{"document":{"slug":"rec-20260929-5145","title":"Motion for Leave to Answer and Answer of Advanced Energy United to PJM Interconnection, L.L.C.'s 09/23/2026 Answer re the Proposal to Establish Interim…","issued":"2026-09-29","accession":"20260929-5145","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Advanced Energy United","kind":"answer","file":"sources/filings/text/20260929-5145_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260929-5145","tier":"record","sha256":"67c43a3378c1635bd27755dacbbc52ba1757f8bf2ced8901fbb0c11d4805d133","pages":9,"tokens":2323,"emptyPages":[],"textThemes":["adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":304,"text":"1 \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n) \nPJM Interconnection, L.L.C    \n \n) \n \nDocket No. ER26-3515-000   \n \n) \n \n  \n \n \n \n \n \n \n \n \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER \n OF ADVANCED ENERGY UNITED  \n \nPursuant to Rule 212 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedures,1 Advanced Energy United2 (“United”) \nsubmits this motion for leave to answer and limited answer to the answer of PJM \nInterconnection, L.L.C. (“PJM”) in the above-captioned proceeding.3 United submits this limited \nanswer because PJM’s Answer mischaracterizes the relief United actually requested regarding \ncustomer-sponsored Peak Shaving Adjustments (“PSA”),4 and because PJM’s stated rationale for \ndeclining that relief is inconsistent with positions PJM takes elsewhere in the same Answer.  \nI. \nMOTION FOR LEAVE TO ANSWER \n \nAlthough Rule 213(a)(2) does not generally permit an answer to an answer, the \nCommission grants leave where good cause is shown, including where an answer assists the \nCommission’s decision-making process by correcting the record or supplying information the \n \n1 18 C.F.R. § 385.211 \n2 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean, \nand affordable. Advanced Energy United is the only industry association in the United States that represents the full \nrange of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes \nenergy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. The \nviews expressed in these comments reflect the position of Advanced Energy United, but do not necessarily reflect \nthe views of any particular member with respect to any issue. \n3 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., Docket No. ER26-3515-000, (Sept. 23, \n2026) (“PJM Answer”) \n4 Comments of Advanced Energy United, Docket No. ER26-3515-000, at 3 (September 3, 2026). (“United \nComments”)"},{"page":2,"startToken":304,"endToken":568,"text":"2 \nCommission needs to resolve a disputed issue.5 Good cause exists here. PJM’s Answer directly \naddresses and rejects a specific request in United’s comments6, but does so by responding to a \ndifferent, broader proposal than the one United actually made, and by relying on a rationale PJM \ndoes not apply consistently elsewhere in that same Answer. Leaving that mischaracterization and \ninconsistency unaddressed risks leading the Commission to resolve this issue based on an \ninaccurate description of the relief United requested. United accordingly requests leave to file \nthis limited answer. \nII. \nANSWER \n \nUnited's answer addresses three distinct flaws in how PJM’s Answer treats Peak Shaving \nAdjustments (“PSA”) under IRAS, each independent of the others. First, PJM’s rejection of \nPSAs as a verifiable tool to reduce resource adequacy need rests on a distinction PJM does not \napply consistently elsewhere in its own Answer. Second, PJM defends against a broader proposal \nto treat PSA as a substitute for large loads supporting new capacity through Bring Your Own \nNew Capacity (“BYONC”), rather than the narrower one United actually requested, which was \nthat PSAs be taken into account when calculating IRAS exposure. Third, PJM treats PSA and \nBYONC as equivalent rather than recognizing that they address the same capacity gap from \ndifferent sides and thus crediting one does not require relaxing requirements for the other. Taken \n \n5 See, e.g., PJM Interconnection, L.L.C., 189 FERC ¶ 61,110, at P 22 (2024) (accepting answers to protests and \nanswers because they assisted the Commission in its decision-making process). \n6 PJM Answer at 47-48 (citing United Comments at 3)."