{"document":{"slug":"rec-20260923-5149","title":"Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026","issued":"2026-09-23","accession":"20260923-5149","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Northern Virginia Electric Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20260923-5149_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260923-5149","tier":"record","sha256":"e73143e6cbd3e1d405819db40936752cc705298aacea66ae2311c97a1a55daf8","pages":24,"tokens":8396,"emptyPages":[],"textThemes":["credit","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":289,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \n \n) \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF \nNORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. TO MOTION FOR LEAVE \nTO ANSWER AND ANSWER OF PJM INTERCONNECTION, L.L.C. \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric \nCooperative, Inc. (“NOVEC”) respectfully submits this motion for leave to answer and answer to \nPJM Interconnection, L.L.C.’s (“PJM”) motion for leave to answer and answer (“PJM Answer”)2 \nto NOVEC’s August 21, 2026, protest (“NOVEC Protest”)3 of the July 31, 2026, filing by PJM \nto revise its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement \nAmong Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement \n(“RBP”).4  \nFor the reasons set forth herein and in the NOVEC Protest, the Commission should reject \nthe RBP as unjust and unreasonable. If the Commission does not reject the RBP, it should \nrequire revisions on compliance to eliminate or substantially reduce the nearly $2 billion \ncollateral requirement that the RBP Proposal would impose on NOVEC, or set the collateral \nrequirement for settlement and hearing judge procedures as suggested by PJM.5  \n \n1 18 C.F.R. §§ 385.212-213.  \n2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer, Docket No. ER26-3380-000 (Sep. 10, \n2026) (Accession No. 20260910-5296) (“PJM Answer”). \n3 Northern Virginia Electric Cooperative, Inc., Protest, Docket No. ER26-3380-000 (Aug. 21, 2026) (Accession No. \n20260821-5307) (“NOVEC Protest”).  \n4 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) \n(Accession No. 20260731-5214) (“RBP Proposal”). \n5 PJM Answer at 92-93."},{"page":2,"startToken":289,"endToken":686,"text":"2 \n \nI. \nMOTION FOR LEAVE TO ANSWER \n \nNOVEC respectfully requests leave to submit this answer. The Commission regularly \nallows answers for good cause shown, such as when the answers help ensure a more accurate and \ncomplete record, clarify the issues, or provide useful and relevant information that will assist the \nCommission in its deliberative process.6 This answer will correct PJM’s mischaracterizations of \nthe context of the RBP framework, the unjust and unreasonable character of the RBP proposal, \nand the need to substantially revise PJM’s proposed collateral requirements for the Load Serving \nEntities (“LSE”) RBP Buyers. In addition, this answer provides useful and relevant information \nthat will assist the Commission in its deliberative process. To the extent that this answer does not \naddress an issue raised in PJM’s answer, that should not be construed as agreement with PJM. \nII. \nANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON \nTHE RBP PROPOSAL \nA. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed \ncollateral requirement that cause that proposal to be disconnected from its stated \npurpose and fundamentally onerous and not just or reasonable. \nWith this answer, NOVEC includes a supplemental affidavit from Mr. Coscia.7 Mr. \nCoscia approaches the PJM collateral requirement from a methodological perspective.8 He points \nout that the amount of collateral should be related to the risk that an LSE fails to pay an RBP \nCharge and PJM’s methodology does not secure against that loss because it is focused on the risk \nthat a large load fails to materialize.9 Mr. Coscia challenges PJM’s use of a uniform Credit \n \n6 See, e.g., City Utils. of Springfield, Mo. v. Sw. Power Pool, Inc., 168 FERC ¶ 61,085, P 51 (2019) (“We accept [the] \nanswers…because they have provided information that assisted us in our decision-making process.”), order on reh’g \n& clarification, 170 FERC ¶ 61,024 (2020); Morgan Stanley Capital Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 \nFERC ¶ 61,017, at 61,036 (2000) (accepting an answer as “helpful in the development of the record”). See also, \nHawtree Creek Farm Solar, LLC, 179 FERC ¶ 61,048, P 21 (2022); California Ridge Wind Energy, LLC, 175 FERC \n¶ 61,110, P 25 (2021); Pleinmont Solar 1, LLC, 173 FERC ¶ 61,126, P 18 (2020). \n7 See Supplemental Coscia Affidavit included with the instant filing.  \n8 Id. P 8.  \n9 Id. PP 9-16."},{"page":3,"startToken":686,"endToken":987,"text":"3 \n \nRate.10 He then turns to a discussion of the opt-out and the undefined MW amount to be \nsecured.11 The Commission should also eliminate the resulting subsidization of the PJM capacity \nmarket by NOVEC and a relatively small number of other LSEs that would be primarily \nresponsible for providing financial security for the contracts that PJM would enter into with RBP \nResources. Mr. Coscia reviews PJM’s explanation of the collateral overlap between the RBP \nCharge collateral and the Peak Market Activity under Attachment Q.12 He concludes his affidavit \nby addressing the need for a reduction mechanism for the collateral obligation, discussing the \nstakeholder process, and opining on the need for a comprehensive overhaul of the credit \nmethodology in the hearing and settlement judge procedures.13 \nB. The capacity shortfall experienced by PJM resulted from a combination of causes in \naddition to growth of large customer load. \n \nPJM recognized in its original filing that the capacity shortfall it is seeking to address is \nthe result of many causes, stating that “it is well-documented and recognized that supply and \ndemand in the PJM Region have converged, as a significant portion of PJM’s thermal generation \nfleet have retired while replacement resources are arriving at a slower pace than the \nunprecedented load growth” and “[t]ogether, these factors have strained the RPM Auction’s \nability to procure sufficient capacity to meet the PJM Region Reliability Requirement in recent \ncapacity auctions.”14 Despite the other causes, PJM in answering NOVEC now maintains that \n“[t]he entire PJM Region is facing a capacity shortfall because entities like NOVEC contracted \nto serve new large loads on an unprecedented scale at an extremely rapid pace—without \n \n10 Id. PP 17-25.  \n11 Id. PP 26-37. \n12 Id. PP 38-45. \n13 Id. PP 46-61. \n14 RBP Proposal at 28."},{"page":4,"startToken":987,"endToken":1433,"text":"4 \n \nrequiring any associated new capacity.”15 PJM’s new interpretation of the context in which it \nurges the Commission to consider its filing is premised on two incorrect presumptions. \n \nFirst, NOVEC does not have any control over which customers receive electric service. \nNor does NOVEC have a say in which customers choose to site in NOVEC’s service territory. \nNOVEC has an obligation under state law to serve its load, and NOVEC follows state law.  \n \nSecond, unlike Regional Transmission Organizations (“RTO”) like the Midcontinent \nIndependent System Operator, Inc. (“MISO”), where the capacity market is a backup mechanism \nand LSEs are primarily responsible for meeting their resource adequacy requirements through \nbilateral arrangements,16 in PJM the Reliability Pricing Model (“RPM”) is the primary \nmechanism for LSEs to procure capacity. The Base Residual Auction in the RPM may allow \nLSEs to bilaterally contract for their capacity needs,17 but PJM operates the RPM to “ensure that \nenough capacity is procured, at a reasonable cost, to maintain reliable grid operations” and the \nrules do not indicate a maximum amount that LSEs can receive from PJM’s relevant capacity \nauctions.18  \n \nFor most utilities, the primary option is to buy capacity in the RPM, and there is no \nrequirement for an LSE to bring its own new capacity.19 There is no basis for PJM’s criticism \n \n15 PJM Answer at 89.  \n16 See Midcontinent Indep. Sys. Operator, Inc., 170 FERC ¶ 61,215, P 13 (2020) (“In other words, unlike the \ncentralized capacity constructs used in the Eastern RTOs/ISOs, MISO’s Auction is not—and has never been—the \nprimary mechanism for its LSEs to procure capacity.”) (emphasis in original). \n17 PJM Business Practice Manual No. 18 at § 1.2.1 (“Under RPM, each LSE that serves load in a PJM Zone during \nthe Delivery Year shall be responsible for paying a Locational Reliability Charge equal to their Daily Unforced \nCapacity Obligation in the Zone multiplied by the Final Zonal Capacity Price applicable to that Zone. LSEs may \nchoose to hedge their Locational Reliability Charge obligations by directly offering and clearing resources in the \nBase Residual Auction and Incremental Auctions or by designating self-supplied resources (resources directly \nowned or resources contracted for through unit-specific bilateral purchases) as self-scheduled to cover their \nobligation in the Base Residual Auction.”) (emphasis added). \n18 PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, P 3 (2025). \n19 PJM is now seeking to impose such an obligation through the pending Interim Resource Adequacy Service \n(“IRAS”) filing in Docket No. ER26-3515. PJM Interconnection, L.L.C., Proposal to Establish Interim Resource \nAdequacy Service and a Large Load Registry, Docket No. ER26-3515-000 (Aug. 13, 2026) (Accession No. \n20260813-5118) (“IRAS Filing”)."},{"page":5,"startToken":1433,"endToken":1747,"text":"5 \n \nthat NOVEC did not secure its own generation, because NOVEC expected to procure capacity \nthrough the RPM as intended by the PJM Tariff. That does not make the shortfall NOVEC’s \nfault, or even its responsibility, as PJM now asserts. \n \nBy filing the RBP, PJM is conceding that its RPM did not function as intended because \nthere is a shortfall. The Commission should consider the RBP Proposal in light of the true \ncontext, namely that there are multiple causes of the present shortfall, that NOVEC reasonably \nrelied on the RPM to procure its capacity, and that NOVEC is being forced to finance the \nconstruction of generation that will provide benefit to the region, as well as post an excessive \ncollateral obligation to do so. \nC. The Commission should exercise its authority under NRG to require PJM to adopt \nthe voluntary RBP framework approved in the stakeholder process, or in the \nalternative, reject the RBP Proposal with guidance on filing a voluntary iteration. \n \nThe Commission should exercise its authority under NRG to require PJM to revise its \nRBP framework to conform to the voluntary, subscription-based, stakeholder-approved model, \nas NOVEC argued in its protest.20 PJM’s arguments do not establish that a voluntary model \nwould not work. PJM contends that “a voluntary, subscription-based framework would not \nprocure sufficient new capacity to meet demand and, in fact, would be highly likely to fail to \ncover that shortfall.”21 By way of evidence, PJM asserts that a voluntary framework is the “status \nquo”22 and that under the status quo, LSEs have not entered into bilateral agreements.23 PJM’s \nobservation that LSEs have not entered into bilateral agreements prior to the filing of the RBP is \nimmaterial and irrelevant. As NOVEC explained above, the RPM does not depend on bilateral \n \n20 NOVEC Protest at 24-26. \n21 PJM Answer at 16.  \n22 Id. at 14. \n23 Id. at 15."},{"page":6,"startToken":1747,"endToken":2131,"text":"6 \n \narrangements. The RPM is intended to set prices needed to attract adequate generation and \nshould not have to rely on LSEs promising out-of-market payments to function. \n \nThat does not mean that the paradigm might not be subject to change on a going-forward \nbasis and, indeed it should be subject to change if it is not working as currently designed. But the \npossible need for change is not grounds to criticize or blame market participants for conducting \nbusiness in accordance with the current paradigm.  \n \nAs NOVEC explained in its protest, the voluntary model would allow the load to \nparticipate in the RBP or be interruptible.24 PJM’s own IRAS filing in Docket No. ER26-3515 is \npremised on the same mechanism to incentivize LSEs and load to “Bring Your Own New \nCapacity” (“BYONC”).25 Under IRAS, if new large loads do not participate with BYONC, they \nare subject to curtailment if PJM would order it and, to avoid the risk of curtailment, the new \nlarge loads are expected to bring their own new generation resources. Thus, it is puzzling why \nPJM maintains that a voluntary RBP model would not work but maintains that its IRAS proposal \nis just and reasonable and effective. \n \nIn addition, a voluntary RBP model is more likely to be effective because many \ncustomers have already agreed to bear their costs through the Ratepayer Protection Pledge. \nWhile NOVEC is not, contrary to PJM’s assertion,26 a signatory to the Ratepayer Protection \nPledge, NOVEC is supportive of the data center industry’s efforts to hold retail customers \n \n24 NOVEC Protest at 25 (“In NOVEC’s view, that control was critical to the success of the RBP process, which \nshould embody a bottom-up, rather than a top-down approach. The bottom-up process gives truly interested \ndevelopers the option to subscribe to pay the RBP costs rather than accept an interruptible form of service which \nPJM has proposed in Docket No. ER26-3515 (the Interim Resource Adequacy Service or ‘IRAS’). Contrary to the \nPJM Board’s determination, the voluntary subscription framework would provide sufficient assurance that capacity \nequal to the identified near-term shortfall would actually be procured. Paired with IRAS, committed load is \nadequately incentivized to participate to avoid an interruptible service—their business models rely on reliable \nservice.”). \n25 See IRAS Filing at 23. \n26 PJM Answer at 59."