{"document":{"slug":"rec-20261013-5331","title":"Motion for Reply and Reply of American Transmission Company LLC to Midcontinent Independent System Operator, Inc.'s 10/09/2026 Motion for Leave to Answer…","issued":"2026-10-13","accession":"20261013-5331","docket":"ER26-3531-000","group":"ATC large-load planning revisions (Attachment FF-ATCLLC)","filer":"American Transmission Company LLC","kind":"answer","file":"sources/filings/text/20261013-5331_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261013-5331","tier":"record","sha256":"6d12a7ea519a9f93a9e91b608627f03d9b4499e3d63d703a351cb97999495f2b","pages":10,"tokens":3056,"emptyPages":[],"textThemes":["study","cost","registry"]},"pages":[{"page":1,"startToken":0,"endToken":249,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nAmerican Transmission Company LLC \n \n \n          Docket No. ER26-3531-000 \n \n \nMOTION FOR REPLY AND REPLY OF  \nAMERICAN TRANSMISSION COMPANY LLC \n \n \nPursuant to Sections 212 and 213 of the Commission’s Rules of Practice and Procedure,1 \nAmerican Transmission Company LLC (ATC) by its corporate manager, ATC Management Inc. \n(collectively, ATC) hereby files this Motion for Leave to Reply and Reply to the Motion for \nLeave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (MISO) \nfiled on October 9, 2026.  On August 17, 2026, ATC filed its proposed revisions to Attachment \nFF-ATCLLC of MISO’s Open Access  Transmission, Energy and Operating Reserve Markets \nTariff (Tariff) in response to the Commission’s Show Cause Order.2  ATC’s proposed revisions \naddress the immediate need for large load integration in the ATC service territory and are just \nand reasonable and should be accepted without hearing or settlement proceedings with an \neffective date of October 17, 2026.   \nMISO does not dispute that ATC’s local planning has functioned successfully without \nissue for two decades or that differences within the region are commonplace, and MISO provides \nno evidence that ATC’s proposal will cause harm.  Instead, MISO avers that ATC’s proposal may \ndiffer from MISO’s processes at some point in the future that may create implementation and \n \n1 18 C.F.R. § 385.212-213 (2026). \n2 Midcontinent Indep. Sys. Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal \nPower Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”)."},{"page":2,"startToken":249,"endToken":679,"text":"2 \n \nreliability challenges.3  ATC appreciates MISO's recognition that immediate implementation of \nAttachment FF-ATCLLC addresses an important near-term need.  Approval of Attachment FF-\nATCLLC should not be temporary or conditioned on future filings; however, ATC remains \ncommitted to working with MISO through the stakeholder process and evaluating any future \nCommission-approved requirements to determine whether further modifications are warranted.  \nThe issue before the Commission in this proceeding is whether ATC's proposed Attachment FF-\nATCLLC is just and reasonable, not whether a future MISO proposal might ultimately be \npreferred.  \nI. \nREPLY \nA. \nFPA Section 205 Requires that the Commission Accept ATC’s Proposal if It is \nJust and Reasonable.  \n  \nIn this Section 205 proceeding, the Commission must evaluate whether ATC’s proposed \nchanges to its Attachment FF-ATCLLC are just and reasonable.  It is not a question whether \nthere are other just and reasonable alternatives or whether other parties suggest that there are \nchanges to the proposal that they would prefer.4  ATC’s proposed changes to Attachment FF-\n \n3 MISO Answer at 4. \n4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,210 (2026) (declining to address the alternative \nproposals raised by intervenors because proposed reforms were just and reasonable); Entergy Svcs., Inc. v. \nFERC, 40 F.4th 689, 701–02 (D.C. Cir. 2022) (finding that the Commission is not required to choose the \nbest solution, only a reasonable one.); Cal. Indep. Sys. Operator Corp., 128 FERC ¶ 61,265, at P 21 \n(2009) (“Under the [FPA], the issue before the Commission is whether the [independent system \noperator’s] proposal is just and reasonable and not whether the proposal is more or less reasonable than \nother alternatives.”); Southwest Power Pool, Inc., 193 FERC ¶ 61,198 (2025) (Accreditation methodology \nneed not predict the future with perfect accuracy, rather the filing party need only show that the proposed \nmethodology would be sufficiently accurate so as to produce just and reasonable results.); Petal