{"document":{"slug":"rec-20260928-5175","title":"Motion for Leave to Answer and Answer of Vistra Corp. in response to certain pleadings and answers filed","issued":"2026-09-28","accession":"20260928-5175","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Vistra Corp.","kind":"answer","file":"sources/filings/text/20260928-5175_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260928-5175","tier":"record","sha256":"285f851e7fe99fcd6019836d1933e4f7bf799ea9c0992c6ba6e9f030928c6e9f","pages":29,"tokens":8864,"emptyPages":[],"textThemes":["flex","adequacy","retail","registry"]},"pages":[{"page":1,"startToken":0,"endToken":226,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n) \n) \n \nDocket No. ER26-3515-000 \n \nANSWER OF VISTRA CORP. \n \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) hereby moves to answer certain \npleadings and answers filed in the above-captioned proceeding.  As the timely-filed comments in \nthis proceeding nearly universally agree, IRAS has not been shown to be just and reasonable and \nnot unduly discriminatory or preferential.  Although PJM stakeholders may disagree about the best \nway to address resource adequacy concerns in PJM, there is nearly unanimous consensus—\namongst Load Serving Entities (“LSE”), independent power producers, vertically integrated \nutilities, end-use customers, state public utility commissions, individual retail ratepayers, and \nPJM’s Independent Market Monitor—that PJM’s Interim Resource Adequacy Service (“IRAS”) \nproposal is not the way forward.   \nIt should be no surprise that IRAS has elicited such strong opposition.  Nor should it be a \nsurprise that its defenders have not put forth a convincing case in support of the proposal.  To start, \nPJM has misdiagnosed the root cause of the region’s resource adequacy issues.  PJM blames large \nloads rather than recognizing a combination of exaggerated load forecasts and capacity auction \nand interconnection delays that contribute significantly to the resource adequacy gap.  To the \n \n1 18 C.F.R. § 385.211 (2026)."},{"page":2,"startToken":226,"endToken":588,"text":"-2- \nextent a market participant is contributing to the resource adequacy gap, it is LSEs and Electric \nDistributors (“EDs”) that commit to load that they do not have the capacity to support. Addressing \nPJM’s resource adequacy quandary by penalizing large loads under IRAS’s discriminatory and ill-\nfitting framework is fraught with risk.   From there, PJM compounds its initial error by offering a \nsolution that is illegal for several independent reasons.  Finally, IRAS threatens to have the exact \nopposite effect PJM intends.  It will make the resource adequacy situation more dire because its \nfailure to include common-sense transition mechanisms and grandfathering provisions will upend \ninvestments made in reliance on the existing market rules, thereby chilling additional investment \nin the PJM region.   \nI. \nMOTION FOR LEAVE TO ANSWER  \nAlthough the Commission’s procedural rules generally do not allow answers to answers, \nthe Commission may permit them for good cause.2  The Commission frequently accepts answers \nthat clarify the issues before the Commission, ensure a complete record, or otherwise assist the \nCommission in its decision-making.3   Vistra therefore respectfully requests that the Commission \naccept this answer, which will assist the Commission with its decision-making by contextualizing \nthe record, responding to answers, and explaining why the scant support for IRAS is misplaced. \n \n2 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or \na request for rehearing, unless otherwise ordered by the decisional authority.”). \n3 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that \n“provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC \n61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s \ndecisionmaking process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that \n“clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage \nCo., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding \nthe issues raised, and will ensure a complete record”)."},{"page":3,"startToken":588,"endToken":960,"text":"-3- \nII. \nANSWER \nAs the record clearly demonstrates, IRAS has myriad fatal flaws.  An order accepting the \nIRAS proposal will not be upheld in court and, in the meantime, will cast a pall of uncertainty over \nthe PJM market, stymying investments in both new capacity and the maintenance of existing \ncapacity.  That, in turn, will further harm PJM’s resource adequacy outlook.     \nA. PJM Has Misdiagnosed the Cause of the Region’s Resource Adequacy Issues \n \nPerhaps the most fundamental of IRAS’s many flaws is that it attempts to solve the wrong \nproblem.  As parties in this proceeding have now demonstrated in several different ways, the \nsource of PJM’s resource adequacy woes is the incentive structure that PJM’s capacity market \ncreates:  incentivizing LSEs to agree to serve more load than they have generation to cover or can \nrealistically procure through the capacity market.4  When the PJM system had excess generation \nand the capacity price was clearing at or below $50/MW-day, this was an entirely rational and \nefficient strategy.  That became particularly problematic in this period of rapid load growth \nbecause LSEs currently have every incentive to sign up as much load as possible without regard \nto whether they have sufficient supply to serve that load, and that dynamic is only made worse in \ntoday’s supply-constrained environment.  “Net-short LSEs” signing up unlimited customers \nwithout a plan to adequately supply them is a recipe for both resource adequacy shortfalls and \nreliability problems.  \n \n4 See Dominion Comments at 3-4 (the resource shortfall stems in part from “LSEs relying solely on the BRA” \nrather than bilateral contracting, and that “LSEs should have an affirmative obligation to procure new capacity to \ncover any new Large Loads they seek to interconnect and serve”); East Kentucky Power Cooperative Comments at \n14-15 (“PJM does not propose to evaluate whether an LSE’s supply resource portfolio is sufficient to satisfy aggregate \nload and reliability requirements. . . . PJM does not address whether the LSE is causing the resource adequacy concern \nthat IRAS is intended to address. However, it is not just and reasonable to subject to IRAS curtailment the load of an \nLSE that has prudently planned its power supply portfolio to include sufficient resources to meet its load-serving \nobligations, including for New Large Load.”)."},{"page":4,"startToken":960,"endToken":1282,"text":"-4- \nYet PJM has entirely ignored that issue, and the reform that PJM proposes—i.e., assigning \ncurtailment obligations based on whether an individual retail load offsets its demand with new \ncapacity—will exacerbate the region’s resource adequacy challenge.  Notably, under PJM’s \nproposal, an LSE would be curtailed because a new large load in its footprint did not bring new \ncapacity online even if that LSE planned ahead and has sufficient resources to meet its load-serving \nobligations.  And, conversely, an LSE that has not procured enough capacity for the load it is \nobligated to serve will avoid curtailment as long as the large load in its footprint brought its own \nnew capacity.  Thus, in the name of solving a resource adequacy shortfall, PJM could \nsimultaneously curtail entities that have done nothing to cause that shortfall in the first place while \nrewarding entities that have signed up more load than they have planned to serve.  