycle, Interconnection Requests with GIAs approved since \ncreation of the prior base case are added to the ZGIA base case.80 Those projects are not, however, \ninserted into an ongoing DPP study.81 \nOnce a DPP cycle begins, its base case generally is not updated to add subsequently \napproved ZGIA projects, except for ordinary changes resulting from withdrawals or generator \nretirements.82 MISO designed that sequencing to ensure that transmission capacity available to \nDPP projects is not taken away by ZGIA projects approved outside the DPP cycle.83 ZGIA projects \nlikewise do not use available transmission capacity reflected in the DPP and ERAS studies.84 \nAfter the DPP cycle concludes, completed DPP, ZGIA, and EPR projects are incorporated \ninto a new MTEP base case.85 Any resulting reconciliation issues are addressed through MTEP, \nand the next DPP cycle uses the reconciled MTEP base case.86 As MISO explained, this process \n“insulates existing DPP projects from negative impacts or cost shifts due to the existence of the \nZGIA process.”87 \nThe limited nature of ZGIS provides an additional safeguard against the cost-shifting \nconcerns raised by Clean Energy. The amount of Interconnection Service awarded to a ZG \n \n79  MISO Transmittal at 15. \n80  MISO Transmittal at 15. \n81  MISO Transmittal at 15. \n82  MISO Transmittal at 15. \n83  MISO Transmittal at 15. \n84  MISO Transmittal at 15. \n85  MISO Transmittal at 15. \n86  MISO Transmittal at 15. \n87  MISO Transmittal at 15."},{"page":15,"startToken":3975,"endToken":4260,"text":"Resource cannot exceed the peak demand of the ZG Associated Load.88 The ZG Resource must \nconnect at the same substation and voltage level as a Point of Withdrawal for the ZG Associated \nLoad, and the ZG Interconnection Study must determine that the project will not require Network \nUpgrades beyond that substation except for System Protection Facilities at adjacent substations.89 \nThe costs of equipment necessary to limit injections consistent with ZGIS are borne by the ZG \nInterconnection Customer.90  \nSEIA similarly explains that the same-substation and load-following requirements \nminimize Transmission System impacts and allow ZGIA projects to proceed without consuming \ntransmission capacity required by DPP projects or increasing costs for projects already in the \nqueue.91  \nClean Energy’s separate contention that the ZGIA creates a fast-track pathway to ERIS or \nNRIS likewise misunderstands the service being offered.92 A project receiving ZGIS receives only \nthe limited Interconnection Service defined by the Tariff; it does not receive ERIS or NRIS.93 If a \nZG Resource later seeks ERIS or NRIS, it must submit an Interconnection Request and proceed \nthrough the DPP or applicable generator-interconnection process on the same footing and on the \nsame study timeline as Interconnection Requests that do not already have ZG Interconnection \nService.94 The ZGIA does not provide a mechanism for a ZG Resource to enter an active DPP \n \n88  MISO Transmittal at 13; Keyser at 10-11; proposed Attachment X § 3.10.1. \n89  MISO Transmittal at 13; proposed Attachment X §§ 3.2.5.1-.2, 3.10.1. \n90  MISO Transmittal at 26-27. \n91  SEIA Comments at 3-6. \n92  Clean Energy Protest at 20-24. \n93  MISO Transmittal at 12-16; proposed Tariff, Module A, ZG Interconnection Service. \n94  Keyser at 14-17."},{"page":16,"startToken":4260,"endToken":4539,"text":"cycle, retain a prior DPP queue position, or otherwise convert ZGIS into ERIS or NRIS without \ncompleting the applicable interconnection process.95 \nSimilarly, if a project already participating in the DPP elects instead to pursue ZGIS, it \nrelinquishes the broader ERIS or NRIS service that could be obtained through its DPP request and \nreceives the more limited ZGIS.96 A later request for ERIS or NRIS would proceed through the \napplicable queue process rather than retaining priority based on the ZGIA. \nThe same service limitation addresses Clean Energy’s concern regarding the commitment \nof the ZG Associated Load. ZGIS is restricted to serving the ZG Associated Load identified in the \nInterconnection Request and memorialized in the ZGIA.97 MISO requires documentation of the \nrelationship between the ZG Resource and ZG Associated Load specifically because the ZG \nResource may serve only that designated load and to prevent speculative Interconnection \nRequests.98  \nIf the ZG Associated Load does not materialize or ceases to exist, the ZG Resource does \nnot thereby acquire ERIS, NRIS, or a general right to inject onto the Transmission System.99 To \nobtain broader Interconnection Service, the Generating Facility must proceed through the \napplicable generator-interconnection process.100  It may not inject onto the Transmission System \nuntil granted a right to do so by such process.  \nG. \nThe ZGIA Provides Appropriate Transparency. \n \n \n95  Id. \n96  Id. At 29 \n97  MISO Transmittal at 12; proposed Tariff, Module A, ZG Interconnection Service; proposed Attachment X § \n3.2.5.1. \n98  MISO Transmittal at 12 & n.41; Keyser at 9; proposed Attachment X § 3.10.1. \n99  MISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service. \n100  Keyser at 29."},{"page":17,"startToken":4539,"endToken":4797,"text":"Clean Energy contends that MISO’s proposal does not adequately address transparency \nbecause the Tariff does not expressly require publication of ZGIA study reports, affected-system \nresults, required or deferred Network Upgrades, or associated Network Upgrade costs.101 This \nobjection is unfounded. These requirements are not currently imposed on Interconnection Requests \nseeking Interconnection Service through other processes, such as the DPP and it is not necessary \nto add such new requirements for ZGIAs independently from any large load transparency reforms.  \nMISO does not propose to reduce any generally applicable transparency requirements currently \nestablished in the GIP for Interconnection Requests seeking ZGIS.   \nZGIA Interconnection Requests remain subject to MISO’s existing affected-system \ncoordination procedures and screening criteria, subject to the specific timing modifications \napplicable to ZGIA requests.102  MISO must provide the information necessary for an Affected \nSystem to study a ZG Interconnection Request prior to the applicable ZG Impact Assessment and \nprovide any affected-system analysis received to the ZG Interconnection Customer.103  \nMore fundamentally, Clean Energy’s concern regarding undisclosed or “deferred” \nNetwork Upgrades does not account for a central eligibility limitation of ZGIS. The ZG Resource \nmust interconnect at the same substation and voltage level as a Point of Withdrawal for its ZG \nAssociated Load, and the ZG Interconnection Study must determine that the ZG Resource will not \nrequire Network Upgrades beyond the substation except for System Protection Facilities at \n \n101  Clean Energy Protest at 14-16. \n102  Proposed Attachment X. \n103  Id. MISO notes that ZG Interconnection Service is not restricted to Generating Facilities serving large loads. \nlimited to Large Loads."},{"page":18,"startToken":4797,"endToken":5116,"text":"adjacent substations.104 The ZG Impact Assessment likewise must determine that no  Network \nUpgrades beyond those specifically allowed for ZGIS are necessary to maintain reliability.105  \nThus, the ZGIA process does not permit MISO simply to defer broader Network Upgrades \nand their associated costs.106 If the study determines that a project requires Network Upgrades \ninconsistent with the eligibility criteria for ZGIS, the project cannot proceed under the ZGIA \nprocess.107 \nBroader transparency requirements associated with large-load interconnection are distinct \nfrom the ZGIA Filing before the Commission here. MISO expressly stated that the ZGIA Filing \naddresses only certain issues raised in the Show Cause Order and that MISO intends to address \nadditional large-load issues through subsequent section 205 filings.108 ZGIS is not restricted to \nGenerating Facilities serving Large loads.  The Commission therefore need not require MISO to \nresolve those broader transparency issues as a condition of accepting ZGIS.109 \nH. \nAdditional Aggregate or Temporal Limits Are Unnecessary Given the Limited \nNature of ZGIS. \n \nClean Energy argues that MISO should establish a pilot program, aggregate MW cap, \nlimited application period, or defined term for individual ZGIAs.110 \nThe proposal already contains significant limitations on the availability and operation of \nZGIS. ZGIS is available only where the Generating Facility and ZG Associated Load satisfy the \n \n104  MISO Transmittal at 13; proposed Attachment X §§ 3.2.5.1-.2, 3.10.1. \n105  MISO Transmittal at 28; proposed Attachment X § 3.2.5.2. \n106  MISO Transmittal at 28; proposed Attachment X § 3.2.5.2. \n107  MISO Transmittal at 28; proposed Attachment X § 3.2.5.2. \n108  MISO Transmittal at 2, 10-11. \n109  MISO Transmittal at 2, 10-11. To the extent that a ZGIA involves a Large Load, nothing in the ZGIA Filing \npurports to exempt a Large Load from any generally applicable transparency requirements that MISO may \npropose in a subsequent filing.  \n110   Clean Energy Protest at 16-18."},{"page":19,"startToken":5116,"endToken":5419,"text":"same-substation and same-voltage requirements established by the Tariff.111 The amount of ZGIS \nawarded cannot exceed the peak demand of the ZG Associated Load.112 The ZG Interconnection \nStudy also must determine that the project will not require Network Upgrades beyond the \ninterconnecting substation except for System Protection Facilities at adjacent substations.113  \nMISO also limits the number of requests that may be processed during each quarterly ZGIA \nstudy cycle.114 MISO adopted that limitation to avoid disruption to the DPP and ensure that \nsufficient resources are available to process ZGIA requests.115  \nAn additional aggregate MW cap is unnecessary because the amount of ZGIS available to \neach project already is tied directly to the peak demand of its ZG Associated Load.116 Moreover, \nZGIS does not provide general injection rights and cannot require the broader Network Upgrades \nassociated with ordinary ERIS or NRIS requests.117 A predetermined expiration date for each ZGIA \nsimilarly is unnecessary because the service remains subject to those limitations throughout the \nlife of the agreement.118 If the studied equipment or configuration changes in a manner that could \naffect the Transmission System impacts of ZGIS, those changes are subject to MISO’s applicable \nmodification rules.119 MISO specifically incorporated the studied configuration into Appendix A \n \n111  MISO Transmittal at 12-13; proposed Attachment X § 3.10.1. \n112  MISO Transmittal at 13; Keyser at 10-11; proposed Attachment X § 3.10.1. \n113  MISO Transmittal at 13, 28; proposed Attachment X §§ 3.2.5.1-.2. \n114  Keyser at 24. \n115  Keyser at 24. \n116  MISO Transmittal at 13; Keyser at 10-11. \n117  MISO Transmittal at 12-13, 16, 26-28; proposed Tariff, Module A, ZG Interconnection Service; proposed \nAttachment X §§ 3.2.5.1-.2. \n118  MISO Transmittal at 12-16; proposed ZGIA. \n119  MISO Transmittal at 43; proposed ZGIA App. A §§ 1-2."},{"page":20,"startToken":5419,"endToken":5689,"text":"so that changes affecting the basis on which ZGIS was granted are subject to those modification \nrequirements.120  \nAccordingly, the absence of an arbitrary aggregate or temporal cap does not render ZGIS \nunlimited. Its scope is limited by the electrical configuration, associated-load relationship, service \namount, Network Upgrade restrictions, study requirements, and continuing operating obligations \nestablished by the Tariff and ZGIA.121  \nI. \nMISO’s Treatment of Hybrid Resources Is Consistent with the Limited Nature \nof ZGIS. \n \nClean Energy seeks clarification concerning Hybrid Resources, including storage charging, \ntripping, metering, injections, and capacity accreditation.122  \nThe presence of an Energy Storage Resource does not alter the fundamental nature of the \nservice. Charging behavior that affects the studied configuration will be evaluated as part of the \nZG Impact Assessment, consistent with MISO’s treatment of charging in the DPP study process. \nThe Hybrid Resource remains subject to the same fundamental requirement that its operation \ncomply with the ZGIS limitation and the equipment and configuration studied by MISO. \nHybrid Resources also are subject to the ZGIA’s separate-metering requirements. MISO \ntherefore will be able to distinguish the generation and load components and verify compliance \nwith the applicable Interconnection Service limitation.123 \nFinally, MISO does not interpret the phrase “firm interconnection service” in Tariff Section \n69.A.4 as excluding ZG Interconnection Service any more than it would exclude ER \n \n120  MISO Transmittal at 43. \n121  MISO Transmittal at 12-16, 21-22, 26-28, 41-43; proposed Attachment X §§ 3.2.5, 3.10.1; proposed ZGIA Arts. \n7.1, 7.1.1, 9.7.4.7. \n122  Clean Energy Protest at 26-29. \n123   MISO Transmittal at 41; Keyser at 38."},{"page":21,"startToken":5689,"endToken":5999,"text":"Interconnection Service.   MISO notes that “firm interconnection service” is not a defined term in \nModule E-1. Any ambiguity that may exist in how Section 69.A.4 applies to specific types of \nInterconnection Service under Attachment X was not created by the ZGIA Filing and should not \nimpede Commission acceptance of this filing. MISO also notes that the quoted language in Section \n69.A.4 applies only for the limited period of time before operating data becomes available. This \nsaid, MISO understands Clean Energy’s concerns and would not object to a compliance directive \nrequiring MISO to clarify that the term “firm interconnection service” is intended to refer to \ndeliverability.  