{"document":{"slug":"rec-20261027-0003-2","title":"20261027-0003_Part1 (1)","issued":"2026-10-27","accession":"20261027-0003","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"EXELON CORPORATIONAMERICAN TRANSMISSION SYSTEMS, INCORPORATEDJERSEY CENTRAL POWER & LIGHT COMPANY ,KEYSTONE APPALACHIAN TRANSMISSION COMPANY ,MID-ATLANTIC INTERSTATE TRANSMISSION LLC ,MONONGAHELA POWER COMPANY ,THE POTOMAC EDISON COMPANY ,TRANS-ALLEGHENY INTERSTATE LINE COMPANY ,APPALACHIAN POWER COMPANY ,INDIANA MICHIGAN POWER COMPANY ,KENTUCKY POWER COMPANY ,KINGSPORT POWER COMPANY ,OHIO POWER COMPANY ,WHEELING POWER COMPANY ,AEP APPALACHIAN TRANSMISSION COMPANY INC ,AEP INDIANA MICHIGAN TRANSMISSION COMPANY, INC. ,AEP KENTUCKY TRANSMISSION COMPANY INC ,AEP OHIO TRANSMISSION COMPANY INC ,AEP WEST VIRGINIA TRANSMISSION COMPANY INC ,THE DAYTON POWER AND LIGHT COMPANY DBA AES OHIO ,VIRGINIA ELECTRIC AND POWER COMPANY D/B/A DOMINION ENERGY VI ,DUQUESNE LIGHT COMPANY ,EAST KENTUCKY POWER COOPERATIVE, INC. ,PPL ELECTRIC UTILITIES CORPORATION ,ROCKLAND ELECTRIC COMPANY ,","kind":"attachment","file":"sources/filings/text/20261027-0003_002.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261027-0003","tier":"record","parent":"rec-20261027-0003","sha256":"b6dff68475569ac1531d24ce36654468c277584a498a01d46539a5e49547dc92","pages":292,"tokens":113740,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":120,"text":"STAN BERMAN PLLC \n3502 FREMONT AVENUE N., SUITE 1 \nSEATTLE, WASHINGTON 98103 \n6 L _0 \no \nek, \nit.O7-boo \noe21.0,- / 409-  6\") \nOctober 21, 2026 \nStan Berman \nDirect Dial (206) 321-3221 \nstan@bermlaw.com \nRe: \nExelon Corp. et al. v FERC, Case No. 26-3621 (3rd Circuit) \nFERC Docket Nos. EL25-20, AD24-11, EL25-49 \nHonorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, D.C. 20426 \nDear Secretary Reese, \nEnclosed is a date-stamped copy of a Petition for Review that was filed in the \nThird Circuit Court of Appeals on October 16, 2026. \nRespectfully submitted, \n/s/ Stan Berman  \nStan Berman \nStan Berman PLLC \n3502 Fremont Ave N, #1 \nSeattle, WA 98103 \n(206) 321-3221 \nstan@bermlaw.com"},{"page":2,"startToken":120,"endToken":300,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 1 \nDate Filed: 10/16/2026 \nIN THE UNITED STATES COURT OF APPEALS \nFOR THE THIRD CIRCUIT \nExelon Corp.; American Transmission Systems, \nIncorporated, Jersey Central Power & Light Company, \nKeystone Appalachian Transmission Company, Mid-Atlantic \nInterstate Transmission LLC, Monongahela Power \nCompany, The Potomac Edison Company, and Trans-\nAllegheny Interstate Line Company; American Electric \nPower Service Corporation on behalf of its affiliates, \nAppalachian Power Company, Indiana Michigan Power \nCompany, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power \nCompany, AEP Appalachian Transmission Company, Inc., \nAEP Indiana Michigan Transmission Company, Inc., AEP \nKentucky Transmission Company, Inc., AEP Ohio \nTransmission Company, Inc., and AEP West Virginia \nTransmission Company, Inc.; The Dayton Power and Light \nCompany d/b/a AES Ohio; Dominion Energy Services, Inc. \non behalf of Virginia Electric and Power Company d/b/a \nDominion Energy Virginia; Duquesne Light Company; East \nKentucky Power Cooperative, Inc.; PPL Electric Utilities \nCorporation; and Rockland Electric Company, \nPetitioners, \nv. \nFederal Energy Regulatory Commission, \nRespondent. \nPETITION FOR REVIEW \nNo. 26-\nPetitioners—collectively, the Indicated PJM Transmission Owners—are \n1 \n1 of 515"},{"page":3,"startToken":300,"endToken":539,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 2 \nDate Filed: 10/16/2026 \nExelonl; FirstEnergy?; American Electric Power Service Corporation on behalf of \nits affiliates, Appalachian Power Company, Indiana Michigan Power Company, \nKentucky Power Company, Kingsport Power Company, Ohio Power Company, \nWheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP \nIndiana Michigan Transmission Company, Inc., AEP Kentucky Transmission \nCompany, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia \nTransmission Company, Inc.; The Dayton Power and Light Company d/b/a AES \nOhio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power \nCompany d/b/a Dominion Energy Virginia; Duquesne Light Company; East \nKentucky Power Cooperative, Inc.; PPL Electric Utilities Corporation; and \nRockland Electric Company. \nPursuant to Section 313(b) of the Federal Power Act, 16 U.S.C. § 8251(b), and \nFederal Rule of Appellate Procedure 15(a), Petitioners hereby petition this Court for \nreview of the following orders and notices of the Federal Energy Regulatory \nExelon refers collectively to Exelon Corporation, on behalf of its affiliates Atlantic \nCity Electric Company, Baltimore Gas and Electric Company, Commonwealth \nEdison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva \nPower & Light Company, PECO Energy Company, and Potomac Electric Power \nCompany. \nFirstEnergy and the FirstEnergy Transmission Companies collectively to American \nTransmission Systems, Incorporated, Jersey Central Power & Light Company, \nKeystone \nAppalachian \nTransmission \nCompany, \nMid-Atlantic \nInterstate \nTransmission LLC, Monongahela Power Company, The Potomac Edison Company, \nand Trans-Allegheny Interstate Line Company. \n2 \n2 of 515"},{"page":4,"startToken":539,"endToken":765,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 3 \nDate Filed: 10/16/2026 \nCommission (FERC): \nPJM Interconnection, L.L.C. et al.; Order on Show Cause Proceeding, \nDirecting Compliance Filings, Establishing Paper Hearings, and Granting in \nPart and Denying in Part Complaint, 193 FERC ¶ 61,217 (December 18, 2025) \n(Attached as Attachment A). \nPJM Interconnection, L.L.C. et al.; Notice of Denial of Rehearing By \nOperation of Law and Providing for Further Consideration, 194 FERC \n¶ 62,089 (Feb. 20, 2026) (Attached as Attachment B). \nPJM Interconnection, L.L.C. et al.; Order on Rehearing, Clarification, \nCompliance Filing, and Paper Hearings, 195 FERC ¶ 61,209 (June 18, 2026) \n(Attached as Attachment C). \nPJM Interconnection, L.L.C. et al.; Notice of Denial of Rehearing By \nOperation of Law and Providing for Further Consideration, 196 FERC \n¶ 62,089 (Aug. 20, 2026) (Attached as Attachment D). \nThe Indicated PJM Transmission Owners petition for review of these orders on the \ngrounds that the Commission's orders are arbitrary and capricious, reflect a failure \nto engage in reasoned decision-making, are not supported by substantial evidence, \nand are otherwise contrary to law. \nExelon and FirstEnergy separately filed petitions for review of the first two of \nthese orders earlier this year (Case Nos. 26-1901 and 26-2494). Those cases have \nbeen consolidated, along with two petitions filed by the PJM Industrial Customer \n3 \n3 of 515"},{"page":5,"startToken":765,"endToken":925,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 4 \nDate Filed: 10/16/2026 \nCoalition et al. (Case Nos. 26-1840 and 26-3122). The PJM Transmission Owners \nPetitioners suggest this case be consolidated with these four prior cases.2 \nBecause the Commission denied the petitioners' most-recent request for \nrehearing by operation of law on August 19, 2026, this petition for review is timely. \nPursuant to Federal Rule of Appellate Procedure 15(c) and 18 C.F.R. \n§ 385.2012, a copy of this Petition will be served by mail upon the Respondent, \nRobert H. Solomon, FERC Solicitor, 888 First Street, NE, Washington, DC 20426, \nand Debbie-Anne Reese, FERC Secretary, 888 First Street, NE, Washington, DC \n20426, and by email on each party in the proceeding below (Service List is \nAttachment E). \na All the cases are currently held in abeyance until the earlier of December 31, 2026 \nor when FERC issues its order on further reconsideration in the underlying \nproceeding. \n4 \n4 of 515"},{"page":6,"startToken":925,"endToken":1083,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 5 \nDate Filed: 10/16/2026 \nRespectfully submitted, \nGary Guy \nAssistant General Counsel \nExelon Corporation \n701 Ninth St. N.W. \nWashington, DC 20068 \n301-956-6754 \ngary.guy@exeloncorp.com \n/s/ Stan Berman  \nStan Berman \nStan Berman PLLC \n3502 Fremont Ave. N. #1 \nSeattle, WA 98103 \n206-321-3221 \nstan@bermlaw.com \nAttorneys for Exelon Corporation \nOn behalf of the Indicated PJM Transmission Owners \nMorgan E. Parke \nAssociate General Counsel \nAmanda Parker \nCorporate Counsel \nFirstEnergy Services Company \n341 White Pond Dr. \nAkron, OH 44320 \n(330) 730-8558 \nmparke@firstenergycorp.com \naparker@firstenergycorp.com \nDavid M. Gossett \nMichael Kunselman \nDavis Wright Tremaine LLP \n1301 K Street, NW, Ste. 500-E \nWashington, DC 20005 \n(202) 973-4200 \ndavidgossett@dwt.com \nmichaelkunselman@dwt.com \nAttorneys for the FirstEnergy Transmission Companies \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp. \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTel. 610.774.4775 \nSMNadel@pplweb.com \nAttorney for PPL Electric Utilities Corp. \n5 \n5 of 515"},{"page":7,"startToken":1083,"endToken":1158,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 6 \nDate Filed: 10/16/2026 \nDavid Samford \nEast Kentucky Power Cooperative, Inc. \nPO Box 707 \nWinchester, KY 40392-0707 \n859-744-4812 \ndavid.samford@ekpc.coop \nAttorney for East Kentucky Power Cooperative, Inc. \nWilliam M. Rappolt \nAssistant General Counsel, FERC \nAES US Services LLC \n4300 Wilson Blvd \nArlington, VA 22203 \n(703) 682-6337 \nWilliam.rappolt@aes.com \nAttorney for Dayton Power and Light Company d/b/a AES Ohio \n6 \n6 of 515"},{"page":8,"startToken":1158,"endToken":1299,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 7 \nDate Filed: 10/16/2026 \nCarrie L. Bumgarner \nSenior Counsel \nAmerican Electric Power Service \nCorporation \n1 Riverside Plaza \nColumbus, OH 43215 \n(614) 716-2941 \nclbumgarner@aep.com \nAttorney for American Electric Power Service Corporation on behalf of its \naffiliates Appalachian Power Company, Indiana Michigan Power \nCompany, Kentucky Power Company, Kingsport Power Company, Ohio \nPower Company, Wheeling Power Company, AEP Appalachian \nTransmission Company, Inc., AEP Indiana Michigan Transmission \nCompany, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio \nTransmission Company, Inc., and AEP West Virginia Transmission, Inc. \nSteven G. Boughton \nDominion Energy Services, Inc. \nSenior Counsel, Federal Regulatory \n120 Tredegar Street \nRiverside Building, Fifth Floor \nRichmond, VA 23219 \nsteven.boughton@dominionenergy.com \n(804) 718-5988 \nAttorney for Dominion Energy Services, Inc. on behalf of Virginia Electric and \nPower Company d/b/a Dominion Energy Virginia \n7 \n7 of 515"},{"page":9,"startToken":1299,"endToken":1353,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 8 \nDate Filed: 10/16/2026 \nMichael Brechlin \nManager Asst GC - Regulatory Law State Regulatory \nDuquesne Light Company \nNova Place \n100 South Commons, Suite 118 \nMail Drop OGC-L1 \nPittsburgh, PA 15212 \nPhone: 412-393-6431 \nEmail: mbrechlin@duqlight.com \nAttorney for Duquesne Light Company \nOctober 16, 2026 \n8 of 515 \n8"},{"page":10,"startToken":1353,"endToken":1505,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 9 \nDate Filed: 10/16/2026 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing Petition for Review \nto be served by email on the service list in the proceeding below (see Attachment E \nfor list of recipients), and, pursuant to Rule 2012 of the FERC Rules of Practice and \nProcedure, 18 C.F.R. § 385.2012, have this day caused to be served a date-stamped \ncopy of the foregoing documents on Respondent FERC both by email and by US \nMail to the FERC Solicitor, Robert Solomon, 888 First St. NE, Washington, DC \n20426, and by US mail to the FERC Secretary, Debbie-Anne Reese, 888 First St. \nNE, Washington, DC 20426. \nDated at Seattle, WA, October 16, 2026. \n/s/ Stan Berman  \nStan Berman \nStan Berman PLLC \n3502 Fremont Ave. N. #1 \nSeattle, WA 98103 \n206-321-3221 \nstan@bermlaw.com \n9 of 515 \n1"},{"page":11,"startToken":1505,"endToken":1555,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 10 \nDate Filed: 10/16/2026 \nATTACHMENT A \nPJM Interconnection, L.L.C. et al.; Order on Show Cause Proceeding, \nDirecting Compliance Filings, Establishing Paper Hearings, and \nGranting in Part and Denying in Part Complaint, 193 FERC ¶ 61,217 \n(December 18, 2025). \n10 of 515"},{"page":12,"startToken":1555,"endToken":1756,"text":"Document Accessicq \ngt4p.k18 _34qcumenwrjd  atlizie:A),Bipte Filed: 10/16/2026 \n193 FERC ¶ 61,217 \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nBefore Commissioners: Laura V. Swett, Chairman; \nDavid Rosner, Lindsay S. See, \nJudy W. Chang, and David LaCerte. \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-000 \nAllegheny Electric Cooperative, Inc. \nEL25-49-001 \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \n11 of 515"},{"page":13,"startToken":1756,"endToken":2009,"text":"DoCument Acce-ssiccia:\n gt§gA18 - 3 E-lacumentiilAd DraEle:inis/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n2 \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nAD24-11-000 \nConstellation Energy Generation, LLC \nEL25-20-000 \n(Consolidated) \nv. \nPJM Interconnection, L.L.C. \nORDER ON SHOW CAUSE PROCEEDING, DIRECTING COMPLIANCE FILINGS, \nESTABLISHING PAPER HEARING, AND GRANTING IN PART AND DENYING \nIN PART COMPLAINT \n(Issued December 18, 2025) \n1. \nOn March 24, 2025, PJM Interconnection, L.L.C. (PJM) and the PJM transmission \nowners filed answers in Docket No. EL25-49-000, to comply with the Commission's \nFebruary 20, 2025 order establishing a show cause proceeding, under section 206 of the \nFederal Power Act (FPA).1  The Show Cause Order directed PJM and the transmission \nowners to either: (1) show cause as to why the Open Access Transmission Tariff \n(OATT), the Amended and Restated Operating Agreement of PJM, and the Reliability \nAssurance Agreement Among Load Serving Entities in the PJM Region (the Tariff) \nremains just and reasonable and not unduly discriminatory or preferential without \n1  PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (Show Cause Order). \n12 of 515"},{"page":14,"startToken":2009,"endToken":2505,"text":"Document Accessig4 a§q: ?pAp 3:18 _3gqcurrleq.ilr j d DeaReAh8/pate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 3 \nprovisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions of service that apply to Co-Location Arrangements;2  or (2) explain what \nchanges to the Tariff would remedy the identified concerns if the Commission were to \ndetermine that the Tariff has in fact become unjust and unreasonable or unduly \ndiscriminatory or preferential and, therefore, proceeds to establish a replacement Tariff. \nThe Show Cause Order consolidated the new show cause proceeding with a pending \ncomplaint proceeding in Docket No. EL25-20 involving Co-Located Load.3 \n2. \nAs discussed below, we find that PJM's Tariff is unjust and unreasonable because \nit does not contain provisions addressing with sufficient clarity or consistency the rates, \nterms, and conditions of service that apply to generators serving Co-Located Load and \nEligible Customers taking transmission service on behalf of Co-Located Load.4 \nSpecifically, we find that PJM's Tariff is unjust and unreasonable because it does not \ninclude types of transmission service that reflect Eligible Customers taking service on \nbehalf of Co-Located Loads that are willing and able to limit their use of the transmission \nsystem under certain conditions. We direct PJM to file, within 60 days of the date of \nissuance of this order, a compliance filing to revise its Tariff to set forth specific terms \nand conditions that an Interconnection Customers  in PJM seeking to serve \n2  The Show Cause Order defined Co-Location Arrangements as referring to both \nthe Co-Located Load and the associated generator. Id P 3 & n.4. \n3  The Show Cause Order defined Co-Located Load as a \"configuration [that] \nrefers to end-use customer load that is physically connected to the facilities of an existing \nor planned Customer Facility on the Interconnection Customer's side of the Point of \nInterconnection to the PJM Transmission System.\" Id \nThe PJM Tariff defines an Eligible Customer as (1) any electric utility or any \nperson generating electric energy for sale for resale, but with respect to transmission \nservice that the Commission is prohibited from ordering by section 212(h) of the Federal \nPower Act, such entity is eligible only if the service is provided pursuant to a state \nrequirement that the Transmission Provider or Transmission Owner offer the unbundled \ntransmission service, or pursuant to a voluntary offer of such service by a Transmission \nOwner or (2) any retail customer taking unbundled transmission service pursuant to a \nstate requirement that the Transmission Provider or a Transmission Owner offer the \ntransmission service, or pursuant to a voluntary offer of such service by a Transmission \nOwner. PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions — E-F (41.0.0). An Eligible \nCustomer may include but is not limited to electric utilities and power marketers. \n5  PJM defines Interconnection Customer as a Generation Interconnection \nCustomer and/or a Transmission Interconnection Customer. PJM, Intra-PJM Tariffs, \nOATT, § I.1 Definitions - I - J - K (15.0.0) \n13 of 515"},{"page":15,"startToken":2505,"endToken":2985,"text":"Document AccessiA a4c: 4'2§P?ii8-311qcurnent'ili-Jd Dftle:iMs/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n4 \nCo-Located Load must follow in order to effectuate a Co-Location Arrangement. We \nalso direct PJM to file, within 30 days of the date of issuance of this order, a compliance \nfiling to revise its Tariff to make clear how Interconnection Customers can make use of \nprovisional interconnection service, the ability to request interconnection service below \nnameplate capacity, the potential to accelerate the interconnection process under certain \ncircumstances, and surplus interconnection service to interconnect new generating \nfacilities seeking to serve Co-Located Load. In addition, we direct PJM to modify its \nTariff to require that the Eligible Customer taking transmission service on behalf of the \nCo-Located Load takes one of three transmission services: (1) Network Integration \nTransmission Service (NITS), (2) a new Firm Contract Demand transmission service, or \n(3) a new Non-Firm Contract Demand transmission service.6  We establish a paper \nhearing to determine the just and reasonable rates, terms, and conditions for these new \ntransmission services. We further find that the Behind the Meter Generation (BTMG) \nrules in PJM's Tariff are no longer just and reasonable because loads with BTMG are not \nfully accounted for in resource adequacy planning and shift costs onto other transmission \ncustomers contrary to the Commission's cost causation principles. We therefore direct \nPJM to revise its Tariff to revise the BTMG rules and to implement a transition process \nfor existing BTMG participants, as described below. We also grant in part and deny in \npart Constellation Energy Generation, LLC's (Constellation) complaint against PJM in \nDocket No. EL25-20-000. Finally, we require PJM to submit an informational report \nwithin 30 days of the date of issuance of this order. \nI. \nBackground \nA. \nShow Cause Order \n3. \nThe Show Cause Order defined Co-Located Load as a \"'configuration [that] refers \nto end-use customer load that is physically connected to the facilities of an existing or \nplanned Customer Facility on the Interconnection Customer's side of the Point of \nInterconnection to the PJM Transmission System.'\"7  As the Commission did in the Show \n6  Capitalized terms used but not otherwise defined in this order have the meanings \nascribed to them in the Tariff. \nShow Cause Order, 190 FERC ¶ 61,115 at P 3 & n.4. We note that, in the Show \nCause Order, the Commission adopted this definition from the Guidance Document that \nPJM developed on Co-Located Load. See id. As noted below, PJM rescinded this \ndocument pending Commission guidance in this docket. PJM March 24 Answer at 33. \nPrior to PJM's transition to its new interconnection process, PJM used the terms \nInterconnection Customer and Generation Interconnection Customer. PJM's Tariff \ndefines Generation Interconnection Customer as \"an entity that submits \nan Interconnection Request to interconnect a new generation facility or to increase the \ncapacity of an existing generation facility interconnected with the Transmission \n14 of 515"},{"page":16,"startToken":2985,"endToken":3379,"text":"Document AccessicciaW ikgpiki8 _3pRcurnentiiirid Dpage:11 18/pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 5 \nCause Order, when referring to both the Co-Located Load and the associated generator, \nwe will use the term Co-Location Arrangement. \n4. \nAs explained in the Show Cause Order, Co-Location Arrangements are becoming \nincreasingly common in PJM and, since the issuance of the Show Cause Order, entities \ncontinue to raise issues involving Co-Location Arrangements with the Commission.8  The \nCommission instituted the Show Cause Order to determine whether the Tariff remains \njust and reasonable and not unduly discriminatory or preferential.9  The Commission set \nforth, in the Show Cause Order, the principles relating to the Commission's jurisdiction \nover the matters relevant to Co-Location Arrangements.10  The Commission also made \nseveral preliminary findings about the justness and reasonableness of the Tariff. First, \nthe Commission found that the Tariff appears to be unjust and unreasonable or unduly \ndiscriminatory or preferential because it does not contain provisions addressing with \nsufficient clarity or consistency the rates, terms, and conditions of service that apply to \nCo-Location Arrangements.\" In addition, the Commission preliminarily found that this \nSystem in the PJM Region.\" PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions — G - H \n(9.0.1) (defining Generation Interconnection Customer). The Tariff's new rules for \ngeneration interconnection, effective January 3, 2023, utilize the terms Project Developer \nand Generation Project Developer. PJM's Tariff defines Generation Project Developer as \n\"an entity that submits a Generation Interconnection Request to interconnect a new \ngeneration facility or to increase the capacity of an existing generation facility \ninterconnected with the Transmission System in the PJM Region.\" PJM, Intra-PJM \nTariffs, OATT, § VIII.A 400 Definitions G (0.1.0) (defining Generation Project \nDeveloper). For ease of simplicity in this order, and consistent with the Show Cause \nOrder, the Commission will use the term Interconnection Customer to refer to both the \nPJM Tariff definitions of Generation Interconnection Customer and Generation Project \nDeveloper. \n8  See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,112 (2025) (accepting \nnecessary studies agreement). The Show Cause Order consolidated the new show cause \nproceeding with a pending complaint proceeding in Docket No. EL25-20-000 involving \nCo-Located Load. We address that complaint below. See discussion infra Part IV.B.7. \n9  Show Cause Order, 190 FERC ¶ 61,115 at P 2. \n18  Id. P66. \n\" Id. P 74. \n15 of 515"},{"page":17,"startToken":3379,"endToken":3770,"text":"Document Accessiccia§e:  g2§gkl8 -3 PicicurnenWrla DrOcite:11Pis/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n6 \nlack of applicable Tariff provisions raises the potential for undue discrimination or \npreferential treatment.I2 \n5.\nAs to specific concerns raised regarding Co-Location Arrangements, the \nCommission found that the Tariff may be unjust, unreasonable, unduly discriminatory, or \npreferential as it does not specify the transmission service that Co-Location \nArrangements must take, if any, or otherwise provide a process to ensure that Co-\nLocation Arrangements are paying for the benefits they receive from the transmission \nsystem consistent with the cost causation principle, which provides that all Commission-\njurisdictional rates and charges must \"reflect to some degree the costs actually caused by \nthe customer who must pay for them,\" and that costs must be allocated in a manner that is \nat least roughly commensurate with the benefits that entity receives.13  The Commission \nalso found that the absence of rates, terms, and conditions of interconnection service \nspecific to Co-Location Arrangements, and, especially regarding studies of the impacts of \nthose arrangements, may render the Tariff unjust and unreasonable or unduly \ndiscriminatory or preferential.14  Moreover, the Commission found that the absence of \nrates, terms, and conditions governing the use and sale of ancillary services and black \nstart services by Co-Location Arrangements may render the Tariff unjust and \nunreasonable or unduly discriminatory or preferential.'' \n6.