{"document":{"slug":"rec-20260930-5211","title":"Answer of Google LLC in response to pleadings re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service","issued":"2026-09-30","accession":"20260930-5211","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Google LLC","kind":"answer","file":"sources/filings/text/20260930-5211_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260930-5211","tier":"record","sha256":"5a5aa30fff868f2013904ad7da0fc7dc39bcc8bfc0a101a57aedddee6bfb17a8","pages":36,"tokens":11873,"emptyPages":[],"textThemes":["flex","retail","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":246,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n) \n) \n         Docket No. ER26-3515-000 \n \n \nANSWER OF GOOGLE LLC \n \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”),1 Google LLC (“Google”) hereby moves to \nanswer and answers the pleadings filed in this proceeding.  PJM is at a crossroads.  The record of \nthis proceeding confirms that its resource adequacy challenges are real and, if left unaddressed, \nwill degrade reliability for all customers.  And although some customers, including Google, are \nmaking the critical investments needed to serve their load growth, that is far from universal.  As a \nresult, there is every reason to believe that forecasted demand for capacity will continue growing \nfaster than supply.  Nevertheless, PJM has offered a proposal, Interim Resource Adequacy Service \n(“IRAS”), that will make the situation worse.  It will chill investment and undermine efforts by \ncompanies, like Google, that are committed to bringing their own new capacity to PJM.  \nAccordingly, the Commission should use this proceeding to put PJM back on course to a resource-\nadequate future.  In particular, as discussed below, it should require PJM to adopt an interruptible \ncapacity service similar to what exists in the natural gas transportation context under the Natural \nGas Act (“NGA”).  This service will provide a mechanism for balancing supply and demand \nwithout undermining investment in new capacity in the way IRAS would.  \n \n1 18 C.F.R. § 385.213 (2026)."},{"page":2,"startToken":246,"endToken":594,"text":"-2- \nGoogle agrees with the principle underlying IRAS: “New Large Loads that do not bring \nsufficient new capacity to offset their expected demand should be subject to curtailment prior to \nother firm wholesale customers during tight system conditions.”2  Consistent with that view and \nGoogle’s commitment to the Ratepayer Protection Pledge, Google is actively procuring new \ncapacity to cover its projected load growth in PJM and will submit documentation to PJM showing \nthat it has brought its own new capacity (“BYONC”) to reduce or offset its obligations under the \nReliability Backstop Procurement (“RBP”) construct.3  For that reason, Google’s interest in this \nproceeding is not to avoid paying for new capacity.  Rather, Google’s concern is that IRAS will \nmake it less likely that Google and other large customers can bring their own new capacity and \navoid curtailment to a market governed by IRAS. \nIn addition, Google agrees with commenters arguing that reform is necessary.  Under the \nstatus quo, capacity market demand is already exceeding supply and it is likely to continue to do \nso in the future as Load Serving Entities (“LSEs”) sign up additional firm retail customers pursuant \nto applicable state law.   A situation in which demand for firm service regularly exceeds supply is \nan untenable outcome.  After all, while those retail arrangements are governed by state law, the \nphysical limitations on the system are not.  The capacity market cannot supply more capacity than \nexists in reality.  But the PJM tariff does not provide LSEs with an option to procure anything \nother than firm capacity, meaning that, when supply exceeds demand, LSEs are left trying to try \nto procure something that does not exist.  An interruptible service—akin to what exists in the gas \ntransportation context and building upon what the Commission required in the PJM Co-Location \nOrder—is the missing link that would allow supply and demand to clear in the capacity market \n \n2 PJM Interconnection, L.L.C., Protest of Google LLC, Docket No. ER26-3515-000, at 1 (filed Sep. 3, 2026) \n(“Google Protest”). \n3 See PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026)."},{"page":3,"startToken":594,"endToken":962,"text":"-3- \nwithout creating pervasive uncertainty that would interfere with investment in new capacity.  In \nthe absence of such an interruptible service, PJM is providing what amounts to non-firm service \nwithout a non-firm service class in the tariff.  That result, Google submits, is unjust and \nunreasonable.         \nIRAS, by contrast, is not the solution.  The overwhelming weight of the record compiled \nin this proceeding indicates that IRAS is, for myriad reasons, illegal, ineffectual, and otherwise \ndeeply flawed.4 It would, therefore, cast a long shadow over resource procurement in the region, \nmeaning that “the result of IRAS will be less investment in new capacity in PJM—the exact \nopposite of what the region needs.”5  An order accepting IRAS will cause resource adequacy in \nPJM to deteriorate further.   \n \nThe Commission must now guide PJM back on course.  To do so, it should use the logic \nof its recent PJM Co-Location Orders6 to require PJM to establish an interruptible service in the \ncapacity market similar to what exists in the gas transportation context.7  It has two viable options \nto do so.  First, it could reject IRAS with guidance on how PJM can reform the proposal to actually \nimprove resource adequacy in PJM.8  Any such order should make clear to PJM that it cannot \ncondition the quality of wholesale service on retail customer characteristics and that a successor \n \n4 Infra section II.A.  \n5 Google Protest at 2. \n6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“PJM Co-Location Order”). \n7 Duke Energy Trading & Mktg., L.L.C. v. FERC, 315 F.3d 377, 378-79 (D.C. Cir. 2003). \n8 This would be consistent with what PJM has requested the Commission to do if the Commission rejects IRAS.  \nSee PJM Answer at 5 (“PJM respectfully requests that, to the extent the Commission rejects any element of this filing, \nthe Commission either direct prescriptive changes to be implemented on compliance or provide guidance to aid PJM \nand stakeholders to develop a just and reasonable approach. The issues outlined herein are simply too important, and \nthe timing too critical, for PJM and its stakeholders to have to guess in such a case as to what the Commission would \nfind acceptable.”)."},{"page":4,"startToken":962,"endToken":1381,"text":"-4- \nconstruct to IRAS must create the conditions necessary to facilitate investment in new capacity, \nnot stymie it.  Specifically, it should create a class of interruptible service governed by transparent, \nclear rules that provide the regulatory certainty necessary to facilitate the at-risk investments that \nare the bedrock of a market-based approach to ensure resource adequacy.    \nAlternatively, the Commission could take the reins and begin the process to “transform” \nthis section 205 into a section 206 proceeding.  Although in a typical proceeding under section 205 \nof the Federal Power Act (“FPA”), the Commission generally “undertakes ‘an essentially passive \nand reactive role’ and restricts itself to evaluating the confined proposal,” 9 the U.S. Court of \nAppeals for the D.C. Circuit has recognized an exception to that general rule.  Specifically, the \ncourt has explained that the Commission may transform a section 205 proceeding into a section \n206 proceeding and impose its own replacement rate provided that it makes three findings.  \n“[F]irst, it must conclude under § [205] that the [public utility] failed to carry its burden of proof \nthat the proposed rate was just and reasonable; second, it must itself demonstrate that the default \nposition, the prior rate, is no longer just and reasonable; and third, it must establish \nthat its substitute rate is just and reasonable.”10   \nThe record in this proceeding shows how the Commission can readily make all three \nfindings:  (1) for the reasons explained in Google’s initial protest and throughout the record, IRAS \nis unjust and unreasonable, unduly discriminatory, and in excess of the Commission’s jurisdiction; \n \n9 Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (quoting City of Winnfield v. FERC, \n744 F.2d 871, 875-76 (D.C. Cir. 1984)). \n10 W. Res., Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993) (citing the parallel provisions of the Natural Gas \nAct); While Western Resources addressed sections 4 and 5 of the Natural Gas Act, its reasoning and framework \nnevertheless apply equally to FPA cases involving section 205 proceedings that the Commission converts into section \n206 proceedings because “the relevant provisions of the [NGA and FPA] ‘are in all material respects substantially \nidentical.’” Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 577 n.7 (1981) (quoting FPC v. Sierra Pacific Power \nCo., 350 U.S. 348, 353 (1956)); see also Monongahela Power Co., 164 FERC ¶ 61,217, at P 17 (2018) (applying \nWestern Resources in an a proceeding that was initiated under FPA section 205)."},{"page":5,"startToken":1381,"endToken":1688,"text":"-5- \n(2) the status quo is also unjust and unreasonable as LSEs are signing up more new retail customers \nthan the region can reliably serve yet the PJM tariff lacks any mechanism for equilibrating supply \nand demand in the capacity market; and (3) as Google explained in its initial protest, “there are \nample alternative avenues through which PJM, in cooperation with the States, could facilitate the \ngoals underlying IRAS, rather than impeding them,”11 including the development of an \ninterruptible service, modeled on what exists for natural gas transportation, that provides clear and \ntransparent rules for determining which customers take interruptible service as well as when and \nhow they will be interrupted to ensure supply and demand remain balanced. To implement this \noption, the Commission could find that all of IRAS is unjust and unreasonable or it could accept \nonly the Large Load Registry.  