{"document":{"slug":"rec-20261001-5356","title":"Motion for Leave to Answer and Answer of Data Center Coalition to the answer of PJM Interconnection, L.L.C. and certain other comments and answers re the…","issued":"2026-10-01","accession":"20261001-5356","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Data Center Coalition","kind":"answer","file":"sources/filings/text/20261001-5356_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261001-5356","tier":"record","sha256":"0d85887afe814cd6198a8a67bc2b5eb4513f38c21d62d5050e4c20fecfced065","pages":28,"tokens":9454,"emptyPages":[],"textThemes":["flex","retail","adequacy","registry"]},"pages":[{"page":1,"startToken":0,"endToken":423,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n) \nPJM Interconnection, L.L.C. \n ) \n Docket No. ER26-3515-000\n) \n \nMOTION FOR LEAVE TO ANSWER  \nAND ANSWER OF THE DATA CENTER COALITION \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 the Data Center Coalition (“DCC”)2 \nhereby moves for leave to answer3 and answers the answer of PJM Interconnection, L.L.C. \n(“PJM”)4 and certain other comments and answers filed by intervenors regarding PJM’s proposal \nto establish Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.5 \nI. \nANSWER \nAs DCC explained in detail in its Protest, DCC strongly supports reforms to ensure that \nlarge loads can be integrated into the grid while preserving reliability and protecting customers.  \n \n1 18 C.F.R. §§ 385.212 and 385.213. \n2 DCC is a membership organization of leading data center owners and operators.  Public testimony and \nwritten comments submitted by DCC do not necessarily reflect the views of each individual DCC member.  A list of \ncurrent DCC members is accessible at https://www.datacentercoalition.org/members. \n3 DCC acknowledges that the Commission’s Rules of Practice and Procedure do not typically allow answers \nto answers.  However, the Commission has accepted answers in the past when they have (i) assisted the Commission \nin understanding the issues presented, (ii) provided additional information for the Commission’s decision-making \nprocess, and (iii) helped ensure an accurate record.  See, e.g., PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P \n29 (2022); Canal Generating LLC, 181 FERC ¶ 61,157, at P 14 (2022); Equitrans, L.P., 134 FERC ¶ 61,250, at P 6 \n(2011); Cal. Indep. Sys. Operator Corp., 132 FERC ¶ 61,023, at P 16 (2010).  In this proceeding, DCC’s answer will \nhelp the Commission understand the issues presented by PJM and the other answers and comments filed in this \nproceeding and provide further information related to the issues in this proceeding to inform the Commission’s \ndecision-making process.  DCC therefore respectfully requests leave to file this answer and asks the Commission to \nconsider this answer in its deliberations in this proceeding. \n4 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of \nPJM Interconnection, L.L.C. (Sept. 23, 2026) (“PJM Answer”). \n5 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to \nEstablish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (Aug. 13, \n2026) (“Filing”)."},{"page":2,"startToken":423,"endToken":740,"text":"- 2 - \nAlong with the Virginia State Corporation Commission, DCC has called on states to develop \nmodel interruptible tariffs and load-reduction programs that would allow large loads to take \ninterruptible service.  DCC shares PJM’s commitment to ensuring that large load growth occurs in \na way that is compatible with reliability and does not result in cost shifts to other customers.  \n \nBut PJM’s proposal to impose a region-wide retail curtailment framework represents an \nunprecedented intrusion into the authority reserved to the states under the Federal Power Act \n(“FPA”) that must be rejected.  Facing strong opposition in this proceeding from a range of parties \nincluding state regulators, utilities, generation owners, and data center developers, PJM’s Answer \nattempts to recast IRAS as focused exclusively on the wholesale markets.  But the highly curated \nset of statements that PJM cites in support of this interpretation cannot overcome the \noverwhelming record evidence demonstrating that IRAS targets, and seeks to dictate, the rates, \nterms, and conditions of retail service.  PJM’s acknowledgment that IRAS requires enlisting \nElectric Distributors and state regulators to implement PJM’s directives highlights that IRAS \ntreads into areas that are beyond PJM’s and FERC’s jurisdiction.  IRAS would invert the regulatory \ndivide established by the FPA by imposing a federally approved retail curtailment framework \nwhere state authorities are charged with conforming their retail curtailment and compensation \npractices to align with PJM policy.   \nPJM continues to claim that states will be provided with complete discretion regarding how \nIRAS is implemented.  But states have no ability to opt in or opt out of IRAS.  PJM will issue \ndirectives to curtail New Large Load customers without regard to the preference of individual \nstates.  Failure to conform state policies to IRAS would risk subjecting all retail customers to \ninterruption when PJM issues curtailment directives—a consequence that is so severe as to leave \nstates with no option but to comply.  IRAS effectively conscripts state authorities into enforcing a"},{"page":3,"startToken":740,"endToken":1088,"text":"- 3 - \nfederal policy respecting matters that have been left to the exclusive judgment and oversight of the \nstates under the FPA. \nThe record in this proceeding demonstrates the risks of PJM’s top-down approach to retail \ncurtailment.  As commenters point out, IRAS fails to account for the reliability contributions of \nstate peak-shaving programs and similar measures that have been implemented by the states to \nencourage voluntary reductions by large load customers.6  Not only will this unduly discriminate \nagainst New Large Loads that have invested in technologies to reduce their loads, but the \ndisconnect between IRAS and state programs has the potential to subject Electric Distributors to \nconflicting regulatory obligations and uncertainty.7   \nPJM accuses DCC of taking contradictory positions by arguing for “rejection of IRAS on \none hand in favor of state jurisdiction but then bemoans that if states take different positions on \ncurtailment, it will not be clear that IRAS will deliver its intended reliability benefits.”8  But the \nreal contradiction lies within PJM’s defense of IRAS.  Because IRAS so clearly targets matters \nwithin the exclusive authority of the states, PJM has no choice but to argue that the states retain \ndiscretion over implementation of IRAS in an effort to justify its proposal.  Yet, its repeated \nassertions about state discretion, in turn, undercut PJM’s claims that IRAS can achieve its \nobjectives. \nWhile the jurisdictional defects in IRAS alone support rejection of PJM’s proposal, PJM \nalso has not demonstrated that IRAS is just, reasonable, and not unduly discriminatory or \n \n6 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of the Chief Energy Officer for the \nGovernor of Virginia at 2-5 (Sept. 3, 2026). \n7 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of the \nNew Jersey Board of Public Utilities at 4-5 (Sept. 18, 2026) (“[I]t is unclear whether EDCs will face penalties for not \ncurtailing the entire amount of the registered peak New Large Load amount directed by PJM, or if EDCs must curtail \nother customers in order to meet this IRAS obligation.”). \n8 PJM Answer at 28."},{"page":4,"startToken":1088,"endToken":1421,"text":"- 4 - \npreferential on its own terms.  PJM does not offer any response to many of the objections that have \nbeen expressed by DCC and other parties, and the responses that PJM does provide are largely \nconclusory and do not respond to the substance of commenters’ concerns.  