{"document":{"slug":"rec-20261023-5191","title":"Motion to Intervene and Limited Protest of Southern Minnesota Municipal Power Agency and WPPI Energy re Midcontinent Independent System Operator, Inc.’s…","issued":"2026-10-23","accession":"20261023-5191","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"WPPI EnergySouthern Minnesota Municipal Power Agency","kind":"protest","file":"sources/filings/text/20261023-5191_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261023-5191","tier":"record","sha256":"8aaf04935a9a4ec6435ed2c7900d582fb3f0709d06087fcf29ac04b500dab61a","pages":15,"tokens":3014,"emptyPages":[],"textThemes":["proximate","study","cost","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":210,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent Independent System \nOperator, Inc. \nDocket No.  ER27-25-000 \n \nMOTION TO INTERVENE AND LIMITED PROTEST \nOF SOUTHERN MINNESOTA MUNICIPAL POWER \nAGENCY AND WPPI ENERGY \nPursuant to Rules 211, 212, and 214 of the Federal Energy Regulatory \nCommission’s (the “Commission”) Rules of Practice and Procedure,1 and the \nCommission’s October 2, 2026 Combined Notice of Filings #1,2 Southern Minnesota \nMunicipal Power Agency (“SMMPA”) and WPPI Energy (“WPPI”) (collectively, \n“Midwest TDUs”) each moves to intervene in this proceeding and together submit this \nLimited Protest of Midcontinent Independent System Operator, Inc.’s (“MISO”) October \n2, 2026 filing to revise its Open Access Transmission, Energy, and Operating Reserve \nMarkets Tariff (“Tariff”) to establish a Large Load Addition Resource Study (“LARS”) \nprocess.3 As MISO explains, its LARS proposal is responsive to the Commission’s June \n18, 2026 Show Cause Order,4 specifically the Commission’s preliminary finding “that \nMISO’s existing Tariff may be unjust and unreasonable because it does not provide \n \n1 18 C.F.R. §§ 385.211, 385.212, 385.214. \n2 eLibrary No. 20261002-3077. \n3 MISO, Large Load Addition Resource Study Process (Oct. 2, 2026), eLibrary No. 20261002-5074 \n(“MISO Filing”). \n4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”)."},{"page":2,"startToken":210,"endToken":470,"text":"- 2 - \ngenerator interconnection study procedures and services that account for the operational \ndynamics of serving electrically proximate large loads.”5 \nMidwest TDUs protest one aspect of MISO’s Filing: MISO’s proposal to make \npaired generation and load within the same Local Resource Zone (“Zone” or “LRZ”) \neligible for the LARS process. This geographic scope is materially different from what \nthe Commission contemplated in its Show Cause Order, which defined “electrically \nproximate” as a large load located no more than two substations away from the \ngenerating facility. MISO’s proposed scope is both significantly overinclusive (including \npaired generation and load that may be hundreds of miles and multiple states apart) and \nunderinclusive (excluding pairs that may be within two or fewer substations but in \ndifferent Zones).  \nFinally, Midwest TDUs appreciate that MISO’s LARS proposal requires that the \nLARS Interconnection Customer remain responsible for identified Generator \nInterconnection Project (“GIP”) Network Upgrades, and the LARS Associated \nTransmission Customer remain responsible for any identified Baseline Reliability \nProjects or Other assigned Network Upgrades. While this requirement is necessary for \nLARS to be just, reasonable, and not unduly discriminatory, it is not sufficient. MISO \nstates that it intends to make a future Federal Power Act (“FPA”) section 2056 filing to \naddress additional cost allocation and transparency issues raised in the Show Cause \nOrder. The Commission should therefore condition any acceptance on MISO’s filing in \nthis proceeding on the Commission finding, in future proceeding(s), that MISO has \n \n5 MISO Filing, Transmittal Letter at 3 (“Transmittal Letter”) (citing Show Cause Order P 113).  \n6 16 U.S.C. § 824d."},{"page":3,"startToken":470,"endToken":770,"text":"- 3 - \nsatisfied its obligations with respect to the Show Cause Order’s discussion of cost \nallocation and transparency as applied to LARS. Midwest TDUs reserve all rights with \nrespect to additional future MISO filings in response to the Show Cause Order.  \nI. \nMOTION TO INTERVENE \nEach Midwest TDU (described in Attachment A hereto) moves to intervene with \nfull rights as parties to this proceeding. As market participants, load-serving entities, and \ncustomers under MISO’s Tariff, Midwest TDUs will be directly affected by MISO’s \nproposed Tariff revisions. They each have clear and substantial interests in this \nproceeding that cannot be represented by any other party, and their participation would be \nin the public interest. Midwest TDUs should therefore each be granted intervention. \nCommunications regarding this proceeding should be directed to the following:7 \nCynthia S. Bogorad \nJeffrey M. Bayne \nSPIEGEL & MCDIARMID LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \nPhone: (202) 879-4000 (Phone)  \nFax: (202) 393-2866 (Fax) \nEmail: cynthia.bogorad@spiegelmcd.com  \n \njeffrey.bayne@spiegelmcd.com \n \nWPPI: \nTom Hanrahan, General Counsel \nWPPI ENERGY \n1425 Corporate Center Drive \nSun Prairie, WI 53590-9109 \nPhone: (608) 834-4556 \nEmail: thanrahan@wppienergy.org \n \nSMMPA: \nJeremy Sutton \nDirector of Operations and COO \nSOUTHERN \nMINNESOTA \nMUNICIPAL \nPOWER AGENCY \n500 First Avenue, SW \nRochester, MN 55902-3303  \nPhone: (507) 292-6444 \nFax: (507) 292-6414 \nEmail: jb.sutton@smmpa.org \n \nSeth Koneczny \nManager of Power Delivery  \nSOUTHERN \nMINNESOTA \nMUNICIPAL \nPOWER AGENCY \n500 First Avenue, SW \nRochester, MN 55902-3303  \nPhone: (507) 292-6456 \nFax: (507) 292-6414 \nEmail: st.kneczny@smmpa.org \n \n7 Midwest TDUs request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, \n18 C.F.R. § 385.203(b)(3), so as to permit more than two entries on the official service list in order to \nenable Midwest TDUs to promptly receive all communications in the proceeding."},{"page":4,"startToken":770,"endToken":1000,"text":"- 4 - \n \n \n \nII. \nLIMITED PROTEST \nA. \nMISO does not show that its proposed geographic scope for \npaired generation and load eligible for LARS is just, reasonable, \nand not unduly discriminatory. \nIn the Show Cause Order, the Commission preliminarily found that MISO’s Tariff \nappears to be unjust and unreasonable because it lacks a generator interconnection study \nprocess and/or generator interconnection service applicable to generation facilities \nserving “electrically proximate large load[s].”8 The Commission used the term \n“electrically proximate large load” in the Show Cause Order to mean:9 \na large load . . . sufficiently electrically close to the \ninterconnection \ncustomer’s \nrequested \npoint \nof \ninterconnection, such that the impact on the transmission \nsystem of the combination of the generating facility and the \nload, with the exception of the transmission facilities \nbetween the two, will be effectively the same as if they were \nlocated at the same substation (e.g., large load that is located \nno more than two substations away from the generating \nfacility). \nWhen paired load and generation are located close enough such that they have the same \nimpact on the transmission system as if they were located at the same substation, the \nCommission preliminarily found that reliance on MISO’s current generation \ninterconnection processes may be unjust and unreasonable because it results in \n“unnecessary interconnection delays, unnecessary Network Upgrades, and an otherwise \n \n8 Show Cause Order P 113. \n9 Id. P 112."},{"page":5,"startToken":1000,"endToken":1252,"text":"- 5 - \ninefficient expansion of the transmission system, imposing unnecessary delays and costs \non transmission customers.”10 \nIn response, MISO’s proposed a new LARS process that would provide \n“expedited review” to “streamline the MISO generator and load interconnection process” \nfor certain generation and large loads.11 But rather than adopting the Commission’s \nelectrically proximate large load concept (i.e., located no more than two substations away \nfrom the generating facility), MISO proposes that its LARS process apply to paired load \nand generation located in the same Local Resource Zone (“Zone” or “LRZ”).12 MISO’s \nFiling does not come close to justifying a departing from the Show Cause Order’s \napproach by substituting a geographic scope that is both overinclusive and \nunderinclusive. \nMISO Zones can span hundreds of miles and cross multiple states.13 For example, \nMISO Zone 1 covers parts of eastern Montana, northeast South Dakota, North Dakota, \nmost of Minnesota, western Wisconsin, and small portions of northeast Iowa and \nnorthwest Illinois. As a result, MISO’s LARS filing would treat a generator in Montana \nas “electrically proximate” to a large load in Wisconsin, despite the hundreds of miles \nand multiple states between them. MISO fails to show that such paired generation and \nload should be treated as electrically proximate, much less that they would have same \nimpact on the MISO Transmission System as if located at the same substation.  \n \n10 Id. P 117. \n11 Transmittal Letter at 1.  \n12 Id. at 10.  \n13 See MISO Tariff, Attach. VV (Map of Local Resource Zone Boundaries)."},{"page":6,"startToken":1252,"endToken":1512,"text":"- 6 - \nAt the same time, MISO’s proposed geographic scope for LARS excludes paired \ngeneration and load that truly are electrically proximate. For example, under MISO’s \nFiling a generator in the portion of Wisconsin covered by Zone 2 could never be treated \nas electrically proximate to a large load located in the portion of Wisconsin in Zone 1, \neven if they are located within two substations of each other. These pairs of generation \nand load are completely denied access to the expedited LARS process, while much more \ndistant generation and load pairs are eligible for the limited spots available per a LARS \ncycle. \nThe few reasons MISO gives in support for its zonal approach to LARS are \nunpersuasive and irrelevant to the Commission’s directive in the Show Cause Order. For \nexample, MISO states that limiting paired generation and load to a specific number of \nsubstations—as suggested in the Show Cause Order—“could limit how MISO may \noptimize common transmission solutions.”14 MISO does not explain how more distant \npaired generation and load, or excluding paired generation and load close to each other \nbut in different Zones, will lead to more optimal transmission solutions. Nor does MISO \nexplain how this scope aligns with the Show Cause Order’s aim of identifying generation \nand load sufficiently close to each other such that they impact the transmission system as \nif they were located at the same substation.  \nMoreover, MISO’s LARS construct already contains numerous elements that \nbroaden the scope of what should be a streamlined study process, e.g.: \n \n14 Transmittal Letter at 21."},{"page":7,"startToken":1512,"endToken":1868,"text":"- 7 - \n• allowing generation at multiple Points of Interconnection for a single LARS \nAssociated Load, with separate Applications for each Point of \nInterconnection; \n• conducting serial studies, even when there are multiple pairs of generation and \nload in the same Zone and even for multiple Points of Interconnection for the \nsame LARS Associated Load; \n• permitting generation to receive Network Resource Interconnection Service \n(“NRIS”) for up to 150% of the LARS Associated Load’s peak demand; and  \n• permitting a LARS Generating Facility to retain NRIS for up to a year without \nits paired LARS Associated Load.15  \nLARS’ flawed geographic and study scope puts in doubt the optimality of the resulting \ntransmission solutions that the LARS process will identify. The purpose of LARS and the \nShow Cause Order’s discussion of electrically proximate large loads is to identify those \npairs of load and generation that can be studied “efficiently and effectively.”16 A \ngeographic measure of eligibility for LARS that fails to address electrical proximity, \nhowever, is incompatible with that goal. \nMISO also states that its zonal scope “avoids potential capacity import / capacity \nexport limitations for the individual LRZ and also avoids price separation between the \npaired generation and LARS Associated Load,”17 referring to Planning Resource Auction \n \n15 Under MISO’s proposal, termination of the LLGIA is triggered if “the LARS Associated Load or a \nportion of the LARS Associated Load has ceased use of Transmission Service granted through LARS for a \nperiod of one year beginning with the last date of use of such Transmission Service.” Id. at 41 (quoting \nrevised Article 2.3.1 of MISO Filing, Tab A, Attach. X – Appendix 6 (emphasis added)). After that full \nyear where there can be no associated load, MISO will then provide the generator an additional full year \n“to continue to operate under the LLGIA in order to provide time for the Interconnection Customer to enter \nthe DPP and obtain new NR Interconnection Service,” with operations subject to MISO’s Quarterly \nOperating Limits and Annual ERIS process during this one-year transition period. Id. at 17.  \n16 Id. at 18. \n17 MISO Filing, Tab C, Prepared Direct Testimony of Christina Drake at 40."