{"document":{"slug":"rec-20261002-5153","title":"Motion for Leave to Answer and Limited Answer of FirstEnergy Service Company to PJM Interconnection, L.L.C.’s 09/23/2026 Answer re Interim Resource Adequacy…","issued":"2026-10-02","accession":"20261002-5153","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"FirstEnergy Service Company","kind":"answer","file":"sources/filings/text/20261002-5153_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261002-5153","tier":"record","sha256":"c032561e30f191f8b3ce7f56d4809b31b349cf5dad69a77d361ff10a71a76caf","pages":7,"tokens":1663,"emptyPages":[],"textThemes":["flex"]},"pages":[{"page":1,"startToken":0,"endToken":308,"text":"UNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.\n)\nDocket No. ER26-3515-000\nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF FIRSTENERGY \nSERVICE COMPANY \nPursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, \nFirstEnergy Service Company, on behalf of its affiliates (“FirstEnergy”), respectfully moves for \nleave to answer and submits this limited answer to PJM Interconnection, L.L.C.’s September 23, \n2026 Answer (“PJM Answer”) to various comments and protests addressing PJM’s Interim \nResource Adequacy Service filing (“IRAS Filing”).  Although Rule 213(a)(2) generally prohibits \nanswers to protests and answers to answers, the Commission accepts otherwise-prohibited answers \nthat clarify the record or assist its decision-making.1  Good cause exists here because PJM leaves \nmaterial arguments in FirstEnergy’s Limited Protest and Comments (“FirstEnergy Protest and \nComments”) unanswered and advances no compelling new law or facts that defeat FirstEnergy’s \nremaining objections.  As the filing entity, PJM bears the burden under section 205 of the Federal \nPower Act.2  Its assertion that silence should not be treated as acceptance3 does not satisfy that \n1 18 C.F.R. §§ 385.212, 385.213 (2025); see Baltimore Gas & Electric Co. v. Columbia \nGas Transmission, LLC, 193 FERC ¶ 61,036, at P 34 & n.28 (2025) (accepting answers to \nanswers because they provided information that assisted the Commission’s decision-making). \n2 16 U.S.C. § 824d(a)-(b); Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, \n1035 (D.C. Cir. 2022); NorthWestern Corp. v. FERC, 884 F.3d 1176, 1182–83 (D.C. Cir. 2018); \nMidcontinent Independent System Operator, Inc., 194 FERC ¶ 61,050, at P 23 (2026). \n3 PJM Answer at 8 n.23 (“While PJM’s answer does not address every argument raised \nby intervenors, silence on any argument should not be deemed as acceptance of the arguments \nraised.”)."},{"page":2,"startToken":308,"endToken":597,"text":"2 \nburden.  The Commission, therefore, should grant the relief requested in the FirstEnergy Protest \nand Comments. \nI. \nLIMITED ANSWER \nA. \nPJM Fails to Respond to Issues Raised by FirstEnergy That Are Material to \nthe Justness and Reasonableness of PJM’s IRAS Filing. \nPJM fails to address a number of issues raised by FirstEnergy in its Protest and Comments.  \nMost notably, PJM does not address FirstEnergy’s argument that its IRAS proposal improperly \ndenies certain new large loads and associated generation access to the Fixed Resource Requirement \n(“FRR”) Alternative.  As FirstEnergy explained, PJM’s proposal would permit new data-center \nload and associated generation within an existing FRR Service Area to remain outside the \nReliability Pricing Model (“RPM”), while requiring Bring Your Own New Capacity (“BYONC”) \nresources associated with new loads outside an existing FRR Service Area to participate in RPM. \nFirstEnergy explained that Schedule 8.1, section B of the Reliability Assurance Agreement \n(“RAA”) permits an eligible Load Serving Entity (“LSE”) to demonstrate that “all or part” of its \nload falls within the RAA’s FRR Service Area definition and is supported by sufficient Capacity \nResources.  FirstEnergy, accordingly, argued that the “all or part” language contemplates use of \nthe FRR Alternative for less than all of an eligible LSE’s load and that PJM has not justified \ndenying new load and associated generation outside an existing FRR Service Area a comparable \nopportunity to use the FRR Alternative.4  PJM addresses other FRR issues but not FirstEnergy’s \nargument.  