{"document":{"slug":"rec-20261023-5198","title":"Motion to Intervene and Comments of Geronimo Power, LLC concerning the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study…","issued":"2026-10-23","accession":"20261023-5198","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"GERONIMO POWER, LLC","kind":"comments","file":"sources/filings/text/20261023-5198_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261023-5198","tier":"record","sha256":"4c6b18680a40bb9de14970fc33e0e324cd19942c9fb9573f53f8cef544fa0eee","pages":21,"tokens":6939,"emptyPages":[],"textThemes":["study","colo","adequacy","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":267,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent Independent System  \nOperator, Inc. \n) \n) \n) \n) \n \nDocket No. ER27-25-000 \n \n \nMOTION TO INTERVENE AND COMMENTS OF  \nGERONIMO POWER, LLC \n \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” \nor “Commission”) Rules of Practice and Procedure1 and the Commission’s October 2, 2026 \nCombined Notice of Filings #1,2 Geronimo Power, LLC (“Geronimo Power”) hereby submits this \nmotion to intervene and comments in the above-captioned proceeding concerning the \nMidcontinent Independent System Operator, Inc.’s (“MISO”) Large Load Addition Resource \nStudy Process (“LARS”) proposal.3 \nI. \nCOMMENTS \nGeronimo Power appreciates MISO’s efforts to develop interconnection processes that \nfacilitate the integration of large loads and respond to the directives included in the Commission’s \nShow Cause Order.4  At a time when the MISO region is experiencing “significant growth in \nelectricity demand”5 and is “[t]he region with the fastest data center capacity growth” in the \ncountry,6 it is imperative that MISO have processes that ensure large loads and generation capacity \n \n1 18 C.F.R. §§ 385.212 and 385.214. \n2 Midcontinent Indep. Sys. Operator, Inc., et al., Docket Nos. ER27-25-000, et al., Combined Notice of \nFilings #1 (Oct. 2, 2026).  \n3 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Large Load Addition Resource Study \nProcess (Oct. 2, 2026) (“LARS Filing”).  \n4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 2 (2026) (“Show Cause Order”). \n5 LARS Filing, Transmittal Letter at 2. \n6 FERC, 2025 State of the Markets Report at 7 (Mar. 2026), available at: https://www.ferc.gov/news-\nevents/news/report-3-state-markets-report-2025."},{"page":2,"startToken":267,"endToken":620,"text":"2 \n \nserving these customers may interconnect to the grid in an efficient, timely, and non-discriminatory \nmanner.   \nGeronimo Power supports the creation of efficient and non-discriminatory procedures that \nprovide for the coordinated study of new generation capacity and large load customers.  Evaluating \npaired generation capacity and large load can provide a more accurate picture of the net impact of \nthese customers on the transmission system and reduce the need for costly network upgrades that \ncan unnecessarily drive up costs and delay energization timelines.  By reducing barriers to entry \nto new generation and large load customers, interconnection procedures that provide for the \ncoordinated evaluation of generation and large loads can play a critical role in providing large \nloads a pathway to power that maintains America’s economic competitiveness while \nsimultaneously mitigating impacts to the grid and avoiding cost shifts to existing customers.   \nNevertheless, any proposal that provides certain customers with a separate path to \ninterconnection service must comply with the Federal Power Act’s (“FPA”) prohibition on undue \ndiscrimination and preference and open access requirements.7  Historically, the Commission has \nbeen skeptical of any proposals that create a separate or expedited path for certain resources to \nobtain interconnection service.8  But the Commission has approved expedited processes in limited \ncircumstances where such processes were narrowly tailored to meet a demonstrated reliability need \nand “aligned with . . . open access principles in an objective and transparent manner.”9   \n \n7 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at PP 201-02 (2025).  See also Cal. Indep. \nSys. Operator Corp., 180 FERC ¶ 61,143, at P 41 (2022); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, at P 248 \n(2025). \n8 Xcel Energy Operating Co., 106 FERC ¶ 61,260, at PP 22-23 (2004); Sw. Power Pool, Inc., 147 FERC ¶ \n61,201, at P 124 (2014); Midcontinent Indep. Sys. Operator, Inc., 185 FERC ¶ 61,200, at PP 176-177 (2023). \n9 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at PP 201-03 (2025).  See also Cal. Indep. \nSys. Operator Corp., 180 FERC ¶ 61,143, at P 41 (2022); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, at P 248 \n(2025)."},{"page":3,"startToken":620,"endToken":980,"text":"3 \n \nMISO’s LARS proposal does not meet this standard.  As currently conceived, LARS would \nprovide incumbent utilities with undue influence over the ability of interconnection customers to \naccess the process.  Notably, an interconnection customer will not be able to participate in LARS \nunless the interconnecting transmission owner “pre-approves” its proposed point of \ninterconnection and a MISO transmission customer—which typically will be a transmission owner \nand load-serving entity (“LSE”)—submits an application into the LARS process.10  The result is a \nframework that will provide incumbent utilities with new opportunities to discriminate against \ncompeting suppliers and secure preferential access to interconnection service for their own \ngeneration resources.  Ultimately, this will provide incumbent utilities with a powerful tool that \nthey can use to pressure large load customers to rely on their generation resources, which will be \neligible to receive interconnection service more quickly and at lower cost than competing resources \nthat have been relegated to the standard interconnection queue.  \nAt the same time, certain aspects of MISO’s proposed framework appear to arbitrarily \nexclude from LARS generation resources that are being developed to meet the demand of large \nload customers in a manner that supports resource adequacy and protects ratepayers.  