MISO has already included revisions to the Tariff sheets included in the ZGIA \nFiling to provide that Resources with ZG Interconnection Service are considered deliverable to the \nZG Associated Load.124  This is consistent with the intent of MISO’s proposal and reflects how \nMISO would have interpreted the requirements of Section 69.A.4 even without further revisions. \n \nJ. \nMISO Agrees with Certain Suggested Drafting Corrections. These Limited \nCorrection Do Not Undermine the Proposal. \n \nMISO appreciates commenters identifying potential drafting errors or language \ninconsistencies.  After carefully reviewing the comments and protest submitted in this docket, \nMISO agrees that the following limited language corrections are consistent with MISO’s proposal \nand improve the clarity of the Tariff language.  Accordingly, MISO would welcome compliance \ndirective to make these changes: \n1. \nMISO agrees with Clean Energy that the references  GIP Section 3.2.3.2 in \nproposed Attachment X Section 3.2.5.1 and Attachment X, Appendix 19 Section \n4.1.4.1 was intended to refer to GIP Section 3.2. be revised to refer to proposed \nsection 3.2.5.2 and should be revised accordingly.  \n \n124  See proposed revisions to Section 69.A.3.1.g Part A and Part B."},{"page":22,"startToken":5999,"endToken":6323,"text":"2. \nMISO agrees that the intent of Section 9.7.4.7 of the ZGIA is intended to limit the \noutput of the Generating Facility with ZG Interconnection Service to the current \nneed of the ZG Associated Load, rather than to the ZG Associated Load’s peak \ndemand over some prior period when ZG Associated Load is drawing power below \nthat peak level. MISO therefore agrees that the use of the word Demand, as defined \nin Module A, may be confusing. MISO believes that any confusion on this point \ncan be clarified by revising Section 9.7.4.7 of the ZGIA to refer to the “amount of \nEnergy currently being withdrawn by the ZG Associated Load”. Consistent with \nthis revision, MISO would also welcome a compliance directive to revise the \ndefinition of Transient Tolerance Window as follows: \nTransient Tolerance Window: shall mean the period of time after a \nreduction or loss of load by the ZG Associated Load by the end of which \nwindow the Generating Facility with ZG Interconnection Service must have \nreduced its injections output to an amount not greater than the Load amount \nof Energy current being withdrawn by the ZG Associated Load. The \nTransient Tolerance Window shall be no greater than 20 seconds, and is \nfurther described by the Business Practices Manual for Large Load. The \nTransient Tolerance Window will be subject to Transmission Owner local \nplanning criteria. \n \nThese revisions are clarifying in nature and will not change how MISO intends to \nimplement ZG Interconnection Service and are consistent with MISO’s original \nproposal. \n4.  MISO does not object to changing references to “injections” to instead refer to \n“output” in GIP Section 1, Attachment X—Appendix 19 Section 1, and Attachment \nA—Appendix 19 Section 9.7.4.7 as suggested by Clean Energy.  MISO does not \nbelieve that that the current use of the word “injections” is problematic because the \nproposed ZGIA Tariff language, supporting testimony, and transmittal letter are"},{"page":23,"startToken":6323,"endToken":6620,"text":"very clear that non-injection refers to injection past the substation to which the \nGenerating Facility and ZG Associated Load are connected.  “Injection” therefore \nrefers to the Generating Facility sending power through the Point of Interconnection \nto the Point of Withdrawal, which may involve power flowing over a transmission \nelement at that substations for a short distance.  This said, the term “output” \naccomplishes the same purpose as “injection” in the cited areas and therefore would \nnot substantively change MISO’s proposal. Accordingly, MISO would not object \nto a directive requiring this revision on compliance.    \n5. \nMISO has also heard from stakeholder since filing the ZGIA that an  \nmisalignment exists between some working in Section 3.11.3 and Sections 3.11.4 \nof Attachment X.  