{"document":{"slug":"rec-20261022-5130","title":"Motion to Intervene and Comments of Northern Indiana Public Service Company in support of the Midcontinent Independent System Operator, Inc’s Large Load…","issued":"2026-10-22","accession":"20261022-5130","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"Northern Indiana Public Service Company","kind":"comments","file":"sources/filings/text/20261022-5130_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261022-5130","tier":"record","sha256":"0b9664575292604a44b75047deb30db1b0391b8b38ecb72ffcf7a18480af099a","pages":10,"tokens":2382,"emptyPages":[],"textThemes":["study","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":237,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nMidcontinent Independent System \nOperator, Inc. \n) \n) \n) \n) \n \nDocket No. ER27-25-000 \n  \n \n \n \n \nMOTION TO INTERVENE AND COMMENTS IN SUPPORT OF  \nNORTHERN INDIANA PUBLIC SERVICE COMPANY LLC \n \n \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission (“FERC” or \nthe “Commission”) Rules of Practice and Procedure,1 Northern Indiana Public Service Company \nLLC (“NIPSCO”), a subsidiary of NiSource Inc., moves for leave to intervene in this proceeding \nand submits these Comments in support of the Midcontinent Independent System Operator, Inc’s \n(“MISO”) filing in the above-captioned docket to establish a Large Load Addition Resource Study \n(“LARS”) process.2  MISO’s LARS Proposal is designed to be a permanent study process that \noptimizes the MISO generator and load interconnection processes by providing expedited review \nof the requested addition of 200 MW or greater loads together with new generation resources that \nare electrically proximate to those loads.  The LARS Proposal is just and reasonable and not unduly \ndiscriminatory.  Therefore, the Commission should approve MISO’s filing, effective December 2, \n2026, as requested by MISO. \nI. \nCOMMUNICATIONS \n \nNIPSCO requests that all communications in this proceeding be served on the following \nrepresentatives: \n \n1 18 C.F.R. §§ 385.212, 214 (2026). \n2 Midcontinent Independent System Operator, Inc., Revisions to the Open Access Transmission, Energy \nand Operating Reserves Tariff Large Load Addition Resource Study Process, Docket No. ER27-25 (filed \nOct. 2, 2026) (“LARS Filing” or, generally, “LARS Proposal”)."},{"page":2,"startToken":237,"endToken":453,"text":"2 \n \nKarl E. Stanley \nVice President, Supply and Optimization \nNiSource Corporate Services \n801 East 86th Avenue \nMerrillville, IN 46410 \n(219) 647-4810 \nkestanley@nisource.com \nM. Bryan Little \nAssistant General Counsel \nNiSource Corporate Services \n150 West Market Street \nIndianapolis, IN 46204 \n(301) 704-5757 \nBLittle@nisource.com \n \nEvan C. Reese III \nMargaret Czepiel \nDina A. Goldman \nDay Pitney LLP \n555 11th Street NW \nWashington, DC 20004 \n202-218-3917 \nereese@daypitney.com \nmczepiel@daypitney.com \ndgoldman@daypitney.com   \n \nII. \nMOTION TO INTERVENE \nA. \nDescription of NIPSCO \nNIPSCO is an Indiana limited liability company headquartered in Merrillville, Indiana, and \nis a subsidiary of NiSource Inc.  NIPSCO serves more than 877,800 natural gas customers and \n492,700 electric customers across Northern Indiana. NIPSCO owns and operates approximately \n3,880 megawatts of electric generating capacity and 2,981 miles of electric transmission lines. \nNIPSCO is an electric load-serving entity and a transmission-owning member of MISO. NIPSCO \nhas transferred functional control of its transmission system to MISO, which serves as NIPSCO’s \nReliability Coordinator.  \nB. \nGrounds for Intervention \nNIPSCO is a transmission-owning member of MISO and owns and operates generation \nfacilities in the MISO footprint. NIPSCO also serves loads across Northern Indiana and expects to \nserve the type of loads that are at issue in the LARS Proposal.  NIPSCO therefore has a direct and"},{"page":3,"startToken":453,"endToken":809,"text":"3 \n \nsubstantial interest in this proceeding that cannot be adequately represented by another party. \nPursuant to Rule 214, NIPSCO moves to intervene with full rights as a party in this proceeding.3 \nIII. \nBACKGROUND \nRecent projections of electricity demand growth and the Commission’s recent Show Cause \nOrder related to large load interconnections underscore the need for MISO to develop a process \nfor studying large loads and the generation intended to serve them.4  Specifically, MISO’s 2026 \nReliability Imperative Report found that data centers, manufacturing expansion, and electrification \nwill drive annual load growth by 1% to 2% through 2044. To address long-term resource adequacy \nissues, the fast connection of new resource additions is paramount for supporting large load growth \nand ensuring reliability as reflected in MISO’s 2026 Planning Resource Auction Results.  \nThe Department of Energy’s (“DOE”) Speed to Power Initiative, likewise reflects the need \nto accelerate the development of generation and transmission infrastructure to serve growing load. \nIn the Show Cause Order issued by the Commission on June 18, 2026, the Commission identified \npotential gaps in the MISO Tariff concerning study procedures and services for the interconnection \nof generation with electrically proximate large loads.5 The Commission directed MISO to provide \n \n3 18 C.F.R. § 385.214 (2026). \n4 MISO, 2026 Reliability Imperative Report at 4 (Feb. 2026) (finding that data centers, manufacturing \nexpansion, and electrification are driving annual load growth of approximately 1% to 2% through 2044) \nhttps://cdn.misoenergy.org/2026%20Reliability%20Imperative%20Report744320.pdf; see also, MISO, \n2026 Planning Resource Auction Results at 2 (May 22, 2026) (“faster resource additions are still needed \nto support large-load growth and ensure resource adequacy”) \nhttps://cdn.misoenergy.org/2026%20PRA%20Results%20Posting%2020260522%20-\n%20Corrections754715.pdf; see also DOE, Speed to Power Initiative (Sept. 18, 2025) (describing the \ninitiative as a federal effort to accelerate development for large-scale transmission and generation projects \nand improve reliability.) https://www.energy.gov/oe/speed-power-through-accelerated-reconductoring-\nand-other-key-advanced-transmission-technology; Midcontinent Independent System Operator, Inc., et \nal., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) \n(“Show Cause Order”).  \n5 Show Cause Order at P 113 (2026)."},{"page":4,"startToken":809,"endToken":1093,"text":"4 \n \na detailed report on any proposals under consideration to address the concerns of resource \nadequacy.6 \nFor its part, NIPSCO, like many other electric utilities in MISO, is facing an unprecedented \nlevel of interest from customers that desire to locate in NIPSCO’s electric service territory. While \nhistorically, a new customer may inquire about adding a few MW of service and an inquiry for 10-\n20 MW was considered a large load addition, new inquiries are now seeking to establish hundreds \nor in some cases thousands of MW of new load. These new customers are also emphasizing the \ndesire for reliable and stable service to begin as soon as possible and the ability to interconnect \nquickly. New generation in the MISO footprint is urgently needed in order to reliably \naccommodate this growth, and accordingly new processes designed to expedite and integrate the \nstudy process for the interconnection of large loads and their associated new generation are critical. \nThe LARS Proposal addresses these resource adequacy concerns and the need to streamline \nthe MISO generator and load study process. Under the LARS Proposal, MISO would provide an \nexpedited pathway for studying qualifying large loads together with associated new generation \nresources. While LARS Interconnection Customers will remain responsible for meeting the \nrequirements of MISO’s standard Generator Interconnection Queue, generation and load studies \nwill be conducted together under a single application.7 Also, Large Load Generator \nInterconnection Agreements would be executed in 120 days.8 Leveraging the successes of MISO’s \nexisting Expedited Project Review process for new electric transmission projects (“EPS”), and \nExpedited Resource Addition Study process for new generation facilities (“ERAS”), this LARS \n \n6 Id. At P 122. \n7 LARS Filing at 7. \n8 Id. at 5."},{"page":5,"startToken":1093,"endToken":1366,"text":"5 \n \nProposal and its expedited timeframe is expected to integrate new large loads to the MISO region \nin a timely and reliable manner.9 Unlike the ERAS process, which is a short-term fix to process \ninterconnection requests for generation necessary to meet significant, near-term needs, the LARS \nProposal is a permanent study process that would address MISO’s long-term need to interconnect \nlarge loads and their associated generation.  \nImportantly, the LARS Proposal contains several requirements that allow MISO to study \nthe new load impacts with greater certainty and reduce the risks of speculative generation or load. \nThese include the mandatory pre-submission coordination activities that require that the entities \ninvolved in each LARS Application are aligned on all relevant details including the point of \ninterconnection and an agreement demonstrating the exact output the generating facility will use \nto serve the associated load.10 In addition, the LARS Associated Transmission Customer, or Load \nServing Entity, must submit a non-refundable fee of $250,000 along with the LARS Application. \nForty-five days in advance of submitting the joint LARS application, the interconnection customer \nmust notify the transmission owner of its intentions to participate in LARS. After receiving the \nrequest, the transmission owner must meet with the interconnection customer and any impacted \nparties.11 These pre-submission coordination activities are designed to increase the efficiency of \nMISO’s review by having all of the necessary details agreed upon prior to filing the LARS \nApplication. \nThe LARS Process provides further certainty because LARS applications must also include \na signed agreement between the interconnection customer and owner or controller of the associated \n \n9   LARS Filing at 2. \n10  Id. at 8-9. \n11 Id."},{"page":6,"startToken":1366,"endToken":1657,"text":"6 \n \nload that demonstrates the commitment that the output of the new generation facility will serve the \nnew load for at least five years.12 This minimum service period provides assurance that the load \nand generation will come online and all affected parties’ investments in the projects are warranted. \nFinally, and importantly, the generation and proximate load must remain paired for a minimum of \nfifteen years to ensure that resources are not reallocated to existing load and the LARS Process is \nnot misused.13  \nMISO first introduced the LARS Proposal at the July 16, 2026 Large Load Working Group \nmeeting and revised the original proposal to address mismatches between the existing MISO study \nprocesses and the LARS study processes in response to feedback from stakeholders.14 \nIV. \nCOMMENTS IN SUPPORT \nNIPSCO supports MISO’s LARS Proposal. By coordinating the study of qualifying large \nloads and associated generation, the LARS Proposal offers a mechanism to identify necessary \nnetwork upgrades and bring new resources online while preserving reliability.15 It also addresses \nthe gaps in MISO’s Tariff as identified by the Commission in the Show Cause Order. MISO’s 2026 \nReliability Imperative Report, the MISO’s 2026 Planning Resource Auction Results, and DOE’s \nSpeed to Power initiative all point to a high level of near-term reliability and resource adequacy \nrisk brought about by large load additions.16  While MISO has made recent strides in addressing \nissues with its interconnection initiatives such as the existing EPR and ERAS processes, LARS \npresents a permanent solution to NIPSCO’s and other MISO participants’ imminent needs to bring \n \n12 Testimony of Christina Drake at 17, 35 (“Drake Testimony”). \n13  See Drake Testimony at 35-36. \n14  See LARS Filing at 11-12. \n15  Show Cause Order at P 113. \n16  Supra at 4."},{"page":7,"startToken":1657,"endToken":1954,"text":"7 \n \nlarge loads and their proximate generation online in a safe and reliable manner. The LARS \nProposal provides a cost-effective tool to address the intersection of large load and generation, as \nwell as identify more optimized Network Upgrades at an expedited rate.17   \nA. \nThe LARS Proposal is Necessary to Address MISO’s Short-Term Needs \nMISO’s existing interconnection process as set forth in Attachment X of MISO’s Tariff (the \nDefinitive Planning Phase (“DPP”) process) alone is insufficient to bridge the corresponding needs \nof new generation and large expected load growth throughout the MISO footprint. While the DPP \nprocess is well-suited to address NIPSCO’s interconnection needs for normal load growth, the \nscale and timing of large load interconnections present a different challenge. NIPSCO and other \nMISO Market Participants are working with potential large load customers, such as data centers, \nthat have unprecedented service needs on short timeframes. NIPSCO, for example, is considering \nrequests to add between 3,000-8,000 MW primarily to serve megaload customers.18  The DPP \nprocess was simply not designed to process the needs for both the interconnection of new large \nload additions and the interconnection of new generation to supply energy to those loads in an \norganized, coordinated and comprehensive fashion.  \nLarge loads present operational and reliability challenges and therefore require detailed \nstudies that enable affected parties to plan for reliability challenges. The LARS Proposal would \nallow MISO to evaluate the associated load and generation using aligned assumptions and to \nidentify the upgrades required to accommodate both, through a single process. This coordinated \n \n17  LARS Filing at 4. \n18 On June 17, 2026, the Indiana Utility Regulatory Commission made several approvals that would allow \nNIPSCO to provide service to an Amazon data center expected to increase to 2,400 MW by the end of \n2032."