{"document":{"slug":"rec-20261006-5150","title":"Motion for Leave to Answer and Limited Answer of PPL Electric Utilities Corporation to the 09/23/2026 Answer et al. of PJM Interconnection, L.L.C","issued":"2026-10-06","accession":"20261006-5150","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"PPL Electric Utilities Corporation","kind":"answer","file":"sources/filings/text/20261006-5150_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261006-5150","tier":"record","sha256":"5ab03a19a2edd28ccbb2fb72a413b1dc58e00cbe4e0e09bca9a17d901d9ca42b","pages":9,"tokens":2617,"emptyPages":[],"textThemes":["retail","flex"]},"pages":[{"page":1,"startToken":0,"endToken":268,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n) \n) \n) \nDocket No. ER26-3515-000 \n \n \n \nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF  \nPPL ELECTRIC UTILITIES CORPORATION  \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure,1 PPL Electric Utilities Corporation (“PPL \nElectric”) submits this Motion for Leave to Answer and Limited Answer (“Limited Answer”) \nto the September 23, 2026 Motion for Leave to Answer and Answer of PJM Interconnection, \nL.L.C. (“PJM”) in the above-captioned proceeding.2   \nPPL Electric reiterates its appreciation for the effort that PJM, its staff, management, \nand Board have put into the proposed Interim Resource Adequacy Service (“IRAS”) \nFramework, and submits this Limited Answer solely to highlight an important clarification \nregarding the IRAS Filing3 that PJM provided on page 29 of its September 23 Answer.  \nSpecifically, PJM now clarifies in the record that under its proposal, state regulatory \nauthorities4 have the power to ‘opt-out’ individual Eligible New Large Loads from the \nrequirement to provide IRAS to PJM under the PJM Tariff by granting those Eligible New \n \n1 18 C.F.R. §§ 385.212, 385.213. \n2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C., \nDocket No. ER26-3515-000 (Sept. 23, 2026) (“September 23 Answer”). \n3 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service & Large Load \nRegistry, Docket No. ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”).  \n4 As used in this filing, “state regulatory authorities” includes Relevant Electric Retail Regulatory Authorities \n(“RERRAs”), which can include local regulatory authorities."},{"page":2,"startToken":268,"endToken":701,"text":"2 \n \nLarge Loads the ability to “say no” under state law.5  This fact was not at all clear in PJM’s \ninitial proposal and implementing tariff language, but if true: (i) raises significant policy \nconcerns regarding undue discrimination and cost shifting in the application of IRAS across \nthe PJM Region; and (ii) deepens PPL Electric’s initial concerns regarding the proposal’s legal \nfoundation under the Federal Power Act (“FPA”).   \nPPL Electric respectfully requests that PJM quickly clarify this point in the record, and \nthat the Commission address it directly in its eventual order, given its importance to the policy \nand legal underpinnings of this proceeding. \nI. \nMOTION FOR LEAVE TO ANSWER \nWhile an answer to an answer or protest is not a matter of right under the Commission’s \nregulations,6 the Commission routinely permits such answers when the answer provides useful \nand relevant information that will assist the Commission in its decision-making process,7 \ncorrects factual inaccuracies and clarifies the issues,8 provides information helpful to the \n \n5 September 23 Answer at 29 (“Third, the IRAS framework does not determine whether any specific retail \ncustomers can say no. Just as the identity of the retail customers who are ultimately implicated by PJM’s directives \nto reduce a MW quantity of load is not decided by PJM, under the IRAS framework, it is also not up to PJM to \ndetermine whether, as PPL puts it, retail customers can say no. That—and the regulation of the terms and \nconditions of retail rates, and the regulation of retail customers—remains within the exclusive jurisdiction of the \nstates.”). \n6 18 C.F.R. § 385.213(a)(2).  \n7 See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co. and Midwest Indep. Transmission Sys. Op., \nInc., 140 FERC ¶ 61,057, at P 94 (2012); Sw. Power Pool, Inc., 131 FERC ¶ 61,252, at P 19 (2010), reh’g \ndenied, 137 FERC ¶ 61,075 (2011) (accepting answers that “provided information that assisted us in our \ndecision-making process”); Duke Energy Ky., Inc., 122 FERC ¶ 61,182, at P 25 (2008) (accepting answers to a \nprotest that “provided information that assisted us in our decision-making process”); Tallgrass Transmission, \nLLC, 125 FERC ¶ 61,248, at P 26 (2008), reh’g denied, 150 FERC ¶ 61,224 (2015); PJM Interconnection, \nL.L.C., 120 FERC ¶ 61,083, at P 23 (2007) (answer to protests permitted when it provides information to assist \nthe Commission in its decision-making process); Entergy Servs. Inc., 126 FERC ¶ 61,227, at P. 76 (2009).  \n8 See, e.g., PJM Interconnection, L.L.C., 84 FERC ¶ 61,224, at 62,078 (1998)."},{"page":3,"startToken":701,"endToken":1029,"text":"3 \n \ndisposition of an issue,9 or permits the issues to be narrowed.10  This Limited Answer will \nassist the Commission in its decision-making process, clarifies the issues, and provides \ninformation helpful to the disposition of an issue.  Accordingly, PPL Electric respectfully \nrequests that the Commission grant leave and accept this Limited Answer.  \nII. \nLIMITED ANSWER \nIn its September 3 Protest, PPL Electric explained that because of how the applicable \ntariff language was written, if accepted without modification the IRAS Filing would mark the \nfirst time in history that the Commission would be requiring the mandatory and involuntary \ndesignation of end-use retail customers (Eligible New Large Loads) to provide a FERC-\njurisdictional wholesale rate service (IRAS), and the compulsory provision of that FERC-\njurisdictional wholesale rate service to a Regional Transmission Organization (“RTO”) \npursuant to FERC-approved rates, terms, and conditions in a FERC-approved tariff.11  PPL \nElectric explained at length that, while PJM correctly defers to the applicable Electric \nDistributor and state regulatory authorities in determining which specific individual Eligible \nNew Large Loads within a given zone should actually provide IRAS when called upon, the \nfact remains that all Eligible New Large Loads (end-use, retail customers) within a zone are \nassigned responsibility by PJM to provide this wholesale rate service, pursuant to FERC-\njurisdictional rates, terms, and conditions, and must provide this wholesale rate service to PJM \nwhen called upon.  As PPL Electric put it, “[t]he issue is not about which entity gets to identify \nthe specific individual Eligible New Large Loads that must provide IRAS when PJM calls for \n \n9 See, e.g., CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287, n.11 (1999).  \n10 See, e.g., New Energy Ventures, Inc. v. S. Cal. Edison Co., 82 FERC ¶ 61,335, at 62,323, n.1 (1998). \n11 PJM Interconnection, L.L.C., Motion to Intervene, Protest, and Request for Clarification of PPL Electric \nUtilities Corporation at 2 (Sept. 3, 2026) (“September 3 Protest”)."},{"page":4,"startToken":1029,"endToken":1407,"text":"4 \n \nit,” but rather “[t]he issue is that, when called upon to provide IRAS under that process, the \nEligible New Large Load cannot say no[,] [i]t must, pursuant to a FERC-approved Tariff, \nprovide IRAS as a FERC-jurisdictional wholesale rate service to PJM.”12   \nIn its September 23 Answer, PJM made a critical clarification in response to PPL \nElectric’s jurisdictional concerns on page 29: \nPPL argues, to no avail, that “[t]he issue is not about which \nentity gets to identify the specific individual Eligible New Large \nLoads that must provide IRAS when PJM calls for it. The issue \nis that, when called upon to provide IRAS under that process, \nthe Eligible New Large Load cannot say no.”  First, the issue of \njurisdiction is about which entity gets to identify the retail \ncustomers who ultimately respond to PJM’s directives to reduce \nload. PJM’s answer is straightforward—the states and/or \nRERRAs, in coordination with Electric Distributors and their \nLSEs and retail customers served by those LSEs ultimately \nidentify those retail customers. Second, PJM has, in fact, been \ncontinuously consulting and communicating with states and \nother stakeholders on the design of IRAS for over a year.  Third, \nthe IRAS framework does not determine whether any specific \nretail customers can say no. Just as the identity of the retail \ncustomers who are ultimately implicated by PJM’s directives \nto reduce a MW quantity of load is not decided by PJM, under \nthe IRAS framework, it is also not up to PJM to determine \nwhether, as PPL puts it, retail customers can say no. That—\nand the regulation of the terms and conditions of retail rates, \nand the regulation of retail customers—remains within the \nexclusive jurisdiction of the states. As noted previously, PJM’s \nload reduction directives will be informed by the degree to \nwhich load in a certain zone/area’s IRAS responsibility has been \nreduced through MW of BYONC or Allocated RBP UCAP MW. \nHowever, PJM will direct load reduction directives to Electric \nDistributors, while states/RERRAs may determine which retail \ncustomers will implement the load reduction directives.   \n \n \nThe concept that state regulatory authorities have the power to ‘opt-out’ individual \nEligible New Large Loads from the requirement to provide IRAS to PJM under the PJM Tariff \n \n12 Id. at 10."},{"page":5,"startToken":1407,"endToken":1696,"text":"5 \n \nby granting those Eligible New Large Loads the ability to “say no” under retail service terms \nand conditions is not at all clear from PJM’s proposed tariff language, but if true is critically \nsignificant.   \nUnfortunately, if this is indeed the intent of the IRAS Filing, PPL Electric’s policy and \njurisdictional concerns have only deepened.  First, with respect to PPL Electric’s policy \nconcerns, the implications of PJM’s clarification in its September 23 Answer are striking.  If \nstate regulatory authorities can exempt Eligible New Large Loads from IRAS curtailment \nobligations simply by permitting them to “say no” under state law or regulation, then there is \na real risk of disparate treatment and cost shifting in the application of IRAS within the PJM \nRegion.  Specifically, if Eligible New Large Loads may ‘opt-out’ through localized \narrangements with state regulatory authorities to limit (or even eliminate entirely) their \nindividual IRAS exposure, the benefits of BYONC in reducing an Eligible New Large Loads’ \nindividual IRAS curtailment exposure are, by definition, undermined.  More importantly, the \nability for state regulatory authorities to use that authority to remove the exposure of an Eligible \nNew Large Load to IRAS curtailment creates the potential for the shifting of cost and reliability \nburdens onto other parts of the PJM Region that do not grant such protection.  This is a recipe \nfor undue discrimination in the implementation of IRAS, and constitutes the exact outcome \nthat PJM is trying to avoid.   \nSecond, with respect to PPL Electric’s jurisdictional concerns, PJM’s clarification in \nits September 23 Answer creates significant ambiguity regarding the legal foundation for IRAS \nunder the FPA.  As PPL Electric noted in its September 3 Protest, IRAS is:  \n1. a FERC-jurisdictional wholesale rate service;  \n2. established under the FERC-jurisdictional PJM Tariff;"},{"page":6,"startToken":1696,"endToken":2038,"text":"6 \n \n3. provided by a FERC-defined class of providers (Eligible New Large Loads); and \n4. compensated pursuant to FERC-jurisdictional rates specified in the PJM Tariff.   \nIf the purpose of PJM’s clarification above is to emphasize that, notwithstanding all of these \nfederal characteristics of IRAS, Eligible New Large Loads are not compelled under federal law \nto provide this FERC-jurisdictional wholesale service but instead are only compelled to do so \nif the applicable state regulatory authority forces them to, this simply reorients PPL Electric’s \noriginal jurisdictional concern.  Specifically, it is unclear under what legal authority state \nregulatory authorities in the PJM Region would be able to compel end-use retail customers \n(Eligible New Large Loads) to provide a FERC-jurisdictional wholesale rate service to PJM.  \nState utility law generally focuses on the entities providing a service to end-use retail \ncustomers, such as distribution utilities, and even then, the service being regulated is one \nestablished under state law itself.  To the extent that PJM is imagining that a state would \nsomehow use its regulatory authority to directly force end-use retail customers to provide this \nFERC-jurisdictional wholesale rate service to PJM, it would be an unprecedented use of state \nauthority and raise bizarre issues of federalism.  This is especially true in light of the fact that \nthe Commission’s jurisdiction under FPA section 201 is “plenary” and extends “to all \nwholesale sales in interstate commerce except those which Congress has made explicitly \nsubject to regulation by the States.”13  The FPA does not grant states the ability to compel the \nprovision of FERC-jurisdictional wholesale rate services.  To the contrary, “[t]he FPA leaves \nno room either for direct state regulation of the prices of interstate wholesales or for regulation \nthat would indirectly achieve the same result.”14  \n \n13 F.P.C. v. S. Cal Edison Co., 376 U.S. 205, 216 (1964). \n14 Fed. Energy Regulatory Comm’n v. Elec. Power Supply Ass’n, 577 U.S. 260, 287 (2016) [hereinafter FERC v. \nEPSA] (citing N. Natural Gas Co. v. State Corp. Comm’n of Kan., 372 U.S. 84, 91 (1963))."