\nThe Commission also expressed concern about the reliability and resource \nadequacy implications of Co-Location Arrangements.16  The Commission stated that it \nwas concerned that the Tariff may be unjust and unreasonable and unduly discriminatory \nor preferential insofar as it lacks rules necessary to provide PJM with sufficient \ninformation to perform appropriate analysis to ensure reliable system operations given \nthe characteristics of Co-Location Arrangements. In response to concerns about the \nmarket and price impacts of Co-Location Arrangements, the Commission recognized that \nthese concerns are not necessarily unique to Co-Location Arrangements and that \nsignificant load growth more generally may raise many of the same concerns.17  The \n12 Id. P75. \n13  Id. PP 74-78 (citing Midwest ISO Transmission Owners v. FERC, 373 F.3d \n1361, 1368 (D.C. Cir. 2004); Ill. Corn. Comm'n v. FERC, 576 F.3d 470, 476 (7th Cir. \n2009)). \n14  Id. P 79. \n15  Id. P 82. \n16  Id. P 83. \n17  Id. PP 84-85. \n16 of 515"},{"page":18,"startToken":3770,"endToken":4208,"text":"Document A„es sicaa§c:  ?P2*218 - 3gqcumentiiirid DDsge:11118/pae Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n7 \nCommission stated that, while both Co-Located Load and non-co-located load may have \nsimilar resource adequacy impacts, the speed at which Co-Located Load can be added to \nthe grid may pose particular resource adequacy challenges, especially if Co-Location \nArrangements are not adequately and transparently reflected in existing resource \nadequacy planning mechanisms, e.g., the PJM capacity market.18 \nB. \nBehind the Meter Generation \n7.\nRegarding PJM's BTMG rules (which we and commenters sometimes refer to as \nretail BTMG),19  the Tariff allows load serving entities (LSEs) that provide service to \nloads with qualifying BTMG to reduce their costs by netting output from BTMG in the \ncalculation of their peak demand for the purpose of determining NITS charges.20  The \nCommission has previously found that BTMG netting is just and reasonable because it \nwould encourage load response during periods when generation or transmission are in \nshort supply and prices are rising.21  The Commission has also found that \"charges for \nuse of PJM's transmission system should be allocated to network customers based on a \nnetwork customer's actual use of PJM's system, consistent with the principle of cost \ncausation.\"22 \n8.\nTransmission rates for NITS and Point-to-Point Service (PTPS) are based on \ntransmission formula rates filed by the transmission owners. Transmission formula rates \ncapture utilities' cost of providing transmission service and include the cost of operating \nand maintaining the transmission facilities, depreciation expenses, taxes, and a rate of \n181d. P 85. \n19  PJM defines BTMG as \"a generation unit that delivers energy to load without \nusing the Transmission System or any distribution facilities (unless the entity that owns \nor leases the distribution facilities has consented to such use of the distribution facilities \nand such consent has been demonstrated to the satisfaction of the Office of the \nInterconnection); provided, however, that [BTMG] does not include (i) at any time, any \nportion of such generating unit's capacity that is designated as a Generation Capacity \nResource; or (ii) in an hour, any portion of the output of such generating unit that is sold \nto another entity for consumption at another electrical location or into the PJM \nInterchange Energy Market.\" PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - A-B \n(21.0.0) (defining BTMG). \n20  See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 6 (2004); PJM, \nIntra-PJM Tariffs, OATT, § III.34.2 Netting of Behind the Meter Generation (0.0.0). \n21  PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at PP 27-28. \n22 Id. P 28. \n17 of 515"},{"page":19,"startToken":4208,"endToken":4631,"text":"Document Acceseiccia,4q: \n_ 34qcument.i1Ad DFage:11818/pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 8 \nreturn for the utility. The rates also include the costs of any Network Upgrades needed to \nensure ongoing reliability or deliverability of generation to Network Load,23  including \nplanned regional transmission upgrades. Transmission rates are charged based on \ndemand coincident with the annual peak(s) of the zone.24  For loads using BTMG, only \nthe net demand is used for billing, but for loads not relying on BTMG, transmission \ncharges are based on their gross use of the transmission system at the time of the \ncoincident peak.25 \n9.\nRecognizing that Co-Location Arrangements may interact with the transmission \nsystem in a similar way to BTMG arrangements, the Show Cause Order sought briefing \non how any proposed replacement rate adopted in this proceeding would interact with \nexisting BTMG arrangements.26 \nC. \nEligible Customer \n10.\nIn Order No. 888 and its progeny, the Commission established specific criteria for \npotential transmission customers to be eligible to receive non-discriminatory open access \ntransmission service.27  Consistent with the Commission's findings about who is an \n23  PJM defines Network Load as the load that a Network Customer designates for \nNITS, including all load served by the output of any Network Resources designated by \nthe Network Customer. See PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - L-M-N \n(51.0.1) (defining Network Load). \n24  See id. § III.34.1 Monthly Demand Charge (1.0.0). PJM's 22 transmission \nzones represent the geographical areas served by individual PJM transmission owners. \nSee id., attach. J (8.0.0). \n25  See id § III.34.2 Netting of Behind the Meter Generation (0.0.0). \n26  Show Cause Order, 190 FERC ¶ 61,115 at P 88, pt. a.iv (\"parties may also ... \nconsider how any proposed replacement rate would interact with [BTMG] \narrangements\"). \n27  See, e.g., Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., \nOrder No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC \n¶ 61,080), order on reh'g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,214 \n(modifying definition of Eligible Customer) (cross-referenced at 78 FERC ¶ 61,220), \norder on reh'g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh'g, Order \nNo. 888-C, 82 FERC ¶ 61,046 (1998), aff'd in relevant part sub nom. Transmission \nAccess Pol 'y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (TAPS), aff'd sub nom. \nNew York v. FERC, 535 U.S. 1 (2002). \n18 of 515"},{"page":20,"startToken":4631,"endToken":4840,"text":"Document Access ici a§e:  gt§g118-3PRCUMentiilAci DFaae:11918/p@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 9 \neligible customer in the pro forma tariff, PJM's Tariff currently defines an Eligible \nCustomer as: \n(i) Any electric utility ... or any person generating electric \nenergy for sale for resale ... However, with respect to \ntransmission service that the Commission is prohibited from \nordering by Section 212(h) of the Federal Power Act, such \nentity is eligible only if the service is provided pursuant to a \nstate requirement that the Transmission Provider or \nTransmission Owner offer the unbundled transmission \nservice, or pursuant to a voluntary offer of such service by a \nTransmission Owner. \n(ii) Any retail customer taking unbundled transmission service \npursuant to a state requirement that the Transmission Provider \nor a Transmission Owner offer the transmission service, or \npursuant to a voluntary offer of such service by a Transmission \nOwner, is an Eligible Customer under the Tariff....28 \n11. \nThis definition forms the basis for PJM's existing transmission cost allocation \napproach, through which each Eligible Customer is billed for the charges associated with \nthe transmission services used to serve its load. \n28  PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - E-F (41.0.0) (defining \nEligible Customer). \n19 of 515"},{"page":21,"startToken":4840,"endToken":5244,"text":"Document Accessiga.§c:  ?g2-§gi.18-3,4qcu me n\n-Aci. DE\"t3ae:3.?918/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 10 - \nH. \nPJM's Answer to Show Cause Order and Responsive Pleadings29 \nA. \nPJM's Options for Co-Location Arrangements  \n12.\nPJM states that its existing Tariff remains just and reasonable \"although \nimprovements and clarifications may be appropriate based on Commission guidance.\"3° \nAs further detailed below, PJM discusses eight pathways to facilitating co-location \nservice, three of which exist in the current Tariff and five of which would be new. PJM \nsupports only five of the eight options and identifies problems with the remaining three. \nPJM requests that, if \"the record supports consideration of additional options,\" the \nCommission issue detailed guiding principles that PJM can operationalize in an FPA \nsection 205 filing.31 \n13.\nPJM notes that the options are not mutually exclusive and instead may be used \nseriatim or concurrently. PJM further clarifies that it does not consider all of the options \n\"equivalent, desirable, or even necessarily workable.\"32  For example, PJM argues that \nstate law may limit the availability of various options. PJM also notes that six of its \noptions are premised on large Co-Located Load being Network Load, where the large \nCo-Located Load would realize significant benefits. PJM also argues that Co-Location \nArrangements implicate several different, interrelated study frameworks and cost \nallocation constructs. PJM further notes that there is a resource adequacy dimension to \nCo-Location Arrangements and explains that three of its potential new options relate to \nadding additional supply and operational flexibility. \n14.\nTurning to the eight options, first, PJM states that new loads may interconnect as \ntraditional Network Load that takes NITS in accordance with traditional load \n29  The appendix lists the entities who intervened and filed responsive pleadings in \nDocket No. EL25-49-000, along with short names. On March 21, 2025, then-Chairman \nChristie responded individually to comments filed with the Commission by Pennsylvania \nGovernor Josh Shapiro of Pennsylvania on October 4, 2024, and by Virginia Governor \nGlenn Youngkin on November 1, 2024, respectively, on data centers and Co-Located \nLoad. On April 2, 2025, then-Chairman Christie responded to a letter filed on \nFebruary 19, 2025, by United States Senators Chris Van Hollen, Cory A. Booker, \nMark Kelly, and Tim Kaine inquiring about a technical conference addressing data \ncenters and other large new loads. \n3°  PJM March 24 Response at 4. \n31  Id. \n32  Id at 5. \n20 of 515"},{"page":22,"startToken":5244,"endToken":5690,"text":"Document AccessiAa§c: gtgp,21_ 3g1qcumeq,i11-jd DWREte:13118/p@tfi Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 11 - \ninterconnection processes (PJM option 1).33  PJM states that the load uses and pays for \nNITS, energy, ancillary services, and capacity. PJM explains that the load has a separate \npoint of interconnection with the grid and thus need not be at the same site as the \ngenerator. PJM supports this option. \n15.\nSecond, PJM explains that load could co-locate with generation behind the same \npoint of interconnection (PJM option 2).34  PJM states that, in this configuration, the load \nis Network Load and the generator is a Capacity Resource, each separately metered, with \nno change to the generator's Capacity Interconnection Rights. PJM states that the load \nuses and pays for NITS, energy, ancillary services, and capacity. PJM also explains that \nthe large load is studied and could be connected to the grid under existing load \ninterconnection processes. PJM supports this option. \n16.\nThird, PJM states that a Network Load could co-locate with generation and then \nuse PJM's BTMG rules under which the load would be charged for its net use of the grid, \nafter deducting BTMG (PJM option 3).35  PJM states that the load uses NITS, energy, \nancillary services, and capacity and pays for these services based on the net peak \nwithdrawal quantity. PJM does not support this option, explaining that historically, \nBTMG has supported relatively small loads, not on the scale of large data centers. PJM \nfurther states that charging load for its net use of the grid under the BTMG rules may not \ncapture the costs caused by co-located data center arrangements because such \narrangements could avoid all costs by netting to zero if the entire data center load is \nsupplied by the associated generator.36 \n17.\nFourth, turning to new options not currently in the existing Tariff, PJM explains \nthat a possible Co-Located Load configuration could include a load located behind a \ngenerator, with system protection facilities in place to prevent the delivery of system \nenergy to serve the load (PJM option 4). PJM states that \"in this configuration, load is \nnot Network Load unless designated by the customer subject to applicable state law.\"37 \nPJM explains that the load is located behind the Point of Change of Ownership between \nthe transmission owner and generator, and system protection facilities are installed to \nprevent delivery of system energy from the grid if the generator goes offline. PJM \nclarifies that this configuration should not be considered \"fully\" or \"wholly\" isolated, \n33  Id. at 10. \n34  Id. at 11. \n35  Id. at 12-13. \n36  Id at 36. \n37  Id. at 14. \n21 of 515"},{"page":23,"startToken":5690,"endToken":6122,"text":"Document Accessircia§C:  ?§2§3:18-311qcurnentiiirad DPaCte:i??1.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 12 - \narguing that it is inconsistent with engineering and economic principles.38  PJM argues \nthat the configuration relies on and takes grid services (e.g., ancillary services) and \nshould pay its fair share of those charges. PJM does not support this option, raising \nconcerns that this configuration carries operational risk because it depends on a \nprotection system to support reliability, and, if the protection system fails, the large load \nwould instantly take significant energy from the system. PJM argues that, though a few \nsuch configurations may seem tolerable, the risk increases with large quantities of such \nconfigurations. \n18.\nFifth, PJM identifies a new option that is the same configuration as PJM option 4, \nbut the load can receive back-up service from the grid with PJM's advanced authorization \n(PJM option 5).39  PJM clarifies that this option requires real-time, bespoke operational \ndecision-making to determine if load can continue to be served. PJM explains that \napproval for back-up service is subject to condition, including withdrawing or \nwithholding authorization if needed to protect grid reliability or integrity. PJM does not \nsupport this option, because, like PJM option 4, the load is not designated as Network \nLoad, which concerns PJM because of the dependence on protection schemes.4° \n19.\nSixth, PJM discusses a new option that would allow new large Network Load \nadditions to bring additional generation that could serve as a Capacity Resource (PJM \noption 6).4' The additional generation, PJM clarifies, could take different forms, such as \nnew incremental generation, generation that has or is scheduled to deactivate, or existing \ngeneration so long as the generator is available to PJM as a Capacity Resource if it clears \nin the capacity market. PJM indicates that incentives could be explored to offer faster \nprocessing of generation that enters the queue under this option, such as (1) accelerating \ninterconnection studies of new generation, (2) enhancing existing provisional \ninterconnection service options at discrete study points to accelerate in a \nnon-discriminatory manner the ability of new generation to achieve commercial \noperation, and (3) states assuming cost responsibility for transmission upgrades in the \nRegional Transmission Expansion Plan pursuant to the State Agreement Approach to \npromote state policies to encourage large load development. PJM clarifies that a physical \nco-location configuration can be used, but the new generation may additionally enter a \nbilateral agreement with the load for financial or contractual purposes. PJM states that \n3s Id. \n39  Id. at 15. \n4°  Id. at 39. \n41 Id. at 16-17. \n22 of 515"},{"page":24,"startToken":6122,"endToken":6538,"text":"Document Accessigna§e:  g`I§P121.18 - 3 gtqcumentiiirid DFacie:IP \n, 18/ :pate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 13 - \nthis option would involve an interconnection study for the new generation resource. PJM \nsupports this option. \n20.\nSeventh, PJM discusses a new option that would allow a new large load to become \nNetwork Load at a potentially faster pace subject to the load electing a new transitional \nnon-capacity backed service offering (PJM option 7).42  PJM states that large loads would \nhave the option to be classified as a non-capacity backed load for a transitional period \nuntil any resource adequacy supply/demand imbalances associated with this load addition \nare addressed. Then, PJM explains, the load could assume full Network Load status. \nPJM states that, under this offering, the load would avoid capacity costs during the \ntransition period in return for its willingness to curtail. PJM indicates that variations of \nthis option could be explored to enhance resource adequacy and allow large loads to \nefficiently connect to the system through incentives to be flexible. PJM states that a \nphysical co-location configuration can be used but all load would be in front of the meter. \nPJM supports this option. \n21.\nEighth, PJM discusses a new option where Co-Located Load that is Network Load \nmay be able to participate in the PJM wholesale markets as a Demand Response resource \n(PJM option 8).43  PJM explains that this option already exists in PJM but there could be \nan additional review of Demand Response rules or review of emissions restrictions on \nback-up generation to enhance this option, potentially requiring Tariff revisions. PJM \nstates that back-up generation provides a way to serve the Co-Located Load when asked \nto curtail for Demand Response. PJM contends that this option may enhance resource \nadequacy under tight system conditions in the short term. PJM supports this option. \nB. \nGeneral  \n1. \nPJM's March 24 Response \n22.\nPJM argues that the Tariff remains just and reasonable.44  PJM argues that its \nTariff is not unjust and unreasonable merely because it does not provide alternative \npathways to accommodate a business goal. However, as noted, PJM discusses \neight pathways, acknowledging that \"clarifications and enhancements could well be in \norder given this is an evolving area and Tariff provisions did not contemplate the type of \narrangements at issue in this docket or their implications.i45  PJM notes that it rescinded \n42  Id. at 18-19. \n43  Id. at 20. \n44  Id. at 32-34. \n451d. at 32. \n23 of 515"},{"page":25,"startToken":6538,"endToken":6920,"text":"Document AcceseiA a§c: 2§2§618 _ 3 nqcumentii1Ad DaNe:3. 418/pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 14 - \nits Guidance Document46  pending Commission guidance in this docket about a \nCommission-approved path forward. \n2. \nTransmission Owners' March 24 Responses47 \n23. \nGenerally, Indicated Transmission Owners contend that no Tariff changes are \nneeded.48  Indicated Transmission Owners argue that the Tariff addresses and \nencompasses Co-Location Arrangements. According to Indicated Transmission Owners, \nall load in PJM must be designated as Network Load and served by a Network Customer \n(or take PTPS), thereby ensuring this load pays its fair share of transmission costs. AES \nOhio also argues that the PJM Tariff is just and reasonable regarding service to \nCo-Located Load taken under NITS or Firm PTPS, but acknowledges there may also be \nalternative reasonable transmission service arrangements.49 \n3. \nReply Comments \n24. \nSome parties agree with PJM and transmission owners that the Tariff remains just \nand reasonable, arguing, for example, that it ensures visibility into Co-Located Loads, \nthat Co-Located Load pays its fair share of costs, and that the grid can continue to rely on \nexisting generation resources.5°  However, a number of parties disagree with PJM and \ntransmission owners, arguing that PJM's Tariff is unjust, unreasonable, and unduly \ndiscriminatory and preferential as to Co-Located Load because the Tariff lacks clarity \nand does not provide for rates, terms, and conditions applicable to Co-Location \n46  PJM developed .a Guidance Document on Co-Located Load, first posted in \n2024, which includes non-binding guidance for generators and loads seeking to enter into \nCo-Location Arrangements in PJM. PJM, PJM Guidance on Co-Located Load (Mar. 22, \n2024) (updated Apr. 17, 2024), https://www.pjm.com/-/media/DotCom/markets-\nops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf. \n47  Apart from the arguments summarized below, several transmission owners \nsubmitted responses that took no position on the issues raised in the Show Cause Order, \nspecifically Allegheny Electric Cooperative, Inc., NextEra Energy Transmission \nMidAtlantic, Inc., and Silver Run Electric, LLC. \n48  Indicated Transmission Owners March 24 Response, attach. A at 2-3. \n49  AES Ohio March 24 Response at 1. \n5°  See Buckeye April 23 Reply Comments at 3, 5; Glatz/Silverman April 23 Reply \nComments at 4; NOVEC April 23 Reply Comments at 8, 10; NREMC April 23 Reply \nComments at 4-6. \n24 of 515"},{"page":26,"startToken":6920,"endToken":7327,"text":"Document AccessiA.aW ?§A§:?i18- 3411curnentiilAd DEaRe:iP \n, 1 8 /pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 15 - \nArrangements.51  Other parties allege the Tariff is unclear and/or urge the Commission to \nprovide guidance on Co-Location Arrangements.52  Indicated Transmission Owners argue \nno party has shown the existing Tariff is unjust and unreasonable, and recent events \nindicate that existing types of service can be used.53 \nC. \nJurisdiction \n1. \nPJM's March 24 Response \n25.\nPJM contends that different state laws may impact the permissibility of certain \npotential Co-Location Arrangements.54  PJM explains that states in the PJM region \nassessed several decades ago whether to introduce competition for retail service. As to \nstates that did not pursue deregulation, PJM argues that the state's exclusive retail \nfranchise territory law may restrict non-franchised suppliers from serving Co-Located \nLoad. PJM further asserts that state laws in deregulated states may or may not impose \nlimitations on Co-Located Load suppliers, such as requiring load to be designated as \nNetwork Load or take a specific transmission service. \n26.\nPJM argues that the Show Cause Order did not capture some nuance regarding the \nCommission's jurisdiction.55  PJM asserts that, due to both federal- and state-level \nderegulation, there could be regulatory gaps with respect to Co-Location Arrangements. \nPJM cautions against overgeneralizing when characterizing what states may or may not \nregulate regarding Co-Location Arrangements. PJM asserts that state law does not \n51  See SEIA April 23 Reply Comments at 2, 5-6; CATF April 25 Reply Comments \nat 6; Constellation April 23 Reply Comments at 13-14; Antora April 23 Reply Comment \nat 2; EPSA/P3 April 23 Reply Comments at 9-12; Enchanted Rock April 23 Reply \nComments at 2; Mainspring April 23 Reply Comments at 2, 4; AEU April 23 Reply \nComments at 10. See also Joint Parties' April 22 Motion to Stay at 3. \n52  See Market Monitor April 23 Reply Comments at 2; BrightNight April 23 Reply \nComments at 3; Bloom April 23 Reply Comments at 2; DCC April 23 Reply Comments \nat 7; Industrials April 23 Reply Comments at 14. See also National Security Experts \nApril 22 Reply Comments at 1. \n53  Indicated Transmission Owners June 3 Answer at 3; Indicated Transmission \nOwners June 27 Answer at 2-3 (noting Talen's announcement that the co-location \narrangement between Talen and Amazon will transition to a front-of-the-meter \narrangement). \n54  PJM March 24 Response at 23, 26-27. \n55  Id. at 21, 27-29. \n25 of 515"},{"page":27,"startToken":7327,"endToken":7763,"text":"Document Accessig., \na§c: ?mg:?1:18 _ 3 PaCUMerVAd Dk)e:3.?23.8/Pge  Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 16 - \nnecessarily regulate companies making end-use sales, for example, in the case of \nindustrial customers' self-supply of electricity in Indiana. Moreover, PJM contends that, \nbased on its understanding of Pennsylvania law, a company agreeing to sell electricity to \na data center may not be subject to public utility regulation in that state. PJM alleges that \nNew Jersey has similarly declined to exercise its authority to regulate retail sales to large \nend users. \n27.\nPJM presents several arguments that the Commission has authority over \nCo-Location Arrangements pursuant to its jurisdiction under the FPA over transmission \nin interstate commerce.56  PJM states that, to adequately support a finding based on \ninterstate transmission jurisdiction, one can show that a utility's lines are indirectly \nconnected to the interstate grid. PJM argues that the Commission has jurisdiction \nregarding the transmission service associated with the ancillary services that Co-Location \nArrangements use because the data center in the arrangement will be interconnected to \nthe grid. PJM separately argues that the Commission's transmission jurisdiction is \nimplicated because the Commission has authority over interconnections to the grid, \nincluding modifications by the generator to add load. With respect to the Commission's \njurisdiction over wholesale sales in interstate commerce, PJM argues that it is \nincreasingly complicated to analyze such sales due to the interconnectivity of the grid, \ntechnological advancements, and industry deregulation, but suggests that some \nCo-Location Arrangements may involve Commission-jurisdictional sales for resale. \n2. \nTransmission Owners' March 24 Responses \n28.