},{"page":7,"startToken":2131,"endToken":2544,"text":"7 \n \nharmless by funding their own power and transmission needs. As PJM points out, many such \nentities have committed to “‘build, bring, or buy the new generation resources and electricity \nneeded to satisfy their new energy demands, paying the full cost of those resources whether by \nbuilding, or buying from, new or otherwise additive power plants.’”27 Participating in a voluntary \nRBP framework would be a natural choice to accomplish what these customers have already \nagreed to do. \n \nPJM manifests a double standard in its comparison of a voluntary framework to its \npreferred RBP alternative. PJM specifically criticizes NOVEC for recognizing that a voluntary \nRBP may not procure the entire shortfall,28 arguing that NOVEC’s perspective “would \neffectively contradict the fundamental core reliability goal of the RBP to acquire the capacity \nshortfall….”29 However, in its transmittal letter, PJM conceded that because “RBP Resources \nshall not be partially cleared…there exists the possibility that PJM may clear a set of resources \nwith a cumulative RBP UCAP MW total that does not exactly match the Final RBP Target.”30 In \nother words, PJM may not procure the entire shortfall through its own process. NOVEC should \nalso add that, because of the expedited time frame, it is possible that an insufficient number of \nresources may bid at the required price level.31 It is unclear to NOVEC why PJM is willing to \n \n27 Id. (quoting Ratepayer Protection Pledge, The White House (Mar. 4, 2026), \nhttps://www.whitehouse.gov/releases/2026/03/ ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T]).  \n28 Without acknowledging NOVEC’s observation that the IRAS would mitigate the consequences of any failure to \nprocure the entire MW target through the voluntary RBP. NOVEC Protest at 25-26.  \n29 PJM Answer at 16-17.  \n30 RBP Proposal at 79.  \n31 NOVEC Protest at 5 (“PJM’s timeline raises additional concerns that adversely affect the market. The success of \nthe RBP depends on generators offering in sufficient quantities and at competitive prices. With only three weeks to \nmake informed decisions based on the final, effective version of the RBP, some participants may not be able to \nprepare offers in time to participate. Indeed, PJM has requested FERC approval by September 29 so it can begin the \nRBP auction on September 30, which means that participants are expected to make decisions with impacts that last \nthe better part of two decades in a span of a few weeks and without knowing what the actual rules or approved state \nregulator allocations will be.”)."},{"page":8,"startToken":2544,"endToken":2850,"text":"8 \n \nbear the risk that its preferred RBP alternative does not cover the shortfall in capacity, but views \nany risk that the voluntary model does not procure the total shortfall as a fatal flaw.  \n \nThe imposition of a voluntary process would also eliminate the contradiction of PJM’s \nopt-out mechanism. As Mr. Coscia explains in his supplemental affidavit, PJM justifies its opt-\nout provision as addressing a limited regulatory gap faced by non-public utilities whose rates are \nnot regulated by the states.32 In its answer, PJM argues that those customers are at the risk of an \n“overbuy” if large loads fail to materialize in the absence of state regulation.33 But the result is \nthat one Virginia cooperative, Old Dominion Electric Cooperative, could opt out but another, \nNOVEC, could not.34 NOVEC’s exposure is not reduced by being state regulated because its \ncustomers may still have to absorb the cost of an overbuy notwithstanding state regulation.35 Mr. \nCoscia opines that “the economic rationale for the opt-out would be stronger if eligibility tracked \nthe overbuy risk PJM identifies rather than state rate-regulatory status standing alone.”36  \nThere are two ways to effectuate Mr. Coscia’s opinion and align risk with the opt-out and \nNOVEC would support either. The Commission could extend the opt-out to all non-public \nutilities in recognition of the presence of the overbuy risk. Or the Commission could require PJM \nto adopt the voluntary, subscription-based RBP framework which would give all utilities and \ntheir customers the ability to manage their own exposure. The voluntary RBP framework \neliminates the need for an opt-out by allowing utilities and their customers to enter arrangements \nthat can effectively manage any overbuy risk.  \n \n32 Supplemental Coscia Affidavit at P 26.  \n33 PJM Answer at 30.  \n34 Supplemental Coscia Affidavit at PP 27-28.  \n35 Id. P 29.  \n36 Id. P 31."},{"page":9,"startToken":2850,"endToken":3246,"text":"9 \n \n \nThe Commission should “exercise its authority under NRG to implement the voluntary \nsubscription model the stakeholders approved as part of the CIFP process.”37 The PJM \nstakeholders sent the PJM Board an unambiguous message by achieving a clear consensus on a \nsingle proposal from more than a dozen considered.38 PJM’s observation that some stakeholders \nhave supported the filed iteration of the RBP does not detract from the consensus achieved by the \nstakeholders on the voluntary, subscription-based framework.39 PJM’s removal of the ability of \nLSEs to accept RBP obligations fundamentally undermined the RBP process, which was \nintended to embody a bottom-up,40 rather than top-down approach, and was one part of an \ninterconnected series of proposals intended to comprehensively address PJM’s resource \nadequacy challenges.41 The Commission should honor the consensus achieved by the \nstakeholders rather than allow PJM to pick and choose proposals it likes without regard for the \ncompromises that led to the whole package, a process that undermines trust in the stakeholder \nprocess.  \nD. The Commission should reject PJM’s argument that NOVEC misrepresents the \ncost-allocation standard because the RBP filing violates the Commission’s cost-\ncausation principles. \n \nNOVEC explained in its protest that the RBP violates the Commission’s cost-causation \nprinciple because it would assign all costs to one cause of the capacity shortfall without \n \n37 NOVEC Protest at 24.  \n38 Id. 24-25.  \n39 PJM Answer at 13. \n40 As Mr. Coscia explains in his supplemental affidavit, the voluntary RBP MWs would be fully secured and would \nnot expose ratepayers to additional risk above PJM’s proposal. Supplemental Coscia Affidavit at P 58. \n41 NOVEC Protest at 25; East Kentucky Power Cooperative, Inc., Protest, Docket No. ER26-3380-000, at \nAttachment 1 Affidavit of Adam Bednarcyzk at P 16 (Aug. 21, 2026) (Accession No. 20260821-5322) (“EKPC \nProtest”) (“By contrast, PJM's filed proposal largely treats procurement, cost allocation, and the forthcoming IRAS \nprocess as separate constructs. PJM states that the RBP does not depend on the IRAS framework. That separation \nbreaks the direct connection between the entity creating the incremental reliability need and the consequences of \nfailing to mitigate that need. Unlike the Coalition proposal, the filing does not establish a unified framework that \ncarries responsibility from procurement through settlement and operational consequences. As a result, it does not \nprovide the same transparent and traceable path for ensuring that large-load customers and their suppliers remain \nreliability neutral.”)