Gas \nStorage, L.L.C. v. FERC, 496 F.3d 695, 703 (D.C. Cir. 2007) (“[The Commission] is not required to \nchoose the best solution, only a reasonable one.”); See PJM Interconnection, L.L.C., 169 FERC ¶ 61,038, \nat P 12 (2019) (citing OXY USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (finding that under the \nFPA, as long as the Commission finds a methodology to be just and reasonable, that methodology “need \nnot be the only reasonable methodology, or even the most accurate one”)); Cities of Bethany v. FERC, 727 \nF.2d 1131, 1136 (D.C. Cir. 1984) (when determining whether a rate was just and reasonable, the"},{"page":3,"startToken":679,"endToken":981,"text":"3 \n \nATCLLC are just and reasonable because they (1) provide an immediately implementable path \nforward for integrating large loads, consistent with ATC’s current practices and responsive to the \nrequirements in the Show Cause Order, (2) provide certainty for large-load projects already \nunderway in ATC’s footprint, (3) contain urgently needed protections against cost shifting among \nwholesale customers, and (4) align with Public Service Commission of Wisconsin retail tariff \nrequirements.   \nMISO agrees that its Show Cause Order compliance processes are working their way \nthrough the stakeholder process and could take many months to be final.  Yet MISO asserts that \nATC’s Attachment FF-ATCLLC may be problematic at some point in the future.  For example, \nMISO asks the Commission to allow ATC’s proposed requirements only where MISO has no \ncorresponding requirements,5 but MISO has no corresponding requirements that are effective to \ndate.  Even if MISO develops corresponding requirements in the future, MISO only speculates \nthat ATC’s requirements will cause harm.6  Alternatively, MISO asks the Commission to allow \nATC to impose stricter requirements in cases where MISO has an established framework.7  \nAgain, there is no established framework and any conjecture as to what might be stricter is \nunknown.8  The Commission should not judge ATC’s Attachment FF-ATCLLC planning \nframework based on MISO’s speculation that ATC’s proposal may conflict with MISO’s \nprocesses in the future and that such conflict will cause harm.  If a future conflict arises that may \ncause harm, it can be addressed at that time.   \n \nCommission properly did not consider “whether a proposed rate schedule is more or less reasonable than \nalternative rate designs”).   \n5 MISO Answer at 2. \n6 Id. at 4 (suggesting that ATC’s proposal “ultimately could create a less stringent standard.”).  \n7 Id. at 2. \n8 Id. at 4 (asserting that ATC’s framework “could result in ambiguity and uncertainty”)."},{"page":4,"startToken":981,"endToken":1294,"text":"4 \n \nThus, for purposes of Section 205 approval of ATC’s filing, MISO has not presented an \nalternative proposal that the Commission could consider.  A speculative future conflict does not \njustify delaying ATC’s requested October 17, 2026 effective date for revisions that are \nindependently just and reasonable and responsive to the Show Cause Order.   \nB. \nConditioning ATC’s Proposed Changes to Attachment FF-ATCLLC on \nCompliance with Yet-Unknown Uniform Base-Level Rules Without a \nDemonstrable Need Will Impose Unnecessary Costs in ATC’s Footprint and \nUndermine Policy Goals to Advance AI. \n \nMISO argues that uniform base-level rules are needed to address reliability concerns and \nthat if ATC had different standards, it would create operational risk.9  MISO has asserted \npotential reliability concerns but has not demonstrated any specific reliability deficiency, \noperational limitation, or planning concern that would result from ATC's proposed framework.  \nFrom a planning standpoint, there has been and will continue to be significant coordination \nbetween ATC and MISO regarding the planning of the system.  Indeed, all of ATC’s projects \nmust be evaluated in MISO’s regional MTEP process—either through the regular planning cycle \nor through the Expedited Project Review (EPR) process.10  That will not change. \nFrom an operations standpoint, it should be abundantly clear that ATC's proposal does \nnot prevent MISO from obtaining information necessary to maintain reliable system \noperations.  ATC is not proposing to displace otherwise applicable MISO requirements \ngoverning load forecasting, telemetry, real-time information, or operational visibility.11  The \n \n9 Id. at 4.  \n10 ATC Answer at 2, 9.  \n11 ATC’s proposed changes to Attachment FF-ATCLLC include language requiring ATC to “maintain \nadditional data monitoring, data retention, forecasting and design criteria in applicable ATCLLC Business \nPractices.”  ATC Transmittal Letter, Tab A, Redlined Attachment FF-ATCLLC, Section V.E.  While ATC \nmaintains its own visibility requirements necessary for its operations, ATC’s requirements will not impact \nMISO’s load forecasting, telemetry, real-time information, or operational visibility requirements."},{"page":5,"startToken":1294,"endToken":1731,"text":"5 \n \nmaterial differences addressed by Attachment FF-ATCLLC concern ATC’s local planning, study, \ninterconnection, and cost-allocation framework that are part of ATC’s local planning role, for \nwhich ATC has developed study-based criteria tailored to its system.  Attachment FF-ATCLLC \nwill not affect MISO’s ability to obtain the operational information needed to operate the \nregional system.   \nAttachment FF-ATCLLC was adopted to fulfill ATC’s state law mandate.  Under the \nWisconsin law that enabled ATC to be formed, ATC is not permitted to delegate its planning \nobligations under state law to any other entity.12  Since the initial approval of Attachment FF-\nATCLLC, the Commission has approved ATC’s proposed changes to comply with other major \nplanning orders without concern for operational risks.  In compliance with Order Nos. 890,13 and \n1000,14 the Commission approved (and MISO did not object) to ATC being the only transmission \nowner in the MISO footprint at that time to decline to integrate its local planning functions into \nMISO’s Attachment FF.15  \n \n12 ATC sought and thereafter became “a transmission company” which obligated ATC to engage in as “its \nsole purpose the planning, constructing, operating, maintain and expanding of transmission facilities, and \nthe providing of transmission service, to provide for an adequate and reliable transmission system that \nmeets the needs of all users that are dependent on the transmission system and that supports effective \ncompetition in energy markets without favoring any market participant.” Wis. Stat. § 196.485(ge) (2025) \n(emphasis added).   \n13 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, FERC Stats. \n& Regs. ¶ 31,241, order on reh’g, Order No. 890-A, FERC Stats. & Regs. ¶ 31,261 (2007), order on \nreh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ \n61,228 (2009), order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).   \n14 Midwest Indep. Transmission Sys. Operator, Inc., 147 FERC ¶ 61,127 at P 76 (2014) (Order 1000 \nCompliance rehearing order); Midwest Indep. Transmission Sys. Operator, Inc., 130 FERC ¶ 61,232, P 36, \non reh’g, 132 FERC ¶ 61,119, PP 20-22 (2010).  Midwest Indep. Transmission Sys. Operator, Inc., 123 \nFERC ¶ 61,165 (2008), order on reh’g, 127 FERC ¶ 61,169 (2009). \n15 Midwest Indep. Transmission Sys. Operator, Inc., 123 FERC ¶ 61,164 at P 124, n.113 (noting that ATC \ndeclined to integrate its local planning process into MISO’s Attachment FF and instead  engages in local \nplanning through a separate ATC-specific local planning process provided in Attachment FF-ATCLLC; \nMidwest Indep. Transmission Sys. Operator, Inc., et.al., 130 FERC ¶ 61,232 at PP 36-42 (accepting \nAttachment FF-ATCLLC with certain modifications); Midwest Indep. Transmission Sys. Operator, Inc.,"},{"page":6,"startToken":1731,"endToken":2103,"text":"6 \n \nContrary to MISO’s claims, Attachment FF-ATCLLC does not exceed the traditional \nbounds of ATC’s local planning criteria.  Large loads are retail customers of the local distribution \ncompanies in ATC’s footprint.  ATC’s planning for large loads interconnecting with the local \ndistribution companies on ATC’s system is fundamental to ATC’s local planning function and \nwill impact retail electric service in ATC’s footprint for many years to come.  Delegating that \nfunction to MISO is contrary to Wisconsin law and prior Commission orders, and would subvert \nATC’s obligations to its stakeholders.  \nMoreover, contrary to MISO’s claims, ATC has adequately addressed cost allocation in \nAttachment FF-ATCLLC to comply with state retail tariff requirements.  Differences in cost \nallocation policies have not been problematic in the past.  In the generation interconnection \ncontext, ATC has had different network upgrade cost allocation provisions from the rest of the \nMISO region with no negative impacts.16 \nMISO’s alleged harm is based on conjecture and dependent on tariff provisions that have \nnot yet been filed or accepted by the Commission.  