\nIndicated Transmission Owners state that they generally agree with the \njurisdictional principles outlined in the Show Cause Order.57  Indicated Transmission \nOwners argue that the Commission can set a transmission rate that Network Customers \nserving all Network Load must pay for services and associated charges, but how a state \nchooses to assign and allocate the recovery of the cost of that charge between individual \nretail customers or among classes of end-use load may vary, as long as there is no \ncost-trapping. Indicated Transmission Owners state they would welcome the \nCommission reaffirming that PJM generation interconnection procedures apply to the \ninterconnection of and service to generation, including generation with Co-Located Load, \nbut not to the load itself, which interconnects under state jurisdiction. \n29.\nAES Ohio argues that no changes are necessary to ensure clarity regarding the \naspects of service to Co-Location Arrangements that may be administered through the \n56  Id at 30-31. \n57  Indicated Transmission Owners March 24 Response, attach. A at 1-2; AES Ohio \nMarch 24 Response at 1. \n26 of 515"},{"page":28,"startToken":7763,"endToken":8190,"text":"Document AccessiAa§c:  ?§2§'18- 3 PficumentiilAd DrtNe:13718/pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 17 - \nTariff versus state jurisdictional retail tariffs.58  Indicated Transmission Owners state that \nthe Commission could clarify that generation interconnection agreements do not \"confer \nthe right to serve end-use retail load or the right of new load to take retail service at a \nspecific point or under particular rates\" as those rights are regulated under state law.59 \nAES Ohio and Indicated Transmission Owners state that, in general, the continued \nobligation, if any, of generation to serve classes of end-use customers to pay for that \ngeneration is a matter of state jurisdiction and concern.°  \n3. \nReply Comments \na. \nRequests to Clarify the Scope of Federal Jurisdiction \n30. \nSeveral parties contest that there is shared responsibility between states and the \nCommission with respect to service to Co-Located Load and generation61  and request that \nthe Commission clarify the scope of its jurisdiction. OPSI, NRDC, and Pennsylvania \nCommission request that the Commission affirm that the sale between a Co-Located \nLoad and a generator is a retail sale subject to state jurisdiction and that states also have \npower to regulate wholesale sales not in interstate commerce, as well as facilities used for \nthe generation and distribution of electricity.62  ELCON and Talen request that the \nCommission use this proceeding to clarify that the Commission generally has jurisdiction \nover the types of large-scale Co-Location Arrangements discussed in PJM's Answer to \nthe Show Cause Order.63  Talen also requests that the Commission clarify that the basis \nof the Commission's jurisdiction will vary based on the specifics of the Co-Location \nArrangement and confirm that the Commission's limited role is to ensure that the \nCo-Location Arrangement does not impair overall system reliability; that \ninterconnections between generators and the grid are safe and reliable; and that the rate \n58  AES Ohio March 24 Response at 12. \n59  Indicated Transmission Owners March 24 Response, attach. A at 20-21. \n6°  Id, attach. A at 21-22; AES Ohio March 24 Response at 13. \n61  See AEU April 23 Reply Comments at 8; Talen April 23 Reply Comments at 9 \n(citing New York v. FERC, 535 U.S. at 20-24). \n62  OPSI April 23 Reply Comments at 6; NRDC April 23 Reply Comment at 2; \nPennsylvania Commission April 22 Reply Comments at 2-3 (citing Nat'l Ass 'n of Regul. \nUtil. Comm 'rs v. FERC, 964 F.3d 1177, 1187 (D.C. Cir. 2020)). \n63  ELCON April 23 Reply Comments at 4-5; Talen April 23 Reply Comments \nat 3. \n27 of 515"},{"page":29,"startToken":8190,"endToken":8577,"text":"Document AccessiAa re:  gt-§.3:18-3,4qcurnentiiirJa DVt:Ne:i?Na/Rigte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 18 - \nfor any service is reasonable.64  Talen argues that the Commission cannot favor one type \nof Co-Location Arrangement or configuration over another. \n31.\nMany parties commented on the scope of the Commission's authority over \nCo-Location Arrangements, but several disagree on the components that are subject to \nCommission oversight. California Utilities, EPSA/P3, AEU, and Talen agree with PJM \nthat the Commission has jurisdiction over the allocation of transmission, ancillary \nservices, and other related costs between customers using or benefiting from the \ntransmission system, but clarify that state or local regulators may choose to reallocate \nsuch costs in retail rates.65  EPSA/P3 qualifies its comments by noting that in states with \nretail choice, there is no nexus between state regulation and the transmission rates \nestablished by the Commission, such that only the Commission-approved transmission \nrate and interconnection procedures govern.66 \nb. \nAreas of Commission Jurisdiction \n32.\nSeveral parties support the Commission's exercise of jurisdiction over the taking \nof transmission service.67  Market Monitor and UCS argue that Co-Location \nArrangements are interconnected to the transmission grid and receive jurisdictional \nservice from jurisdictional transmission facilities.68  CATF argues that the Commission \nhas jurisdiction to require transmission tariff provisions for Co-Located Load because all \nco-located configurations receive essential services from the transmission grid, and \ntherefore, all rates, practices, and procedures involving such facilities must be just, \nreasonable, and not unduly discriminatory.69 \n33.\nTalen contends that if the load is not using any transmission network, \npoint-to-point, or ancillary services, then the basis of Commission jurisdiction is not that \n64  Talen April 23 Reply Comments at 3, 9-10 (citing 16 U.S.C. § 824d). \n65  California Utilities April 23 Reply Comments at 3-4. \n66  EPSA/P3 April 23 Reply Comments at 6-8. \n67  NOVEC April 23 Reply Comments at 8. \n68  Market Monitor April 23 Reply Comments at 13; UCS April 11 Reply \nComments at 16 (citing Show Cause Order, 190 FERC ¶ 61,115 at P 76 (\"The \nCommission has defined transmission service as the provision of `electric transmission, \nnetwork or point-to-point service, ancillary services or other methods of electric \ntransmission, or the interconnection with jurisdictional transmission facilities.'\")). \n69  CATF April 25 Reply Comments at 5. \n28 of 515"},{"page":30,"startToken":8577,"endToken":8957,"text":"Document Accessiccia§9:  gc72.§§?18 -3“qcumen ilrid Drelfle:1;918/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 19 - \nthe Co-Located Load itself takes a Commission-jurisdictional form of transmission \nservice but that the Interconnection Service Agreement (ISA) governing the Co-Location \nArrangement is jurisdictional.70  Talen contends that there may be situations in which \nCo-Located Load takes Commission-jurisdictional transmission service. \n34.\nTalen also agrees with PJM that \"the Commission's jurisdiction over transmission \nservice in interstate commerce\" is \"necessarily implicated in matters relating to \nco-located load arrangements where generator interconnections are being modified,\" or \nwhere a generator's ISA contemplates a Co-Location Arrangement.71  California Utilities \ndisagree, arguing that the Commission has jurisdiction only over the wholesale generator \ninterconnection and cannot \"bootstrap such jurisdiction to dictate the terms and \nconditions of service to retail load.i72  Talen asserts that Co-Location Arrangements may \nalso create different (or supplementary) bases for Commission jurisdiction either because \nsales are interstate sales or when they constitute sales for resale.73  Talen concludes that \nwhen the load has no grid connection, there can be no jurisdictional service. \n35.\nTalen argues, however, that the Commission should not condition its assertion of \njurisdiction on the assumption that Co-Located Loads always take \nCommission-jurisdictional services from the transmission system. Talen contends that \nthe specifics of Susquehanna's Co-Location Arrangement, in which the Co-Located Load \nis not a network customer and has no right to take transmission service or backup from \nthe grid, make clear why it would be a mistake for the Commission to assert blanket \njurisdiction over Co-Location Arrangements based on that load's supposed receipt of \njurisdictional transmission service or ancillary services. Talen contends that the practical \neffect of such an assertion would be to improperly federalize the entire electric system. \n36.\nPPL argues that the Commission has the jurisdictional authority to ensure that \nCo-Location Arrangements do not impact the safety or reliability of the bulk electric \nsystem and do not create conditions for improper subsidization of Co-Located Loads by \n70  Talen April 23 Reply Comments at 4-5. \n71  Id. at 5. \n72  Id. at 2; California Utilities April 23 Reply Comments at 4; EPSA/P3 April 23 \nReply Comments at 6; AEU April 23 Reply Comments at 8. \n73  Talen April 23 Reply Comments at 4-8. \n29 of 515"},{"page":31,"startToken":8957,"endToken":9308,"text":"Document Accessicia§c:  g2§§3:18-3q19,curnenti9.1111 DFACIe:A918/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 20 - \nnetwork customers.74  Chevron states that the Commission has the right to clarify rules \nrelating to the ongoing sales of essential reliability services by the generator.75 \nc. \nAreas of Exclusive State Jurisdiction \n37. \nMany parties note that states retain sole jurisdiction over distribution and retail \nrates and sales, non-bypassable charges, and interconnection of load at distribution \nvoltage levels, whereas the Commission has jurisdiction over the interaction of generators \nwith the PJM markets.76  Among other retail charges, PIOs argue that states retain \nauthority over whether consumption by a Co-Located Load should count for purposes of \nallocating transmission and distribution system charges to retail customers.77  Indicated \nTransmission Owners note that state-jurisdictional special contracts or rates can provide \nother financial benefits to the Co-Located Load.78  Constellation and Talen state that the \nCommission has no authority to prohibit a generator from selling directly to Co-Located \nLoad.79  Talen adds that the Commission cannot compel participation in federally \nregulated energy or capacity markets.8° \nd. \nPotential Jurisdictional Gap \n38. \nCommenters disagree on whether the FPA's division of jurisdictional authority \nleaves a regulatory gap with respect to Co-Location Arrangements. PPL agrees with PJM \n74  PPL April 23 Reply Comments at 7. \n75  Chevron April 23 Reply Comments at 4. \n76  See Constellation April 23 Reply Comments at 68, 70; EDFR April 23 Reply \nComments at 7; Joint Consumer Advocates April 23 Reply Comments at 8; NOVEC \nApril 23 Reply Comments at 8. EPSA/P3 April 23 Reply Comments at 6; AEU April 23 \nReply Comments at 8; Talen April 23 Reply Comments at 2; PPL April 23 Reply \nComments at 1; Indicated Transmission Owners April 23 Reply Comments at 2; \nCalifornia Utilities April 23 Reply Comments at 2. \n77  PIOs April 23 Reply Comments at 42. \n78  Indicated Transmission Owners April 23 Reply Comments at 14. \n79  Constellation April 23 Reply Comments at 72; Talen April 23 Reply Comments \nat 10. \n80  Talen April 23 Reply Comments at 10. \n30 of 515"},{"page":32,"startToken":9308,"endToken":9720,"text":"Document Accessiga§c:  g24c42113- 3 Pp, CUrnentii irJa Dk \ne.l )18/Pate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 21 - \nthat there is a potential jurisdictional gap.81  PPL states that under prevailing \nPennsylvania law, a single generator providing service to a single customer is not a \npublic utility and is not subject to the retail jurisdiction of the Pennsylvania Commission, \nnor are the terms of that retail sale subject to federal oversight. Pennsylvania \nCommission rejects this view, however.82  Pennsylvania Commission argues that when \nCo-Located Load receives services from the grid, the respective Commission that \nregulates that portion of the grid has jurisdiction over those services.83  OPSI also argues \nthat there is no regulatory gap, explaining that sales of electricity from a generator to an \nend use customer in intrastate commerce are subject to state jurisdiction.84  OPSI \ndisagrees with PJM's assertion that jurisdiction across the PJM region is unclear, \nemphasizing that OPSI's member states have processes by which jurisdictional issues can \nbe resolved. Constellation states that differing treatment of direct sales by states is not \nindicative of a regulatory gap, but a deliberate policy choice.85 \ne. \nJurisdiction over Large Load Interconnection  \n39. \nCommenters also disagree on whether the Commission should assert jurisdiction \nover the interconnection of large loads. California Utilities state that the Commission \ncannot exercise jurisdiction over the interconnection of a Co-Located Load to the \ntransmission system as an element of transmission service in interstate commerce where \nthe purpose of the arrangement is to facilitate a retail sale.86  PIOs argue, however, that \nthe Commission should assert jurisdiction over Co-Location Arrangements on PJM's \ntransmission system and must not disclaim jurisdiction over interconnection of large \nloads.87  PIOs note that the introduction of large loads has potential to disrupt \ntransmission system reliability. PIOs state that the Commission has not historically \nexercised jurisdiction over \"any and all transmission-level interconnections of retail \n81  PPL April 23 Reply Comments at 7. \n82  Pennsylvania Commission April 22 Reply Comments at 3-4 (citing 66 Pa.C.S. \n§ 102; Drexelbrook Assocs. v. Penn. Pub. Util. Comm'n, 212 A.2d 237, 240 (Pa. 1965); \nBorough of Ambridge v. Pub. Serv. Comm 'n of Penn., 165 A. 47, 49 (Pa. Super. Ct. \n1933)). \n831d at 5. \n84  OPSI April 23 Reply Comments at 5-6. \n85  Constellation April 23 Reply Comments at 73. \n86  California Utilities April 23 Reply Comments at 5. \n87  PIOs April 23 Reply Comments at 34-35, 37. \n31 of 515"},{"page":33,"startToken":9720,"endToken":10156,"text":"Document Accessicaa c:  ?I§2§g18-3PAcurnenWAd Dfta.9e:A?18/Pg.te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 22 - \nload.\"88  PIOs interpret \"any and all\" to mean the Commission has not exercised plenary \nauthority over every transmission-level load interconnection, although there are cases \nwhere the Commission and its regulated entities have sought to control interconnections \nof load. PIOs assert that \"the Commission's statutory mandate to ensure that \ntransmission users, owners, or operators satisfy reliability criteria provides ample support \nfor regulating the interconnections of large loads that . . . have usage characteristics that \ncan cause unacceptable disruption to the bulk power system.\"89  PIOs argue that the \nCommission must plan for wholesale sales at co-located facilities. \n40.\nTalen asserts that interconnection service is a form of Commission-jurisdictional \nservice, and a generator's interconnection to the interstate transmission system does not \nstop being Commission-jurisdictional merely because there is Co-Located Load behind \nthe point of interconnection.90  Talen argues that for that reason, the Commission has for \ndecades approved amendments to ISAs designed to accommodate Co-Located Load, and \nnotes that Order No. 2003 rejected the idea that the Commission loses jurisdiction over \ninterconnections if the generator makes behind-the-meter sales. Talen states that the \npresence of non-jurisdictional facilities behind the meter does not divest the Commission \nof jurisdiction over the generator's interconnection, because non-jurisdictional facilities \n(including the generator itself) always exist behind the meter. Talen contends that the \nargument that the Commission does not have jurisdiction over the interconnection of \nend-use load is undermined by the Supreme Court's decision in EPSA, which confirmed \nthat the Commission can exercise jurisdiction over matters the FPA charges it with \nadministering, even if the exercise of jurisdiction indirectly affects the states' regulatory \npowers, so long as Commission's action does not \"target\" the states' domain.91 \nf. \nNeed for Flexible PJM Tariff Provisions \n41.\nAEU, NOVEC, and PIOs argue that any tariff changes put forward by PJM must \nbe flexible enough to accommodate states' different regulatory frameworks and \n88  Id. at 34 (citing Show Cause Order, 190 FERC ¶ 61,115 at P 72). \n89  Id. at 36. \n90 Talen April 23 Reply Comments at 8-9. \n91  Id. at 9 (citing Standardization of Generator Interconnection Agreements & \nProcs., Order No. 2003, 104 FERC ¶ 61,103, at PP 813-14 (2003), order on reh'g, Order \nNo. 2003-A, 106 FERC ¶ 61,220, order on reh'g, Order No. 2003-B, 109 FERC ¶ 61,287 \n(2004), order on reh'g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff'd sub nom. \nNat'l Ass 'n of Regul. Util. Comm'rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007) \n(NAR UC)). \n32 of 515"},{"page":34,"startToken":10156,"endToken":10530,"text":"Document Accessigha§e:  g2§§?18-3Pacumentiiirid DeaCie:iPis/p,? \nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 23 - \nacknowledge that not all Co-Location Arrangements will be available in all states.92 \nAEU argues that such flexibility will allow states to decide whether changes to state law \nare needed to either expand or constrain access to Co-Location Arrangements, according \nto state-specific circumstances and policy goals. NOVEC explains that, under its \nunderstanding of relevant state law, the Co-Location Arrangements sought by \nConstellation in Docket No. EL25-20 would not be permissible in Virginia unless the \nsupplier to the Co-Located Load is authorized under state law to be a retail supplier in the \ngeographic area in which the Co-Located Load is located.93 \n42.\nNOVEC submits that the Commission should not create a novel contractual \narrangement in the PJM Tariff that allows Co-Location Arrangements to bypass \ntransmission service, local distribution utilities, and the capacity market.94  If it does, \nNOVEC contends that the Commission risks creating an uneven patchwork of \nco-location rules across PJM as some jurisdictions permit it and others do not. PIOs \nargue that PJM must not limit states' authority over the co-located generation mix.95 \nPIOs add that the PJM Tariff should treat Co-Located Load as any other consumption. \n43.\nConstellation argues that requiring Co-Located Loads to take NITS unduly limits \nstate jurisdiction and flexibility.96  Constellation asserts that requiring large loads to take \nwholesale service, rather than taking service directly from a generator, and requiring the \ngenerator to only make wholesale sales, rather than providing service directly to a \nCo-Located Load, effectively precludes states from regulating transactions that fall \nsquarely within their jurisdiction. \nD. \nCost Allocation \n1. \nPJM's March 24 Response \n44.\nPJM states that Co-Location Arrangements should pay the costs of any grid \nservices they consume.97  PJM states that it believes the load and generator must be \ncompletely isolated and physically disconnected from the grid to ensure the load never \n92  AEU April 23 Reply Comments at 8; NOVEC April 23 Reply Comments at 8. \n93  NOVEC April 23 Reply Comments at 8. \n94  Id. \nPIOs April 23 Reply Comments at 40-43. \n96  Constellation April 23 Reply Comments at 26-28, 73-74. \n97  PJM March 24 Response at 4, 42-45. \n33 of 515"},{"page":35,"startToken":10530,"endToken":10985,"text":"Document AccessiAa§q: \nprtaie:A.,48/pg.te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 24 - \ntakes any form of transmission service. PJM maintains that it is always possible that any \nprotection system in an isolated (but not islanded) Co-Location Arrangement could \nmis-operate, be disabled, or degrade, and that, in the few instances where such schemes \nexist on the PJM system, PJM has observed these schemes fail, and the load has taken \ngrid service. Other challenges, PJM notes, include unplanned generator run-backs or \nreductions in output, generator megawatt (MW) oscillations, and Co-Located Load \nutilization fluctuations. PJM argues that, when these conditions occur, they result in \nbrief, but routine, imbalances between the load and the generation that would need to rely \non the grid to balance. \n45. \nPJM explains that proposed Co-Located Loads are not \"wholly isolated from the \ngrid\" because the load and generator are connected to and synchronized with the \nmulti-state bulk power system.98  PJM avers that there are obligations to ensure power to \nnuclear plants to ensure safe shutdown. PJM explains that synchronized to the grid \nmeans the generator matches the voltage, frequency, and phase of the entire grid before \nconnecting to the grid to facilitate safe, stable power transfer. PJM also asserts that \nCo-Located Load is connected to and synchronized with the multi-state bulk power \nsystem and, at minimum, benefits from ancillary services. \n46. \nPJM states that it prefers that Co-Location Arrangements be designated as \nNetwork Load in front of the meter.99  In support of its preference, PJM argues the \nNetwork Load designation means: (1) more reliable service for these critical loads; \n(2) more comprehensive and holistic system planning based on Network Load status; \n(3) enhanced ability to manage load curtailment priority in emergency conditions; (4) less \noperating complexity and reduced dependence on protective schemes, which can \nmis-operate and are designed to address N-1 conditions; (5) greater access to potential \nDemand Response capabilities of large Co-Located Loads; and (6) fewer negative \nimplications for resource adequacy if accompanied by some of the optional offerings \n(i.e., Demand Response, incentives to bring generation, or use of a new \nnon-capacity-backed service). PJM suggests that it may be an open question what level \nof NITS charges, if any, should be assessed to certain Co-Location Arrangements in \naccordance with cost causation principles. \n47. \nPJM recognizes that Co-Location Arrangements involving large data centers may \nappear similar to the BTMG configuration in PJM's Tariff but that the rules were not \ndesigned for large loads and are not a good fit.'°°  PJM explains that its BTMG Tariff \nprovisions were developed in 2004 and that BTMG netting is only available to entities \n98  Id. at 42-43. \n99  Id. at 38-40. \n10°  Id. at 34-36. \n34 of 515"},{"page":36,"startToken":10985,"endToken":11400,"text":"Document Accessiccia§c:  gct-\ni18_31;:gcumentiiirid DP \ne.1\nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 25 - \ntaking NITS. PJM states that BTMG netting was justified at the time it was proposed \nbecause certain market participants \"rely to a lesser degree on the PJM integrated \ntransmission system to serve load.\"1°1  However, PJM cautions that \"20-years later cost \ncausation principles may dictate a different outcome for co-located data center loads that \nappear to have different customer profile and load characteristics.\"102  PJM contends that \nco-located data center configurations use the transmission grid to receive service because \nthey \"appear to require certain ancillary services (load following) and black start service\" \nand ancillary services \"pass through transmission lines, not the air.\"1°3  PJM asserts that \n\"simple netting may not capture the costs `caused' by co-located data center \narrangements\" because they would always net to zero where the generator serves the \nentire data center load.104  PJM notes that BTMG does not carry reserves, and that PJM's \nplanning and resource adequacy will not account for loads in this configuration. PJM \nsuggests that the record \"raise[s] questions about the status\" of the BTMG rules.'°5 \n2. \nTransmission Owners' March 24 Responses \n48. \nIndicated Transmission Owners and AES Ohio argue that Co-Located Load \ninterconnected to the transmission system is using and benefiting from the transmission \nsystem, causes changing flows from second to second, and should pay its costs of \nessential grid services.1°6  Indicated Transmission Owners state that Co-Located Load \nthat is connected to the grid has the potential to draw real or reactive power from the grid \nat any time and relies on and benefits from its connection to the transmission system at all \ntimes. Indicated Transmission Owners state that the presence of on-site backup \ngeneration does not exempt load from paying the costs of transmission service because it \nstill benefits from the transmission system. \n1°1  Id. at 36 (citing PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 7). \n102  Id. (citing Cities of Bethany v. FERC, 727 F.2d 1131, 1138 (D.C. Cir. 1984) \n(recognizing different rates could be charged to different customer groups); Ala. Elec. \nCoop., Inc. v. FERC, 684 F.2d 20, 27-28 (D.C. Cir. 1982) (explaining undue \ndiscrimination)). \n103 Id \n104 Id. \n1°5  Id. \n106 Indicated Transmission Owners March 24 Response at 5, 7, 14; id., attach. A \nat 5, 19-20; AES Ohio March 24 Response at 2. \n35 of 515"},{"page":37,"startToken":11400,"endToken":11875,"text":"Document AccessiAa§q:\n Pz§.P.i.18-3Rcicurner1W111 DPtaae:A21.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 26 - \n49.