."},{"page":10,"startToken":3246,"endToken":3602,"text":"10 \n \nrecognizing the impact of other causes, such as generation retirement driven by state policy \nchoices,42 and because it creates benefits for other capacity customers in PJM by forcing \ngeneration subsidized by NOVEC to bid into the capacity market as a price-taker.43 As NOVEC \nclarified, “PJM’s requirement that RBP Resources offer at $0 can affect the RPM clearing price, \nand any resulting price reduction benefits capacity purchasers beyond the LSEs required to bear \nthe incremental costs of supporting those resources.”44 The reasoning behind the premise is \nsimple. The cost-causation principle requires the Commission to have “an articulable and \nplausible reason” to believe that the benefits are roughly commensurate with the costs.45 \n \nPJM argues that NOVEC “seeks to establish a false standard for cost allocation \napproaches.”46 PJM argues that “all approved rates reflect to some degree the costs actually \ncaused by the customer who must pay them”47 and “[t]o the extent an entity causes the costs to \nbe incurred, it will have to pay its share.”48 PJM stresses that the Commission is not required to \nensure full or perfect cost causation,49 and argues that the RBP Proposal “easily meets this \nstandard.”50 PJM argues that it meets this standard because it tracked the Load Adjustments to \nthe zones/areas where they occurred and allocated the costs to the Electric Distributor zones and \nthis was the most granular way available to PJM to allocate costs.51 \n \nGranularity is beside the point. PJM cannot assert that NOVEC has articulated a false \nstandard because PJM did not acknowledge or even engage with NOVEC’s arguments. PJM did \n \n42 NOVEC Protest at 9-14. \n43 Id. at 15-17.  \n44 Id. at 17.  \n45 Illinois Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009). \n46 PJM Answer at 62.  \n47 Id. (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (internal citations omitted)). \n48 PJM Answer at 62.  \n49 Id. (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C. Cir. 2014)).  \n50 PJM Answer at 62. \n51 Id. at 62-63."},{"page":11,"startToken":3602,"endToken":4030,"text":"11 \n \nnot challenge NOVEC’s argument that there are other causes for the shortfall besides load \ngrowth or that other customers will benefit from NOVEC paying for generation to bid as a price-\ntaker in the RPM. NOVEC pointed out that thousands of MWs of retirements were caused by \nstate policies and that a reduction in generation is a key cause of the shortfall.52 Bidding as price-\ntakers can cause lower RPM prices because those offers “crowd out other capacity that is priced \nat a higher, cost-based rate” and thereby produce a lower clearing price.53 PJM explained that to \n“the extent an entity causes the costs to be incurred, it will have to pay its share,” which is \nexactly how NOVEC described the cost-causation principle and why PJM’s proposed cost \nallocation violates that principle. \n \nThe Commission “may never approve unjust and unreasonable rates by allocating costs to \nthose who reap little to no benefit…nor may it choose not to allocate costs to ‘those who cause \nthe costs to be incurred and reap the resulting benefits.’”54 In other words, the Commission \ncannot approve a cost-allocation scheme that ignores beneficiaries and other causes of the \nshortfall. If it does not reject the RBP Proposal as unjust and unreasonable, the Commission \nshould modify PJM’s cost-allocation approach to reflect the benefits received by the rest of PJM \nby adjusting the RBP Charges to account for those benefits and reducing the RBP collateral \nrequirement to reflect those same benefits. \n \n52 NOVEC Protest at 11.  \n53 New Jersey Board of Public Utilities v. FERC, 744 F.3d 74, 85 (3d Cir. 2014). It goes without saying that in \naddition to the price depressive effect benefiting other customers, it also distorts the PJM capacity market signals by \naltering the price signals being sent. The Commission should not lose sight of the fact that a cost-based intervention \nis not going to solve the problems with PJM’s market structure. It becomes, as former Chairman Christie warned, \nanother iteration of the “perpetual tweaking” needed to keep the RPM moving forward. NOVEC Protest at 13 \n(quoting Mark C. Christie, It’s Time to Reconsider Single-Clearing Price Mechanisms in U.S. Energy Markets, 44 \nEnergy L.J. 1, 26 (2023)). Before the Commission approves another kludge for the RPM, it should consider, as \ndiscussed above, whether the voluntary option interfaces better with PJM’s market design. \n54 El Paso Elec. Co. v. FERC, 76 F.4th 352, 362 (5th Cir. 2023) (quoting Nat’l Ass’n of Reg. Util. Comm’rs, 475 \nF.3d 1277, 1285 (D.C. Cir. 2007) (emphasis added))."},{"page":12,"startToken":4030,"endToken":4393,"text":"12 \n \nE. The collateral requirement is unjust and unreasonable because it is duplicative, \nexcessive, and the initial credit rate is insupportably high. The collateral \nrequirement should be revised to allow other forms of collateral.  \na. The collateral requirement is subjective, unduly discriminatory, and unjust \nand unreasonable because it is excessive. \n \nPJM’s proposed collateral requirement is not just and reasonable. PJM asserts that its \nmethodology strikes an appropriate balance between protecting PJM’s markets and ensuring \nmarket participants have adequate flexibility to manage their collateral requirements.55 PJM \nnotes that the Commission has cautioned against overly conservative credit requirements that are \npoorly correlated to credit risk that would impose costs.56 PJM’s methodology does not strike \nthat balance. \n \nAs a threshold matter, not even PJM can reasonably claim that its proposal ensures \nmarket participants have adequate flexibility to manage their collateral requirements. Market \nparticipants have no flexibility to manage their collateral requirements. They must post the full \namount, with no exceptions for individual credit risk and subject only to intermittent and \nirregular reductions at PJM’s discretion.57 PJM has set the obligation so high for NOVEC that \nneither option is practicable.58 As Mr. Coscia explained in his affidavit, “[c]ash is not available” \nbecause the obligation “is approximately eight times [NOVEC’s] entire cash and temporary \ninvestments and approximately 3.4 times all of its current and accrued assets.”59 A letter of \ncredit, if one could be had, “would have to be supported by [NOVEC’s] balance sheet.”60 The \n \n55 PJM Answer at 84. \n56 Id. (quoting PJM Interconnection, L.L.C., 186 FERC ¶ 61,055, P 28 (2024)).  \n57 RBP Proposal, Attachment A at § 18.8(b)(i)(A) (“...the RBP Credit Rate shall equal $1.5 million, as may be \nreduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral \nis greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an \namount sufficient to cover the total existing RBP Charges obligations….”) (italics added). \n58 NOVEC Protest, Rollins Affidavit at 3:7-16.  \n59 NOVEC Protest, Coscia Affidavit at P 64 (“NOVEC Coscia Affidavit”). \n60 Id. P 65."},{"page":13,"startToken":4393,"endToken":4835,"text":"13 \n \nRural Utilities Service holds a mortgage over most of NOVEC’s assets and its loan documents \nlimit the incurrence of additional secured obligations and liens.61 The carrying cost would \nconsume NOVEC’s entire operating margin even under the most favorable circumstances, but, \nrealistically, the cost is likely to be multiples of the margin, forcing NOVEC into a permanent \nnet-loss position for the foreseeable future due to following the rules set out before it and then \nhaving those rules drastically changed without any consideration.62 \n \nPJM cannot reasonably claim that the collateral requirement is necessary to protect PJM’s \nmarkets because it has, at best, a limited correlation to the risk to PJM’s markets.63 Mr. Coscia \nexplained that the RBP settles as a contract for differences and NOVEC pays the difference \nbetween the RBP price and the RPM clearing price for the year, multiplied by its allocated RBP \nUCAP MW.64 NOVEC does not pay the RBP price and when the RPM clears above it, NOVEC \nreceives a payment.65 As Mr. Coscia explains, PJM has not linked the collateral obligation to the \nrisk of loss because it is based on the RBP Resources’ revenue and not what would remain \npayable on default.66 The credit rate is theoretical, dismissive of likely outcomes and \ndisconnected from NOVEC’s obligation: \nBecause the Credit Rate makes no reference to RPM, the requirement bears \nno stable relationship to what the cooperative will owe. Where RPM clears \nclose to the RBP price the difference approaches zero while the collateral \ndoes not move. Where RPM clears far below it the difference widens and \n \n61 Id. \n62 Id. P 66 (“Carrying cost compounds the problem. Taking the most favourable assumption available — that a letter \nof credit can be obtained at 100 basis points — the annual cost would be approximately $19.5 million. The \ncooperative reported patronage capital and operating margins of approximately $20.8 million for 2025, after existing \ninterest expense of approximately $0.8 million. At 100 basis points the carrying cost alone would consume \napproximately 94 percent of that margin; at 150 basis points, approximately 141 percent; at 200 basis points, \napproximately 188 percent; and at 300 basis points, approximately 281 percent. Each is between approximately \ntwenty-five and seventy-five times the cooperative's entire existing annual interest expense, and each would recur \nfor as long as the requirement remains outstanding.”).  \n63 See Supplemental Coscia Affidavit at P 12 (“Gross contractual value therefore is not itself a measure of loss on \ndefault.”) \n64 NOVEC Coscia Affidavit at P 38; see also RBP Proposal at 59-60.  \n65 See NOVEC Coscia Affidavit at P 38.  \n66 Supplemental Coscia Affidavit at PP 9-12."},{"page":14,"startToken":4835,"endToken":5169,"text":"14 \n \nthe collateral is unchanged again. A requirement calibrated to exposure \nwould vary with the second price; this one is fixed against the first.67 \n \nMr. Coscia points out that a collateral requirement is ordinarily derived from three components: \nan identified position, a price at which the position would be replaced, and a period of time of \nexposure.68 The size of the residual loss should be identified before the amount of collateral to \nabsorb it is decided and “a formula based on approximately one-half of gross contractual value \ndoes not establish that relationship.”69 Mr. Coscia attempted to estimate total exposure based on \nRPM clearing prices over 13 years and the full 15 years based on a conservative assumption that \nthe RBP would clear at $555/MW-day.70  \n \nIt is worth noting that PJM clarified that no collateral requirement would be required for \nyears that RBP Resources are not in service.71 Mr. Coscia calculated an exposure at $200 to $290 \nmillion for two years without RBP Resources receiving the RPM clearing price because they \nwere not in service.72 NOVEC will not have charges for that period, which means that his \nestimate for the 13-year exposure is closer to reality. Even using his lifetime exposure of 15 \nyears, the total collateral obligation never dropped below the total exposure and was as high as \nninefold.73 As a multiple of the 13-year exposure (the true lifetime exposure), the collateral \nobligation now ranges, depending on the RPM clearing prices, from multiples of 1.1 to 1,149. \nAlthough Mr. Coscia does not forecast the RPM clearing prices, he does opine that if the RBP \n“does not resolve the shortfall and the Interim Resource Adequacy Service is not implemented, \n \n67 NOVEC Coscia Affidavit at P 40.  \n68 Id. P 41.  \n69 Supplemental Coscia Affidavit at PP 15-16.  \n70 NOVEC Coscia Affidavit at PP 41-51.  \n71 PJM Answer at n.234.  \n72 NOVEC Coscia Affidavit at P 47. \n73 See id. P 49 (showing demonstrative table)."},{"page":15,"startToken":5169,"endToken":5655,"text":"15 \n \nprices would in my opinion almost certainly clear above the present cap once the collar comes \noff, at or near the level PJM has itself simulated.”74 \n \nMr. Coscia comments that the table shows “that the filed requirement exceeds the \nexposure at every path in the range.”75 PJM did not in its answer to NOVEC’s protest address the \nsubstance of the affidavit Mr. Coscia submitted on behalf of NOVEC, perhaps because it \nconfirms that PJM’s collateral obligation is excessive. Requiring NOVEC to post collateral that \nprotects the PJM market potentially multiples above its total exposure is excessive and does not \nsatisfy the Commission’s requirement that the collateral obligation strike an appropriate balance \nbetween protecting the market and facilitating market participation. “Magnitude is the measure \nof” limiting access to the market.76 NOVEC’s nearly $2 billion collateral requirement is close to \na third of all collateral PJM held in 2025 to cover all market activities by all Market \nParticipants.77  \n \nFurther, NOVEC demonstrated that the collateral obligation contemplated by the RBP \nwas partly duplicative of the collateral amounts already held by PJM.78 PJM argues that the RBP \ncollateral is not duplicative of the Peak Market Activity collateral PJM requires for transactions \n \n74 Id. P 50.  \n75 Id. P 51.  \n76 EKPC Protest, Attachment 2 Affidavit of Carl F. Coscia at P 61 (“EKPC Coscia Affidavit”) (“The Commission’s \nstandard has two sides: an RTO must minimize the risk that a default is socialized among non-defaulting \nparticipants, while ‘ensuring that the credit or collateral requirements are not so stringent that they unnecessarily \ninhibit access to the marketplace.’ Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at P 19 (2009). Magnitude is the \nmeasure of the second. In what follows I compare the proposed requirement to the collateral PJM actually holds, to \nthe relationship PJM maintains between collateral and market activity, and to the annual charge the requirement \nsecures. On each comparison the proposed requirement stands apart from anything in PJM’s experience.”). \n77 See id. P 63. \n78 NOVEC Protest at 21-22 (“Second, the calculation assumes that the RBP buyers have to collateralize the entire \n$555/MW-day. In actuality, the RBP Charges will be the RBP clearing-price average (which can be less than \n$555/MW-day) net of revenues from the capacity auction. Effectively, RBP buyers are providing collateral to ensure \nthat everyone in PJM pays the capacity costs associated with the RBP Resources. RBP buyers themselves already \nprovide PJM collateral to ensure that they pay their capacity rates under Attachment Q, and so do all other capacity \nbuyers. PJM is requiring duplicative collateral — at the most, RBP buyers should only have to provide collateral for \nthe incremental cost of the RBP clearing price above the weighted RPM clearing price for the relevant delivery year. \nThat is the only cost that RBP buyers will actually have to pay, and thus the only payments that need to be \ncollateralized.”)."},{"page":16,"startToken":5655,"endToken":6064,"text":"16 \n \nin PJM’s markets because the “long-term” obligations to RBP Resources are “unlike any other \ncommitment in PJM.”79 PJM distinguishes the two obligations by arguing that the capacity \nobligation is “backward-looking” and “to the extent an LSE defaults on its obligations, the \nprovider of last resort for that load becomes responsible on a going-forward basis.”80 In contrast, \nPJM “envisions that an LSE’s obligation to pay RBP Charges should not be shunted to a \nprovider of last resort—the idea is that the large load driving the need for the RBP should bear \nthese costs—through its LSE, consistent with the Ratepayer Protection Pledge.”81 But even RPM \ncapacity is procured through the Base Residual Auction held approximately three years before \nthe Delivery Year and every “LSE carries, as a matter of course, a forward RPM capacity \nobligation extending roughly three years.”82    \n \nNotwithstanding PJM’s unclear argument premised on retail choice,83 the RBP Proposal \nindeed requires NOVEC to provide duplicative collateral.84 NOVEC provides PJM with a \ncollateral amount that guarantees NOVEC will pay the recurring capacity costs every day. When \nNOVEC’s load grows by the Load Adjustment, it will likely provide additional collateral to \naccount for the new capacity purchased above the original amount. At the same time, NOVEC \nwould also be required to provide a collateral amount to PJM to guarantee its payment of the \nRBP Charge. The RBP Charge is a contract for difference.85 NOVEC will pay (or receive) the \ndifference between the RBP Charge and the capacity clearing price. But PJM determines \n \n79 PJM Answer at 76-77.  \n80 Id. at 77-78. \n81 Id. \n82 Supplemental Coscia Affidavit at P 41.  \n83 It is unclear what PJM means here because the paradigm of a “provider of last resort” is only applicable in a retail \nchoice state. NOVEC does not operate in a retail choice state. But, to the extent that NOVEC is itself functionally a \nprovider of last resort because it is, as previously explained, obligated by law to serve customers within its \ndesignated service area, PJM is already shunting RBP Charges to the provider of last resort by imposing such \nobligations directly on NOVEC, and doing so without knowing whether NOVEC will be able ensure that the large-\nload customers will bear these cost.  \n84 NOVEC Protest at 21-22; see also EKPC Protest at 23; EKPC Coscia Affidavit at P 98. \n85 RBP Proposal at 59-60; NOVEC Coscia Affidavit at P 38."},{"page":17,"startToken":6064,"endToken":6444,"text":"17 \n \nNOVEC’s RBP collateral obligation as if NOVEC were paying the entire RBP Charge, which \nmeans that NOVEC is providing collateral for the cost of capacity of its RBP MWs and \nproviding collateral for the RBP clearing price, and not just for the difference between the RBP \nprice and the capacity clearing price. The capacity obligation has a three-year forward-looking \ntime horizon which is, functionally, renewed each year for a successive three-year period for \nexisting load. In effect, PJM is seeking to require NOVEC to post collateral for the same MWs \nof capacity twice. In particular, Mr. Coscia demonstrates that in the final three-year period, “an \nordinary LSE and an RBP buyer carry forward RPM obligations of the same horizon at \nessentially the same price.”86 Coupled with the magnitude of the $2 billion requirement, the \nduplicative nature of the collateral obligation makes it excessive, and so the Commission should \nfind that the RBP Proposal is not just and reasonable and reject it.87  \nb. The Commission should require PJM to allow other methods of posting \ncollateral. \n \nPJM argues that the collateral obligation should only be secured with cash or a letter of \ncredit because “there is a likelihood that even entities with investment grade credit may see their \nfinancial condition deteriorate over 15 years.”88 PJM overstates the risk because the RBP \nCharges that NOVEC could be responsible for represent, in any given year, a tiny fraction of the \ncollateral PJM would require NOVEC to post.89 Further, while NOVEC agrees that it is possible \nfor credit ratings to change, the greatest threat to NOVEC’s credit rating is PJM’s own RBP \n \n86 Supplemental Coscia Affidavit at P 44.  \n87 PJM commits to eliminating a sentence from proposed Tarif, Attachment DD to eliminate “confusion that RBP \nCharges may be captured in the Peak Market Activity credit tool, and therefore its omission from the accepted \nlanguage would facilitate proper understanding of the RBP Credit rules.” PJM Answer at n.259. The tariff language \nremains in the proposal because PJM has not filed to revise it. Moreover, the structure still assumes that the RBP \ncollateral’s pricing is not redundant of NOVEC’s other future obligations.  \n88 PJM Answer at 85; EKPC Coscia Affidavit at P 53.  \n89 NOVEC Coscia Affidavit at P 50."