This problem \nwill only get worse as resources reach the end of their useful lives and state and federal \nenvironmental regulations begin to bind.  The likely wave of resource retirements is the next \nsignificant challenge the PJM system will face. By misidentifying the source of the current \nresource shortfall, PJM will hinder the ability to address the next resource adequacy challenge.   \nIn defending IRAS, Governor Shapiro’s filing claims that “PJM is appropriately aligning \nIRAS with existing practices that generally limit curtailment signals to zones with real-time \ncapacity shortfalls.”5  But IRAS does not limit curtailments to zones with real-time capacity \nshortfalls.  Instead, IRAS directs curtailments based on individual retail customers’ contracting \ndecisions, which is not necessarily indicative of whether a zone or area is resource adequate.  \nIndeed, a zone or area with a 100 MW capacity surplus that adds a 50 MW Eligible New Large \nLoad to its footprint would nevertheless be called to curtail 50 MW whenever an IRAS event is \n \n5 Gov. Shapiro Answer at 9."},{"page":5,"startToken":1282,"endToken":1564,"text":"-5- \ntriggered.  The notion that the “aggregate MW limitations on service imposed [through IRAS] at \nthe zonal transmission system-level[] is appropriate and commensurate with the risks posed to the \nbulk power system”6 is misinformed.  An ED or LSE that poses no risk to reliability could still be \ncalled to curtail because IRAS is not keyed to wholesale zonal conditions.  This, in turn, means \nthat PJM will curtail LSEs or EDs that are resource adequate while not curtailing LSEs or EDs \nthat are not resource adequate.  That, by definition, will jeopardize reliability in the operational \ntime horizon and make it more difficult to ensure resource adequacy in the planning horizon.  A \n“solution” that misidentifies the problem, rewards entities that are causing the problem, and \npunishes entities that are not causing the problem is definitionally unjust, unreasonable, and unduly \ndiscriminatory and preferential.  \nThe most frustrating element of PJM’s IRAS proposal is that PJM could have designed a \ncurtailment protocol similar to IRAS but focused on short LSEs.  Rather than develop a large load \nregistry, PJM could have designed a registry where LSEs identify their supply arrangements.  \nInstead of designating LSEs with large loads for curtailments, PJM could have required short LSEs \nto identify loads that would be curtailed when PJM is in an operational emergency.  If PJM had \nsimply targeted the IRAS infrastructure at short LSEs instead of large loads it could have addressed \nits near-term challenges in a just and reasonable, not unduly discriminatory, and jurisdictionally \ndurable fashion.          \nB. IRAS Exceeds the Commission’s Jurisdiction \nThe record resoundingly demonstrates that IRAS is jurisdictionally impermissible.  \nNumerous parties have echoed Vistra’s arguments that the proposal targets retail customers, in \n \n6 Gov. Shapiro Answer at 4."},{"page":6,"startToken":1564,"endToken":1888,"text":"-6- \nviolation of the FPA’s jurisdictional boundaries.7  Although a small handful of parties take the \nopposite view, their arguments are flawed, self-defeating, or lack support altogether.  \n \nPJM’s jurisdictional defense stalls in the garage because it fundamentally misunderstands \nthe controlling Supreme Court precedent.  PJM myopically insists that the Supreme Court’s \n“targeting” inquiry turns only on the utility’s stated justification for the rate it is proposing.  \nSpecifically, in PJM’s telling, EPSA instructs that “[w]hether [] a rule ‘targets’ retail or wholesale \ncustomers turns on the justification for the rule, not on whether or the extent to which the rule \naffects or even compels action of retail or wholesale customers.”8  This is wrong.  While the Court \nin EPSA considered the Commission’s justification for Order No. 745, it did so only after \nconsidering how the rule “work[ed]” and concluding that “whatever the effects at the retail level, \nevery aspect of the regulatory plan happens exclusively on the wholesale market and governs \nexclusively that market’s rules.”9  So while PJM argues that language in its transmittal confirms \nthat IRAS is “targeted to PJM’s wholesale market and enhancing the reliable operation of the bulk \nelectric power system”10 that is beside the point because, in practice, every aspect of IRAS does \nnot happen exclusively at the wholesale level.  In other words, PJM’s stated target does not match \nits reforms’ actual target. \nContrary to PJM’s position, the jurisdictional inquiry required by the FPA does not turn on \nhow a utility characterizes a rate in a transmittal letter.  If it did, any utility could bend the FPA’s \njurisdictional bright line to its liking based on how it characterized its proposal in the transmittal \n \n7 See, e.g., Constellation Comments at 13; Corporate Energy Buyers Association Comments at 7.   \n8 PJM Answer at 19-20 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 264 (2016) (“EPSA”)). \n9 EPSA, 577 U.S. at 282. \n10 PJM Answer at 21."},{"page":7,"startToken":1888,"endToken":2259,"text":"-7- \nletter.  Claiming that up is down does not make it so.  The FPA’s jurisdictional divide cannot turn \non how a filer describes its intent in a transmittal letter.  The Commission must look at the filed \nrate itself and determine whether it targets a matter within the states’ jurisdiction.     \nNext, PJM and several other parties contend that, because PJM would not literally curtail \nindividual retail customers, it cannot be targeting them.11  But that response entirely misses the \npoint.  PJM is targeting retail customers’ capacity procurement practices and requiring those \ncustomers’ LSEs and EDs to curtail service to those retail customers based on their retail-level \nactivity.  Despite PJM’s argument to the contrary, the stated intent of a regulatory action is not \nwhat matters from a jurisdictional perspective.  If PJM were correct, it would have been completely \nunnecessary for the Supreme Court to “consider[] ‘the target at which a law aims’” in the first \nplace.12  The Supreme Court instead could have held that the jurisdictional inquiry turns on “the \nstated intent of the law.”  But that was not the holding in EPSA or Oneok.   \nThus, it is simply incorrect that “protestors cannot logically claim both that PJM’s proposal \nunlawfully ‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot \nguarantee which individual retail customers are curtailed.”13  It is true that PJM has targeted retail \ncustomers by proposing to assign load curtailments to EDs and LSEs based on the retail customers \nthey serve.  It is also true that EDs and LSEs assigned curtailment may direct those curtailments \nat other end-use customers such that the incentives for large loads to BYONC are undermined.  \nThe fact that PJM’s shot may miss the target does not change where PJM aimed.  As the Supreme \n \n11 PJM Answer at 26-28; See, e.g., Gov. Shapiro Answer at 9-10 (“[P]rotestors cannot logically claim both that \nPJM’s proposal unlawfully ‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot \nguarantee which individual retail customers are curtailed. Both cannot be true.”); Appalachian Voices Comments at \n8.  \n12 EPSA, 577 U.S. at 282 (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) (“Oneok”)). \n13 Gov. Shapiro Answer at 9-10."