\nIndicated Transmission Owners state that the only arrangement where the end-use \nload does not need to take some form of transmission service is one in which the load is \ncompletely islanded and does not connect to, take service from, or rely on the \ntransmission or distribution system in any way, for any grid service, at any time.107 \nIndicated Transmission Owners note that such an arrangement would not be within the \nCommission's jurisdiction. Indicated Transmission Owners further contend that \"[e]ven \nif operational protection and control technologies, such as relay switches, are used with \nCo-Located Load and generation, the load still benefits from and utilizes grid services \nwhen 1) the load and generator are both connected to the system, and 2) the load is \nconnected and the generator is disconnected from the system, even if the load is \nconnected momentarily before it trips.\" Further, Indicated Transmission Owners argue \nthat, regardless of Co-Located Load using grid services, Co-Location Arrangements rely \non the grid and grid facilities without which the generator could not operate and the \narrangement could not exist. \n50.\nIndicated Transmission Owners argue that load cannot be \"fully isolated\" if it \nremains connected to the transmission and/or distribution grid, even through protection \nsystems.108  Indicated Transmission Owners note that the definition of a Co-Location \nArrangement that the Commission adopted in the Show Cause Order \"obscures the \nengineering and economic truth that the load relies upon the functioning grid and grid \nservices whichever side of the meter it is located on.\"109  Indicated Transmission Owners \nstate that PJM's pro forma tariffs and interconnection agreements require that all \ninterconnection customers be synchronized to the grid as a condition of service and \nexplain that this is necessary to preserve voltage stability and reliability.110 \n51.\nIndicated Transmission Owners argue that the transmission system must be \nplanned and built to support any load able to be served by the transmission system to \nensure compliance with state requirements that end-use load must be served.111  Indicated \n107  Indicated Transmission Owners March 24 Response, attach. A at 9-10. \n1°8  Id. at 7, 9. \n109  Id. at 7, n.17. \n11°  Id. attach. A at 9 (citing e.g., PJM, Intra-PJM Tariffs, OATT, attach. O app. 2, \n§ 1.4 Initial Operation)). \n111  Id. at 5, 8, 16, attach. A at 6 (citing PJM, Intra-PJM Tariffs, OATT, § 28.2 \nTransmission Provider Responsibilities (stating, \"[t]he Transmission Provider shall \ninclude the Network Customer's Network Load in the Transmission System planning and \nthe Transmission Owners shall, consistent with the terms and conditions of the Tariff, the \nOperating Agreement, and Good Utility Practice, endeavor to construct and place into \nservice sufficient transfer capability to deliver the Network Customer's Network \n36 of 515"},{"page":38,"startToken":11875,"endToken":12330,"text":"Document Accessiccia§e:g,2§giis_ 3 nqcumen0-jd Draae:147,8,p@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 27 - \nTransmission Owners explain that the fact that the load is not constant does not reduce \nthe capital investment or operational and maintenance costs incurred to ensure the system \nis available to the customer if the customer has the ability to serve their full load from the \ntransmission system. \n52.\nIndicated Transmission Owners argue that Co-Located Load fits within the current \nTariff construct and should receive either NITS or PTPS.112  Indicated Transmission \nOwners argue that this will ensure Co-Located Loads are appropriately studied, charged, \nand factored in operationally by PJM and transmission owners. Indicated Transmission \nOwners therefore conclude that the PJM Tariff is just and reasonable and there is no basis \nfor the Commission to act under FPA section 206. Indicated Transmission Owners \nclarify that no party has alleged that the current Tariff, which requires load to take either \nNITS or PTPS, has impaired any load's ability to secure service safely, reliably, and at \nreasonable cost, or that service had been unobtainable. Indicated Transmission Owners \nargue that there have been, instead, allegations that efforts to request service outside of \nthe PJM Tariff provisions have been thwarted, but that such allegations do not impact the \nTariff. AES Ohio generally agrees, but notes that different configurations of Co-Located \nLoad may result in different forms of service and there may be new approaches that are \njust and reasonable and incentivize Co-Located Load to provide reliability benefits and \ncost savings.\"3 \n53.\nIndicated Transmission Owners suggest that adding a definition of Co-Located \nLoad to the PJM Tariff specifying that co-located must be either Network Load or served \nby PTPS and does not meet the definition of BTMG may clarify expectations and \nobligations associated with such load.114  Indicated Transmission Owners argue that \nallowing Co-Located Load to evade existing Tariff charges for grid usage by carving out \nthis load from NITS or PTPS would violate cost causation principles.'\" \n54.\nIndicated Transmission Owners further contend that if Co-Located Loads are not \ndesignated as Network Load, it would undercut reliability and exacerbate affordability \nResources to serve its Network Load on a basis comparable to the delivery of each \nTransmission Owner's own generating and purchased resources to its Native Load \nCustomers\")). \nn2  Id at 2-3, 13; id., attach. A at 7, 21. \n113  AES Ohio March 24 Response at 2, 5. \n114  Indicated Transmission Owners March 24 Response, attach. A at 2, 9, 18. \nn5  Id. at 18 (citing Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. \nCir. 2021) (quoting Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1368-69)). \n37 of 515"},{"page":39,"startToken":12330,"endToken":12774,"text":"Docurnent Accessicgra rc:\n §.2.§g:?18-3Placumentiiii-Jd DetaSte:APi /Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 28 - \nconcerns because it would allow Co-Located Load to avoid \"wires charges,\" including \nthe fixed costs of the poles, wires, transformers, and substations that comprise the \ntransmission and distribution network that would then be subsidized by other \ncustomers.116  Indicated Transmission Owners allege that \"carving a 480 MW \nCo-Located Load in the Commonwealth Edison territory (which hosts multiple nuclear \nunits) out from Network Service would avoid approximately $121 million in annual \ncharges, leading to a 1.53% increase in representative residential customer bills, or about \n$25.57 annually, compared to a similar load customer who paid its share of the costs of \nthe grid.\"117 \n55.\nIndicated Transmission Owners explain that transmission owners are allowed to \nrecover the embedded costs of the transmission grid from network customers on a \npostage stamp basis without consideration of the distance between load and generation.118 \nIndicated Transmission Owners argue the idea that load is responsible for the embedded \ncosts of the transmission grid based on fairness predates Order No. 888.119  Indicated \nTransmission Owners state that the Commission's pro forma definition of Network Load \ndoes not allow a Network Customer to designate only part of the load at a discrete Point \nof Delivery as Network Load unless arrangements for PTPS are made. Indicated \nTransmission Owners explain the Commission found in Order No. 888-A that \"all \npotential transmission customers, including those with generation behind the meter, must \nchoose between [NITS] or [PTPS].',120 \n56.\nIndicated Transmission Owners argue that the PJM RAA provides that a Load \nServing Entity (LSE) is defined as \"any entity (or the duly designated agent of such an \nentity), including a load aggregator or power marketer, (i) serving end-users within the \nPJM Region and (ii) that has been granted the authority or has an obligation pursuant to \nstate or local law, regulation or franchise to sell electric energy to end-users located \n116  Id at 3, 18. \n117  Id. at 18-19. \n118  Id. at 10-12, 17-18. \n119  Id. at 10-11 (citing Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,707; \nFla. Mun. Power Agency v. Fla. Power & Light Co., 67 FERC ¶ 61,167, at 61,482 \n(1994)). \n120 Id at 11-12 (citing Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,260). \nIndicated Transmission Owners argue the Commission has recently rejected requests that \nsome load should be treated as \"special third categories.\" Id. at 17-18 (citing e.g., Nat'l \nR.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237, order on reh'g, \n173 FERC ¶ 61,043 (2020) (Amtrak)). \n38 of 515"},{"page":40,"startToken":12774,"endToken":13170,"text":"Document Accessig.p§c: g)2§§kia_ 3gqcumerA.A-jd Deage:30 18/pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 29 - \nwithin the PJM Region.\"121  According to Indicated Transmission Owners, the RAA \nfurther requires that LSEs shall \"provide or arrange for Network Transmission Service or \nFirm Point-to-Point Transmission Service for service to the projected load of the \nparty....9122 Indicated Transmission Owners contend that, together, these provisions \nmean that any entity serving an end-use load, including a Co-Located Load, must become \nan LSE and is responsible for ensuring that its load is taking either NITS or PTPS. \n57.\nIndicated Transmission Owners state that the BTMG rules do not apply to \nCo-Located Load that is Network Load because such arrangements must deliver energy \nto load without using the transmission system.123  Further, Indicated Transmission \nOwners explain, BTMG adjustments are only available to Network Customers and would \nnot be available to Co-Located Loads served by a contractual intermediary, rather than \nthe generator directly, as the generator would only be an upstream supplier. \n58.\nPSE&G states that transmission charges, if imposed, must apply cost causation \nprinciples that are based on a party's actual usage of the transmission system, which \nPSE&G argues should include netting consistent with BTMG rules.124  PSE&G and AES \nOhio state that both Co-Located Load and BTMG employ similar configurations and \nshould pay for transmission services based on their actual system usage, i.e., net use.125 \nPSE&G argues that Co-Located Load is not using or impacting the transmission system \nany differently than BTMG customers and urges the Commission to ensure that there is \nno undue discrimination in the treatment of Co-Location Arrangements.126  PSE&G adds \nthat any replacement rate must not adversely impact existing customers with BTMG. \n59.\nThe transmission owners also argue that Co-Located Load that is physically \ninterconnected with and synchronized to the grid uses ancillary services and black start \n121  Id. at 15-16 (citing PJM, Intra-PJM Tariffs, RAA, ARTICLE 1 -\nDEFINITIONS (53.0.0) (Definition of Load Serving Entity)). \n122 Id. (citing PJM, Intra-PJM Tariffs, RAA, Article 9 Sec 1 - Overall \nCoordination (2.0.0)). \n123 Id., attach. A at 4. \n124  PSE&G March 24 Response at 5-6, 11-13. \n125  Id. at 15; AES Ohio March 24 Response at 4. \n126  PSE&G March 24 Response at 2, 13-14, 18. \n39 of 515"},{"page":41,"startToken":13170,"endToken":13546,"text":"Document AccessigaW g).2§.M8- 3 gqcu \nnefae:a.491.8/pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 30 - \nservice.127  Indicated Transmission Owners state that Co-Located Load that is connected \nto the grid has the potential to draw real or reactive power from the grid and change \npower flows at any time, even if connected to the distribution system.128  Indicated \nTransmission Owners note load co-located with nuclear units depends on the grid for \nload following, voltage support, black start, and other ancillary services. PSE&G argues \nthat the Commission should establish ancillary services charges for Co-Located Load \nconfigurations based on actual use consistent with cost causation principles.129 \n3. \nReply Comments \na. \nGeneral \n60. \nSeveral commenters urge the Commission to ensure any cost allocation to \nCo-Location Arrangements is consistent with the Commission's cost causation and \nbeneficiary pays principes.13°  California Utilities argue that cost allocation will depend \non whether a state or local regulator allows a generator to serve Co-Located Load and \nwhether the regulator requires the Co-Located Load to pay for retail transmission \nservice.131  Data Center Coalition argues that large loads, particularly data center \noperators, must retain the ability to pursue behind-the-meter and other innovative \nconfigurations.132  United States Senators argue that the Show Cause Order is an \nimportant start to address a crisis affecting ratepayers, and the Commission should ensure \n127  Indicated Transmission Owners March 24 Response, attach. A at 5; AES Ohio \nMarch 24 Response at 7-8. \n128  Indicated Transmission Owners March 24 Response, attach. A at 5. \n129  PSE&G March 24 Response at 9-13. \n138  See AEU April 23 Reply Comments at 17-19; ACEG April 23 Reply \nComments at 2; BrightNight April 23 Reply Comments at 7; Consumers' Research \nApril 23 Reply Comments at 1-2; EEI April 23 Reply Comments at 7; ELCON April 23 \nReply Comments at 6-7; PIOs April 23 Reply Comments at 25-26; Vistra April 23 Reply \nComments at 24 (citing Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1368; \nIll. Corn. Comm'n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009) (/CC v. FERC 1)). \n131  California Utilities April 23 Reply Comments at 2, 8. \n132  Data Center Coalition April 23 Reply Comments at 4. \n40 of 515"},{"page":42,"startToken":13546,"endToken":13973,"text":"Document Accessiccia§c: gp2-4g?,18_3pacumentiiirid DFaae:14118/Pge  Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 31 - \nthat data center owners and operators do not burden households with more than their fair \nshare of power infrastructure costs.\"' \n61.\nSeveral commenters argue that Co-Located Load should be assessed charges based \non services it uses.134  OPSI states that the Commission must determine the extent to \nwhich Co-Location Arrangements rely on the bulk power system and impact rates for \nother customers in determining cost allocation.135  Several commenters argue that \nCo-Located Load uses and benefits from its connection to the transmission system.136 \nNREMC states that the intermittent nature of Co-Located Load does not lessen the need \nfor ongoing investment in infrastructure or the operational costs to ensure reliability.137 \nCATF similarly argues that Co-Located Load creates the need for additional new \ninvestment in transmission infrastructure and grid services. Pennsylvania Commission \nstates that the grid must be planned to accommodate the Co-Located Load should any \nprotection schemes fail. Several parties warn of potential cost shifts to consumers if costs \nare not appropriately allocated to Co-Located Load. t38  NOVEC argues that co-location \nproposals that exempt Co-Located Load from the costs of transmission service effectively \ngive them free use of the transmission system and cause other load to subsidize that use. \n62.\nSeveral parties argue Co-Located Load cannot be fully isolated because \nCo-Located Load and generators are physically interconnected to and rely on the \n133  United States Senators November 25 Letter at 2. \n134  See SEIA April 23 Reply Comments at 3-4; EDFR April 23 Reply Comments \nat 10; Glatz/Silverman April 23 Reply Comments at 5; AEU April 23 Reply Comments \nat 18; EPSA/P3 April 23 Reply Comments at 13; BrightNight April 23 Reply Comments \nat 7; Ohio FEA April 23 Reply Comments at 5. \n135  OPSI April 23 Reply Comments at 4. \n136  See CATF April 25 Reply Comments at 4; NREMC April 23 Reply Comments \nat 7; NOVEC April 23 Reply Comments at 10; Pennsylvania Commission April 22 Reply \nComments at 4-5; UCS April 11 Reply Comments at 1-2. \n137  NREMC April 23 Reply Comments at 7. \n138  See id. at 5-6; CATF April 25 Reply Comments at 12; Consumers' Research \nApril 23 Reply Comment at 1-2; ELCON April 23 Reply Comments at 7; PIOs April 23 \nReply Comments at 26-28; ACEG April 23 Reply Comments at 2; Market Monitor \nApril 23 Reply Comments at 4, 7; NOVEC April 23 Reply Comments at 11; \nPennsylvania Commission April 22 Reply Comments at 4. \n41 of 515"},{"page":43,"startToken":13973,"endToken":14390,"text":"Document Accessiciag)2§g118-3PRCUmentiilrjd DFp„Re:14?3.8/pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 32 - \ntransmission system.139  CATF states Co-Location Arrangements routinely include \nunplanned generator run-backs, MW output oscillations, and load utilization fluctuations, \nresulting in brief imbalances that rely on the grid for support. Parties also argue that \nprotection systems could fail and the generator may go offline.'\" NOVEC contends that \n\"fully isolated\" Co-Located Load is not fully isolated if there is any physical tie to the \ntransmission system. NOVEC asserts that the benefits of, and the need for, the \ntransmission system is why Co-Located Loads do not seek islanded arrangements. \nCalifornia Utilities similarly argue for Co-Located Load to be fully isolated, neither the \ngenerator nor the load may be electrically connected to the transmission system. UCS \nargues that the Co-Located Load would require system generation reserves and \ntransmission capacity when the output of the generator does not match their consumption \nand may impact load ramp rates.14' OPSI discourages the Commission from accepting \nthe premise that load can be wholly isolated from the grid without a comprehensive \nshowing that it is impossible for the load to ever receive grid services or impact \ntransmission rates for existing customers.142 \n63.\nELCON states that large loads that do not take any grid services should not be \nallocated any grid costs unless there is a demonstration that such configuration has a \ndirect cost impact on other grid consumers.143 \nb. \nNetwork Service \n64.\nSeveral commenters argue that Co-Location Arrangements should be required to \ntake either NITS or PTPS.144  NOVEC notes that PJM charges transmission customers on \n139  See CATF April 25 Reply Comments at 4; Pennsylvania Commission April 22 \nReply Comments at 4; Joint Consumer Advocates at 5; UCS April 11 Reply Comments \nat 4-5; PIOs April 23 Reply Comments at 25; Buckeye April 23 Reply Comments at 8; \nNOVEC April 23 Reply Comments at 9; California Utilities April 23 Reply Comments \nat 8. \n140 UCS April 11 Reply Comments at 4-5; Buckeye April 23 Reply Comments \nat 8. \n141  UCS April 11 Reply Comments at 4-5, 8-9. \n142  OPSI April 23 Reply Comments at 4-5. \n143  ELCON April 23 Reply Comments at 7. \n144  UCS April 11 Reply Comments at 16; NREMC April 23 Reply Comments at 4; \nNOVEC April 23 Reply Comments at 9-10; AMP April 23 Reply Comments at 3; PIOs \nApril 23 Reply Comments at 8 (Network Load); CATF April 25 Reply Comments at 4; \n42 of 515"},{"page":44,"startToken":14390,"endToken":14849,"text":"Document Accessiccia§C:  gt§P?18 -3 gq.cumentiiiAd Drage:143 ,18/p@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 33 - \na formulary basis without regard for the distance between load and generation and thus \ndistance does not relieve one of the need to procure transmission service. Pennsylvania \nCommission states that if a retail customer is served by a generator connected to the \ntransmission system that is prima facie evidence the Co-Located Load is Network Load. \nBuckeye notes non-Network Load, \"behind-the-generator\" Co-Location Arrangements \nmay not be permissible in all states and argues that treating Co-Located Load as Network \nLoad respects state laws while providing for consistent application of the Tariff across \nthe PJM footprint. AMP states that it is important that Co-Located Load should take \nNITS or PTPS to avoid unjust and unreasonable cost-shifting and to promote reliable \ntransmission planning and resource adequacy. PIOs argue that it would violate cost \ncausation and beneficiary pays principles to allow Co-Location Arrangements that rely \non ancillary services to avoid paying transmission rates because transmission service is \nrequired to receive these services.145 \n65.\nBuckeye states that ensuring Co-Located Load is Network Load will ensure \nvisibility to the grid operator, allow PJM to conduct appropriate planning to ensure grid \nreliability, ensure the load pays for its share of grid costs, and ensure generation resources \nremain available for the entire grid.146  Buckeye states that, conversely, co-located large \nload arrangements where the load is behind the meter of the generator, and is not \nNetwork Load, may create significant impacts to the grid, increase costs, and decrease \nreliability for those that rely on the grid for affordable and reliable electricity. Buckeye \nstates that, while certain parties have advocated that these \"fully isolated\" arrangements \nwill avoid transmission investments, those potential cost savings are outweighed by \nsignificant concerns about impacts to reliability, resource adequacy, and just and \nreasonable rates. \n66.\nOther commenters disagree that Co-Located Load should be required to take NITS \nor PTPS.147  Industrials state that requiring all Co-Located Load be Network Load would \nbe a departure from precedent that actual use of the transmission system is the \nappropriate way to measure cost causation. Constellation states that Co-Located Load \nshould not be required to pay for transmission service where there are physical \nprotections to prevent the delivery of system energy from the grid. EDFR asserts that \nBuckeye April 23 Reply Comments at 5, 7-8; Pennsylvania Commission April 22 Reply \nComments at 5. \n145  PIOs April 23 Reply Comments at 26. \n146  Buckeye April 23 Reply Comments at 5-6. \n147  Industrials April 23 Reply Comments at 3; Constellation April 23 Reply \nComments at 82-83; EDFR April 23 Reply Comments at 11, 13; EPSA/P3 \nApril 23 Reply Comment at 13. \n43 of 515"},{"page":45,"startToken":14849,"endToken":15240,"text":"Document Accessig'i a§c: g,2-§g318 _3pOqcumenti,i1Ad \ntaze:14 18/pg.te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 34 - \nCo-Located Load that places minimum demands on the transmission system should pay \nless in grid costs. EPSA/P3 argues that Co-Located Load that is behind the meter does \nnot require full Network Services for gross load. SEIA urges the Commission not to \nmandate one approach.'\" \n67.\nData Center Coalition argues that requiring all load to be classified as Network \nLoad risks undermining commercial arrangements, misaligning cost allocation, and \nchilling innovation.'49  BrightNight states that Co-Located Load should not have to \nsubsidize other customers.15°  Constellation asserts that requiring all large Co-Located \nLoads to take NITS is unjust and unreasonable because it: (1) would delay service to \ndata centers due to system studies and the need for new upgrades; (2) would impose \nunnecessary transmission upgrade costs on all existing customers; (3) does not respect \nstate jurisdictional authority; and (4) violates fundamental ratemaking principles and is \nunduly discriminatory by imposing a one-size-fits-all solution on loads that are not \nsimilarly situated.151  Constellation states that the expected integration cost of a \n1,000 MW large load is about $126 million, which would be socialized across all \ntransmission customers under a NITS-only approach. Antora argues that requiring \nCo-Located Load to be Network Load would overcharge both the interconnecting load \ncustomer and other customers on the system for transmission service or upgrades to the \nextent PJM assumes it must serve the customer's full peak demand even if the load is \nflexible or curtailable.152 \n68.\nELCON states that the Commission should ensure that there are no regulatory \nbarriers to islanded configurations with no connection to the larger grid if allowed by \nstate law.153  ELCON states that forcing all large loads into either NITS or PTPS and \nlimiting flexibility risks driving significant increased overall system costs and limits the \nability of customers, state regulators, and utilities to find creative and cost-effective \nsolutions based on individual needs and circumstances. \n148  SEIA April 23 Reply Comments at 4. \n149  Data Center Coalition April 23 Reply Comments at 7. \n15°  BrightNight April 23 Reply Comments at 7. \n151 Constellation April 23 Reply Comments at 15, 20. \n152 Antora April 23 Reply Comments at 11. \n153  ELCON April 23 Reply Comments at 6. \n44 of 515"},{"page":46,"startToken":15240,"endToken":15684,"text":"Document AccessiAa§e: 4 2§cqi18 _3,14qcunnentiiii-jd DE:Age:14518 /pat Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 35 - \nc. \nNetting \n69.\nSeveral commenters argue that Co-Located Load should be charged for any \nwholesale services it uses on a net demand basis.'54  Industrials state that a gross load \nmetering approach is analogous to the gross load outcome that the Commission rejected \nin prior cases.'55  Industrials assert that this approach would cause significant rate \nincreases and disincentivize customers from taking steps to manage use of the grid which \ncould otherwise lead to the avoidance of network upgrades. \n70.\nConstellation argues that requiring Co-Located Loads to be charged NITS on a \ngross basis is unduly discriminatory because it would charge the same rates to customers \nwho impose different costs on the system.'56  Constellation states that Co-Located Load \nshould have the choice to be Network Load and pay gross NITS or to pay net NITS if the \nportion of the generator serving the load delists and PJM procures capacity for the load \nbased on net load during the coincident peaks. Constellation states that since Co-Located \nLoad is unlikely to be withdrawing energy during coincident peak hours, it is appropriate \nto charge the higher of NITS or a `standby charge' to reflect that the system must be built \nto a certain extent to serve the load on a firm basis. \n71.