{"document":{"slug":"rec-20261008-5058","title":"Motion for Leave to File Supplemental Comments and Supplemental Comments of Persistence Analytics Group LLC re Validated Project State, Evidentiary…","issued":"2026-10-08","accession":"20261008-5058","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Individual No Affiliation","kind":"comments","file":"sources/filings/text/20261008-5058_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261008-5058","tier":"record","sha256":"ef1f4fd94656ce70f223c0cc32604b9413cf85d74491b507683e66c7e134021e","pages":4,"tokens":1725,"emptyPages":[],"textThemes":["registry"]},"pages":[{"page":1,"startToken":0,"endToken":581,"text":"Docket No. ER26-3515-000\nPage 1\nUNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\nPJM Interconnection, L.L.C.\nDocket No. ER26-3515-000\nMOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS AND\nSUPPLEMENTAL COMMENTS OF PERSISTENCE ANALYTICS GROUP LLC\nREGARDING VALIDATED PROJECT STATE, EVIDENTIARY CURRENCY, AND \nREVALIDATION\nI. MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS\nPersistence Analytics Group LLC (\"PAG\") respectfully submits these supplemental comments concerning \nPJM Interconnection, L.L.C.'s proposed Interim Resource Adequacy Service (\"IRAS\") and Large Load \nRegistry. PAG submitted initial comments in this docket on August 13, 2026. Those comments recommended, \namong other things, that material large-load information carry sufficient context to distinguish projected or \nrequested load from more mature states, that execution-critical assumptions have identifiable revalidation \ntriggers, and that material registry inputs preserve useful provenance and validation timing.\nSince PAG's initial filing, PJM has published implementation materials that provide materially greater \ndetail about the Phase 1 Large Load Registry and the Bring Your Own New Capacity (\"BYONC\") validation \nprocess. Those materials include PJM's Large Load Registry Field Definitions and Examples, a BYONC Officer \nCertification Template, and an October 7, 2026 presentation describing the reporting and validation process for \nthe 2029/30 Base Residual Auction.\nThese materials could not have been addressed in PAG's August 13 comments and directly illuminate how \nseveral of the evidentiary issues raised there will be implemented. The supplemental comments are narrow, \nacknowledge the meaningful validation PJM has now established, and do not seek to delay the Phase 1 process \nor the upcoming auction. To the extent leave is required, PAG respectfully requests leave under Rule 212 of the \nCommission's Rules of Practice and Procedure, 18 C.F.R. § 385.212, because consideration of this limited \nupdate will assist the Commission without prejudice to any participant.\nII. PJM'S NEW MATERIALS ESTABLISH MEANINGFUL VALIDATION OF SPECIFIC \nPROPOSITIONS\nPJM's October 7 presentation describes Phase 1 as a temporary process used to determine the 2029/30 \nVariable Resource Requirement curve adjustment for BYONC, with an enhanced process and tool to be \ndeveloped based on experience and feedback for determining eligible IRAS for the 2027/28 Delivery Year and \nforward. PJM, Large Load Registry and BYONC Reporting Process for 2029/30 BRA, at 2 (Oct. 7, 2026).\nThe new implementation materials provide more assurance than a reporting-only registry. An Electric \nDistribution Company (\"EDC\") submits the New Large Load and associated BYONC information, and PJM \nstates that the relevant BYONC contract must be executed. Where an LSE submits directly, PJM instructs the \nLSE to obtain EDC confirmation of the New Large Load and provide that confirmation to PJM. Id. at 5.\nThe Capacity Market Seller must separately provide an officer certification. The template states that PJM \nand PJM Settlement are relying on the certification as evidence that the participant has an executed contract with \nthe specified New Large Load for the 2029/30 Delivery Year; the officer also certifies that the arrangement \nidentified in Attachment A is true and accurate and that the underlying resource qualifies as BYONC under the \napplicable Tariff requirements. PJM, BYONC Officer Certification Template, Officer Certification & \nAttachment A (Oct. 2026).\nPJM then validates the registry information. For the large load, PJM checks for duplicates and uses EDC \nvalidation as needed. For BYONC, PJM verifies information against Capacity Exchange, ensures the resource \nmeets Tariff criteria, checks for duplicates, and confirms submission of the executed-contract certification. \nPJM's determination of BYONC eligibility is then published in the Registry's BYONC Status field. PJM Oct. 7 \nPresentation at 8."