{"document":{"slug":"rec-20260929-5071","title":"Supplemental Comments of Voltus, Inc. in response to PJM Interconnection, L.L.C.'s 09/23/2026 et al. Answers re the Proposal to Establish Interim Resource…","issued":"2026-09-29","accession":"20260929-5071","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Voltus, Inc.","kind":"comments","file":"sources/filings/text/20260929-5071_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260929-5071","tier":"record","sha256":"cdcb03791121397af3089be21d750ac5326a2fc9f4068ed4feedb808b57b6c3d","pages":7,"tokens":2082,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":187,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nReliability Backstop Procurement to Address \nResource Adequacy and Large Loads \nDocket No. ER26-3380-000\nProposal Of PJM Interconnection, L.L.C. to \nEstablish Interim Resource Adequacy Service \nand a Large Load Registry to Address System \nReliability  \nDocket No. ER26-3515-000\n \nSUPPLEMENTAL COMMENTS OF VOLTUS \nIN RESPONSE TO PJM’S ANSWERS \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“FERC’s” or “Commission’s”) Rules of Practice and Procedure, Voltus, Inc., (“Voltus”) hereby \nmoves for leave to answer and respectfully submits these brief comments in response to PJM \nInterconnection, L.L.C.’s (“PJM’s”) answers filed September 10, 2026, and September 23, 2026, \nin the above-captioned Reliability Backstop Procurement (“RBP”) and Interim Resource \nAdequacy Service (“IRAS”) proceedings, respectively. Voltus’s purpose is to supplement the \nrecord related to Demand Resource and DER Capacity Aggregation Resource (“DR/DER”) \neligibility criteria in light of PJM’s updates, in order to assist the Commission in ensuring \nalignment between these two closely related frameworks and enable the urgent addition of new \ncapacity to the PJM system in furtherance of overall RBP/IRAS design objectives. \n1"},{"page":2,"startToken":187,"endToken":544,"text":"I.​\nPJM’S ANSWERS IN THE INTERLINKED RBP AND IRAS DOCKETS \nHELPFULLY ADDRESS DR/DER ELIGIBILITY BUT INTRODUCE A \nKEY DISCREPANCY \nAt issue is the allowable composition of DR/DER resources that may be considered new \nsystem capacity that, if bilaterally contracted by a relevant large load, may perform two distinct \nbut related functions: (1) reducing the RBP procurement target—the Qualified RBP Offset \n(“QRBPO”) function—and (2) reducing the large load’s IRAS curtailment exposure (more \naccurately, the volume of IRAS MW assigned to the Electric Distributor zone/area in which the \nlarge load is located)—the Bring Your Own New Capacity (“BYONC”) function.  \nPJM’s original proposed tariff revisions to implement RBP did not specify the allowable \ncomposition of DR/DER resources for QRBPO purposes,1 and the original proposed IRAS tariff \nrevisions appeared to expressly limit the composition of DR/DER resources to retail customer \nsites that had never before been registered toward a capacity resource.2 “Dormant” sites—those \nthat had once supported a wholesale capacity resource but had since terminated \nparticipation—were disallowed, as were, it appeared, capacity increases at existing sites tied to \nnew assets. These exclusions represented a departure from positions PJM had taken during the \nstakeholder process and amounted to undue discrimination between the treatment of DR/DER \nand utility-scale generation/storage, since PJM had proposed to include the repowering of \ndeactivated generators and various forms of uprates/increments at utility-scale facilities as \nallowable new capacity for BYONC, QRBPO, and even RBP offer purposes, and had not \n2 PJM IRAS Filing of Aug. 13, 2026, in Docket No. ER26-3515 (hereinafter “PJM IRAS Filing”), proposed Tariff \nAttachment DD-4, section VI(b)(ii) (specifying BYONC resource eligibility for DR/DER); see also Comments of \nVoltus of Sept. 3, 2026, in Docket No. ER26-3515 (hereinafter “Voltus IRAS Comments”) at § II.A, pp. 7-9. \n1 PJM RBP Filing of July 31, 2026, in Docket No. ER26-3380 (hereinafter “PJM RBP Filing”), proposed Tariff \nAttachment DD, section 18.2(b)(vi) (specifying QRBPO resource eligibility); see also Comments of Voltus of Aug. \n21, 2026, in Docket No. ER26-3380 (hereinafter “Voltus RBP Comments”) at § II.A, pp. 4-5. \n2"},{"page":3,"startToken":544,"endToken":858,"text":"justified why analogous behind-the-meter capabilities should be removed from the RBP/IRAS \nframework.3  \nVoltus sought clarification in both dockets. In the RBP docket, PJM’s answer introduced \nlanguage to explicitly identify increments in capacity tied to new generation or storage \ninvestments behind-the-meter as eligible for the QRBPO function.4 The proposed update did not, \nhowever, take up “reactivations” of dormant DR sites.5 PJM’s answer in the IRAS docket \naddressed Voltus’s requested revisions on DR/DER BYONC eligibility in full, clarifying that \nasset-backed increments at existing sites qualify, and