For instance, \nthe requirement that an interconnection customer provide an offtake agreement demonstrating that \nits facility will be used to provide energy to large load customers would appear to prevent a \ngeneration resource that has entered into a virtual power purchase agreement (“PPA”) with a large \nload customer from participating in LARS.  Additionally, MISO’s description of the scope of \nLARS could be interpreted as prohibiting co-located generation and load from accessing the LARS \n \n10 Midcontinent Indep. Sys. Operator, Inc., 170 FERC ¶ 61,215, at P 13 (2020) (“[A]pproximately 90% of \nthe load in MISO is served by vertically integrated LSEs[.]”); Entergy Ark., LLC v. Webb, Case No. 24-1074, Brief of \nAmicus Curiae the MISO Transmission Owners Supporting Petitioner at 1, 9 (U.S. Supreme Court, May 14, 2025) \n(explaining that the MISO transmission owners include vertically integrated utilities and that “vertically integrated \nutilities with load serving obligations take transmission service under the MISO Tariff to serve their retail (state-\nregulated) customers.”)."},{"page":4,"startToken":980,"endToken":1324,"text":"4 \n \nprocess which would undermine an effective means for large loads to achieve speed to power while \nsimultaneously mitigating the operational impact and reliability concerns that MISO claims its \nLARS proposal is intended to address.   \nAt a time when large load customers are being asked to take a greater role in identifying \nand funding the construction of new generation capacity to offset their demand,11 it is critically \nimportant that the frameworks adopted by MISO and other transmission providers do not create \nbarriers to large loads pursuing supply options that best align with their needs and that support the \nobjectives of ensuring speed to power and protecting retail customers.  A generation developer \nthat enters into an agreement with a large load customer under which the customer assumes the \nfinancial risk of the generation resource should be able to submit a request into LARS without the \nblessing or involvement of the incumbent utility.  Although a large load customer and generation \ndeveloper may need to coordinate their supply arrangement with an LSE to comply with applicable \nstate law, those issues can be resolved by the large load customer, generation developer, and \napplicable LSE outside of the context of the MISO market.   \nGeronimo Power does not question MISO’s intent in proposing LARS and appreciates \nMISO’s efforts to come up with frameworks that address the concerns expressed in the Show \nCause Order.  But the effect of MISO’s proposal would be to create new opportunities for undue \ndiscrimination and arbitrarily limit the availability of LARS to certain interconnection customers.  \nLARS should remove barriers to the entry of new capacity to serve large load customers; it should \nnot protect the market position of incumbent utilities within the region.   \n \n \n11 \nSee, \ne.g., \nThe \nWhite \nHouse, \nRatepayer \nProtection \nPledge \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ (stating that “[c]ompanies will build, \nbring, or buy the new generation resources and electricity needed to satisfy their new energy demands, paying the full \ncost of those resources whether by building, or buying from, new or otherwise additive power plants”)."},{"page":5,"startToken":1324,"endToken":1626,"text":"5 \n \nAccordingly, Geronimo Power urges the Commission to reject LARS on the basis that it \nhas not been shown to be just, reasonable, and not unduly discriminatory or preferential.  The \nCommission’s order rejecting LARS should make clear that it is without prejudice to MISO \nmaking a future filing to establish a coordinated study process for generation and large load \ncustomers that aligns with open access requirements, the goals of the Show Cause Order, and the \nCommission’s policies aimed at efficiently integrating large loads. \nA. \nMISO’s Proposal To Allow Incumbent Utilities To Determine Access To \nLARS Is Unduly Discriminatory And Will Undermine The Objective Of \nEfficiently Integrating Large Loads \n \nThe current design of LARS will create opportunities for undue discrimination by \nproviding incumbent utilities with the ability to control which interconnection customers are able \nto participate in, and obtain service through, the process.  Even if a generation resource has entered \ninto an agreement to serve large load and otherwise meets the criteria to participate, an \ninterconnection customer will be unable to access LARS without the cooperation and support of \nincumbent utilities within the MISO region.  \nIndeed, from the beginning of the process, incumbent utilities within MISO would have \nthe ability to create barriers to competing suppliers.  As an initial matter, an interconnection \ncustomer would be ineligible to participate in LARS unless the transmission owner that owns the \nfacilities that the customer is planning to interconnect to agrees to the proposed point of \ninterconnection.12  If the interconnection customer and the transmission owner are unable to jointly \nagree on a point of interconnection at least ten business days prior to the next LARS application \ndeadline, then the interconnection customer would be ineligible for the LARS.13  A transmission-\n \n12 LARS Filing, Transmittal Letter at 8.  \n13 Id., Proposed Tariff, Att. X § 3.12.1."},{"page":6,"startToken":1626,"endToken":2117,"text":"6 \n \nowning utility can limit access to LARS by competing suppliers simply by withholding approval \nfor a customer’s proposed point of interconnection.14 \nThe requirement that transmission owners approve a proposed point of interconnection is \nparticularly problematic given MISO’s proposal to require an interconnection customer to \ndemonstrate 100% site control for a customer’s generation facility and interconnection customer \ninterconnection facilities.15  In practice, an interconnection customer seeking to enter LARS could \nobtain site control over the land necessary to reach its proposed point of interconnection only to \nhave the transmission owner propose an alternative point of interconnection that does not align \nwith the customer’s land acquisition strategy.  