\nConstellation further argues that charging all large Co-Located Loads NITS based \non gross demand would be unduly discriminatory because it is inconsistent with \ntreatment of BTMG.157  Constellation argues that there are no physical, technical, or \neconomic reasons why netting rules applied to existing retail BTMG customers should \nnot apply to co-located. Constellation states that size is not a rationale for discriminatory \nrate treatment. In response to concerns that PJM is not required to carry reserves for \nBTMG, Constellation states that BTMG rules could be modified to require the \nCo-Located Load to carry or pay for reserves and ancillary services or, if needed, a \nminimum demand charge for NITS for any non-volumetric costs the BTMG load imposes \non the system. \n72.\nOn the other hand, Indicated Transmission Owners argue that to afford \nCo-Located Load similar treatment to BTMG load would be to grant an undue preference \n154  Vistra April 23 Reply Comments at 25; Constellation April 23 Reply \nComments at 31; Industrials April 23 Reply Comments at 4. \n155  Industrials April 23 Reply Comments at 4-5 (citing Occidental Chem. Corp. v. \nPJM Interconnection, L.L.C., 102 FERC ¶ 61,275 (2003)). \n156  Constellation April 23 Reply Comments at 31-33, 40-41. \n157  Id. at 32-33, 39, 41-45, 77, 80-81. \n45 of 515"},{"page":47,"startToken":15684,"endToken":16108,"text":"Document Accessig\"la: g)2N18-3149. cumentiilAd DERReAP18/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 36 - \nto such configurations over others that also rely upon Network Service.158  Indicated \nTransmission Owners and AMP argue that because Co-Location Arrangements use the \ntransmission system, they cannot qualify as BTMG. PPL states that behind-the-meter \ngeneration at an existing load differs both in kind and degree from load appearing behind \nthe meter of an existing generator. Indicated Transmission Owners and NREMC argue \nthat allowing large Co-Located Load to utilize the BTMG model of netting generation \nagainst load could allow these facilities to avoid most, if not all, costs, unfairly shifting \ncosts to other grid users since Co-Located Loads rely on and benefit from the grid. \n73.\nAMP and NREMC agree with PJM that BTMG was not designed to accommodate \nlarge loads.159  NOVEC argues that BTMG loads had or developed generation to supply \nthe load, but Co-Located Load as contemplated in this record would instead repurpose \nexisting generation from the supply stack.16°  NOVEC contends that the additional \ngeneration provides greater flexibility to customers and PJM, not less, and that \nCo-Located Loads are on a significantly larger scale than existing BTMG and may have \nlarger impacts on the PJM system. NREMC argues that large Co-Located Loads paired \nwith BTMG present significantly greater operational risks than traditional BTMG \narrangements because they lack adequate reserves.161 \n74.\nAMP states that regardless of what the Commission decides with respect to \nCo-Located Load, the Commission should preserve the current BTMG netting provisions \nin the PJM Tariff.162  AMP contends that PJM does not provide any citations to \ndiscussion in the record regarding PJM's BTMG rules that call the existing netting \nprovisions into question, nor does it identify any reason why the practice of netting loads \nserved by BTMG might no longer be consistent with cost causation principles. AMP \nstates that the longstanding nature of the netting provisions is a reason to retain, not \n158  Indicated Transmission Owners April 23 Reply Comments at 6-7 (citing \n16 U.S.C. § 824d(b)). See also AMP April 23 Reply Comments at 12 (citing PSE&G \nMarch 24 Response at 15); PPL April 23 Reply Comments at 8; NREMC April 23 Reply \nComments at 5. \n159  NREMC April 23 Reply Comments at 5; AMP April 23 Reply Comments \nat 11-12 (citing PJM March 24 Response at 35). \n16°  NOVEC April 23 Reply Comments at 18. \n161  NREMC April 23 Reply Comments at 5. \n162  AMP April 23 Reply Comments at 13. \n46 of 515"},{"page":48,"startToken":16108,"endToken":16465,"text":"Document Accessigia§c:  g'24§1318-3gqcumentiiirli DPACIe:1473.8/p@te Filed.  10/16/2026 \nDocket No. EL25-49-000, et al. \n- 37 - \nrevisit them, given the reliance interests of PJM market participants in the existing \nrules.163 \nd. \nReplacement Rates \ni. \nPJM Options  \n75.\nAEU contends that all eight PJM co-location options should be accommodated, \nalthough each also requires additional development.'\" Vistra argues that if PJM option 3 \n(BTMG where load is Network Load) left the BTMG rules unchanged, it would be \nunduly discriminatory to prohibit behind-the-meter loads from engaging in the same type \nof netting.165  Vistra also argues that PJM option 4 configurations (Co-Located Load \nconnected to the grid with protection facilities) would use the transmission system less \nthan a retail BTMG configuration because protective systems ensure that the load never \ndraws energy from the grid, whereas retail BTMG arrangements may do so. Antora \nargues that PJM option 4 is the only pathway that allows for the fully coordinated study \nof co-located generation and load.166  Antora states that the risks PJM identifies with this \noption would be mitigated for low-load factor loads that only charge when energy is \nabundant and low cost. \n76.\nVistra argues that when option 5 configurations (Co-Located Load connected to \nthe grid with protection facilities, but with back-up service from the grid) draw power \nfrom the grid, PJM should apply netting provisions consistent with the BTMG \nprogram.167  Vistra states that, during those periods when the configuration is drawing \npower from the grid, it may make sense to require such configurations to pay for PTPS, \nNITS, or a new conditional, non-firm transmission service. PPL states that under this \noption, PJM must modify its Tariff to facilitate the type of \"real-time, bespoke \noperational decision-making to determine whether load can continue to be served\" that \n163  Id. at 10-11 (citing Dep't of Homeland Sec. v. Regents of the Univ. of Cal., \n591 U.S. 1, 30 (2020)). \n164  AEU April 23 Reply Comments at 11-17. \n165  Vistra April 23 Reply Comments at 14. \n166  Antora April 23 Reply Comments at 6, 13-14-15. \n167  Vistra April 23 Reply Comments at 8, 28. \n47 of 515"},{"page":49,"startToken":16465,"endToken":16912,"text":"Document Accessig1 a re: \n_ 3 pacumentiiirJa Detaoqe:i4P18/Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 38 - \nPJM contemplates.168  PPL notes that under Pennsylvania law, PPL cannot deny backup \nservice properly requested under its General Tariff.169 \n77.\nAntora argues that the Commission should direct PJM to build out option 7 by \ndeveloping a new non-capacity backed service offering that is available on both a \npermanent and transitional basis (as PJM's option 7 is only transitional) to facilitate the \nintegration of highly flexible, low load factor Co-Located Loads.17°  Antora argues that \noffering non-capacity backed transmission service on a permanent basis would allow \nPJM to capture the benefits of co-located facilities, serving the same amount of total load \nat lower cost, with less transmission infrastructure and fewer capacity resources. \n78.\nConstellation states it supports an interruptible transmission service assessed on \nnet load to promote a more efficient use of the system's existing headroom, resource \nadequacy benefits, and lower costs for customers.171  Constellation argues that allowing \nload to temporarily curtail consumption during peak periods would limit needed \nupgrades, arguing a study showed that a new load curtailment rate of just 0.5% annually \nwould result in nearly 18 GW of potential new load integration in PJM without capacity \nexpansion. Constellation states that an interruptible service should cease to be available \nonce the upgrades are complete—not based on PJM's assessment of resource adequacy as \nPJM suggests. NRDC states that it has concerns that the proposed no-capacity backup \nservice could lead to unduly preferential results and argues it would be preferable to use \nexisting demand products than invent new ones.172  Indicated Transmission Owners argue \nthat if Co-Located Load wishes to be compensated for being interruptible, at the \ntransmission level, such load must show why that outcome is the correct rate design and \n168 PPL April 23 Reply Comments at 11. \n169  Id. (citing PPL Electric Utilities Corporation General Tariff, Rule 6, \nhttps://www.pplelectric.com/-/media/PPLElectric/At-Your-Service/Docs/Current-\nElectric-Tariff/rule6.pdf (providing for \"[s]ervice to customers who have another source \nof power which can be substituted for Company's service for any of customer's \noperations\"); PPL Electric Utilities Corporation General Tariff, Rule 7, \nhttps://www.pplelectric.com/-/media/PPLElectric/At-Your-Service/Docs/Current-\nElectric-Tariff/rule7.pdf (providing for \"[t]emporary service . . . for less than one year or \nfor a year or more when Company must install facilities that will be used solely for a \nservice that is known to be limited in duration.\")). \n170  Antora April 23 Reply Comments at 6-7, 13, 16-18. \n171  Constellation April 23 Reply Comments at 23-26, 56-57. \n172  NRDC April 23 Reply Comments at 5-6. \n48 of 515"},{"page":50,"startToken":16912,"endToken":17327,"text":"Document AccessiAa§q: ?§2-qi18 _ 3 aqcumeq,il-i-ja  Dfacie:i491 8/pate  Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 39 - \nwhy the current demand response rules fail to adequately compensate load \nappropriately.173 \nOther \n79.\nVistra states that it would be reasonable to create a penalty regime to address any \nunintended grid use by Co-Located Loads with protective schemes.174  Vistra explains \nthat such a penalty would be conceptually similar to the unreserved use penalties that the \nCommission created in Order No. 890 that subject transmission customers to penalties for \nusing transmission service that they did not reserve. Buckeye raises concerns with an \nannual single coincident peak (1 CP) transmission cost allocation, arguing that reduction \nin the load during a single hour after building the transmission infrastructure to serve that \nload will not reduce overall costs.175  Buckeye suggests a potential mechanism that \nshould be considered to help mitigate unreasonable cost shifts is changing the 1 CP \nbilling determinant to 12 coincident peaks (12 CP) or to one or more non-coincident \npeaks (NCP). Buckeye argues that moving to 12 CP may make it more difficult for large \nloads to shift costs to other wholesale customers and their retail members, but notes this \nwould not address stranded costs. \n80.\nGlatz and Silverman recommend the Commission explore the potential to develop \na new level of non-firm or interruptible transmission service that prioritizes connection of \nnew flexible loads, regardless of whether they are co-located with generation.176 \nEnchanted Rock supports a transitional non-firm service where the load relies on PJM to \nprovide energy, but where the load is under a commitment to dispatch co-located \ngeneration during PJM curtailments.177  Under this option, Enchanted Rock maintains \nthat the co-located facilities could be quickly interconnected and would only require \ncurtailment in a small number of hours of a year, allowing more efficient use of \ngeneration resources and transmission capacity, lowering costs to customers, and buying \ntime for new infrastructure to be built. \n81.\nConstellation states Co-Located Loads should have three options: (1) a firm NITS \noption with the load paying based on either gross load or net load, depending on its \nconfiguration; (2) a generator-contingent option where Co-Located Load does not pay \n173  Indicated Transmission Owners April 23 Reply Comments at 12. \n174  Vistra April 23 Reply Comments at 13, 25-26. \n175  Buckeye April 23 Reply Comments at 12. \n176  Glatz/Silverman April 23 Reply Comments at 12-13. \n177  Enchanted Rock April 23 Comments at 10-12. \n49 of 515"},{"page":51,"startToken":17327,"endToken":17741,"text":"Document Accessig!PW P-2-§g18-3Pcsq.CUrneq'ilijd Deae:1§918/Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 40 - \nNITS but pays for any necessary upgrades and could pay a discounted transmission \ncharge for as-available energy purchases, if any; and (3) an interruptible transmission \noption—lasting until network upgrades are completed—where Co-Located Load pays a \ndiscounted transmission charge reflecting its inferior service.178  Constellation proposes \nthat, regarding the generator-contingent option, it would be reasonable to provide \nas-available energy at the locational marginal price plus a discounted transmission charge \nbecause, while energy would be drawn from the grid, it would only be \"as-available\" \nwhen it is not adding any burden to the transmission system and the load would not need \nto be planned for reliability or resource adequacy. \n82.\nIndicated Transmission Owners oppose Constellation's proposal, arguing that a \ndiscounted transmission rate for Co-Located Load only taking energy from the \ntransmission system on an as-available basis would be unduly discriminatory because \ntransmission rates are charged to all other customers based on full embedded costs, \nregardless of whether they take energy during peak times.179  Indicated Transmission \nOwners also argue that allowing certain customers with bundled load and generation to \nchoose their own level of transmission service outside of NITS would be a departure \nfrom NERC Reliability Standards FAC-002-2 and TPL-001-5. Finally, Indicated \nTransmission Owners' affiant argues a flexible bundled interconnection framework is a \nnew concept. Constellation opposes Indicated Transmission Owners' claims about \nNERC violations and Constellation emphasizes that it does not oppose studies of \nCo-Located Load, consistent with Reliability Standard FAC-002-2.18° \n83.\nCalifornia Utilities state that, if PJM permits netting of load for transmission \nservice, one option for cost allocation would be to require the Co-Located Load to pay for \nretail stand-by transmission service.181  Joint Consumer Advocates argue that forms of \nservice tailored to specific Co-Located Load will lead to litigation that will further muddy \nthe regulatory waters.182  Invenergy asserts that while new comprehensive rules are \ndeveloped, PJM should implement a transition process so that large loads customers can \nmove forward with Co-Location Arrangements in the short-term.183  Specifically, \n178  Constellation April 23 Reply Comments at 37-38, 51. \n179  Indicated Transmission Owners June 3 Answer at 20-21 (citing Powers \nDeclaration at PP 7, 25-29). \n180  Constellation June 12 Answer at 6. \n181  California Utilities April 23 Reply Comments at 9. \n182  Joint Consumer Advocates April 23 Reply Comments at 7. \n183  Invenergy April 23 Reply Comments at 7. \n50 of 515"},{"page":52,"startToken":17741,"endToken":18132,"text":"Document Accessigh a§e: \n§§i1,3 _ 3 gltqcumenilria. Diage:1§,18/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 41 - \nInvenergy suggests that large-load customers should be allowed to pursue \nbehind-the-meter configurations with new generating facilities without being considered \nNetwork Load. \ne. \nAncillary Services  \n84.\nSeveral parties argue that any ancillary services charges assessed to Co-Located \nLoad must be based on the extent to which Co-Located Loads use ancillary services.184 \nMarket Monitor argues that co-location allows large loads to avoid ancillary service \ncharges.185  Several commenters argue that Co-Located Load configurations either benefit \nfrom the provision of or contribute to the need for certain ancillary services and other \nservices, including load balancing, reactive compensation, frequency response, voltage \ncontrol, regulation, and black start service.186 \n85.\nNREMC argues that Co-Located Load benefits from the full range of ancillary \nservices since both transmission and distribution operators depend on ancillary services \nto maintain grid reliability, stability, and power quality.187  California Utilities argue that \ngenerators synchronized to the grid serving Co-Located Load should pay ancillary \nservice costs because they are not fully isolated, use ancillary services, and benefit from \nreliability and recovery services such as spinning reserve.188  UCS states that load \nvariability from data centers can create imbalances more quickly than generators can \ncorrect them, resulting in voltage disturbances, thermal overloads, and stability issues, \n184  See OPSI April 23 Reply Comments at 4; Pennsylvania Commission April 22 \nReply Comments at 5; Talen April 23 Reply Comments at 13; ACEG April 23 Reply \nComments at 2. \n185  Market Monitor April 23 Reply Comments at 4. \n186  See Pennsylvania Commission April 22 Reply Comments at 4-5; California \nUtilities Reply Comments at 8-9; UCS April 11 Reply Comments at 14, 15 n.42 (citing \nKyle Hannah of Dominion Energy Inc., Pre-Conference Statement, Docket \nNo. AD24-11-000 (filed Nov. 1, 2024)); ENGIE April 23 Reply Comments at 7; \nNREMC April 23 Reply Comments at 7; NOVEC April 23 Reply Comments at 9-10; \nPIOs April 23 Reply Comments at 25; ACEG April 23 Reply Comments at 2; California \nUtilities April 23 Reply Comments at 8-9; Buckeye April 23 Reply Comments at 8; AEU \nApril 23 Reply Comments at 19; ELCON April 23 Reply Comments at 7. \n187  NREMC April 23 Reply Comments at 7. \n188  California Utilities April 23 Reply Comments at 8. \n51 of 515"},{"page":53,"startToken":18132,"endToken":18527,"text":"Document AccessiAa rc:  gAg?1:15-3Picumentiiii-Jd Det3ae:1.§2 , \nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 42 - \nwhich can be mitigated by ancillary services.189  UCS states that Co-Location \nArrangements benefit from essential reliability services including short-circuit fault \ncurrent and system inertia. ACEG contends that if Co-Located Loads avoid their share of \nsystem costs while relying on that system in emergencies, or even just for stability, such \nreliance would undermine cost causation principles and unfairly shift costs onto other \nratepayers!\" Mainspring argues that black start and ancillary service cost allocation will \nvary by technology type as some generators can provide ancillary services others . \ncannot.191 \n86.\nNOVEC argues that the grid necessarily responds to all power-quality issues, \nincluding but not limited to frequency response, reactive needs, transient issues, and \nvoltage contro1.192  NOVEC contends that Co-Located Load is akin to \"parasitic load\" \nbecause the transmission grid cannot differentiate between energy that is injected into the \nmarket and energy that is injected to serve Co-Located Load. Additionally, NOVEC \nargues that nuclear powered generation units are not operated as flexible or partially \nloaded assets but instead operate at full load between fueling cycles to maximize the \nvalue of their fuel rods and therefore, nuclear powered generation assets depend upon \nother generators on the grid to provide all ancillary service and other power-quality \nneeds. \n87.\nCalifornia Utilities argue it is up to the generator to decide how or whether to pass \nancillary and black start service costs onto Co-Located Load.193  Talen states that while it \ncontinues to believe Co-Located Load should not pay for services it is not using, in the \ninterest of compromise, Talen supports the load paying for certain ancillary services.194 \n88.\nConstellation argues that, while there may be some benefit to Co-Located Load for \nsome ancillary services provided to the interconnected generator, a universal requirement \nfor every Co-Located Load to pay for all ancillary services is unjust and unreasonable \nand unduly discriminatory and preferentia1.195  Constellation acknowledges, for example, \n189  UCS April 11 Reply Comments at 13-15. \n190 ACEG April 23 Reply Comments at 2. \n191  Mainspring April 23 Reply Comments at 9. \n192  NOVEC April 23 Reply Comments at 9-10. \n193  California Utilities April 23 Reply Comments at 8-9. \n194  Talen April 23 Reply Comments at 13 \n195  Constellation April 23 Reply Comments at 34, 48, 85-86. \n52 of 515"},{"page":54,"startToken":18527,"endToken":18891,"text":"Document Accessicqe§e: \n, 18 / —Ate \ng2r§g.?18 - 3 4cicumentiiUd Drtae:i§ \nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 43 - \nthat Co-Location Arrangements drawing energy from the system benefit from ancillary \nservices and black start, but argues the generator relies on the service, not the load, and \ncurrent Commission policy does not support charging generators for ancillary services. \n89.\nVistra requests that the Commission create a new rate design to ensure that \nCo-Located Load that is not Network Load pays only for ancillary services that they \nuse.196  However, Vistra argues that PJM has not provided analysis of which ancillary \nservices benefit Co-Located Load. As an example, Vistra offers that variances in the \nCo-Located Load could be viewed as related to the need for regulation service. \n90.\nVistra argues that ongoing charges for reactive power supply and black start \nservice should not be assessed to Co-Located Load, however.19' Vistra argues that \"the \nability to isolate large loads so they cannot draw power from the system would act to \nsectionalize the grid and make black start more manageable.\"198  AEU argues Co-Located \nLoads should be compensated for any ancillary services their connections provide.199 \nE. \nInterconnection Procedures and Cost Allocation \n1. \nPJM's March 24 Response \n91.\nPJM states that the necessary study process is among several studies it may \nemploy to evaluate Co-Location Arrangements, depending upon the type of co-location \narrangement.200  PJM explains that it does not have a tariffed study process for \nnon-Network Load located behind a generator's point of interconnection. PJM explains \nthat its necessary studies process is designed to evaluate the potential reliability impact of \na proposed addition or reduction of a Co-Located Load configuration on the PJM \nTransmission System.201  PJM explains that the scope of the study addresses generation \ndeliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems \nreview, baseline stability, and, if applicable, a nuclear plant interface requirements \nvoltage analysis. \n196  Vistra April 23 Reply Comments at 8, 26-27. \n197  Id. at 27-28. \n198  Id. at 28 (quoting Shanker Aff. ¶ 66). \n199  AEU April 23 Reply Comments at 19. \n200  PJM March 24 Response at 47-49. \n201 Id at 48-50. \n53 of 515"},{"page":55,"startToken":18891,"endToken":19302,"text":"Dociament Accesgigei \n42-118-34(icurnent'ili-Jd neae:IKEi/P§te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 44 - \n92.\nPJM explains that load studies currently are performed only through the traditional \nretail load integration processes. PJM commits, however, to exploring opportunities to \nenhance the visibility of the necessary study process and results where Co-Located Load \nis not Network Load. PJM notes that a deactivation study, unlike the necessary study, \nwould not be appropriate for Co-Location Arrangements because deactivation studies are \ndesigned for the complete cessation of operations by a generator. \n93.\nPJM states that its current necessary study process allows a co-location \narrangement to demonstrate its capability to flexibly adjust its withdrawals from or \ninjections to the transmission system.202  PJM clarifies that Co-Located Load \nconfigurations usually are modeled as if they never take power from the grid -that this \n\"always on\" load is modeled as offsetting the net output of a generator. PJM adds that if \nthe result of this study indicates a thermal or voltage violation, the generator must \nmitigate the violation before the load can be added. \n94.\nPJM states that, under certain Co-Location Arrangements, it is possible that the \ngeneration owner could propose a special protection scheme or Remedial Action Scheme \nto reduce the load under certain conditions.203  PJM states that, if such a configuration \nwere permitted by the Commission, PJM would require language similar to the protection \nfacilities language proposed in the most-recently filed Susquehanna ISA. PJM asserts \nthat, if and where such facilities might misoperate, additional new language should be \ndeveloped to require the generator to take immediate steps to stop the flow of energy \nfrom the grid to any co-located load or risk breach and non-compliance (given the \nabsence of contractual privity between and among PJM, the Transmission Owner, and the \nCo-Located Load in certain situations). \n95.\nPJM states that it conducts dynamic studies for Co-Located Load projects, which \nevaluate all applicable NERC, PJM, and transmission owner-specific contingencies and \ncriteria.204  PJM notes that it also assesses the impact of the ramping behaviors of large \nloads, generally, and the stability impact of large Co-Located Loads, specifically. \n96.\nPJM states that it would not support creating an additional interconnection queue \nfor Co-Located Load because the necessary study process is capable of incorporating and \nevaluating the impact of Co-Location Arrangements.2°5 \n2°2  Id at 51-52. \n2°3  Id. at 52. \n2°4  Id at 53. \n2°5  Id at 56. \n54 of 515"},{"page":56,"startToken":19302,"endToken":19585,"text":"Document Accessicgia§c:\n )2N?i18,..34cicumen't-cid Dfgite:i.§3.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 45 - \n2. \nTransmission Owners' March 24 Responses \n97.