{"document":{"slug":"rec-20260924-5153","title":"Motion for Leave to Answer and Limited Answer of ON Energy Storage, Inc. in response to comments and protests re Midcontinent Independent System Operator,…","issued":"2026-09-24","accession":"20260924-5153","docket":"ER26-3650-000","group":"MISO interconnection reliability requirements for large loads","filer":"ON Energy Storage, Inc.","kind":"protest","file":"sources/filings/text/20260924-5153_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260924-5153","tier":"record","sha256":"fcd1c66b536adbc4f495e99330448b63767da63997499de6b1782a5fd1dded30","pages":16,"tokens":4496,"emptyPages":[],"textThemes":["study"]},"pages":[{"page":1,"startToken":0,"endToken":264,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nMidcontinent Independent System Operator, Inc. \n \n \nDocket No. ER26-3650-000 \n \nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER \nOF ON ENERGY STORAGE, INC. \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission” or “FERC”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213, \nON Energy Storage, Inc. (“ON.energy”) respectfully moves for leave to answer and submits this \nLimited Answer in response to comments and protests concerning the transition and \ngrandfathering provisions in the Midcontinent Independent System Operator, Inc. (“MISO”) \nproposal to establish Interconnection Reliability Requirements for Large Loads (“IRR Proposal”).1 \nMOTION FOR LEAVE TO ANSWER \n \nRule 213(a)(2) generally prohibits an answer to a protest or an answer unless otherwise \nordered by the decisional authority.2 To the extent leave is required, good cause exists to accept \nthis Limited Answer. ON.energy filed a timely motion to intervene in this proceeding on \nSeptember 18, 2026.3 The September 18, 2026 and September 21, 2026 pleadings present \ncompeting positions on the scope and design of MISO’s transition provisions. Google LLC \n(“Google”) supports MISO’s proposed grandfathering framework; the Data Center Coalition \n(“DCC”) and Rowan Digital Infrastructure, LLC (“Rowan”) urge greater reliance on objective \n \n1 Midcontinent Indep. Sys. Operator, Inc., Interconnection Reliability Requirements for Large Loads, Docket No. \nER26-3650-000, Accession No. 20260828-5278 (Aug. 28, 2026) (“MISO Filing”). \n2 18 C.F.R. § 385.213(a)(2). \n3 Doc-less Motion to Intervene of ON Energy Storage, Inc., Docket No. ER26-3650-000, Accession No. 20260918-\n5094 (Sept. 18, 2026)."},{"page":2,"startToken":264,"endToken":652,"text":"2 \nevidence of commercial maturity; Entergy Services, LLC (“Entergy”) identifies recently \ndeveloped and late-stage projects that may not satisfy MISO’s proposed grandfathering criteria; \nand Verrus LLC (“Verrus”) generally supports MISO’s transition approach while seeking clarity \nfor phased development.4 Other commenters and protestors, including the Organization of MISO \nStates, Inc. (“OMS”), the Iowa Office of the Consumer Advocate and the other signatories to its \njoint protest (“Joint Protestors”), and Sierra Club and the other Public Interest Organizations \n(“PIOs”), question whether development status should determine exemption from the ramp and \nride-through requirements, whether proposed Section 37A.II.3 permits MISO to act before an \nexempt Large Load causes a reliability problem, and how MISO will address the combined effect \nof multiple exempt Large Loads.5 \n \nThis Limited Answer responds to the positions already placed before the Commission by \nexplaining why legitimate reliance interests can be protected through objective and time-limited \ntransition treatment without foreclosing prospective assessment of the reliability consequences of \nride-through exemptions. In particular, ON.energy asks the Commission to condition acceptance \nof MISO’s transition provisions on an outside energization date for Large Loads that receive \ntransition treatment based on the MTEP/EPR Condition or any broader commercial-maturity test, \nand to direct MISO to clarify that exempt Large Loads will be subject to prospective, system-level \nreliability review under proposed Section 37A.II.3. ON.energy does not seek to introduce new \n \n4 See Comments of Google LLC, Docket No. ER26-3650-000, at 2-5 (Sept. 18, 2026) (“Google Comments”); Motion \nto Intervene and Comments of the Data Center Coalition, Docket No. ER26-3650-000, at 26-29 (Sept. 18, 2026) \n(“DCC Comments”); Limited Protest of Entergy Services, LLC, Docket No. ER26-3650-000, at 3 (Sept. 18, 2026) \n(“Entergy Protest”); Comments of Rowan Digital Infrastructure, LLC, Docket No. ER26-3650-000, at 2-3 (filed Sept. \n21, 2026) (“Rowan Comments”); Comments of Verrus, LLC in Support of MISO’s Interconnection Reliability \nRequirements for Large Loads, Docket No. ER26-3650-000, at 4 (Sept. 18, 2026) (“Verrus Comments”). \n5 See Notice of Intervention and Comments of the Organization of MISO States, Inc., Docket No. ER26-3650-000, at \n4-5 (Sept. 18, 2026) (“OMS Comments”); Joint Protest of the Iowa Office of the Consumer Advocate et al., Docket \nNo. ER26-3650-000, at 3-4 (Sept. 18, 2026) (“Joint Protest”); Protest of Sierra Club et al., Docket No. ER26-3650-\n000, at 2-3, 12-15 (Sept. 18, 2026) (“PIO Protest”)."