{"document":{"slug":"rec-20261007-5161","title":"Motion for Leave to File Limited Answer and Answer of Southern Maryland Electric Cooperative, Inc. to PJM Interconnection, L.L.C.'s 09/23/2026 Answer","issued":"2026-10-07","accession":"20261007-5161","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Southern Maryland Electric Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20261007-5161_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261007-5161","tier":"record","sha256":"de6c56e30de5e2a68e6c73d1a0ad6b7153f51bbef7b6a15e6a385e51b03906d6","pages":9,"tokens":2393,"emptyPages":[],"textThemes":["registry","flex"]},"pages":[{"page":1,"startToken":0,"endToken":278,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3515-000 \n \n \n) \n \nMOTION FOR LEAVE TO FILE LIMITED ANSWER, AND LIMITED ANSWER OF \nSOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC.  \nI. Introduction and Summary \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (\"Commission\"), 18 C.F.R. §§ 385.212, 385.213, Southern Maryland \nElectric Cooperative, Inc. (\"SMECO\") respectfully moves for leave to file this limited answer \n(“Limited Answer”) and answer to the September 23, 2026 Answer of PJM Interconnection, \nL.L.C. (\"PJM\") filed in the above-captioned docket on September 23, 2026 (\"PJM Answer\"). \nOn September 3, 2026, SMECO filed Comments and Limited Protest (\"SMECO Limited \nProtest\")1 regarding PJM's August 13, 2026 proposal to establish Interim Resource Adequacy \nService (\"IRAS\") and a Large Load Registry (\"IRAS Filing\").  SMECO's Limited Protest raised \nthree discrete issues affecting Electric Distributors: \n1. The real-time Interim Resource Adequacy Service Action mechanism does not confirm \nthat the New Large Load underlying an Electric Distributor's assigned obligation is actually \nenergized, risking curtailment of the Electric Distributor's core native load.2  \n2. The billing indemnification provision in proposed Tariff, Attachment DD-4, section \nX(b)(iii) shifts compensation default risk to Electric Distributors, including for payments \nowed by unaffiliated entities.3  \n3. The Large Load Registry rests on Manual provisions not yet developed, leaves unclear the \nscope of Electric Distributor liability for third-party data, and identifies no cost-recovery \nmechanism (Section IV.D). 4 \n \n1 https://elibrary.ferc.gov/eLibrary/filedownload?fileid=23DDE71C-2F9E-CCFF-9E1B-A068EDF00000 \n2 SMECO Limited Protest at 7-10. \n3 SMECO Limited Protest at 10-11. \n4 SMECO Limited Protest at 11-12."},{"page":2,"startToken":278,"endToken":710,"text":"2 \n \nThe PJM Answer does not respond to any of SMECO's issues. PJM states that its \"silence on any \nargument should not be deemed as acceptance of the arguments raised.\"5 But silence also supplies \nno record basis on which the Commission can resolve these issues. As the filing utility under \nsection 205 of the Federal Power Act (\"FPA\"), PJM bears the burden of demonstrating that its \nproposal is just and reasonable.6 The New Jersey Board of Public Utilities (\"NJBPU\"), moreover, \nhas filed an answer supporting SMECO's position on the first of these issues.7  \nSMECO therefore respectfully requests that, in acting on the IRAS Filing, the Commission \ndirect PJM to make the clarifications and revisions described below, either on compliance or before \nthe relevant provisions take effect. \nII. Motion for Leave to Answer \nAlthough Rule 213(a)(2) generally prohibits answers to protests or answers absent \nCommission authorization, the Commission accepts otherwise-prohibited answers when they \nprovide information that assists its decision-making,8 and clarify the record.9 Good cause exists \nhere to justify the Commission’s granting this motion and accepting this Limited Answer.   