{"document":{"slug":"rec-20261014-5184","title":"Answer of Northern Virginia Electric Cooperative, Inc. in Support of PJM Interconnection, L.L.C.’s Motion for Abeyance filed on 10/13/2026","issued":"2026-10-14","accession":"20261014-5184","docket":"EL26-108-000","group":"PJM Reliability Backstop Procurement","filer":"Northern Virginia Electric Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20261014-5184_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261014-5184","tier":"record","sha256":"06909a8a38c1bce592d4646532e418cc9c69d20e77e96629645cddf061c4fbe1","pages":3,"tokens":541,"emptyPages":[],"textThemes":["procedure"]},"pages":[{"page":1,"startToken":0,"endToken":271,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, L.L.C. \n) \n) \n) \nDocket Nos. ER26-3380-000 \n                EL26-108-000\n \n \nANSWER OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.  \nIN SUPPORT OF PJM INTERCONNECTION, L.L.C.’S MOTION FOR ABEYANCE \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Northern Virginia Electric Cooperative, Inc. \n(“NOVEC”) respectfully submits this answer in support of PJM Interconnection, L.L.C.’s \n(“PJM”) motion for abeyance of the Reliability Backstop Procurement (“RBP”) paper hearing \nprocedures to allow PJM to revise its RBP Proposal2 (the “Abeyance Motion”).3 For the reasons \nset forth herein and in the NOVEC Protest,4 the Commission should accept PJM’s Abeyance \nMotion. \nI. \nTHE COMMISSION SHOULD GRANT PJM’S ABEYANCE MOTION \n \nPJM advised the Commission that it plans “to submit a new FPA section 205 filing that \naddresses, inter alia, cost allocation issues, Transmission Owner exit responsibilities, and LSE \ncollateral requirements as they relate to RBP by October 29, 2026.”5 The Commission invited \nsuch a filing in its September 29, 2026, Order Accepting Reliability Backstop Procurement and \nEstablishing Further Procedures and indicated that it would be open to holding the paper \n \n1 18 C.F.R. § 385.213.  \n2 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) \n(Accession No. 20260731-5214) (“RBP Proposal”). \n3 PJM Interconnection, L.L.C., Motion for Abeyance, Docket Nos. ER26-3380-000 and EL26-108-000 (Oct. 13, \n2026) (Accession No. 20261013-5141) (“Abeyance Motion”). \n4 Northern Virginia Electric Cooperative, Inc., Protest, Docket No. ER26-3380-000 (Aug. 21, 2026) (Accession No. \n20260821-5307) (“NOVEC Protest”).  \n5 Abeyance Motion at 2."},{"page":2,"startToken":271,"endToken":462,"text":"2 \n \nhearing proceeding in abeyance if PJM made such a filing because it may obviate the need for \nthe paper hearing.6 As PJM states in its Abeyance Motion, holding the paper hearing in abeyance \nwill allow PJM and all other interested stakeholders to focus on PJM’s forthcoming filing \nwithout having to work in parallel on initial paper hearing briefs that may never be needed. \nII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the \nCommission grant PJM’s Abeyance Motion.  \n \nRespectfully submitted, \n \n  //s// Alan I. Robbins \n \nAlan I. Robbins \nDebra D. Roby \nThomas B. Steiger III \nPeter E. Colvin \nWashington Energy Law LLP \n900 17th Street. N.W., Suite 500-A  \nWashington, D.C. 20006 \nTel: (202) 326-9313 \nEmail: arobbins@washingtonenergylaw.com \ndroby@washingtonenergylaw.com \ntsteiger@washingtonenergylaw.com \npcolvin@washingtonenergylaw.com \n \nCounsel to Northern Virginia Electric Cooperative, Inc. \n \n \nDated: October 14, 2026.\n \n6 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245, P 24 (2026) (“…we anticipate that the Commission would grant \na motion to hold that briefing in this proceeding in abeyance if PJM submitted a new section 205 filing within 30 \ndays from the date of this order.”)."},{"page":3,"startToken":462,"endToken":541,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in ER26-3380 and EL26-108. \nDated at Washington, D.C. this 14th day of October, 2026. \n \n  //s// Jessika Dziechciowska  \n \nJessika Dziechciowska \nEnergy Practice Analyst \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A \nWashington, D.C. 20006 \nTel: (202) 326-9308  \nEmail: jdziechciowska@washingtonenergylaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":845,"startToken":0,"endToken":120},{"p":1,"at":845,"title":"I. THE COMMISSION SHOULD GRANT PJM’S ABEYANCE MOTION","method":"printed heading","endPage":2,"endAt":381,"startToken":120,"endToken":336},{"p":2,"at":381,"title":"II. CONCLUSION","method":"printed heading","endPage":3,"endAt":0,"startToken":336,"endToken":462},{"p":3,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":3,"endAt":546,"startToken":462,"endToken":541}]}