\nIndicated Transmission Owners state that the necessary study process, together \nwith other studies, including the individual transmission owners' studies, \"are designed to \nensure appropriate evaluation of, among other things, generator interconnections, \nmodifications, and retirements and load additions.\"206  Indicated Transmission Owners \nexplain that these studies are typically compatible with retail load addition studies and \ncan be coordinated. Indicated Transmission Owners argue that these studies are \ncollectively sufficient and that a separate study process for Co-Located Load is not \nnecessary or appropriate. \n98.\nIndicated Transmission Owners explain that it would not be appropriate for the \nnecessary study process to include a \"flexibility\" analysis because whether a Co-Location \nArrangement is capable of being flexible does not guarantee how the end-use load or \ngenerator will operate in real time.207  Indicated Transmission Owners state that, \"[i]fl the \nabsence of a state law or retail tariff allowing for a more durable commitment, any \ncontractual commitment by end-use load to interrupt its operations or its use of retail \nelectric service will at best be limited to the current contracting party.\"208 However, \nIndicated Transmission Owners note, known flexibility should be captured in PJM's large \nload forecast. \n99.\nIndicated Transmission Owners state that the existing queue process is sufficient \nto study the interconnection of generation and that all load and generation seeking to \ninterconnect should go through the established processes, as they can operate \nindependently.209 \n206 Indicated Transmission Owners March 24 Response, attach. A at 12-13. \n207 id \n208 Id \n209 \n, \nu attach. A at 16. \n55 of 515"},{"page":57,"startToken":19585,"endToken":19929,"text":"Document AccessiAa§C.: glA§ 1.18 _ 3 gqC U \nD' e:1018 D e Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 46 - \n3. \nReply Comments  \na. \nInterconnection Procedures  \ni. \nExpedited Process & Joint Queue \n100.\nSeveral parties generally support creating a separate process in PJM for expediting \nthe interconnection of new generation to serve Co-Located Load,21°  such as a joint review \nprocess for large load and generation.211  ENGIE and Enchanted Rock note challenges \nwith having different studies for generation and load, including potential mismatching of \nthe time when the load and the generation come online, mismatches in the lifetime of the \nload versus the lifetime of the generation, and variances of operational characteristics.212 \nEnchanted Rock also argues that generation interconnection study processes and queues \ndo not adequately recognize the benefits Co-Location Arrangements can provide.213 \nBrightNight, Invenergy, EDFR, and ENGIE recommend that the Commission and PJM \nexplore studying Co-Location Arrangements based on the net impact on the grid.214 \n101.\nInvenergy proposes studying large loads over 50 MW or interconnecting to \nfacilities at voltages greater than 115 kV along with generation and argues that this would \nmore efficiently use the transmission system, decrease ratepayer costs, promote \ntransparency, ensure that network upgrades reflect the expected topology of the system, \nand address a number of concerns raised in the Show Cause Order.215 \n210  See SEIA April 23 Reply Comments at 2; BrightNight April 23 Reply \nComments at 9; Chevron April 23 Reply Comments at 7; AEU April 23 Reply Comments \nat 19-21. \n211  See ENGIE April 23 Reply Comments 8; Invenergy April 23 Reply Comments \nat 3; EDFR April 23 Reply Comments at 7. \n212  ENGIE April 23 Reply Comments at 8; Enchanted Rock April 23 Reply \nComments at 14. \n213  Enchanted Rock April 23 Reply Comments at 15. \n214  See ENGIE April 23 Reply Comments at 8; BrightNight April 23 Reply \nComments at 9; Invenergy April 23 Reply Comments at 5-6; EDFR April 23 Reply \nComments at 7, 9. \n215  Invenergy April 23 Reply Comments at 3-5. \n56 of 515"},{"page":58,"startToken":19929,"endToken":20361,"text":"Document Accessicqa§c:  g'24'18 - 3 AqCUrnentiiiAd DEWie:i§lis/P@ \nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 47 - \n102. BrightNight states that an expedited process for generation serving Co-Located \nLoad would incentivize Co-Located Load to bring its own generation.' BrightNight \nsuggests using the surplus interconnection process to screen for material impacts and, if \nfound, shifting the request into the normal interconnection process. Chevron argues that \na separate expedited interconnection process for Co-Located Load is required to support \nAI data centers as part of the declared emergency processes and national security policy \nof the United States.217  Consumers' Research states that if Co-Located Load uses \ndispatchable fossil fuels, it should be moved ahead in the interconnection queue because \nit can increase grid reliability.218 EDFR states that the Commission should encourage \nPJM and other Independent System Operators to develop an expedited process for \ncontrollable load to interconnect and economically dispatch in the wholesale market, or \nto participate as voluntary load shed resources. \n103.\nSeveral parties support PJM's option 6 specifically.219  Market Monitor states that \nit supports an expedited interconnection process for load and matching new generation \nthat is consistent with PJM's queue process so long as the load is connected to the grid \ndirectly and the new generation resource becomes a Capacity Resource. Ohio FEA \nexplains this could mitigate both local grid impacts and regional resource adequacy \nconcerns. AEU argues that allowing large loads to bring their own new generation would \naddress the root causes of co-location while reducing the new load's impact on resource \nadequacy. \n104.\nPPL generally supports PJM's option 6, but notes that the option appears to be \nindependent from questions around Co-Located Load.Z20  Enchanted Rock argues that, to \nthe extent that the Commission directs PJM to implement option 6, load co-located with \ndispatchable generation projects should also be permitted to participate.221  SEIA asks the \nCommission to direct PJM to modify option 6 to implement an expedited co-located \ninterconnection process, separate from the queue, to determine whether the \n216  BrightNight April 23 Reply Comments at 9. \n217  Chevron April 23 Reply Comments at 7. \n218  Consumers' Research April 23 Reply Comment at 4. \n219  See Mainspring April 23 Reply Comments at 11; Market Monitor April 23 \nReply Comments at 11; PPL April 23 Reply Comments at 13; Buckeye April 23 Reply \nComments at 9; Ohio FEA April 23 Reply Comments at 4-5; Exus May 15 Reply \nComments at 1; AEU April 23 Reply Comments at 14. \n220 PPL April 23 Reply Comments at 13. \n221  Enchanted Rock April 23 Comments at 15. \n57 of 515"},{"page":59,"startToken":20361,"endToken":20762,"text":"Document AccessiA aye: gi2g.§3:18-3PocicurnentiiirJa DE)tae:AP18/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 48 - \ninterconnection request for the co-located generation would require new network \nupgrades.222  SEIA suggests that this process would be analogous to surplus \ninterconnection service and that there would be no queue jumping because the co-located \nresources would not be competing for network upgrades. SETA argues that such service \nis beneficial as it may help prevent transmission system overbuild and would help \naddress issues of supply and demand. \n105.\nOther parties oppose PJM's option 6.223  Bloom argues that PJM's proposal to \noffer incentives for faster interconnection when the load is Network Load is too narrow. \nBloom also asserts that a requirement that a generator with Co-Located Load be a \nCapacity Resource appears to mandate that the generator enter into a financial contract \nwith Co-Located Load and may undermine resource adequacy goals by disincentiAfizing \nload seeking only physical arrangements. Bloom proposes an alternative to PJM's \noption 6 to adopt reforms to interconnect generation and Co-Located Load (both new) as \na composite facility called an \"energy park,\" instead of studying the load in one process \nand the generation in another.224 \n106.\nConstellation asserts that PJM's option 6 is discriminatory against existing \ngeneration because it is functionally equivalent to an out-of-market payment or subsidy \nthat depresses market economics for all other resources.225  Glatz and Silverman also \nquestion why PJM's option 6 should provide a preference to large load customers over \ncustomers aiming to meet other objectives, like clean energy commitments.226  Invenergy \nasserts that Co-Location Arrangements should not get priority access to available \ntransmission system headroom, or deprive PJM of the resources needed to process the \ninterconnection queue, in keeping with the Commission's long-standing policy against \nqueue jumping.227  Constellation also argues it will lead to reduced new entry outside of \nthe large load contract path and restrict the right to integrate with the system to only those \n222 SETA April 23 Reply Comments at 10-11. \n223  See e.g., Bloom April 23 Reply Comments at 8; Constellation April 23 Reply \nComments at 52; NRDC April 23 Reply Comments at 3-4. \n224  Bloom April 23 Reply Comments at 2, 10. \n225  Constellation April 23 Reply Comments at 52 (citing Patterson Aff. ¶ 40). \n226  Glatz/Silverman April 23 Reply Comments at 8-9. \n227  Invenergy April 23 Reply Comments at 6. \n58 of 515"},{"page":60,"startToken":20762,"endToken":21144,"text":"Document AccessiS a§C:?§2§§?18 - 3 RqCUrnentiiirJd DE)Xte:1§918 /Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 49 - \nloads that bring their own generation. In addition, Constellation states that this option \nmay create perverse incentives for existing generators to retire.228 \n107.\nCATF states that the Commission must require large loads with co-located \ngeneration (such as data centers) to follow the same interconnection requirements of \nOrder No. 2023 and Order No. 1920.229  PIOs argue that the Commission should reject \nproposals to allow generators seeking Co-Location Arrangements to access special, \nexpedited interconnection pathways, because this would run counter to Order No. 2023 \nand Commission precedent, offer unduly preferential terms and conditions to a select set \nof entities, and come at the expense of the significantly backlogged interconnection \nprocess.23°  NRDC states that PJM's proposal could erode open access principles as this \nwould be dividing what types of load can get this qualified access.231  Glatz and \nSilverman argue it is unclear whether option 6 would interconnect generation faster than \nthe current interconnection queue.232  United States Senators argue that the Commission \nshould not support arguments that large fossil fuel generators can jump the \ninterconnection queue because of data center demand projections.233 \nii. \nStudy Processes \n108.\nSome parties argue that PJM's necessary study process remains just and \nreasonable. Constellation asserts that the necessary study process evaluates system-wide \nreinforcements and provides transparency and predictability into the development of \nCo-Location Arrangements. 234  Constellation and Vistra support adding clarifying \n228  Glatz/Silverman April 23 Reply Comments at 8-9. \n229  CATF April 25 Reply Comments at 16. \n23°  PIOs April 23 Reply Comments at 28-30 (citing Midcontinent Indep. Sys. \nOperator, Inc., 186 FERC ¶ 61,054, at P 17 (2024); Order No. 2003, 104 FERC 61,103 \nat P 12; Improvements to Generator Interconnection Procs. & Agreements, Order \nNo. 2023, 184 FERC ¶ 61,054, at PP 4, 5, 177, order on reh'g, 185 FERC ¶ 61,063 \n(2023), order on reh'g, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC \n¶ 61,134 (2024)). \n231 NRDC April 23 Reply Comments at 3-4. \n232  Glatz/Silverman April 23 Reply Comments at 8. \n233  United States Senators November 25 Letter at 2. \n234  Constellation April 23 Reply Comments at 47, 62-63, 94-95. \n59 of 515"},{"page":61,"startToken":21144,"endToken":21622,"text":"Document Acces s igtia&e: g,Agii8 _ 3  gqcumenWrJa Egtae:19.21.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 50 - \nlanguage to the Tariff of the obligation of transmission owners to cooperate and provide \ntimely feedback on the necessary studies.235 \n109.\nOn the other hand, several parties express concern that the necessary study process \nis not adequate or appropriate to study Co-Location Arrangements.236  Antora argues that \nstudying co-location using PJM's necessary study process offers a significant efficiency \nadvantage over studying load separately from the co-located generation, as it assesses the \nelectrical impacts of proposed new generation and load in a single interconnection \nprocess. However, Antora argues that the existing process is inadequate, because the \nTariffs study procedures lack the necessary detail to inform customers such as Antora \nhow their charging loads will be studied and confirm that the loads' flexibility will be \naccounted for. PIOs argue that thd necessary study \"may not be fully capturing the \ntransmission system impacts of co-locating load,\" and thus could result in Co-Location \nArrangements with already-operational generators, \"not paying the costs of network \nupgrades that would be caused by the co-location.\"237  Similarly, Market Monitor also \nargues that necessary study agreements miss the most fundamental issues associated with \nco-location. PIOs argue that the necessary studies process was designed for studying \npotential impacts from more minor, routine changes to the electrical characteristics of \nexisting generating units previously studied by PJM and is a poor fit for the more \nsignificant nature of an existing generator entering into a Co-Location Arrangement for \nall or most of its energy production. PIOs argue that PJM has not allowed the addition of \nbattery storage to existing generation to go through the necessary study process, in large \npart because batteries can act as load. PIOs argue that PJM offers no explanation for why \nCo-Located Load is thus offered preferential treatment. \n110. PIOs state that PJM defends the necessary study process for studying co-location \nwith an existing generator by explaining that other study processes are also used; \nhowever, PIOs argue that each of the other studies that PJM identifies pass costs to \nbroader sections of load, not the large load customer(s) causing the need for the \nupgrades.238  PIOs argue that the necessary study process is the only process that PJM \nuses to identify the direct interconnection-related cost responsibility of co-locating large \n235  Id. at 89; Vistra April 23 Reply Comments at 33-34. \n236  Glatz/Silverman April 23 Reply Comments at 7; PIOs April 23 Reply \nComments at 9-10, 14; OPSI April 23 Reply Comments at 3; RMI April 23 Reply \nComments at 3-4; Market Monitor April 23 Reply Comments at 9; Antora April 23 Reply \nComments at 7-8. \n237  PIOs April 23 Reply Comments at 9 (citing Show Cause Order, 190 FERC \n¶ 61,115 atP 79). \n238  Id. at 10-11. \n60 of 515"},{"page":62,"startToken":21622,"endToken":22048,"text":"Document Accessig:PW: igAc421:18 _ 3\nqcumentii1rjd DK)ActeA118/p@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 51 - \nload with an existing generator, and it fails to do so with appropriate accuracy. RMI \nstates that PJM's necessary study process is not adequate because it does not assess the \nprotection system that would prevent the load from using the transmission system.239 \n111.\nGlatz and Silverman argue that a generator's reduction in Capacity \nInterconnection Rights (CIR) is effectively a partial deactivation and that evaluating such \nchanges without a deactivation study appears to be a means to avoid review by the \nMarket Monitor, as such CIR reductions can affect market outcomes.24°  Glatz and \nSilverman also maintain that, when CIRs are removed from the system, the existing load \nmust still be served and the generation to serve that load may require new network \nupgrades. Glatz and Silverman also charge that any system capacity potentially available \ndue to a reduction in CIRs becomes unavailable if studied in concert with a \nbehind-the-meter load addition. \n112.\nOhio FEA also notes that Co-Location Arrangements that propose to take existing \ngeneration off the system have broad implications because they would change the power \nflow across the transmission system and affect the mix of resources available to \nparticipate in PJM's energy and capacity markets and should be subject to a robust \nanalysis before they are allowed to proceed.24I \n113.\nSeveral parties argue that the necessary study process lacks transparency.242 OPSI \nemphasizes that modifications are privately negotiated and under non-disclosure \nagreements.243  OPSI also states that these arrangements avoid a comprehensive \nreliability analysis because the necessary study process was developed to study \nmodifications to existing generating units, not the addition of large Co-Located Loads \nthat are sometimes as large as metropolitan areas. PIOs argue the opaque process \nprevents ratepayer advocates from effectively challenging the prudence of transmission \ninvestments and cost allocation at either the federal or the state level. \n114.\nPennsylvania Commission states that PJM's necessary study process must be \nrevised to provide more information to regulators at the initial stage of the generation \n239  RMI April 24 Reply Comments at 3-4. \n24°  Glatz/Silverman April 23 Reply Comments at 8. \n241  Ohio FEA April 23 Reply Comments at 4. \n242  Glatz/Silverman April 23 Reply Comments at 7; OPSI April 23 Reply \nComments at 3; PIOs April 23 Reply Comments at 9, 14; Pennsylvania Commission \nApril 22 Reply Comments at 7. \n243  OPSI April 23 Reply Comments at 3; PIOs April 23 Comments at 11, 15. \n61 of 515"},{"page":63,"startToken":22048,"endToken":22430,"text":"Document Accesei.larc: gtgg?,18  _3 aqcumentiil-Ad DeElie:ip 18/14@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 52 - \ninterconnection process because, sometimes when Co-Located Load comes online, the \nfirst time a state regulator hears about it is when the arrangement is filed with the \nCommission, unlike with generation retirement, even though they can have the same \neffects.244  Glatz and Silverman note that Indicated Transmission Owners mentioned that \nthe necessary study process is conducted \"together with other studies and analysis\" but \nthese other studies and analyses are not spelled out, nor is there transparency for \nconsumers.245 \n115.\nSeveral parties ask the Commission for further clarity on how Co-Location \nArrangements will be studied and how those studies will be evaluated.246  AEU contends \nthere must be a level of uniformity and detail outlining study requirements to ensure \nregulatory certainty for large loads and new generation and storage resources seeking to \nserve large loads.247  Glatz and Silverman recommend the Commission adopt a principle \nof \"comparability\" to ensure that new Co-Location Arrangements go through a study \nprocess comparable in terms of timing and cost responsibility to a new load locating in \nfront of the meter.248 \n116.\nRegarding PJM's current load interconnection process, Invenergy asserts that \nAttachment M-3 was designed for supplemental transmission projects, not load \ninterconnection, and is not suitable for large load interconnection.249  EDFR asks the \nCommission to provide guidance to PJM and other Regional Transmission Organization \nor Independent System Operator (RTO/ISO) and non-RTO/ISO regions for developing a \nstandardized and transparent load interconnection process at the federal leve1.25° \n117.\nVistra explains that transmission owner load integration studies \"live in a \nregulatory gap,\" because the studies, processes, and facilities associated with those \ninterconnections are not currently subject to Commission regulation or oversight, despite \n244 Pennsylvania Commission April 22 Reply Comments at 7. \n245  Glatz/Silverman April 23 Reply Comments at 7 (citing Indicated Transmission \nOwners March 24 Response, attach. A at 12). \n246  AEU April 23 Reply Comments at 19; Glatz/Silverman April 23 Reply \nComments at 6. \n247  AEU April 23 Reply Comments at 19. \n248  Glatz/Silverman April 23 Reply Comments at 6. \n249  Invenergy April 23 Reply Comments at 3-4. \n250 EDFR April 23 Reply Comments at 6. \n62 of 515"},{"page":64,"startToken":22430,"endToken":22840,"text":"Document Accessigla§c:  g`24 4 118 - 3 Aqui mentiiirli Dfacte:i.g.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 53 - \nthe fact that these configurations involve interconnections directly to the transmission \nsystem.' Vistra argues that the Commission has jurisdiction to close this regulatory gap \nbecause the Commission has jurisdiction when load interconnects to the transmission \nsystem in interstate commerce based on its exclusive authority over interstate \ntransmission, just as the Commission regulates the terms of generation interconnections \nto the transmission system. Vistra states that the Commission should consider \ncommencing a separate proceeding to explore the issue of front-of-the-meter load \ninterconnection practices. Vistra argues that the Commission should exercise its \nauthority over load interconnection to the transmission system to prevent undue \ndiscrimination and ensure that interconnection service is provided in a just and reasonable \nmanner, perhaps by issuing a notice of inquiry on this issue. \n118. Data Center Coalition recommends that the Commission direct PJM to enhance \nvisibility into the relationship between new large loads and the transmission upgrades that \nsupport them by requiring: (1) disclosure of load linkages for Supplemental Projects, and \n(2) confirmation that loads driving Supplemental Projects have already been incorporated \ninto PJM's load forecast.252 \n119. Market Monitor argues for complete transparency in PJM's planning on the load \nside.253  Market Monitor requests that the PJM planning process be modified to integrate \ntransmission planning with markets planning to eliminate major gaps. Market Monitor \nargues that PJM must have the authority to plan to meet large load additions as it does for \ngeneration additions. \niii. \nChanges to Pro Forma Interconnection Procedures \n120.\nSeveral parties request that the Commission modify the pro forma generator \ninterconnection procedures and ISA. BrightNight states that at a minimum the pro forma \nprocess and agreement should allow for three configurations: (1) load and generation \nfully islanded from the electric grid, with no services from the grid; (2) flexible loads or \ndemand response loads; and (3) loads that require backup service (e.g., behind-the-meter \ngeneration).254  Glatz and Silverman propose a new pro forma process for co-location.255 \nVistra requests that the Commission modify the pro forma ISA to include a co-location \n251  Vistra April 23 Reply Comments at 14-15, 36-39. \n252  Data Center Coalition April 23 Reply Comments at 11-12. \n253  Market Monitor April 23 Reply Comments at 7-9. \n254 BrightNight April 23 Reply Comments at 7. \n255  Glatz/Silverman April 23 Reply Comments at 9. \n63 of 515"},{"page":65,"startToken":22840,"endToken":23251,"text":"Document Accesig`ia,Sre:  g2§,§?18-3PRCLIMerlWil. Deta-tge:1K8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 54 - \nsection that will govern the applicable data exchange and coordination requirements and \nformalize any requirements regarding applicable protective schemes.2' 6  Vistra argues \nthat, in addition to the items highlighted by PJM in its response, the pro forma ISA must \ninclude (1) details about coordinating the use of a secondary backup generator and (2) a \nprocess relating to the treatment of the generator's CIRs. \nb. \nCost Allocation \n121.\nCenter refers to a Harvard Law School report stating that utilities are socializing \nthe costs of data center booms by: (1) entering into special contracts; (2) taking \nadvantage of discrepancies between federal and state regulations over cost allocation; and \n(3) relying on co-location agreements.257  Center points out that quick moves to \naccommodate this load growth may result in residential customers shouldering \ninfrastructure costs that are not ultimately needed. ELCON states that the Commission \nshould ensure that regulatory authorities consider the long-term impacts of new large load \nprojects in allocating network upgrade costs to protect non-large load ratepayers from \npaying the generation and transmission costs to serve large load even after initial electric \nservice agreement terms expire.' \n122.\nGlatz and Silverman argue that the Commission should address the risk of \nstranded transmission investment associated with co-location where load does not \nmaterialize, particularly as all of PJM's proposed solutions socialize transmission costs, \noften spreading costs over multiple jurisdictions.259  Glatz and Silverman urge the \nCommission to ensure that any tariff changes account for the potential that data center \nload does not materialize and collaborate with states to manage this risk. Glatz and \nSilverman suggest that the Commission consider imposing \"take-or-pay\" structures for \nnew large loads triggering transmission upgrades and backed by financial security \npostings.26°  Consumers' Research states that retail customers should not bear any of the \n256  Vistra April 23 Reply Comments at 8, 29. \n257  Center April 23 Reply Comments at 22 (citing Eliza Martin and Ari Peskoe, \nExtracting Profits from the Public: How Utility Ratepayers Are paying for Big Tech's \nPower, Environmental & Energy Law Program, Harvard Law School, (Mar. 2025), \nhttps ://eelp. law.harvard. e du/extracting-profits-from-the-pub lic-how-utility-ratep ayers-\nare-paying-for-big-techspower); id. at 25-26. \n258  ELCON April 23 Reply Comments at 7. \n259  Glatz/Silverman April 23 Reply Comments at 11-12. \n260 Id. (indicating such structures are comparable to those debated in a proceeding \nbefore the Ohio Public Utilities Commission). \n64 of 515"},{"page":66,"startToken":23251,"endToken":23665,"text":"Document Accessiccia§c: ?