},{"page":8,"startToken":1868,"endToken":2151,"text":"- 8 - \ncapacity prices that are set by Zone under MISO’s Resource Adequacy construct.18 These \ncursory references to capacity prices are a non sequitur. MISO does not explain why the \ngeographic scope used for certain Resource Adequacy purposes is the correct scope for \nan expedited interconnection study process. MISO also does not explain why a desire to \navoid capacity price separation should determine the geographic scope of LARS, \nparticularly given that there can be energy price separation (based on nodes) within the \nsame Zone.  \nConsistent with the Show Cause Order, the scope of LARS eligibility should \ninstead be based on which paired generation and load are likely to either have limited \nimpacts on the Transmission System or result in more optimal transmission solutions \nwhen paired, such that a unique, expedited study process is justified. An inappropriately \nbroad geographic scope for LARS will likely capture more generation and load pairs, \nrequiring more time and resources to implement, which risks detracting from MISO’s \nability to improve the timing and processes for its “standard” interconnection processes. \nIt also invites gaming by those seeking to take advantage of differences in the LARS and \nstandard generation and load interconnection study processes. In contrast, a more targeted \nscope ensures that LARS is appropriately focused on generation and load pairs likely to \neither present fewer challenges to the Transmission System or result in more optimal \ntransmission solutions when paired—without diverting more resources than necessary \n \n18 See also Transmittal Letter at 10 (stating that MISO’s proposed geographic scope for LARS “aligns with \nMISO’s Resource Adequacy construct” and “provid[es] an incentive for Load to bring Generation in a \nmanner that maximizes the positive impact this Generation has on Resource Adequacy”)."},{"page":9,"startToken":2151,"endToken":2420,"text":"- 9 - \naway from the standard generation and load interconnection study processes that non-\npaired MISO loads must depend on for affordable and reliable electricity.  \nB. \nAdditional cost allocation issues must be addressed in future \nproceedings.  \nUnder MISO’s LARS Filing, “[t]he Interconnection Customer remains \nresponsible for any identified GIP Network Upgrades and the LARS Associated \nTransmission Customer remains responsible for any identified [Baseline Reliability \nProjects] or Other assigned Network Upgrades.”19 Midwest TDUs support this \nrequirement, which appropriately links cost responsibility with cost causation.  \nMISO’s filing, however, does not purport to address all cost-related issues raised \nin the Commission’s Show Cause Order.20 MISO specifically notes that it is “continuing \nto work with stakeholders . . . to develop the pro forma cost shifting agreement and any \nnecessary terms for transmission service for large loads, all of which will be submitted to \nthe Commission in a FPA section 205 filing by November 16, 2026.”21 Although MISO \nstates that “[t]he LARS structure is compatible with these agreements and MISO will \nincorporate them into LARS once they are accepted,” it also states that “LARS can be \nimplemented based on the Tariff revisions filed herein and need not await these future \nfilings.”22  \n \n19 Id. at 16. \n20 MISO explains that its LARS filing “responds to concerns identified in the Show Cause order regarding \nproximity between large loads and their associated generation,” id. at 18, and that “other concerns raised by \nthe Show Cause Order . . . will ultimately be presented to the Commission in separate FPA section 205 \nfilings by November 16, 2026,” id. at 20. \n21 Id. at 14.  \n22 Id. n.66."},{"page":10,"startToken":2420,"endToken":2612,"text":"- 10 - \nAs a result, the Commission currently has an incomplete picture of how cost \nallocation and transparency will work in the context of the LARS process. Midwest \nTDUs do not oppose MISO responding to the Show Cause Order through multiple \nsection 205 filings, but the Commission must ensure that the end results are Tariff \nrevisions that work together and comprehensively address the issues raised in the Show \nCause Order. The Commission should therefore condition any acceptance on MISO’s \nfiling in this proceeding on the Commission finding, in future proceeding(s), that MISO \nhas satisfied its obligations with respect to the Show Cause Order’s discussion of cost \nallocation and transparency as applied to LARS. \nCONCLUSION \nFor the reasons discussed above, the Commission should (1) reject MISO’s \nproposed geographic scope for paired generation and load eligible for LARS and direct \nMISO to revise its Tariff language consistent with the Show Cause Order; and \n(2) condition any acceptance on MISO’s filing in this proceeding on the Commission \nfinding, in future proceeding(s), that MISO has satisfied its obligations with respect to the \nShow Cause Order’s discussion of cost allocation and transparency as applied to LARS."