},{"page":3,"startToken":652,"endToken":934,"text":"3 \ntechnical ride-through, modeling, or equipment requirements, and it does not address the other \nissues raised in the comments and protests, such as the rule of reason, the definition of Large Load, \nforecasting, or cost allocation. ON.energy submits this Limited Answer promptly after the \npleadings it addresses and well before the requested December 4, 2026 effective date. Acceptance \nof this Limited Answer will assist the Commission in resolving an issue already squarely presented \nby the parties and will not delay the proceeding or prejudice any participant. The Commission has \naccepted otherwise-prohibited answers where they provide information that assists its decision-\nmaking.6 \n \nAccordingly, ON.energy respectfully requests that the Commission grant leave to answer \nand consider the Limited Answer below. \nLIMITED ANSWER \nI. \nON.energy Supports Reasonable, Objective, and Time-Limited Transition Treatment \nthat Protects Legitimate Reliance Interests. \n \nMISO’s filing establishes three principal transition categories. First, Large Loads with a \nService Commencement Date on or before December 4, 2026 are fully exempt from proposed \nSection 37A with respect to the portion of the Large Load that has procured Transmission Service \nas of the Service Commencement Date. Second, projects that meet the MTEP/EPR Condition are \nsubject to the visibility requirements but are exempt from the ramp and ride-through requirements. \nThird, certain projects submitted to EPR between June 19 and October 31, 2026 may receive a \nride-through waiver only if MISO determines that the exemption would not have an adverse \n \n6 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 187 FERC ¶ 61,202, at P 24 (2024); Sw. Power Pool, Inc., 194 \nFERC ¶ 61,031, at P 58 (2026) (accepting answers because they provided information that assisted the Commission \nin its decision-making process)."},{"page":4,"startToken":934,"endToken":1247,"text":"4 \nreliability impact and compliance would impose significant costs.7 ON.energy does not challenge \nthe first category, which applies to Large Loads taking service by the proposed effective date, or \nthe third, which conditions relief on a determination that the exemption would not have an adverse \nreliability impact. ON.energy does not advocate automatic retroactive application of new ride-\nthrough requirements to facilities already operating under existing requirements. Its concern is \nwith the second category, which exempts qualifying Large Loads from the ride-through and ramp \nrequirements without any limit on when they must begin taking service. As explained below, \nON.energy asks that the second category, and any broader eligibility test the Commission may \nadopt, be bounded by an outside energization date.  \n \nON.energy agrees with these commenters that transition provisions should recognize \nlegitimate reliance interests, although it does not endorse each eligibility test they propose. For \nexample, Google emphasizes commercial certainty and investments made under the rules in effect \nwhen projects were developed.8 DCC argues that MTEP or EPR status is not a reliable proxy for \nthe commercial maturity of a Large Load project and proposes that grandfathering instead turn on \nobjective evidence of material commercial arrangements, such as executed interconnection, \ntransmission service, or utility service agreements, or major equipment orders, with qualifying \nprojects exempt from the ride-through and ramp requirements.9 Rowan similarly asks that \ntransition relief account for objective evidence of project maturity, procurement, engineering, and \nconstruction.10 Verrus generally supports MISO’s transition provisions and emphasizes the phased \nbuildout of large load campuses.11 Entergy likewise notes that certain recently developed projects \n \n7 MISO Filing, Transmittal Letter at 13-14; id., Proposed Tariff § 37A.II; id., Tab C, Prepared Direct Testimony of \nBeibei Li at 18-22 (“Li Testimony”). \n8 Google Comments at 1, 3-4. \n9 DCC Comments at 26-29. \n10 Rowan Comments at 2-3. \n11 Verrus Comments at 4."