},{"page":3,"startToken":568,"endToken":877,"text":"3 \ntogether, these flaws show that PJM’s Answer does not actually respond to the issue United \nraised.  \nA. PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal \nInconsistency in PJM’s Own Answer \n \nPJM’s Answer rejects crediting PSA against a New Large Load’s IRAS exposure on the \nground that PSA amounts are “adjustments to PJM’s load forecasts, not resources that may \nparticipate in RPM Auctions,” and are not a “real-time dispatchable product.”7 PJM reasons that \nthis distinction settles the question: because PSA does not clear an auction and cannot be called \nupon in real time, it categorically cannot reduce the capacity need giving rise to IRAS \ncurtailment. \nPJM’s own Answer, however, shows that this distinction does not actually settle \nanything. In the same filing, PJM confirms that it already permits qualifying PSA MW “that \nqualify for an opt-out to potentially reduce the identified 2027/2028 Delivery Year capacity \nshortfall for which the RBP will procure.”8 That is, PJM already treats a PSA value, the identical \nkind of forecast adjustment PJM now calls too unreliable to be taken into account under IRAS, \nas sound enough to shrink the actual, binding quantity of capacity PJM goes out and procures \nthrough the companion Reliability Backstop Procurement mechanism.9 Just as a PSA value \nserves to reduce how much capacity PJM is targeting to procure under the RBP, it should be \nfactored into how much of a load’s demand counts as unmet capacity need under IRAS. \nPJM offers no explanation for why the same PSA value should be treated as germane in \none proceeding and irrelevant in the other. Both the RBP procurement target and the IRAS \n \n7 Id.  \n8 Id. \n9 See, PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000, (July 31, 2026) (“PJM RBP”)"},{"page":4,"startToken":877,"endToken":1168,"text":"4 \nEligible New Large Load Amount are wholesale-level calculations of how much capacity is \nactually needed to serve PJM’s system given the unmet demand from New Large Loads. PJM \ndesigned RBP and IRAS as companion mechanisms addressing the same shortfall, and PJM \ncannot now maintain two incompatible positions on the reliability of the same underlying data \ndepending on which mechanism is more convenient in each instance. \nIf a qualifying PSA value is sound enough to reduce PJM’s own procurement target \nunder RBP, it is sound enough to reduce the capacity need attributable to the New Large Load \nthat sponsored it. The same treatment of PSA that already applies under RBP is equally relevant \nhere and should be incorporated as a means to reduce IRAS exposure. \nB. PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not \nMake \n \nPJM’s Answer builds its rejection of PSA credit around PSA’s unsuitability as a \nsubstitute for BYONC, a tradable, must-offer capacity resource that PJM’s Tariff requires to \nsatisfy specific capacity market obligations.10 On that framing, PSA fails because it cannot be \ndispatched, cannot clear an auction, and carries none of the ongoing capacity-market obligations \nBYONC carries. \nPJM is drawing an unnecessary parallel between BYONC and PSA, and responding to a \nrequest United never made. United’s comments did not ask PJM to treat PSA as BYONC, to \npermit PSA to participate in RPM Auctions, or to make PSA dispatchable during an IRAS \nAction. United asked only that PJM’s Tariff “specify that the deduction under this formula for a \nqualifying Peak Shaving Adjustment or comparable state-authorized reduction shall equal the \nMW value calculated and verified by PJM pursuant to its applicable procedures.”11 That is a \n \n10 PJM Answer at 47-48 \n11 United Comments at 4."