Even if an interconnection customer is willing to \nshift to the transmission owner’s point of interconnection, an interconnection customer is unlikely \nto have sufficient time to establish site control for a new location given that MISO’s process \ncontemplates that transmission owners will render a decision on a proposed point of \ninterconnection immediately prior to the deadline for submitting a request into LARS. \nNotably, an interconnection customer that clears these hurdles still would be ineligible to \nparticipate in LARS unless it is able to identify an LSE willing to submit an application into the \n \n14 It also appears that a transmission owner could “run out the clock” on an interconnection customer while \nremaining in compliance with applicable rules.  Proposed Section 3.12.1 of Attachment X requires the interconnection \ncustomer to notify the transmission owner 45 calendar days prior to the LARS application deadline and states that the \ninterconnection customer and transmission owner must reach agreement on the point of interconnection at least ten \nbusiness days prior to the application deadline.  This means that there will be approximately 31 calendar days between \nthe deadline for notifying the transmission owner and when the parties must reach agreement.  However, Section \n3.12.1 also states that (1) the transmission owner has up to ten business days (approximately 14 calendar days) after \nreceiving notice from the customer to meet with the interconnection customer and request any information necessary \nto agree on the point of interconnection and (2) that the transmission owner must be given at least 15 business days \n(approximately 21 calendar days) to approve a point of interconnection.  If the 15-business day period does not begin \nrunning until the transmission owner meets with the interconnection customer (or after the interconnection customer \nprovides any required information), the 15-business day period would not run until after the deadline for the \ninterconnection customer to reach agreement on the point of interconnection to enter the LARS process (i.e., ten \nbusiness days prior to the application deadline).  In fact, since Section 3.12.1 states that the transmission owner must \nhave at least 15 business days, the transmission owner could delay a decision well beyond this period without violating \nthe applicable tariff language.  MISO has not demonstrated that this timeline is workable or reasonable.   \n15 LARS Filing, Transmittal Letter at 28."},{"page":7,"startToken":2117,"endToken":2601,"text":"7 \n \nLARS process.  A LARS Application “may only be initiated by the LARS Associated \nTransmission Customer,”16 which MISO describes as the “entity that procures Transmission \nService for load and has a direct relationship with the load” and that “is often a Load Serving \nEntity.”17  As a practical matter, this means that a generation resource being developed to serve a \nlarge load cannot enter LARS unless the transmission customer, typically an LSE and transmission \nowner, elects to sponsor the LARS application.  This limitation on access to LARS applies even \nwhere the generator has site control, an executed agreement with the large load, and is prepared to \nsatisfy all other LARS requirements.   \nMISO has not demonstrated that allowing incumbent utilities to act as gatekeepers to the \nLARS process is just, reasonable, not unduly discriminatory or preferential, and consistent with \nopen access principles.  The Commission and courts have recognized that utilities that own \ngeneration have an incentive to favor their own generation facilities in providing access to the \nelectric grid.18  Indeed, the Commission’s concern that incumbent utilities might favor their own \ngeneration over that of competitors in the interconnection process led the Commission to require \ntransmission providers to adopt a standard set of interconnection procedures to limit the ability of \n \n16 While MISO states that a LARS application may only be initiated by the LARS Associated Transmission \nCustomer and certain proposed tariff provisions reflect that it is the LARS Associated Transmission Customer that “is \nresponsible for submitting the LARS Application,” proposed Section 3.12.1 of Attachment X states that “[p]rior to \nthe applicable Transmission Owner submitting a LARS Application, the potential LARS Interconnection Customer \nand the Transmission Owner shall meet and agree on a definitive Point of Interconnection for the LARS Generating \nFacility.” (emphasis added).  MISO should, at minimum, be required to revise this proposed tariff language to make \nclear that the LARS Associated Transmission Customer is responsible for submitting the LARS application rather \nthan the transmission owner.   \n17 LARS Filing, Transmittal Letter at 6, 7 (“[T]he LARS Application process may only be initiated by the \nLARS Associated Transmission Customer.”).   \n18 E.ON Climate & Renewables North Am., 137 FERC ¶ 61,076, at P 38 (2011), order on reh’g, 142 FERC \n¶ 61,048 (2013), order on reh’g, 151 FERC ¶ 61,264 (2015) (explaining that when discretion in the interconnection \nprocess rests with transmission owner rather than independent system operator it “creates unacceptable opportunities \nfor undue discrimination by affording a transmission owner the discretion to increase the costs of interconnection \nservice.”); PacifiCorp, 171 FERC ¶ 61,112, at P 101 (2020); Cal. Pub. Util. Comm’n v. FERC, 29 F.4th 454, 458-59 \n(9th Cir. 2022) (noting that “the transmission-system owner has natural gatekeeping powers and an incentive to favor \nits own generation facilities in providing access to the electricity grid”); Xcel Energy Servs. v. FERC, 41 F.4th 548, \n561 (D.C. Cir. 2022)."