},{"page":5,"startToken":1247,"endToken":1541,"text":"5 \nand projects in the late stages of negotiations may not satisfy MISO’s proposed grandfathering \ncriteria or may qualify only for limited exemptions.12   \n \nTaken together, these comments identify a legitimate need to account for genuine late-stage \nreliance. ON.energy agrees that this need should be accommodated but believes the relief should \nbe objectively bounded in time, under whichever eligibility test the Commission accepts, including \nany test based on commercial maturity, as DCC and Rowan request. This need can be met without \nopen-ended relief for projects that are still being designed and developed. \n \nAn outside energization date would meet that need, and MISO’s second category does not \ncurrently include one. MISO explains that tying transition treatment to MTEP and EPR status \nrecognizes the “more immediate, non-speculative, nature of the Load additions,” and it describes \nthe October 31, 2026 cutoff for the third category as establishing “a finite transition period, after \nwhich prospective projects are expected to account for MISO’s ride-through requirements as part \nof their development and design.”13 The second category, by contrast, has a fixed eligibility date \nbut no limit on when a qualifying Large Load must begin taking service. DCC itself observes that, \nunder the MTEP/EPR Condition, a Large Load customer that “may have to wait several years to \ncommence operations” could nonetheless qualify for exemption based on the timing of its \nassociated transmission submissions.14 The PIOs similarly read the Commission’s directive to \npropose a “reasonable implementation period” as implying “a period after which implementation \nwill be completed.”15 An outside energization date would align the second category with MISO’s \n \n12 Entergy Protest at 3. \n13 MISO Filing, Transmittal Letter at 14; Li Testimony at 19:20-23, 22:1-4. \n14 DCC Comments at 27. \n15 PIO Protest at 14."},{"page":6,"startToken":1541,"endToken":1850,"text":"6 \nown rationale without disturbing the reliance interests of projects that are genuinely near \ncompletion.  \n \nThe Electric Reliability Council of Texas, Inc. (“ERCOT”) is addressing the same problem \nMISO faces here: establishing clear and achievable ride-through requirements that maintain \nsystem stability without being unduly burdensome to Large Loads. ERCOT’s framework shows \nthat those objectives can be pursued together, and it offers a useful model for MISO. In particular, \nERCOT’s transition framework shows that an outside energization date can work alongside the \nkind of commercial-milestone evidence DCC and Rowan propose. ERCOT’s ride-through \nexemption turns on objective milestones achieved by its November 14, 2025 grandfathering date, \nsuch as operation or written approval to energize, or executed interconnection agreements together \nwith notice to proceed and funding of the required interconnection facilities. For a Large \nComputational Load that was not required to be in ERCOT’s interim Large Load interconnection \nprocess, the exemption also requires a written attestation from the interconnecting utility and Initial \nEnergization by December 31, 2026.16 ERCOT thus tied eligibility to milestones achieved before \nits grandfathering date and, for one category of projects, to a defined outside energization date. \nThat category offers the closest parallel to MISO’s situation. ERCOT applied its outside date to \nloads that were not required to go through its interim Large Load interconnection process, and \nMISO does not currently have a Load interconnection process at all; it relies instead on MTEP and \nEPR status.17 A similarly defined outside boundary in MISO could complement, rather than \ndisplace, the objective evidence of commercial maturity urged by DCC and Rowan, and could \naddress the circumstances Entergy describes for recently developed and late-stage projects. It \n \n16 See ERCOT, Nodal Operating Guides § 2.15(1)(a)-(d) (eff. Aug. 1, 2026); see also id. § 2.6.4(1) (parallel exemption \nfrom frequency ride-through requirements). \n17 Li Testimony at 19:17-20."},{"page":7,"startToken":1850,"endToken":2143,"text":"7 \nwould also advance the commercial certainty emphasized by Google by allowing developers to \nknow in advance the period during which transition treatment is available. \n \nON.energy therefore requests that the Commission condition acceptance of the second \ntransition category on an outside energization date, so that transition treatment under that category \nis available only to Large Loads whose Service Commencement Date, the measure MISO already \nuses for the first category, occurs within approximately one year after the effective date of the new \nrequirements. ON.energy recommends approximately one year as a reasonable outer limit and \nwould leave the precise date and implementing details to