{"document":{"slug":"rec-20261008-5211","title":"Answer and Motion for Leave to Answer of the Independent Market Monitor for PJM to the 09/23/2026 Answer of PJM Interconnection, L.L.C","issued":"2026-10-08","accession":"20261008-5211","docket":"ER26-3515-000","group":"PJM Large Load definition, Registry and Interim Resource Adequacy Service","filer":"Monitoring Analytics, LLC","kind":"answer","file":"sources/filings/text/20261008-5211_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261008-5211","tier":"record","sha256":"7bff4d30ee476f5cf0c8f501b506a097f39dbafdd6c0ed6c6fa6d87f48703690","pages":26,"tokens":8161,"emptyPages":[],"textThemes":["adequacy","flex","cost","retail"]},"pages":[{"page":1,"startToken":0,"endToken":241,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n \n \nDocket No. ER26-3515-000 \nANSWER AND MOTION FOR LEAVE TO ANSWER \nOF THE INDEPENDENT MARKET MONITOR FOR PJM \nPursuant to Rules 212 and 213 of the Commission’s Rules and Regulations,1 \nMonitoring Analytics, LLC, acting in its capacity as the Independent Market Monitor \n(“Market Monitor”) for PJM Interconnection, L.L.C. (“PJM”),2 submits this answer to, and \nmoves for leave to answer, the answer submitted by PJM on September 23, 2026 \n(“September 23rd Answer”), and to the answer submitted by the Data Center Coalition3 \n(“DCC”) to the September 23rd Answer on October 1, 2026. \nOn August 13, 2026, PJM submitted a proposal “to establish Interim Resource \nAdequacy Service (“IRAS”)—a service to be implemented by PJM solely during periods \nwhen there are insufficient resources to reliably meet demand in real time operations” \n(“IRAS Filing”).4 The IRAS rules would (id.) “enable PJM to prioritize load reduction in \n \n1 \n18 CFR §§ 385.212 & 385.213 (2026). \n2 \nCapitalized terms used herein and not otherwise defined have the meaning used in the PJM Open \nAccess Transmission Tariff (“OATT”), the PJM Operating Agreement (“OA”) or the PJM Reliability \nAssurance Agreement (“RAA”). \n3  \nDCC \nstates \n(at \n1 \nn.2) \nthat \na \nlist \nof \ncurrent \nDCC \nmembers \nis \naccessible \nat \n<https://www.datacentercoalition.org/members>. \n4  \nThe IRAS Filing is supported by an Affidavit of Christopher Pilong (Attachment C) (“Pilong \nAffidavit”)."},{"page":2,"startToken":241,"endToken":639,"text":"- 2 - \nzones/areas where New Large Loads [citation omitted] have not brought their own new \ncapacity or had their capacity needs covered through the Reliability Backstop Procurement \n(“RBP”).” An order on the RBP auction process issued September 29, 2026 (“RBP Order”).5 \nThe IRAS Filing has not been supported as just and reasonable. The IRAS Filing is \nnot just and reasonable and it should be rejected. The IRAS Filing proposal for curtailments \nis not actually a proposal but is rather an attempt to shift responsibility for curtailments to \nthe states. To the extent that the IRAS Filing would create actual rules, it has not been \ndemonstrated to be consistent with cost causation principles, the same defect in the RBP \nFiling identified in the RBP Order (at PP 150–157). The IRAS Filing is unjust and \nunreasonable, and attempting to implement it will damage PJM markets and create \nunintended consequences. Contrary to DCC’s argument that the IRAS Filing proposes rules \nthat exceed the Commission’s jurisdiction, the IRAS Filing’s core flaw is the failure to \nprovide a solution that is consistent with federal jurisdiction, that is consistent with cost \ncausation principles and that is consistent with federal policy. \nThe IRAS Filing is PJM’s non responsive response to broad agreement among policy \nmakers, regulators, and developers, captured in the Ratepayer Protection Pledge and \nPrinciples, on the need to ensure that data centers bring their own new generation and pay \ntheir own way and to prioritize the protection of reliability and affordability for all the \nother customers.6 7 The Pledge affirms: “The Ratepayer Protection Pledge and the \n \n5  \nSee PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (“RBP Order”). \n6 \nSee \nThe \nWhite \nHouse, \n“Ratepayer \nProtection \nPledge” \n(March \n4, \n2026), \n<https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/?utm_source=wh_social\n_share_button>, Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026) (“Today, pursuant to the \nRatepayer Protection Pledge, leading United States hyperscalers and AI companies guarantee that \ndata centers’ energy needs will not increase household electricity costs for American citizens. \nInstead, these companies will build, bring, or buy the new generation resources and electricity \nneeded to satisfy their energy demands, and pay for all new power delivery infrastructure \nupgrades to service their data centers. They will voluntarily negotiate new, separate rate structures \nwith their utilities and relevant State governments, and pay those rates, and for their infrastructure,"},{"page":3,"startToken":639,"endToken":1145,"text":"- 3 - \ncommitments embodied therein effectuate the national policy of the United States.” The \nCommission has recognized the Pledge and Principles.8 The Pledge and Principles should \nguide the development of rules to support resource adequacy by requiring data centers to \nbring their own new generation, or when that is not done, procuring new capacity to serve \n \n \nwhether they use the electricity or not. They will also invest in local communities and coordinate \nwith grid operators to contribute to a more reliable grid.”) (“Pledge”). On July 23, 2026, over 200 \nadditional entities joined the pledge. See The White House, “President Trump’s Ratepayer \nProtection Pledge Secures American AI Dominance, Protects Consumers” (July 23, 2026), \n<https://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayer-protection-pledge-secures-\namerican-ai-dominance-protects-consumers/?utm_source=wh_social_share_button>. \n7  \nNational Energy Dominance Council, Statement of Principles Regarding PJM (January 16, 2026) \n<https://www.energy.gov/documents/statement-principles-regarding-pjm> (“Principles”). Two principles \napply to the contemplated procurement of new generation. First, the procurement should \n“[p]rovide 15-year price certainty for new capacity resources” [emphasis]. The statement notes that \nthis can be done in through a “Reliability Backstop Auction,” but does not require that this auction \nbe a centralized procurement by PJM or that PJM customers assume risks. Second, “PJM should \nallocate the cost of any new capacity through the aforementioned Reliability Backstop Auction to \nload serving entities (LSEs) with new data centers that have not self-procured new capacity or \nagreed to be curtailable.” The principles, agreed to by the Governors of PJM States Indiana, Ohio, \nMaryland Pennsylvania, Virginia, West Virginia, Delaware, Illinois, Michigan, New Jersey, \nTennessee, North Carolina and Kentucky, call for PJM to do the allocation and to match data \ncenters to the costs not excluding risks of new resources