For instance, DCC \ndemonstrated that the design of IRAS will result in customers in zones with New Large Loads \nsubsidizing rate reductions for other customers within the PJM footprint; yet, PJM’s Answer does \nnot acknowledge or address these concerns.9  PJM also does not offer any response to concerns \nraised by DCC and others that IRAS will undermine the settled expectations of New Large Loads \nthat have made investment decisions.10   \n PJM attempts to salvage IRAS by arguing that every aspect of its proposal is severable \nand inviting the Commission to rewrite the proposal to cure its defects.  PJM even goes so far as \nto ask the Commission to impose a stand-alone requirement that all load-serving entities (“LSE”) \nbring new capacity to serve New Large Loads.  Other parties ask the Commission to strike aspects \nof the IRAS framework that they argue go too far.  But even with PJM’s consent, the Commission \nhas no authority under FPA Section 205 to “go beyond approval or rejection of a proposal to \nadoption of an entirely different rate design.”11  And the Commission should decline PJM’s \ninvitation to do so here.  \nRather than approving a framework that conscripts state authorities into enforcing federal \ncurtailment policies, the Commission should reject the Filing and encourage PJM to work with \nstakeholders and the states to develop emergency procedures that accommodate—rather than \ndictate—the retail curtailment priorities of individual states.  Alternatively, if the Commission \n \n9 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion to Intervene and Protest of the Data \nCenter Coalition at 22-23 (Sept. 3, 2026) (“DCC Protest”). \n10 Id. at 30-34.   \n11 NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 115 (D.C. Cir. 2017) (internal quotations omitted) \n(“NRG”)."},{"page":5,"startToken":1421,"endToken":1752,"text":"- 5 - \nfinds that PJM’s existing emergency procedures have been rendered unjust and unreasonable, it \nshould initiate an FPA Section 206 proceeding to develop reforms that respect the jurisdictional \nboundaries established by the FPA.  At a minimum, if the Commission does not reject IRAS \noutright, it should direct PJM to establish a meaningful transition mechanism and delay \nimplementation until June 1, 2028 to provide New Large Loads and state authorities a reasonable \ntimeline to adapt.   \nA. \nPJM’s Justifications Cannot Cure The Jurisdictional Defects With IRAS \n1. \nIRAS Is Premised On An Overly Broad View Of FERC’s Jurisdiction \nThat Cannot Be Squared With The FPA \nPJM argues that the jurisdictional concerns expressed by DCC and numerous other parties \nin this proceeding are misplaced.  According to PJM, whether IRAS “‘targets’ retail or wholesale \ncustomers turns on the justification for the rule, not on whether or the extent to which the rule \naffects or even compels action of retail or wholesale customers.”12  PJM then offers a series of \njustifications that it claims eliminate any doubts about the legality of IRAS including that it will \n“support[] system reliability in the PJM region” and provide a new tool to address situations where \nsupply shortfalls jeopardize system reliability.13   \nIt is worth pausing for a moment on the breadth of authority that PJM seeks to claim for \nitself.  Under PJM’s theory, the extent to which IRAS “affects or even compels action of retail” \ncustomers is immaterial to the jurisdictional analysis.14  All that matters is whether PJM can \narticulate some way in which its proposal will support reliability or allow it to more effectively \nmanage its system when supply is tight.  But if the sole test for Commission jurisdiction is whether \na filing utility can articulate some nexus between the rule at issue and the reliability of the \n \n12 PJM Answer at 19-20 (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 265 (2016) (“EPSA”)). \n13 Id. at 21. \n14 Id. at 20 (emphasis added)."},{"page":6,"startToken":1752,"endToken":2018,"text":"- 6 - \ntransmission system, there is virtually no aspect of the production, delivery, or consumption of \nelectricity that would be beyond the reach of PJM and FERC.  PJM could, on the same logic, adopt \ntariff requirements that require utilities to construct new generation facilities to resolve supply \nshortfalls, impose mandatory energy efficiency standards on their retail customers, or require all \nretail customers to participate in a mandatory demand-response program of PJM’s design—each \ntime invoking the need to address supply shortfalls and manage transmission system reliability \nwhen the system is stressed.   \nBut no precedent supports PJM’s theory of FERC’s jurisdiction.  And even if the \njustifications offered by a filing utility were the sole benchmark for evaluating whether a proposal \nwas consistent with the jurisdictional boundaries established by the FPA, IRAS would not survive \nscrutiny.    \n2. \nPJM Misinterprets Applicable Precedent Defining The Respective \nResponsibilities Of FERC And The States \nPJM’s arguments that the Commission need only consider PJM’s justification for IRAS \nare based on an unduly narrow and selective reading of applicable court and Commission \nprecedent.  While PJM relies heavily on FERC v. EPSA, nothing in that case stands for the \nproposition that FERC may regulate any matter that has an impact on the reliability of wholesale \nmarkets.  To the contrary, the Court recognized that interpreting the FPA as providing FERC \nauthority to regulate any matter that affects wholesale markets would extend FERC’s power \nbeyond the scope of authority envisioned by Congress15 and that the FPA prohibited FERC from \napproving rules that target matters within the exclusive authority of the states “no matter how \n \n15 EPSA at 277-278."},{"page":7,"startToken":2018,"endToken":2347,"text":"- 7 - \ndirect, or dramatic, its impact on wholesale sales.”16  PJM’s interpretation of the scope of federal \nauthority cannot be squared with the Court’s reasoning. \n \nNor did the Court confine itself to examining the justifications offered by the agency when \nevaluating whether FERC’s actions exceeded the bounds established by Congress.  Although the \nCourt noted the justifications offered by FERC in support of Order No. 745, the Court assigned \nequal—if not more—weight to the fact that rules adopted by the Commission addressed only \n“transactions occurring on the wholesale market.”17  “[W]hatever the effects at the retail level, \nevery aspect of the regulatory plan happens exclusively on the wholesale market and governs \nexclusively that market’s rules.”18  As DCC explained in its Protest, this simply is not the case \nwith IRAS.19  \nPJM argues that the Commission’s recent decision to approve Tri-State’s High Impact \nLarge Load Tariff (“HILT”) demonstrates that the FPA does not prevent transmission providers \nfrom imposing obligations on utilities serving large loads merely because they “affect the quantity \nor terms of retail rate regulation.”20  But PJM’s reliance on Tri-State overlooks the Commission’s \nreason for approving the revised HILT proposal: it exclusively governed wholesale service to \nutility members without seeking to dictate the rates, terms, and conditions of retail service.21  The \nCommission was able to reach this conclusion with respect to Tri-State’s HILT proposal because \nits terms and conditions were entirely limited to wholesale sales (e.g., evaluation fees, resource \n \n16 Id. at 277-278 (“[I]f indirect or tangential impacts on wholesale electricity rates sufficed, FERC could \nregulate now in one industry, now in another, changing a vast array of rules and practices to implement its vision of \nreasonableness and justice.  We cannot imagine that was what Congress had in mind.”). \n17 Id. at 281. \n18 Id. \n19 DCC Protest at 8-15.  \n20 PJM Answer at 25-26 (quoting Tri-State Generation & Transmission Ass’n, Inc., 196 FERC ¶ 61,127 \n(2026) (“Tri-State”)). \n21 Id. at PP 66-68."