explicitly “agree[ing]” with Voltus that  \n“dormant” registered locations should be allowed to be reactivated to support \nBYONC resources. Such locations are not currently supporting Capacity \nResources, and therefore any capacity capability they can provide would be new \nas compared to the capacity on the system for the 2026/2027 Delivery Year.6 \nPJM suggests to reflect this capability in tariff language by allowing “locations that did \nnot support a Capacity Resource, a Peak Shaving Adjustment, or Price Responsive Demand for \nthe 2026/2027 Delivery Year . . .” to support BYONC arrangements.7 \n Voltus thanks PJM for these clarifications and substantive modifications which take \nseveral \nsteps towards parity between demand-side and utility-scale resources for \nBYONC/QRBPO purposes. However, if the adjustments PJM has proposed in its separately filed \nanswers are taken up in the final tariff exactly as written, the reactivation of dormant DR/DER \nlocations will fulfill the BYONC but not the QRBPO function. This discrepancy contravenes \nintended design, with material impact, as further discussed below. \n7 Id. \n6 PJM Answer of Sept. 23, 2026, in Docket No. ER26-3515 (hereinafter “PJM IRAS Answer”) at p. 65. \n5 Id. \n4 PJM Answer of Sept. 10, 2026, in Docket No. ER26-3380 (hereinafter “PJM RBP Answer”) at p. 29. \n3 See Voltus RBP Comments at § II.C, pp. 6-8; Voltus IRAS Comments at § II.C.1-2, p. 12.  \n3"},{"page":4,"startToken":858,"endToken":1151,"text":"II.​\nVOLTUS SUGGESTS A STRAIGHTFORWARD EDIT TO ADDRESS THE \nIDENTIFIED DISCREPANCY \nVoltus respectfully but strongly recommends one additional, critical revision to PJM’s \nproposed tariff language as revised by its RBP Answer, to align incentives and ensure a \ncontinuity in PJM’s overall approach: PJM’s QRBPO resource eligibility definition should allow \nfor the reactivation of a “dormant” registered location, in line with the same allowance PJM has \nsupported on the BYONC side. \nThe following straightforward edit to proposed Tariff, Attachment DD, section \n18.2(b)(vi) would achieve the necessary alignment: \n(vi) Planned Demand Resource or Planned DER Capacity Aggregation Resources, \nas described in the RAA, Schedule 6 and Schedule 6.2, where such incremental \ncapacity are not reliant on locations which previously provided capacity for the \n2026/2027 Delivery Year unless such previous location represents additional \ncapacity resulting from an investment in new generation or new storage resources \nat that location. \nThe above redline takes as its starting point the updated language PJM proposed in its RBP \nAnswer and implements the same definition of a “dormant” location that PJM provided in its \nIRAS Answer. \nIII.​\nENABLING THE SAME RESOURCES TO SUPPORT BOTH QRBPO \nAND BYONC ALIGNS INCENTIVES AND SUPPORTS THE OVERALL \nDESIGN \nOF \nPJM’S \nLARGE \nLOAD \nRESOURCE \nADEQUACY \nSOLUTIONS \nWithout this or similar adjustment in the final tariff filing, BYONC arrangements \nincorporating reactivated locations will not function to reduce the volume of RBP central \nprocurement, resulting in duplicative matching of new capacity volumes to DY27/28 and \nDY28/29 load additions, along with the unnecessary imposition of socialized risk across all \nratepayers in the PJM footprint. It is the shared preference of a wide range of stakeholders to \nshift capacity procurement from RBP to bilateral transactions so as to avoid this socialization and \n4"},{"page":5,"startToken":1151,"endToken":1485,"text":"make good on the Ratepayer Protection Pledge by ensuring that large loads bear the costs \nassociated with serving their growth. To effectuate this shift from centralized to private-market \nfunding, the same bilateral contracts that relieve a load of IRAS exposure and return the load and \nits matched supply to RPM must also decrement the RBP target. This requires that the \nunderlying BYONC and QRBPO resource eligibility criteria be the same. Indeed, for \nutility-scale generation and storage, PJM has defined eligibility with exactly the same tariff \nlanguage for both functions.8 Thus each and every generation/storage MW that can support \nBYONC is also eligible as a QRBPO MW—provided, of course, that commercial operation date \n(“COD”) meets the QRBPO requirement. This same alignment is necessary on the DR/DER \nside, and it is Voltus’s understanding from stakeholder conversations with PJM staff that \nalignment of BYONC and QRBPO resource eligibility has been PJM’s ongoing design intention. \nIV.