ATC’s amendments to Attachment FF-\nATCLLC are supported by studies used in developing the planning criteria to address the needs \nof its system and will apply to large loads in its footprint.17  We are not aware of any similar \n \net.al., 132 FERC ¶ 61,119 at P 22 (2010) (order accepting compliance filing and noting that ATC’s \nprojects still must flow through MTEP.).  \n16 For several years, ATC had a roll-in cost allocation policy for generator interconnection network \nupgrades when MISO had adopted a participant funding methodology.  American Transmission Co. LLC, \n120 FERC ¶ 61,221 at P 17 (2007)(“We likewise find that the proposal of ATC to adopt a 100% \nreimbursement policy is just and reasonable. As long-recognized by the courts, different rate proposals \ncan be just and reasonable; there is no one correct method for calculating rates.”) order denying reh’g, \n123 FERC ¶ 61,065 (2008).  \n17ATC engaged specialized power system consultants to study large loads, including flicker analyses, \nrotor-swing modes, generator-shaft studies to develop ramp-rate, and voltage-ride-through requirements.  \nATC Answer at 7.  The proposed changes to Attachment FF-ATCLLC’s operating requirements are based \non these extensive studies and advance these proven large load processes developed over the past several \nyears."},{"page":7,"startToken":2103,"endToken":2385,"text":"7 \n \nstudies by MISO.  MISO is assuming that its requirements will be more stringent than ATC’s but \nthat remains unknown.  ATC’s studies were intended to build efficiencies in design, maintain safe \nand reliable service, and rein in costs.  Any perceived need for more stringent planning/operating \nrequirements is not supported by studies.  Without additional technical support, uniformity for \nthe sake of uniformity will add an unnecessary burden to large load customers in ATC’s footprint \nby requiring unnecessary and costly equipment requirements.  This poses the risk of driving up \ncosts for customers and undermining the administration’s policy goals for advancing AI (or super \nintelligence). \nATC has already committed to adjusting its processes, if necessary, as MISO’s \nrequirements develop through the stakeholder process.  It is unreasonable for MISO to suggest \nthat ATC should defer or condition its proposal because it may conflict with MISO’s future Show \nCause Order compliance filing.   \nC. \nThe Commission has Encouraged Individual Transmission Owners to Make \nSection 205 Filings to Address the Show Cause Order Requirements and to \nFacilitate AI Development.  \n \nAs the Commission noted in the Show Cause Order, ATC’s current Attachment FF-\nATCLLC includes an approved distribution-to-transmission interconnection process and a load \ninterconnection procedure, but it does not have procedures specific to large loads.18  ATC is \nfollowing the Commission’s directive in the Show Cause Order with proposed revisions in this \nfiling that are intended to fill that gap and to be tailored to work within the established \nAttachment FF-ATCLLC procedures.  The Commission has encouraged transmission owners to \n \n18  Show Cause Order at n. 75.  The Commission recognized that ATC has established procedures for \ninterconnection of large loads outside of the Tariff.  Id. at P 21, n. 77."},{"page":8,"startToken":2385,"endToken":2842,"text":"8 \n \npropose tariff revisions to address issues pursuant to their applicable Section 205 filing rights.19  \nATC’s proposal here is intended to comply with the Show Cause Order and formalize what ATC \nis already doing in its footprint to manage the challenges of large load integration and facilitate \nAI development, as well as adopt new practices required of the Show Cause Order.20  \nII. \nMOTION FOR LEAVE TO REPLY \nTo the extent required, ATC respectfully requests leave to submit this Reply.  The \nCommission’s Rules of Practice and Procedure prohibit answers to protests unless otherwise \nauthorized.21  The Commission regularly allows answers for good cause shown, such as when \nthe answers help ensure a more accurate and complete record, clarify the issues, or provide \nuseful and relevant information that will assist the Commission in its deliberative process.22  \nATC’s Reply will clarify the record, correct misinformation and ensure a more accurate and \ncomplete record.  