},{"page":8,"startToken":2347,"endToken":2664,"text":"- 8 - \nstudies, deposit requirements, and associated agreements)22 and transmission service (e.g., \ntransmission cost allocation rules, reliability and transmission planning criteria) to Tri-State’s \nmembers.23  The Commission explained that Tri-State’s proposal thus did “not dictate the terms \nor conditions of retail service” but merely established pro forma terms for taking transmission \nservice and provisions related to wholesale sales to its full requirements customers.24  Nothing \nabout this arrangement, the Commission found, imposed requirements as to the retail arrangements \nTri-State’s members could enter into with their customers.25    \nUnlike HILT, IRAS is not limited to the terms and conditions of wholesale sales or \ntransmission planning.  To the contrary, IRAS seeks to prescribe resource procurement and \ncurtailment requirements for retail customers within the PJM region.  PJM’s proposed tariff \nrevisions direct Electric Distributors to curtail “Eligible New Large Loads,” establish a default rate \nfor compensating customers for these curtailments to be recovered “in its retail rates,”26 and direct \nElectric Distributors to recover the costs of these payments from other retail customers.  \nPJM also argues that the U.S. Court of Appeals for the Third Circuit’s decision in New \nJersey Board of Public Utilities v. FERC affirming the Commission’s elimination of the state-\nmandated exemption from the minimum offer price rule demonstrates that FERC has authority to \ntake steps to prevent the “state’s choices from adversely affecting wholesale capacity rates.”27  But \nthe rule at issue in NJ BPU is easily distinguishable from IRAS.  NJ BPU concerned the rules \ngoverning the submission of offers into the PJM capacity market.  As in EPSA, the actions under \n \n22 Id. at PP 12, 14.  \n23 Id. at PP 13, 16. \n24 Id. at P 67.  \n25 Id. at P 66.  \n26 Filing, Proposed Tariff, Att. DD-4 § X(a). \n27 PJM Answer at 27 (quoting N.J. Bd. of Pub. Util. v. FERC, 744 F.3d 74, 98 (3d Cir. 2014) (“NJ BPU”))."},{"page":9,"startToken":2664,"endToken":3016,"text":"- 9 - \nreview in NJ BPU exclusively governed the rules for participating in the wholesale markets.  IRAS, \nin contrast, invades state authority over retail rates by seeking to exercise control over the \ncurtailment of retail customers and even the credits and charges passed through retail customers’ \nbills.  Nothing in NJ BPU supports accepting IRAS.   \nIRAS bears a striking resemblance to the “far-fetched example” the Court in EPSA offered \nto illustrate the type of action that would unlawfully intrude on state authority—namely, a federally \nimposed requirement “compelling every consumer to buy a certain amount of electricity on the \nretail market.”28  IRAS effectively mandates that New Large Load customers procure sufficient \ncapacity to cover their demand consistent with PJM’s bring your own new capacity (“BYONC”) \nrequirements; if a customer does not, then PJM will issue instructions to Electric Distributors to \ncurtail service to customers to enforce PJM’s procurement mandate.  Although the growth of large \nloads has led PJM to propose frameworks that previously seemed far-fetched, the governing \njurisdictional principles remain the same: PJM and FERC cannot seek to regulate the rates, terms, \nand conditions of retail service.  And like the example provided by the Court in EPSA, IRAS \nexceeds the authority granted to FERC under the FPA.  \n3. \nPJM’s Statements And Tariff Language Support Rejection Of IRAS \nAs An Unlawful Intrusion On State Authority \nWhile PJM encourages the Commission to focus on the justifications offered by PJM, \nPJM’s statements confirm that IRAS explicitly targets the rates, terms, and conditions of retail \nservice.  Among other things, PJM’s statements make clear that IRAS establishes a policy that \nretail customers must bring their own capacity or face service interruptions,29 seeks to identify and \n \n28 EPSA at 280.  \n29 PJM Answer at 17 (“PJM intends to establish the policy that New Large Loads must bring new capacity \nor PJM may request that they reduce their energy consumption to alleviate emergency conditions.”).  See also id. at 3 \n(stating that absent compliance with PJM’s BYONC requirements, “New Large Loads must be flexible and, pursuant \nto PJM’s operational needs, reduce their energy demands when called upon during system emergencies”)."},{"page":10,"startToken":3016,"endToken":3443,"text":"- 10 - \ntarget retail customers that do not meet BYONC requirements for curtailment,30 establishes a \n“default” rate and framework for Electric Distributors to pay retail customers that are curtailed \nunder IRAS,31 and directs Electric Distributors to recover these costs from other retail customers \nthrough their retail rates.32  PJM also explains that IRAS is intended to ensure that states “re-\nevaluate” their retail curtailment practices and “enlists” states to implement PJM’s proposed \nframework.33   \nThe target of IRAS is readily apparent from PJM’s proposed tariff language as well.  \nAlthough PJM claims that IRAS does not dictate which customers will be curtailed, its tariff \nlanguage says otherwise.  For instance, proposed Attachment DD-4 states that Electric Distributors \n“shall execute . . . PJM’s directives to implement Interim Resource Adequacy Service Actions \namong Eligible New Large Loads in the Electric Distributor’s zone/area.”34  This language does \nnot provide Electric Distributors discretion regarding whether to curtail Eligible New Large Loads \nwithin their zone.  To the contrary, an Electric Distributor that curtailed retail customers other than \nEligible New Large Loads would be in direct violation of its obligations under the tariff. \nLikewise, PJM’s tariff language obligates Electric Distributors to implement a \ncompensation program that would provide Eligible New Large Loads with credits in their retail \n \n30 Filing, Transmittal Letter at 28 (stating that the Large Load Registry will be used to track Large Loads \nwithin the PJM region to monitor whether they are complying with requirements to bring new capacity or should be \nsubject to IRAS). \n31 Id. at 27 (explaining that Electric Distributors must “implement compensation program[s] consistent with” \nPJM tariff); id. at 102 (“PJM is proposing a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate”); \nid. (“[A] rate of zero dollars for IRAS would apply where Eligible New Large Loads waive in their retail rates receipt \nof compensation for the provision of wholesale Interim Resource Adequacy Service”); id. at 104 (“[T]he IRAS rate is \nintended to be conjoined with retail rates and ultimately paid to Eligible New Large Loads that reflects a discount on \ncapacity costs commensurate with the impact of Interim Resource Adequacy Service on addressing resource adequacy \nissues.”).  \n32 Id. at 104 (explaining that payments to retail customers curtailed under IRAS will be recovered from retail \nloads consistent with Electric Distributors’ state-approved programs).  \n33 Id. at 3, 107.  See also PJM Answer at 3 (stating that IRAS establishes a “region-wide response” to “guide \nand provide a framework for the PJM states’ various disparate approaches”).  \n34 Filing, Proposed Tariff, Att. DD-4 § III(a)."},{"page":11,"startToken":3443,"endToken":3783,"text":"- 11 - \nrates equal to 50% of the Non-Performance Charge Rate.35  Notably, while PJM characterizes its \ndefault rate as a cap that can be modified by state regulators, the only exception from this \nrequirement recognized in the tariff is if the Eligible New Large Load agrees to “accept in its retail \nrates” a sum lower than the default rate or “waive[s] receipt in its retail rates” of the default rate.36  \nAnd if state regulators do not take action to permit implementation of these requirements, PJM \nstates that Eligible New Large Loads may initiate state regulatory proceedings to enforce their \nrights to receive compensation.37 \nPJM’s arguments that states will retain full discretion regarding how IRAS is implemented \ncannot save IRAS.  