​\nA FAILURE TO RESOLVE THE IDENTIFIED DISCREPANCY WILL \nDISINCENTIVIZE \nLARGE \nVOLUMES \nOF \nPOTENTIAL \nNEW \nCAPACITY \nWITH \nNEAR-TERM \nAVAILABILITY, FRUSTRATING \nRELIABILITY AND AFFORDABILITY GOALS \nNote also that the specific category here under consideration—the capabilities of dormant \nlocations—is uniquely relevant in the context of QRBPO. As Voltus has explained elsewhere, \nDR/DER aggregations are functionally precluded from direct RBP participation.9 Yet they \nrepresent the set of resources with perhaps the earliest average commercial operation date \n(because DR/DER aggregations take advantage of capabilities already “latent” on the grid) and \nthus are among the most attractive resources for large load growth that will be subject to IRAS in \nthe 27/28 and 28/29 Delivery Years. These near-term loads are subject to uncertain, 15-year cost \nallocation from RBP in addition to IRAS curtailment, and are looking for resources that limit \n9 See Voltus RBP Comments at § III.A, pp. 10-13. \n8 Compare proposed Tariff, Attachment DD, section 18.2(b)(i)-(v) in PJM’s RBP Filing with proposed Tariff, \nAttachment DD-4, section VI(b)(i)(1)-(5). \n5"},{"page":6,"startToken":1485,"endToken":1840,"text":"both exposures. Allowing dormant locations to qualify as QRBPO is therefore crucial to \neffectively incentivizing large loads and aggregators to reactivate this capacity. Note that without \nsuch allowance, a large load prioritizing RBP cost avoidance will prefer a new capacity resource \nwith a June 1, 2032, COD over DR/DER reactivation capacity available in 2027/2028—a \nperverse outcome for grid reliability and ratepayer affordability.  \n The volumes at issue are not small. Voltus estimates that dormant commercial and \nindustrial locations are capable of providing in the range of 2 GW of new capacity given \nBYONC price signals.10 Incentivizing such capacity to be brought online in the next two delivery \nyears will relieve grid strain immediately and improve near-term affordability. \nIndeed, new capacity contracted to come online in the 27/28 and 28/29 Delivery Years \nhas a unique ratepayer affordability benefit. Beginning with Delivery Year 29/30, New Large \nLoads will be excluded from the Reliability Pricing Model (“RPM”) by default and brought back \nto the Variable Resource Requirement (“VRR”) curve only if matched by new capacity that \nenters the relevant auction as a price taker. The expected impact will be price neutral. But since \nNew Large Loads have not been excluded from 27/28 and 28/29 RPM, any new capacity \ncontracted in time to enter, as price taker, the 27/28 and 28/29 Incremental Auctions will exert \ndownward pressure on the capacity costs borne by all ratepayers as 27/28 and 28/29 RPM cost \nallocation, with the potential to provide immediate relief. \nCounting demand-side reactivations as QRBPO will have the additional impact of \nprotecting “native” load from the risk of RBP cost-shifting over the next 15 years. For all these \nreasons, affording DR/DER reactivations equivalent BYONC and QRBPO treatment is not a \ndrafting detail but an impactful policy choice.  \n10 This estimate is based on an analysis of Voltus’s past customers and their reasons for dropping out of DR capacity, \nVoltus’s share of the DR capacity market in PJM, and external data points. See also Voltus IRAS Comments at p. 11 \n(referencing statistics on past DR participation volumes). \n6"},{"page":7,"startToken":1840,"endToken":2082,"text":"V.​\nCONCLUSION \nPJM has proposed to allow reactivated DR/DER locations for BYONC but not QRBPO \npurposes, introducing a discrepancy that impedes the overall design of the RBP/IRAS \nframework. The impact is highly material, because reactivations are among the only resources \navailable to match 27/28 and 28/29 large load additions, and they are available to do so in \nsignificant volumes. However, because DR/DER resources are functionally excluded from RBP, \nDR/DER reactivations are only able to match large load additions and reduce IRAS exposure via \nbilateral contracts.  Unless these same bilaterals also reduce RBP cost exposure, large loads will \nbe disincentivized from procuring DR/DER reactivations as compared to other resources. The \nfinal result will be less new capacity coming online over the next several delivery years and a \nreduction in the volume of emergency DR available for PJM to dispatch. The negative impacts \non reliability, near-term affordability via RPM price impacts, and long-term RBP cost-shifting \nrisk may be avoided by the simple tariff revision Voltus has recommended herein. Voltus \nrespectfully asks that PJM take up such revision, or similar, with Commission support. \nVoltus deeply appreciates PJM’s ongoing collaboration with stakeholders on effective \nRBP/IRAS design and thanks the Commission for this opportunity to supplement the record. \n \n \nRespectfully submitted, \n \n/s/ Kimaya Abreu \nKimaya Abreu \nSr. Manager, Regulatory Affairs \nVoltus, Inc. \n2443 Fillmore St. \nSan Francisco, CA 94115 \n609.994.7686 \nkabreu@voltus.co \n \nDated: September 29, 2026 \n7"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":7,"endAt":4,"startToken":0,"endToken":1841},{"p":7,"at":4,"title":"CONCLUSION","method":"printed heading","endPage":7,"endAt":1602,"startToken":1841,"endToken":2082}]}