},{"page":18,"startToken":6444,"endToken":6845,"text":"18 \n \ncollateral requirement.90 PJM’s estimate that there is an 11% likelihood that an entity with a \nBBB rating could transition to default status is problematic because it is based on a study that \nincludes non-utilities and because it does not consider NOVEC as an individual creditor.91 Mr. \nCoscia pointed out that PJM “bills [NOVEC] weekly, observes whether it pays, and has an \nunbroken record of that performance for as long as [NOVEC] has taken service in its markets.”92 \nIn short, NOVEC maintains an investment-grade credit rating and has always met its obligations \nin PJM.93  \n \nPJM’s refusal to allow an unsecured credit allowance is inconsistent with every other \ncredit policy it maintains. With respect to PJM’s existing credit policy, “[t]he general credit \nrequirement is sized to Peak Market Activity, computed from a participant’s own observed \nbilling history; unsecured credit allowances are keyed to creditworthiness and tangible net worth; \nand requirements are recalculated on an ongoing basis.”94 PJM’s only explanation for why it is \nrefusing to allow an unsecured credit allowance is that in PJM’s experience, “Market Participants \nused their full amount of unsecured credit to cover their Peak Market Activity credit obligations” \nduring hot and cold-weather events.95 As Mr. Coscia cogently explains, “[c]redit migration over \na fifteen-year horizon is a legitimate credit consideration” but “it does not explain why \n[NOVEC’s] credit condition should be ignored.”96 In contrast with the buyers, PJM’s seller \n \n90 Id. PP 30-31; Supplemental Coscia Affidavit at P 20 (“A generalized corporate transition matrix does not measure \nthe effect of imposing collateral comparable to or exceeding an obligor’s balance sheet. A requirement of that \nmagnitude can consume liquidity, encumber assets, absorb credit-facility capacity, and impose recurring financing \nexpense. The requirement can therefore affect the very credit quality the migration analysis is used to predict.”). \n91 PJM Answer at n.245 (citing Default, Transition, and Recovery: 2025 Annual U.S. Corporate Default And Rating \nTransition Study, S&P Global Inc. (June 12, 2026), https://www.spglobal.com/ratings/en/regulatory/article/default-\ntransition-and-recovery-2025-annual-us-corporate-default-and-rating-transition-study-s101688003 \n[https://perma.cc/7LTL-J8SQ]). \n92 NOVEC Coscia Affidavit at P 25.  \n93 NOVEC Protest, Rollins Affidavit at 3:3-4 (“NOVEC has an investment-grade credit rating. Further, to my \nknowledge, NOVEC has always paid its obligations related to PJM membership.”). \n94 EKPC Coscia Affidavit at P 17.  \n95 PJM Answer at 85.  \n96 Supplemental Coscia Affidavit at P 18."},{"page":19,"startToken":6845,"endToken":7251,"text":"19 \n \nmethodology allows for reductions that take account of credit quality.97 In a section 205 \nproceeding, PJM bears the burden to show that its proposal is just and reasonable and this \nstatement is insufficient explanation for why no allowance for unsecured credit should be \nextended to RBP Buyers. If the Commission does not reject the RBP Proposal as unjust and \nunreasonable, it should exercise its authority under NRG to require PJM to allow alternative \ndemonstrations of creditworthiness to secure the collateral requirement.98 \nF. The RBP Proposal is unjust and unreasonable because it does not address \nunderlying practical implementation issues and imposes unrealistic requirements. \n \nPJM relies in substantial part on the availability of mitigation to the RBP Charges and \ncollateral obligation but gives only a limited window to make those arrangements. NOVEC \nwould have to procure 1,619.2 MW to offset its obligation in the RBP auction.99 As a practical \nmatter, NOVEC would not be able to prudently enter into the necessary transactions to procure \nsuch a large amount of power. The procurement process would require multiple counterparties \nand transactions, credit diligence, commercial and risk analyses, contract negotiations, internal \napprovals, and potential regulatory review, which could take from four to twelve months to \nnegotiate.100 PJM has given NOVEC—and every RBP Buyer—ninety days. \n \nThe expedited process rests on the viability of unproven assumptions. The obligation is \nfixed for 15 years even if the underlying load is delayed, reduced, canceled, or never \nmaterializes. For instance, PJM is relying on NOVEC’s 2025 aggregate LSE-level forecast even \n \n97 Id. P 24.  \n98 NOVEC Protest at 24.  \n99 RBP Proposal, Attachment C, Croop Affidavit at P 47. \n100 NOVEC Protest at 7 (“NOVEC in particular is prejudiced because the Initial Load Adjustment MW that it would \nneed to offset to eliminate its obligation in the RBP auction is so high (1,619.2 MW) that NOVEC is unlikely to be \nable to secure bilateral contracts with new generators for anything approaching that amount… As a rural, not-for-\nprofit cooperative and a transmission-dependent distribution utility, NOVEC faces a procurement challenge that is \nunusual both in magnitude and structure. A prudent procurement of more than 1,600 MW cannot reasonably be \ncompleted within the period PJM proposes. A procurement of this magnitude would likely require multiple \ncounterparties and transactions, each involving counterparty and credit diligence, commercial and risk analysis, \ncontract negotiations, internal approvals, and potentially regulatory review.”)."},{"page":20,"startToken":7251,"endToken":7567,"text":"20 \n \nthough NOVEC’s 2026 forecast is lower. Or, for another example, PJM proposes to permit \nforecast-based RBP MW offsets for committed demand-side participation but does not explain \nhow those commitments are reconciled with actual load.101 If the load does not materialize, it \ndoes not exist to be curtailed. \n \nEven if it were feasible to secure the RBP MW offsets, the procedures for an RBP Buyer \nto offset are not just and reasonable. Even though the Initial RBP Target is only 6,831.3 MW, \nPJM would require buyers to procure over 9,000 MW to eliminate their RBP allocations.102 \nNOVEC would have to procure over 300 MW above its RBP allocation to remove its RBP \nallocation.103 The excess MW provide additional value to the PJM capacity market for which the \nRBP Buyer is not compensated. Further, any reductions NOVEC achieves are in effect shared \nwith other RBP Buyers and vice versa, which, in addition to being unfair, creates a perverse \nincentive to free ride on others’ efforts.104 These provisions also mean that NOVEC will not \nknow what its individual obligation is until the auction’s conclusion, which can create a material \neconomic impact for a participant with as much exposure as NOVEC has.105 \n \nPJM also asserts that NOVEC could use its existing collateral obligations with its \ncustomers to secure this new obligation or issue “low-interest, ratepayer-backed bonds” to meet \nthe requirement.106 True or not, it is immaterial to the question of whether the collateral \nrequirements asked by PJM are just and reasonable. To the extent that NOVEC can, NOVEC \nwill explore every commercially reasonable option available to it if the collateral obligation is \n \n101 RBP Proposal at 40.  \n102 Id., Attachment C, Croop Affidavit at P 46. \n103 NOVEC Protest at 17.  \n104 Id. at 17-18.  \n105 Supplemental Coscia Affidavit at PP 35-36.  \n106 PJM Answer at 90; id. n.274."