{"document":{"slug":"rec-20261023-5200","title":"Motion to Intervene and Comments of Invenergy Transmission LLC on the Midcontinent Independent System Operator, Inc.’s Large Load Addition Resource Study filing","issued":"2026-10-23","accession":"20261023-5200","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"Invenergy Transmission LLC","kind":"comments","file":"sources/filings/text/20261023-5200_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261023-5200","tier":"record","sha256":"a2d35665f0a7803b3e3e093b110024e6a044b64d3624a858818a9fe908c1f407","pages":19,"tokens":5762,"emptyPages":[],"textThemes":["study","cost","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":249,"text":"DCACTIVE-89594348.4 \n \n \n1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \nMidcontinent Independent System Operator, Inc.     ) \nDocket No. ER27-25-000 \nMOTION TO INTERVENE AND COMMENTS OF  \nINVENERGY TRANSMISSION LLC \nPursuant to Rules 212 and 214 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”),1 Invenergy Transmission LLC \n(“Invenergy”) hereby submits this motion to intervene and comments on the Midcontinent \nIndependent System Operator, Inc.’s (“MISO”) proposed Large Load Addition Resource Study \n(“LARS”) process, filed in the above-captioned proceeding on October 2, 2026,2 pursuant to \nSection 205 of the Federal Power Act (“FPA”).3 For the reasons set forth below, Invenergy \nrespectfully requests that the Commission direct MISO to clarify that Merchant High Voltage \nDirect Current (“MHVDC”) facilities and generating facilities interconnected to MHVDC are \neligible to participate in LARS, thereby ensuring entities capable of providing capacity to large \nload customers seeking interconnection to the MISO system are able to do so through the LARS \nprocess. \nI. \nMOTION TO INTERVENE \nInvenergy respectfully moves to intervene in this proceeding.4 Invenergy and its affiliates \ndevelop generation and MHVDC transmission lines, including the 800-mile MHVDC Grain Belt \nExpress transmission line, throughout the Midwest region. MHVDC transmission lines are capable \n \n1 18 C.F.R. §§ 385.212, 385.214. \n2 Midcontinent Independent System Operator, Inc., Large Load Addition Resource Study Process, Docket No. \nEL27-25-000 (filed Oct. 2, 2026) (“LARS Filing”). \n3 16 U.S.C. § 824d. \n4 18 C.F.R. § 385.214."},{"page":2,"startToken":249,"endToken":523,"text":"DCACTIVE-89594348.4 \n \n \n \n2 \n \nof serving the large load customers whose interconnection needs are at issue in this proceeding, \nand Invenergy is in fact in advanced commercial negotiations to serve data center load in MISO, \ngiving the company a substantial and direct interest in its outcome that cannot be adequately \nrepresented by any other party. Accordingly, Invenergy requests that the Commission grant this \nmotion, consistent with the public interest. \nII. \nCOMMUNICATIONS \nPlease address all notices and communications regarding this proceeding to the following \npersons who are also designated for service in this proceeding. \nWill Borders, Chief Compliance Officer \nNicole Luckey, Senior Vice President, Regulatory \nAffairs \nInvenergy LLC \nOne South Wacker Drive, Suite 1800  \nChicago, IL 60606  \nTel: 312-224-1400 \nNLuckey@invenergy.com  \nFerccompliance@invenergy.com  \n \nTyler O’Connor \nKathy Lowrey \nKathryn Douglass  \nCrowell & Moring LLP \n600 Fifth St NW \nWashington, DC 20001 \nTel: 202-624-2500  \ntoconnor@crowell.com \nklowrey@crowell.com \nkdouglass@crowell.com  \n \n \nIII. \nINTRODUCTION \nOn October 2, 2026, MISO submitted its LARS Filing, proposing a new study process \nunder Section 3.12 of Attachment X of MISO’s Open Access Transmission, Energy and Operating \nReserve Markets Tariff (“Tariff”) “to facilitate the cost effective, timely and reliable integration \nof new large loads into the system.”5 Under the proposed framework, MISO would coordinate the \nstudy of paired generation and new large loads on an expedited, parallel basis, enabling both to be \nbrought online more efficiently than under existing interconnection procedures.6 With projected \nannual load growth of approximately 1-3% through 2044,7 new processes to facilitate the orderly \n \n5 LARS Filing at 2. \n6 See id. at 5-7, 11-18 (describing the LARS study process). \n7 Id. at 4."},{"page":3,"startToken":523,"endToken":802,"text":"DCACTIVE-89594348.4 \n \n \n \n3 \n \ninterconnection of large loads while safeguarding system reliability for all customers on the MISO \nsystem are necessary. The LARS Filing advances these objectives and is well-aligned with the \ngoals of the Department of Energy’s (“DOE”) Speed to Power Initiative,8 which supports efforts \nto expedite large-scale transmission and generation infrastructure to address rapidly increasing \nelectricity demand while keeping costs affordable and supporting the United States’ AI \ncompetitiveness. The Commission’s Show Cause Order likewise preliminarily found that MISO’s \nexisting Tariff provisions may be unjust and unreasonable to the extent it fails to adequately \naddress the integration of new large loads paired with generation.9 To fully achieve MISO’s stated \npurpose for the filing and to satisfy the objectives of both DOE and the Commission, MHVDC \nand associated generation should be eligible for the LARS process.  \nInvenergy is concerned that, as written, the LARS process inadvertently precludes certain \nentities—including MHVDC transmission lines and their associated generating facilities—from \navailing themselves of this new process, notwithstanding their ability to provide much-needed \ncapacity to large load customers in MISO. Clarification is therefore necessary to ensure that MISO \ndoes not errantly restrict the pool of eligible participants and thereby undermine the efficacy of its \nproposal. \nIV. \nCOMMENTS \nInvenergy respectfully submits the following comments regarding eligibility for \nparticipation in the LARS process. As discussed below, targeted clarifications to the proposed \n \n8 Department of Energy, Speed to Power Initiative (Sept. 18, 2025) (“Speed to Power Initiative”), available at \nhttps://www.energy.gov/oe/speed-power. \n9 Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal \nPower Act, 195 FERC ¶ 61,212 at P 113 (2026) (“Show Cause Order”)."},{"page":4,"startToken":802,"endToken":1097,"text":"DCACTIVE-89594348.4 \n \n \n \n4 \n \nTariff are necessary to ensure that the LARS process is available to all resource types capable of \nserving large load customers. \nA. \nThe Commission Should Direct MISO To Revise Its Proposed Tariff To \nClarify That MHVDC Transmission Lines and Associated Interconnected \nGeneration Should Be Eligible To Participate In LARS. \nAs currently drafted, several of the proposed Tariff definitions identify Generating \nFacilities10 as the sole type of resource that may be paired with a large load customer in the LARS \nprocess. The LARS Filing, however, is intended to facilitate the timely and reliable interconnection \nof large loads to the fullest extent practicable. Achieving this objective requires maximizing the \npool of resources available to serve new large loads. Restricting LARS eligibility to Generating \nFacilities alone would arbitrarily exclude other resource types equally capable of delivering \ncapacity, thereby undermining the very objectives the LARS Filing is designed to advance. \nIn addition to Generating Facilities, two categories of resources are equally capable of \nserving large load customers—MHVDC transmission lines and the generating facilities \ninterconnected to an MHVDC transmission line. These entities can deliver capacity in a manner \nfunctionally equivalent to a directly interconnected Generating Facility, and an MHVDC entity \ncan contract with a large load customer to provide the capacity necessary to serve that customer’s \nload. Indeed, under Attachment X, MHVDC Connection Customers’ requests for injection rights \nare processed through the same study processes as Interconnection Requests submitted by \nInterconnection Customers seeking to interconnect Generating Facilities. MISO’s existing Tariff \nthus treats these requests similarly, and there is no basis for departing from that equivalent \ntreatment in the context of LARS. The manner in which capacity is delivered to the Transmission \n \n10 Capitalized terms not otherwise defined herein have the meaning set forth in MISO’s Tariff."},{"page":5,"startToken":1097,"endToken":1418,"text":"DCACTIVE-89594348.4 \n \n \n \n5 \n \nSystem—whether directly or through an MHVDC transmission line—does not diminish the \nresource’s ability to reliably serve the paired load. \nThat MHVDC transmission lines and their associated generating facilities are equally able \nto timely serve large load customers is further supported by MISO’s own filing. MISO designed \nLARS to “address the electrically proximate large load portion of the [Show Cause] Order, by \npairing generation with large load in the same LRZ.”11 MISO explained that it chose to “anchor” \nthe LARS framework at the Local Resource Zone (“LRZ”) level, rather than on a more narrow \ngeographic basis, so as not to constrain MISO’s ability to optimize transmission solutions.12 \nMHVDC transmission lines can satisfy this same requirement because each MHVDC transmission \nline maintains a designated Point of Connection at which it interconnects to the MISO system \nwithin a given LRZ.13 Accordingly, where a large load’s point of withdrawal is located in the same \nLRZ as an MHVDC transmission line’s Point of Connection, the large load and the MHVDC \ntransmission line are electrically proximate under the LARS framework. MHVDC transmission \nlines and their associated generating facilities should therefore be eligible to participate in the \nLARS process on the same basis as directly interconnected Generating Facilities. \nInvenergy therefore respectfully requests that the Commission direct MISO, on \ncompliance, to revise the proposed Tariff to clarify that MHVDC transmission lines are eligible to \nparticipate in the LARS process, as set forth in the redline attached hereto as Attachment A. There \nis no reason to exclude such resources if they are capable of satisfying all other applicable \neligibility requirements of the LARS process, and their inclusion would meaningfully advance \nMISO’s ability to maintain resource adequacy across the region. \n \n11 LARS Filing at 21.  \n12 See id. at 21. \n13 See Tariff, Attachment X, section 1, Definitions – Point of Connection; see also id. at sections 3.2.4, 16.1, 16.2."},{"page":6,"startToken":1418,"endToken":1705,"text":"DCACTIVE-89594348.4 \n \n \n \n6 \n \nB. \nMHVDC Participation in LARS Advances the Goals of MISO, DOE and \nFERC to Facilitate Timely and Reliable Large Load Interconnection. \nClarifying the categories of resources eligible to participate in the LARS process would \ndirectly advance the objectives of MISO, the DOE, and the Commission to facilitate the timely, \ncost-effective, and reliable interconnection of large loads. \nAs MISO explained, it “designed [the LARS process] to facilitate the reliable integration \nof significant new load and generation on an accelerated timeline.”14 Including MHVDC \ntransmission lines and their associated generating facilities in the pool of resources available \nthrough LARS would afford large load customers the opportunity to contract with a wider and \nmore diverse range of resource types to meet their capacity needs. This clarification is critical \nprecisely because all sources of generation must be available to serve large load. MISO recognizes \nthat “the challenge presented by new large load growth is not limited to connecting the load itself” \nand “[s]ignificant new demand must be accompanied by sufficient resources to maintain reliability \nand resource adequacy.”15 The proposed revisions would advance this mandate by clarifying the \nrange of eligible resource types. \nThe proposed fix would also address the Commission’s concerns in the Show Cause Order, \nin which the Commission preliminarily found MISO’s Tariff unjust and unreasonable for lacking \ngenerator interconnection procedures and services designed to facilitate the integration of new \ngenerating facilities intended to serve electrically proximate large loads.16 The Commission \nemphasized that this deficiency “will result in MISO’s current generator interconnection process \nfailing to keep pace with the new large loads seeking to be integrated onto MISO’s transmission \n \n14 LARS Filing at 5. \n15 Id. \n16 See Show Cause Order at PP 113-119."},{"page":7,"startToken":1705,"endToken":1894,"text":"DCACTIVE-89594348.4 \n \n \n \n7 \n \nsystem,”17 and warned that it would produce “unnecessary interconnection delays, unnecessary \nNetwork Upgrades, and an otherwise inefficient expansion of the transmission system, imposing \nunnecessary delays and costs on transmission customers.”18 Ensuring LARS is available to all \nresources capable of satisfying its eligibility criteria would more fully address these concerns by \nmitigating the delays and inefficiencies identified in the Show Cause Order. \nFinally, the proposed adjustments complement the goals of DOE’s Speed to Power \nInitiative, which aims to “dramatically accelerate development timelines for large-scale \ntransmission and generation projects . . . [and] ensure sufficient power to support American \ncompetitiveness in artificial intelligence while meeting rising demand for affordable, reliable and \nsecure energy.”19 Ensuring that all capable resource types are eligible to participate in the LARS \nprocess is squarely aligned with these objectives and may, in some circumstances, identify sources \nof capacity that can be brought online more rapidly to meet rising demand. \nV. \nCONCLUSION \nFor the foregoing reasons, Invenergy respectfully requests that the Commission consider \nthese comments in acting on MISO’s proposed LARS process. \n \n \n \n17 Id. at P 117. \n18 Id. \n19 See Speed to Power Initiative."},{"page":8,"startToken":1894,"endToken":1931,"text":"DCACTIVE-89594348.4 \n \n \n \n8 \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \nOctober 23, 2026 \n/s/ Tyler O’Connor_ \nTyler O’Connor \nKathryn Douglass \nKathy Lowrey \nCrowell & Moring LLP \n600 Fifth St NW \nWashington, D.C. 20001 \n202-624-2500 \ntoconnor@crowell.com \n \nCounsel for Invenergy Transmission \nLLC"},{"page":9,"startToken":1931,"endToken":1936,"text":"DCACTIVE-89594348.4 \n \n \n \n9 \n \n \n \n \n \n \n \n \nAttachment A"},{"page":10,"startToken":1936,"endToken":2419,"text":"DCACTIVE-89594348.4 \n \n \n \n10 \n \nProposed Revisions: Attachment X \nDefinitions \nInterconnection Customer shall mean any entity, including Transmission Provider, Transmission \nOwner or any of the Affiliates or subsidiaries of either, that proposes to interconnect its Generating \nFacility with the Transmission System. For the purposes of Large Load Addition Resource Study \n(LARS), Interconnection Customer shall refer to the entity developing the Generating Facility, or \nMHVDC Connection Customer, that will execute the LLGIA or Large Load Transmission \nConnection Agreement, as applicable, which may be a different entity from the LARS Associated \nTransmission Customer that submitted the LARS Application.  \n \nInterconnection Request shall mean (1) an Interconnection Customer’s request, in the form of \nAppendix 1 to the Generator Interconnection Procedures, to interconnect a new Generating \nFacility, or a request for the Expedited Resource Addition Study for a new generation capacity, or \na request for the processing of a proposed Generating Facility or an MHVDC Connection \nCustomer’s request as part of a Large Load Addition Resource Study, or to increase the capacity \nof, or make a Material Modification to the operating characteristics of, an Existing Generating \nFacility that is interconnected with the Transmission System, or to interconnect an Existing \nGenerating Facility that is external to the Transmission System, or to change Energy Resource \nInterconnection Service to Network Resource Interconnection Service for an Existing Generating \nFacility; or (2) an MHVDC Connection Customer’s request, in the form of Appendix 1 to the \nGenerator Interconnection Procedures, to obtain Injection Rights.  \n \nLarge Load Addition Resource Study (LARS) shall mean the procedure as set forth in Section \n3.12 of this GIP for studying an Interconnection Customer’s proposed Generating Facility or \nMHVDC Connection Customer’s request in parallel with the study of a LARS Associated Load \nCustomer’s proposed load.  \n \nLarge Load Addition Resource Study (LARS) Period shall mean the period of time in which \nInterconnection Requests for proposed Generating Facility or MHVDC Connection Customer’s \nrequest are studied in parallel with the study of a LARS Associated Load Customer’s proposed \nload. There are three LARS study periods in one year and each study period will run for \napproximately 120 days. All Interconnection Customers requesting to join the next Large Load \nAddition Resource Study (LARS) shall submit their Interconnection Request to the Transmission \nProvider no later than the LARS Application deadline as published on the MISO public website, \nwhich shall be at least twenty (20) Business Days prior to the scheduled kick-off of the LARS \ncycle published on the MISO public website.  \n \nLarge Load Transmission Connection Agreement (LLTCA) shall mean the form of \ntransmission connection agreement for merchant HVDC transmission facilities set forth in \nAppendix 2 to the MHCP, with modifications to reflect the Large Load Addition Resource Study \nProcess. Unless otherwise provided, all requirements applicable to the Transmission Connection \nAgreement shall apply to the LLTCA. A LLTCA is a form of TCA and, where used in the Tariff, \nreferences to Transmission Connection Agreement or TCAs encompasses LLTCAs."},{"page":11,"startToken":2419,"endToken":2868,"text":"DCACTIVE-89594348.4 \n \n \n \n11 \n \n \nLARS Application shall be a single submission consisting of the materials required for LARS \nprocessing as required by Section I.D.1.b.ii of Attachment FF to the Tariff as well as the \ninformation required for studying the Generating Facilities or the MHVDC Connection \nCustomer’s request under this Attachment X (in the form of Appendix 1) to these generator \ninterconnection procedures. For purposes of this GIP, a LARS Application shall be a form of \nInterconnection Request.  \n \nLARS Associated Load shall mean a source of electrical load that is at least 200 MW and that is \nformally paired with one or more Interconnection Customer(s) that have submitted an \nInterconnection Request to LARS proposing one or more new Generating Facility(ies) or an \nMHVDC Connection Customer’s request to provide energy to such load.  \n \nSection 3.2 \nAt the time the Interconnection Request is submitted, Interconnection Customer must \nrequest NR Interconnection Service, ER Interconnection Service or Surplus Interconnection \nService, as described; provided, however, any Interconnection Customer requesting NR \nInterconnection Service may also request that it be concurrently studied as an ER \nInterconnection Service, up to the expiration of Interconnection Customer Decision Point II. \nInterconnection Customer may then elect to proceed with NR Interconnection Service or to \nproceed under a lower level of NR Interconnection Service to the extent that only certain \nupgrades will be completed. A description of the modeling details used when studying a project \nas ER Interconnection Service or NR Interconnection Service can be found in Section 6 of the \nGenerator Interconnection Business Practices Manual (BPM-015). MHVDC Connection \nCustomer may only request Injection Rights pursuant to Section 16 or Section 3.12 of the GIP \nand shall not be eligible to receive any Interconnection Services specified in the GIP. \nSection 3.5.4 \nSection 3.5.4 \n(3) In the event that affected systems studies and cost information are not available at the time \nthe LLGIA or LLTCA is tendered, such LLGIA or LLTCA shall include an obligation to execute \nany agreements for the study, construction, or funding of Network Upgrades identified by the \nAffected System within fifteen (15) Calendar Days after such agreement is tendered for \nexecution to the Interconnection Customer . . .  \nSection 3.12.1 \nPrior to the applicable Transmission Owner submitting a LARS Application, the potential LARS \nInterconnection Customer and the Transmission Owner shall meet and agree on a definitive \nPoint of Interconnection for the LARS Generating Facility or MHVDC Transmission Line. . . . \n \nThe Transmission Owner will have a minimum of fifteen (15) Business Days to provide an \nattestation and approve a valid Point of Interconnection. The Transmission Owner and LARS \nInterconnection Customer shall jointly agree upon a feasible Point of Interconnection no later"},{"page":12,"startToken":2868,"endToken":3309,"text":"DCACTIVE-89594348.4 \n \n \n \n12 \n \nthan ten (10) Business Days prior to the next LARS Application deadline as published on the \nMISO public website. An Interconnection Request seeking LARS Interconnection Service must \ninclude an attestation that the Transmission Owner and LARS Interconnection Customer have \nagreed upon the Point of Interconnection for the Generating Facility or MHVDC Transmission \nLine for which LARS processing is sought.  \n \nSection 3.12.2 \n(i) The Interconnection Request shall be accompanied by an agreement executed by the \nInterconnection Customer and either the LARS Associated Transmission Customer or the entity \nthat owns or controls the LARS Associated Load evidencing that the output of the Generating \nFacility or MHVDC Transmission Line for which LARS processing is sought shall be used to \nprovide energy to the LARS Associated Load. . . . \n \n(iv) The Interconnection Request shall include a one-line diagram showing the Generating \nFacility(ies) or MHVDC Transmission Line and associated electrical equipment with appropriate \nrating and impedance information.  \n \n(v) The Interconnection Request shall include a detailed power flow model for the proposed \nGenerating Facility or MHVDC Transmission Line that includes the Point of Interconnection for \nthe Interconnection Request and any proposed system protection facilities. Such model must be \nsubmitted in a format specified by the Generator Interconnection Business Practices Manual and \nalign with the data provided in the Interconnection Request, including the one-line diagram \nrequired in Section 3.12.2.iv of these GIP. . . . \n \n(vii) The Interconnection Request seeking LARS processing shall specify a Commercial \nOperation Date for the Generating Facility or MHVDC Transmission Line and a date by which \nthe LARS Associated Load shall commence service for the full amount of transmission service \nrequested in the LARS Application that is not later than three (3) years from the date such \nInterconnection Request is submitted. . . . \n \nNo changes shall be made to the LARS Application after submission and prior to the execution \nor the unexecuted filing of the LLGIA or LLTCA and MTEP approval for the LARS Associated \nLoad except that a LARS Application that is deferred to the next available LARS Study Period \nwill be allowed to extend its In-Service Date or Commercial Operation Date to be no more than \nthree calendar years from the kickoff of the LARS Study Period in which its LARS Application \nis studied. . . . \n \nSection 3.12.4 \nThe Interconnection Study for LARS will follow the same manner of NR Interconnection Study \nas noted in Sections 3.2.1.2 and 3.2.2.2 needed to integrate the Generating Facility in the same \nmanner as for any Generating Facility being designated as a Network Resource. Transmission \nProvider will use Reasonable Efforts to study LARS Interconnection Requests from all"},{"page":13,"startToken":3309,"endToken":3733,"text":"DCACTIVE-89594348.4 \n \n \n \n13 \n \nInterconnection Customers regardless of Generating Facility or MHVDC Transmission Line \nwithin sixty (60) Calendar Days after the kickoff date for such study. . . . \nSection 3.12.5 - Notice to Proceed to LLGIA or LLTCA. \nSection 3.12.6 \nTransmission Provider shall tender a draft pro forma LLGIA or LLTCA, as applicable, that \nconforms to the pro forma GIA or pro forma TCA in effect at the time, as modified for LARS, \nno later than 90 Calendar Days after the date LARS studies commence for such Interconnection \nRequest with a confirmed Notice to Proceed… Upon tender of the LLGIA or LLTCA, the LARS \nInterconnection Request shall be subject to the timing and procedures set forth in Sections 11.1 \nthrough 11. 4 of these GIP. \n \nTransmission Provider shall include in the final LLGIA or LLTCA any Affected System Study \nresults and information regarding Network Upgrades from Affected Systems provided the \nAffected System Study Reports are available. If Affected System analysis is not available for \ninclusion in the final LLGIA or LLTCA, the Transmission Provider shall provide such analysis \nseparately when received from the applicable Affected System. . . . \n \nSection 3.12.7.2 \nInterconnection Customers are eligible to receive one hundred percent (100%) refund of the \nLarge Load Addition Resource Study entry milestone (M2) upon withdrawal prior to execution \nor unexecuted filing of the final LLGIA or LLTCA. Interconnection Customers that terminate \nthe LLGIA or LLTCA after execution or unexecuted filing are eligible to receive a refund of the \nremaining M2 milestone payment.  \nSection 3.12.7.3 \nIn the event the Interconnection Customer has elected to make its milestones in the form of cash, \nTransmission Provider will transfer the Large Load Addition Resource Study milestone to the \nappropriate Transmission Owner to satisfy the initial payment requirement of the Large Load \nGenerator Interconnection Agreement, TCA or other applicable service agreement within the \ntimeline specified in the Appendix B of the LLGIA or Exhibit B11 of the LLTCA. Provided that \nthe Interconnection Customer has not requested withdrawal, is deemed withdrawn, or is pending \ntermination of its applicable service agreement, the Transmission Provider shall refund milestone \ncash payments exceeding the initial payment requirement to the Interconnection Customer upon \nInterconnection Customer’s request with Transmission Owner’s consent, within forty-five (45) \nCalendar Days of the later effective date of the LLGIA, or LLTCA, or other applicable \nconstruction agreements. In the event the milestone payments are less than the initial payment \nrequirement, the Interconnection Customer shall be responsible for the remaining payment to the \nTransmission Owner.  \nSection 3.12.7.4"},{"page":14,"startToken":3733,"endToken":4251,"text":"DCACTIVE-89594348.4 \n \n \n \n14 \n \nIn the event that the Interconnection Customer’s LLGIA or LLTCA is terminated after execution \nby all parties or after LLGIA or LLTCA is filed unexecuted, the Interconnection Customer will \nbe responsible for the costs of the Network Upgrades that are classified as GIPS and documented \nin the LLGIA, LLTCA, and/or corresponding FCAs or MPFCAs, including those GIP Network \nUpgrades arising from the Affected System Study process. . . . \n \nIn the event that the LARS Associated Load is withdrawn from LARS or ceases use of the \nTransmission Service granted through LARS within the first fifteen (15) Calendar Years after the \nLARS Associated Load commences use of the Transmission Service granted through LARS, \nthen operations of the Generating Facility shall be subject to the Annual ERIS (“AERIS”) and \nQuarterly Operating Limit (“QOL”) for a one year period until termination as set forth in Article \n2.3.1 of Attachment X Appendix 6 or the LLTCA. An Interconnection Customer that desires to \ncontinue injections shall be required to obtain Interconnection Service or injection rights through \nthe DPP as described in Attachment X. The LLGIA will be terminated after the period specified \nin Article 2.3.1, or applicable injection rights under the LLTCA, as relevant. Following the first \nfifteen (15) Calendar Years after a LARS Associated Load ceases use of its Transmission \nService or if the agreement required by GIP Section 3.12.2.i is terminated or otherwise ceases to \nbe in effect, then Transmission Provider shall not terminate the Generating Facility’s \nInterconnection Service or the MHVDC Connection Customer’s injection rights with respect to \nthe LARS Associated Load. \n \nOnce MTEP approval occurs for the LARS Associated Load, the LARS Associated \nTransmission Customer remains responsible for the identified BRPs and Other assigned projects \neven if such LARS Associated Load does not commence service. In addition, if the LLGIA or \nLLTCA for a LARS Associated Load is terminated, the LARS Associated Transmission \nCustomer remain responsible for the costs thereof. . . . \n \nSection 3.12.9 \nAfter submission of the LARS Application, no modification to the Interconnection Request or \nany of its parameters, including any information provided by the Transmission Owner such as \nthe agreed-upon Point of Interconnection, is permitted under Section 4.4 or otherwise prior to the \nexecution or unexecuted filing of the final LLGIA or LLTCA. Any modification made by the \nInterconnection Customer, LARS Associated Transmission Customer, or Transmission Owner \nprior to the execution or unexecuted filing of the final LLGIA or LLTCA shall cause the LARS \nInterconnection Request to be deemed withdrawn.  \n \nAfter entering the Large Load Addition Resource Study as defined in Section 3.12.4, no changes \nto the In-Service Date or Commercial Operation Date of the Generating Facility is permitted via \nsection 4.4.4 except that a LARS Application that is deferred to the next available LARS Study \nPeriod will be allowed to extend its In-Service Date or Commercial Operation Date to be no \nmore than three calendar years from the kickoff of the LARS Study Period in which its LARS \nApplication is studied. At the completion of the Large Load Addition Resource Study, the"},{"page":15,"startToken":4251,"endToken":4768,"text":"DCACTIVE-89594348.4 \n \n \n \n15 \n \nCommercial Operation Date and Service Commencement Date for the LARS Associated Load \nshall be set forth in the LLGIA or LLTCA. . . . \n \nSection 11.1 \nThroughout this Section 11, the applicable Interconnection Facilities Study for a GIA shall be the \nInterconnection Facilities Study that was initiated for that project in DPP Phase II. For EGIAs, \nLLTCAs, or LLGIAs, this shall be the applicable Interconnection Facilities Study initiated \nthrough ERAS or LARS. Throughout this Section 11, the applicable Interconnection Facilities \nStudy for a Network Upgrade that is addressed in a FCA or MPFCA or GIA shall be the \nInterconnection Facilities Study performed for that Network Upgrade. For Interconnection \nRequests initiated through LARS, the Final System Impact Study shall be the LARS System \nImpact Study.   \nSection 11.3 \nTransmission Provider shall provide to Interconnection Customer and Transmission Owner a \nfinal GIA, and, as applicable, final JTIQ Service Agreement(s), final FCA(s) and/or final \nMPFCA(s) prepared for execution by the parties within fifteen (15) Business Days after the \ncompletion of the forty (40) Business Day negotiation period in accordance with Section 11.2 of \nthis GIP. For Interconnection Requests for an ERAS, the Transmission Provider shall provide to \nInterconnection Customer and Transmission Owner a final EGIA within ten (10) Business Days \nafter the completion of the negotiation period in accordance with Section 11.2 of this GIP. For \nLARS Interconnection Requests, the Transmission Provider shall provide to Interconnection \nCustomer and Transmission Owner a final LLGIA or LLTCA executed by Transmission \nProvider, within fifteen (15) Business Days after the completion of the negotiation period in \naccordance with Section 11.2 of this GIP. Within forty-five (45) Calendar Days of tender of the \nfinal GIA, and within fifteen (15) Business Days for LLGIA and LLTCA, and, as applicable, \nfinal JTIQ Service Agreement(s), final FCA(s) and final MPFCA(s), Interconnection Customer \nand Transmission Owner shall either: (i) execute the tendered GIA or LLGIA, and, as applicable, \nfinal JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s); or (ii) request in writing that \nTransmission Provider file with FERC the GIA, LLGIA, LLTCA, and, as applicable, JTIQ \nService Agreement(s), FCA(s) and/or MPFCA(s) in unexecuted form.  \nIf Interconnection Customer has neither executed the GIA, LLTCA, or LLGIA, and, as \napplicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s), nor requested filing \nof the GIA, LLGIA, or LLTCA, and, as applicable, JTIQ Service Agreement(s), FCA(s) and/or \nMPFCA(s) in unexecuted form within forty-five (45) Calendar Days, or for Interconnection \nRequests in an ERAS ten (10) Business Days, or for Interconnection Requests in LARS fifteen \n(15) Business Days, of tender of the final GIA, LLGIA, LLTCA, and, as applicable, JTIQ \nService Agreement(s), final FCA(s) and final MPFCA(s), Interconnection Customer shall be \ndeemed to have withdrawn its Interconnection Request. The Interconnection Customer’s forty-\nfive (45) Calendar Day deadline for execution will not reset in the event that an additional \nchange is made to the GIA, LLGIA, LLTCA, JTIQ Service Agreement(s), FCA, or MPFCA after \ncirculation for execution."},{"page":16,"startToken":4768,"endToken":5233,"text":"DCACTIVE-89594348.4 \n \n \n \n16 \n \nWithin ten (10) Business Days after receiving from the Interconnection Customer(s) and the \nTransmission Owner either the executed tendered GIA, LLTCA or LLGIA, and, as applicable, \ntendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) or the request to file an \nunexecuted GIA, LLTCA or LLGIA, and, as applicable, tendered JTIQ Service Agreement(s), \nFCA(s) and/or MPFCA(s), Transmission Provider shall report or file the GIA, LLTCA or \nLLGIA, and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) with \nFERC, together with its explanation of any matters as to which Interconnection Customer, \nTransmission Owner and Transmission Provider disagree and support for the costs that \nTransmission Owner proposes to charge to Interconnection Customer under the GIA, LLTCA or \nLLGIA and, as applicable, tendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s). An \nunexecuted GIA, LLTCA or LLGIA, and, as applicable, JTIQ Service Agreement(s), FCA(s) \nand/or MPFCA(s), shall contain terms and conditions deemed appropriate by Transmission \nProvider for the Interconnection Request.  \nSection 11.4 \nIf Interconnection Customer executes the final GIA, LLTCA, or LLGIA and, as applicable, \ntendered JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) Transmission Provider, \nTransmission Owner and Interconnection Customer shall perform their respective obligations in \naccordance with the terms of the GIA, LLTCA, or LLGIA and, as applicable, tendered JTIQ \nService Agreement(s), FCA(s) and/or MPFCA(s), subject to modification by FERC. Unless \notherwise agreed by all Parties, upon submission of an unexecuted GIA, LLTCA, or LLGIA, \nand, as applicable, unexecuted tendered JTIQ Service Agreement(s), unexecuted FCA(s) and/or \nunexecuted MPFCA(s), the Parties shall promptly comply with the unexecuted GIA, LLTCA, or \nLLGIA, and, as applicable, unexecuted JTIQ Service Agreement(s), unexecuted FCA(s) and/or \nunexecuted MPFCA(s), subject to modification by FERC. As applicable, compliance with the \nterms of such unexecuted JTIQ Service Agreement(s), FCA(s) and/or MPFCA(s) or execution \nand performance under a JTIQ Service Agreement(s), FCA and/or MPFCA will be a requirement \nunder the GIA, LLGIA or LLTCA.  \nAppendix 1 \n1. [The undersigned Interconnection Customer submits this request to interconnect its Generating \nFacility, located in ______________ County, [ State], with the Transmission System pursuant to \nthe Tariff.] or;  \n[The undersigned MHVDC Connection Customer submits this request for Injection Rights for its \nMHVDC Transmission Line, located in ______________ County, [ State], with the \nTransmission System pursuant to a Tariff.];  \n[The undersigned Interconnection Customer submits this request to interconnect its Generating \nFacility, located in ______________ County, [ State], located in ____________County, \n[________State], with the Transmission System pursuant to the Tariff as part of a LARS \nApplication.] [The undersigned Interconnection Customer submits this request to interconnect its \nMHVDC Transmission Line and/or Generating Facility, located in ______________ County, ["},{"page":17,"startToken":5233,"endToken":5620,"text":"DCACTIVE-89594348.4 \n \n \n \n17 \n \nState], located in ____________County, [________State], with the Transmission System \npursuant to the Tariff as part of a LARS Application.]  \n4.j. An agreement executed by the Interconnection Customer and the entity that owns or controls \nthe LARS Associated Load evidencing that the output of the Generating Facility or MHVDC \nTransmission Line for which LARS processing is sought is intended to be used to provide energy \nto the LARS Associated Load. Such agreement shall meet the requirements of Section 3.12.2 of \nthe Generator Interconnection Procedures (for LARS Application);  \n4.l. The attestation required by Section 3.12.1 of the Generator Interconnection Procedures \nconfirming agreement upon the Point of Interconnection for the Generating Facility or MHVDC \nTransmission Line (for the LARS Application). \n \nAppendix 1, Attachment A-4 \nA LARS Interconnection Request seeking Interconnection Service shall include:  \n(1) A detailed power flow model for the proposed Generating Facility or MHVDC \nTransmission Line…  \n \nProposed Revisions: Attachment FF \nSection I.D.1.b.ii(c) \nThe anticipated Service Commencement Date for the LARS Associated Load listed in the LARS \nApplication shall be no later than three calendar years from the submission date of the LARS \nApplication and shall be identical to the Commercial Operation Date listed for the Generating \nFacility or MHVDC Transmission Line in the LARS Interconnection Request.  \n \nSection I.D.1.b.ii(g) - Termination of LLGIA, LLTCA, and/or Withdrawal of Large Load \nIn the event that the Interconnection Customer’s LLGIA or LLTCA is terminated after execution \nby all parties or after LLGIA or LLTCA is filed unexecuted, the Interconnection Customer will \nbe responsible for the costs of the Network Upgrades that are classified as GIPS and documented \nin the LLGIA, LLTCA and/or corresponding FCAs or MPFCAs, including those GIP Network \nUpgrades arising from the Affected System Study process. \n \nOnce MTEP approval occurs for the LARS Associated Load, the LARS Associated \nTransmission Customer remains responsible for the identified BRPs and Other assigned projects \neven if such LARS Associated Load does not commence service or commences service for less \nthan the total amount of the LARS Associated Load. In addition, if the LLGIA or Large Load \nTransmission Connection Agreement for a LARS Associated Load is terminated, the LARS \nAssociated Transmission Customer remain responsible for the costs thereof. . . . \n  \nSection I.D.1.b.ii(j)"},{"page":18,"startToken":5620,"endToken":5707,"text":"DCACTIVE-89594348.4 \n \n \n \n18 \n \nIn accordance with the LARS definitions, Section 3.3.1, and Section 3.12 of Attachment X, and \nnotwithstanding the requirements of Section I.D.1.b.ii, a generating solution that does not yet \nhave generator interconnection agreement filed with the Commission pursuant to Attachment X \nof this Tariff may be considered as an alternative transmission solution if: (1) a valid \nInterconnection Request for such Generating Facility has been submitted for processing under \nthe LARS process specified by Attachment X to the Tariff . . ."},{"page":19,"startToken":5707,"endToken":5762,"text":"DCACTIVE-89594348.4 \n \n \n \n19 \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that on this 23rd day of October, 2026, a copy of the foregoing document \nhas been electronically served upon each person designated on the official service list in this \nproceeding. \n \n/s/ Kathy Lowrey_ \nKathy Lowrey \n600 Fifth St NW \nWashington, D.C. 20001 \nklowrey@crowell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1177,"startToken":0,"endToken":165},{"p":1,"at":1177,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":2,"endAt":464,"startToken":165,"endToken":317},{"p":2,"at":464,"title":"II. COMMUNICATIONS","method":"printed heading","endPage":2,"endAt":1088,"startToken":317,"endToken":399},{"p":2,"at":1088,"title":"III. INTRODUCTION","method":"printed heading","endPage":3,"endAt":1452,"startToken":399,"endToken":727},{"p":3,"at":1452,"title":"IV. COMMENTS","method":"printed heading","endPage":4,"endAt":163,"startToken":727,"endToken":826},{"p":4,"at":163,"title":"A. The Commission Should Direct MISO To Revise Its Proposed Tariff To","method":"printed heading","endPage":6,"endAt":32,"startToken":826,"endToken":1421},{"p":6,"at":32,"title":"B. MHVDC Participation in LARS Advances the Goals of MISO, DOE and","method":"printed heading","endPage":7,"endAt":1135,"startToken":1421,"endToken":1859},{"p":7,"at":1135,"title":"V. CONCLUSION","method":"printed heading","endPage":9,"endAt":46,"startToken":1859,"endToken":1934},{"p":9,"at":46,"title":"Attachment A","method":"printed heading","endPage":19,"endAt":35,"startToken":1934,"endToken":5710},{"p":19,"at":35,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":357,"startToken":5710,"endToken":5762}]}