This \nLimited Answer raises no new issues and is narrow. It identifies for the Commission issues in \nSMECO's Limited Protest that remain unaddressed on the record. PJM has asked the Commission \n \n5 PJM Answer at 8, FN.23. \n6 16 U.S.C. § 824d(e). \n7 Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities, Docket No. ER26-3515-000, \nat 3-4 (September 18, 2026) (\"NJBPU Answer\"). \n8 See PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting an answer that assisted with the \ndecision-making process); N.Y. State Pub. Serv. Comm’n v. N.Y. Indep. Sys. Operator, Inc., 158 FERC ¶ 61,137, at P \n29 (2017) (same), order granting in part and denying in part reh’g and clarification, 170 FERC ¶ 61,120, order on \nclarification, 171 FERC ¶ 61,114 (2020); Colonial Pipeline Co., 157 FERC ¶ 61,173, at P 23 (2016) (same). \n9 See, e.g., Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229, P 102 (2012) (accepting answer \nto an answer because it provided material evidence that corrected the record and informed the Commission’s decision-\nmaking process); High Island Offshore Sys., L.L.C., 113 FERC ¶ 61,202, P 8 (2005) (accepting an answer to a protest \nbecause it assisted the Commission with a more complete record); N.E. Utils. Servs. Co. v. NRG Energy, Inc., 101 \nFERC ¶ 61,327, P 17 (2002) (accepting answer to an answer because it helped clarify issues in the proceeding)."},{"page":3,"startToken":710,"endToken":997,"text":"3 \n \nto act by October 12, 2026. An accurate account of the unresolved issues will assist the \nCommission in issuing an order that addresses them. SMECO respectfully requests that the \nCommission accept this Answer. \nIII. Answer \nA. PJM Did Not Respond to SMECO's Showing That an IRAS Action Could Require \nCurtailment of Core Native Load. \nSMECO showed that, under the Affidavit of Christopher Pilong, an Interim Resource \nAdequacy Service Action directs an Electric Distributor to reduce load up to its full pre-Delivery \nYear IRAS obligation. That quantity is fixed before the Delivery Year and is not tied to whether \nthe underlying New Large Load is energized and taking service. No IRAS Alert need precede an \nAction.10 Eligible New Large Loads are, by definition, loads that have not brought their own \ncapacity, and are disproportionately likely to still be under construction or commissioning.11 If \nsuch a load is not yet drawing power when an Action issues, the Electric Distributor's only means \nof compliance would be to curtail its existing, non-Large-Load native customers.12  \nSMECO asked the Commission to direct PJM to clarify: (1) whether an Electric \nDistributor's obligation under an IRAS Action is capped by the New Large Load MW actually \nenergized and taking service at the time of the Action; (2) if not, what safeguard prevents an \nElectric Distributor from being directed to reduce more load than its energized New Large Load \nrepresents; and (3) whether PJM will adjust or suspend an assigned IRAS obligation when the \nunderlying New Large Load's in-service date is delayed.13  \n \n10 PJM Answer at 8 and at 9 (citing Pilong Aff. para. 34). \n11 PJM Answer at 8. \n12 PJM Answer at 9. \n13 PJM Answer at 9–10."},{"page":4,"startToken":997,"endToken":1344,"text":"4 \n \nThe PJM Answer does not respond to any of these questions. Instead, it restates the zone-level \ndesign that gives rise to SMECO's concern: \n• \nPJM \"will be issuing broad load reduction directives to Electric Distributors.\"14  \n• \nElectric Distributors \"will retain full discretion\" as to how PJM's MW reduction \ninstructions \"will ultimately be carried out just as they do today.\"15 \n• \nPJM's directives \"will be informed by the degree to which load in a certain zone/area's \nIRAS responsibility has been reduced through MW of BYONC or Allocated RBP UCAP \nMW.\"16  \nThese statements do not account for New Large Load that is not yet energized or is still ramping. \nDiscretion over which retail customers to curtail is of no help when the load that created the \nobligation is not consuming power. PJM identifies offsets for BYONC and Allocated RBP UCAP \nMW, but no corresponding adjustment for delayed in-service dates. \nThis gap matters because it runs counter to IRAS's stated purpose. PJM describes IRAS as \nprotecting \"native loads from the cost and reliability impacts\" of New Large Loads that have not \nbrought capacity.17 Under the design as filed, an IRAS Action could instead fall on native load. \nPJM also states that “[i]n particular, the in-service date is a critical piece of information\" collected \nthrough the Large Load Registry.18 The data needed to cap an Action at energized New Large Load \nMW will therefore be available to PJM. \nSMECO is not alone in this concern. In its answer, the NJBPU observed that SMECO's \nLimited Protest \"highlight[s] that this is not merely a hypothetical scenario,\" because an Electric \nDistributor's \"assigned New Large Loads may not be yet energized, or may have only just begun \na ramp or testing period that is below its expected draw when PJM issues an IRAS Action.