},{"page":21,"startToken":7567,"endToken":7910,"text":"21 \n \nimposed as PJM has requested. NOVEC requires a just and reasonable collateral obligation \nbased on a just and reasonable methodology, which the RBP Proposal does not have. \nG. If the Commission does not reject the RBP Proposal, the Commission should \nrequire PJM to revise the PJM Tariff to precisely reflect commitments made in the \nPJM Answer. \n \nIn its answer, PJM clarified that collateral for a Delivery Year will be based only on RBP \nUCAP MW committed for that year and that “no collateral would be required for RBP Resources \n[that] are not in service for that Delivery Year, and no RBP Charges would be assessed.”107 \nNOVEC supports this clarification. However, NOVEC has reviewed Section 18.8(b)(i)(A), and \nPJM’s interpretation relies on the meaning of the term “committed” as it pertains to that section. \nPJM should be required to revise the proposed Tariff section to explicitly state that NOVEC and \nother LSEs with RBP obligations will not be required to post collateral for RBP Resources that \nare not in service. Mr. Coscia points out that Section 18.6(e) permits a resource to remain \ncommitted for up to three Delivery Years and Section 18.8(b)(i)(A) does not have an “in-\nservice” limitation, creating the risk that NOVEC could post collateral for an RBP Resource that \ndoes not operate during those three Delivery Years without clarification.108 \n \nPJM also stated in its answer that the total collateral obligation “can decline as the \nremaining exposure declines.”109 The Commission should not approve the RBP Proposal with a \nprovision that grants PJM the discretion not to reduce a collateral requirement that NOVEC has \nshown is already excessive. “A reduction that occurs only after remaining gross payments fall \nbelow posted collateral can leave the requirement unchanged for years despite changes in market \nprices, remaining tenor, or credit condition.”110 Given the enormous sums involved, the Tariff \n \n107 Id. at n.234. \n108 Supplemental Coscia Affidavit at PP 32-34.  \n109 PJM Answer at 88.  \n110 Supplemental Coscia Affidavit at P 49."},{"page":22,"startToken":7910,"endToken":8194,"text":"22 \n \nshould incorporate a mechanism to automatically reduce the collateral obligation with “objective, \ntariff-based standards…[that] state the frequency of review, the inputs used, the circumstances \nrequiring a reduction, and the time within which excess collateral is returned.”111 \nH. While PJM has not proposed a just and reasonable collateral framework for the \nRBP, if the Commission does not reject the RBP Proposal, the Commission should \nfollow PJM’s suggestion to set the matter for further proceedings to decide the \ncollateral obligation.  \n \nTo be clear, NOVEC believes that the RBP Proposal is not just and reasonable and \nshould be rejected. However, to the extent that the Commission is inclined to approve the RBP \nProposal, NOVEC would support the Commission “resolving the applicable buyer-side LSE \nRBP Credit Rate through additional procedures” as PJM suggests.112 \n \nPJM indicates that it consents to keying the credit rate “to the actual MW-weighted \naverage of the levelized procurement cost of all selected RBP Sell Offers that results from the \nRBP and not the maximum of such value” and references the NOVEC Protest for clarity on the \ndescription.113 “Using the actual RBP procurement price would reduce the requirement if the \nprocurement clears below $555/MW-day” but “[i]t would not resolve the underlying \nmethodology.”114 NOVEC supports this minor modification to the credit requirement, but would \nstress to the Commission that, in order to be most conducive to settlement, the scope of the \nhearing and settlement judge procedures set on the RBP Buyer-side credit requirement should \nencompass the entire collateral framework.115  \n \n \n111 Supplemental Coscia Affidavit at P 50.  \n112 PJM Answer at 93.  \n113 Id. at 92-93.  \n114 Supplemental Coscia Affidavit at P 57.  \n115 See id. P 58."},{"page":23,"startToken":8194,"endToken":8318,"text":"23 \n \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the \nCommission grant this motion for leave to answer, accept NOVEC’s answer, and reject the RBP \nProposal. In the alternative, NOVEC respectfully requests that the Commission order PJM to \nmodify the RBP as requested herein to eliminate or substantially reduce the collateral obligation \nand set the entire RBP buyer-side credit requirement for hearing and settlement judge \nprocedures. \n \nRespectfully submitted, \n \n  //s// Alan I. Robbins \n \nAlan I. Robbins \nDebra D. Roby \nThomas B. Steiger III \nWashington Energy Law LLP \n900 17th Street. N.W., Suite 500-A  \nWashington, D.C. 20006 \nTel: (202) 326-9313 \nEmail: arobbins@washingtonenergylaw.com \ndroby@washingtonenergylaw.com \ntsteiger@washingtonenergylaw.com \n \nCounsel to Northern Virginia Electric Cooperative, Inc. \n \n \n \n \nDated: September 23, 2026."},{"page":24,"startToken":8318,"endToken":8396,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in this proceeding. \nDated at Washington, D.C. this 23rd day of September, 2026. \n \n  //s// Jessika Dziechciowska  \n \nJessika Dziechciowska \nEnergy Practice Analyst \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A \nWashington, D.C. 20006 \nTel: (202) 326-9308  \nEmail: jdziechciowska@washingtonenergylaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":290},{"p":2,"at":5,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":900,"startToken":290,"endToken":427},{"p":2,"at":900,"title":"II. ANSWER TO PJM’S ANSWER TO THE PROTESTS AND COMMENTS ON","method":"printed heading","endPage":2,"endAt":979,"startToken":427,"endToken":441},{"p":2,"at":979,"title":"A. Mr. Coscia’s Supplemental Affidavit explains the many flaws in PJM’s proposed","method":"printed heading","endPage":3,"endAt":810,"startToken":441,"endToken":814},{"p":3,"at":810,"title":"B. The capacity shortfall experienced by PJM resulted from a combination of causes in","method":"printed heading","endPage":5,"endAt":738,"startToken":814,"endToken":1557},{"p":5,"at":738,"title":"C. The Commission should exercise its authority under NRG to require PJM to adopt","method":"printed heading","endPage":9,"endAt":1104,"startToken":1557,"endToken":3018},{"p":9,"at":1104,"title":"D. The Commission should reject PJM’s argument that NOVEC misrepresents the","method":"printed heading","endPage":12,"endAt":6,"startToken":3018,"endToken":4031},{"p":12,"at":6,"title":"E. The collateral requirement is unjust and unreasonable because it is duplicative,","method":"printed heading","endPage":19,"endAt":540,"startToken":4031,"endToken":6929},{"p":19,"at":540,"title":"F. The RBP Proposal is unjust and unreasonable because it does not address","method":"printed heading","endPage":21,"endAt":179,"startToken":6929,"endToken":7595},{"p":21,"at":179,"title":"G. If the Commission does not reject the RBP Proposal, the Commission should","method":"printed heading","endPage":22,"endAt":287,"startToken":7595,"endToken":7949},{"p":22,"at":287,"title":"H. While PJM has not proposed a just and reasonable collateral framework for the","method":"printed heading","endPage":23,"endAt":6,"startToken":7949,"endToken":8195},{"p":23,"at":6,"title":"III. CONCLUSION","method":"printed heading","endPage":24,"endAt":0,"startToken":8195,"endToken":8318},{"p":24,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":24,"endAt":541,"startToken":8318,"endToken":8396}]}