},{"page":5,"startToken":1168,"endToken":1456,"text":"5 \nrequest to reflect an already-measured reduction in resource-adequacy need, not a request to \nconvert PSA into a capacity product it was never designed to be. \nThe distinction matters because PJM’s own Eligible New Large Load Amount \ncalculation is not itself a real-time dispatch decision. It is a forecast-based determination, built \nfrom registration data, load forecasts, and capacity commitments, that fixes a load’s exposure \nbefore any Interim Resource Adequacy Alert is ever called.12 A qualifying PSA reduces the \nunderlying capacity need that calculation is meant to measure before any such Alert occurs, in \nexactly the same way BYONC and Allocated RBP UCAP MW do. Whether PSA could be \ndispatched during an emergency is beside the point; the reduction it represents has already \noccurred by the time PJM performs the calculation PJM proposes to use.  \nUnited respectfully requests that the Commission consider the argument in our original \nfiling, which was that the IRAS exposure calculation should take into account a verified \nreduction in resource-adequacy need resulting from PSA, rather than PJM’s mischaracterization \nof that request as an ask to treat PSA as a dispatchable capacity resource. \nC. PSA and BYONC Are Complementary, Not Competing, Categories \nPJM’s Answer proceeds as though recognizing PSA within the Eligible New Large Load \nAmount formula would require treating PSA as a substitute for BYONC, competing for the same \nrole BYONC already fills. It would not. BYONC and PSA address the same underlying problem, \ni.e., the gap between a New Large Load’s demand and the capacity available to serve it, from \ntwo different directions, and nothing in United’s request asks PJM to blur that distinction. \n \n12 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, (Aug. 13, \n2026)\")"},{"page":6,"startToken":1456,"endToken":1868,"text":"6 \nBYONC works on the supply side: it adds new capacity to the system to match or offset a \nload’s demand. PSA works on the demand side: it reduces the capacity PJM must otherwise \nprocure, or the amount of curtailment that may be necessary. A load that brings 50 MW of \nBYONC and a load that supports the reduction of the zonal or EDC peak by 50 MW through a \nqualifying PSA arrive at an identical outcome, from PJM’s perspective: the load’s otherwise-\nunmet capacity need shrinks by the same amount. The mechanism differs, but the resource-\nadequacy benefit does not, and thus large loads should be given the same credit. PJM itself \nrecognized PSA and BYONC as different sides of the same coin in its Transmittal Letter when it \nexcluded any locations from “new” BYONC status that had previously helped “reduce the \namount of capacity needed to meet the PJM Region Reliability Requirement through a Peak \nShaving Adjustment or Price Responsive Demand.”13   \nRecognizing the verified benefit of PSA does not require PJM to loosen any of the \nrequirements applicable to BYONC, which would remain the only pathway to recognize a New \nLarge Load’s contribution to bringing actual new capacity to the system, subject to must-offer \nrequirements, capacity market participation, and the ten-year commitment discussed above.14 \nPSA would remain what it already is under PJM’s own rules, a verified reduction to the forecast \npeak demand from which a load’s capacity need is calculated.15 Because PJM already relies on \nPSA as a demand-side decrement in the RPM today, alongside other demand-side measures such \nas Price Responsive Demand (“PRD”),16 it is not a speculative or unverified figure. Rather, it is \n \n13 Transmittal Letter at 54 (citing Proposed Tariff, Attachment DD-4, §§ VI(b)(ii)(1)-(2)) \n14 Id at 43-44. \n15 Id at 47-48; see also, PJM Manual 19, Load Forecasting and Analysis, § 3.2 (explaining, “In cases where a zone \ncontains a peak shaving program with an approved Peak Shaving Adjustment Plan, the zone’s forecast will be \nadjusted to reflect the program’s impact.”). \n16 PJM committed 106.5 MW UCAP of PRD in the 2027/2028 Base Residual Auction (“BRA”) PJM \nInterconnection, L.L.C., 2027/2028 Base Residual Auction Report, at 3 n.1 (Dec. 17, 2025). PJM describes PRD as \n“a predictable change in the amount of electricity used, not as additional generation.” PJM Interconnection, L.L.C., \n“Price Responsive Demand Fact Sheet” at 2 (March 23, 2017)."