},{"page":8,"startToken":1954,"endToken":2195,"text":"8 \n \napproach could reduce the time needed to bring qualifying projects online without relying solely \non improvements to the broader DPP queue. \nB. \nThe LARS Proposal is a Just and Reasonable Solution \nAs MISO outlines in its filing, the LARS Proposal is tailored to meet a specific need \nidentified by the Commission.19  It is self-limiting in that it is designed solely to study \ngeneration/load pairs and maintains several guardrails in order to protect the DPP process and DPP \ninterconnection customers. MISO developed the LARS Proposal to ensure that the process works \nin tandem with the DPP process and existing interconnection customers are not adversely \nimpacted. For instance, the LARS Proposal is designed to keep the transmission capacity available \nfor LARS applications separate from the transmission capacity headroom available throughout the \nDPP cycle.20  \nFurther, LARS Applicants must commit to a substantially higher financial commitment \nincluding a non-refundable $250,000 application fee. This payment will be used to fund the \nadditional tools, staffing, and process enhancement MISO needs to support its existing process and \nLARS.21  \nFinally, LARS applications cannot be modified after submission and prior to the execution \nof the Large Load Generator Interconnection Agreement, ensuring that LARS Applicants avoid \nsudden changes causing delays and withdrawals.22 The LARS Proposal is a just and reasonable \nsolution to MISO’s current resource adequacy dilemma. \n \n19 LARS Filing at 20. \n20 Id. \n21 Drake Testimony at 32. \n22 LARS Filling at 30."},{"page":9,"startToken":2195,"endToken":2292,"text":"9 \n \nV. \nCONCLUSION \nWHEREFORE, and for good cause shown, NIPSCO respectfully requests that the \nCommission grant this Motion to Intervene and consider these Comments in support and accept \nMISO’s LARS Proposal, effective December 2, 2026, as requested.  \n \n \n \n \n \n \n \n \n \n \n \n \nOctober 22, 2026 \nRespectfully submitted,  \n \n \n/s/ Evan C. Reese III \nEvan C. Reese III \nMargaret Czepiel \nDina A. Goldman \nDay Pitney LLP \n555 11th Street NW \nWashington, DC 20004 \n202-218-3917 \nereese@daypitney.com \nmczepiel@daypitney.com \ndgoldman@daypitney.com  \n \nM. Bryan Little \nAssistant General Counsel \nNiSource Corporate Services \n150 West Market Street \nIndianapolis, IN 46204 \n(301) 704-5757 \nBLittle@nisource.com"},{"page":10,"startToken":2292,"endToken":2382,"text":"10 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon the parties \ndesignated on the official service list compiled by the Secretary for the above-captioned dockets \nin accordance with the requirements of Rule 2010 of the Federal Energy Regulatory Commission’s \nRules of Practice and Procedure, 18 C.F.R. 385.2010 (2026). \nDated at Washington, DC this 22nd day of October, 2026. \n \n \n/s/ Dina A. Goldman \nDina A. Goldman \nDay Pitney LLP \n555 11th Street NW \nWashington, DC 20004 \n202-218-3906 \ndgoldman@daypitney.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1252,"startToken":0,"endToken":176},{"p":1,"at":1252,"title":"I. COMMUNICATIONS","method":"printed heading","endPage":2,"endAt":539,"startToken":176,"endToken":311},{"p":2,"at":539,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":565,"startToken":311,"endToken":315},{"p":2,"at":565,"title":"A. Description of NIPSCO","method":"printed heading","endPage":2,"endAt":1182,"startToken":315,"endToken":403},{"p":2,"at":1182,"title":"B. Grounds for Intervention","method":"printed heading","endPage":3,"endAt":200,"startToken":403,"endToken":485},{"p":3,"at":200,"title":"III. BACKGROUND","method":"printed heading","endPage":6,"endAt":790,"startToken":485,"endToken":1492},{"p":6,"at":790,"title":"IV. COMMENTS IN SUPPORT","method":"printed heading","endPage":7,"endAt":274,"startToken":1492,"endToken":1700},{"p":7,"at":274,"title":"A. The LARS Proposal is Necessary to Address MISO’s Short-Term Needs","method":"printed heading","endPage":8,"endAt":146,"startToken":1700,"endToken":1976},{"p":8,"at":146,"title":"B. The LARS Proposal is a Just and Reasonable Solution","method":"printed heading","endPage":9,"endAt":5,"startToken":1976,"endToken":2196},{"p":9,"at":5,"title":"V. CONCLUSION","method":"printed heading","endPage":10,"endAt":6,"startToken":2196,"endToken":2293},{"p":10,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":565,"startToken":2293,"endToken":2382}]}