},{"page":7,"startToken":2038,"endToken":2337,"text":"7 \n \n \nPPL Electric appreciates the fine line that PJM is attempting to walk under FPA section \n20115 in this proceeding.  But given the importance of establishing a sound legal basis for \nCommission approval of IRAS, PJM must fully explain and support the actual intent and \njurisdictional basis of its proposal.  Put simply: \n1. What legal authority (federal or state/local) is being invoked to force the involuntary \ndesignation of end-use retail customers to provide a FERC-jurisdictional wholesale rate \nservice (IRAS), and to compel those end-use retail customers to provide that service to \nPJM at rates, terms, and conditions established under the PJM Tariff?   \n \na. If the answer is “federal,” then under what provision of the FPA does the \nCommission have that power?   \n \nb. Alternatively, if the answer is “state,” then again, under what legal basis do state \nregulatory authorities have this ability, given FERC’s plenary jurisdiction over \nwholesale rates, services, and markets? \nPPL Electric encourages PJM and the Commission to consider the alternatives that PPL \nElectric provided in its September 3 Protest which, if adopted, would strengthen the \njurisdictional foundation upon which IRAS is built.  Specifically:    \nOption 1 -  \nHave PJM’s Tariff language stop at the issuance of the \nOperating Instruction to Electric Distributors to curtail load, and \nleave the rates, terms, and conditions of that load curtailment \nservice to state and local regulatory authorities—many of whom \nhave already signed the Ratepayer Protection Pledge.  This \nwould avoid a scenario where federally imposed obligations are \ncolliding with state and local-jurisdictional law and tariffs, \nincluding the statutory “obligation to serve,” and would provide \na much more jurisdictionally sound legal pathway to effectuate \nconnect and manage under FPA section 201.   \nOption 2 - \nAlternatively, make IRAS a voluntary FERC-jurisdictional \nservice, whereby Electric Distributors and/or large load \n \n15 16 U.S.C. § 824."},{"page":8,"startToken":2337,"endToken":2551,"text":"8 \n \ncustomers themselves can voluntarily choose to participate like \nany other wholesale market service provider in PJM (including \ndemand response providers).  Given the enthusiasm with which \nmany large load developers and Electric Distributors have \nsigned the Ratepayer Protection Pledge,16 there should clearly \nbe a high level of interest in voluntarily participating in such a \nprogram.  Such a program would also be consistent with EPSA,17 \nwhere the Supreme Court affirmed the Commission’s ability to \ncreate programs that “lure,” rather than force, end-use retail \ncustomers into participating in FERC-jurisdictional wholesale \nmarkets. \nIII. \nCONCLUSION \nIn accordance with the foregoing, PPL Electric respectfully requests that the \nCommission grant leave and accept this Limited Answer into the record of this proceeding. \n \nRespectfully submitted, \n \nSteven Nadel  \nSenior Counsel  \nPPL Services Corporation  \n645 Hamilton Street, Suite 601  \nAllentown, PA 18101  \nTel: 610.774.4102  \nSMNadel@pplweb.com   \n/s/ Thomas DeVita     \nKimberly B. Frank \nThomas S. DeVita \nStuart B. Robbins \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006 \nTel: 202.778.9064 \nkimberly.frank@klgates.com \nthomas.devita@klgates.com \nstuart.robbins@klgates.com  \n \n \nOctober 6, 2026 \n \n16 \nSee \nRatepayer \nProtection \nPledge, \nThe \nWhite \nHouse \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.  \n17 FERC v. EPSA, 577 U.S. 260, 286 (2016)."},{"page":9,"startToken":2551,"endToken":2617,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day of October 6, 2026 served the foregoing document \nupon each person designated on the official service list compiled by the Secretary in this \nproceeding. \n \n \nRespectfully submitted, \n/s/ Stuart Robbins \nStuart B. Robbins \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006  \nTel: 202.778.9064 \nstuart.robbins@klgates.com  \n \nOctober 6, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":672,"startToken":0,"endToken":372},{"p":2,"at":672,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":356,"startToken":372,"endToken":754},{"p":3,"at":356,"title":"II. LIMITED ANSWER","method":"printed heading","endPage":8,"endAt":649,"startToken":754,"endToken":2428},{"p":8,"at":649,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2428,"endToken":2551},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":411,"startToken":2551,"endToken":2617}]}