},{"page":8,"startToken":2259,"endToken":2637,"text":"-8- \nCourt has long recognized, both federal and state regulators can nominally address a matter within \ntheir respective purview while in fact impermissibly targeting or aiming at the other.14  Doing so \nviolates the FPA’s bright line between federal and state jurisdiction as much as if the relevant \nregulator exceeded its jurisdiction directly.15  For example, in Hughes, Maryland’s state-\njurisdictional contract-for-differences scheme did not dictate the wholesale auction clearing price \ndirectly.  Nevertheless, the Supreme Court held that the scheme was jurisdictionally impermissible \nbecause it guaranteed the generator a rate distinct from the auction clearing price, even though it \ndid not literally change that price.  “That Maryland was attempting to encourage construction of \nnew in-state generation does not save its program,” because, as the Court put it, the program \namounted to indirect wholesale rate setting that “invade[d] FERC’s regulatory turf.”16  So too here \nwhere PJM has proposed to differentiate customers’ wholesale service based solely on the \npractices of retail customers.    \nAlthough certain parties try to frame IRAS as working only at the wholesale level,17 their \nown pleadings prove otherwise.  For example, Governor Shapiro’s filing claims that IRAS does \nnot “[t]arget retail customers . . . by mak[ing] the characteristics of the retail customer . . . the basis \nfor a curtailment obligation.”18  At the same time, Governor Shapiro’s filing asserts that IRAS \nwould “limit the total MWs of load reduction in a zone or area based on the share of new large \nloads . . . that have failed to meet their capacity needs through BYONC or capacity procured \n \n14 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164 (2016); Oneok, 575 U.S. at 385; N. Nat. Gas Co. v. \nState Corp. Comm’n of Kan., 372 U.S. 84, 94 (1963); Nw. Cent. Pipeline Corp. v. State Corp. Com’n of Kan., 489 \nU.S. 493, 514-15 (1989).   \n15 EPSA, 577 U.S. at 289 (“The FPA leaves no room either for direct state regulation of the prices of interstate \nwholesales” or for regulation that “would indirectly achieve the same result.” (internal quotation marks omitted)). \n16Hughes v. Talen Energy Mktg., LLC, 578 U.S. at 163-64.  \n17 See, e.g., Gov. Shapiro Answer at 10; Public Interest Organizations Comments at 19 (“PIOs Comments). \n18 Gov. Shapiro Answer at 7."},{"page":9,"startToken":2637,"endToken":2920,"text":"-9- \npursuant to Reliability Backstop Procurement (RBP) rules.”19  Those two statements cannot be \nsquared.  Indeed, as Governor Shapiro’s filing acknowledges, load reductions are based \nexclusively and entirely on the characteristics of retail customers in the zone—not the \ncharacteristics of the LSE or ED.  That is impermissible targeting of retail customers, plain and \nsimple.   \nNor is it correct that IRAS “focus[es] on zones or areas projected to have capacity shortfalls \nin real-time—through the existence of non-capacity backed large loads in the planning horizon.”20  \nAs explained above, IRAS does not focus on zones or areas with shortfalls and instead turns solely \non the characteristics of individual retail customers.  Indeed, an LSE/ED could be net long, with \nsufficient capacity to serve all of the loads in its footprint, but if a new large load comes online \nwithout offsetting capacity, that LSE would still receive a curtailment instruction.  In other words, \nthe characteristics and practices of a single retail customer would dictate the wholesale service \navailable to the LSE.  \n Similarly, the Public Interest Organizations (“PIOs”) contend that “PJM will respect \njurisdictional boundaries by directing IRAS Actions at the wholesale level.  PJM will never curtail \nindividual retail customers—instead, it uses the Registry and results from the most recent BRA to \ndesignate megawatt quantities of IRAS curtailment by zone.”21  This argument actually \nunderscores how IRAS targets retail customers.  Indeed, the Registry, in fact, helps ensure that \nIRAS is “aimed” at “the correct customers”—i.e., specific retail customers without Bring Your \nOwn New Capacity (“BYONC”) arrangements.  Or, as the PIOs put it, “[b]y tracking individual \n \n19 Gov. Shapiro Answer at 8. \n20 Id. at 9. \n21 PIOs Comments at 19."},{"page":10,"startToken":2920,"endToken":3198,"text":"-10- \nlarge loads and BYONC arrangements, the Registry helps ensure that EDs allocate interruptions \nto the correct customers during IRAS Actions.”22  The FPA does not allow such targeting of retail \ncustomers in a FERC tariff.  \nPJM tries a different approach to defend its proposal on jurisdictional grounds.  \nSpecifically, PJM skips past IRAS’s targeting of retail customers when it describes how IRAS will \nwork in practice.  PJM states that when system conditions are tight “PJM would determine the \nquantity of MW that load in a zone/area would need to be reduced by to maintain system reliability \nin the PJM Region and provides a directive to Electric Distributors accordingly.”23  But crucially, \nthis ignores the key fact that PJM would determine the quantity of MW that would be reduced \nbased solely on whether individual retail customers have offset their demand with new capacity.   \nPJM also claims that the Commission’s recent Tri-State decision shows that IRAS is \njurisdictionally sound, but this comparison is inapt.  PJM argues that, because the Commission \nfound that Tri-State’s HIL Program respected the FPA’s jurisdictional boundaries, it must find that \nIRAS does as well.  But the only similarity between the two programs that PJM identifies is that \nboth address “concerns regarding the rapid growth of large loads.”24 But that is where the \nsimilarities between the HIL Program and IRAS begin and end.  Under the HIL tariff, Tri-State \nimposes reliability impact review and financial obligations on its Utility Members to prevent costs \nor operational impacts caused by serving a large load from being shifted to other Utility \n \n22 PIOs Comments at 19. \n23 PJM Answer at 26. \n24 Id. at 25 (internal quotation marks omitted)."},{"page":11,"startToken":3198,"endToken":3527,"text":"-11- \nMembers.25  In this regard, Tri-State’s regime is more consistent with the net-short LSE-\nresponsibility approach that Vistra supports than IRAS’s plain targeting of retail customers.  Tri-\nState’s regime is meaningfully distinct from IRAS’s targeting of retail customers, but would \nsupport Vistra’s proposed alternative of focusing on net-short LSEs rather than particular retail \ncustomers.  Under PJM’s proposal, the wholesale customer, unlike Tri-State’s Utility Members, is \ncompelled to take diminished wholesale service solely to address the characteristics and practices \nof retail customers.  Thus, while the Commission found that Tri-State’s proposal “does not present \nan impermissible intrusion on retail rate regulation” even though it did “affect the quantity or terms \nof retail sales,”26 the same cannot be said of PJM’s proposal. \nParties also contend that IRAS must be legal because “actions that would be possible under \nIRAS are no different from other actions” that PJM can take when carrying out its NERC \nresponsibilities.27  Vistra does not dispute that PJM can initiate emergency procedures to maintain \nreliability, but that does not give PJM the authority to initiate emergency procedures in any way it \nchooses, as parties suggest.  For example, PJM could not decide to curtail only EDs in parts of \nPJM that voted for a certain political party in a particular election, regardless of how concerned it \nis about resource adequacy.   \nFinally, parties are wrong to suggest that Vistra and other protesters are arguing that “PJM \nmust blind itself—that it is legally barred from acting on information about the characteristics of \n \n25 Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at PP 14-16 (2026) (“Tri-State”).  PJM \nincorrectly points to paragraph 25 of Tri-State in support of IRAS, but paragraph 25 is a summary of Tri-State’s \ndeficiency letter response, not part of the Commission’s determination.  See PJM Answer at 25 (citing Tri-State, 196 \nFERC ¶ 61,127 at P 25). \n26 PJM Answer at 26 (quoting Tri-State, 196 FERC ¶ 61,127 at P 66). \n27 Gov. Shapiro Answer at 7."},{"page":12,"startToken":3527,"endToken":3838,"text":"-12- \nload growth in a zone or area.”28  This glosses over how IRAS would work.  PJM can and should \nconsider information about aggregate load growth in a zone or area to ensure reliability of the bulk \npower system, which is jurisdictionally appropriate and directly related to resource adequacy.  But \nthat is not what IRAS does.  Rather, PJM is proposing to determine the quality of wholesale \ntransmission service based on the characteristics and practices of individual retail customers within \na zone, which is a bridge too far.  Similarly, the claim that “the protestors’ position would bar PJM \nfrom taking into consideration information about generating facilities—ramp rates, minimum run \ntimes, outage rates, and so on—because neither the Commission nor PJM have authority to directly \nregulate generation”29 suffers from the same fallacy.  The Commission can consider information \nabout and regulate wholesale generators that sell into a Commission-jurisdictional wholesale \nmarket without running afoul of the states’ jurisdiction over those same generators.  Because those \ngenerators are participating in the wholesale market, regulation that considers how the \ncharacteristics of those generators impact their wholesale market activity is “aimed” at and “all \nabout” wholesale market participation.30  Even if that regulation incidentally affects areas within \nthe states’ authority, that is of no consequence because FERC’s regulation is aimed at the \nwholesale market.  And were the Commission to not regulate those generators in the wholesale \nmarket, that would give rise to the type of regulatory gap that cannot exist under the FPA, as states \ncannot set the terms and conditions governing how generators participate in federal wholesale \nmarkets.  But the same is not true of retail loads that just want to take retail service.  Unlike the \ngenerators that FERC permissibly regulates within its jurisdictional sphere, the retail customers \n \n28 Gov. Shapiro Answer at 10. \n29 Id. at 11. \n30 EPSA, 577 U.S. at 282."},{"page":13,"startToken":3838,"endToken":4148,"text":"-13- \ntargeted by IRAS are not participating in the FERC-jurisdictional wholesale market.  Accordingly, \na rule that prohibits the Commission from conditioning jurisdictional service on the characteristics \nof non-jurisdictional entities would not preclude the Commission from considering ramp rates, \noutage rates, or anything else in that parade of horribles. \nC. IRAS Unduly Discriminates Against Existing Resources \nAs Vistra has explained, PJM’s proposal unlawfully discriminates against existing \nresources in favor of new resources.  Neither PJM’s original filing nor any of the subsequent \ncomments and answers provide record evidence that justifies that discriminatory treatment, much \nless render it undue.  Even IRAS’s defenders do not explain why new and existing resources are \ndifferent in any respects that are material to the inquiry at hand—i.e., that they contribute \ndifferently to resource adequacy—such that discriminating against existing resources is “due.”   \nPJM blithely asserts that IRAS is not unduly discriminatory against existing generators \nbecause “[t]he PJM Region needs new capacity.”31  Vistra agrees, but a construct designed to \nattract new capacity without sufficient attention to retaining existing capacity may even make \nmatters worse.  As the Commission has explained, “[b]oth new entry and retention of existing \nefficient capacity are necessary to ensure reliability and both should receive the same price so that \nthe price signals are not skewed in favor of new entry.”32  A MW of existing supply does as much \nto maintain resource adequacy as a MW of new supply.  That is an issue of physics, not policy, \nand so it is unsurprising that nothing in the record calls this fundamental fact into question.  In \nrequiring balance between supply and demand, the system does not (and cannot) distinguish \nbetween the in-service dates of the resource providing the supply.  A single-minded focus on \n \n31 PJM Answer at 44. \n32 PJM Interconnection, L.L.C., 128 FERC ¶ 61,157, at P 102 (2009)."},{"page":14,"startToken":4148,"endToken":4450,"text":"-14- \nincentivizing new entry that comes at the cost of driving existing capacity into retirement will not \nhelp PJM’s resource adequacy issues—it will exacerbate them. \nGovernor Shapiro’s filing attempts to distinguish new and existing generation on the basis \nthat existing generators have previously received capacity market commitments and customers \nhave previously contributed to the “embedded costs” of those generators.33  These arguments are \ncontradicted by the most basic principles of PJM’s capacity market.  The use of the phrase \n“embedded costs” reveals the misguided focus of Governor Shapiro’s filing.  “Embedded costs” \nis an established term relevant to monopoly utilities to describe the combined capital, operations, \nand maintenance costs associated with a resource that a utility is including in its regulated rate \nbase.  In a monopoly utility setting, captive customers are obligated to ensure full recovery of \nresource costs, including a guaranteed rate of return, and thus it is fair to consider generation \nresources as having been paid for and thus entitled to existing customers.  Competitive generators \nsell capacity for a specific delivery year.34  Doing so does not obligate the generator to continue to \nbe a capacity resource after that delivery year35 nor does it obligate any captive customer to \nguarantee the generator fully recover its costs including a return on equity.  Nor does it entitle PJM \n(or any loads) to any “special equitable claim [to that capacity] in perpetuity.”36  Indeed, arguments \nto the contrary disregard the fact that independent generators provide services through voluntary \n \n33 Gov. Shapiro Answer at 16. \n34 PJM, Open Access Transmission Tariff, attach. DD.5.4 (Reliability Pricing Model Auctions) (10.0.0), § 5.4. \n35 See Id. Common Service Provisions, Definitions C-D, (23.1.0), “Delivery Year.” \n36 See BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 269 (D.C. Cir. 2014)."},{"page":15,"startToken":4450,"endToken":4762,"text":"-15- \nparticipation in the markets and amount to the unprecedented and unconstitutional assertion that \nexisting load has a property right in existing generation.37   \nThe New Jersey Board of Public Utilities (“NJBPU”) argues that new capacity resources \nshould be favored because they “require additional price certainty to enter PJM’s uncertain \ninvestment environment, take on risks from federal regulatory uncertainty, and undergo longer \nproject development timelines due to supply constraints and siting and permitting delays.”38  There \nare at least three flaws with that argument. First, it ignores the fact that new resources have been \nentering the nation’s organized capacity markets for many years without “additional price \ncertainty.”  