Either way, it would simultaneously initiate a section 206 \nproceeding regarding the existing tariff (Western Resources Step 2 above) and potential \nreplacement rates (Western Resources Step 3 above) and consolidate the record of this proceeding \ninto that new one.12  \nIt bears reiterating: Google’s interest in this proceeding is to ensure that PJM has a \nfunctioning resource adequacy construct that provides the incentives necessary to develop \nsufficient new capacity to meet demand in PJM over the short-, medium-, and long-term.  IRAS is \nemphatically not that.  Accordingly, Google urges the Commission to assert its leadership on these \nissues and put PJM back on course.   \nI. \nMOTION FOR LEAVE TO ANSWER \nAlthough the Commission’s procedural rules generally do not allow answers to answers, \n \n11 Google Protest at 16. \n12 See Tennessee Gas Pipeline Co.v. FERC, 860 F.2d 446, 456 (D.C. Cir. 1988); W. Res., Inc. v. FERC, 9 F.3d \nat 1579; Monongahela Power Co., 164 FERC ¶ 61,217 at P 17."},{"page":6,"startToken":1688,"endToken":2089,"text":"-6- \nthe Commission may permit them for good cause.13  The Commission frequently accepts answers \nthat clarify the issues before the Commission, ensure a complete record, or otherwise assist the \nCommission in its decision-making.14  Google therefore respectfully requests that the Commission \naccept this answer, which will assist the Commission with its decision-making by setting forth the \njustification for the Commission action under the Western Resources framework, discussed above. \nII. \nANSWER \nAs Google explained in its initial protest, PJM is correct that the demand for electricity is \noutpacing supply, and reforms are necessary to manage periods in which demand exceeds supply \nand to incentivize the development of the new capacity to prevent those imbalances in the future.  \nBut IRAS would only make things worse.  As an overwhelming majority of commenters pointed \nout, IRAS is both illegal and likely to be counterproductive.  Rather than incentivizing New Large \nLoads to contract with new capacity, it will chill such investment and further erode resource \nadequacy in the region.  That uncertainty is the result of both IRAS’s patent legal deficiencies, \nwhich provide ample bases for it to be overturned on appeal, and the fact that PJM lacks authority \nto dictate retail curtailment priority, which means that IRAS will not provide the regulatory \ncertainty that is necessary to incentivize investment in new capacity.   \nThe Commission must either reject IRAS with guidance to PJM to establish a legally \ndurable approach that includes a clear and transparent category interruptible service that does not \n \n13 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, \nor a request for rehearing, unless otherwise ordered by the decisional authority.”). \n14 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that \n“provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC \n61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s \ndecisionmaking process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that \n“clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage \nCo., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding \nthe issues raised, and will ensure a complete record”)."},{"page":7,"startToken":2089,"endToken":2443,"text":"-7- \ntarget individual retail customers or take the reins itself to do the same pursuant to the D.C. \nCircuit’s decision in Western Resources by “transforming” this section 205 proceeding into one \nunder section 206.15     \nThe Commission can satisfy all three Western Resources conditions here.  First, it should \nreject IRAS because it exceeds the Commission’s jurisdiction under the FPA and has not been \nshown to be just and reasonable and not unduly discriminatory or preferential.  Google explained \nthese points in its initial protest, and the record established so far in this proceeding only confirms \nthe point.  The one possible exception is the Large Load Registry, which could play a valuable \ninformation-sharing role without transgressing the FPA’s jurisdictional lines and could be severed \nfrom the rest of the filing consistent with PJM’s statements in its transmittal letter and the \nprinciples in NRG.16 \nSecond, despite demand for firm capacity outpacing supply, there is no option in PJM’s \ntariff allowing LSEs to take interruptible service.  The absence of any interruptible service, and \nthe resulting imbalance in the supply and demand for firm capacity, is eroding system reliability \nand will degrade the quality of firm service because PJM will inevitably have to manage supply \nand demand through the use of emergency procedures and curtailment of customers attempting to \ntake firm service.  In addition to degrading the quality of Commission jurisdictional service, it also \ncreates uncertainty that impairs investment in new capacity needed for PJM to eventually escape \nthe current resource adequacy crisis.  Accordingly, the fact that the PJM tariff lacks a permanent, \n \n15 W. Res., Inc. v. FERC, 9 F.3d at 1579; see also Monongahela Power Co., 164 FERC ¶ 61,217 at P 17. \n16 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load \nRegistry to Address System Reliability, Docket No. ER26-3515-000, at 9 (filed Aug. 13, 2026) (“Transmittal”); NRG \nPower Mktg., LLC v. FERC, 862 F.3d 108, 114 (D.C. Cir. 2017) (holding that the Commission has “some authority \nto propose modifications to a utility’s [FPA section 205] proposal if the utility consents to the modifications”)."},{"page":8,"startToken":2443,"endToken":2752,"text":"-8- \nclearly defined service option through which an LSE can procure interruptible, non-capacity \nbacked service renders the PJM tariff unjust and unreasonable.   \nThird, the Commission should adopt a replacement rate that establishes an interruptible \nservice option through which an LSE can elect to serve load on a non-firm basis.  Such service \nwould not be capacity-backed, and PJM would not procure capacity to serve it.  Instead, load \ntaking interruptible service could consume electricity when there is sufficient capacity on the \nsystem, subject to defined triggers to interrupt the provision of electricity as conditions tighten and \nbefore emergency procedures are triggered.  This service would be highly similar to interruptible \nservice in the gas transportation context, which would allow additional demand to be served while \npreserving priority for firm customers.  It would also build on the reasoning underlying the \nCommission’s recent PJM Co-Location Order where it created interim Network Integration \nTransmission Service (“NITS”) to address a similar concept.  \nPJM should define this service in its tariff, including when it is available and when PJM \nwould direct LSEs to curtail participating load. Curtailment would be a condition of interruptible \nservice, triggered before emergency procedures become necessary.  States would then be \nresponsible for determining which retail customers take interruptible retail service.   That approach \nboth solves the basic supply and demand problem—because PJM knows to interrupt the \ninterruptible customers when demand exceeds supply—and puts states in position to determine \nwhich customers qualify for firm service and which do not.  For example, the states could \ndetermine whether data centers can receive firm service only if they bring their own new capacity \nand customers, including data centers, would have the certainty they need to make investments in \nsuch new capacity because the regulator imposing the requirement also has authority over the \ncurtailment priority.  In that way, this approach would address the basic motivation behind IRAS"},{"page":9,"startToken":2752,"endToken":3086,"text":"-9- \nwithout the self-defeating uncertainty that it would create.  Additionally, to address a potential \nsupply shortfall in the near term, PJM should establish a framework for curtailing large loads, \nincluding those with firm service, prior to other retail customers during emergency conditions \nwhen PJM is approaching a broad Manual Load Dump.  \nA. The Record Confirms that PJM Has Not Satisfied Its FPA Section 205 Burden \nGoogle explained in its initial protest that IRAS falls well short of meeting PJM’s burden \nunder section 205 to show that its proposal meets the just and reasonable standard and is not unduly \ndiscriminatory.  Instead, it is fatally flawed in several respects.  First, IRAS exceeds the \nCommission’s authority because it aims at, targets, and is impermissibly tethered to the retail \nsphere.17  Second, IRAS unduly discriminates on the basis of retail customer characteristics that \nare beyond the Commission’s jurisdiction to consider and, separately, for reasons that have nothing \nto do with the resource adequacy concerns that PJM is trying to address (e.g., when the large load \nbegan operating).18  Finally, IRAS is unjust and unreasonable because PJM would require IRAS \ncurtailment before deploying demand response resources that have agreed to be curtailable and \nbecause PJM cannot ensure that New Large Loads that bring new capacity will receive firm \nservice.19  Each of those several issues would provide an appellate court with sufficient \njustification to overturn an order accepting the IRAS proposal.   \nWere there any doubts about the legality of IRAS, the Commission need only look at the \npleadings in this docket, which overwhelmingly confirm that IRAS has not been shown to be just \nand reasonable and not unduly discriminatory or preferential.  Indeed, the overwhelming majority \n \n17 Google Protest at 8-11; see Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) (“Oneok”); FERC v. Elec. \nPower Supply Ass’n, 577 U.S. 260, 282 (2016) (“EPSA”); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 166 \n(2016) (“Hughes”). \n18 Google Protest at 11-13. \n19 Id. at 13-16."},{"page":10,"startToken":3086,"endToken":3413,"text":"-10- \nof entities participating in this proceeding—utilities, independent power producers, data center \noperators, consumer advocates, industry trade groups, state public utility commissions, and \nindividual retail customers—all oppose IRAS in whole or part.  Of the roughly 40 parties that filed \ninitial pleadings in the docket, only a few embrace the IRAS proposal and recommend that the \nCommission accept it as proposed.  The number and quality of the protests provide compelling \nevidence both that PJM has not met its burden with respect to IRAS and that any order accepting \nit would face strong challenges on appeal.  Simply put, the record in this proceeding provides \nmore-than-ample evidence for the Commission to conclude that IRAS exceeds the Commission’s \njurisdiction and has not been shown to be just and reasonable and not unduly discriminatory or \npreferential.    \nAlthough the record reflects overwhelming opposition to IRAS, a handful of answers now \nseek to resuscitate the moribund case for accepting it.  Google appreciates that those answers \nreflect a genuine belief that IRAS will respond to the very real practical challenges caused by load \ngrowth that outstrips supply.  Nevertheless, as explained below and in Google’s initial protest, \naccepting IRAS would make matters worse by creating pervasive uncertainty that will exacerbate \nthe region’s resource adequacy shortfall.  Although Google agrees that PJM and the Commission \nshould do something, it is critical that PJM and the Commission do the right thing, lest PJM’s \nresource adequacy situation deteriorate further at a time when PJM can least afford it.   \nGoogle agrees that PJM is facing the prospect of a serious resource adequacy shortfall and \nthat New Large Loads must step up and cover that capacity shortfall, consistent with the Ratepayer \nProtection Pledge.  As noted above, that is exactly what Google is doing as it expands its operations \nin PJM.  Google has also made clear that New Large Loads that do not offset their demand with \nnew capacity should be curtailed prior to other firm wholesale customers when system conditions"},{"page":11,"startToken":3413,"endToken":3702,"text":"-11- \nwarrant.  Accordingly, when it comes to Google, it is incorrect to suggest that opposition to IRAS \n“fl[ies] in the face of commitments . . . already made in the Ratepayer Protection Pledge, and [is] \nessentially an argument that the new capacity needed to serve data centers must be paid for by all \nPJM customers through higher capacity market prices rather than by the actual cost-causers.’”20  \nInstead, Google opposes IRAS because of its potential to exacerbate the region’s resource \nadequacy issues, harming all PJM customers.  Far from evincing any weakness in Google’s \ncommitment to the Ratepayer Protection Pledge, our opposition reflects our commitment to well-\nfunctioning and rational markets as one of the central pillars by which the industry can realize the \ngoals of the Pledge.  \nBelow, Google addresses the key points in the answers filed to date and explains why they \ndo not call into question the clear consensus among the initial comments that IRAS is \nfundamentally flawed and must be rejected.   \n1. Jurisdiction \nIRAS exceeds the Commission’s jurisdiction.  The arguments to the contrary do not wrestle \nwith the critical jurisdictional arguments, instead slaying strawmen and assuming away IRAS’s \nfundamental flaws.  Indeed, many of those arguments are variations on the theme that, because \nPJM does not direct the curtailment of individual retail customers, IRAS must not exceed the \nCommission’s jurisdiction.  For instance, PJM contends that “the issue of jurisdiction is about \nwhich entity gets to identify the retail customers who ultimately respond to PJM’s directives to \nreduce load.”21  But the FPA does not so rigidly elevate form over substance in the way some \nparties suggest.  Instead, courts have “emphasize[d] the importance of considering the target” of \n \n20 Gov. Shapiro Answer at 5. \n21 PJM Answer at 29."},{"page":12,"startToken":3702,"endToken":4017,"text":"-12- \nthe regulation in question when considering jurisdictional challenges under the FPA. 22  It is that \ninquiry that recognizes the fact that the federal and state spheres of jurisdiction under the FPA are \nnot “hermetically sealed”23 and, if not properly policed, a federal or state regulation that purports \nto address a jurisdictionally appropriate matter can, in fact, regulate a matter within the other’s \nexclusive jurisdiction.   \nIRAS’s target is evident from its very structure.  IRAS conditions the quality of wholesale \nservice on the characteristics of retail customers.  Specifically, under IRAS, PJM would identify \nfor each zone or area the Eligible New Large Load Amounts—i.e., the quantity of New Large Load \ndemand that is not offset by new capacity.24  When system conditions warrant, PJM would instruct \n(“Electric Distributors”) EDs to curtail load in amounts equal to or less than the ED’s Eligible New \nLarge Load Amount.25  In other words, the amount of load shed under IRAS depends entirely and \nexclusively on the characteristics of the retail load in each zone or area.  Retail customers are “the \nmechanism through which the rule operates.”26  That is the purpose of IRAS, not some unintended \nbyproduct.  To see that clearly, it is worth considering what would happen if the IRAS MW load \nreduction in each zone or area was not determined by, and thus tethered to, individual retail \ncustomer characteristics.  In that hypothetical, PJM would have no mechanism for determining the \namount of load to reduce in a given footprint, and, simply put, IRAS would cease being IRAS.  The \nretail customer targeting is therefore the defining feature of the proposal. \n \n22 Oneok, 575 U.S. at 385; EPSA, 577 U.S. at 282 (citing Oneok, 575 U.S. at 385).  \n23 EPSA, 577 U.S. at 281. \n24 Transmittal at 69. \n25 See, e.g., id. at 86. \n26 EPSA, 577 U.S. at 283."},{"page":13,"startToken":4017,"endToken":4332,"text":"-13- \nIn arguing to the contrary, PJM fundamentally misrepresents the Supreme Court’s \n“targeting” inquiry, arguing that “[w]hether such a rule ‘targets’ retail or wholesale customers \nturns on the justification for the rule, not on whether or the extent to which the rule affects or even \ncompels action of retail or wholesale customers.”27  When it comes to determining whether a rate \nis jurisdictionally permissible under the FPA, the dispositive question is how it works in practice, \nnot the relevant public utility’s transmittal letter.  While the justification a public utility provides \ncan shed light on how the tariff works, the jurisdictional inquiry turns on what is actually on file \nwith the Commission.28  After all, if the justification were all that matters, FERC could force a \npublic utility to adopt time-of-use retail rates by listing their salutary effects on the wholesale \nmarket.   \nThe Court’s precedents confirm that is how the FPA works.  In EPSA, the Court began by \nexamining how “demand response works” and concluding that it was an exclusively wholesale \nconstruct before observing that the Commission’s justification was “all about and only about” the \nwholesale market.29  Similarly, in Hughes, although Maryland’s justification was to encourage \nconstruction of new in-state generation,30 that did “not save” the program because “States may not \nseek to achieve ends, however legitimate, through regulatory means that intrude on FERC’s \nauthority.”31   \n \n27 PJM Answer at 18-19. \n28 See 16 U.S. Code § 824d(c) (“[E]very public utility shall file with the Commission . . . and shall keep open in \nconvenient form and place for public inspection schedules showing all rates and charges for any transmission or sale \nsubject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates \nand charges.”). \n29 EPSA, 577 U.S. at 282. \n30 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 158 (2016).  \n31 Id. at 163-64."},{"page":14,"startToken":4332,"endToken":4655,"text":"-14- \nApplying that framework here, the fact that PJM’s transmittal letter uses “reliability,” 32 \n“resource adequacy,”33 “reserve requirements,”34 and other wholesale-market verbiage cannot \nmake IRAS legal.  That is because no number of synonyms for reliability can cure the fact that \nretail characteristics, including retail customer size and retail customer interconnection and ramp \nrates, are what determine whether and how IRAS applies.  As Google explained in its opening \nprotest, it is not the wholesale-market growth rates that determine whether IRAS applies; \nwholesale-market growth is irrelevant.   Consider the following two examples.  First, IRAS would \nnot apply to an ED that grows by 1,000 one-MW increments while it would apply to an ED that \ngrows by 50 MW due to a single customer.  Second, an ED that adds an otherwise Eligible New \nLarge Load on May 31, 2027 would not be subject to IRAS, while an identical ED that adds an \nEligible New Large Load on June 1, 2027 would be.  In other words, while an ED’s aggregate load \ngrowth is the demand-side metric relevant to resource adequacy, it is not the focus of IRAS and \ndoes not determine whether IRAS applies.  