MISO on compliance. If the Commission \nalso accepts DCC’s and Rowan’s requests to base eligibility on commercial commitments, the \nsame outside date should apply to that broader eligibility. A boundary of that general magnitude \nwould separate projects with genuine near-term implementation constraints from projects that \nremain sufficiently prospective to account for ride-through requirements before energization, \nconsistent with the Show Cause Order’s direction that MISO “propose a reasonable \nimplementation period to ensure minimal disruption to such existing commercial arrangements” \nand “allow a reasonable amount of time to finalize ongoing agreements that are nearing \ncompletion.”18 \nII. \nCommercial Reliance Does Not, by Itself, Resolve the Reliability Questions Presented \nby a Ride-Through Exemption. \n \nDCC would exempt qualifying projects from the ride-through and ramp requirements based \non objective evidence of commercial commitments, and Rowan would extend transition relief on \na similar basis.19 OMS and the Joint Protestors, by contrast, observe that the reliability risks of \n \n18 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 5 (2026) (“Show Cause Order”); see MISO Filing, \nTransmittal Letter at 13; Google Comments at 4. \n19 DCC Comments at 28-29; Rowan Comments at 3."},{"page":8,"startToken":2143,"endToken":2492,"text":"8 \nLarge Loads do not necessarily depend on when a load becomes operational.20 Both concerns are \nlegitimate. The existence of legitimate commercial reliance addresses a different question from \nwhether exempting a Computational Load from disturbance ride-through requirements can be \naccommodated without creating a material reliability concern. A project may have substantial sunk \ninvestment and genuine reliance interests while still presenting disturbance behavior that requires \nstudy or mitigation. Conversely, a late-stage project may present no material reliability concern \nand therefore warrant transition treatment without additional measures. ON.energy believes both \ncommercial reliance and reliability should be considered, but agrees with Google that “ensuring \nelectric reliability must remain job number one.” Where a material reliability concern is identified, \ngrid reliability should control.21  \n \nMISO’s own proposal recognizes this distinction for one category of in-flight projects. For \nprojects submitted to EPR between June 19 and October 31, 2026, MISO does not grant an \nautomatic ride-through exemption. Instead, MISO may waive the ride-through requirement only \nwhere the applicable reliability assessment demonstrates that operation without full ride-through \ncapability would not have an adverse reliability impact and compliance would result in significant \ncosts. MISO’s supporting testimony states that, where such a reliability determination cannot be \nmade, appropriate ride-through capability or mitigation would still be required.22  \n \nThat same distinction should govern any request to broaden transition eligibility for other \nin-flight projects. Objective commercial commitments may be relevant to whether a project \n \n20 OMS Comments at 5 (“reliability risks associated with Large Loads do not necessarily depend on when a load \nbecomes operational”); Joint Protest at 3 (“Large Loads have reliability impacts regardless of operational date”). \n21 Google Comments at 5; see also id. at 1; Show Cause Order at P 58 (integrating large loads “poses specific \nchallenges to transmission system operation given their size, operational behavior, and unique potential to impact the \ntransmission system”); OMS Comments at 5 (asking “whether loads that present material reliability risks should be \nsubject to appropriate reliability requirements regardless of their development status”). \n22 MISO Filing, Proposed Tariff § 37A.II.2(b)(ii); Li Testimony at 21:6-22:13."},{"page":9,"startToken":2492,"endToken":2760,"text":"9 \nqualifies for transition consideration, but they should not substitute for evaluating the reliability \nconsequences of the resulting ride-through exemption. Rowan’s own formulation reflects this \ndistinction: it would provide relief where compliance would require material redesign or \nreplacement of previously procured equipment “without a demonstrated reliability necessity.”23 \nON.energy agrees with that formulation. If the Commission broadens transition eligibility based \non commercial commitments, as DCC and Rowan request, ON.energy asks that any resulting \nexemption remain subject to MISO’s authority to require ride-through capability or other \nmitigation where MISO identifies a material reliability concern, as discussed in Section III below. \nIII. \nProspective Reliability Review Can Provide Greater Commercial