or commitments to curtail. Additional \nprinciples that going beyond the RBF Proposal, the Market Proposal, or potential alternatives, \ninclude: (i) extending the price collar for two additional RPM Base Residual Auctions, (ii) PJM \nimproving load forecasting, (iii) accelerating generator interconnections, i.e., the Reliability \nResource Initiative (RRI), and (iv) continued efforts to reform the capacity market. \n8  \nSee PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at PP 2, 5, 8, 32 & 69 (2026) (“Large Load Show \nCause Order”). The Large Loads Show Cause Order states (at P 66) (“We next preliminarily find \nthat PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to \nmitigate the risk of cost shifting among transmission customers, which may result in unjust and \nunreasonable rates for transmission service. In particular, we are concerned about the apparent lack \nof: (1) transparency regarding the assignment of Network Upgrades, and their associated costs, that \nare needed to provide transmission service to Eligible Customers on behalf of large loads; and (2) a \npro forma cost recovery agreement between PJM, the relevant transmission owner, and the Eligible \nCustomer taking transmission service on behalf of large loads that help ensure that Eligible \nCustomers bear the risk and are ultimately responsible for costs incurred to provide transmission \nservice, including the cost of Network Upgrades.”)."},{"page":4,"startToken":1145,"endToken":1452,"text":"- 4 - \ndata centers and ensuring that data centers pay for that capacity and that those costs are not \nassigned, allocated or otherwise imposed on other customers. \nThe IRAS Filing ignores the Pledge and Principles. The IRAS Filing is a convoluted, \ninconsistent, confusing proposal that PJM justifies based on a misreading of jurisdictional \nresponsibilities and under which PJM denies responsibility for reliability and assigns key \nundefined and inappropriate roles to the states. The September 23rd Answer does not \nanswer the objections raised and does not provide the support needed to approve the IRAS \nFiling. \nIn addition to rejecting the IRAS Filing as not just and reasonable, an order should \nbe issued, finding that the existing rules relating to resource adequacy for serving data \ncenters in the PJM Region are unjust and unreasonable under Section 206 of the Federal \nPower Act. Such an order should direct that PJM file rules for the PJM Region establishing \ntariff defined curtailment obligations for wholesale service to data centers during a defined, \nlimited transition period that would allow data centers that interconnect without new \ngeneration the time to contract for new generation but that would include curtailment rules \nas a long term solution to meeting the need for data centers to bring their own new \ngeneration. \nThese requirements meet the goals of the Pledge and Principles and can be \nimplemented immediately. \nI. ANSWER \nA. Neither the IRAS Filing nor the Market Monitor’s Proposed Remedial \nDirective Unduly Discriminates Against Data Centers. \nThe RBP Filing reveals PJM’s confusion on the purpose of the RBP Filing and, by \nimplication, the purpose of the associated IRAS Filing.9 The RBP Order directs PJM to file \n \n9  \nCf. PJM Answer, Docket No. ER26-3380-000 (September 10, 2026) at 64 (“It is fallacious to suggest \nthat a just and reasonable cost allocation approach must either identify specific loads (which are"},{"page":5,"startToken":1452,"endToken":1839,"text":"- 5 - \nadditional rules to address the central issue, to assign RBP auctions costs (at PP 150–157), \nfinding “PJM has not adequately demonstrated that its proposal is just and reasonable and \nconsistent with the cost causation principle.” Market Monitor believes that this means that \nthe costs of serving data centers should be assigned to data centers. Assigning the RBP \nauction costs to data centers meets the definition of the cost causation standard because \ndata centers are the cause of the problem to be solved by the RBP Filing. The stated purpose \nof the IRAS Filing is to define rules that would require curtailments when some data centers \nfail to bring their own new generation. Yet the IRAS Filing fails to meet its stated purpose. \nThe Commission’s issuance of Remedial Directives advocated by the Market \nMonitor would solve the problem in a manner fully consistent with both cost causation \nprinciples and the Pledge and Principles.10 \nDCC, nevertheless, argues (at 18) “PJM has not demonstrated that New Large Loads \nare in fact causing PJM’s capacity shortfall.” DCC also argues (at 16–19) that the “factual \ndifferences” relied upon by PJM are not adequate to justify discriminatory treatment. \nDCC’s surprising assertion that the reasons for the IRAS Filing do not justify rules specific \nto data centers has no merit. It is data centers that are uniquely seeking interconnection at \nthe scale and at the speed sought by data centers. It is clear from the evidence that data \n \n \nnot FPA-jurisdictional actors) and not the LSEs serving those loads or be limited to one type of load \nwhen the resource adequacy shortfall is caused by all types of loads that comprise the subject Load \nAdjustments” [emphasis in original].); RBP Filing, Docket No. ER26-3380-000 (August 13, 2026) at 1 \n(PJM proposes “to establish the Reliability Backstop Procurement (“RBP”)—a one-time \nprocurement of new capacity to address resource adequacy challenges in the PJM Region arising \nfrom insufficient commitments of capacity in the 2027/2028 and 2028/2029 Reliability Pricing Model \n(“RPM”) Auctions, primarily driven by the unprecedented addition of large loads, most notably \ndata centers”). \n10  \nSee Protest of the Independent Market Monitor for PJM, Docket No. ER26-3380-000 (August 21, \n2026) at 28–32; Protest of the Independent Market Monitor for PJM, Docket No. ER26-3515-000 \n(September 3, 2026) (“IMM Protest”) at 36–40."},{"page":6,"startToken":1839,"endToken":2144,"text":"- 6 - \ncenter customers are uniquely the cause of the reliability issues faced by PJM.11 It is \nuniquely data center customers that are seeking to rely on curtailments so that they can \nparticipate in the wholesale power markets before the infrastructure needed to serve them \nis ready. \nThe Pledge and Principles demonstrate that data centers recognize that the data \ncenters are causing the problems that the IRAS Filing purports to address and that the data \ncenters recognize that they need to bring their own generation and pay their own costs. \nDCC never mentions the Pledge and Principles, and the DCC fails to explain how its \nopposition comports with the Pledge and Principles and the commitments and public \npositions of some of the most significant members of the DCC. DCC’s arguments that the \nIRAS Filing fails because it is unduly discriminatory are not supported and should be \nrejected. \nB. PJM Can File a Complete Proposal Consistent with the Pledge and Principles \nfor the Same Reasons It Defends the Commission’s Jurisdiction to Approve \nthe IRAS Filing. \nThe September 23rd Answer defends (passim) against protests and comments alleging \nthe IRAS Filing proposes rules beyond the Commission’s jurisdiction to approve. PJM is \ncorrect that the IRAS Filing is within the Commission’s jurisdiction to approve. In addition, \nfor the same reasons that PJM provides in defense of the IRAS Filing, PJM could have \nproposed rules that recognize the scope of the Commission’s jurisdiction and that therefore \nactually address the issue affecting wholesale energy markets and regional reliability \nconsistent with the Pledge and Principles. \n \n11  \nThe \nmost \nrecent \nBase \nResidual \nAuction \nReports \nare \nlocated \nat \n<https://www.monitoringanalytics.com/reports/Reports/2026.shtml>. Also see, the 2026 Quarterly \nState \nof \nthe \nMarket \nReport \nfor \nPJM: \nJanuary \nthrough \nJune \nat \n<https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2026.shtml>."