},{"page":8,"startToken":2601,"endToken":3070,"text":"8 \n \nincumbent utilities to provide preferential treatment to their affiliates and erect barriers to the entry \nof competing resources.19  These standardized procedures were intended to limit the discretion of \nincumbent utilities to preference their own generation resources or “delay[] entry into the market \nby new generators.”20 \n \nIn this case, incumbent utilities will have a strong economic incentive to use the discretion \nafforded to them to limit the access of competing suppliers to LARS.  Independent power \nproducers (“IPP”) and incumbent utilities are competing to construct generation within the MISO \nregion necessary to meet the growing demand from large load customers.21  As designed, the \nLARS process will provide incumbent utilities with a new tool that they can use to provide their \nown resources with preferential access to interconnection capacity and bolster their ability to \ncorner the new and significant market for serving data centers and other large loads.  Because \ninterconnection customers that are studied through the standard interconnection queue are likely \nto be processed more slowly and incur higher network upgrade costs than customers processed \nthrough LARS, large loads will have a strong incentive to enter into contracts with resources that \nare able to access the LARS process.  And by using their gatekeeper role in the process to limit \n \n19 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ \n61,103, at P 12 (2003), order on reh’g, Order No. 2003‐A, 106 FERC ¶ 61,220 (2004), order on reh’g, Order No. \n2003‐B, 109 FERC ¶ 61,287 (2005), order on reh’g, Order No. 2003‐C, 111 FERC ¶ 61,401 (2005), aff’d sub nom., \nNat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007). \n20 ESI Energy, LLC v. FERC, 892 F.3d 321, 324 (D.C. Cir. 2018). \n21 See, e.g., Mich. Pub. Serv. Comm’n, MPSC Approves DTE Electric Energy Contracts For Google Data \nCenter, \nProtects \nOther \nCustomers \nFrom \nThe \nProject’s \nCosts \n(Oct. \n1, \n2026), \nhttps://www.michigan.gov/mpsc/commission/news-releases/2026/10/01/mpsc-approves-dte-electric-google-data-\ncenter-and-contracts-protects-customers-from-project-cost; N. States Power Co., Minn. PUC Docket No. M-26-170, \nPetition Requesting Approval of New Large Load Customer Project (Apr. 14, 2026) (petition filed by incumbent \nutility seeking approval of agreements to provide Google subsidiary with 1,900 MWs of power); Verified Joint Petition \nof Northern Indiana Public Service Company LLC (“NIPSCO”) and NIPSCO Generation LLC (“GenCo”) for \nApproval of (1) A Customer-Specific Contract Between NIPSCO and Data Center Customer #2 Pursuant to Ind. Code \n§§ 8-1-2-24 and 8-1-2-25; (2) A Power Purchase Agreement between NIPSCO and GenCo; and (3) Alternative \nRegulatory Plans for Both NIPSCO and GenCo pursuant to Ind. Code §§ 8-1-2.5-5 and 8-1-2.5-6, Cause No. 46393, \nOrder of the Commission (July 23, 2026) (approving agreements for NIPSCO and its generation affiliate to provide \npower to Alphabet, Inc. subsidiary)."},{"page":9,"startToken":3070,"endToken":3393,"text":"9 \n \nIPP access to LARS, incumbent utilities can increase the pressure for large loads to enter into \ncontracts with their own resources or those of their affiliates.   \nThe risk of undue discrimination is not limited only to incumbent utilities vetoing a \nproposed point of interconnection or declining to submit an application into the LARS process for \na competing supplier.  Because LARS applications are processed on a serial, time-stamped basis \nand only a limited number of projects may participate in each study period,22 an incumbent utility \nalso can favor its own generation through more subtle means.  For example, an LSE could submit \na LARS application for its own generation capacity and an associated large load in advance of \nsubmitting a LARS application for a large load customer that has agreed to contract with a \ncompeting supplier to ensure that the application for its own resource is higher in the queue and \nprocessed more quickly than the application for a competing supplier.  \nWhile IPPs will continue to have access to the legacy interconnection queue, this does not \nmean that LARS is not unduly discriminatory or preferential or consistent with open access.  The \nprohibition on undue discrimination mandates that LARS be designed in a manner that provides \nall interconnection customers with comparable access to interconnection service.  A structure that \nprovides incumbent utilities with the ability to discriminate and erect barriers to competing \nsuppliers is inconsistent with this requirement.  And the fact that LARS would be a permanent \nfeature of the MISO market—rather than a one-time process similar to ERAS or similar processes \nthat have been adopted by other markets—only increases the need to scrutinize the proposal to \nensure that it does not create opportunities for undue discrimination.  \nMISO has not demonstrated that the features of LARS described above are necessary to \naddress the reliability needs that LARS seeks to address.  Indeed, expedited large load and paired \n \n22 LARS Filing, Transmittal Letter at 9."},{"page":10,"startToken":3393,"endToken":3995,"text":"10 \n \ngenerator interconnection processes adopted by other transmission providers demonstrate that \nthere is no reason why access to LARS must be conditioned on sponsorship by an incumbent \nutility.  For example, Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Load Generation \nAssessment (“HILLGA”) process—which the Commission has cited as a model process for \nefficiently integrating new large loads with paired generation23—provides customers developing \ngeneration to support a large load the ability to submit a request for interconnection service \ndirectly.  Specifically, under SPP’s HILLGA process a generator supporting one or more high \nimpact large loads (i.e., a “HILL”) is permitted to submit its HILLGA request so long as it is able \nto demonstrate that it is supporting a large load being studied through SPP’s High Impact Large \nLoad Study process.24  MISO has provided no explanation as to why LSEs must play a \n \n23 Show Cause Order at PP 17-19, 115.  