},{"page":7,"startToken":1868,"endToken":2205,"text":"7 \ntied to a specific, state-authorized program, triggered by an objective measure, the actual \nmaximum daily temperature-humidity index for the relevant zone, scored over a rolling three-\nyear period, and verified through PJM’s own applicable procedures.17 PSA does not need to be \ndispatchable or tradable to be a reliable input into a forecast-based formula that is not itself a \nreal-time dispatch determination. It only needs to be measured accurately, and PJM’s own rules \nalready ensure that it is.  \nConsideration of both BYONC and PSA as complementary tools will result in a more \naccurate measure of a load’s true, net capacity need than a Tariff that recognizes only one side of \nthat calculation. The success and impact of PJM’s IRAS proposal depends on getting that net \nfigure right. The purpose of the Eligible New Large Load Amount formula is to identify how \nmuch of a load’s demand remains genuinely uncovered.18 A formula that credits new supply but \nignores a verified reduction in peak demand does not measure that figure accurately, it \nsystematically overstates it for any load that has taken real, verified steps to reduce the regional \nshortfall. PJM should be directed to correct the formula so that it reflects both halves of a New \nLarge Load’s actual net capacity need. Failure to do so will result in a harmful over-estimation of \nIRAS need while diminishing the incentive for New Large Loads to pursue PSA as a mechanism \nto affordably and quickly reduce pressure on the strained PJM grid. \nIII. \nCONCLUSION \n \nPJM’s Answer does not resolve the issue United raised; it responds to a different request \nwhile relying on a rationale PJM does not apply consistently elsewhere in the same filing. United \nasks the Commission to direct PJM to credit qualifying, verified PSA values in the Eligible New \n \n17 PJM Answer at 48 (citing PJM Manual 19: Load Forecasting and Analysis, § 3.2 (rev. 39, June 30, 2026)). \n18 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, \n2026)."},{"page":8,"startToken":2205,"endToken":2281,"text":"8 \nLarge Load Amount formula on the same basis PJM already applies under RBP. United \nrespectfully requests that the Commission grant this motion for leave to answer and accept this \nanswer.  \n \nRespectfully submitted, \n \n \n \n \n \n \n \n/s/   Mike Haugh                             \n \n \n  \nCaitlin Marquis, Managing Director   \nMike Haugh, Director  \nJon Gordon, Senior Director \nKelsey Koenig, Associate \nAdvanced Energy United   \n1801 Pennsylvania Ave. N.W., Suite 410    \nWashington, D.C. 20006    \ncmarquis@advancedenergyunited.org   \nmhaugh@advancedenergyunited.org \njgordon@advancedenergyunited.org  \nkkoenig@advancedenergyunited.org"},{"page":9,"startToken":2281,"endToken":2323,"text":"9 \nCERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated this 29th day of September, 2026. \n \n \n \n \n \n \n \n \n/s/ Mike Haugh"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":875,"startToken":0,"endToken":119},{"p":1,"at":875,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":598,"startToken":119,"endToken":394},{"p":2,"at":598,"title":"II. ANSWER","method":"printed heading","endPage":3,"endAt":105,"startToken":394,"endToken":585},{"p":3,"at":105,"title":"A. PJM’s Rejection of PSA Credit to Displace IRAS Need Rests on an Internal","method":"printed heading","endPage":4,"endAt":770,"startToken":585,"endToken":1002},{"p":4,"at":770,"title":"B. PJM’s “Not Dispatchable” Rationale Answers a Request United Did Not","method":"printed heading","endPage":5,"endAt":1217,"startToken":1002,"endToken":1354},{"p":5,"at":1217,"title":"C. PSA and BYONC Are Complementary, Not Competing, Categories","method":"printed heading","endPage":7,"endAt":1522,"startToken":1354,"endToken":2118},{"p":7,"at":1522,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":3,"startToken":2118,"endToken":2282},{"p":9,"at":3,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":279,"startToken":2282,"endToken":2323}]}