Second, to the extent “additional price certainty” is a virtue, it is one that also benefits \nexisting resources which need ongoing investments for maintenance and refueling in order to \ncontinue providing capacity. Third, NJBPU fails to recognize that constant tinkering with the \nmarket, including via interventions like IRAS, artificially skews prices (e.g., by removing certain \nnew large loads from the Variable Resource Requirement (“VRR”) Curve), which undermines \nprice certainty for all resources—new and existing.  Neither NJBPU nor any other party has \nattempted to quantify and compare the alleged benefits of providing “additional price certainty” to \nnew resources with the unavoidable and well-understood costs of IRAS’s extreme market \nintervention, including potentially the cost of replacing the resources that IRAS could incentivize \nto retire. NJBPU is, therefore, wrong to suggest that the BYONC construct will help attract new \nresources by providing price certainty. If anything, IRAS signals to developers that the rules of the \n \n37 U.S. Const. amend. V; Duquesne Light Co. v. Barasch, 488 U.S. 299, 299 (1989) (“If the rate does not afford \nsufficient compensation, the State has taken the use of utility property without paying just compensation and so \nviolated the Fifth and Fourteenth Amendments.”). \n38 NJBPU Comments at 6."},{"page":16,"startToken":4762,"endToken":5125,"text":"-16- \ngame in PJM will continue to be shuffled and reshuffled with little-to-no regard for the effects on \nexisting contracts and commercial arrangements, actually discouraging new investment.   \nD. IRAS Unduly Discriminates Against New Large Loads \nAs Vistra demonstrated in its initial comments, IRAS discriminates against New Large \nLoads.  Certain commenters attempt to claim otherwise using three arguments.  None of those \narguments are sound. \nFirst, some parties try to justify discrimination between new and existing large loads, \narguing that New Large Loads are solely or disproportionately responsible for the region’s \nresource adequacy shortfall.39  But no party has explained why this is the case.  Nor could they:  \naccording to economic principles espoused by the D.C. Circuit, every user of the transmission \nsystem is economically marginal, meaning that increases in demand can be attributed to every \nuser, both new and existing.40 \nSecond, Governor Shapiro’s filing asserts that any differential treatment between new and \nexisting large loads is simply due to the fact that IRAS applies on a forward-looking basis.41  That \nargument is contradicted by the IRAS proposal itself: the IRAS on/off switch makes clear that \nIRAS does not apply to all new large loads.  Under IRAS, “new” is a term of art that is dictated by \nvariables independent of the load’s vintage or characteristics.  Whether IRAS applies to a given \nlarge load is not a function of whether it was online as of the IRAS effective date (i.e., how a \n \n39 E.g., PJM Answer at 61 (“New, not existing load, is the reason for the shortfall, which drives the need for IRAS. \nFailing to make a distinction between New Large Loads and Large Loads for purposes of applying IRAS would fail \nto account for causation.”); NJBPU Comments at 5 (framing large loads as “those who have contributed the most to \nthe grid’s current resource adequacy shortfall”); Joint Consumer Advocates Comments at 10 (arguing that large loads \n“that cause the need for network upgrades or system stress are ‘differently situated’”); Appalachian Voices Comments \nat 8 (“New Large Loads have caused the capacity shortfall in PJM.”). \n40 See BNP Paribas, 743 F.3d at 268-69. \n41 Gov. Shapiro Answer at 18."},{"page":17,"startToken":5125,"endToken":5444,"text":"-17- \ngrandfathering provision would typically work) but instead depends, in large part, on the resource \nadequacy picture in the region in the three years immediately prior to a particular delivery year.  \nSpecifically, PJM can switch BYONC obligations off when the region is long capacity for three \nyears, then switch them back on the moment capacity runs short.  When that happens, large loads \nthat were once considered “new” lose that designation even though they never operated under the \npre-IRAS rules.  And when the IRAS rules are toggled off, a “new” resource is not considered \n“new” for IRAS purposes.  Therefore, it is simply incorrect to suggest that IRAS’s differential \ntreatment between new and existing loads is needed to “grandfather existing entities under prior \nrules.”42 As the IRAS on/off switch shows, IRAS treats New Large Loads differently precisely \nbecause they are “new” (as defined in reference to PJM’s ever-shifting baseline) not because they \ncame online after IRAS went into effect.     \nThird, PJM appears to misunderstand the precedent it cites when it argues that the \nCommission has permitted differential treatment of large loads if such treatment is “tailored to the \nspecific and unique nature of” such loads.43  In the order on which PJM relies, the Commission \nfound that the differences between CHILLS—a new, non-firm transmission service—and existing \ntransmission service were “narrowly tailored to reflect the interim nature of CHILLS and the \nunique characteristics of the CHILLS that transmission customers will serve.”44  At most, CHILLS \nsupports the unremarkable proposition that a utility can offer different transmission services to \nserve differently situated loads.  That is a far cry from PJM’s proposal to diminish the network \ntransmission service of EDs serving materially identical loads. \n \n42 Gov. Shapiro Answer at 18. \n43 PJM Answer at 60 (quoting Sw. Power Pool, 195 FERC ¶ 61,196, at PP 85, 87 (2026)). \n44 Sw. Power Pool, Inc., 195 FERC ¶ 61,196 at P 85."},{"page":18,"startToken":5444,"endToken":5816,"text":"-18- \nE. PJM’s Proposed Curtailment Priority Scheme Is Unjust and Unreasonable \nNeither PJM nor any other party defending IRAS has justified the proposal to curtail new \nlarge loads seeking firm service before demand response resources that have volunteered and are \npaid to be curtailable.  To start, parties argue that “the proposed order of curtailment are policy \njudgments that do not render the design unjust and unreasonable.” 45  But curtailing retail load \nbefore demand response is not a run-of-the-mill policy judgment—it is a choice that would be \narbitrary and capricious and invert basic economic principles by interrupting would-be firm \ncustomers before deploying resources that are paid to provide capacity.  Such a design cannot be \njust and reasonable.  \nPJM and NJBPU argue that curtailing demand response resources after eligible new large \nloads will help avoid “fatigue” that could arise if demand response resources are called to curtail \ntoo frequently. 46  Demand response resources are paid to curtail when system conditions are \ntight—that is the entire reason for compensating demand response in the first place.  Demand \nresponse resources providing capacity are paid the same price as every other capacity resource and \nthere is no explicit or implicit limit to the frequency with which they will be called to provide \ncapacity.  It would be entirely novel to structure PJM’s curtailment regime to increase the \nlikelihood that demand response resources will meet their contractual obligations going forward.  \nVistra is aware of no precedent that would permit disadvantaging one class of customers to \n \n45 Gov. Shapiro Answer at 5. \n46 PJM Answer at 36 (“The more often a load center is asked to reduce consumption the more disruptive the \nprovision of demand response and the greater the opportunity cost. The result is load centers become less willing to \nprovide demand response and support Demand Resources. . . . Were such Demand Resource fatigue to manifest, there \nwould be a significant adverse effect on the reliability and resource adequacy for the PJM Region.”); NJBPU \nComments at 5 (“Importantly, this proposed step will be initiated prior to calling on Pre-Emergency Load Management \nReductions Actions, which will help maintain the participation of certain load management reduction resources, like \nDR, by minimizing ‘fatigue’ that can occur from being over-called on during stress events.”)."},{"page":19,"startToken":5816,"endToken":6125,"text":"-19- \nincrease the likelihood that another class will meet contractual obligations to which they have \nvoluntarily agreed.  If PJM is concerned that demand response may not perform adequately as a \ncapacity resource because it is called to curtail too frequently, that should be addressed through \naccreditation or by creating a demand response product that can only be dispatched a limited \nnumber of times, not by introducing a curtailment scheme that is unjust and unreasonable.47   \nPJM’s proposal is likely to be counter-productive in the long run.  By protecting demand \nresponse resources from the need to perform, PJM will encourage additional, less reliable demand \nresources to enter the market.  These less reliable resources could displace physical generation (or \ndemand response that will actually perform), especially because the reduced expectation of \nperformance will likely lead to demand response capacity offers below the cost of new entry for a \nnew gas-fired plant.  Over time, PJM could become increasingly reliant on demand response that \ndoes not expect to need to perform.  That is a recipe for a deepening reliability crisis. \nPJM also claims that “[t]he Eligible New Large Loads available to provide IRAS have not \nsatisfied their respective capacity needs through BYONC, and therefore, should not obtain the \ncapacity benefit of Demand Resources.”48  In other words, PJM’s position is that Eligible New \nLarge Loads will pay for capacity, including from demand response resources, but should receive \nno capacity benefit for those payments.  That would flagrantly violate bedrock cost causation \nprinciples, as the cost for capacity would be substantial and yet the benefit would be zero.  This is \nsufficient reason to reject IRAS.   \nPJM itself “recognized that Eligible New Large Loads would not be able to obtain the full \nbenefit, and therefore, consistent with cost causation principles, [] proposed to compensate them \n \n47 See Google Protest at 21-22.  \n48 PJM Answer at 31."},{"page":20,"startToken":6125,"endToken":6446,"text":"-20- \nfor the load reduction service—both for the load reduction service provided and in exchange for \nthe avoided capacity service not provided.”49  As a threshold matter, the issue is that Eligible New \nLarge Loads would receive zero benefit for the capacity they paid for, not that they would be \nunable to obtain “the full benefit.”  More troubling still, PJM is essentially conceding that it will \neither (1) violate the FPA’s jurisdictional scheme by dictating how retail customers will be \ncompensated at the retail level or (2) violate cost causation because it cannot ensure that retail \ncustomers will, in fact, be compensated for their load reduction service.  Put another way, PJM has \ncreated a construct that treats certain large loads as if they do not benefit from capacity service, \nwhile nonetheless charging them for such service.  Presumably to avoid this obviously unlawful \napproach, PJM has proposed a compensation scheme that it either cannot implement, or it would \nbe unlawful for PJM to implement.  Either way, this aspect of IRAS is itself sufficient to render it \nunlawful.   \nHow and whether Eligible New Large Loads are compensated for curtailing should be \ndetermined at the state level.  That means PJM has no authority to avoid a cost-benefit mismatch \nand instead, under IRAS, is left to hope that every large load curtailed under IRAS receives \ncompensation for that curtailment—an uncertainty that in itself is likely to chase investment away \nfrom PJM and into other markets where large loads have the benefit of clear rules of the road \ngoverning their curtailment obligations.  The cost causation principle requires more than wishful \nthinking.  PJM errs again when it claims that “when viewed globally” it is just and reasonable to \ncurtail New Large Loads before demand response but compensate them for curtailing.  Cost \ncausation requires that an entity that pays for a service gets that service in a manner that is roughly \n \n49 PJM Answer at 56."},{"page":21,"startToken":6446,"endToken":6750,"text":"-21- \ncommensurate with the costs it incurred; it cannot be satisfied by tallying up all of a customer’s \ncredits and debits and seeing if the ledger balances “globally.”     \nThe Organization of PJM States (“OPSI”) contends that curtailing new large loads after \ndemand response resources would shift the consequences of the region’s shortfall “onto customers \nand resources that did not cause it,” which “would undermine the basic purpose of IRAS.”50  But \nOPSI’s argument is not a principled rationale for curtailing new large loads first and, indeed, would \nundermine the entire demand response construct.  As noted above, demand response resources \nhave volunteered to be curtailed in tight conditions; so, by design, the consequences of shortfalls \nand tight system conditions always fall on entities that volunteer to be curtailed when conditions \nwarrant.  Further, if PJM had to consider the causes of a shortfall or tight conditions before \ndispatching demand response resources, which is what OPSI’s argument implies, dispatching \ndemand response would become a fraught and administratively infeasible exercise that would \nrender demand response unusable.  Essentially, the implication of OPSI’s argument is that the \ncurtailment priority that dictates the timing for dispatching demand response resources should be \ndependent on the general nature of system conditions.  That notion runs contrary to the demand \nresponse construct. Finally, OPSI’s argument implies that IRAS curtailments are meant to punish \nnew loads that do not offset their demand with new capacity, but the goal of IRAS is to preserve \nreliability,51 and curtailing demand response resources first is the best way to do that. \nFinally, PJM defends the curtailment priority as a way to ensure that New Large Loads \nsatisfy the Ratepayer Protection Pledge, but this is a repeat of a flawed argument that parties rely \n \n50 Organization of PJM States, Inc. Comments at 5 (“OPSI Comments”). \n51 See Transmittal at 7."},{"page":22,"startToken":6750,"endToken":7071,"text":"-22- \non to defend illegal aspects of IRAS.52  Vistra believes that it is important that large loads do not \nshift costs onto other customers.  But the Commission cannot accept tariff provisions that violate \nthe FPA just because they make it easier for entities to comply with voluntary commitments they \nmade in other fora.  