§2§§i18_341CUMeiltiilAd Drage:l@Pia/Pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 55 - \nrisks of co-location, e.g., the costs for the infrastructure not being recovered or the ability \nto access reliable power, and suggest long-term financial commitments, take-or-pay \nclauses, and paying for the development of additional reliable generation as a way to \nmitigate this risk.261  Consumers' Research also states that Co-Location Arrangements \nshould be transparent to the public to protect and inform customers. \n123.\nBuckeye argues that the Commission should consider requiring the LSE that is \ndriving the transmission investment (i.e., the LSE in whose service territory the retail \nlarge load is locating) to be responsible for any cost-shifting caused by large loads that do \nnot show up as expected, thereby covering the costs of transmission investments caused \nby their retail load.262  Buckeye states that the LSE with the large new load should be the \nentity that receives this price signal, because it has a retail relationship with the large load \nthat creates the potential for stranded transmission investment and is therefore able to \npass the stranded cost responsibility to that retail load. Buckeye argues that any costs \ncollected under such retail arrangements should be credited to the wholesale transmission \nrevenue requirement to ensure that any stranded transmission costs associated with such \nlarge loads are not shifted to other LSEs in the zone. \n124.\nParties advocate that costs assigned for network upgrades required to \naccommodate Co-Located Load should be consistent with cost causation principles.263 \nFor example, ELCON states that, according to cost causation, if a large consumer in any \nco-location configuration impacts electricity flows on the grid either through adding to \ncongestion, creating voltage or frequency instability, or impacting access to generation, \nand such impacts require upgrades to the distribution or transmission system, those costs \nshould be allocated to that large consumer.264  Vistra requests that the Commission ensure \nthat Co-Location Arrangements pay their fair share, including by allocating the costs of \nupgrades identified in the necessary study process to the generator.265  Consumers' \n261  Consumers' Research April 23 Reply Comments at 2-3, 5. \n262  Buckeye April 23 Reply Comments at 12. \n263  Data Center Coalition April 23 Reply Comments at 4; ELCON April 23 Reply \nComments at 7; Vistra April 23 Reply Comments at 8; PIOs April 23 Reply Comments \nat 12. \n264  ELCON April 23 Reply Comments at 7. \n265  Vistra April 23 Reply Comments at 8. \n65 of 515"},{"page":67,"startToken":23665,"endToken":24088,"text":"Document Accessicgi a§e: gt§6k18 _ 3 gq.cumeq,i1Ad DfaRe:A \nn gte Filed: 10/16/2026 \nTivz-u \nDocket No. EL25-49-000, et al. \n- 56 - \nResearch states that to avoid improper subsidization the direct and indirect costs of \nCo-Located Load need to be considered, including any needed infrastructure upgrades.266 \n125.\nPennsylvania Commission states that PJM should revisit the potential direct cost \nallocation of transmission network upgrade costs for large load and should consider how \nzonal disparities in congestion and resource adequacy impact network upgrade costs.267 \nPIOs similarly argue that PJM's existing Tariff fails to ensure that Co-Location \nArrangements pay their fair share of upgrade costs, which is unjust and unreasonable.268 \nPIOs note that when a Transmission Owner Load Integration Study identifies \nSupplemental Projects that resolve local transmission reliability needs, the costs are \nallocated not just to the large load customer that triggered the local transmission \nreliability need, but to the transmission owner's entire local utility footprint in that zone. \nPIOs argue that despite this cost allocation, there is no guarantee that these projects \nprovide greater system benefits. PIOs argue that the transmission upgrades required to \nreliably integrate Co-Location Arrangements are differently situated from transmission \nupgrades required to reliably deactivate uneconomic generation (the costs of which are \nalso socialized to load) and thus should be treated differently. PIOs state that while only \nthe remaining load—not the deactivating generator—would utilize the transmission \nupgrades associated with retirements, Co-Located Load will continue to rely on, and \nbenefit greatly from, such upgrades. PIOs argue that many early examples of \ntransmission upgrades driven by data center loads have not led to system benefits, but \nrather, only provide the benefit of allowing the large load to operate—disproportionately \nbenefiting the Co-Location Arrangement. \nF. \nPJM Capacity Market, Reliability, and Resource Adequacy \n1. \nPJM's March 24 Response \n126.\nPJM states that it does not believe that any changes to capacity market rules are \nnecessary to accommodate Co-Location Arrangements.269  PJM explains that three of its \nproposed co-location options (PJM options 6, 7, and 8) address resource adequacy \nconsiderations. PJM adds that it is exploring with regulators and generators opportunities \n266  Consumers' Research April 23 Reply Comments at 2. \n267  For example, Pennsylvania Commission notes that the retirement of a \ngeneration resource to serve a single co-located customer may necessitate vastly different \ntransmission upgrade plans with significant cost implications for customers to whom \nthose costs may be allocated. \n268  PIOs April 23 Reply Comments at 8, 12-13. \n269  PJM March 24 Response at 57, 62-63. \n66 of 515"},{"page":68,"startToken":24088,"endToken":24522,"text":"Document AccessiAa4c:  ?§2g§3:16 - \nacumentiiii-Ja \ne Filed-  10/16/2026 \nDocket No. EL25-49-000, et al. \n- 57 - \nto leverage at least 50 hours (or more) of diesel back-up generator service to enhance the \navailable demand response portfolio. PJM also points to other ongoing efforts, including \nthe transition to a new interconnection process and implementation of the Reliability \nResource Initiative. \n127.\nPJM notes that, to the extent resources request removal from Capacity Resource \nstatus to serve non-PJM load, such requests will only be granted if Market Monitor \napproves it and PJM agrees, or if the Commission issues an order as such.27°  PJM adds \nthat, to the extent PJM determines that a Co-Location Arrangement would result in \ntransmission reliability issues, upgrades would have to be funded and constructed. \n128.\nPJM states that there may be opportunities to clarify or enhance existing planning \nprocesses.271 PJM  states that one such opportunity includes addressing risks that arise \nbased on the existing load forecasting process since, given the potential size of these \nlarge load additions in the forecasts, uncertainty with respect to whether the large loads \nare actually added to the system could cause either overbuild or under-build to occur \nbased on a single customer addition. PJM states that if Co-Located Load is not Network \nLoad, questions arise as to how requirements for visibility and control of the Co-Located \nLoad configuration are applied since the third-party load would not be a signatory to \ninterconnection agreements. PJM states that the ISA and other governing documents \nmay need to be revised to ensure that the overall system will continue to operate reliably \nas designed or as imposed by any temporary operational conditions on the system, \nincluding, for example, the non-conforming provisions included in the Susquehanna ISA. \n2. \nTransmission Owners' March 24 Responses  \n129.\nIndicated Transmission Owners state that if Co-Located Load is required to take \neither NITS or PTPS, no changes to the capacity market rules, energy market rules, or \nplanning and load forecasting processes are necessary.272  Indicated Transmission Owners \nnote that if a Co-Located Load is not metered, it can create an emergency if it appears on \nthe system unexpectedly. AES Ohio urges PJM to consider whether the forecast \nfrequency and load addition certainty are adequate given the pace of large load \nadditions.273  AES Ohio argues that PJM should be required to advise stakeholders if it \n270  Id. at 58-59, 63-65. \n271  Id. at 60-62, 65-66. \n272  Indicated Transmission Owners March 24 Response, attach. A at 17-19: see \nalso AES Ohio March 24 Response at 12-13. \n273  AES Ohio March 24 Response at 13. \n67 of 515"},{"page":69,"startToken":24522,"endToken":24904,"text":"Doctiment Acces-icciarq: gc,Ap?,18 _3pRcumenteili-jd DEpae:j0 2.8/Rgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 58 - \nreasonably expects to serve all load, including Co-Located Load, reliably, particularly in \nperiods of rapid load growth. \n3. \nReply Comments  \n130.\nMarket Monitor argues that there should be no artificial incentives or changes to \nfundamental capacity market rules that allow preferential treatment of large loads.274 \nOPSI states that Capacity Resources cannot prioritize serving non-PJM load, even as \nbackup, without undermining system reliability and that sellers should not be allowed to \nchoose between fulfilling PJM obligations or facing penalties.275  Vistra similarly states \nthat resources that are committed to providing primary service to a Co-Located Load \nshould not also sell that same capacity to PJM.276  NOVEC states that the lack of supply \narising from congestion in the interconnection queue, failures to act on existing \ninterconnection approvals, and retiring thermal generation are the collective impetus for \nthe interest in Co-Located Load, but those supply problems affect all load, and it is \ndiscriminatory to afford some load a lifeboat in the form of co-location while the \nremaining load must address the consequences made worse by that lifeboat.277 \n131.\nPennsylvania Commission states that PJM's Tariff may not provide sufficient \nvisibility into Co-Located Load's potential impacts on reliability and resource adequacy \nwhen generation is removed from the grid.278  Delaware Commission states that the \nexisting Tariff will likely not maintain resource adequacy and reliability.279  Delaware \nCommission adds that the failure to adequately plan for and address resource adequacy \nshortages will result in system load curtailments and extreme shortage prices. \n132.\nSome parties argue that Co-Located Load should be Network Load to ensure \nreliability and resource adequacy.280 Indicated Transmission Owners contend that when \n274  Market Monitor April 23 Reply Comments at 6-7. \n275  OPSI April 23 Reply Comments at 3. \n276  Vistra April 23 Reply Comments at 30. \n277  NOVEC April 23 Reply Comments at 14. \n278 Pennsylvania Commission April 22 Reply Comments at 6. \n279  Delaware Commission April 23 Reply Comments at 1-2, 5. \n28°  See Buckeye April 23 Reply Comments at 6 (citing PJM March 24 Response \nat 16-20); Indicated Transmission Owners April 23 Reply Comments at 13; Joint \nConsumer Advocates April 23 Reply Comments at 3. \n68 of 515"},{"page":70,"startToken":24904,"endToken":25349,"text":"Document Accessicgi a§c: g)Acqii8  _3 gqcumentiiirjd Draae:19916/ p@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 59 - \nCo-Located Load is hidden and not appropriately accounted for, there is not only a cost \nallocation problem, but the study process is undermined and, consequently, PJM may be \nunable to adequately procure enough capacity to serve the load because the full load will \nnot be accounted for in the capacity market, transmission planning, or operations \nprocesses and protocols. Buckeye states that Co-Located Load as Network Load \nprovides significant reliability benefits by avoiding reliance on protective relays and \nenhances PJM's visibility and control over the Co-Located Load. Buckeye asserts that, \n\"[i]f these large loads have the potential to appear on the system, even for a short time, \nthis could have a significant impact on the grid.\"281 \n133.\nConstellation argues that interruptible Co-Located Load and co-location \nconfigurations with protection schemes to prevent energy withdrawals should not be \nassessed capacity charges.282  Vistra also argues that special protection schemes are \ncommonly used and reliable technologies, also referred to as \"remedial action schemes,\" \nand that a NERC standard governs these technologies.283  On the other hand, NRDC \nstates that if Co-Located Load is not Network Load, existing rules would not allocate the \nload any capacity costs if the on-site generation was running during PJM's peak hours, \nwhich would shift capacity costs to other customers.284  California Utilities argue that \ntraditional customers could be forced to subsidize Co-Located Load or suffer impaired \nreliability without proper cost allocation of reliability services and resource adequacy \ncosts.285  California Utilities acknowledge that the Commission cannot prevent a \ngenerator from making retail sales, even if those sales erode reliability, but argues the \nCommission can require wholesale customers to procure adequate capacity. California \nUtilities argue that the entity directly selling at retail to the Co-Located Load should pay \nits capacity costs because the Co-Located Load can impact grid reliability, but notes that \nhow such costs are passed on to the load is a retail issue. \n134. Vistra requests that the Commission clarify that a secondary generator that \nprovides occasional, interruptible backup service to a Co-Located Load can also serve as \na Capacity Resource because the generator will be available to PJM when needed.286 \nVistra notes that existing retail BTMG provisions allow a generator that designates a \n281  Buckeye April 23 Reply Comments at 8. \n282  Constellation April 23 Reply Comments at 66. \n283  Vistra April 23 Reply Comments at 18-19. \n284 NRDC April 23 Reply Comments at 7-8. \n285  California Utilities April 23 Reply Comments at 2, 6-7. \n286  Vistra April 23 Reply Comments at 8, 30-31. \n69 of 515"},{"page":71,"startToken":25349,"endToken":25823,"text":"Document AccessiS;, a§e: 2p2N?:18 _3gqcumentii1-Ad DFAqe:319 18/13gle Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 60 - \nportion of its resource as BTMG to sell the rest of its resource as a Capacity Resource. \nVistra argues that allowing secondary backup resources to participate in the capacity \nmarket ensures that the market gets the greatest reliability benefit from these resources \nbecause ratepayers would enjoy access to additional capacity that would otherwise be \nunderutilized, while the generation resource's owner would put its resource to use and \nincrease its contribution to the market. Comparing these secondary units to reliability \nmust run (RMR) units, Vistra notes that the Commission currently allows RMR resources \nto participate in the capacity market because they \"can be reasonably expected to \nperform\" and argues that a secondary unit that occasionally serves Co-Located Load on \nan interruptible basis can also be expected to perform when needed because PJM can \nrecall it. Vistra states that these secondary units also could be held subject to capacity \nmarket non-performance penalties and do not distort dynamic efficiency in the capacity \nmarket. Vistra adds that, if PJM deems it necessary, it could also create a mechanism to \naddress how the secondary unit complies with its capacity must offer obligation when it \nis serving the Co-Located Load. \n135.\nSeveral commenters argue that existing generators moving to Co-Located Load \nconfigurations could threaten grid reliability and worsen the affordability crisis.287  Joint \nConsumer Advocates note this shift may degrade resource adequacy at an accelerated \npace relative to connecting such load in traditional ways. Buckeye states that, although \nthe balance of demand and supply is arguably the same regardless of whether the load is \nco-located with the generation, a non-Network Load Co-Location Arrangement has the \npotential to accelerate the pace with which the incremental demand arrives on the system, \npotentially without sufficient additional incremental supply, thereby exacerbating \nresource adequacy concerns. Glatz and Silverman suggest requiring PJM to manage the \nrate at which co-location is allowed to ensure reliability and affordability and avoid \nshortage conditions. Buckeye states that removing generation that is associated with a \n\"fully isolated\" Co-Location Arrangement from the rest of the grid is inconsistent with \nthe grid's planning and operational foundations and thus threatens to alter flows in a \nmanner that could require additional transmission upgrades and impair the operational \nflexibility that is essential to reliability.288 \n136. NERC states that co-location of large loads with generation facilities can have \nsubstantial reliability impacts due to interconnection timelines and loss of load incidents, \nwhile also presenting unique challenges and opportunities for grid transformation that \n287  See Glatz/Silverman April 23 Reply Comments at 10-11; Joint Consumer \nAdvocates April 23 Reply Comments at 5; NOVEC April 23 Reply Comments at 14; \nBuckeye April 23 Reply Comments at 6-7. \n288  Buckeye April 23 Reply Comments at 7. \n70 of 515"},{"page":72,"startToken":25823,"endToken":26204,"text":"Document Access Aa§c: ?§2§cq118  _ 3 g4JcumentillAd DE)ACie:1D ie/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 61 - \nrequire special consideration.289  NOVEC argues Co-Located Loads can impact reliability \nand resource adequacy since, for example, protection systems may fail and place the full \nburden of the Co-Located Load onto the grid.290  PPL similarly states that because the \nCommission denied the amended Susquehanna ISA on unrelated grounds, the PJM Tariff \ndoes not include sufficient protections against this reliability risk.291  On the other hand, \nConstellation argues that it would be discriminatory to suggest that protective relaying \ncannot be used in the context of Co-Location Arrangements or that Co-Located Load \nmust be designed to a different standard. 292  Constellation states that each element of the \nprotective scheme is redundant, and the system is not planned for nor does PJM require \nupgrades to address subsequent \"third contingency events.\"293 \n137.\nGlatz and Silverman also express concern that, when load directly connects to \nanother customer's facilities, the connection may not be subject to PJM's Consolidated \nTransmission Owners Agreement, which ensures not only that each PJM Transmission \nOwner maintain its system reliably, but also any connections to other systems, including \nload customers and other transmission systems as wel1.294  UCS states new variability in \nload resulting from data centers may require new Transmission Reliability Margin levels \nin some or all of PJM.295 \n138.\nOn the other hand, Vistra states that the development of Co-Located Load \nconfigurations \"provides ample time for the PJM capacity market to calibrate to respond \nto changes in the balance of supply and demand.\"296  Vistra concludes that neither \nresource adequacy nor reliability concerns justify the failure to accommodate \nbehind-the-meter Co-Located Load. Constellation argues that new load is no different \nthan existing load with respect to resource adequacy planning, and the Commission \nshould determine whether there are additional tools to address near-term capacity needs \n289  NERC April 23 Reply Comments at 3. \n29°  NOVEC April 23 Reply Comments at 11-12. \n291  PPL April 23 Reply Comments at 10-11. \n292  Constellation April 23 Reply Comments at 49. \n293 Id. \n294  Glatz/Silverman April 23 Reply Comments at 13-14. \n295  UCS April 11 Reply Comments at 16-17. \n296  Vistra April 23 Reply Comments at 17-18. \n71 of 515"},{"page":73,"startToken":26204,"endToken":26618,"text":"Document Acces'dicqac.: g\n3:18 _3,4qcument,i1Ad Detae:ini 8/pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 62 - \nin separate proceedings.297  Antora also contends that if properly incorporated into PJM's \noperations, fully flexible load need not impose any new resource adequacy burden.298 \n139.\nSome commenters argue that Co-Location Arrangements can provide reliability \nbenefits.299  ENGIE contends that Co-Location Arrangements can offer improved grid \nreliability and stability. Data Center Coalition states that flexible, efficient service \narrangements like co-location can help alleviate pressure on the broader system, which \ncan serve both reliability and affordability objectives. Constellation argues that \nco-location provides reliability benefits by minimizing grid operational risks because \nfewer grid infrastructure facilities and potential failure points are implicated in serving \nthe load. \n140.\nSeveral commenters recommend enhancements, such as additional clarity and \ntransparency, to PJM's resource adequacy planning to account for the addition of large \nCo-Located Loads.30°  Glatz and Silverman express concern that neither PJM's nor \nIndicated Transmission Owners' studies would evaluate resource adequacy, and contend \nthat requiring such a study would ensure system reliability. Pennsylvania Commission \nstates that the Tariff must be revised to require PJM to conduct long-term scenario \nanalysis on the potential reliability and cost impacts of Co-Location Arrangements. \n141.\nSeveral parties urge reforms to PJM's load forecasting process.301  PIOs, AEU, \nand ELCON argue for standard, transparent terminology and comparable parameters \nacross planners, operators, and users. Data Center Coalition and PIOs argue that PJM's \n297  Constellation April 23 Reply Comments at 11, 60-61 (citing Patterson Aff. \n¶ 15). \n298  Antora April 23 Reply Comments at 12. \n299  See ENGIE April 23 Reply Comments at 7; Data Center Coalition April 23 \nReply Comments at 5; Constellation April 23 Reply Comments at 22-23 (citing Kormos \nAff. ¶ 4). \n300 See CATF April 25 Reply Comments at 7, 8; California Utilities April 23 \nReply Comments at 2; Glatz/Silverman April 23 Reply Comments at 10; NRDC April 23 \nReply Comments at 8-9; PIOs April 23 Reply Comments at 22; Pennsylvania \nCommission April 22 Reply Comments at 7; OPSI April 23 Reply Comments at 3. \n301 ELCON April 23 Reply Comments at 9; PIOs April 23 Reply Comments \nat 16-18, 20, 23; AEU April 23 Reply Comments at 22; Data Center Coalition April 23 \nReply Comments at 9-10; Ohio FEA April 23 Reply Comments at 4; Constellation \nApril 23 Reply Comments at 47; ACEG April 23 Reply Comments at 5, 7; Buckeye \nApril 23 Reply Comments at 11. \n72 of 515"},{"page":74,"startToken":26618,"endToken":27031,"text":"Document Accessigha§e:  ?§2.§c4k 18-3ACICUrnentiilAd DEACie:i??18/P@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 63 - \ncurrent load forecasting methodology often reflects inconsistent assumptions. Ohio FEA \nstates that installing large off-system loads behind existing generators adds complexity, \nincluding that the load would not be captured in the annual load forecasting and planning \nprocesses conducted by LSEs and PJM. Constellation and Data Center Coalition support \nincreased transparency in forecasting. PIOs, Data Center Coalition, and ACEG argue for \nreforms to the load forecasting process to ensure that forecasted data center load is \ncommitment-backed. PIOs state that PJM's load forecasting process does not include \nsufficient controls or standards to prevent speculative additions of large load from \nentering PJM's load forecast. ELCON, PIOs, and Buckeye argue that overestimating \nload growth could lead to substantial overbuilding of infrastructure, which increases costs \nfor consumers. PIOs also argue that inaccurate load forecasting can artificially inflate the \nreserve margin in PJM's capacity market, which could result in unnecessary price \nincreases. \n142. At the same time, ELCON states that underestimating load growth could cause \nreliability challenges.302  ELCON states that enhanced transparency regarding both \nfront-of-the-meter and behind-the-meter loads is necessary to enable operators to \nascertain real-time load behavior, including the potential for excess power injection and \nreliance on back-up services during on-site interruptions. \n143.\nPIOs argue that consistent with the Commission's Rule of Reason doctrine, PJM's \nLarge Load Forecast Process should be in its Tariff.303  ELCON states that the \nCommission should convene a dialogue addressing load forecasting methodologies and \nhow to facilitate communication among state and federal regulators, transmission \noperators, generators, and customers to ensure all parties are positioned to serve all \ncustomers reliably and affordably.304  United States Senators maintain that the \nCommission should consider broader proceedings that would standardize load forecasting \nand other practices relevant to addressing data center demand growth.3°5 \n144.