See also id. (Comm’r Rosner, concurring at P 14) (“SPP has been a \nleader in showing how to push beyond the status quo.  With its innovative HILLGA proposal, approved by the \nCommission in January, SPP leveraged the opportunity for speed and efficiency by studying load and generation \ntogether, and by creating a limited, expedited interconnection service to connect faster.  By matching the generator’s \noutput to the electrically proximate large load’s demand, the impacts to the grid are less than they otherwise would \nbe, minimizing the need for time-consuming and costly Network Upgrades needed to connect.  HILLGA is one \nsolution that works for SPP, but today’s orders direct other regions to follow SPP’s lead in ways that work for them.”). \n24 See Sw. Power Pool, Inc., Docket No. ER26-247-000, Submission of Tariff Revisions to Add the High \nImpact Large Load Processes and High Impact Large Load Generation Assessment, Transmittal Letter at 24 (Oct. 24, \n2025) (“The submission and eligibility requirements for a HILLGA Request are similar to the requirements in the \nDISIS process.  The HILLGA Customer must submit the following: (1) an executed HILLGA Study Agreement; (2) \na nonrefundable application fee of $20,000; (3) a study deposit of $250,000 for HILLGA Requests up to 500 MW or \na study deposit of $500,000 for HILLGA Requests over 500 MW; (4) demonstration of Site Control; (5) definitive \nPOI; (6) Nameplate Capacity, Maximum Injection Capability, and Network Resource Deliverability (MW) pursuant \nto Appendix 1, Attachment A of Attachment BB; (7) Security deposit equal to $8,000/MW of the requested Maximum \nInjection Capability (‘Financial Security One’); (8) reasonable evidence of satisfaction of one of the listed \ndevelopment milestones; and (9) if applicable, the charging parameters of the Generating Facility that includes at least \none electric storage resource, and a description of any control technologies that will limit the operation of the \nGenerating Facility to the operating assumptions submitted by the HILLGA Customer.”).  See id., Proposed Tariff, \nAtt. BB § 1 (Definitions – HILLGA Customer) (defining HILLGA Customer as “an Interconnection Customer that \nproposes to interconnect its Generating Facility with the Transmission System pursuant to the High Impact Large \nLoad Generation Assessment”); Southwest Power Pool, Inc., Open Access Transmission Tariff, Att. BB § 8.2(g) \n(stating that interconnection customer must provide executed HILL delivery point study agreement or show that such \nan agreement has been executed).  See also Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 69 (2026) (“We find that \nSPP’s HILLGA-related revisions, taken together, accomplish these purposes because they will help ensure that \nHILLGA Customers seeking to serve HILLs are able to interconnect to the transmission system in a timely manner \nand increase the speed of interconnection queue processing.”)."},{"page":11,"startToken":3995,"endToken":4305,"text":"11 \n \ndeterminative role in what generation resources are allowed to access its LARS process when such \nrole is not required under similar processes adopted by other transmission providers. \nMISO attempts to justify its proposal to place incumbent utilities in this gatekeeping role \non the grounds that only a transmission customer can procure transmission service for a large \nload.25  But while that rationale may explain why the transmission customer must participate in \nthe load-side study and obtain any necessary transmission service, it does not address why a \ngenerator—which will independently complete the generation portion of the LARS Application, \nsatisfy the Attachment X requirements, post the required financial security, execute the Large Load \nGenerator Interconnection Agreement, and bear responsibility for network upgrades—must rely \non an LSE to initiate the LARS process.  Indeed, whether an LSE chooses to sponsor a particular \napplication has no bearing on the claimed objectives of MISO’s proposal—i.e., whether the paired \ngeneration is commercially ready, whether it will serve the large load, or whether it will support \nresource adequacy.  If anything, the discretion afforded to LSEs under the LARS proposal may \nresult in projects developed by LSEs being admitted to the LARS process over more commercially \nviable projects developed by IPPs given that there are no objective criteria or oversight imposed \non LSEs for evaluating what projects should be admitted to LARS. \nMISO also defends its proposal by arguing that “Independent Power Producers and other \nkinds of Interconnection Customers are not prohibited from participating in the LARS process.”26  \nBut the fact that MISO’s proposed tariff language does not explicitly prohibit IPPs from \nparticipating in the LARS process is not determinative.  Indeed, the courts and the Commission \nhave found that facially neutral tariff provisions that have the effect of preferencing generation of \n \n25 LARS Filing, Transmittal Letter at 6, 9. \n26 Id. at 7-8."},{"page":12,"startToken":4305,"endToken":4645,"text":"12 \n \nincumbent utilities or providing incumbent utilities with the discretion to preference their own \ngeneration are unduly discriminatory.   \nFor instance, the D.C. Circuit has explained that the fact that a proposal “looks like a non-\ndiscriminatory proposal on the surface,” does not excuse that “in practice its design ‘inherently \nfavor[s]’ … existing [incumbent] generators ‘over developers or owners of third-party \ngeneration’” and is unduly discriminatory.27 Similarly, the Commission rejected a PacifiCorp \nproposal that would have provided LSEs with the option to demonstrate commercial readiness for \ntheir generation facilities by submitting a site-specific purchase order for generating equipment or \na signed statement that the facility will be supplied with generating equipment while requiring \nIPPs to demonstrate that they had an executed term sheet or other reasonable evidence that the \ndeveloper would sell the resource, or the resource’s output, to an LSE or large end-use customer.28  \nThe Commission found that allowing LSEs to meet these criteria by providing a purchase order or \nattestation would impermissibly allow PacifiCorp’s “own generation an easier path to \ndemonstrating readiness than other interconnection customers and could allow PacifiCorp to use \nthe interconnection process to favor its own generation.”29  \nMISO also argues that requiring pre-approval of a proposed point of interconnection by \nthe transmission owner will increase the “efficiency of reviewing the LARS Application” and \n“avoid future disagreements or changes, which can lead to unnecessary or late withdrawals from \nthe study process.”30  But MISO has not demonstrated that transmission owners should have any \n \n27 See Xcel Energy Servs. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022) (quoting Pub. Serv. Co. of Colo., \n172 FERC ¶ 61,297, at P 13 (2020)). \n28 PacifiCorp, 171 FERC ¶ 61,112, at PP 68-69 (2020). \n29 Id. at P 101.  Although the Commission ultimately accepted PacifiCorp’s proposed commercial readiness \ncriteria, it did so only after the criteria were modified to allow IPPs to provide similar evidence as LSEs that they were \ndeveloping a project.  Id. at P 102. \n30 LARS Filing, Transmittal Letter at 8-9."},{"page":13,"startToken":4645,"endToken":4994,"text":"13 \n \nrole in pre-approving a customer’s point of interconnection or that doing so will achieve any of \nMISO’s stated objectives.  A transmission owner’s agreement to a point of interconnection is \nhardly evidence that a proposed point of interconnection is viable.  MISO’s proposed framework \ncontemplates that the parties will reach agreement on the proposed point of interconnection in a \nmatter of weeks immediately prior to the LARS application deadline.  It is unclear what analysis—\nif any—the relevant transmission owner would conduct during this period or the criteria that it \nwould use to evaluate whether to agree to a proposed point of interconnection.  And any assessment \nthat a transmission owner can make during this period is likely to be preliminary and provide no \nassurance that other unforeseen issues will not arise later in the process that render the point of \ninterconnection non-viable.31   \nThere can be little question that the design of LARS will favor incumbent utilities and their \ngeneration resources over third-party developers.  MISO’s proposal does not merely establish \neligibility criteria or commercial readiness requirements that will apply equally to all market \nparticipants.  Rather, it grants incumbent utilities the unilateral ability to determine whether \ncompeting generation projects gain access to an expedited interconnection pathway and when \nthose projects may enter that process.  In practical terms, an incumbent utility can ensure that its \nown generation resources are positioned to receive priority consideration while delaying or \nlimiting access for competing resources.  Here, the risk of undue discrimination is particularly \nacute because incumbent utilities are actively competing to serve large loads and the number of \nprojects that can obtain access to interconnection service through LARS is inherently limited.   \n \n31 Notably, proposed section 3.12.9 of Attachment X states that any modification made by a transmission \nowner after submission of the LARS application, including to the point of interconnection, “shall cause the LARS \nInterconnection Request to be deemed withdrawn.”  Id., Proposed Tariff, Att. X § 3.12.9.  MISO has not demonstrated \nthat it is just and reasonable to withdraw an interconnection customer’s application due to modifications made by the \ninterconnecting transmission owner."},{"page":14,"startToken":4994,"endToken":5303,"text":"14 \n \nIn short, the design of LARS would allow incumbent utilities to play a gatekeeper function \nthat is incompatible with open access and unnecessary to achieve the objectives that LARS seeks \nto achieve.  Rather than creating opportunities for incumbent utilities to discriminate against \ncompeting generation resources, LARS should be designed in a manner that supports the timely \nentry of new generation capacity that is best positioned to meet the demand of large load \ncustomers.  The best way to achieve this objective is to establish a process that is flexible enough \nto allow large load customers to work with potential suppliers to identify and pursue the generation \nsolutions that most align with their needs.  A process that allows incumbent utilities or any other \nmarket participant an opportunity to erect barriers to these arrangements cannot be squared with \nthe stated purpose of the LARS process, the resource adequacy needs of the MISO region, or the \nobjectives of the Show Cause Order.   \nB. \nLARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And \nUnduly Discriminatory  \n \nUnder MISO’s proposal, a LARS application would need to be accompanied by “an \nagreement executed by the Interconnection Customer and either the LARS Associated \nTransmission Customer or the entity that owns or controls the LARS Associated Load evidencing \nthat the output of the Generating Facility for which LARS processing is sought shall be used to \nprovide energy to the LARS Associated Load.”32  MISO proposes to limit the universe of \nacceptable agreements to a PPA or similar off-take agreement, a build-own-transfer agreement, \nand, for LSEs or Alternative Retail Electric Suppliers only, other agreements such as special \ncontracts, large load tariff agreements, or retail service agreements.33   \nThe requirement that a contract evidence that the “output” of a generation facility will be \n \n32 Id., Att. X § 3.12.2(i).  \n33 Id., Att. X § 3.12.2(i)(a)-(c)."},{"page":15,"startToken":5303,"endToken":5648,"text":"15 \n \n“used to provide energy to the LARS Associated Load” has the potential to arbitrarily exclude \ncommercial agreements between generation and loads that align with the objectives underlying \nLARS, support the reliable integration of large loads into the MISO system, and protect ratepayers.  \nImportantly, given the significant financial and commercial risks associated with entering into \nlong-term supply agreements, utilities increasingly are encouraging large loads to take a more \nproactive role in identifying, and entering into contracts with, the generation resources needed to \nmeet their needs.  Although these agreements may involve a physical sale of electricity to the large \nload customer, large load customers and generation resources increasingly are turning to virtual \nPPAs as another option to bring new capacity online.  Under a virtual PPA, a large load enters into \na financially settled arrangement with a generation developer that provides the revenue certainty \nneeded to finance and build a new resource, but does not provide for the transfer of title to energy \nbetween the parties.  Yet, it is not clear that a virtual PPA would qualify an IPP’s project for LARS \ngiven the requirement that the generator’s output “be used to provide energy” to the large load.34 \nMISO has not demonstrated that excluding customers that into enter virtual PPAs and \nsimilar arrangements from LARS is just, reasonable, and not unduly discriminatory or preferential.  \nA virtual PPA does exactly what LARS is meant to encourage: it de-risks a new generation project \nand supports the entry of new capacity necessary to offset the resource adequacy requirements \nassociated with new large loads.  Additionally, a virtual PPA can protect ratepayers by ensuring \nthat the large load—rather than the LSE—is responsible for the costs of the generation resource, \nreducing the risk that customers will be assigned costs for stranded assets.  And since a virtual \nPPA generally calls for the resource to sell its generation into the market, a resource that is \nconstructed based on a virtual PPA will be available to serve the needs of the region as a whole.    \n \n34 Id., Att. X § 3.12.2(i)."},{"page":16,"startToken":5648,"endToken":6045,"text":"16 \n \nUsing a virtual PPA to support new capacity is therefore consistent with the objectives of \nthe Show Cause Order in which the Commission directed MISO to address resource adequacy \nissues associated with integrating new large loads and in the MISO region generally.35  A \nrequirement that excludes arrangements like a virtual PPA that advance the resource adequacy and \nspeed to power objectives the process is designed to advance is not narrowly tailored and should \nbe rejected as unduly discriminatory and preferential.  \nC. \nCo-Located Generation And Load Should Be Permitted To Participate In \nLARS \n \nIn its filing, MISO makes certain statements that could be interpreted as excluding \ngeneration co-located with load from LARS.  For example, MISO states that LARS is intended to \nserve electrically proximate generation and load but that co-located arrangements will be \naddressed through MISO’s separate, pending Zero Injection Generator Interconnection Agreement \n(“ZGIA”) framework.36  MISO states that “the ZGIA process will be utilized to meet the co-located \nportion of the [Large Load Show Cause] Order and LARS will address the electrically proximate \nlarge load portion of the [Large Load Show Cause] Order, by pairing generation with large load in \nthe same [local resource zone (‘LRZ’)],”37 and describes LARS as “differentiated from the co-\nlocation requirements of the ZGIA process.”38  At the same time, nothing in the proposed tariff \n \n35 Show Cause Order at PP 120-22, 127.  See also Midcontinent Indep. Sys. Operator, Inc., Docket No. EL26-\n70-000, Informational Report at 1 (July 20, 2026) (“The unique nature of certain new large loads and the need to help \nensure speed to power, however, brings new challenges that require MISO to continue to work with its states and \nbroader stakeholder community to develop new tools and processes to ensure resource adequacy is maintained going \nforward.… This concentrated and discontinuous load growth requires new processes to most effectively meet this new \ndemand and maintain resource adequacy.”). \n36 LARS Filing, Transmittal Letter at 19 (“While the ZGIA process addresses the generator interconnection \nservice and study framework for generation serving co-located load, LARS will address the distinct study issues \npresented by new generation and large load that are electrically proximate but are not eligible for ZG Interconnection \nService.”).  See also Midcontinent Indep. Sys. Operator, Inc., Docket No. ER26-3552-000, Zero Injection Generator \nInterconnection Agreement (Aug. 18, 2026). \n37 LARS Filing, Transmittal Letter at 20-21.  \n38 Id. at 22."},{"page":17,"startToken":6045,"endToken":6339,"text":"17 \n \nlanguage explicitly prohibits co-located load and generation from participating in the LARS \nprocess. \nCategorically prohibiting co-located generation and load from participating in LARS \nwould be unjust, unreasonable, and unduly discriminatory and preferential.  A co-located \ngeneration and load pair is similarly situated to an electrically proximate pair in every respect \nrelevant to LARS: both involve a formal contractual pairing, both are located in the same LRZ, \nboth would be studied together for their combined system impacts, and both are intended to bring \nnew generation online to serve new large load.  The only difference is that the co-located pair is \ncloser together and less likely to trigger network upgrades.  MISO has not identified any material \ndifference between electrically proximate load and co-located load that would justify allowing one \nto use LARS while excluding the other and it is difficult to see how the greater proximity of co-\nlocated load could justify less favorable treatment in a process that uses proximity as its organizing \nprinciple.  Excluding co-location arrangements would arbitrarily deny an entire class of large load \naccess to interconnection service through LARS. \nExcluding co-location arrangements would also undermine the incentives the Commission \ndirected MISO to pursue in the Show Cause Order and the objectives MISO itself has identified \nfor the LARS process.  