\"19 The \n \n14 PJM Answer at 26. \n15 PJM Answer at 27. \n16 PJM Answer at 29. \n17 PJM Answer at 31 (heading); see also, PJM Answer at 35. \n18 PJM Answer at 13. \n19 NJBPU Answer at 3 (citing SMECO Limited Protest at 8-9)."},{"page":5,"startToken":1344,"endToken":1635,"text":"5 \n \nNJBPU agreed that SMECO had raised, as did Buckeye Power and East Kentucky Power \nCooperative in their pleadings in this docket, that requiring Electric Distributors to curtail other \ncustomers to meet the assigned IRAS MW amount is \"clearly not PJM's intent,\" and asked PJM to \nclarify how it will use real-time demand from New Large Loads to inform curtailment directives.20 \nThe NJBPU also supported SMECO’s and Buckeye Power’s request also made for clarification \nthat Electric Distributors \"will not be required to shed more load than what is being used by New \nLarge Loads in real-time.\"21 \nThe Commission should direct PJM to (1) cap an Electric Distributor's obligation under an \nIRAS Action at the New Large Load MW actually energized and taking service in its zone/area at \nthe time of the action, or explain on the record what alternative safeguard prevents curtailment of \nnative load; and (2) adjust or suspend an Electric Distributor's assigned IRAS obligation when an \nunderlying New Large Load's in-service date is delayed. \nB. PJM Did Not Respond to SMECO's Protest of the Billing Indemnification Provision. \nIn its Limited Protest, SMECO showed that proposed Tariff, Attachment DD-4, section \nX(b)(iii) provides that any default in the payment of IRAS compensation \"shall be assessed to the \nElectric Distributor,\" not to PJM or its membership. 22  In restructured states, the defaulting LSE \nmay have no affiliation, and no commercial or credit relationship, with the Electric Distributor.23 \nThe proposal includes no collateral requirement or PJM-administered mutualization to protect the \nElectric Distributor.24  \n \n20 NJBPU Answer at 3. \n21 NJBPU Answer at 3-4. \n22 SMECO Limited Protest at 10 (quoting IRAS Filing at 108–09). \n23 SMECO Limited Protest at 11. \n24 SMECO Limited Protest at 11."},{"page":6,"startToken":1635,"endToken":1933,"text":"6 \n \nWhile the PJM Answer addresses IRAS compensation25,  the discussion does not mention \nsection X(b)(iii), default allocation, or Electric Distributor credit exposure.  What the PJM Answer \ndoes say, however,  underscores the problem. PJM describes the mechanism as \"compensating \nLSEs, which are NITS customers.\"26 PJM further states that the entities to be paid and the loads to \nbe charged are \"determined at the state level.\"27 If the wholesale compensation flows to LSEs, and \npayors and payees are set by state authorities, PJM offers no reason why an Electric Distributor \nshould guarantee payment by other entities. \nIn its Answer, PJM consents to clarifying proposed Tariff, Attachment DD-4, section X on \ncompliance, and asks the Commission to \"prescribe the compliance requirement in as much detail \nas possible.\"28 SMECO agrees that compliance is the appropriate vehicle. The Commission should \ndirect PJM, in that compliance filing, to revise section X(b)(iii) so that an Electric Distributor is \nnot assessed defaults on IRAS compensation owed by other entities. Alternatives include limiting \nan Electric Distributor's payment obligation to amounts it actually collects, or establishing \ncollateral requirements or PJM-administered credit support for IRAS compensation billing. \nC. PJM Did Not Address SMECO's Large Load Registry Concerns, and Its Statements to \nOther Parties Leave Them Unresolved. \nSMECO requested that the Commission direct PJM to clarify the scope of an Electric \nDistributor's liability for Registry information sourced from LSEs or Large Loads29 The PJM \nAnswer does not respond to SMECO on any of this point. In response to Old Dominion Electric \nCooperative and East Kentucky Power Cooperative, PJM states that the obligation to provide \n \n25 PJM Answer at 54–58. \n26 PJM Answer at 54. \n27 PJM Answer at 58. \n28 PJM Answer at 58, FN 204. \n29 SMECO Limited Protest at 13."},{"page":7,"startToken":1933,"endToken":2252,"text":"7 \n \nRegistry information \"is borne by the LSE, not the Electric Distributor directly, although PJM \nwould welcome information provided by an Electric Distributor.