},{"page":7,"startToken":2144,"endToken":2559,"text":"- 7 - \nThe IRAS Filing falls far short of what is needed because PJM fails to propose \ncurtailment rules that are consistent with the Commission’s jurisdiction and therefore have \nthe intended result. Instead, PJM relies on speculation about what states may do to \ncomplete its proposal. The IRAS Filing should be rejected because it does not result in \nassigning the costs and risks of meeting data center load to data center customers. PJM \nfailed to file a consistent regional solution consistent with its role as an RTO and consistent \nwith the Commission’s jurisdiction. PJM’s balkanized approach cannot create a consistent \nregional market that applies the same rules across the entire market and that does not create \nunintended consequences across states that result from different interpretations of \ncurtailment rules. PJM’s approach is likely to create more problems than it solves because it \nfails to include a comprehensive and consistent regional approach. \nPJM attempts to justify its incomplete IRAS Filing based on an incorrect statement of \nthe Commission’s jurisdiction. States have jurisdiction over generation in their own states \nand over retail sales in their own states. States do not have jurisdiction over neighboring \nstates. States cooperating with (or failing to cooperate with) other states to regulate \ninterstate commerce, displacing federal regulation, is not cooperative federalism. PJM \nshould not attempt to transfer its responsibility to operate the regional capacity market to \nthe states. The Supreme Court has recognized that the Commission’s jurisdiction extends to \nrules related to retail customers’ participation in the wholesale power markets as sellers.12 \n \n12  \nSee FERC v. EPSA, 577 U.S. 260, 281 (2016) (EPSA) (“Yet a FERC regulation does not run afoul of \n§824(b)’s proscription just because it affects—even substantially—the quantity or terms of retail \nsales. It is a fact of economic life that the wholesale and retail markets in electricity, as in every \nother known product, are not hermetically sealed from each other. To the contrary, transactions \nthat occur on the wholesale market have natural consequences at the retail level. And so too, of \nnecessity, will FERC’s regulation of those wholesale matters. Cf. Oneok, Inc. v. Learjet, Inc., 575 U. S. \n373, 387… (2015) (noting that in the similarly structured world of natural gas regulation, a “Platonic \nideal” of strict separation between federal and state realms cannot exist). When FERC sets a \nwholesale rate, when it changes wholesale market rules, when it allocates electricity as between \nwholesale purchasers—in short, when it takes virtually any action respecting wholesale"},{"page":8,"startToken":2559,"endToken":2849,"text":"- 8 - \nThe Supreme Court recognizes federal jurisdiction over the terms and conditions of retail \ncustomers’ participation in wholesale markets even as they remain retail customers. \nPJM apparently believes, and DCC argues (at 12–15), that because data centers are \nretail customers, PJM cannot require that the load serving entities (“LSEs”) who serve them \nplace terms and conditions on service to data centers.13 PJM has not reconciled this position \nwith the jurisdiction currently exercised under the Reliability Assurance Agreement \n(“RAA”). The RAA requires LSEs to meet their obligations, defined in the RAA, from \ncapacity provided by generators that meet the terms and conditions of the RAA.14 LSEs are \nnot permitted under the RAA to rely on Generation Capacity Resources that do not meet \nthese terms and conditions regardless of state views about the capability of the facilities.15 \nResources included in Fixed Resource Requirement (“FRR”) Plans under Schedule 8.1 to the \nRAA must also meet requirements specified in the RAA.16 \nPJM does not explain why it cannot propose to require terms and conditions for the \ncapacity required to meet data center loads through the LSEs that serve them when it can \nand does include terms and conditions through LSEs on the capacity that can meet the \nreliability obligations of LSEs. \n \n \ntransactions—it has some effect, in either the short or the long term, on retail rates. That is of no \nlegal consequence.”). \n13  \nSee RBP Filing at 64 (“It is fallacious to suggest that a just and reasonable cost allocation approach \nmust … identify specific loads (which are not FPA-jurisdictional actors) …”). \n14  \nSee RAA Schedules 9, et seq. & 10 (rules for PJM to evaluate capability and deliverability of \nGeneration Resources). \n15  \nSee id. \n16  \nSee RAA § 7.2."},{"page":9,"startToken":2849,"endToken":3201,"text":"- 9 - \nDCC objects that data centers are retail customers, and that requirements related to \ncurtailments affect their consumption at retail.17 The IRAS Filing is not about retail power \nuse. Any curtailments directed by PJM support the reliable operation of the wholesale \nmarket and power grid. PJM does not operate retail markets or local infrastructure. IRAS \ncurtailments are for the sole purpose of protecting wholesale market reliability by curtailing \ncustomers that have not procured through their LSEs the necessary capacity in the \nwholesale market. The focus of the IRAS Filing is regional resource adequacy and the \nregional capacity markets. An attempt by a state to regulate such matters would unlawfully \nintrude on an area subject to federal jurisdiction and would be preempted.18 \nPJM’s attempt to manufacture unneeded and inappropriate state involvement in \noperating the wholesale energy markets confuses rather than clarifies the jurisdictional \nboundaries. Allowing states to perform the role proposed in the IRAS Filing (and the \nallocation function in the RBP Filing)19 is, under Hughes, an abdication of the RTO’s \nresponsibility under federal law.20 \nThe case for federal jurisdiction is stronger in the IRAS case than it was in EPSA. The \nIRAS case concerns the consequences of the failure to procure capacity under proposed \ncapacity market rules. The IRAS Filing should provide rules for curtailment that are a \n \n17  \nSee DCC at 8 (“IRAS seeks to prescribe resource procurement and curtailment requirements for \nretail customers within the PJM region.”). \n18  \nSee Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 163 (2016) (“We agree with the Fourth \nCircuit’s judgment that Maryland’s program sets an interstate wholesale rate, contravening the \nFPA’s division of authority between state and federal regulators. As earlier recounted, … the FPA \nallocates to FERC exclusive jurisdiction over ’rates and charges . . . received . . . for or in connection \nwith’ interstate wholesale sales. §824d(a). Exercising this authority, FERC has approved the PJM \ncapacity auction as the sole rate setting mechanism for sales of capacity to PJM, and has deemed \nthe clearing price per se just and reasonable”). \n19  \nSee RBP Order at PP 150–157. \n20  \nSee id."