PJM, therefore, has not rebutted FirstEnergy’s showing or carried its section 205 burden \nto justify the different treatment of new load and associated generation inside and outside existing \nFRR Service Areas. \n4 FirstEnergy Protest at 6-7 & n.19 (citing PJM Reliability Assurance Agreement, \nSchedule 8.1, section B)."},{"page":3,"startToken":597,"endToken":896,"text":"3 \nPJM also does not squarely address several other FirstEnergy objections.  PJM explains \ngenerally why IRAS distinguishes between new and existing load, but does not explain how its \nJune 1, 2027 in-service date protects existing commercial arrangements or agreements nearing \ncompletion when the IRAS Proposal was filed.  PJM likewise explains why existing Capacity \nResources should not qualify as BYONC, but does not address FirstEnergy’s distinct argument \nthat an Energy Resource, which is not presently a Capacity Resource, should be eligible to qualify \nas new capacity for purposes of BYONC.  Nor does PJM substantively address FirstEnergy’s \nobjection to terminating IRAS after three consecutive years of sufficient capacity, even though \nsubsequent large-load additions could recreate the shortfall.  PJM likewise fails to rebut \nFirstEnergy’s objection that the annual reallocation of IRAS curtailment obligations could unduly \nfavor a new large load by reducing its obligation solely because unrelated generation enters or \nother load exits the region, even though the load itself has not brought capacity.  PJM further offers \nno response to FirstEnergy’s objection to crediting a load with Reliability Backstop Procurement \n(“RBP”) capacity when that load was not included in the forecast supporting the procurement.5\nFinally, although PJM separately clarifies that the capacity and Registry-reporting \nobligations fall on LSEs and that Electric Distributors receive load-reduction directives, it does \nnot address FirstEnergy’s broader request that the proposed provisions consistently identify the \nentity responsible for each IRAS requirement.6  Clear assignment of those responsibilities is \nessential to effective planning, implementation, compliance, and enforcement. \nB. \nWhere PJM Does Respond to FirstEnergy, Its Arguments Are Unconvincing \n5 FirstEnergy Protest at 7-9 (transition and existing commercial arrangements), 13-14 \n(Energy Resources), 14-15 (termination of IRAS), 15-16 (allocation of RBP capacity), 16-17 \n(reallocation of curtailment obligations). \n6 FirstEnergy Protest at 12-13; see also PJM Answer at 13, 17-18, 26-30."},{"page":4,"startToken":896,"endToken":1208,"text":"4 \nFirst, PJM claims that requiring BYONC resources to participate in RPM for ten years \nensures that the capacity is “real and lasting.” 7   That rationale may support requiring an \nenforceable, durable capacity commitment, but it does not demonstrate that mandatory RPM \nparticipation for ten consecutive Delivery Years is reasonably tailored to that objective.  PJM does \nnot adequately explain why continued capacity availability could not be secured through the \ncommercial arrangement supporting the resource or another enforceable commitment tied to the \nassociated load.  PJM, therefore, has not established that the specific ten-year RPM participation \nrequirement is just and reasonable under section 205. \nSecond, PJM’s response does not cure the jurisdictional defect identified by FirstEnergy. \nPJM characterizes the payment as compensation to an LSE for a wholesale load-reduction service \nand establishes a default rate equal to 50 percent of the Non-Performance Charge Rate.  Yet PJM \npermits state and retail regulatory authorities to reduce that purportedly wholesale rate, including \nto zero, and to determine which entities receive the compensation and which retail customers fund \nit.8  That substantial state control over the amount and allocation of the payment reinforces, rather \nthan resolves, FirstEnergy’s objection that the proposed mechanism concerns retail rates and \nservice.  Nor does characterizing the LSE as the initial recipient change the fact that the PJM tariff \ncreates a compensation framework based on curtailment that will ultimately be implemented at the \nretail level.  PJM’s reliance on FERC v. Electric Power Supply Association and Tri-State \nGeneration and Transmission Association, Inc. does not defeat that objection.9  As PJM describes \n7 PJM Answer at 43 & n.161; see also FirstEnergy Protest at 5-6, 15. \n8 PJM Answer at 54-58; see also FirstEnergy Protest at 3-5. \n9 PJM Answer at 19-30, 54-58 (citing FERC v. Electric Power Supply Ass’n, 577 U.S. \n260 (2016), and Tri-State Generation & Transmission Association, Inc., 196 FERC ¶ 61,127 \n(2026))."