That is what matters because, when it comes to FPA \njurisdiction, actions speak louder than words.   \nPJM also suggests that IRAS must be jurisdictionally sound because it would regulate \nissues at the confluence of federal and state jurisdiction, arguing that “entities that seek rejection \nof the IRAS proposal on jurisdictional grounds conveniently overlook the fact that integrating \nlarge loads in a manner that (1) ensures reliability; (2) allows for these loads to interconnect to the \nsystem; and (3) protects existing ratepayers, is a responsibility shared between the states and \nPJM.”35  Google agrees that both the Commission and the states have important roles to play in \n \n32 PJM Answer at 21 (quoting Transmittal at 6). \n33 Id. (quoting Transmittal at 3). \n34 Id. (quoting Transmittal at 2). \n35 Id. at 3."},{"page":15,"startToken":4655,"endToken":4997,"text":"-15- \naddressing the issues in this docket.36  But the fact that both the Commission and states have an \nimportant role to play does not give PJM license to redraw the FPA’s jurisdictional line to suit its \npreferences. \nOther specific arguments advanced in defense of IRAS fare no better.  For example, parties \ncontend that IRAS does not “target retail customers by making the characteristics of the retail \ncustomer the basis for a curtailment obligation.”37  But the same Answer disproves this argument, \nexplaining that “PJM proposes to limit the total MWs of load reduction in a zone or area based on \nthe share of new large loads . . . that have failed to meet their capacity needs through BYONC or \ncapacity procured pursuant to Reliability Backstop Procurement (RBP) rules.”38  Similarly, the \nPublic Interest Organizations argue that “PJM will respect jurisdictional boundaries by directing \nIRAS Actions at the wholesale level.  PJM will never curtail individual retail customers—instead, \nit uses the Registry and results from the most recent BRA to designate megawatt quantities of \nIRAS curtailment by zone.”39  But here too, the quoted language proves that the opposite is true \nbecause the individual retail customer characteristics in the Large Load Registry are what trigger \nthe wholesale curtailments under IRAS, illustrating how IRAS is targeted at retail customers.  In \nshort, no one in this proceeding has credibly shown that IRAS is “all about, and only about” the \nwholesale market.40  Instead, as even statements from supporters of IRAS demonstrate, retail \ncustomer characteristics are the trigger for IRAS, which illustrates how IRAS targets the retail \n \n36 See infra section II.C. (explaining that the Commission could direct PJM to amend its tariff to establish a \nfederal interruptible service framework that would accommodate state retail-level tariffs). \n37 Gov. Shapiro Answer at 7 (cleaned up) (quoting Google Protest at 8-9). \n38 Id. at 8; see id. (IRAS “[d]uly target[s] load reductions in zones or areas with non-capacity backed new large \nloads . . . .” (emphasis added)). \n39 PIOs Comments at 19. \n40 EPSA, 577 U.S. at 282."},{"page":16,"startToken":4997,"endToken":5333,"text":"-16- \nmarket by creating the sort of impermissible “tether” to the retail market that cannot be remedied \nby its wholesale market effects.41   \nThe same goes for arguments that IRAS is about addressing transmission zones with \ncapacity shortfalls.  For example, parties attempt to recast IRAS as “focus[ing] on zones or areas \nprojected to have capacity shortfalls in real-time—through the existence of non-capacity backed \nlarge loads in the planning horizon.”42   But those descriptions overlook the defining feature of \nIRAS: how PJM determines the amount of load to be reduced under IRAS.  That determination \ndepends entirely on the extent to which certain retail customers offset their demand with new \ncapacity.  IRAS does not focus on areas projected to have capacity shortfalls; only on areas with \nretail customers that qualify as Eligible New Large Loads.  As explained above, a zone could have \na GW capacity shortfall and be exempt from IRAS if its load growth is in the form of 1,000 one-\nMW loads (or, indeed, 20 49-MW loads), while another zone that does not have a shortfall but has \none New Large Load that did not bring new capacity would be subject to IRAS.  Put differently, \nunder IRAS, an LSE or an ED could be net long, with sufficient capacity to serve all of the loads \nin its footprint, but if a New Large Load comes online without offsetting capacity, that LSE/ED \nwould still receive a curtailment instruction.  As the above hypothetical confirms, yet again, IRAS \nis about the transmission zone’s retail customers, not about its capacity shortfall.   \nParties claim that “protestors cannot logically claim both that PJM’s proposal unlawfully \n‘targets retail customers’ and that PJM’s proposal is fatally flawed because it cannot guarantee \n \n41 Hughes, 578 U.S. at 165-66 (explaining that States can encourage production of new or clean generation—\nwhich comes within the states’ jurisdiction of generation facilities—as long as the states’ actions are “untethered to a \ngenerator’s wholesale market participation.” (emphasis added)). \n42 Gov. Shapiro Answer at 9."},{"page":17,"startToken":5333,"endToken":5722,"text":"-17- \nwhich individual retail customers are curtailed.”43  Supreme Court precedent says otherwise.  \nIndeed, the Supreme Court developed its jurisprudence regarding the “target” or “aim” of a \nregulation precisely because it is possible for a regulator to nominally address a matter within its \njurisdiction while actually “targeting” a matter outside its jurisdiction.44  In Oneok, Hughes, and \nthe Court’s predecessor cases, the Court recognized the distinct possibility that a state or the \nCommission could impermissibly target or aim at a matter outside of its jurisdiction without \nliterally regulating the matter in question.45  There is no logical inconsistency in the fact that IRAS \nis unlawfully targeted at retail customers even though PJM would not take the final step of carrying \nout the curtailment decisions.46   \nElsewhere, parties claim that, as the region’s Reliability Coordinator, Transmission \nOperator, and Balancing Authority, PJM already has the authority to take the curtailment actions \nthat it might have to under IRAS. 47  Google agrees that PJM has (and must have) the authority to \ncurtail loads to protect reliability.  But that does not make IRAS legal.  The fact that PJM has the \nauthority to order curtailments in general does not mean that any curtailment mechanism is \nnecessarily legal.  Similarly, because, for the reasons explained above,48 IRAS would condition \nthe quality of a wholesale service on retail customer characteristics, it would exceed the \nCommission’s jurisdiction though PJM can order curtailment in other circumstances.    \n \n43 Id. at 9-10; PJM Answer at 28 (quoting Gov. Shapiro Answer at 9-10). \n44 See Hughes, 578 U.S. at 164; Oneok, 575 U.S. at 385; N. Nat. Gas Co. v. State Corp. Comm’n of Kan., 372 \nU.S. 84, 94 (1963); Nw. Cent. Pipeline Corp. v. State Corp. Com’n of Kan., 489 U.S. 493, 514 (1989). \n45 See Hughes, 578 U.S. at 164; Oneok, 575 U.S. at 385; N. Nat. Gas Co., 372 U.S. at 94; Nw. Cent. Pipeline \nCorp., 489 U.S. at 514. \n46 See Hughes, 578 U.S. at 164. \n47 Gov. Shapiro Answer at 7 (“Indeed, actions that would be possible under IRAS are no different from other \nactions (or ‘Operating Instructions,’ as defined by NERC) that PJM has long been authorized to take as the region’s \nReliability Coordinator, Transmission Operator, and Balancing Authority.”). \n48 See supra section II.A.1."},{"page":18,"startToken":5722,"endToken":6043,"text":"-18- \n \nNext, parties suggest that protesters are arguing that PJM “is legally barred from acting on \ninformation about the characteristics of load growth in a zone or area, even if that information is \ndirectly relevant to reliable operation of the bulk power system and enables PJM to provide a just \nand reasonable wholesale product or service.”49  That is another strawman.  As explained above, \nPJM is emphatically not considering “load growth in a zone or area” or even capacity shortfalls in \nspecific zones.50  IRAS does not apply based on any of those considerations.  Instead, IRAS applies \nbased on retail customer characteristics.  As such, the question of whether the Commission could \nact on the basis of load growth itself is simply not presented in this proceeding.   In any case, \nGoogle’s position is not that PJM cannot consider “the characteristics of load growth in a zone or \narea.”  After all, Google supports the Large Load Registry as a valuable means of gathering that \ninformation, and PJM can and does consider the aggregate characteristics of each zone in \nregulating wholesale market participants, whether LSEs or EDs.  What PJM cannot do is condition \nthe quality of wholesale service on individual retail customer characteristics.   \nFurther, parties are incorrect that “the protestors’ position would bar PJM from taking into \nconsideration information about generating facilities—ramp rates, minimum run times, outage \nrates, and so on—because neither the Commission nor PJM have authority to directly regulate \ngeneration.”51  Generators participate in wholesale markets under Commission jurisdiction and \nthose characteristics are directly relevant to and directly affect wholesale sales under the \nCommission’s jurisdiction.  In other words, rules regarding those factors can be aimed at and \njustified by a rationale that is “all about, and only about, improving the wholesale market.”52  The \n \n49 Gov. Shapiro Answer at 10. \n50 See supra section II.A.1. \n51 Gov. Shapiro Answer at 11. \n52 EPSA, 577 U.S. at 282."},{"page":19,"startToken":6043,"endToken":6358,"text":"-19- \nsame cannot be said of retail customers or retail customer characteristics that never come within \nCommission jurisdictional markets.   \nPerhaps most surprisingly, PJM tries to fit IRAS within the context of the Commission’s \nrecent Tri-State order.  Specifically, PJM notes that the Commission’s most recent order held that \nin “addressing ‘concerns regarding the rapid growth of large loads,” Tri-State’s proposal “do[es] \nnot constitute ‘an impermissible intrusion upon retail rate regulation.’”53  From that, PJM reasons \nthat, “while the IRAS framework may ultimately affect retail customers, it cannot be said to \n‘present an impermissible intrusion upon retail rate regulation.’”54  But beyond pointing out the \nobvious fact that both the Tri-State proposal and IRAS addressed large load growth, PJM never \nexplains how Tri-State bears any resemblance to this case.55  That similarity cannot be enough to \nestablish jurisdiction for IRAS.  After all, the Commission rejected Tri-State’s earlier filing \naddressing large loads on the ground that it exceeded the Commission’s jurisdiction. 56  In any case, \nthe Tri-State HIL proposal applies to wholesale transmission customers—i.e., Tri-State Member \nUtilities—who have the discretion to decide whether to pass certain HIL-related obligations on to \ntheir retail customers.   The Tri-State proposal would not condition wholesale market service on \nthe characteristics of specific retail customers.  Under IRAS, by contrast, the wholesale \ncustomer—i.e., the LSE or ED—is required to curtail transmission service and to do so in amounts \ndetermined solely based on the characteristics of retail customers.  Were the Tri-State proposal to \nactually resemble IRAS, as PJM claims, then the requirements that Tri-State imposes on its \n \n53 PJM Answer at 25 (quoting Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at P 68 (2026)). \n54 Id. at 26 (quoting Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at P 66). \n55 See id. at 24-26.   \n56 See Tri-State Generation and Transmission Association, Inc., 193 FERC ¶ 61,070 (2025)."},{"page":20,"startToken":6358,"endToken":6668,"text":"-20- \nMember Utilities would vary depending on the characteristics of the retail customers those \nMembers serve.   \n2. Undue Discrimination \nIRAS is also unduly discriminatory.  The Answers that contend otherwise fail to either \nwrestle with or rebut the arguments illustrating that IRAS would treat similarly situated entities \ndifferently without a legally cognizable basis for doing so.  As such, the discrimination inherent in \nIRAS cannot be “due.”   \nAs a threshold matter, while parties contend that IRAS is not unduly discriminatory \nbecause it treats “novel forms of load” differently than “traditional forms of load,” this argument \nconfirms that IRAS unlawfully “targets” the characteristics of certain retail customers.  \nSpecifically, protestors argue that new loads have different characteristics (i.e., they are larger, \nfast-paced additions, concentrated in a single location) than traditional retail customers and \ntherefore it is not unduly discriminatory to treat them differently.57  All of those features—the size, \nspeed, and geographic proximity of the loads within a transmission zone—are again characteristics \nof the retail customer, not the wholesale market.  The fact that defending IRAS requires \ndistinguishing between retail characteristics to explain why one group of those retail customers \nshould be curtailed only confirms that IRAS unlawfully targets retail customers. \nIn any case, the Commission cannot justify discrimination based on characteristics that the \nCommission is legally prohibited from regulating—i.e., retail customer characteristics—because \nsuch differences are not (and cannot be) “material to the inquiry at hand.”58  A conclusion to the \n \n57 Gov. Shapiro Answer at 15-16. \n58 N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at PP 10, 14 (2018) (“To say that entities are similarly \nsituated does not mean that there are no differences between them; rather, it means that there are no differences that \nare material to the inquiry at hand.”); see also id. P 14 (finding that a difference between incumbent and non-incumbent"},{"page":21,"startToken":6668,"endToken":7044,"text":"-21- \ncontrary would open the door to a host of “surprising”59 new bases for Commission regulation.  \nFor example, if retail customer characteristics were a legitimate basis for wholesale market \ndiscrimination provided that the public utility could ascribe reliability benefits to the \ndiscrimination, there would be nothing to prevent the Commission from conceivably justifying \nwithholding firm service to LSEs that serve a disproportionate number of single-family homes on \nthe basis that LSEs that instead disproportionately serve apartment buildings are more electrically \nefficient and incentivizing apartments relative to single-family homes would enhance regional \nresource adequacy.  Yet such a scheme would clearly be impermissible because it so obviously \ndiscriminates against LSEs based on the retail loads in their footprints.  Nevertheless, that is the \nprinciple that PJM is asking the Commission to endorse by finding that retail customer \ncharacteristics could be valid bases for conditioning the quality of wholesale service in IRAS. \nParties argue that the Commission has already distinguished New Large Loads in the \ncontext of its June 18th Show Cause Orders and NERC’s forthcoming Reliability Standards.60  \nWhile the Commission has found that large loads are different in certain respects from organic \nload growth, those findings were made in proceedings addressing different issues and statutory \nauthorities than here.  First, the Commission’s Show Cause Orders carefully target the transmission \nservices that Eligible Customers—i.e., wholesale customers—take to serve New Large Loads \nbased on how those Eligible Customers request service and use the transmission system. 61  For \n \ntransmission developers was not material to the issue at hand and therefore could not be the basis for discriminating \nbetween incumbents and non-incumbents). \n59 EPSA, 577 U.S. at 277. \n60 Gov. Shapiro Answer at 17. \n61 See, e.g., PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 41 (2026) (“We today make a preliminary \nfinding that PJM’s Tariff appears to be unjust and unreasonable because it lacks provisions that address, with sufficient \nclarity and consistency, how PJM and/or the Transmission Owners will timely study (i.e., within 60-90 days of \nreceiving the request) the provision of transmission service to Eligible Customers on behalf of large loads.” (emphasis \nadded)); id. P 45 (“Specifically, we find that it is within the Commission’s exclusive authority to ensure that"},{"page":22,"startToken":7044,"endToken":7413,"text":"-22- \ninstance, the PJM Show Cause Order preliminarily found PJM’s Tariff unjust and unreasonable \nbecause it does not sufficiently address how PJM and the Transmission Owners “will study the \nprovision of transmission service to Eligible Customers on behalf of large loads.”62  That is \ndistinctly different from IRAS where the retail customer characteristics are what determines the \nquality of wholesale service.  Second, NERC Reliability Standards are issued under Section 215 \nof the Federal Power Act, which applies to “all users, owners and operators of the bulk-power \nsystem.”63  Whether a New Large Load constitutes a user of the bulk-power system is irrelevant \nto the question at issue here:  whether two classes of customers are differently situated such that \ndifferential treatment is permissible under section 205.   \nAttempts to justify undue discrimination based on the vintage of the retail load fare no \nbetter.  Most notably, PJM is wrong to argue that “[n]ew, not existing load, is the reason for the \nshortfall, which drives the need for IRAS. Failing to make a distinction between New Large Loads \nand Large Loads for purposes of applying IRAS would fail to account for causation.” 64  As the \nD.C. Circuit has explained, all load is “economically marginal” in the sense that customers impose \nequivalent costs “whether by adding or merely continuing their usage” regardless of when they \nfirst took service, meaning that each MW of demand, whether new or existing, contributes equally \nto the region’s current resource adequacy picture.65  \n \ntransmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing \nhow transmission service to Eligible Customers on behalf of large loads interconnecting to the transmission system \nwill be studied, including whether new or upgraded transmission facilities are necessary to provide the requested \ntransmission service.”); id. P 49 (“In sum, we today exercise our authority to ensure that the process by which \njurisdictional transmission providers and/or transmission owners will study the provision of jurisdictional transmission \nservice to Eligible Customers on behalf of large loads.”). \n62 Id. P 51. \n63 16 U.S.C. § 824o(b)(1). \n64 PJM Answer at 61. \n65 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268-69 (D.C. Cir. 2014) (citations omitted)."},{"page":23,"startToken":7413,"endToken":7770,"text":"-23- \nWhile parties suggest that IRAS does not discriminate between new and existing loads and \ninstead simply applies “on a forward-looking basis to new large loads after its acceptance,”66 this \nis not the case.  IRAS is not merely an extension of the Commission’s standard practice of \naccepting new rules on a prospective basis while grandfathering existing entities.  Instead, IRAS \nwould switch on and off again based on future supply and demand conditions.67  If and when IRAS \nswitches on again, it would reset what constitutes baseline and new, meaning that retail customers \nthat would count as New Large Loads in 2027 might not be subject to IRAS in just a few years \nand would instead be considered baseline loads during a future invocation of IRAS.  