Whether or not IRAS is just and reasonable and not unduly discriminatory is \nwholly independent of whether and how entities satisfy the commitments they made under the \nvoluntary Ratepayer Protection Pledge that is nowhere to be found in PJM’s tariff. \nF. IRAS Is Unjust and Unreasonable Because it Will Undermine Market \nFundamentals and Harm Resource Adequacy  \nPJM and IRAS’s defenders have not justified PJM’s proposal to undermine capacity \nmarket fundamentals by excluding new large loads from the VRR Curve.  Although PJM argues \nthat it is necessary to exclude new large loads from the VRR Curve to protect other retail customers \nfrom high capacity prices,53 PJM has provided no evidence demonstrating that this drastic market \nintervention is necessary, nor has PJM meaningfully analyzed the foreseeable impacts of that \nmarket intervention.  As Vistra has explained, this aspect of PJM’s IRAS proposal will leave PJM \nworse off than before, by divorcing the VRR Curve from the region’s actual level of demand and \nmuddling the capacity market’s investment signals.   \nPJM further justifies exclusion of large load from the capacity market by arguing that “the \nauction will continue to produce a price signal that incents supply to meet the needs of the capacity-\nbacked loads that are included in the demand curve.”54  This response is flawed for several reasons.  \nFirst, IRAS loads are still paying for capacity, they are simply not getting the benefit of that \npayment.  To assert that IRAS loads are not “capacity-backed” is not a statement about what they \n \n52 See, e.g., Ohio FEA Comments at 7. \n53 PJM Answer at 50-53. \n54 Id. at 52-53."},{"page":23,"startToken":7071,"endToken":7451,"text":"-23- \nhave paid for, it is a statement about what they are getting.  Second, Vistra showed, and PJM does \nnot refute, that excluding large loads from the capacity market will impair the capacity price signal \nfor non-IRAS loads.  As the Commission has repeatedly explained, a capacity market based on \nrational economic theory provides price signals and an investment environment that will help \nensure resource adequacy.55  That is of paramount importance to the PJM region if it is to attract \nthe investments necessary to both satisfy the growth of large loads while also maintaining \naffordability.  Depending on the results of RBP, there may continue to be a resource adequacy gap \nthat will require additional new entry.  A well-functioning market based on true supply and demand \nfundamentals is necessary to give developers confidence that their decision to enter the market \nwill not destroy the price signal to which their entry was responding.  That developer confidence \nto enter the market is what will ultimately moderate prices for all loads.  Constant market \ninterventions that collapse demand signals make developers and existing resource owners less \nlikely to invest in the region, which means that the conditions that have been straining resource \nadequacy in PJM will continue to persist.    \nCritically, the desire for a well-functioning capacity market does not reflect a belief that \n“PJM’s only option is to procure supply for all new large loads through the capacity market.” 56  \nQuite the opposite.  A well-functioning market that fosters innovative commercial arrangements \nbetween large loads and generation resources (existing and new) by harnessing competition is the \n \n55 See, e.g., ISO New England Inc., 162 FERC ¶ 61,205, at P 21 (2018) (“A capacity market should facilitate \nrobust competition for capacity supply obligations, provide price signals that guide the orderly entry and exit of \ncapacity resources, result in the selection of the least-cost set of resources that possess the attributes sought by the \nmarkets, provide price transparency, shift risk as appropriate from customers to private capital, and mitigate market \npower. Ultimately, the purpose of basing capacity market constructs on these principles is to produce a level of investor \nconfidence that is sufficient to ensure resource adequacy at just and reasonable rates.” (footnote omitted)); Calpine \nCorp., 171 FERC ¶ 61,035 (2020). \n56  Gov. Shapiro Answer at 24."},{"page":24,"startToken":7451,"endToken":7772,"text":"-24- \nsurest path to serving historic load growth at least cost.  Indeed, Vistra showed that efforts to keep \ncapacity market prices artificially low would ultimately undermine the incentive for large loads to \nBYONC because the combination of low capacity costs and curtailment risk may provide better \nvalue than paying the cost of new entry for the potential to avoid curtailment.  Furthermore, Vistra \nhas not argued that the capacity market should be the sole mechanism for procuring capacity.  As \nVistra has repeatedly emphasized, PJM should foster a range of commercial arrangements, \nincluding bilateral co-location arrangements, that allow sophisticated parties to procure capacity \nin ways that move the market and the economy forward at the speed of competition.  But the PJM \ncapacity market should not be thrown by the wayside in that effort.  As PJM acknowledges, part \nof the role of the capacity market is to “produc[e] a forward price signal that load and generation \ncan contract around through bilateral arrangements.”57  Without that clear price signal, PJM would \nbe banking entirely on the gamble that IRAS sufficiently works as intended to incentivize new \nentry.  As Vistra previously explained, that gamble is unlikely to pay off. 58 \nFinally, PJM also attempts to support its proposal to exclude Eligible New Large Loads \nfrom the VRR Curve by analogizing to its practice of excluding energy-only resources from the \nsupply curve.  That analogy illustrates the opposite point that PJM intended.  PJM excludes energy-\nonly resources from the capacity market because they are not paid for capacity.  To contrast, the \nload PJM is proposing to exclude will pay for capacity.  This is the core of the cost causation \nproblem that Vistra explained in its initial Protest:  loads will be expected to pay for a benefit that \nthey will not receive.59  To be consistent with cost causation principles, the supply and demand \n \n57 PJM Answer at 52. \n58 Vistra Protest at 20-21. \n59 Id. at 16-17."},{"page":25,"startToken":7772,"endToken":8095,"text":"-25- \ncurves should exclude entities that do not pay for capacity or receive capacity payments, while \nincluding entities that do pay for or receive capacity payments.  That accurate reflection of basic \nsupply and demand dynamics is also what will, in the long run, incentivize new entry. \nPJM’s analogy to energy-only resources also fails because it ignores that PJM treats \nenergy-only resources and Eligible New Large Loads differently for planning purposes.  In the \nplanning context, PJM makes conservative assumptions as to both load and generation to ensure \nthat it is able to meet its installed reserve margin.  Specifically, PJM excludes energy-only \nresources from the studies it conducts to develop the target installed reserve margin and Effective \nLoad Carrying Capability (“ELCC”) and explicitly chooses not to rely on those resources to offset \nthe supply needed to meet the installed reserve margin.  On the other hand, PJM would model all \nlarge loads—including Eligible New Large Loads—in the studies it uses to develop the target \ninstalled reserve margin and ELCCs.  This conservative approach to planning stands in contrast to \nwhat PJM is proposing to do with load in the VRR Curve, where it would administratively tinker \nwith the market to ignore Eligible New Large Loads that will, nevertheless, be connected to PJM’s \nsystem.  