},{"page":5,"startToken":1208,"endToken":1482,"text":"5 \nit, Tri-State emphasized that the jurisdictional utility’s members retained discretion whether to \nflow the relevant terms through to their retail contracts.  Here, by contrast, the PJM tariff itself \nwould establish a default compensation mechanism based on load reductions that will ultimately \nbe implemented at the retail level.  PJM’s cited authorities therefore do not establish that the \nchallenged compensation mechanism falls within FERC’s jurisdiction. \nThird, PJM does not adequately justify applying the proposed Large Load definition to \nmanufacturing and other industrial facilities.  Although PJM asserts that FirstEnergy identified no \nbasis for treating those facilities differently from data centers, it does not address FirstEnergy’s \nexplanation that, unlike data centers, short-notice curtailment of manufacturing facilities may \ndisrupt production and supply chains, strand inventory, damage equipment, and require costly \ncleaning and restart procedures.  Those differences bear directly on whether subjecting both \ncategories of load to the same IRAS obligations is just, reasonable, and not unduly discriminatory. \nPJM, therefore, should be required to address those differences and justify the proposed treatment \nof manufacturing and other industrial facilities before subjecting them to the same IRAS \nrequirements as data centers.10\nFinally, PJM’s assertion that it does not presently perceive a connection between the Large \nLoad Registry and the forthcoming pro forma transmission-service agreement does not \ndemonstrate that finalizing the Registry now will avoid overlapping, inconsistent, or duplicative \nrequirements.11\nFirstEnergy does not dispute that large-load growth presents resource-adequacy concerns \nrequiring action.  But the need for some action does not establish that each component of PJM’s \n10 FirstEnergy Protest at 10–11; PJM Answer at 14–16. \n11 PJM Answer at 14 n.47; see also FirstEnergy Protest at 11-12."},{"page":6,"startToken":1482,"endToken":1587,"text":"6 \nproposal satisfies section 205.  PJM leaves material FirstEnergy arguments unrebutted and, as to \nthe arguments it addresses, advances no compelling new law or facts that defeat FirstEnergy’s \nspecific objections. \nII.  \nCONCLUSION\nFor these reasons, FirstEnergy respectfully requests that the Commission accept this \nlimited Answer, grant the relief requested in the FirstEnergy Protest and Comments, and direct \nPJM to correct the identified deficiencies through a compliance filing. \nRespectfully submitted,  \n/s/___Evan K. Dean_____________  \nMorgan Parke  \nVice President - Associate General Counsel  \nEvan K. Dean  \nManaging Counsel  \nFirstEnergy Service Company  \n341 White Pond Drive  \nAkron, Ohio 44320  \n(330) 942-2519  \nedean@firstenergycorp.com\nCounsel for FirstEnergy Service Company"},{"page":7,"startToken":1587,"endToken":1663,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have served the foregoing document upon all parties listed on the \nofficial service list for the captioned proceeding in accordance with Rule 2010 of the \nCommission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \nDated at Washington, D.C., this 2nd day of October, 2026. \n/s/ Daniel Klein \nDaniel Klein  \nDavis Wright Tremaine LLP  \n1301 K Street NW \nSuite 500 East \nWashington, D.C. 20005"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":116,"startToken":0,"endToken":324},{"p":2,"at":116,"title":"I. LIMITED ANSWER","method":"printed heading","endPage":2,"endAt":136,"startToken":324,"endToken":327},{"p":2,"at":136,"title":"A. PJM Fails to Respond to Issues Raised by FirstEnergy That Are Material to","method":"printed heading","endPage":3,"endAt":1791,"startToken":327,"endToken":845},{"p":3,"at":1791,"title":"B. Where PJM Does Respond to FirstEnergy, Its Arguments Are Unconvincing","method":"printed heading","endPage":6,"endAt":218,"startToken":845,"endToken":1512},{"p":6,"at":218,"title":"II. CONCLUSION","method":"printed heading","endPage":7,"endAt":0,"startToken":1512,"endToken":1587},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":447,"startToken":1587,"endToken":1663}]}