On the third and fourth line of proposed Section 3.11.4, the \nlanguage reads “Transmission Provider will complete the ZG Facilities Study and \nthen tender a draft ZG Interconnection Agreement.”  Section 3.11.4 Section states: \nTransmission Provider shall tender a draft pro forma ZGIA or ZGIA… \nwithin five (5) Business Days after the Interconnection Customer \ncommunicates its election to proceed with ZG Interconnection Service, and \ncomplete any unfinished portion of the Facilities Study and tender the \nresults to Interconnection Customer within the timeframe specified in \nSection 3.11.2 of these GIP. \n \nThe proposed language in Section 3.11.4 properly states MISO’S proposed process \nand matches the description included in the Transmittal letter. However, the \ninclusion of the word “then” in Section 3.11.3 can be read to suggest that MISO \nwill complete the unfinished portion of the Facilities Study prior to tendering the \nGIA rather than tendering the draft GIA and then tendering the results of any \nunfinished portion of the Facilities Study within the timeframe specified in Section"},{"page":24,"startToken":6620,"endToken":6885,"text":"3.11.2. To avoid confusion and align with the proposal as described in Section \n3.11.2. and 3.11.4, MISO requests a limited compliance directive to revise the first \nsentence of Section 3.11.3 to state “Transmission Provider will complete the ZG \nFacilities Study within the timeframe specified by Section 3.11.2 of this GIP  and \nthen tender a draft ZG Interconnection Agreement within the timeframe specified \nby Section 3.11.4 of this GIP”. Such a directive would not change the process from \nthat explained in the ZGIA Filing and in surrounding Tariff Sections but will be \nuseful to avoid timing confusion by Interconnection Customers. \nMISO submits that these corrections do alter the fundamental design or operation of ZGIS and a \nlargely ministerial clarifications. Such limited drafting corrections provide no basis to reject or \ndelay an otherwise just and reasonable proposal. \nK. \nConsumers’ Jurisdictional Concerns Do Not Require Modification of the \nZGIA. \n \nConsumers asks the Commission to preserve state authority over retail loads and retail cost \nrecovery, prevent MISO’s regional processes from becoming prerequisites to state authorization \nof retail service except as necessary to provide jurisdictional transmission service, and preserve \nsufficient information for state regulators to perform their statutory responsibilities.125  \nThe proposal already respects that jurisdictional divide. The proposed definition of ZG \nInterconnection Service expressly states that ZGIS does not provide a right to serve, or a right to \nTransmission Service to serve, ZG Associated Load or a retail customer except as permitted by \napplicable state law.126 \n \n125  Consumers Comments at 2-3. \n126   MISO Transmittal at 16."},{"page":25,"startToken":6885,"endToken":7134,"text":"The ZGIA addresses the generator-interconnection component of the arrangement. It does \nnot establish retail rates, authorize retail service, determine retail cost recovery, or otherwise \ndisplace applicable state authority. MISO takes no position on whether the Commission should \naddress Consumers’ requested assurances other than to note that because these matters are outside \nof the scope of MISO’s proposal,  to the extent that the Commission determines to include such \nassurances in its order, this should not such discussion should not impact Commission acceptance \nof MISO’s proposal. \nIII. \nCONCLUSION \nFor the foregoing reasons, MISO respectfully requests that the Commission accept the \nproposed Tariff revisions establishing ZG Interconnection Service and the ZGIA, effective \nOctober 18, 2026, as requested, subject to the limited clarifications identified herein, and reject \nrequests to delay implementation, impose additional program limitations, or condition acceptance \nupon resolution of distinct large-load, transmission-service, or generator-interconnection reforms \noutside the scope of this proceeding \nIV. \nCOMMUNICATIONS \nMISO requests waiver of Rule 203(b)(3)127 of the Commission’s Rules of Practice and \nProcedure to the extent necessary to permit the designation of more than two persons for service \non behalf of MISO in this proceeding and requests all communications related to this filing be \ndirected to: \nChristopher D. Supino \n    Managing Senior Corporate Counsel \nMidcontinent Independent  \nSystem Operator, Inc. \n720 City Center Drive \nCarmel, Indiana 46032 \nJames C. Holsclaw \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-7970 \n \n127  18 C.F.R. § 385.203(b)(3) (2026)."