Pulling Eligible New Large Loads out of the VRR Curve therefore creates a mismatch \nbetween PJM’s conservative planning assumptions and its market assumptions.  That is, PJM is \nplanning its system around the same Eligible New Large Loads that it has chosen to exclude from \nthe capacity market precisely because, in the planning context, PJM does want to account for all \nlarge loads.  \nG. IRAS Will Be Counterproductive and Undermine Investment  \nNot only do stakeholders across the industry agree that IRAS is illegal, they also agree that \nit will undermine the investments in new capacity that will ultimately resolve PJM’s resource \nadequacy shortfall.  IRAS proposes to establish a profoundly novel regulatory framework without"},{"page":26,"startToken":8095,"endToken":8409,"text":"-26- \nany grandfathering mechanism for the investments made in reliance on the rules that have \npreviously governed—and, at present, continue to govern—resource adequacy in PJM.   \nUnder IRAS, entities that have made billion-dollar investments in digital and energy \ninfrastructure—investments that were informed by the rules in place at the time they made those \ninvestments—would be exposed to a regulatory regime that “could not reasonably have been \nanticipated when a large retail customer and utility entered into their agreement, causing abrupt, \nsubstantial impairment to the value of these long-lead time projects.”60  That type of dramatic \nregulatory change will deter companies from making those billion-dollar investments in the \nfuture—the very investments that are needed to actually resolve the resource adequacy issues that \nPJM faces in a durable manner.  No party appears to rebut that argument. 61 \nIronically, while PJM contends that the capacity market was never intended to be the only \nmechanism for procuring capacity and that it was instead designed to facilitate bilateral \ncontracting,62 its recent market interventions have thrown bilateral contracting into a tailspin.  \nBetween IRAS, the Reliability Backstop Procurement, and PJM’s ongoing failure to grandfather \nexisting contracts when it rolls out new regulatory regimes, PJM has created profound regulatory \nuncertainty and shown an avowed disregard for bilateral contracting. \nGovernor Shapiro’s filing proffers the explanation that IRAS will, on its own, create \nsufficient investment incentives because “individual large loads materially decrease their \nlikelihood of being subject to curtailment by investing in new capacity.” 63  But there is no \n \n60 Microsoft Comments at 5. \n61 See Gov. Shapiro Answer at 18 (acknowledging that “when needed,” the Commission “grandfathers existing \nentities,” based on “whether the disruption of settled expectations due to the new rules is significant enough to warrant \na transition period to mitigate the harm to settled expectations.”). \n62 PJM Answer at 51-52. \n63 Gov. Shapiro Answer at 22."},{"page":27,"startToken":8409,"endToken":8694,"text":"-27- \nguarantee that bringing your own new capacity will actually “materially decrease” the likelihood \nof being curtailed.  PJM cannot ensure that the states will give BYONC load the benefit it hopes \nto purchase.  Indeed, PJM goes to great lengths to disclaim any role in curtailing individual retail \ncustomers.64  In any event, even if BYONC did “materially decrease” the likelihood of curtailment, \na “material” chance is insufficient to support multi-billion-dollar investments.   \nFinally, parties incorrectly assert that there is a logical inconsistency in the idea that “IRAS \nwill not be effective in incenting new large loads to bring their own capacity because only retail \nauthorities, not PJM, decide which specific retail customers are [curtailed]” while also insisting \nthat IRAS “will disrupt expectations, and new large loads need a longer transition period[.]”65  To \nthe contrary, it is fully consistent to point out that IRAS will fail to incentivize investments in new \ncapacity and that existing contracts should be honored.  While these are separate issues with the \nIRAS proposal, they both serve to illustrate one of the critical underlying flaws in IRAS:  it will \nundermine the investor confidence needed to build and finance the generation that the region \nrequires.  Under IRAS, new loads coming to the system would have no certainty that bringing their \nown new capacity would buy them firm service.  And if IRAS does not grandfather existing \ncontracts, investors will have little reason to trust that PJM and the Commission will honor their \nnext contract either.  In that way, IRAS is a recipe for a perpetual resource adequacy and reliability \nshortfall rather than the type of durable solution the region requires. \n \n64 See, e.g., PJM Answer at 23. \n65 Gov. Shapiro Answer at 3-4."},{"page":28,"startToken":8694,"endToken":8805,"text":"-28- \nIII. \nCONCLUSION \nThe record before the Commission clearly demonstrates that IRAS is unlawful several \ntimes over and it will make PJM’s resource adequacy situation worse, not better.  The Commission \nshould reject PJM’s proposal.   \n \n \nRespectfully submitted, \n \n \n \n/s/ J. Arnold Quinn \nJ. Arnold Quinn \nSVP of Regulatory Policy  \n \nAndrew Weinstein \nVice President, FERC Market Policy \n \nVistra Corp. \n325 7th Street NW \nSuite 520 \nWashington, DC 20004 \narnie.quinn@vistracorp.com    \nandrew.weinstein@vistracorp.com  \n \n                             \n \nNic Gladd \nSarah Greenberg \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nngladd@wsgr.com \nsgreenberg@wsgr.com   \nbshpall@wsgr.com  \n \nCounsel for Vistra Corp. \n \nDated:  September 28, 2026"},{"page":29,"startToken":8805,"endToken":8864,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated:  September 28, 2026 \nWashington, D.C. \n \n \n/s/ Bryan Shpall \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":818,"startToken":0,"endToken":346},{"p":2,"at":818,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":5,"startToken":346,"endToken":589},{"p":3,"at":5,"title":"II. ANSWER","method":"printed heading","endPage":3,"endAt":383,"startToken":589,"endToken":649},{"p":3,"at":383,"title":"A. PJM Has Misdiagnosed the Cause of the Region’s Resource Adequacy Issues","method":"printed heading","endPage":5,"endAt":1629,"startToken":649,"endToken":1530},{"p":5,"at":1629,"title":"B. IRAS Exceeds the Commission’s Jurisdiction","method":"printed heading","endPage":13,"endAt":363,"startToken":1530,"endToken":3886},{"p":13,"at":363,"title":"C. IRAS Unduly Discriminates Against Existing Resources","method":"printed heading","endPage":16,"endAt":196,"startToken":3886,"endToken":4789},{"p":16,"at":196,"title":"D. IRAS Unduly Discriminates Against New Large Loads","method":"printed heading","endPage":18,"endAt":6,"startToken":4789,"endToken":5445},{"p":18,"at":6,"title":"E. PJM’s Proposed Curtailment Priority Scheme Is Unjust and Unreasonable","method":"printed heading","endPage":22,"endAt":580,"startToken":5445,"endToken":6844},{"p":22,"at":580,"title":"F. IRAS Is Unjust and Unreasonable Because it Will Undermine Market","method":"printed heading","endPage":25,"endAt":1743,"startToken":6844,"endToken":8045},{"p":25,"at":1743,"title":"G. IRAS Will Be Counterproductive and Undermine Investment","method":"printed heading","endPage":28,"endAt":6,"startToken":8045,"endToken":8695},{"p":28,"at":6,"title":"III. CONCLUSION","method":"printed heading","endPage":29,"endAt":0,"startToken":8695,"endToken":8805},{"p":29,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":29,"endAt":390,"startToken":8805,"endToken":8864}]}