},{"page":10,"startToken":3201,"endToken":3520,"text":"- 10 - \ncondition of taking wholesale service when the data center load has not procured capacity \nrequired for it to be served reliably. The purpose of the IRAS is to address the particular \nand extraordinary demands related to resource adequacy and the capacity market \nattributable to the rapid interconnection of data centers in the PJM Region. The Supreme \nCourt held that the Commission has preempted state action related to the capacity market \nrules.21 Data centers are receiving wholesale sales along with the associated terms and \nconditions of such sales from PJM through Load Serving Entities. \nPJM’s attempt to justify its incomplete proposal based on an incorrect jurisdictional \nanalysis and to instead rely on speculation about actions that states may take is insufficient \nto support the IRAS Filing as just and reasonable. For all these reasons, PJM’s approach is \nunjust and unreasonable. The IRAS Filing should be rejected for that reason. \nC. The IRAS Filing Has Not Been Shown to be Just and Reasonable. \nPJM’s Answer ignores or fails to adequately address the issues raised by the Market \nMonitor. These issues include: PJM’s failure to support its policy of interconnecting new \nlarge loads when there is not capacity to serve them; PJM’s failure to include the locational \nconstraints that are an essential feature of PJM’s capacity market; PJM’s failure to \nappropriately or consistently define the capacity that can meet the data center obligation to \nbring their own new capacity; PJM’s unjust shifting of ELCC risk to other customers; and \nPJM’s failure to support its definition of large load; PJM’s proposal to interrupt IRAS \ncustomers who paid for capacity before demand side resources who sold capacity.  \n1. PJM Fails to Justify Its Failure to Recognize Locational Constraints. \nLocational constraints are core to the PJM capacity market construct. PJM failed to \naddress the concerns raised by the stakeholders about the lack of locational constraints in \n \n21  \nSee 578 U.S. 150, 163."},{"page":11,"startToken":3520,"endToken":3887,"text":"- 11 - \nthe RBP and IRAS Filings.22 Modeling locational constraints in the capacity market is \nessential. Rules that ignore and exclude locational constraints cannot ensure reliability, \ncannot incent investors to site new generation where it is most needed, and do not protect \nexisting customers from the increased costs caused by data center load. The RBP and IRAS \nFilings do not accomplish PJM’s two central stated objectives: provide reliability and \nprotect customers from increased costs related to data centers.23  \nPJM argues that locational constraints should be ignored for two reasons: PJM \ncannot accurately predict transmission topography 15 years into the future; and PJM’s \ndeliverability analysis at the time of unit interconnection is a substitute for the CETO/CETL \nanalysis. Neither argument is correct or supportable. \nThe fact that PJM cannot accurately predict transmission topography 15 years in \nadvance is not an excuse for ignoring the core locational feature of the capacity market. \nRequiring that the generation be located electrically close to the data center load would be a \nreasonable approach that would resolve the basic issue. PJM ignores that option.  \nPJM repeated the clearly incorrect and unsupported argument that the deliverability \ntest required of all capacity resources means that “there does not need to be any locational \nrequirement for BYONC.”24 If PJM’s argument were correct, there would never be a need \nfor the LDA CETO/CETL analysis. Of course, PJM conducts the CETO and CETL analysis to \nensure that, for each LDA, the sum of the internal capacity in each LDA and the ability to \nimport capacity is enough to meet the reliability criterion for each modeled LDA. PJM’s \n \n22  \nPPL correctly highlighted that “allowing BYONC generation to be sited anywhere on the system, \nwithout regard to its proximity to the load it offsets, will not eliminate resource adequacy risk so \nmuch as convert generation-related constraints into transmission-related constraints. See PPL \nProtest at 20; ODEC asked for clarification on how locational resource adequacy would be \nimpacted given that “[PJM] appears to allow a New Large Load in one zone to be supported by \nBYONC located in another zone.” See ODEC’s Protest at 9. \n23  \nSee IRAS Filing at 5–6. \n24  \nSeptember 23rd Answer at 38."},{"page":12,"startToken":3887,"endToken":4182,"text":"- 12 - \nassertion is simply wrong. The deliverability study does not obviate the need for the \nCETO/CETL local resource adequacy study as the almost 20 year history of the locational \ncapacity market demonstrates.  \nAllowing data centers to contract with generation outside a constrained region \nreduces reliability for existing customers inside the constrained region. Under PJM’s IRAS \nFiling, data center load could be contracted with capacity located outside the constrained \nLDA that cannot meet the load in the constrained LDA and would not be subject to \ncurtailment. Higher load within the constrained region without offsetting generation within \nthe constrained region means there may be times when there is not enough capacity to \nserve that load. PJM fails to state what load would be curtailed under those conditions. \nIgnoring locational issues simply shifts the costs and risks of resolving the \npredictable consequences of meeting data center load to other customers. \nThe fact that PJM ignores the fundamental locational element of the PJM Capacity \nMarket and all the resultant negative consequences means that the PJM IRAS Filing is not \njust and reasonable. \n2. PJM Fails to Address Inconsistent Definitions of Qualifying Capacity \nThe Market Monitor raised concerns regarding the proposed BYONC gating criteria \nincluding the inconsistent definitions of capacity that can be used to satisfy the \nrequirements to meet the data center load in the IRAS Filing and the RBP Filing, the \nproposed definition of new, allowing inferior capacity and shorter term capacity.25  \nIn the September 23rd Answer, PJM fails to address any of the concerns raised by the \nMarket Monitor.  \nPJM’s proposed BYONC gating criteria allow previously cleared capacity to count as \nnew and qualify as BYONC. PJM argues at 40 that “An advantage of PJM’s approach is that \n \n25  \nSee IMM Protest at 18–20."},{"page":13,"startToken":4182,"endToken":4494,"text":"- 13 - \nCapacity Resources ready to participate in RPM and commit to provide capacity are not \ndisincentivized to do so while they wait for the BYONC marketplace to develop.” These \npreviously cleared resources are ready to commit and provide capacity because they were \nalready committed. While PJM states at 44 “Allowing existing Capacity Resources to \ncontract with New Large Loads would not solve the problem that the BYONC scheme is \ndesigned to address,” the PJM IRAS Filing allows existing resources to be repackaged as \nnew. The IRAS Filing allows previously cleared resources to qualify as BYONC but would \nnot address the resource adequacy shortfall and would result in the shifting of risk and \ncosts to LSEs and their customers. \nPJM’s IRAS Filing violates the fundamental concept of BYONG that data centers \nneed to bring new capacity and not remove existing capacity from the capacity market and \ncannibalize existing capacity resources. For that reason, the IRAS Filing is not just and \nreasonable. \n3. PJM Unjustly Shifts Generators’ ELCC Risk to Other Customers. \nPJM proposes to set a final and unchangeable ELCC value, and therefore a fixed \nUCAP MW, for each BYONC arrangement at the level for which the BYONC first cleared.26 \n27 The ELCC rating used to establish the initial UCAP value will be in place for up to 15 \nyears. PJM responds (at 45) that recognizing changes in the actual ELCC values would \ncreate uncertainty in the contractual arrangement and therefore undermine the incentive to \nenter into such a contractual arrangement. Ignoring the uncertainty does not make it go \naway. The IRAS Filing will shift the risk to customers. PJM misunderstands its role. PJM’s \nrole is not to create artificial incentives to allow the entry of data center load. If PJM \n \n26  \nSee IMM Protest at 20. \n27  \nSee IRAS Filing, Attachment A–(Marked Tariff), OATT Attachment DD-4 §§ VII(i)(i)–(ii)."},{"page":14,"startToken":4494,"endToken":4843,"text":"- 14 - \ncontinues to believe in its flawed ELCC model it should not create arbitrary and \ndiscriminatory exceptions to the ELCC rules. \nUnder the IRAS Filing, the BYONC generators’ revenues will change with the ELCC \nvalue. However, the IRAS Filing exempts the BYONC generator and the data center from \nthe risk of a reduced UCAP MW value and the requirement to make up any shortfall if the \nELCC decreases. Under the PJM rules, neither the capacity resource nor the data center load \nhas an obligation to cover the short position. This creates a reliability risk when the ELCC \ndecreases and the result is a capacity shortfall. The load of the data center in the BYONC \ncontract is no longer covered.  \nIf the ELCC decrease is significant, PJM will need to purchase additional capacity to \nmeet its reliability objective. Other PJM customers will pay for that additional capacity. \nOther PJM customers will bear the risk and the associated costs. \nThe fact that the IRAS Filing would arbitrarily freeze ELCC values and shift the risk \nof actual ELCC changes to other customers makes the IRAS proposal unjust and \nunreasonable. \n4. PJM Fails to Support the 50 MW Threshold. \nPJM did not respond to the Market Monitor’s demonstration that the proposed \ndefinition could exclude significant amounts of data center load. Table 1 in the Market \nMonitor’s Protest (at 31) shows that 28.5 percent of expected data center load is below the \n50 MW threshold. Grouping by data center campus, 6.9 percent of expected data center \ncampus load is below the 50 MW threshold. It remains unclear how much of the data center \nload would qualify as large load under PJM’s affiliate and one mile proximity rules. PJM \nincluded the one mile rule to reduce the ability to game the rules by building a group of \nsmaller data centers. A more efficient and precise path to this end is to simply lower the \nthreshold. \nIn addition to missing a significant level of data center load, PJM’s arbitrary \ndefinition of large data center load is outdated. The rapid advancements in the data center"},{"page":15,"startToken":4843,"endToken":5200,"text":"- 15 - \nbuilding technology mean that new data centers are going to be increasingly prefabricated \ncontainerized computing units that can be built quickly and are scalable.28 29 According to \nmarket reports, small data centers that are typically 5 MW or less are expected to grow at a \nhigher rate than the larger data centers.30 These data centers are considerably smaller than \nthe 50 MW threshold proposed by PJM. \n5. PJM’s One Mile Radius Criterion is Unworkable. and Unreasonable. \nThe PJM IRAS Filing includes the following definition of Large Load:  \n‘Large Load’ shall mean end-use customer(s) load that has a \ncumulative peak load of 50 megawatts or greater at a single \nelectrical site behind one or more points of interconnection, where \nfor configurations involving multiple affiliated load facilities or \nmultiple points of interconnection with affiliated load facilities \nbehind them, all affiliated load facilities within a one-mile radius \nwill be considered a single electrical site as further described in \nthe PJM Manuals.31 \nPJM does not provide any details regarding the implementation of the one-mile \nradius rule. PJM fails to explain or provide any criteria needed to uniformly and fairly \n \n28  \nSee Fortune Business Insights, “Modular Data Center Market Size, Share & Industry Analysis,” \n<https://www.fortunebusinessinsights.com/industry-reports/modular-data-center-market-100504>. \n29  \nSee “The Startup That Built Open AI’s Biggest Data Center Is Now Making Tiny Ones,” published \nin Wall Street Journal, September 17, 2026. <https://www.wsj.com/tech/ai/the-startup-that-built-openais-\nbiggest-data-center-is-now-making-tiny-ones-71f36a4f>.  \n30  \nSmall data centers are expected to grow at the highest Compounded Annual Growth Rate (CAGR) \nduring the forecast period, as they are more cost-effective to build, operate, and maintain compared \nto large-scale facilities. They require less initial investment in real estate, equipment, and \ninfrastructure, making them an attractive option for businesses with limited budgets or smaller IT \nrequirements. Small facilities typically operate below 5 megawatts and support localized or edge \nworkloads. They offer lower capital requirements but limited scalability. This segment is often \ndeployed in regional or distributed architectures. See Fortune Business Insights, Data Center \nMarket Size, Share & Industry Analysis. <https://www.fortunebusinessinsights.com/data-center-market-\n109851>.  \n31  \nPJM IRAS Filing, Proposed RAA, Definitions—Large Load."},{"page":16,"startToken":5200,"endToken":5425,"text":"- 16 - \napply such a rule. For instance, if there are four affiliated data centers in an area as depicted \nin Figure 1, there are many possibilities for grouping the data centers under a one-mile \nradius rule. Each circle in Figure 1 represents an area with a one-mile radius centered at a \ndata center. Data center A is within one mile of D, B is within one mile of C, C is within one \nmile of B and D, and D is within one mile of A and C. PJM also has not defined the term \n“affiliated load facilities.” Data center campuses and individual data center buildings can \nbe populated by data centers with unaffiliated ownership but may be considered affiliated, \nor part of the single data center, because they are co-located on the same campus or in the \nsame building. \nA data center campus includes multiple data centers and the data centers may or \nmay not be grouped together under PJM’s one-mile radius rule. \nFigure 1 Potential groupings of five affiliated data centers under the one mile radius rule \n \n6. PJM Has Not Demonstrated That IRAS Should Be Called Before \nExisting Demand Response Resources. \nPJM has not provided and cannot provide a good explanation of why it is reasonable \nto curtail eligible New Large Loads through IRAS before deploying existing, compensated \nA\nD\n    B\n     C"},{"page":17,"startToken":5425,"endToken":5763,"text":"- 17 - \nDemand Resources that have been sold in the capacity market specifically to provide \nreliability service. PJM now justifies the proposed sequencing on the grounds that New \nLarge Loads that have not brought sufficient new capacity should bear the “initial \noperational consequences” of their capacity shortfall, that calling Demand Resources first \nwould weaken incentives to bring new capacity, and that greater use of Demand Resources \ncould result in “fatigue.”32 These arguments are not consistent with the basic rules and logic \nof the PJM Capacity Market. In asserting these strained rationales, PJM appears to forget \nthat these problems could be avoided by not permitting significant data center loads to \ninterconnect without matching new generation. PJM should not create the problem in the \nfirst place. However, having created the problem, PJM should follow its logic through to \nthe end. PJM fails to do so. For example, of course it would provide a stronger incentive to \nIRAS load to be curtailed before demand resources. But that is not relevant to the “logic” of \nIRAS load created by PJM. IRAS load is data center load without matching generation that \nis nonetheless required to pay for capacity. It would also create a stronger incentive to \ncurtail IRAS load prior to shortage pricing or whenever prices exceed $500/MWh. PJM’s \nargument about incentives proves too much. It does not stand the test of simple PJM \ncapacity market logic. IRAS load pays for capacity. Demand resources supply capacity that \nIRAS load pays for. \nPJM's principal rationale is that Eligible New Large loads have not brought new \ncapacity and therefore should not receive the “capacity benefit” of Demand Resources.33 \nPJM ignores the salient fact that these IRAS loads are required to pay for capacity. PJM fails \nto explain what not bringing new generation had to do with being interrupted before \ndemand resources that PJM has already procured, compensated, and obligated to provide \nreliability service. Demand Resources are Capacity Resources precisely because PJM has \n \n32  \nSeptember 23rd Answer at 31–32. \n33  \nId. at 31."},{"page":18,"startToken":5763,"endToken":6074,"text":"- 18 - \ndetermined that their committed load reductions can contribute to satisfying the system's \nresource adequacy requirement. PJM’s argument is a subjective judgement that is not based \non the facts of the capacity market rules and the IRAS rules proposed by PJM. \nPJM's proposed framework requires an IRAS load to pay for capacity while \nproposing to curtail that load before calling on the Demand Resources whose sale of \ncapacity is included in the cost of capacity.34 \nPJM relies on its treatment of IRAS as analogous to the curtailment of non firm \ntransmission service.35 That analogy is misplaced. Non firm transmission service is non firm \nbecause the customer did not pay for firm. IRAS loads pay for capacity at the market price. \nIt is not non firm capacity. \nThe September 23rd Answer also confirms an important limitation of the proposed \nsequencing. PJM acknowledges that its dispatchers have discretion under Manual 13 to \nimplement emergency procedures “in whatever order is required to ensure system \nreliability” and to exit those procedures in a different order.36 Thus, the tariff's nominal \nstatement that the curtailment of IRAS load precedes Pre-Emergency Load Management \ndoes not establish an actual, predictable operational hierarchy. PJM should establish \nobjective criteria to permit the Commission and market participants to understand when \nIRAS will actually be curtailed and when Demand Resources will be called. The current \nproposal does not do so. The level of uncertainty that PJM would impose on both IRAS and \nDemand Resources is unacceptable and inconsistent with an orderly market. \nPJM’s reliance on asserted Demand Resource “fatigue” illustrates the illogic of PJM’s \nposition. PJM argues that repeated calls on Demand Resources increases their opportunity \ncosts and could reduce future participation, noting that PJM relies on 7,641 MW of Demand \n \n34  \nSee IMM Protest at 17. \n35  \nSee September 23rd Answer at 34. \n36  \nSee id. at 33."},{"page":19,"startToken":6074,"endToken":6392,"text":"- 19 - \nResources for the 2027/2028 Delivery Year.37 If Demand Resources cannot provide the \nreliability that they sell in the capacity market then they are not viable capacity resources. \nPJM does not allow for fatigue at generating units as an excuse for failure to perform. \nThe PJM response to Constellation is irrelevant to the question.38 Both IRAS load and \nDemand Response load have made decisions that are in their own interests. IRAS load has \nto pay for capacity because it failed to bring its own new capacity. Demand Resources sell \ncapacity because they believe it to be profitable. It is not PJM’s role to ensure that the \nexpectations of either group are met. If Demand Resources are called on more frequently as \na result of the system conditions that result from PJM decisions, such resources can decide \nif continuing to sell capacity remains profitable. \nPJM’s argument here is beyond ironic. PJM’s concern for native loads ignores the \nfact that PJM’s entire RBP/IRAS construct imposes data center costs on native loads.39  \nPJM's invocation of the Ratepayer Protection Pledge does not resolve this issue. PJM \nstates that IRAS is consistent with the Pledge because it places the “reliability and cost \nburden” of a New Large Load’s failure to bring new capacity on that New Large Load.40 \nBut the Pledge cannot substitute for a demonstration that the proposed tariff actually \nproduces that result. If IRAS causes PJM to commit higher cost generation, maintain \nreserves using more expensive resources, or incur scarcity pricing before deploying an \navailable Demand Resource, the resulting costs will be borne by existing customers even \nthough the underlying IRAS load is the party that caused the incremental capacity \nrequirement. The fact that the IRAS load itself is curtailed does not establish that existing \n \n37  \nId. at 36–37. \n38  \nSee id. at 34–37 \n39  \nSee id. at 35. \n40  \nId. at 35."