\"30   SMECO indeed welcomes \nthat clarification. It does not, however, resolve SMECO's concern, for three reasons: \n• \nProposed Tariff, Attachment DD-4, section III(b) still provides that an Electric Distributor \n\"shall\" provide Registry information and coordinate with PJM on its validity. A voluntary \nrole described in an answer does not modify mandatory tariff language. \n• \nPJM states that Electric Distributors \"may provide the information for the Large Load \nRegistry on behalf of their relevant LSEs,\" and that PJM may reach out to Electric \nDistributors to supplement LSE submissions.31 That is precisely the relay role for which \nSMECO sought clarity on exposure under FPA section 222 and 18 C.F.R. § 35.41(b), \nwhich the IRAS Filing itself invoked.32  PJM does not address that exposure. \n• \nPJM acknowledges that the RAA's definition of \"Party\" is broader than LSEs, and that PJM \n\"will continue to evaluate this.\"33 The identity of the obligated entity therefore remains \nunsettled. \nThe Commission should direct PJM to conform proposed Tariff, Attachment DD-4, section \nIII(b) to PJM's stated position that the LSE bears the Registry reporting obligation, and to clarify \nthat an Electric Distributor that relays, in good faith, information originating with an LSE or Large \nLoad is not responsible for the accuracy of that information. \nD. The Commission Can Resolve These Issues Through Prescriptive Compliance Directives. \nPJM asks that, to the extent the Commission rejects any element of its filing, the \nCommission \"either direct prescriptive changes to be implemented on compliance or provide \nguidance\" to PJM and stakeholders.34 SMECO's requests are limited and can be addressed in that \nmanner. \n \n30 PJM Answer at 9–10, FN 27. \n31 PJM Answer at 13. \n32 IRAS Filing at 44–45. \n33 PJM Answer at 13 FN 41. \n34 PJM Answer at 8."},{"page":8,"startToken":2252,"endToken":2345,"text":"8 \n \nIV. Conclusion \nFor the foregoing reasons, SMECO respectfully requests that the Commission (1) grant \nSMECO leave to file this Limited Answer and accept it into the record; and (2) in acting on the \nIRAS Filing, direct PJM to make the clarifications and revisions described above and in SMECO’s \ninitial Limited Protest. \nRespectfully submitted, \nDamon L. Krieger \nSenior Vice President, Legal and Strategy, and \nGeneral Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, MD 20637-1937 \n301.274.4323 \nDamon.Krieger@SMECO.coop \nDated: October 7, 2026."},{"page":9,"startToken":2345,"endToken":2393,"text":"9 \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served a copy of the foregoing document upon each \nparty on the official service list compiled by the Secretary of the Federal Energy Regulatory \nCommission in this proceeding. \n \n \n \nDated: October 7, 2026. \n \n \n \n \n \n \n \n /s/ _____ \nJohn S. Rohrbach"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":268,"startToken":0,"endToken":35},{"p":1,"at":268,"title":"I. Introduction and Summary","method":"printed heading","endPage":2,"endAt":794,"startToken":35,"endToken":407},{"p":2,"at":794,"title":"II. Motion for Leave to Answer","method":"printed heading","endPage":3,"endAt":217,"startToken":407,"endToken":744},{"p":3,"at":217,"title":"III. Answer","method":"printed heading","endPage":3,"endAt":230,"startToken":744,"endToken":746},{"p":3,"at":230,"title":"A. PJM Did Not Respond to SMECO's Showing That an IRAS Action Could Require","method":"printed heading","endPage":5,"endAt":1046,"startToken":746,"endToken":1513},{"p":5,"at":1046,"title":"B. PJM Did Not Respond to SMECO's Protest of the Billing Indemnification Provision.","method":"printed heading","endPage":6,"endAt":1297,"startToken":1513,"endToken":1828},{"p":6,"at":1297,"title":"C. PJM Did Not Address SMECO's Large Load Registry Concerns, and Its Statements to","method":"printed heading","endPage":7,"endAt":1515,"startToken":1828,"endToken":2166},{"p":7,"at":1515,"title":"D. The Commission Can Resolve These Issues Through Prescriptive Compliance Directives.","method":"printed heading","endPage":8,"endAt":5,"startToken":2166,"endToken":2253},{"p":8,"at":5,"title":"IV. Conclusion","method":"printed heading","endPage":9,"endAt":7,"startToken":2253,"endToken":2346},{"p":9,"at":7,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":322,"startToken":2346,"endToken":2393}]}