},{"page":2,"startToken":581,"endToken":1195,"text":"Docket No. ER26-3515-000\nPage 2\nPAG supports those controls. They demonstrate that PJM is not treating every submitted representation as \nself-proving. They also sharpen the remaining question: what proposition has been validated, and for what later \ndecision is that validation sufficient?\nIII. VALIDATION SHOULD IDENTIFY THE PROPOSITION VALIDATED\nA verified contractual relationship is decision-grade evidence of that contractual relationship; it \nis not necessarily decision-grade evidence of future energized or sustained demand.\nThe current Registry field set appropriately identifies the customer, EDC interconnection request, location, \nzone, business segment, 2026/27 and expected 2029/30 peak load, BYONC contract status, associated resource \nidentifiers, BYONC MW, submitter contacts, and PJM's BYONC Status. PJM, Large Load Registry Field \nDefinitions and Examples (Oct. 2026). Those fields are useful and substantially improve visibility.\nThe field set does not, however, appear to contain a structured project-state field that distinguishes whether \nthe represented future load is reported or requested, contractually committed, executable, energized, or operating \non a persistent basis. Nor does the validation label itself distinguish whether PJM has validated identity and \nduplicate status, an executed contractual relationship, Tariff eligibility, a forecast quantity, an executable project \nstate, or an operating state.\nThat distinction matters because the same record can support different propositions with different degrees \nof confidence. An executed BYONC contract may be sufficient evidence for a BYONC contractual or eligibility \ndetermination while remaining insufficient, standing alone, to establish that the corresponding New Large Load \nwill energize on the represented schedule or sustain the represented demand.\nPAG therefore recommends that, as PJM develops the enhanced process, any material validation status \nidentify the proposition validated. PJM need not create a public scoring system or adopt PAG's terminology. A \nconcise status definition or associated metadata can make clear whether the validated fact concerns identity, \ncontract execution, Tariff eligibility, forecast state, project execution, operational capability, or another defined \nproposition.\nIV. EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER \nRELIANCE IS CONSEQUENTIAL\nThe Registry contains submitter identity and contact information, but the current field definitions do not \nappear to require an effective-as-of date for the underlying project-state evidence, a last-revalidated date, or a \nstructured material-change indicator for the large-load state itself. That omission becomes more important when \na validated record is reused for a different or later decision.\nPJM's implementation schedule illustrates the speed with which the information can become consequential. \nThe October 7 presentation shows the Phase 1 Registry closing on October 20, PJM finalizing validation on \nNovember 14, planning parameters posting on November 19, and the Base Residual Auction opening on \nDecember 9. PJM Oct. 7 Presentation at 3.\nPAG does not recommend continuous resubmission of unchanged data. It recommends that a material \nvalidated state carry enough currency information to allow the relying entity to know when the relevant \nevidence was effective or last materially confirmed. Where the represented MW, energization timing, customer \nidentity, EDC interconnection status, BYONC arrangement, resource status, or another fact supporting the \nearlier determination changes materially, the affected determination should be revalidated before that prior \nstatus is used as if nothing changed.\nV. THE ENHANCED IRAS PROCESS IS THE APPROPRIATE PLACE TO MATCH EVIDENCE TO \nTHE DECISION\nPJM expressly characterizes Phase 1 as temporary and states that it will implement an enhanced process and \ntool based on feedback and experience for eligible IRAS in later Delivery Years. That planned enhancement \nprovides a practical opportunity to preserve the distinction between a validated reported state and a state \nsufficiently evidenced for a specific consequential decision.\nPAG does not ask the Commission to direct a new public scoring methodology, create a separate approval \nlayer, or displace PJM's technical judgment. Nor does PAG suggest that the current Phase 1 Registry must be"},{"page":3,"startToken":1195,"endToken":1634,"text":"Docket No. ER26-3515-000\nPage 3\nredesigned before the 2029/30 auction. The narrow recommendation is that the evidentiary maturity of a \nrepresented state be matched to the consequence of the decision for which PJM or another authorized entity \nrelies upon it.\nThis can be implemented incrementally through status definitions, effective or validation dates, source \ncategories where useful, and material-change/revalidation indicators. The goal is not more data for its own sake. \nIt is to prevent a validated fact from being silently generalized beyond the proposition that the supporting \nevidence actually establishes.