IRAS exhibits none of the “solicitude towards the States” that the Court relied \nupon in upholding the program at issue in EPSA.38  As discussed above, the level of discretion that \nPJM claims IRAS affords to the states is simply not reflected in the tariff.  Nor do states have the \nability to “opt in” or “opt out” of IRAS.  If IRAS is approved, PJM will instruct Electric \nDistributors to curtail New Large Loads that have not complied with BYONC requirements \nregardless of the preferences of state authorities.  And state authorities will have little choice but \nto modify their policies to align with IRAS to avoid the risk that the brunt of PJM’s curtailments \nwill be borne by retail customers generally rather than the Eligible New Large Loads targeted by \nPJM.  \nUltimately, PJM’s arguments about the discretion of state regulators miss the point.  If the \ndecisions at issue—how retail customers are served, which retail customers are subject to \ncurtailment, under what terms, and at what rates—are properly within the states’ exclusive \n \n35 Id., Att. DD-4 § X(a). \n36 Id., Att. DD-4 § X(c)(ii).  \n37 Id., Transmittal Letter at 106-107 (“[I]f states decline to act, Eligible New Large Loads could initiate \nregulatory proceedings to develop retail pathways to recover wholesale IRAS rates.”).   \n38 EPSA at 287."},{"page":12,"startToken":3783,"endToken":4148,"text":"- 12 - \nauthority, then it is not PJM’s place to design the program that frames and compels those decisions \nin the first instance.  Delegating implementation to the states does not change the fact that PJM is \nseeking to establish procurement requirements for large load customers, define the conditions \nunder which curtailment is triggered, and prescribe a default compensation rate that is intended to \nbe embedded in retail rate structures.  These are retail policy and ratemaking choices and no \namount of state-level implementation discretion transforms them into wholesale ones.39  \nB. \nPJM Has Not Demonstrated That Curtailing Eligible New Large Loads Before \nRequiring Demand Resources To Perform Is Just, Reasonable, And \nConsistent With Cost Causation Requirements \n \nUnder IRAS, Eligible New Large Loads will be required to bear the costs of Demand \nResources cleared through PJM’s forward capacity market, but will not enjoy the benefits of this \ncapacity.  While Demand Resources are committed through the capacity market to “avoid periods \nof involuntar[y] firm load shed or blackouts,”40 PJM now proposes to curtail service to Network \nIntegration Transmission Service (“NITS”) customers serving Eligible New Large Loads prior to \nasking Demand Resources to fulfill their capacity commitments.  Yet, PJM continues to maintain \nthat it is just and reasonable to force Eligible New Large Loads to bear the costs of these capacity \ncommitments. \nPJM does not deny that IRAS will result in Eligible New Large Loads paying for Demand \nResources that will not be used to provide them with service.  Instead, PJM claims that this \ntreatment is justified because Eligible New Large Loads “failed to cover their capacity \n \n39 Notably, if the proposed payments under IRAS are wholesale rates, then states have no authority to assert \njurisdiction over them.  Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150, 163 (2016) (“FPA leaves no room \neither for direct state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve \nthe same result.”) (internal quotation and citations omitted).   \n40 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, \nand Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-\ndesign.pdf."},{"page":13,"startToken":4148,"endToken":4454,"text":"- 13 - \nobligations.”41  But that is a non-answer to the concerns expressed by DCC and other commenters \nthat PJM’s proposal will force customers “to pay for capacity without receiving commensurate \nreliability benefits.”42  Even if a New Large Load has not procured capacity that complies with \nPJM’s BYONC requirements, that does not change the fact that these loads will pay the cost of \ncapacity procured through the PJM markets.  And PJM has not demonstrated that it is just and \nreasonable to require Eligible New Large Loads to bear the cost of Demand Resources when these \ncustomers will be curtailed prior to when the Demand Resources they pay for have been deployed.  \nPJM also claims that calling on Demand Resources prior to curtailing Eligible New Large \nLoads would be inappropriate because it would reduce the incentive for such loads to meet \nBYONC requirements.43  But the fact that a proposed rate may incentivize a particular customer \nclass to take certain actions does not inherently render the rate as a whole just and reasonable.  \nIndeed, by PJM’s logic, it would also be appropriate to curtail Eligible New Large Loads before \nPJM takes any other action to maintain reliability or to prevent Eligible New Large Loads from \nreceiving service entirely since taking these actions would incentivize Eligible New Large Loads \nto meet BYONC requirements.  \nPJM further argues that its proposal to curtail Eligible New Large Loads before deploying \nDemand Resources is justified since it is consistent with its current approach to curtailing non-\nfirm transmission service after economic generation and before Pre-Emergency Load Management \nbecause both non-firm transmission customers and Eligible New Large Loads have transacted in \nthe PJM energy markets without having secured any capacity.44  But PJM’s comparison of Eligible \n \n41 PJM Answer at 33-34. \n42 DCC Protest at 17. \n43 PJM Answer at 34. \n44 Id."},{"page":14,"startToken":4454,"endToken":4755,"text":"- 14 - \nNew Large Loads to non-firm transmission customers overlooks that Eligible New Large Loads \nin fact pay for capacity while non-firm transmission customers do not.  As PJM’s Answer \nconcedes, “[t]hose entities that fail to arrange for BYONC will still be paying for capacity…”45 \nPJM’s entire basis for comparing the curtailment of non-firm transmission customers to Eligible \nNew Large Loads is thus unfounded.  \nPJM attempts to justify its approach by noting that customers that are curtailed under IRAS \nwill be eligible to receive compensation equal to 50% of the Non-Performance Charge Rate.  PJM \noverlooks, however, that Eligible New Large Loads will be eligible for compensation only during \nthe limited intervals each year when they are subject to curtailment under IRAS while they will be \nrequired to pay capacity charges reflecting the cost of Demand Resources every day during the \nDelivery Year even though these resources are not available to meet their load.46  PJM has not \nprovided any evidence demonstrating that providing a limited reimbursement in a subset of hours \nwill offset the costs borne by Eligible New Large Loads for capacity that they do not benefit from \nor otherwise result in these customers bearing costs that are roughly commensurate with the \nbenefits they receive.  PJM’s claim that the availability of compensation addresses any concerns \nrings particularly hollow given PJM’s repeated statements that this compensation may be reduced \nto zero.47  \nPJM also attempts to justify its proposal by introducing the concept of “Demand Resource \nfatigue.”48 PJM explains that the more often that Demand Resources are called upon, the more \n \n45 Id. at 53.  \n46 Id. at 55-56. \n47 Id. at 55 (acknowledging that “the IRAS compensation rate may be reduced, even to 0%, by the states \nand/or appropriate RERRAs at the retail level.”). \n48 Id. at 36-37."},{"page":15,"startToken":4755,"endToken":5124,"text":"- 15 - \nlikely it is that Demand Resources will become unwilling to provide Demand Response.49  As a \nresult, PJM indicates that although “Demand Resources are paid the same daily rate as other \nCapacity Resources,” it cannot call upon Demand Resources to perform in the same way it does \nother Capacity Resources.50  PJM thus contends that it is appropriate not to call upon Demand \nResources until after it has curtailed retail loads.  \nPJM’s concession that it is paying Demand Resources as Capacity Resources yet cannot \nexpect such resources to perform as Capacity Resources and thus will instead curtail retail loads \nis alarming.  “All supply-side capacity resources, including Demand Resources, are required to \nmeet the Capacity Performance requirements.”51  Demand Resources have been paid over $1.5 \nbillion over the past two Base Residual Auctions alone on the basis that they can meet these \nrequirements and maintain the reliability of the PJM system for the benefit of load.52  If PJM \nbelieves that it cannot rely on Demand Resources to consistently perform when called upon for \nthe benefit of load that pays for their performance, it should take actions to reform its tariff to \nreflect that it cannot rely on these resources in the same way it does other Capacity Resources.  But \nPJM should not be permitted to excuse Demand Resources from providing the capacity that \ncustomers have paid them for and instead curtail retail customers.53   \n \n49 Id. at 36. \n50 Id.  \n51 PJM Interconnection, L.L.C., 169 FERC ¶ 61,252, at P 2 (2019).  \n52 See PJM 2028/2029 Base Residual Auction Report at 2-3, 5, 12 (July 14, 2026), available at: \nhttps://www.pjm.com/markets-and-operations/rpm.aspx (showing 7,641 MW of Demand Response clearing at \n$333.44/MW-day for 2027/2028 Delivery Year and 7,364 MW of Demand Response clearing at $325.00/MW-day \nfor 2028/2029 Delivery Year). \n53 PJM’s purported concern about Demand Resource fatigue stands in stark contrast to recent efforts by PJM \nto expand the availability requirements imposed on Demand Resources to ensure that they are available when needed \nto maintain system reliability.  PJM Interconnection, L.L.C., 191 FERC ¶ 61,103 (2025) (expanding availability \nwindows for Demand Resources)."},{"page":16,"startToken":5124,"endToken":5442,"text":"- 16 - \nFinally, PJM attempts to bolster its decision to curtail retail customers before calling upon \nDemand Resources by highlighting statements from states that purportedly attest to “the benefits \nand purpose of calling for IRAS prior to Pre-Emergency Load Management.”54  The statements \nthat PJM cites, however, are limited to restatements of PJM’s assertions or claims that deploying \nDemand Resources prior to curtailing Eligible New Large Loads would shift costs to other \ncustomers and result in the curtailment of non-IRAS eligible load.55  But deploying Demand \nResources that have voluntarily assumed a capacity obligation and agreed to curtail in exchange \nfor capacity revenues is not shifting reliability burdens or costs onto other customers.  It is merely \nrequiring that Capacity Resources paid for their performance in times of system stress in fact \nperform.  Requiring Capacity Resources to perform the service for which they are compensated is \nnot an inappropriate cost shift and will not harm other customers. \nC. \nPJM Has Not Demonstrated That Its Proposal Is Not Unduly Discriminatory \nOr Preferential  \n \n1. \nPJM Has Not Justified The Disparate Treatment Of NITS Customers \nServing Eligible New Large Loads   \nPJM does not deny that NITS customers serving Eligible New Large Loads will receive \ninferior service to other NITS customers.  Yet, PJM continues to argue that any difference in \ntreatment is justified because these customers are large,56 drive “novel degrees of load growth,”57 \nor have not brought their own new capacity.58  But the FPA’s prohibition on undue discrimination \nis not satisfied solely by the utility identifying some differences between customer classes.  As \nDCC explained in its Protest, PJM has the burden to demonstrate that there are identifiable factual \n \n54 PJM Answer at 31-33.   \n55 Id.    \n56 Id. at 58-59. \n57 Id. at 60 (quoting PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Answer of Pennsylvania \nGovernor Josh Shapiro at 18 (Sept. 15, 2026) (“Governor Shapiro Answer”)).  \n58 Id. at 61."},{"page":17,"startToken":5442,"endToken":5770,"text":"- 17 - \ndifferences between the customers that justify the specific rates, terms, and conditions imposed by \nthe utility that are “material to the inquiry at hand.”59  While PJM offers generalities about the \npurported differences between Eligible New Large Loads and other customers, PJM never \ndemonstrates how these differences justify the specific disparities in treatment that PJM has \nproposed in its Filing.  \nNone of the factual differences identified by PJM justify the discriminatory treatment that \nwould be afforded to NITS customers serving Eligible New Large Loads under IRAS.  PJM argues \nthat Eligible New Large Loads are not similarly situated to other customers because of their size.60  \nBut 100 MW of load has the same effect on resource adequacy regardless of whether these MWs \ncome from a single New Large Load or an aggregation of smaller retail customers.  Yet, only NITS \ncustomers serving New Large Loads will be required to meet PJM’s BYONC requirements to \nreceive the same level of service that PJM will provide to other NITS customers as a matter of \ncourse.  \nPJM asserts that these differences in treatment are appropriate because a NITS customer \nserving an Eligible New Large Load has not supported its load with new capacity meeting PJM’s \nBYONC requirements.61  But PJM does not require other NITS customers to demonstrate that they \nhave offset any load growth with new capacity to obtain access to firm service.  Indeed, there is \nno assurance that other NITS customers have fully covered any load growth within their service \nterritories with new capacity.  As a result, a NITS customer that has experienced 100 MW of load \ngrowth on its system from smaller industrial and commercial customers will not see any reduction \nin the quality of transmission service provided even if it has not secured new capacity to meet this \n \n59 DCC Protest at 27 (quoting N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018)). \n60 PJM Answer at 58-59. \n61 Id. at 61."},{"page":18,"startToken":5770,"endToken":6111,"text":"- 18 - \ndemand.  Rather than justifying its proposal, PJM’s reference to the BYONC requirements only \nhighlights the unduly discriminatory treatment that New Large Loads will receive under PJM’s \nproposal.   \nPJM attempts to defend its disparate treatment of large loads that come online after the \nJune 1, 2027 cutoff on the grounds that “[n]ew, not existing load, is the reason for the shortfall, \nwhich drives the need for IRAS” and that providing comparable treatment “would fail to account \nfor causation.”62  But PJM has not demonstrated that New Large Loads are in fact causing PJM’s \ncapacity shortfall.  The demand from New Large Loads contributes to PJM’s capacity shortfall \njust as much as the demand from existing loads.  Moreover, PJM’s attempt to identify New Large \nLoads as the sole cause of its capacity shortfall overlooks that there are multiple factors that have \ncontributed to PJM’s capacity shortage, including PJM’s broken generator interconnection process \nand the premature retirement of generation resources.63 \nNor can PJM justify its proposal by making general references to the “uniqueness of large \nloads.”64  While PJM cites the Commission’s approval of Southwest Power Pool, Inc.’s \nConditional High Impact Large Load Service (“CHILLS”) in support of its proposal, the \nCommission’s order in that case did not find that any difference in treatment is justified merely \nbecause of the size and characteristics of large loads.65  To the contrary, the Commission examined \nCHILLS to ensure that it treated large loads comparably to other customers and that any \ndifferences were tailored to reflect the nature of the service and characteristics of the customers at \n \n62 Id. \n63 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, \nand \nStimulating \nInvestment \nTo \nSupport \nDurable \nReliability \nat \n18 \n(May \n6, \n2026), \nhttps://www.pjm.com//media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-\nthrough-marketdesign.pdf (acknowledging that “PJM’s generation interconnection queue could be viewed as a once-\nbinding constraint.”).  \n64 PJM Answer at 49. \n65 Id. at 59 (citing Sw. Power Pool, Inc., 195 FERC ¶ 61,196, at PP 84-85, 87 (2026))."},{"page":19,"startToken":6111,"endToken":6478,"text":"- 19 - \nissue.66  PJM’s assumption that the characteristics of large loads inherently justify less favorable \ntreatment is unsupported by case law and inconsistent with the FPA.  \nPJM also implies that because IRAS is “limited and narrowly tailored” to address instances \nof capacity shortfall in the PJM region, it is somehow not unduly discriminatory.67  But the FPA \ndoes not provide an exception for undue discrimination that is narrowly tailored.  Its prohibition \non undue discrimination is absolute.68  The fact that PJM’s IRAS proposal is time-limited and \nintended to address capacity constraints says nothing about whether it is unduly discriminatory or \npreferential.  \n2. \nPJM’s Refusal To Credit New Large Loads For Their Demand \nReduction Is Unduly Discriminatory And Preferential \n \nThe IRAS proposal is similarly unduly discriminatory with respect to PJM’s refusal to \nacknowledge that New Large Loads may offset their demand through mechanisms other than \nCapacity Resources.  Under IRAS, New Large Loads can avoid being subject to IRAS curtailment \nprocedures by meeting BYONC requirements through arranging new Capacity Resources that \noffset their demand.69  The Capacity Resources that a New Large Load may rely on to offset its \ndemand include Demand Resources since “capacity may also be supplied by demand-side \nresources.”70  Yet despite its recognition that reductions in demand can appropriately be considered \ncapacity, PJM has refused to allow a New Large Load to reduce its exposure to IRAS by \n \n66 Sw. Power Pool, Inc., 195 FERC ¶ 61,196, at PP 84-85, 87. \n67 PJM Answer at 60.  \n68 16 U.S.C. § 824d(b) (stating that “no public utility shall make or grant any undue preference or advantage” \nor “subject any person to any undue prejudice or disadvantage”) (emphasis added).  In contrast to the FPA, Congress \nprovided certain exceptions to FERC’s ability to regulate undue discrimination under the Natural Gas Act (“NGA”). \nSee Dominion Cove Point LNG, LP, 164 FERC ¶ 61,107, at P 22 (2018) (finding that NGA section 4 grants broad \nauthority to regulate undue discrimination by natural gas companies, while section 3(e)(4) applies only to \ndiscrimination in terms of service at LNG terminals, emphasizing Congress’s intentional distinction between the two \nsections). \n69 Filing, Transmittal Letter at 51.  \n70 Id. at 54."},{"page":20,"startToken":6478,"endToken":6867,"text":"- 20 - \nparticipating in peak shaving programs and similar mechanisms.71 \nPJM has not justified its proposal to withhold crediting demand reductions under the Peak \nShaving Adjustment or other load reduction mechanisms.  PJM’s Peak Shaving Adjustment is \ndefined as “a load forecast mechanism that allows load reductions by end-use customers” to result \nin downward zonal load adjustment.72  PJM has proposed to include information pertaining to  \nPeak Shaving Adjustments in its Large Load Registry because such adjustments “inform PJM \noperators of Large Loads that are managing their resource needs through peak shaving adjustments \nunder a state program.”73  Yet despite PJM’s acknowledgment that Peak Shaving Adjustments can \nreduce a load’s demand to meet its capacity needs, it is refusing to allow New Large Loads to \noffset their demand and meet BYONC requirements with Peak Shaving Adjustments or other load \nreduction mechanisms.74  In short, PJM is subjecting competing demand reduction approaches to \ndisparate treatment “for no good reason.”75 \nIn its Answer, PJM defends its proposal to exclude Peak Shaving Adjustments from \nreducing New Large Loads’ demand on the grounds that unlike other Capacity Resources, Peak \nShaving Adjustments are not a real-time dispatchable product.76  But PJM does not explain why it \nis relevant that a reduction in a New Large Load’s demand be in the form of dispatchable \ncapacity.77  If a New Large Load will be reducing its demand in a manner recognized by the PJM \n \n71 See e.g., PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Protest, Request for Clarification and \nComments of Equinix Inc. at 14-17 (Sept. 3, 2026) (“Equinix Protest”); PJM Interconnection, L.L.C., Docket No. \nER26-3515-000, Comments and Limited Protest of the NRG Companies at 7-10 (Sept. 3, 2026); PJM Interconnection, \nL.L.C., Docket No. ER26-3515-000, Comments of the Chief Energy Officer for the Governor of Virginia at 2-4 (Sept. \n3, 2026). \n72 PJM Reliability Assurance Agreement, Art. 1 – Definitions (Peak Shaving Adjustment). \n73 Filing, Transmittal Letter at 41.  \n74 PJM Answer at 48.  \n75 Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265, 282 (D.C. Cir. 2022); State Corp. Comm’n of Kan. \nv. FERC, 876 F.3d 332, 335 (D.C. Cir. 2017). \n76 PJM Answer at 48. \n77 See Pub. Serv. Co. of Ind. v. FERC, 575 F.2d 1204, 1212 (7th Cir. 1978)."},{"page":21,"startToken":6867,"endToken":7214,"text":"- 21 - \ntariff—as Peak Shaving Adjustments are78—then the amount of capacity needed to serve such load \nwill also be reduced and the purpose behind PJM’s BYONC requirements—i.e., “to offset the \ncapacity need presented by the New Large Load”79—will be fulfilled.  The fact that the reduction \nin a New Large Load’s demand is not dispatchable is irrelevant.  This is particularly true given \nthat, as the Corporate Energy Buyers Association observes, demand reduction under a Peak \nShaving Adjustment occurs “before any real-time IRAS Action ever occurs.”80  \nAt a time when the PJM region “need[s] every megawatt [it] can get,”81 it should be \nincentivizing large loads to take any actions they can to reduce their demand.  Yet PJM’s limits on \nthe types of demand reductions that can reduce a customer’s exposure to IRAS will undermine the \nincentive for New Large Loads to invest in these capabilities and result in unduly discriminatory \ntreatment of customers that have taken steps to manage their demand in accordance with state \nprograms or otherwise.    \nD. \nPJM Has Not Demonstrated That Excluding Eligible New Large Loads From \nThe VRR Curve Is Just And Reasonable  \n \nPJM has proposed to exclude New Large Loads that do not meet BYONC requirements \nfrom the Variable Resource Requirement curve (“VRR Curve”) beginning with the 2029/2030 \nDelivery Year on the grounds that these loads should not impact the capacity prices paid by other \ncustomers.82  But if the VRR Curve does not reflect the total actual demand in the PJM market—\nas would be the case under PJM’s proposal—it cannot “produce accurate market signals that will \n \n78 PJM Tariff, Att. DD-2. \n79 Filing, Transmittal Letter at 51.  \n80 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Motion for Leave to Answer and Answer of \nCorporate Energy Buyers Association at 4 (Sept. 28, 2026).  \n81 Laila Kearney, America’s largest power grid is struggling to meet demand from AI, Reuters (July 9, 2025), \navailable \nat: \nhttps://www.reuters.com/sustainability/boards-policy-regulation/americas-largest-power-grid-is-\nstruggling-meet-demand-ai-2025-07-09/? (quoting PJM spokesman Jeffrey Shields).  \n82 Filing, Transmittal Letter at 23."},{"page":22,"startToken":7214,"endToken":7569,"text":"- 22 - \nencourage appropriate capacity investment and achieve an adequate level of reliability.”83  The \nVRR Curve and PJM capacity markets will thus instead send a suppressed price signal that is \ndisconnected from the actual level of demand in the PJM market and insufficient to drive needed \ninvestment in new capacity resources.  