Certainty While \nPreserving MISO’s Proposed Backstop. \n \nGoogle describes the “notwithstanding” language in proposed Section 37A.II.3 as \nimportant because it “allows [MISO] to continue monitoring the operational risks introduced by \ncertain large loads and modify its approach where necessary to address reliability risks.”24 \nON.energy agrees that this authority is an important backstop and should be preserved, and \nbelieves it will work best, for both reliability and commercial certainty, if MISO can apply it \nprospectively. A study before energization can identify a material reliability concern while the \ncustomer still has time to address it with less disruption, rather than after a problem has occurred \nin operation. DCC itself recognizes that “the timing of any such evaluation and the compliance \ntimeline afforded to an affected customer will determine whether revocation is a manageable \ntransition or a significant disruption to the customer’s operations.”25   \n \n23 Rowan Comments at 3. \n24 Google Comments at 5. \n25 DCC Comments at 13."},{"page":10,"startToken":2760,"endToken":3076,"text":"10 \n \nMISO’s tariff language does not expressly establish a prospective screening requirement \nfor automatically exempt facilities. The proposed tariff states that MISO may require compliance \nwhere operation of a Large Load “results in a material adverse effect” and leaves the process for \nmaking that determination, as well as the requirements to be imposed, to the Business Practices \nManual.26 The PIOs read that language as ambiguous regarding whether MISO may impose \nrequirements before an exempt Large Load has caused a reliability problem.27 DCC has separately \nraised concerns that the standards and procedures governing withdrawal of an exemption are not \nsufficiently defined in the tariff.28 ON.energy agrees in part with both concerns. Section 37A.II.3 \nshould permit MISO to act before an exempt Large Load causes a reliability problem, as the PIOs \nurge, and the criteria and process MISO will apply should be objective and known in advance, as \nDCC urges. ON.energy takes no position here on whether those details belong in the tariff or the \nBusiness Practices Manual.  \n \nON.energy believes that a prospective, study-based process can respond to both the PIOs’ \nand DCC’s concerns. For a facility that has not yet energized, MISO can evaluate expected \ndisturbance performance before operation and inform the affected customer of any identified \nreliability limitation while the customer still has an opportunity to implement ride-through \ncapability or another technically appropriate mitigation. For an operating or substantially \ncompleted facility, MISO can account for legitimate reliance interests when determining the timing \nand scope of any necessary action. In either case, ON.energy believes the relevant measure is the \nfacility’s performance at its Point(s) of Withdrawal, and it defers to MISO’s Business Practices \nManual process on the study methods and criteria used to evaluate that performance. ON.energy \n \n26 MISO Filing, Proposed Tariff § 37A.II.3. \n27 PIO Protest at 12. \n28 DCC Comments at 12-13, 15-16."},{"page":11,"startToken":3076,"endToken":3343,"text":"11 \ndoes not ask the Commission or MISO to prescribe any particular equipment, architecture, or \ntechnology. \n \nThis approach can provide developers with more certainty, not less. DCC seeks assurance \nthat exemptions, once granted, will not be “summarily revoked based on a subjective MISO \nassessment without regard to the stage of development of their facilities.”29 Rather than granting \nan exemption subject to an undefined possibility that MISO may later impose additional \nrequirements after an operating problem emerges, a prospective assessment can identify before \nenergization the circumstances in which mitigation may be required. Nothing in this approach \nrequires eliminating MISO’s Section 37A.II.3 backstop or subjecting all grandfathered loads to \nthe full requirements irrespective of demonstrated need. ON.energy therefore requests that the \nCommission accept Section 37A.II.3 and confirm, or direct MISO to clarify on compliance, that \nMISO will evaluate exempt Large Loads before energization, using objective criteria established \nin advance, and will require ride-through capability or other appropriate mitigation where that \nevaluation identifies a material reliability concern. \nIV. \nSystem-Level Review Should Consider the Aggregate Amount and Electrical \nConcentration of Exempt Computational Load. \n \nThe PIOs note that the IRR Proposal does not explain how MISO would address \ncircumstances in which Large Loads that would not individually cause a material adverse effect \non reliability could do so in combination.30 ON.energy agrees the question warrants attention and \nbelieves MISO should address it by evaluating exempt Computational Load, including load that \nhas not yet energized, in its system stability studies and by requiring an appropriate reliability \n \n29 DCC Comments at 15-16. \n30 PIO Protest at 13."