},{"page":20,"startToken":6392,"endToken":6692,"text":"- 20 - \ncustomers are economically insulated from the consequences of that load’s capacity \nshortfall.  \nPJM’s approach to curtailing IRAS load is subjective and illogical and ignores the \nobligations and commitments created by the capacity market. For all these reasons, PJM’s \nIRAS Filing should be rejected because it is not just and reasonable. \n7. Interconnecting Large Data Center Loads Without Generation \nDecreases Reliability and Increases Cost to Other Consumers. \nPJM makes the unsupported assertion that “calling for IRAS load reductions before \npre-emergency load management” completely mitigates the resource adequacy risk of \ninterconnecting new large loads without matching capacity and “protects native loads from \nthe cost and reliability impacts of such new large loads.”41  \nPJM’s asserts that, from a reliability perspective, adding large data center load to the \nPJM system with curtailment provisions is the same as not adding large data center load or \nadding data center load with matching generation. PJM provides no analytical support for \nthis claim. PJM’s operational history contradicts PJM’s claim. Higher levels of 8,760 hour \nload in PJM without matching generation, net of accounting for curtailments, increases the \nrisk of unanticipated operational events. The higher the load, the larger the risk. \nHigher capacity factors lead to a need for higher maintenance outages and a higher \nrisk of unforced outages and more units reaching emissions limits. \nLarge data center loads consume energy around the clock. Existing generating units \nare required to run more and therefore have higher capacity factors. Higher capacity factors \nmean an increased frequency of maintenance outages and a higher risk of forced outages.42 \n \n41  \nId. at 31. \n42  \nSee Additional Large Load Challenges: Peak vs Shoulder Seasons & Gen Outage Scheduling, \nPresented \nat \nCIFP \nEducation \nSession, \n(October \n21, \n2025) \n<https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-lla/2025/20251021/20251021-item-04---additional-large-load-\nchallenges---pjm-presentation.pdf>."},{"page":21,"startToken":6692,"endToken":7000,"text":"- 21 - \nMany older generating units in the PJM system have high forced outage rates and low \ncapacity factors. Prior to the introduction of ELCC based accreditation, the forced outage \nrates of these generators were directly reflected in their accredited UCAP values. In the \nELCC based accreditation model, a generator with a high forced outage rate outside critical \nhours will not generally receive a lower accredited UCAP value, meaning that PJM counts \non this generation as available to serve the data center load when clearing capacity \nauctions. Higher failure rates for these generators means reduced reliability for the PJM \nsystem and other customers. \nData Center load presents a unique operational challenge unlike dispersed \ntraditional loads. Unlike dispersed traditional load, data center load is concentrated. If a \nlarge data center load disconnects from the PJM system, losing hundreds of MW at a single \nsite creates substantial challenges for grid operators.43 PJM has just proposed reliability \nstandards to manage large load disconnection events. NERC and PJM are still developing \neffective ways to manage a grid with highly concentrated loads. PJM lacks relevant \nexperience. The implications of highly concentrated load for reliable grid operation are not \nyet fully understood.44 Allowing the interconnection of large loads without matching \ngeneration and with only curtailment provisions ignores the other reliability implications of \nthis highly concentrated large load. \n \n43  \nSee PJM. July 22, 2026 Dominion Load Transfer Event, presented at Operating Committee, \n<https://www.pjm.com/-/media/DotCom/committees-groups/committees/oc/2026/20260806/20260806-item-\n05---dominion-july-loss-of-load-event---presentation.pdf> (August 6, 2026).  \n44  \nNERC has identified that large load ride-through and ramping characteristics are a risk to BPS \nreliability and that the lack of predictable ride-through performance for large loads is a reliability \ngap. See NERC “Draft Large Load Disturbance Performance, Impact Analysis and Ride-Through \nRecommendations”, (December 10, 2026) <https://www.nerc.com/our-work/white-papers>."},{"page":22,"startToken":7000,"endToken":7368,"text":"- 22 - \n8. PJM’s Proposal Will Negatively Affect Reliability.  \nThe essential requirement for scheduling planned outages is substantially lower load \nduring off peak seasons. Lower load outside peak summer and winter periods, typically \nduring the shoulder months, provides an opportunity to operate the grid reliably with less \navailable generation. PJM schedules planned maintenance outages during this period. As \nthe load without matching generation increases in PJM, PJM operations is and will be \nchallenged to meet higher loads with lower generation capacity due to planned outages. \nPJM acknowledged this important concern. During the Critical Issue Fast Path Education, \nPJM stated that “if load continues to increase 8,760 hours/year, and the BRA clears the IRM, \neither: Future generation outages may be denied/deferred to the following season to avoid \nemergency procedures; Not a good option - Units may then be less reliable or become an \nUnplanned Outages if Planned/Maintenance Outages requests are denied.”45  \nIn addition to the scheduling of outages, when units reach their emission limits they \nare no longer available to meet 8,760 hour load. There are multiple generating units in PJM \ntoday that are subject to emission restrictions.46 In some cases, the restrictions limit the total \noutput within a rolling calendar year to only a few hours. There are other restrictions that \nhave not been previously binding that have become binding and more will become binding \nas unit capacity factors increase. These emission restrictions are not considered in the \nresource adequacy models and capacity accreditation. Under PJM’s ELCC based \n \n45  \nSee Additional Large Load Challenges: Peak vs Shoulder Seasons & Gen Outage Scheduling, \nPresented at CIFP Education Session, October 21, 2025 Additional Large Load Challenges: Peak vs \nShoulder Seasons & Gen Outage Scheduling <https://www.pjm.com/-/media/DotCom/committees-\ngroups/cifp-lla/2025/20251021/20251021-item-04---additional-large-load-challenges---pjm-\npresentation.pdf>. \n46  \nThe Market Monitor calculates opportunity costs for generation units subject to federal or state \nimposed emissions restrictions if owners request it and provide the required data. The Market \nMonitor calculated opportunity cost adders for 172 generators in the first six months of 2026. See \n2026 Quarterly State of the Market Report for PJM: January through June, Section 8 Environmental and \nRenewable Energy Regulations (August 13, 2026)."