Specifically, in the Show Cause Order, the Commission found that co-\nlocating generation with large load or locating it in an electrically proximate area, could reduce \n“the impacts to the transmission system of interconnecting the generating facility to serve that \nelectrically proximate large load or large co-located load … thereby potentially reducing the need \nfor Network Upgrades, which can accelerate the generator interconnection process.”39  \nImportantly, the Commission’s findings on this issue made no distinction between electrically \n \n39 Show Cause Order at P 113."},{"page":18,"startToken":6339,"endToken":6612,"text":"18 \n \nproximate large loads and co-location arrangements.  To the contrary, the Commission \npreliminarily found “that MISO’s Tariff appears to be unjust and unreasonable because it lacks a \ngenerator interconnection study process and/or generator interconnection service to reflect an \ninterconnection customer’s commitment in an interconnection agreement to limit the generating \nfacility’s output to minimize the impact on the transmission system while serving an electrically \nproximate large load or large co-located load.”40   \n  MISO similarly explains that its requirement that a generator and paired load be located \nin the same LRZ is designed to give load “an incentive . . . to bring Generation in a manner that \nmaximizes the positive impact this Generation has on Resource Adequacy.”41  Given that co-\nlocated generation is equally capable of addressing resource adequacy needs as electrically \nproximate load and generation, providing co-located load and generation access to interconnection \nservice through the LARS process would be consistent with the objectives of MISO’s proposal.  \nExcluding co-location arrangements from LARS is arbitrary, unduly discriminatory and \npreferential, and inconsistent with the objectives underlying LARS.  \nII. \nMOTION TO INTERVENE \nGeronimo Power respectfully moves to intervene in this proceeding.  Geronimo Power is \na leading developer of energy projects in North America focused on meeting the needs of the \nnation’s electric grids generally and in light of the anticipated significant increase in demand from \nnew large loads.  Geronimo Power has numerous projects in various stages of development, \nconstruction, and operation in markets throughout the U.S., including in MISO.  Accordingly, \nGeronimo Power has a direct and immediate interest in the outcome of this proceeding which \n \n40 Id. (emphasis added).   \n41 LARS Filing, Transmittal Letter at 10."},{"page":19,"startToken":6612,"endToken":6785,"text":"19 \n \ncannot be adequately represented by any other party.  For these reasons, Geronimo Power’s \nintervention is in the public interest and it respectfully requests that the Commission grant its \nmotion to intervene in this proceeding. \nIII. \nCORRESPONDENCE AND COMMUNICATIONS  \nGeronimo Power respectfully requests that the following names be placed on the official \nservice list for this proceeding by the Commission and that all correspondence and \ncommunications with respect to this proceeding be addressed to the following:42 \nMatthew Morais \nSenior Director, Policy \nKurt Rempe \nAssistant General Counsel \nGERONIMO POWER, LLC \n8400 Normandale Lake Blvd., Ste. 1200 \nBloomington, MN 55437 \nmmorais@geronimopower.com  \nkrempe@geronimopower.com  \n  \nStephen J. Hug \nBen N. Reiter \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \nTel: (202) 887-4084 \nshug@akingump.com \nbreiter@akingump.com   \n \n42 Geronimo Power respectfully requests waiver of Rule 203(b)(3) of the Commission’s regulations, 18 \nC.F.R. § 385.203(b)(3), in order to permit designation of more than two persons for service in this proceeding."},{"page":20,"startToken":6785,"endToken":6875,"text":"20 \n \nIV. \nCONCLUSION \nGeronimo Power respectfully requests that the Commission issue an order consistent with \nthese comments.  \nRespectfully submitted, \n \n/s/ Stephen J. Hug \nMatthew Morais \nSenior Director, Policy \nKurt Rempe \nAssistant General Counsel \nGERONIMO POWER, LLC \n8400 Normandale Lake Blvd., Ste. 1200 \nBloomington, MN 55437 \nmmorais@geronimopower.com  \nkrempe@geronimopower.com  \n  \nStephen J. Hug \nBen N. Reiter \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \nTel: (202) 887-4084 \nshug@akingump.com \nbreiter@akingump.com   \nOn behalf of Geronimo Power \nDated: October 23, 2026"},{"page":21,"startToken":6875,"endToken":6939,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have caused the foregoing document to be served upon the individuals \ndesignated on the Commission’s official service list for this proceeding. \nDated at Washington, D.C., this 23rd day of October 2026. \n \n \n/s/ Stephen J. Hug \n \nStephen J. Hug \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \n(202) 887-4084"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":700,"startToken":0,"endToken":94},{"p":1,"at":700,"title":"I. COMMENTS","method":"printed heading","endPage":5,"endAt":538,"startToken":94,"endToken":1407},{"p":5,"at":538,"title":"A. MISO’s Proposal To Allow Incumbent Utilities To Determine Access To","method":"printed heading","endPage":14,"endAt":1015,"startToken":1407,"endToken":5153},{"p":14,"at":1015,"title":"B. LARS Agreement Eligibility Criteria Are Unnecessarily Restrictive And","method":"printed heading","endPage":16,"endAt":531,"startToken":5153,"endToken":5730},{"p":16,"at":531,"title":"C. Co-Located Generation And Load Should Be Permitted To Participate In","method":"printed heading","endPage":18,"endAt":1258,"startToken":5730,"endToken":6513},{"p":18,"at":1258,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":19,"endAt":237,"startToken":6513,"endToken":6647},{"p":19,"at":237,"title":"III. CORRESPONDENCE AND COMMUNICATIONS","method":"printed heading","endPage":20,"endAt":6,"startToken":6647,"endToken":6786},{"p":20,"at":6,"title":"IV. CONCLUSION","method":"printed heading","endPage":21,"endAt":0,"startToken":6786,"endToken":6875},{"p":21,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":21,"endAt":392,"startToken":6875,"endToken":6939}]}