},{"page":12,"startToken":3343,"endToken":3710,"text":"12 \nresponse where those studies identify a material reliability concern. Ride-through risk is not solely \nan individual-project question. The reliability consequence of an exemption can depend on the \naggregate amount, location, electrical concentration, and modeled coincident response of similarly \nsituated Computational Loads.31 A facility that may not present a material concern when evaluated \nalone may contribute to a different system response when considered with other exempt load \nexposed to the same disturbance. This kind of coincident response has already been observed in \nERCOT and in the Eastern Interconnection, where MISO also operates, and ERCOT has accounted \nfor it in its ride-through framework, as discussed below.32  \n \nSeveral parties have raised concerns regarding the amount of existing and in-flight Large \nLoad that could receive full or partial transition treatment.33 ON.energy does not contend that the \naggregate quantity cited in those pleadings would disconnect simultaneously or that a nameplate \ntotal, standing alone, establishes a reliability violation. The analysis should focus on the amount \nand electrical concentration of exempt Computational Load that could respond coincidentally to a \ncredible voltage or frequency disturbance. \n \nERCOT’s experience is relevant to MISO because the underlying mechanism does not \ndepend on market design: in any system, the question is whether the combined response of exempt \nload exposed to a common disturbance stays within that system’s stability limits. ERCOT has \nrecognized that multiple large electronic load facilities “at nearby locations could trip or transfer \n \n31 See OMS Comments at 4 (Computational Loads “can experience dramatic and coordinated changes in demand, \npotentially across multiple facilities”). \n32 See NERC, Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions at 2, 8 (Jan. 8, 2025) \n(approximately 1,500 MW of data center load reduction coincident with a July 10, 2024 transmission disturbance in \nthe Eastern Interconnection); NERC, Incident Review: Voltage-Sensitive Crypto Load Reductions at 2 (Jan. 9, 2026) \n(ERCOT identified 26 ride-through events involving indirect load loss greater than 100 MW from one or more crypto \nfacilities between January 2023 and September 2025); PIO Protest at 4-5 (describing a July 2026 event in PJM in \nwhich approximately 3.8 GW of load tripped offline). \n33 See OMS Comments at 5; Joint Protest at 3; PIO Protest at 2-3."},{"page":13,"startToken":3710,"endToken":4046,"text":"13 \nload at a level exceeding frequency and voltage stability limits during a common system \ndisturbance.”34 When asked to move its grandfathering date, ERCOT evaluated the additional \namount of exempt Large Load and concluded that expanding the exempt population could worsen \nexisting reliability risk and increase the likelihood of real-time curtailment “to maintain necessary \nSystem Operating Limits to prevent load loss exceeding frequency stability thresholds.”35 ERCOT \nalso evaluates Large Loads prospectively: new Large Loads must be included in its quarterly \nstability assessment to qualify for Initial Energization, and under its interim ride-through \nassessment it provided that energization would be conditioned on an appropriate System Operating \nLimit or Interconnection Reliability Operating Limit where the assessment identified a stability \nconcern.36 ERCOT has since reported that its studies identified a load loss limit of 3,200 MW “to \nensure frequency stability and reliable grid operations,” and that its most recent quarterly stability \nassessment identified three groups of Large Loads where a disturbance could cause a loss above \nthat limit from loads without ride-through capability operating at or near full consumption. In each \ngroup, combined approved capacity already exceeds the limit, but ERCOT reports maximum \nsimultaneous consumption well below it. ERCOT will implement constraints as actual \nconsumption approaches the limit.37 Importantly, the aggregate reliability effect of transition \ntreatment can be evaluated prospectively through system studies. MISO’s limits and load \nconcentrations will differ from ERCOT’s, and ON.energy does not ask MISO to adopt ERCOT’s \n3,200 MW limit or other ERCOT-specific thresholds. \n \n34 ERCOT Comments on Nodal Operating Guide Revision Request 282, 282NOGRR-17, at 2 (Mar. 27, 2026). \n35 Id. at 5. \n36 ERCOT, Item 9: System Operations Update, Board of Directors Meeting, slide 6 (Sept. 14–15, 2026), available at \nhttps://www.ercot.com/files/docs/2026/09/07/9-System-Operations-Update.pdf (“ERCOT Board Update”); ERCOT, \nMarket Notice M-A013126-01, Optional, Final Ad Hoc Interim Voltage Ride-Through Assessment for Large Loads \nRequesting Initial Energization Before July 1, 2026 (Jan. 31, 2026). \n37 ERCOT Board Update, slide 6."