Although \nthere may be a reasonable policy justification for this approach, it shows that IRAS is not a one-\ntime grandfathering mechanism but rather an arbitrary distinction that treats retail customers \ndifferently based on the background circumstances at the time they interconnected and ramped up \ntheir load.68   \nFinally, attempts to justify undue discrimination based on the fact that existing loads paid \nfor capacity in previous years reveal a misunderstanding of the basic principles that underlie PJM’s \ncapacity market.  The capacity market auction functions for resources to sell capacity for a specific \ndelivery year.69  The market procures capacity to meet aggregate regional needs for that particular \nyear; it does not provide specific individual customers the right to specific shares of capacity.  Nor \n \n66 Gov. Shapiro Answer at 18 (emphasis added). \n67 Transmittal at 52-53, 72. \n68 But see BNP Paribas, 743 F.3d at 268 (“[T]he cost causation principle generally calls for giving the same \ntreatment to new and continuing customers.”); 1 Alfred Kahn, The Economics of Regulation: Principles and \nInstitutions 140 (The MIT Press 1998) (explaining that an existing customer that is “continuing to take service is just \nas responsible, in proportion to the amount they take, for the need to expand investment” to accommodate another \ncustomer’s increasing demand). \n69 PJM, Open Access Transmission Tariff, attach. DD.5.4 (Reliability Pricing Model Auctions) (10.0.0), § 5.4."},{"page":24,"startToken":7770,"endToken":8086,"text":"-24- \ndoes it provide customers any claim to preferential treatment for subsequent years. 70  Otherwise, \nevery new subdivision, factory, or business would need to bring its own new capacity because \nexisting capacity can only be committed to serve existing loads.  By the same token, no capacity \nresource could ever retire or de-list because it would be obligated to continue serving as a capacity \nresource in perpetuity.   \n3. Unjust and Unreasonable \nIRAS is also unjust and unreasonable.  Here too, there are multiple bases for that \nconclusion:  (i) the curtailment priority cannot be the product of reasoned decision-making and (ii) \nPJM cannot ensure that loads that bring new capacity to secure firm transmission service will, in \nfact, receive that service.  Either of these issues is sufficient reason to reject IRAS, and the Answers \nhave not shown otherwise.    \ni. \nCurtailment Priority  \nAs an initial matter, the suggestion that the curtailment priority, which is the central feature \nof IRAS, is a “policy judgment[] that do[es] not render the design unjust and unreasonable,” 71 is \nnovel, unsupported by any citation to precedent or other authority, and incorrect.  The curtailment \npriority is part of the tariff language filed with FERC and therefore it must be just and reasonable, \nwhether or not it implicates any policy judgment.72  A rule providing that the Commission could \nnot reject a filing because it contained a policy judgment would fly in the face of the section 205’s \nplain language and be unworkable in the extreme.   \nThe merits of the IRAS curtailment priority are equally problematic.   \n \n70 See BNP Paribas, 743 F.3d at 269 (“[T]he Commission doesn’t explain why the historic shippers’ earlier \n[payments] . . . give[] them a special equitable claim in perpetuity.”). \n71 Gov. Shapiro Answer at 5. \n72 Section 205 provides that all “rules and regulations affecting or pertaining to [Commission-jurisdictional \nrates] . . . shall be just and reasonable.” 16 U.S.C. § 824d(a)."},{"page":25,"startToken":8086,"endToken":8418,"text":"-25- \nFirst, PJM’s answer all but concedes that curtailing Eligible New Large Loads before \ndemand response resources violates cost causation principles.  According to PJM, “Eligible New \nLarge Loads available to provide IRAS have not satisfied their respective capacity needs through \nBYONC, and therefore, should not obtain the capacity benefit of Demand Resources.” 73  \nNevertheless, Eligible New Large Loads will be allocated capacity charges, which will include \ncosts to pay for demand response resources providing capacity.  But those New Large Loads will \nnot get any benefit for the portion of their capacity costs attributable to demand response resources.  \nAnd that is not some rounding error that is acceptable in the name of a roughly commensurate cost \nallocation.74  Rather, it is a foundational feature of IRAS and reason enough to conclude that it has \nnot been shown to be just and reasonable.    \nNevertheless, PJM attempts to defend this result by asserting that Eligible New Large \nLoads “would be compensated [to curtail under IRAS], in part, to account for the fact” that those \nloads “would not be able to obtain the full benefit” of the demand response capacity they have \nhelped finance.75  In other words, PJM is proposing to require New Large Loads to pay for capacity \nfrom which they will receive no benefits in exchange for the hope that those loads will receive an \noffsetting retail payment, which the Commission cannot ensure they will receive.  While cost \ncausation does not require exacting precision, it requires more than the mere hope that wholesale \ncosts will be offset down the line by retail compensation.   \nSecond, PJM is also wrong to argue that the curtailment order “is consistent with PJM’s \ncurrent processes to recall/curtail non-firm transmission service after economic generation and \n \n73 PJM Answer at 31. \n74 See Paragould Light & Water Comm’n v. FERC, 144 F.4th 287, 292 (D.C. Cir. 2025) (“[W]e do not require \nFERC to allocate costs with exacting precision.” (internal quotation marks omitted)). \n75 PJM Answer at 56."},{"page":26,"startToken":8418,"endToken":8780,"text":"-26- \nbefore Pre-Emergency Load Management [because in] both instances, these entities transact in the \nPJM Energy Market without having secured any capacity.”76  For one thing, elsewhere PJM \ncontends that Eligible New Large Loads are served by LSEs that take firm Network Integration \nTransmission Service,77 so the suggestion that they take non-firm transmission service is \ninconsistent.  Further, the statement that Eligible New Large Loads have not “secured any \ncapacity” belies the fact that they have, nevertheless, paid for capacity, just without receiving the \nfull benefit. \nThird, PJM and some parties argue that curtailing New Large Loads before demand \nresponse is necessary to avoid demand response fatigue, which would “reduce available capacity \nto meet regional needs by deterring demand response registration.” 78  If PJM cannot rely on \ndemand response when system conditions are tight then, by definition, demand response is not \n“available capacity to meet regional needs.”79  To the extent demand response resources cannot \nperform the function for which they elected to provide under the terms for which they  were \nprocured, the solution is to reform the demand response program—e.g., through the development \nof a bounded demand response product and adjusted accreditation 80—rather than develop a \nconvoluted and illogical curtailment structure.   \n \n76 PJM Answer at 34. \n77 Transmittal at 94. \n78 Gov. Shapiro Answer at 5; see also Gov. Shapiro Answer at 24 (“Moreover, if called upon too frequently, \ndemand response resources will be less likely to register over time, reducing the capacity available to serve the region \nat a time when every resource that can be quickly brought online is needed.”); PJM Answer at 36 (“The more often a \nload center is asked to reduce consumption the more disruptive the provision of demand response and the greater the \nopportunity cost. The result is load centers become less willing to provide demand response and support Demand \nResources.”); New Jersey Board of Public Utilities (“NJBPU”) Comments at 5 (the IRAS curtailment scheme will \n“help maintain the participation of certain load management reduction resources, like DR, by minimizing ‘fatigue’ \nthat can occur from being over-called on during stress events.”). \n79 Gov. Shapiro Answer at 5. \n80 Google Protest at 19."},{"page":27,"startToken":8780,"endToken":9145,"text":"-27- \nFinally, it is also incorrect to suggest that curtailing demand response first would allow \nNew Large Loads to rely on demand response resources to provide capacity, which “would result \nin existing customers sharing the increased cost of calling on the demand response that is due to \nlarge load growth.”81  If existing loads were forced to pay for demand response capacity from \nwhich they derive no benefit, as parties suggest would happen under IRAS, this would violate \nbedrock cost causation principles, which require that costs be assigned in a manner that is roughly \nproportionate with benefits.82  To the extent load growth from New Large Loads leads to more \nreliance on demand response, cost causation and beneficiary pays principles require that those \nloads pay for their share of increased capacity costs. \nii. \nIRAS Will Not Incentivize New Large Loads to Bring New Capacity \nAs Google and others explained in their protests, one of the fundamental flaws of IRAS is \nthat different entities are imposing the obligation to bring new capacity (PJM) and determining \nwhich retail loads are interruptible if not (EDs).  That bifurcation creates regulatory uncertainty \nabout whether a load that brings new capacity will actually receive the firm service that it seeks.  \nThat regulatory uncertainty will, in practice, make it harder for companies like Google to sign the \nlong-term off-take agreements that are necessary to actually develop significant quantities of new \ncapacity and make PJM resource adequate again. \n PJM does not dispute that it lacks the authority to ensure that New Large Loads that bring \nnew capacity will, in fact, receive the firm service that they have spent billions of dollars to \nreceive.83  And while other parties claim that bringing new capacity will “materially decrease” \n \n81 Gov. Shapiro Answer at 24. \n82 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018).  \n83 See, e.g., Transmittal at 92.  Throughout this proceeding, PJM has consistently taken the position that it has \nno authority to order the curtailment of specific retail customers.  Nevertheless, PJM’s proposed tariff language could \nbe read to suggest that PJM can do just that.  See Proposed Tariff, attach. DD-4, section III (“Electric Distributors"},{"page":28,"startToken":9145,"endToken":9589,"text":"-28- \ntheir curtailment risk, that will not necessarily be the case.84  To see why, consider a hypothetical \nin which two new 50 MW loads—one offsetting its demand with new capacity and the other \nbringing no new capacity to the system—begin operating in an ED’s footprint.  PJM has no \nauthority to determine which 50 MW the ED drops when PJM calls for IRAS curtailments; the ED \nis free to curtail either load.  The fact that PJM’s aggregate curtailment instruction to the ED may \nbe lower if the new load brought its own capacity does not necessarily affect the ED’s likelihood \nof curtailing a specific retail customer.  For instance, the ED might be required to act pursuant to \na state policy to curtail certain end uses of loads over others, regardless of which end user brought \nits own capacity.  Or the ED might simply have a better relationship with one end user rather than \nanother.  In any event, it is not at all clear that a large load can actually decrease, much less \nmaterially decrease, its curtailment risk by bringing its own capacity. \nWe also disagree with the contention that “protestors’ arguments that IRAS will fail to \nincentivize new large loads to invest in new capacity . . . is contradicted by arguments that IRAS \nis too harsh and must be mitigated by a more generous transition period.”85  Google’s concern \nabout IRAS has never been that it is “too harsh.”  Google’s concern is that IRAS is illegal and will \nbe ineffectual.  Further, there is nothing inherently inconsistent in pointing out, as Google and \nother protestors have, that IRAS will fail to incentivize investments in new capacity.  On both \n \nshall: execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions \namong the Eligible New Large Loads in the Electric Distributor’s zone/area . . . .” (emphasis added)).  Given PJM’s \nrepresentations about the extent of its jurisdiction, Google believes that the proposed tariff language should not \nreasonably be read to allow PJM to order EDs to curtail specific retail loads or classes of re-tail loads.  If PJM takes \nthe opposite position, that would be inconsistent with both the FPA and PJM’s representations to the Commission. \n84 Gov. Shapiro Answer at 21-22 (“PJM proposes to identify the total MW quantity of load subject to IRAS in a \nzone or area based on new large loads that have not addressed their capacity needs within that zone/area, and to leave \nthe actual curtailment directions being made to end-use retail load to the Electric Distributer. As a result, individual \nlarge loads materially decrease their likelihood of being subject to curtailment by investing in new capacity.”). \n85 Id. at 21."},{"page":29,"startToken":9589,"endToken":9919,"text":"-29- \nissues, the point is that investors require regulatory certainty to make the billion-dollar investments \nin new capacity in PJM that are necessary to resolve its resource adequacy challenges.  New Large \nLoads coming to the region need certainty that bringing new capacity will mean that they receive \nfirm service, and IRAS does not provide that certainty.  There is nothing inconsistent in the idea \nthat PJM’s market rules must create an investable environment. \nB. The Current Tariff Is Unjust and Unreasonable \nAs for the second prong of the Western Resources framework, the record of this proceeding \npresents an ample basis to conclude that the status quo is unjust and unreasonable.86  Demand, \nlargely in the form of New Large Loads, is outpacing supply to such a degree that near-term \nreliability and resource adequacy are now very much in question.87  Although some New Large \nLoads in PJM, including Google’s, are making the investment necessary to procure sufficient new \ncapacity to cover their demand, that is the exception to the rule.  Instead, capacity market demand \ncan and likely will continue to exceed supply for the foreseeable future and yet there is no option \nin PJM’s tariff for LSEs to take interruptible service.  That means that the PJM tariff lacks a \nmechanism to interrupt service in an orderly fashion or before PJM enters emergency procedures \nnotwithstanding the inescapable fact that not all demand can be backed with firm capacity.  This \nsubjects otherwise firm customers to curtailment, degrading firm service.    \n In response to those circumstances, the Commission should find, now or following \nadditional process, that the tariff is unjust and unreasonable because it does not provide a pathway \nfor LSEs to take interruptible service similar to what is available in the natural gas transportation \n \n86 That does not, however, prevent the Commission from conducting a further proceeding to supplement the \nrecord.  W. Res., Inc. v. FERC, 9 F.3d 1568; 16 U.S.C. § 824e. \n87 Transmittal at 13; Gov. Shapiro Answer at 1."},{"page":30,"startToken":9919,"endToken":10264,"text":"-30- \ncontext.88  In the absence of such a pathway, there is pervasive uncertainty about how demand will \nbe curtailed to maintain reliability and real risk that entities will be curtailed without any option to \nmake investments or take other measures to avoid that result.89  An interruptible capacity service \nproduct, by contrast, would provide order and predictability by establishing when and under what \ncircumstances customers subject to the service would be interrupted while also allowing the \ncapacity market to clear under conditions where demand exceeds supply.  \nIn this sense, the Commission would build on its findings in the PJM Co-Location \nProceeding and the Large Load Show Cause Orders, which required and proposed to require, \nrespectively, that creation of an interim service in part to promote efficient allocation of \ntransmission capacity and “preserv[e] reliability for other . . .  customers.” 90  In so doing, the \nCommission would, in effect, extend that logic underlying its findings with respect to transmission \nservice to the capacity market, requiring the creation of a non-capacity backed interruptible \nservice.  In other words, whereas the PJM Co-Location Proceeding provided for interruptibility \nwhen there is inadequate transmission, this interruptible service would provide for interruptibility \nwhen there is inadequate capacity. \nFinally, while the Commission lacks authority over the rules governing whether and how \nLSEs sign up new retail customers, the creation of wholesale interruptible service would provide \na framework by which states and LSEs could implement their preferences regarding which retail \ncustomers get firm retail service and what steps they must take to qualify.  States, for example, \ncould condition firm retail service for customers above a certain MW threshold on those customers \n \n88 Duke Energy, 315 F.3d at 378-79 (distinguishing between firm and interruptible in the natural gas context). \n89 See Vistra Protest at 4; Dominion Comments at 4 (“LSEs should have an affirmative obligation to procure \nnew capacity to cover any new Large Loads they seek to interconnect and serve.”). \n90 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 201; see id. P 177; PJM Interconnection, L.L.C., 195 FERC \n¶ 61,211."},{"page":31,"startToken":10264,"endToken":10624,"text":"-31- \nbringing new capacity with those that do not being forced to take interruptible retail service backed \nonly by a new interruptible wholesale service.  In this way, requiring the creation of an interruptible \nwholesale service could give states the impetus to address the fundamental problem—large load \ngrowth that is outstripping supply—which IRAS was in theory supposed to solve, but in manner \nthat is legal and consistent with the FPA’s allocation of jurisdiction.    \nC. Replacement Rate \n \nGoogle strongly supports Commission action to adopt a legally durable path to ensuring \nresource adequacy in the face of load growth driven by New Large Loads.  As explained above, \ngiven the current—and likely continuing—imbalance between demand and supply in the PJM \ncapacity market, a just and reasonable replacement rate will need to incorporate some form of \ninterruptible service.  Below, Google presents a relatively surgical option for the Commission to \nset as a replacement rate, following the appropriate notice and opportunity for a hearing, that \naddresses the need for an interruptible service class while also achieving the goals underlying \nIRAS, but while doing so legally and without the investment-defeating uncertainty IRAS would \ncreate.91 The approach has two principal elements, which the Commission could make the basis \nfor further elaboration and development in a paper hearing.92 \n \nFirst, the Commission would require PJM to create an interruptible class of capacity market \nservice that, as discussed above, is similar to the analogous service available in the gas \ntransportation context under the NGA and builds upon the interim interruptible NITS product \n \n91 16 U.S.C. § 824e. \n92 Monongahela Power Co., 164 FERC ¶ 61,217.  