},{"page":23,"startToken":7368,"endToken":7715,"text":"- 23 - \naccreditation, a 100 UCAP MW capacity resource with an emission restriction is treated the \nsame as a 100 UCAP MW capacity resource without an emission restriction. However, a 100 \nUCAP MW emission restricted resource cannot meet the 8,760 data center load as a result of \nthe emission restrictions. Additional data center load without matching generation will \nincrease capacity factors for these emission restricted, but committed, capacity resources \nand will eliminate their energy output after the emissions limits are reached.  \nAs a result, adding data center loads with no matching generation will decrease \nreliability for the PJM system and for all other customers.  \nCurtailment provisions do not address these issues. PJM has failed to define \ncurtailment rules. PJM has not explained how it could curtail highly concentrated large \nloads without significantly affecting reliable grid operation. Under PJM’s proposal, PJM \nwould not direct EDCs to curtail specific data center loads or use CSPs to do so. EDCs \nwould have to determine which data center loads to curtail. However, EDCs do not have \nthe visibility into grid conditions, transmission constraints, voltage limits, or spillover \neffects that are required in order to make informed curtailment decisions in order to \nmaintain system reliability. \nPJM’s current resource adequacy studies would not account for lower reliability \nresulting from higher continuous load. PJM’s resource adequacy models are not forward \nlooking, but reflect historical resource performance. The models cannot assess PJM’s \nresource adequacy under higher load scenarios because generator performance at higher \ncapacity factors is not known and because PJM does not know how EDCs would handle \ncurtailments. PJM has not explained how PJM would model the large load with curtailment \nin the resource adequacy simulations. PJM’s assertion that adding load subject to \ncurtailment would not decrease reliability is not supported by facts or analysis. PJM would \nnot account for the secondary impact of higher load on maintenance and unforced outages. \nPJM’s assertions are not supported. Under PJM’s IRAS Filing, PJM could not reliably \nserve PJM’s organic load. For all these reasons, PJM's IRAS proposal is not just and \nreasonable and should be rejected."},{"page":24,"startToken":7715,"endToken":7983,"text":"- 24 - \nII. MOTION FOR LEAVE TO ANSWER \nThe Commission’s Rules of Practice and Procedure, 18 CFR § 385.213(a)(2), do not \npermit answers to protests, answers, or requests for rehearing unless otherwise ordered by \nthe decisional authority. The Commission has made exceptions, however, where an answer \nclarifies the issues or assists in creating a complete record.47 In this answer, the Market \nMonitor provides the Commission with information useful to the Commission’s decision \nmaking process and which provides a more complete record. Accordingly, the Market \nMonitor respectfully requests that this answer be permitted. \nIII. CONCLUSION \nThe Market Monitor respectfully requests that the Commission afford due \nconsideration to this answer as the Commission resolves the issues raised in this \nproceeding. \n \nJoseph E. Bowring \nIndependent Market Monitor for PJM \nPresident \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n \nRespectfully submitted, \n \nJeffrey W. Mayes \n \nGeneral Counsel \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n \n47 \nSee, e.g., PJM Interconnection, L.L.C., 119 FERC ¶61,318 at P 36 (2007) (accepted answer to answer \nthat “provided information that assisted … decision-making process”); California Independent \nSystem Operator Corporation, 110 FERC ¶ 61,007 (2005) (answer to answer permitted to assist \nCommission in decision-making process); New Power Company v. PJM Interconnection, L.L.C., 98 \nFERC ¶ 61,208 (2002) (answer accepted to provide new factual and legal material to assist the \nCommission in decision-making process); N.Y. Independent System Operator, Inc., 121 FERC ¶61,112 \nat P 4 (2007) (answer to protest accepted because it provided information that assisted the \nCommission in its decision-making process)."},{"page":25,"startToken":7983,"endToken":8096,"text":"- 25 - \n(610) 271‐8051 \njoseph.bowring@monitoringanalytics.com \n(610) 271‐8053 \njeffrey.mayes@monitoringanalytics.com \nPaul G. Scheidecker \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \npaul.scheidecker@monitoringanalytics.com  \nAlexandra Salaneck \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \nalexandra.salaneck@monitoringanalytics.com  \nJohn Hyatt \nSenior Economist \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \njohn.hyatt@monitoringanalytics.com \nDevendra R. Canchi \nSenior Analyst \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610) 271‐8050 \ndevendra.canchi@monitoringanalytics.com  \nDated: October 8, 2026"},{"page":26,"startToken":8096,"endToken":8161,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated at Eagleville, Pennsylvania, \nthis 8th day of October, 2026. \n \nJeffrey W. Mayes \nGeneral Counsel \nMonitoring Analytics, LLC \n2621 Van Buren Avenue, Suite 160 \nEagleville, Pennsylvania 19403 \n(610)271‐8053 \njeffrey.mayes@monitoringanalytics.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":1451,"startToken":0,"endToken":1370},{"p":4,"at":1451,"title":"I. ANSWER","method":"printed heading","endPage":4,"endAt":1462,"startToken":1370,"endToken":1372},{"p":4,"at":1462,"title":"A. Neither the IRAS Filing nor the Market Monitor’s Proposed Remedial","method":"printed heading","endPage":6,"endAt":904,"startToken":1372,"endToken":1986},{"p":6,"at":904,"title":"B. PJM Can File a Complete Proposal Consistent with the Pledge and Principles","method":"printed heading","endPage":10,"endAt":961,"startToken":1986,"endToken":3351},{"p":10,"at":961,"title":"C. The IRAS Filing Has Not Been Shown to be Just and Reasonable.","method":"printed heading","endPage":24,"endAt":8,"startToken":3351,"endToken":7716},{"p":24,"at":8,"title":"II. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":24,"endAt":626,"startToken":7716,"endToken":7809},{"p":24,"at":626,"title":"III. CONCLUSION","method":"printed heading","endPage":26,"endAt":0,"startToken":7809,"endToken":8096},{"p":26,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":26,"endAt":447,"startToken":8096,"endToken":8161}]}