},{"page":14,"startToken":4046,"endToken":4336,"text":"14 \n \nON.energy therefore requests that the Commission direct MISO to clarify on compliance \nthat MISO will evaluate the aggregate amount and location of exempt Computational Load, \nincluding load that has not yet energized, through appropriate post-fault voltage and frequency \nstudies and other dynamic analysis, and, where those studies identify a material reliability concern, \nwill require an appropriate reliability response, such as an operating limit or other mitigation, under \ncriteria established in advance. Where the studies demonstrate that an exemption can be \naccommodated without material adverse effect, the project’s reliance interests can be respected \nwithout unnecessary additional requirements. Setting limits proactively and updating them as new \nComputational Load approaches energization, as ERCOT does, would help protect grid stability \nand give developers of facilities without ride-through capability earlier notice of any limits that \nmay apply.  \nV. \nConclusion \n \nFor the foregoing reasons, ON.energy respectfully requests that the Commission grant \nleave to answer and accept this Limited Answer. In acting on MISO’s filing and the competing \nrequests concerning transition treatment, ON.energy requests that the Commission: (1) condition \nacceptance of the second transition category on an outside energization date limiting transition \ntreatment to Large Loads whose Service Commencement Date occurs within approximately one \nyear after the effective date, with the precise date specified by MISO on compliance; (2) if it \nbroadens transition eligibility based on commercial commitments, as DCC and Rowan request, \napply the same outside date to that broader eligibility and keep any resulting exemption subject to \nSection 37A.II.3; and (3) direct MISO to clarify on compliance that, under Section 37A.II.3,  \nMISO will evaluate exempt Large Loads, individually and in the aggregate, before energization \nusing objective criteria established in advance, and will require ride-through capability or other"},{"page":15,"startToken":4336,"endToken":4414,"text":"15 \nappropriate mitigation where that evaluation identifies a material reliability concern. These \nrequests would preserve reasonable protection for legitimate reliance interests while keeping \ntransition eligibility objective and time-limited and preserving prospective, system-level \nassessment of material reliability risks. \n \n \nRespectfully submitted, \n \nON ENERGY STORAGE, INC. \n \n/s/ Lucas Fykes \nLucas Fykes \nSenior Director, Policy & Regulatory Affairs \nON Energy Storage, Inc. \n2900 SW 28th Terrace, Suite 701 \nMiami, FL 33133 \nEmail: lucas.fykes@on.energy \nPhone: (614) 254-8565 \nDated: September 24, 2026"},{"page":16,"startToken":4414,"endToken":4496,"text":"16 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding in accordance \nwith Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \n \nDated at Scottsville, Kentucky, this 24th day of September, 2026 \n \n/s/ Lucas Fykes \nLucas Fykes \nON Energy Storage, Inc. \n2900 SW 28th Terrace, Suite 701 \nMiami, FL 33133 \nPhone: (614) 254-8565"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":842,"startToken":0,"endToken":775},{"p":3,"at":842,"title":"I. ON.energy Supports Reasonable, Objective, and Time-Limited Transition Treatment","method":"printed heading","endPage":7,"endAt":1402,"startToken":775,"endToken":2048},{"p":7,"at":1402,"title":"II. Commercial Reliance Does Not, by Itself, Resolve the Reliability Questions Presented","method":"printed heading","endPage":9,"endAt":761,"startToken":2048,"endToken":2593},{"p":9,"at":761,"title":"III. Prospective Reliability Review Can Provide Greater Commercial Certainty While","method":"printed heading","endPage":11,"endAt":1204,"startToken":2593,"endToken":3246},{"p":11,"at":1204,"title":"IV. System-Level Review Should Consider the Aggregate Amount and Electrical","method":"printed heading","endPage":14,"endAt":979,"startToken":3246,"endToken":4180},{"p":14,"at":979,"title":"V. Conclusion","method":"printed heading","endPage":16,"endAt":4,"startToken":4180,"endToken":4415},{"p":16,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":501,"startToken":4415,"endToken":4496}]}