},{"page":11,"startToken":2612,"endToken":2649,"text":"- 11 - \nRespectfully submitted, \n /s/ Cynthia S. Bogorad \nCynthia S. Bogorad \nJeffrey M. Bayne \nAttorneys for Midwest TDUs \nLaw Offices of: \nSpiegel & McDiarmid LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \n(202) 879-4000 \nOctober 23, 2026"},{"page":12,"startToken":2649,"endToken":2651,"text":"ATTACHMENT A"},{"page":13,"startToken":2651,"endToken":2886,"text":"A-1 \nATTACHMENT A: DESCRIPTION OF MIDWEST TDUS \nSouthern Minnesota Municipal Power Agency (“SMMPA”) is a joint action \nagency composed of seventeen member municipalities in Minnesota that own and operate \nmunicipal electric systems. SMMPA is also a non-profit political subdivision of the State \nof Minnesota organized under Chapter 453 of the Minnesota Statutes that is not subject to \nthe Commission’s full jurisdiction. SMMPA became a Transmission Owning Member of \nMISO, effective April 1, 2006. \nWPPI Energy (“WPPI”) is a municipal electric company formed pursuant to \nWis. Stat. § 66.0825. WPPI provides bulk power and other services to its 51 members (50 \nmunicipalities and one cooperative), each of which operates a distribution utility and sells \nelectricity at retail to the residences, businesses, and industries in and around its \nmunicipality. These members are located within the Wisconsin, Michigan, and/or Iowa \nservice territories of four large investor-owned utilities: Northern States Power-\nWisconsin (Xcel Energy (“Xcel”)), WEC Energy Group (Wisconsin Electric Power \nCompany (“WEPCO”) and Wisconsin Public Service Corp. (“WPS”)), Upper Peninsula \nPower Co., and Alliant Energy (Wisconsin Power & Light Co. (“WP&L”) and Interstate \nPower and Light Co.). The bulk of WPPI’s load is on the American Transmission \nCompany LLC (“ATCLLC”), Xcel, or ITC Midwest transmission systems, although \nsome of WPPI’s resources are located in other transmission zones in MISO, as well as in \nPJM Interconnection, L.L.C. WPPI supplies the bulk power and energy requirements of"},{"page":14,"startToken":2886,"endToken":2948,"text":"Attachment A \nA-2 \n \nits members from generation resources owned by WPPI and through purchased power \ncontracts. \nWPPI is a longstanding member of MISO, with both generation and load within \nthe MISO footprint, and owns portions of transmission projects. WPPI also is a \nparticipating owner of ATCLLC, a MISO Transmission Owner which was formed \npursuant to 1999 Wisconsin Act 9 with WPPI’s support."},{"page":15,"startToken":2948,"endToken":3014,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing document to be served \nupon each person designated on the official service list compiled by the Secretary in this \nproceeding. \nDated on this 23rd day of October, 2026. \n /s/ Jeffrey M. Bayne \nJeffrey M. Bayne \nLaw Offices of: \n \nSpiegel & McDiarmid LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \n(202) 879-4000"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":259,"startToken":0,"endToken":510},{"p":3,"at":259,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":4,"endAt":13,"startToken":510,"endToken":771},{"p":4,"at":13,"title":"II. LIMITED PROTEST","method":"printed heading","endPage":4,"endAt":35,"startToken":771,"endToken":774},{"p":4,"at":35,"title":"A. MISO does not show that its proposed geographic scope for","method":"printed heading","endPage":9,"endAt":168,"startToken":774,"endToken":2175},{"p":9,"at":168,"title":"B. Additional cost allocation issues must be addressed in future","method":"printed heading","endPage":10,"endAt":726,"startToken":2175,"endToken":2533},{"p":10,"at":726,"title":"CONCLUSION","method":"printed heading","endPage":12,"endAt":0,"startToken":2533,"endToken":2649},{"p":12,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":13,"endAt":5,"startToken":2649,"endToken":2652},{"p":13,"at":5,"title":"ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS","method":"printed heading","endPage":14,"endAt":0,"startToken":2652,"endToken":2886},{"p":14,"at":0,"title":"Attachment A","method":"printed heading","endPage":15,"endAt":0,"startToken":2886,"endToken":2948},{"p":15,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":404,"startToken":2948,"endToken":3014}]}