},{"page":26,"startToken":7134,"endToken":7311,"text":"Telephone: (317) 249-5400 \ncsupino@misoenergy.org  \nmkessler@misoenergy.org   \n \njholsclaw@calfee.com  \n \nV. \nNOTICE AND SERVICE \nMISO has served a copy of this filing electronically, including attachments, upon each \nperson designated on the official service list compiled by the Secretary as well as on all Tariff \ncustomers, MISO Members, Member representatives of transmission owners and non-\ntransmission owners, as well as all state commissions within the MISO Region and the \nOrganization of MISO States.  The filing has been posted electronically on MISO’s website at \nhttps://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter. \nVI. \nCONCLUSION \nWHEREFORE, MISO respectfully requests that the Commission dismiss the complaint in \nits entirety.  \nRespectfully submitted, \n/s/ Christoper D. Supino \n \nChristopher D. Supino \n    Managing Senior Corporate Counsel \nMidcontinent Independent  \nSystem Operator, Inc. \n720 City Center Drive \nCarmel, Indiana 46032 \nTelephone: (317) 249-5400 \ncsupino@misoenergy.org  \n \nJames C. Holsclaw \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-7970 \njholsclaw@calfee.com \n \nAttorneys for the Midcontinent Independent \nSystem Operator, Inc. \nDATED: September 23, 2026"},{"page":27,"startToken":7311,"endToken":7395,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day e-served a copy of this document upon all parties listed \non the official service list compiled by the Secretary in the above-captioned proceeding, in \naccordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and \nProcedure (18 C.F.R. § 385.2010). \n \nDated this 23rd day of September 2026, in Carmel, Indiana. \n/s/ Dawn Kaminski \nDawn Kaminski  \nMidcontinent Independent  \nSystem Operator, Inc.  \n720 City Center Drive  \nCarmel, IN 46032  \n317-249-5400"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":141,"startToken":0,"endToken":552},{"p":3,"at":141,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":851,"startToken":552,"endToken":658},{"p":3,"at":851,"title":"II. ANSWER","method":"printed heading","endPage":3,"endAt":864,"startToken":658,"endToken":660},{"p":3,"at":864,"title":"A. The ZGIA Is a Just and Reasonable Standalone Interconnection Service That","method":"printed heading","endPage":5,"endAt":1230,"startToken":660,"endToken":1262},{"p":5,"at":1230,"title":"B. ZGIS Is a Limited Zero-Injection Service, and the Transient Tolerance","method":"printed heading","endPage":8,"endAt":1427,"startToken":1262,"endToken":2122},{"p":8,"at":1427,"title":"C. MISO Appropriately Establishes Performance-Based System Protection","method":"printed heading","endPage":10,"endAt":1025,"startToken":2122,"endToken":2707},{"p":10,"at":1025,"title":"D. The Twenty-Second Maximum Transient Tolerance Window Has a","method":"printed heading","endPage":12,"endAt":342,"startToken":2707,"endToken":3165},{"p":12,"at":342,"title":"E. The ZGIA Provides Appropriate Operational Visibility and Verification.","method":"printed heading","endPage":13,"endAt":947,"startToken":3165,"endToken":3530},{"p":13,"at":947,"title":"F. MISO’s Study and Model-Reconciliation Processes Protect Existing DPP","method":"printed heading","endPage":16,"endAt":1403,"startToken":3530,"endToken":4475},{"p":16,"at":1403,"title":"G. The ZGIA Provides Appropriate Transparency.","method":"printed heading","endPage":18,"endAt":1033,"startToken":4475,"endToken":4947},{"p":18,"at":1033,"title":"H. Additional Aggregate or Temporal Limits Are Unnecessary Given the Limited","method":"printed heading","endPage":20,"endAt":446,"startToken":4947,"endToken":5480},{"p":20,"at":446,"title":"I. MISO’s Treatment of Hybrid Resources Is Consistent with the Limited Nature","method":"printed heading","endPage":25,"endAt":596,"startToken":5480,"endToken":6969},{"p":25,"at":596,"title":"III. CONCLUSION","method":"printed heading","endPage":25,"endAt":1128,"startToken":6969,"endToken":7034},{"p":25,"at":1128,"title":"IV. COMMUNICATIONS","method":"printed heading","endPage":26,"endAt":106,"startToken":7034,"endToken":7146},{"p":26,"at":106,"title":"V. NOTICE AND SERVICE","method":"printed heading","endPage":26,"endAt":670,"startToken":7146,"endToken":7231},{"p":26,"at":670,"title":"VI. CONCLUSION","method":"printed heading","endPage":27,"endAt":0,"startToken":7231,"endToken":7311},{"p":27,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":27,"endAt":541,"startToken":7311,"endToken":7395}]}