PJM’s Answer fails to address this flaw.    \nPJM instead defends the exclusion of New Large Loads that have not entered into BYONC \narrangements from the VRR Curve on the grounds that it expects New Large Loads to bring their \nown new generation resources to meet demand—which it characterizes as an action that would \noccur outside the capacity market.84  But PJM’s expectation that New Large Loads will bring their \nown new generation to market to match their demand does not address the underlying market \ndesign flaw in PJM’s proposal.  While many New Large Loads, including New Large Loads \ndeveloped by DCC members, will indeed be bringing a significant amount of new generation \ncapacity to the PJM market, not all new large load growth within the region may be matched by \nnew generation capacity.  It is thus important that the VRR Curve reflect the incremental new \ndemand in the PJM region so that—as PJM initially recognized until being overridden by its \nBoard85—PJM’s capacity markets send the price signals that appropriately incentivize investment \nin new resources.  PJM’s proposal to pretend as if the demand from New Large Loads does not \nexist will result in capacity prices that are disconnected from the realities of the market and fail to \nprovide the incentives needed to help pull PJM out of its current resource adequacy situation.  \nPJM also argues that excluding Eligible New Large Loads from the VRR Curve is \nwarranted because they have elected not to receive capacity service and are comparable to energy-\n \n83 PJM Interconnection, L.L.C., 167 FERC ¶ 61,029, at P 19 (2019). \n84 PJM Answer at 51.  \n85 PJM CIFP – RBP / Connect and Manage - Stage 3 (May 27, 2026 – Meeting Materials), Connect and \nManage PJM Package at 29 (May 27, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp."},{"page":23,"startToken":7569,"endToken":7904,"text":"- 23 - \nonly resources.86  But the analogy fails.  Energy-only resources are excluded from the capacity \nsupply curve because they do not offer capacity into the market.  Eligible New Large Loads, by \ncontrast, are NITS customers that pay the same transmission and capacity charges as all other firm \ncustomers. They are not opting out of capacity-backed service—they are being involuntarily \nexcluded from the VRR Curve by PJM while remaining obligated to pay for capacity that, under \nIRAS, will not be deployed to serve them.   \nE. \nPJM’s One-Mile Rule Is Not Just and Reasonable \nPJM proposes treating “all affiliated facilities within a one-mile radius” as “a single electric \nsite” for determining which loads are “Large Loads” and could be subject to IRAS.87  PJM asserts \nthat this one-mile rule is necessary to deter large loads from circumventing its IRAS rules by siting \na number of smaller loads with peak loads under 50 MW in the vicinity of each other.88  DCC \nagrees with its members and other commenters in this proceeding: PJM has not shown this \ncomponent of its proposal is just and reasonable.89 \nFirst, the one-mile rule would subject facilities that have operated for decades to IRAS and \npotential curtailment simply because a separately developed facility is sited nearby.90  PJM’s anti-\n \n86 PJM Answer at 53.  \n87 Filing, Proposed Reliability Assurance Agreement, Art. 1 (Definition of “Large Load”). \n88 Filing, Transmittal Letter at 33. \n89 See Equinix Protest at 2, 12-14; PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of \nCyrusOne, L.P. at 4-6 (Sept. 11, 2026) (“CyrusOne Comments”). \n90 See Equinix Protest at 13 (explaining PJM’s proposal “would retroactively aggregate loads that were \nseparately developed, separately studied, and separately contracted for service”); CyrusOne Comments at 4 (stating \nPJM’s proposed language “could potentially cause an existing, already-operational facility to become newly subject \nto IRAS curtailment risk solely because a later, unrelated facility happens to be developed nearby, even though the \nexisting facility’s capacity needs were accounted for and arranged years earlier”)."},{"page":24,"startToken":7904,"endToken":8348,"text":"- 24 - \ngaming rationale does not justify this treatment.91  Legacy loads predate IRAS and have already \nbeen planned for through the regional planning process.92 \nSecond, PJM’s use of “affiliated” is unclear.  PJM does not define “affiliated,” identify \nwhose affiliation matters, or explain how it will make that determination,93 deferring the “method \nof calculating the one-mile distance and for examining different configurations” to the Manuals.94  \nFor example, it is unclear whether facilities on a third-party-developed data center campus are \n“affiliated” merely because they share a developer, even where the end-use customers have no \nownership or control relationship and may have separate service arrangements, distinct points of \ninterconnection, independent development histories, or electrical and operational independence.95  \nIt is also unclear whether PJM’s use of “affiliation” would result in large loads being considered \nat the same site based on shared upstream institutional investors or financing parties.   \nThese issues should not be deferred to the PJM Manuals.  Whether facilities are “affiliated” \ndetermines whether they constitute a Large Load and, in turn, whether they may be required to \narrange new capacity or face curtailment under IRAS.  This is precisely the type of term that \nbelongs in the tariff as it “affect[s] rates and service significantly,” is “realistically susceptible of \n \n91 See Filing, Transmittal Letter at 34 (“The one-mile radius requirement is intended to avoid a scenario \nwhere, for example, a data center owner is not categorized as Large Load simply because the owner has elected to site \na number of smaller data centers, each with peak loads below 50 MW, close together.”); id. (“Similarly, the reference \nto a single ‘electrical’ site is similarly intended to avoid a scenario where data centers and other Large Loads avoid \nthe 50 MW threshold by configuring themselves into smaller loads.”). \n92 See Equinix Protest at 13. \n93 See, e.g., PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of Old Dominion Electric \nCooperative at 8 (Sept. 3, 2026) (“PJM’s filing does not provide how affiliation will be determined for purposes of \nthe one-mile radius measurement.”); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Protest of the \nIndependent Market Monitor of PJM at 30 (Sept. 3, 2026) (“PJM does not provide any details regarding the \nimplementation of the one-mile radius rule”). \n94 Filing, Transmittal Letter at 34. \n95 See Equinix Protest at 3 (stating facilities should be able to argue they are not “affiliated” based on “factors \nsuch as separate service arrangements, points of interconnection, ownership and control, development history, or \nelectrical and operational independence”); id. at 14 (similar); CyrusOne Comments at 4 (stating facilities should not \nbe aggregated when they are not “commercially, contractually, or electrically independent”)."},{"page":25,"startToken":8348,"endToken":8829,"text":"- 25 - \nspecification,” and is not “so generally understood in any contractual arrangement as to render \nrecitation superfluous.”96 \nF. \nThe Commission Cannot Sever Components Of IRAS As PJM And Others \nHave Proposed \n \nSeveral parties—including PJM itself—make recommendations that the Commission sever \nor reframe elements of PJM’s proposal in an attempt to improve its legal posture.97  But the \nCommission’s authority to direct modifications to PJM’s filing under Section 205 of the FPA is \nlimited, even with PJM’s consent.  