\nVI. REQUESTED COMMISSION RECOGNITION\nIn light of PJM's new implementation materials, PAG respectfully recommends that the Commission \nrecognize the following principles as PJM completes Phase 1 and develops its enhanced Large Load Registry \nand IRAS processes:\n1. Validation should identify the proposition validated. A status showing that a contract, identity, duplicate \ncheck, or Tariff criterion has been validated should not be assumed to establish a more mature project or \noperating state unless the supporting evidence is suited to that proposition.\n2. Material large-load states should preserve useful evidence currency. Where consequential reliance depends on \na represented future state, the record should allow the relying entity to understand when the supporting \nevidence was effective or last materially validated.\n3. Material change should trigger revalidation of the affected determination. Changes in represented MW, \ntiming, customer or project identity, interconnection status, BYONC arrangement, resource status, or \nanother decision-critical fact should not leave a prior validated state silently unchanged.\n4. Evidence should be matched to the decision. Information sufficient for early planning visibility or a defined \ncontractual determination may not be sufficient for an operational baseline, market parameter, infrastructure \ncommitment, or other consequential reliance.\nVII. CONCLUSION\nPJM's new implementation materials meaningfully strengthen the Large Load Registry by requiring EDC-\nlinked reporting, an executed BYONC contract, officer certification, duplicate checks, Tariff-eligibility review, \nand PJM validation. PAG supports those controls.\nThe remaining implementation issue is narrower but important: validation should make clear what has \nactually been validated, how current that evidence is, and whether a material change requires the affected \ndetermination to be revisited before continued reliance.\nValidation should identify the proposition validated. Evidence sufficient for one determination \nshould not silently become evidence sufficient for every later decision.\nRecognizing these principles would build on PJM's current work, preserve implementation flexibility, and \nimprove the ability of PJM, state commissions, Electric Distributors, and other authorized users to distinguish a \nvalidated reported state from a decision-reliance state.\nRespectfully submitted,\nNeil P. Osnato\nFounder\nPersistence Analytics Group LLC | United Grid™\n82 Spring Lake Blvd.\nWaretown, NJ 08758\nneil@persistenceanalyticsgroup.com\n609-464-9055\nDated: October 8, 2026\nCERTIFICATE OF SERVICE"},{"page":4,"startToken":1634,"endToken":1725,"text":"Docket No. ER26-3515-000\nPage 4\nI hereby certify that on October 8, 2026, I served the foregoing Motion for Leave to File Supplemental \nComments and Supplemental Comments of Persistence Analytics Group LLC electronically on the applicant's \nrepresentatives identified in PJM Interconnection, L.L.C.'s filing in Docket No. ER26-3515-000 and, to the \nextent applicable, on all persons appearing on the official service list for this proceeding in accordance with \nRule 2010 of the Commission's Rules of Practice and Procedure.\nNeil P. Osnato\nPersistence Analytics Group LLC\nDated: October 8, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":341,"startToken":0,"endToken":46},{"p":1,"at":341,"title":"I. MOTION FOR LEAVE TO FILE SUPPLEMENTAL COMMENTS","method":"printed heading","endPage":1,"endAt":2081,"startToken":46,"endToken":294},{"p":1,"at":2081,"title":"II. PJM'S NEW MATERIALS ESTABLISH MEANINGFUL VALIDATION OF SPECIFIC","method":"printed heading","endPage":2,"endAt":291,"startToken":294,"endToken":622},{"p":2,"at":291,"title":"III. VALIDATION SHOULD IDENTIFY THE PROPOSITION VALIDATED","method":"printed heading","endPage":2,"endAt":2302,"startToken":622,"endToken":889},{"p":2,"at":2302,"title":"IV. EVIDENCE CURRENCY AND MATERIAL CHANGE SHOULD BE VISIBLE WHERE LATER","method":"printed heading","endPage":2,"endAt":3722,"startToken":889,"endToken":1089},{"p":2,"at":3722,"title":"V. THE ENHANCED IRAS PROCESS IS THE APPROPRIATE PLACE TO MATCH EVIDENCE TO","method":"printed heading","endPage":3,"endAt":621,"startToken":1089,"endToken":1286},{"p":3,"at":621,"title":"VI. REQUESTED COMMISSION RECOGNITION","method":"printed heading","endPage":3,"endAt":2021,"startToken":1286,"endToken":1476},{"p":3,"at":2021,"title":"VII. CONCLUSION","method":"printed heading","endPage":3,"endAt":3221,"startToken":1476,"endToken":1631},{"p":3,"at":3221,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":4,"endAt":594,"startToken":1631,"endToken":1725}]}