Because this information will assist the Commission in its decision-making, \nATC respectfully requests that the Commission accept this Reply for good cause shown. \n \n19 Id. at P 36 (“We recognize that MISO and/or the Transmission Owners (to the extent the matters \naddressed herein implicate aspects of the Tariff over which they have the filing rights) may elect to \naddress some or all of the issues discussed in this order by proposing revisions to the Tariff pursuant to \ntheir applicable FPA section 205 filing rights. We strongly encourage this.”).   \n20 See Interconnection of Large Loads to the Interstate Transmission System, Advance Notice of Proposed \nRulemaking, Docket No. RM26-4-000 (Oct. 23, 2025) (ANOPR); see also Letter from Chris Wright, \nSec’y, U.S. Dep’t of Energy, Docket No. RM26-4-000 (Oct. 23, 2025); Show Cause Order, Commissioner \nRosner, concurring at P 2 (“It is also crucial that we unlock the immense economic opportunity that once-\nin-a-generation growth represents.”); Id. Commissioner Lacerte concurring at P 5 (“Time is of the \nessence. By inviting you to proceed under FPA section 205, we are giving you significant perks:  the \nbenefits of first wielder of the pen and the relatively capacious standard under FPA section 205 that allows \nus to accept a potentially broad range of proposals provided they are shown to be just and reasonable and \nnot unduly discriminatory or preferential.”). \n21 18 C.F.R. § 385.213(a)(2). \n22 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 at P 24 (2025) (accepting \nanswers to answers “because they have provided information that assisted us in our decision-making \nprocess”); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205 at P 8 (2008) (accepting answer that \ncompleted the record); California Indep. Operator Corp., 105 FERC ¶ 61,284 at P 10 (2003) (accepting \nMISO’s answer that clarified the issues)."},{"page":9,"startToken":2842,"endToken":2971,"text":"9 \n \nIII. \nCONCLUSION \nFor the foregoing reasons, ATC’s proposed revisions to Attachment FF-ATCLLC are just \nand reasonable and will provide greater clarity and transparency for the immediate and reliable \ninterconnection of large loads in ATC’s footprint.  ATC respectfully requests that the \nCommission grant leave to accept this Reply and accept the proposed revisions to Attachment \nFF-ATCLLC as just and reasonable, effective October 17, 2026.   \nRespectfully submitted,  \n \n \n \n \n \n \n \n \n \n/s/  Linda Walsh    \nEllen Nowak, Vice President, State  \n \n \nLinda Walsh \nand Federal Affairs  \n \n \n \n \nHusch Blackwell LLP \nStephanie Neitzel, Senior Counsel  \n \n \n1801 Pennsylvania Ave., NW \nATC Management Inc., corporate manager of \n \nSuite 1000 \nAmerican Transmission Company LLC  \n \nWashington, DC 20006 \nP.O. Box 47 \n \n \n \n \n \nTel: (202) 378-2308 \nWaukesha WI 53187-0047 \n \n \n \nlinda.walsh@huschblackwell.com \nTel: (262) 506-6170 \n \n \n \n \n \n \n \nsneitzel@atcllc.com \n \n \n \n \n \n \n \n \n \nDated: October 13, 2026"},{"page":10,"startToken":2971,"endToken":3056,"text":"10 \n \nCERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated at Washington, D.C. this 13th day of October 2026. \n \n/s/ Emily Starobin \n \nEmily Starobin   \nHusch Blackwell LLP  \n1801 Pennsylvania Ave. NW, Suite 1000  \nWashington, D.C. 20006 \nTel: (202) 378-5784  \nemily.starobin@huschblackwell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":650,"startToken":0,"endToken":336},{"p":2,"at":650,"title":"I. REPLY","method":"printed heading","endPage":2,"endAt":661,"startToken":336,"endToken":338},{"p":2,"at":661,"title":"A. FPA Section 205 Requires that the Commission Accept ATC’s Proposal if It is","method":"printed heading","endPage":4,"endAt":356,"startToken":338,"endToken":1034},{"p":4,"at":356,"title":"B. Conditioning ATC’s Proposed Changes to Attachment FF-ATCLLC on","method":"printed heading","endPage":7,"endAt":1010,"startToken":1034,"endToken":2251},{"p":7,"at":1010,"title":"C. The Commission has Encouraged Individual Transmission Owners to Make","method":"printed heading","endPage":8,"endAt":386,"startToken":2251,"endToken":2448},{"p":8,"at":386,"title":"II. MOTION FOR LEAVE TO REPLY","method":"printed heading","endPage":9,"endAt":5,"startToken":2448,"endToken":2843},{"p":9,"at":5,"title":"III. CONCLUSION","method":"printed heading","endPage":10,"endAt":6,"startToken":2843,"endToken":2972},{"p":10,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":555,"startToken":2972,"endToken":3056}]}