While the Commission may accept a proposed rate with “minor \ndeviations” when the filing utility consents,98 any change that “impose[s] a new rate scheme” or \nfollows “‘a completely different strategy’ than, or is ‘methodologically distinct’ from, the \nproposed rate” exceeds the Commission’s authority regardless of consent.99  This limitation exists \nbecause customers must receive “adequate notice of the proposed changes” and “an adequate \nopportunity to comment on the proposed changes.”100 \nMany of the recommendations made by PJM and other parties to sever and reformulate \nPJM’s Filing go far beyond the minor modifications permitted under Section 205 of the FPA.  For \n \n96 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985). \n97 See, e.g., PJM Answer at 6-7 (requesting timely approval of only “discrete elements” of the IRAS \nproposal); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of Dominion Energy Services, Inc. \nat 6 (Sept. 3, 2026) (requesting revisions to the IRAS BYONC provisions because “PJM’s proposed framework, \nhowever, moves needlessly from federal wholesale jurisdiction into retail jurisdiction and is likely to cause confusion \nand potential legal challenges”); Governor Shapiro Answer at 14-15 (“reformulat[ing]” compensation mechanism \nbecause “PJM confusingly appears to be speaking about compensation that would be provided to individual retail \ncustomers”); PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Comments of the Pennsylvania Public Utility \nCommission at 5-7 (Sept. 3, 2026) (“Pennsylvania PUC Comments”) (proposing changes to address the fact that “[a]s \nwritten, the language of PJM’s tariff does not contemplate application of state regulatory authority to either prohibit \nor determine NLL curtailment compensation as necessary to regulate recovery through retail rates”).  See also PJM \nInterconnection, L.L.C., Docket No. ER26-3515-000, Supportive Comments and Limited Protest of the New Jersey \nBoard of Public Utilities at 13 (Sept. 3, 2026) (recommending severance of the IRAS compensation mechanism \nbecause “PJM’s compensation structure is ambiguous, unclear, and unnecessary”). \n98 See NRG at 115 (quoting Western Resources Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993)). \n99 Id. (quoting Western Resources Inc., 9 F.3d at 1578-79). \n100 Id. at 116-117. See also City of Winnfield v. FERC, 744 F.2d 871, 876 (D.C. Cir. 1984) (“Section 205 \nauthorizes the Commission to ‘make . . . orders’ only ‘after full hearings,’ and that requirement unquestionably \nimposes the duty to give adequate notice of the subject to which the orders pertain.”)."},{"page":26,"startToken":8829,"endToken":9231,"text":"- 26 - \nexample, PJM suggests that the Commission approve only its proposed Large Load Registry, the \ndefinition of “Large Load,” and proposed RAA Section 7.8.101  But PJM materially \nmischaracterizes what Section 7.8 requires. PJM repeatedly describes Section 7.8 as requiring \nLSEs to “bring new capacity in an amount that equals or exceeds its New Large Loads’ peak \nload.”102  But the proposed tariff language does not say that.  It provides that an LSE serving a \nNew Large Load must bring new capacity “or such New Large Load may be subject to load \nreduction requests during Emergencies prior to Pre-Emergency Load Management Response.”103  \nSection 7.8 thus gives LSEs and the New Large Loads they serve a choice to either (1) bring new \ncapacity, or (2) accept the possibility of curtailment under IRAS.  It does not prohibit New Large \nLoads from interconnecting in the PJM region unless they bring new capacity.  Converting that \nchoice into a mandatory new-capacity requirement would impose a fundamentally different tariff \ndesign than PJM filed and is not permitted under Section 205 of the FPA.  \nGovernor Shapiro’s and the Pennsylvania Public Utility Commission’s recommendations \nsuffer the same defect.  Governor Shapiro proposes that the Commission modify proposed \nAttachment DD-4 terms related to compensating Eligible New Large Loads by removing \nreferences to “Eligible New Large Loads” and adding language specifying that state compensation \nprovisions apply.104  The Pennsylvania Public Utility Commission makes a similar \n \n101 PJM Answer at 7. \n102 See Id. at 7 and n.20 (“The revisions to the RAA clarify an LSE’s obligation to bring new capacity in an \namount that equals or exceeds its New Large Loads’ peak load or be subject to load reduction requests during \nEmergencies prior to Pre-Emergency Load Management Response”) (citing Proposed Reliability Assurance \nAgreement § 7.8); id. at 16 (“Based on the filings in this proceeding, there is widespread support for the notion that \nall LSEs in PJM serving New Large Loads via Network Integration Transmission Service … must bring new capacity \nto satisfy the resource adequacy needs of such New Large Load.”); id. at 62 (“The resource adequacy needs of New \nLarge Loads will be met through new capacity.  PJM proposed new RAA, section 7.8 to memorialize this policy as \nan obligation on all LSEs, including the LSEs within FRR Entities’ service territories.”). \n103 Filing, Proposed Reliability Assurance Agreement § 7.8.  \n104 Governor Shapiro Answer at 15."},{"page":27,"startToken":9231,"endToken":9402,"text":"- 27 - \nrecommendation.105  But under PJM’s Filing, the New Large Load itself elects whether to waive \nor accept reduced compensation.106  Making the changes recommended by Governor Shapiro and \nthe Pennsylvania Public Utility Commission would result in an entirely different rate scheme than \nthe one proposed by PJM and would exceed the Commission’s authority under Section 205 of the \nFPA.  \nII. \nCONCLUSION \nFor the reasons set forth above, DCC respectfully requests that the Commission issue an \norder consistent with its filings in this proceeding. \n \nRespectfully submitted, \n \n \n \n/s/ Stephen J. Hug \nMorgan A. Sipple \nDirector, Energy Policy – FERC and RTOs \nDATA CENTER COALITION \n1250 H Street, N.W. \nWashington, D.C.  20005 \nmorgan@datacentercoalition.org  \n \nData Center Coalition \nStephen J. Hug \nBen N. Reiter \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \nTel: (202) 887-4000 \nshug@akingump.com \nbreiter@akingump.com \n \n \n \n \n \nDated: October 1, 2026 \n \n \nCounsel for the Data Center Coalition \n \n105 Pennsylvania PUC Comments at 6-7. \n106 Filing, Proposed Tariff, Att. DD-4 § X(a)."},{"page":28,"startToken":9402,"endToken":9454,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served a copy of the foregoing document on the persons \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Washington, D.C., this 1st day of October, 2026. \n/s/ Stephen J. Hug \n \n \n \nStephen J. Hug"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":665,"startToken":0,"endToken":103},{"p":1,"at":665,"title":"I. ANSWER","method":"printed heading","endPage":5,"endAt":498,"startToken":103,"endToken":1495},{"p":5,"at":498,"title":"A. PJM’s Justifications Cannot Cure The Jurisdictional Defects With IRAS","method":"printed heading","endPage":12,"endAt":591,"startToken":1495,"endToken":3871},{"p":12,"at":591,"title":"B. PJM Has Not Demonstrated That Curtailing Eligible New Large Loads Before","method":"printed heading","endPage":16,"endAt":1036,"startToken":3871,"endToken":5279},{"p":16,"at":1036,"title":"C. PJM Has Not Demonstrated That Its Proposal Is Not Unduly Discriminatory","method":"printed heading","endPage":21,"endAt":1062,"startToken":5279,"endToken":7041},{"p":21,"at":1062,"title":"D. PJM Has Not Demonstrated That Excluding Eligible New Large Loads From","method":"printed heading","endPage":23,"endAt":532,"startToken":7041,"endToken":7653},{"p":23,"at":532,"title":"E. PJM’s One-Mile Rule Is Not Just and Reasonable","method":"printed heading","endPage":25,"endAt":133,"startToken":7653,"endToken":8366},{"p":25,"at":133,"title":"F. The Commission Cannot Sever Components Of IRAS As PJM And Others","method":"printed heading","endPage":27,"endAt":395,"startToken":8366,"endToken":9291},{"p":27,"at":395,"title":"II. CONCLUSION","method":"printed heading","endPage":28,"endAt":0,"startToken":9291,"endToken":9402},{"p":28,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":28,"endAt":306,"startToken":9402,"endToken":9454}]}