Separately, Google supports the Commission creating \nsomething akin to the Large Load Registry proposed by PJM, which the Commission could do this either by accepting \nthe proposed Registry subject to a hearing on the appropriate data management and confidentiality guarantees, or by \nrejecting with guidance to PJM on the need to establish such guarantees.  The Commission has the authority to accept \nonly the Large Load Registry and sever and reject the rest of PJM’s filing.  See Transmittal at 10 (consenting to \nmodify/sever certain aspects of the IRAS proposal)."},{"page":32,"startToken":10624,"endToken":10936,"text":"-32- \nestablished in the PJM Co-Location Proceeding.93  The interruptible class of service would reflect \nthe fact that demand cannot exceed supply and, if necessary, something must give to prevent that \nresult and ensure system reliability.   Instead of using a blunt, haphazard, or, in the case of IRAS, \nillegal approach, an interruptible class of service enshrined in the PJM tariff would provide an \norderly means for equilibrating supply and demand and create the conditions for the regulatory \ncertainty needed to make long-term investments in new capacity.  In addition, the creation of an \ninterruptible class of service would also prevent the degradation of firm service by providing a tool \nto manage supply and demand without triggering emergency procedures and, if necessary, a \nmanual load dump.   \nAn interruptible service class would resolve several of the fundamental flaws in IRAS.  For \nexample, because the service class would be available to LSEs directly, there would be no need \nfor IRAS’s targeting of retail customer characteristics or, for that matter, any tethering to the retail \nmarket whatsoever.94  In addition, it would also address the price formation and retail ratemaking \nconcerns associated with IRAS’s proposal to remove load from the VRR curve, but nevertheless \ncharge and rebate capacity costs for customers that are subject to IRAS and ultimately curtailed.  \nBecause the service class is interruptible and, therefore, not backed by firm capacity, there would \nbe no need to include this load in the capacity market at all or provide compensation to retail \ncustomers when it is interrupted.  \nCritically, a federal interruptible service framework would also establish the necessary \nfoundation for BYONC to work in practice.  That is because any BYONC requirement could be \nenshrined in the state retail-level tariffs that by determining the rules and criteria by which retail \n \n93 PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 177, 201. \n94 Supra section II.A.1."},{"page":33,"startToken":10936,"endToken":11231,"text":"-33- \ncustomers are subject to receiving or potentially receiving interruptible service, (e.g., loads that \ndisplay defined electrical characteristics, are over a certain MW threshold, are of a certain vintage, \netc.).  The retail tariffs would also enumerate what steps those loads need to take to secure firm \nservice, such as by bringing their own new capacity and the requirements to qualify for having \ndone so (e.g., the required quantity, resource eligibility, accreditation, location, generation type, if \napplicable).  In the event those loads do not meet the state-level requirements for firm retail \nservice—e.g., because they did not secure sufficient capacity to cover their demand—their LSE \nwould procure interruptible capacity service for them.   \nIn addition, as part of the replacement rate, PJM would need to establish clear rules \ngoverning how state-designated interruptible loads are reflected in the relevant programs under its \njurisdiction, including capacity procurement requirements, capacity obligations, and transmission \nplanning.  Interruptible loads should be included in PJM’s gross load forecast and operating models \nbecause they will consume electricity under ordinary conditions and should thus be planned for \naccordingly.  A load’s verified interruptible capability, however, should be separately identified \nand reflected in the reliability analyses and procurement obligations applicable to that load.  PJM \nwould need to establish rules to avoid treating interruptible load as indistinguishable from firm \nload and double counting the interruptible capability.  These measures could be addressed in \nfurther process before the Commission under FPA section 206 or by PJM in the first instance on \ncompliance.  \nSecond, to provide near-term measures to address a potential supply shortfall, PJM would \nestablish a framework for curtailing large loads—including those with firm service95—prior to \n \n95 Those under interruptible load tariffs would already have been interrupted by the time emergency conditions \nset in."},{"page":34,"startToken":11231,"endToken":11571,"text":"-34- \nother retail customers during emergency conditions when PJM is approaching a broad Manual \nLoad Dump.  To create this framework, PJM would need to revise its emergency procedures to \ncreate a Priority Firm Large Load Reduction Action prior to Voltage Reduction and before Manual \nLoad Dump (a new Step 9A).96 \nThese “9A eligible loads” would be determined pursuant to the rules established in the \nretail tariff, with PJM seeing only the quantity of MWs to signal to each ED to reduce if Step 9A \nis reached.  Before each Delivery Year, EDs would report to PJM the aggregate quantity and \nlocation of firm large load subject to or that has volunteered for interruption at Step 9A, together \nwith its response time, minimum service level, telemetry, restoration requirements, and other \nrelevant operating characteristics.  PJM would incorporate this capability into its emergency \noperating plans but would not direct the curtailment of individual retail customers, which would \nbe executed by the ED itself.  When system conditions warrant and the applicable emergency step \nis reached, PJM would direct the relevant ED to reduce a specified aggregate quantity of registered \nfirm large load. The ED would then implement the instruction under its state-approved emergency \nload-shed plan. If the load reductions at 9A were insufficient to maintain system reliability, PJM \ncould then proceed to a Voltage Reduction Action (would become Step 9B), and if still insufficient, \na Manual Load Dump Action (Step 10). \nTogether, these two steps—creation of a wholesale interruptible service and the \nestablishment of a new Step 9A—would largely achieve the goals behind IRAS97—managing the \ncircumstances when demand exceeds supply while also creating the foundation for an incentive \n \n96 The Commission should also direct PJM to establish how these loads would be treated under other aspects of \nPJM’s tariff.  For example, loads included for curtailment at this new step 9A would continue to be treated as firm \nload for the purposes of capacity procurement, transmission planning, and ordinary system operations. \n97 See, e.g., Transmittal at 7; PJM Answer at 2-3."},{"page":35,"startToken":11571,"endToken":11814,"text":"-35- \nfor New Large Loads to bring their own new capacity—without violating the FPA or creating the \ninvestment-killing uncertainty inherent in IRAS.  In so doing, it would create a legally durable \nmeans of addressing the current resource adequacy situation in PJM without stymying the \ninvestment in new capacity that is the only way out of that situation.   \nIII. \nCONCLUSION \nDemand for capacity in PJM is exceeding supply, creating a significant resource adequacy \nshortfall.  Accepting IRAS would only worsen the situation.  Instead, the Commission should use \nthis proceeding as the jumping off point to create a new interruptible capacity service.  In so doing, \nthe Commission would put in place the conditions to manage the existing capacity shortfall while \nalso establishing the foundation for States to exercise their retail authority to impose a legally \ndurable BYONC obligation on New Large Loads should they choose to do so.  Accordingly, a new \ninterruptible service would provide a legally durable path to achieve the goals underlying IRAS \nwithout the self-defeating uncertainty that IRAS would create.   \n \n \nRespectfully submitted, \n \n/s/ Brian George \nBrian George \nSr. Lead, US Energy Markets  \nElizabeth Savage \nStrategic Negotiator \nGoogle LLC \n655 New York Ave., NW \nWashington, DC 20001 \n(202) 999-0990 \n \nbriangeorge@google.com  \neomsavage@google.com    \n \n \nMatt Christiansen \nSarah Greenberg \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \n \nmchristiansen@wsgr.com \nsgreenberg@wsgr.com    \nbshpall@wsgr.com \n \nCounsel for Google LLC \nDated:  September 30, 2026"},{"page":36,"startToken":11814,"endToken":11873,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated:  September 30, 2026 \nWashington, D.C. \n \n \n/s/ Bryan Shpall \nBryan Shpall \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":5,"endAt":1597,"startToken":0,"endToken":1628},{"p":5,"at":1597,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":6,"endAt":491,"startToken":1628,"endToken":1757},{"p":6,"at":491,"title":"II. ANSWER","method":"printed heading","endPage":9,"endAt":350,"startToken":1757,"endToken":2803},{"p":9,"at":350,"title":"A. The Record Confirms that PJM Has Not Satisfied Its FPA Section 205 Burden","method":"printed heading","endPage":29,"endAt":472,"startToken":2803,"endToken":9661},{"p":29,"at":472,"title":"B. The Current Tariff Is Unjust and Unreasonable","method":"printed heading","endPage":31,"endAt":479,"startToken":9661,"endToken":10338},{"p":31,"at":479,"title":"C. Replacement Rate","method":"printed heading","endPage":35,"endAt":362,"startToken":10338,"endToken":11629},{"p":35,"at":362,"title":"III. CONCLUSION","method":"printed heading","endPage":36,"endAt":0,"startToken":11629,"endToken":11814},{"p":36,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":36,"endAt":390,"startToken":11814,"endToken":11873}]}