\nIn its response to then-Chairman Rosner's letter to the RTOs/ISOs asking about \nlarge load forecasting, PJM explains that it currently relies on Electric Distribution \nCompanies (EDCs) and LSEs within the PJM footprint to provide relevant data on large \nload requests because PJM does not presently have a load interconnection process.306 \n3°2  ELCON April 23 Reply Comments at 9. \n303 PIOs April 23 Reply Comments at 19. \n3°4  ELCON April 23 Reply Comments at 8. \n3°5  United States Senators November 25 Letter at 3. \n3°6  PJM Response to Then-Chairman Rosner at 4. \n73 of 515"},{"page":75,"startToken":27031,"endToken":27435,"text":"Document Acceseigia5 :  ?§A§,?1.18-3PaCLIMentiilAd Deta.ge.1;118/Pg.te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 64 - \nPJM states that load interconnection processes are generally administered through retail \ntariffs. PJM states that, based on its survey of certain EDCs and LSEs, there are a wide \nrange of approaches to load adjustment processes, from requiring financial commitments \nbased on a minimum demand to using less stringent approaches. PJM also discusses how \nit recently enhanced transparency in its load adjustment request submission process by \npublishing the Load Adjustment Request Implementation Document that addresses load \nforecasting methods and PJM's need for certain information from forecast submitters.307 \nPJM explains that it relies on historical data when available for forecasting purposes, but \nwhen utilities have no historical data, utilities rely on milestone tracking and customer \nrepresentations about expected demand.308  Lastly, PJM notes that utilities share best \npractices on load adjustment at the Load Analysis Subcommittee.3°9 \nG. \nOther Arguments  \n145.\nSeveral commenters highlight the importance of data centers and AI to national \nsecurity, particularly defense operations.31°  Several commenters also urge the \nCommission to act quickly, given that data centers seeking to connect and take service \nfrom the grid may face delays of seven to ten years before they can receive power. \nSeveral commenters argue that certainty is critical to foster national security goals \nassociated with AI development. Indicated Transmission Owners contend that any \nattempt to change the PJM Tariff would likely stymie data-center development, as new \nterms would require development through the PJM stakeholder process, followed by \nCommission consideration and acceptance. \n146. NOVEC and Market Monitor argue that national security is broader than AI and \nthat other customers are vital to national security, such as existing large industrial \ncustomers and commercial and residential load.3\" Market Monitor also argues that any \nnational security issues relate not to co-location but to serving data center load. NOVEC \nalso notes the Commission should consider whether the price increases that Co-Located \n3\" Id. at 2, 6. \n3°8  Id. at 6. \n3°9  Id. at 7. \n310  See National Security Experts April 22 Reply Comments at 1; Constellation \nApril 23 Reply Comments at 15-17; AEU April 23 Reply Comments at 25; PSE&G \nMarch 24 Response at 1, 20; BCSE April 23 Reply Comments at 2. \n311  NOVEC April 23 Reply Comments at 19; Market Monitor April 23 Reply \nComments at 7. \n74 of 515"},{"page":76,"startToken":27435,"endToken":27834,"text":"Document AccessiAa§c:  ?§AP?18 - 3 “qcumentiiAd DFACte:i1P18/14@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 65 - \nLoad could cause may threaten national security by harming existing data centers and the \ngeneral prosperity of the United States. \n147.\nParties argue that co-location offers a number of benefits to the grid that lower \ncosts for customers. Several parties argue that Co-Location Arrangements can make \nefficient use of existing transmission infrastructure and forestall the need for new \ninfrastructure investments.312  For example, California Utilities and Constellation argue \nthat Co-Location Arrangements decrease line losses. In addition, Constellation argues \nthat the benefits of co-location include speed to market, increased interconnection \navailability, and extended facility utilization. ENGIE contends Co-Location \nArrangements can offer environmental benefits by encouraging the use of renewable \nenergy sources and energy-efficient technologies.3\" ENGIE also argues Co-Location \nArrangements that provide benefits to the grid such as back-up service should be \ncompensated for those benefits.314  Enchanted Rock argues that in regions with \ncentralized transmission, but insufficient local generation, co-location can help reduce \ncongestion and backfill any required transmission contingencies in the short-term.315 \nIndicated Transmission Owners note that the addition of end-use load typically benefits \nother customers with respect to transmission costs because it spreads the shared costs \nmore broadly.316  However, Indicated Transmission Owners also argue that many loads \nprovide benefits to the grid but are still required to pay their share of grid services.317 \n148.\nSeveral parties argue that Co-Location Arrangements may encourage the \ndevelopment of new generating resources that can contribute to increased capacity and \ngrid reliability.318  CATF states Co-Located Loads can provide demand response, access \n312  ENGIE April 23 Reply Comments at 7; Constellation April 23 Reply \nComments at 100-103; EDFR April 23 Reply Comments at 7; Enchanted Rock April 23 \nReply Comments at 17-18; PSE&G March 24 Response at 7, 20; AES Ohio March 24 \nResponse at 14; Enchanted Rock April 23 Reply Comments at 17; CATF April 25 Reply \nComments at 12; California Utilities April 23 Reply Comments at 2. \n313  ENGIE April 23 Reply Comments at 7. \n314  Id. \n315  Enchanted Rock April 23 Reply Comments at 12. \n316  Indicated Transmission Owners March 24 Response, attach. A at 22. \n317  Indicated Transmission Owners June 3 Reply Comments at 11. \n318  ENGIE April 23 Reply Comments at 7; Chevron April 23 Reply Comments \nat 6. \n75 of 515"},{"page":77,"startToken":27834,"endToken":28315,"text":"Document Accessila \n?P2N?18 - 3 nqCUMent'ilAd DE'Age:1321e/Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 66 - \nto lower cost power, or black start and other ancillary services, and can help states to \nmeet their clean energy obligations.319  EDFR states that large loads can also benefit: \n(1) existing generators by locating in areas with surplus energy that would otherwise be \ncurtailed; (2) American industries looking for access to affordable, carbon-free energy; \nand (3) local communities through tax revenue, construction jobs, and employment.32° \n149. \nConstellation states that consumers bear no risk related to owning and operating \nmerchant generating resources originally paid for in base rates.321  Further, Constellation \nargues that consumers only paid for service, not for assets. On the other hand, NOVEC \nargues that given the historical cost-of-service arrangements for nuclear power plants that \nnow, in part, make them attractive for these bilateral contracts, it would be unfair to \ndedicate such legacy generation to a single private customer after customers at large paid \nfor such facilities and took the risks of construction since the time such resources were \nbuilt.322  NOVEC urges the Commission to consider the legacy costs that retail customers \nbore before allowing private parties to dedicate the remaining benefits of existing \ngeneration to Co-Located Load and argues that the Commission should not permit any \nco-location paradigm that removes nuclear generation from the capacity market. \nNOVEC contends that nuclear units serve an important role in PJM's energy and capacity \nmarket, and notes that Market Monitor has described them as \"baseload power.\" \nAlthough NOVEC agrees in principle that owners of generation assets should be able to \nseek to maximize the beneficial ownership of those assets, NOVEC argues that the \nCommission has the responsibility to reject proposals that are not just and reasonable \nbecause the Federal Power Act is a consumer protection statute.323  NOVEC notes that \nthe Commission has periodically observed how the legacy of the pre-restructuring period \nhas created inequities and the possibility of unjust and unreasonable results.324 \n319  CATF April 25 Reply Comments at 12. \n320 EDFR April 23 Reply Comments at 8. \n321  Constellation April 23 Reply Comments at 107-108. \n322  NOVEC April 23 Reply Comments at 7, 15-17. \n323  Id. at 16 (citing Xcel Energy Services, Inc. v. FERC, 815 F.3d 947, 952 (D.C. \nCir. 2016) (\"It is long-established that the `primary aim [of the FPA] is the protection of \nconsumers from excessive rates and charges:\" (quoting Mun. Light Bds. of Reading & \nWakefield v. FPC, 450 F.2d 1341, 1348 (D.C. Cir. 1971))). \n324  Id. at 17. For example, NOVEC states that in Opinion No. 494, the \nCommission found that the costs of legacy transmission facilities which were built to \nserve the transmission systems of individual companies and their customers could not be \nallocated to the entire PEW region under the Commission's cost causation principles. \n76 of 515"},{"page":78,"startToken":28315,"endToken":28668,"text":"Document AccessiAa§c:  ?P24gqi)8 _ 3 PacumentiilAd DPACte:1?/18/-pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 67 - \n150.\nA number of parties urge that any Commission action in this proceeding provide \nflexibility for different regions325  and/or different co-location configurations.326 \nCalifornia Utilities request that the Commission recognize that approaches to co-located \nfacilities must be tailored to account for different state regulators, self-regulated \nnon-jurisdictional entities, and regions.327  ENGIE contends that flexibility can enhance \nsystem reliability as configuration design can provide multiple pathways for power \ndelivery.328 \n151.\nEnchanted Rock and CATF oppose PJM's suggestion in option 8 to ease air \npollution standards for co-located generation.329  Relatedly, Center argues that the \nCommission should consider the environmental implications of rules that encourage the \ngrowth of data centers or other large load facilities, including the climate change threats \nthey pose, and should encourage renewable power to these facilities.330 \nIII. \nNotice of Show Cause Proceeding and Responsive Pleadings \n152. Notice of the Show Cause Order was published in the Federal Register, \n90 Fed. Reg. 10818 (Feb. 27, 2025), with interventions due on or before March 13, 2025. \nThe Appendix identifies entities that submitted notices of intervention and motions to \nintervene, as well as abbreviations for those entities. Numerous entities submitted \ncomments and protests, as summarized in this order. Answers were submitted by \nConstellation, Vistra, Buckeye, PSE&G, PPL, and Indicated Transmission Owners. \nNOVEC explains that the instant situation is the inverse, but claims that it implicates the \nsame principle. Id. (citing PJM Interconnection, L.L. C., Opinion No. 494, 119 FERC \n¶ 61,063, at P 42 (2007)). \n325  EDFR April 23 Reply Comments at 7. \n326  Data Center Coalition April 23 Reply Comments at 4; ENGIE April 23 Reply \nComments at 5-6; EDFR April 23 Reply Comments at 9; AEU April 23 Reply Comments \nat 10. \n327  California Utilities April 23 Reply Comments at 9. \n328  ENGIE April 23 Reply Comments at 6. \n329  CATF April 25 Reply Comments at 13, 14; Enchanted Rock April 23 \nComments at 16-17. \n330 Center April 23 Reply Comments at 3-20. \n77 of 515"},{"page":79,"startToken":28668,"endToken":29112,"text":"Dodument Accessig \ng2§M18 - 3 gla.curnenWrJa DE'e:a.018/P§te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 68 - \n153.\nOn April 4, 2025, Vistra filed a motion for clarification and request for expedited \ntreatment.331  On April 9, 2025, Talen filed an answer to Vistra's motion. On April 22, \n2025, EPSA, P3, Calpine, Cogentrix, Constellation, and LS Power (together, Joint \nParties), pursuant to Rules 212 and 603 of the Commission's Rules of Practice and \nProcedure, filed Joint Comments, a Motion to Stay Proceedings, and a Request to \nEstablish Settlement Judge Procedures (Motion to Stay).332\n AMP, Indicated \nTransmission Owners, PJM, NREMC, NOVEC, and Talen filed answers to the Motion to \nStay. \n154.\nOn September 19, 2025, a letter from then-Chairman Rosner to PJM was filed in \nthis proceeding; then-Chairman Rosner's letter requests information on load forecasting. \nOn October 20, 2025, PJM's response to then-Chairman Rosner's letter was filed in this \nproceeding. \n155.\nOn November 21, 2025, Constellation filed a motion for expedited action. \nConstellation contends that the Secretary of Energy's October 23, 2025 proposal to the \nCommission of an Advanced Notice of Proposed Rulemaking (ANOPR) on large load \ninterconnection to the transmission system underscores the urgent need for clarity \nregarding Co-Location Arrangements.333  PJM timely answered and AEP, Exelon, \nIndicated Transmission Owners, ODEC, and Virginia Commission filed late answers to \nor comments on Constellation's motion for expedited action. Indicated Transmission \nOwners, ODEC, PJM, and Virginia Commission argue that Constellation's motion asks \nthe Commission to prejudge issues raised in the ANOPR proceeding. PJM alleges that \ngranting the motion would not only preempt the PJM stakeholder process concerning the \nintegration of large loads, but also violate the principle that agencies should defer taking \n331  Vistra requests clarification regarding the Commission's interpretation of the \nNovember 1, 2024 Order in Docket No. ER24-2172 regarding whether it: (1) prejudged \nthe permissibility of any particular co-location configuration; (2) indicated that the \nCommission generally opposes fully isolated behind the meter co-located load; or \n(3) prohibits parties from following the currently effective tariff rules and negotiating the \nterms of non-conforming ISAs pursuant to existing tariff provisions while this proceeding \nis underway. \n332  Joint Parties request that the Commission stay the show cause proceeding for a \nlimited period of 90 days and establish settlement judge proceedings as expeditiously as \npossible to allow the parties to develop a new replacement rate. \n333  Motion at 3-4 (citing U.S. Department of Energy, Secretary of Energy, \nDirection that the Commission Initiate Rulemaking Procedures and Proposal Regarding \nthe Interconnection of Large Loads Pursuant to the Secretary's Authority Under \nSection 403 of the Department of Energy Organization Act (Oct. 23, 2025)). \n78 of 515"},{"page":80,"startToken":29112,"endToken":29498,"text":"Document AccessiAa§c: ?§24@\"21:18 - 3ggcumentiiirli DraEle:M3.8/pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 69 - \naction in specific adjudicatory matters where such action would supplant ongoing generic \nrulemakings.334  The Indicated Transmission Owners contend that granting the motion \nwould cause confusion and unwarranted expense if it modified the PJM Tariff on an \ninterim basis before addressing issues nationwide in the ANOPR proceeding.335  The \nIndicated Transmission Owners further allege that granting the motion would result in a \npremature, improper jurisdictional determination in this proceeding.336 \nIV. \nDiscussion \nA. \nProcedural Matters \n156.\nPursuant to Rule 214 of the Commission's Rules of Practice and Procedure, \n18 C.F.R. § 385.214 (2025), the notices of intervention and timely, unopposed motions to \nintervene serve to make the entities that filed them parties to this proceeding. \n157.\nPursuant to Rule 214(d) of the Commission's Rules of Practice and Procedure, \n18 C.F.R. § 385.214(d), we grant the late-filed motions to intervene given these entities' \ninterests in the proceeding, the early stage of the proceeding, and the absence of undue \nprejudice or delay. \n158.\nRule 213(a)(2) of the Commission's Rules of Practice and Procedure, 18 C.F.R. \n§ 385.213(a)(2), prohibits an answer to a protest or answer unless otherwise ordered by \nthe decisional authority. We accept the answers because they have provided information \nthat assisted us in our decision-making process. \nB. \nSubstantive Matters  \n159. As discussed further below, we find that the PJM Tariff is unjust and unreasonable \nbecause it does not contain provisions addressing with sufficient clarity or consistency \nthe rates, terms, and conditions of service that apply to Interconnection Customers \nserving Co-Located Load and Eligible Customers taking transmission service on behalf \nof Co-Located Load. We find that the absence of such provisions leaves entities unable \nto determine what steps they must take to effectuate Co-Location Arrangements, which \ncreates uncertainty that has resulted in disparate treatment in PJM, where transmission \nowners have taken different approaches to performing the necessary steps that apply to \nInterconnection Customers seeking to serve Co-Located Load through a Co-Location \n334  PJM Answer at 2 (citing Cities of Anaheim v. FERC, 723 F.2d 656, 659 \n(9th Cir. 1984). \n335  Indicated Transmission Owners Answer at 3. \n336  Id. at 5. \n79 of 515"},{"page":81,"startToken":29498,"endToken":30013,"text":"Document AccessiAa5q:  g'2§118 - 3 gl,cicurnentiiii-Ja Drage:1§918/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 70 - \nArrangement, leading to no consistent understanding of entities' responsibilities with \nrespect to their planned Co-Location Arrangements. We also find that PJM's Tariff is \nunjust and unreasonable because it does not include transmission services that reflect an \nEligible Customer taking service on behalf of a Co-Located Load that is willing and able \nto limit its energy withdrawals from the transmission system under certain conditions. \nFurther, we find that PJM's Tariff is unjust and unreasonable because it does not address \ncharges related to Co-Located Loads' use of regulation and black start services, which \nintroduces the risk that Co-Located Loads may benefit from regulation and black start \nservices without contributing to cost recovery for such services and, thereby, the risk that \ncosts may be allocated entirely to other transmission customers and passed through to \nresidential customers, among others. \n160. \nAs a replacement rate, we direct PJM to revise its Tariff to require that an \nInterconnection Customer who will use its generating facility to serve Co-Located Load \nspecify an Eligible Customer who will take transmission service on behalf of the Co-\nLocated Load. We also direct PJM to establish three new transmission services that \nreflect that Eligible Customers taking service on behalf of Co-Located Load are willing \nand able to limit their energy withdrawals from the transmission system under certain \nconditions. Specifically, we direct PJM to revise its Tariff to allow Eligible Customers \nseeking to take NITS on behalf of Co-Located Load to, at their option, take a new \ninterim, non-firm transmission service until all Network Upgrades necessary to provide \nNITS are complete. We further direct PJM to offer two other new transmission \nservices—a Firm Contract Demand transmission service and a Non-Firm Contract \nDemand transmission service—that an Eligible Customer can choose to take on behalf of \na Co-Located Load instead of taking NITS. These new transmission service options \nreflect a Co-Located Load's ability to limit withdrawals from the transmission system \nand potentially avoid costly and inefficient transmission system buildout that may not be \nnecessary. Eligible Customers serving Co-Located Load that seek to rely on the \ntransmission system to the same extent as Network Load customers will continue to be \neligible to take NITS, billed on a gross demand basis. All Eligible Customers taking \nNITS or one of the new transmission services on behalf of Co-Located Load must be \nassessed charges for regulation and black start services on a gross demand basis, \nregardless of which transmission service they select, to ensure Co-Located Load \ncontributes to cost recovery for such services. As noted below, a Co-Location \nArrangement is synchronized to the transmission system.337  We also seek briefing as to \nwhether the rate paid by an Eligible Customer on behalf of a Co-Located Load taking \nonly the new Non-Firm Contract Demand transmission service that elects to not reserve \nany amount of that service for a period of time (e.g., one month) reflect not only charges \n337  See also PJM March 24 Response at 42-43. \n80 of 515"},{"page":82,"startToken":30013,"endToken":30518,"text":"Document AccessiAa§c:  gctg§.218-3P6qcumentiiirid DPAReA,18/pate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 71 - \nfor regulation and black start services, but also an additional charge given that regulation \nand black start services could not be provided without the transmission system. \n161.\nNext, we direct PJM to clarify its interconnection procedures and agreements to \nensure that it is clear to both new and existing Interconnection Customers how to \ninterconnect in a Co-Location Arrangement. Specifically, we direct PJM to revise its \nTariff to make clear how Interconnection Customers can make use of provisional \ninterconnection service, the ability to request interconnection service below nameplate \ncapacity, the potential to accelerate the interconnection process under certain \ncircumstances (e.g., where the request has no Network Upgrade costs and does not \nrequire further studies), and Surplus Interconnection Service to interconnect new \ngenerating facilities seeking to serve Co-Located Load. We also direct PJM to revise its \nTariff to clarify the procedures for the study necessary to determine any modifications to \ninterconnection facilities or Network Upgrades to the transmission system PJM finds are \nneeded to maintain transmission system reliability as a result of the Interconnection \nCustomer's request to modify its interconnection service level for an existing generating \nfacility to serve Co-Located Load. These clarifications also require existing \nInterconnection Customers to pay the full cost of any such modifications to \ninterconnection facilities or Network Upgrades to the transmission system and specify \nthat an existing generating facility cannot withdraw its capacity from the system to begin \nserving a Co-Located Load until all such modifications and Network Upgrades necessary \nto maintain reliability for existing customers are in service. \n162.\nIn furtherance of the Commission's mandate to ensure just and reasonable rates for \nconsumers, the replacement rate will ensure that Eligible Customers on behalf of \nCo-Located Load take transmission service and incur transmission costs in a way that is \nat least roughly commensurate with their derived benefits. The replacement rate will also \nensure that Eligible Customers on behalf of Co-Located Load are able to take \ntransmission services that reflect their actual impact on the transmission system, which in \nmany cases may be more limited relative to conventional front-of-meter load and \ngeneration. Collectively, the replacement rate provides pathways that recognize \nCo-Located Loads that limit their energy withdrawals from the transmission system, \nwhich may require fewer Network Upgrades, and therefore may result in lower Network \nUpgrade costs as compared to requiring all Eligible Customers taking service on behalf \nof Co-Located Load to take NITS. \n163.\nThe remainder of this determination is organized as follows. Part IV.B.1 \nestablishes the definition of Co-Located Load and directs PJM to incorporate this \ndefinition into its Tariff. Part IV.B.2 addresses the Commission's and the states' \njurisdiction over Co-Location Arrangements. Part IV.B.3 explains why PJM's Tariff is \nnot just and reasonable absent provisions addressing the rates, terms, and conditions of \nservice that apply to Interconnection Customers seeking to serve Co-Located Load and \nEligible Customers taking transmission service on behalf of Co-Located Load. \n81 of 515"},{"page":83,"startToken":30518,"endToken":30930,"text":"Document AccessiA a5e: ?§23 :18 _3,t1qcumenWrjd DepAe:a.§?2.8/Pge  Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 72 - \nPart IV.B.4 directs a replacement rate that establishes just and reasonable rates, terms, \nand conditions of service for Eligible Customers taking transmission service on behalf of \nCo-Located Load and for Interconnection Customers that serve Co-Located Load. \nPart IV.B.4 also establishes paper hearing procedures to gather additional record \nevidence to set the appropriate replacement rate. The remaining sections address other \nissues raised in the record. \n1. \nDefinition \n164. The Show Cause Order used the following definition of Co-Located Load: a \n\"'configuration [that] refers to end-use customer load that is physically connected to the \nfacilities of an existing or planned Customer Facility on the Interconnection Customer's \nside of the Point of Interconnection to the PJM Transmission System. \"'338  We adopt that \ndefinition in this order as well. Indicated Transmission Owners object to this definition, \narguing that this definition obscures that Co-Located Loads rely on the transmission \nsystem to receive service.339  We disagree. This definition reflects the fact that the \nCo-Location Arrangement is physically connected to and synchronized to the \ntransmission system. This relationship, and specifically the interconnection of the \ngenerator to the transmission system, is critical to the determinations we make below. \nWe thus direct PJM to incorporate this definition into its Tariff on compliance as part of \nthe replacement rate detailed below. \n2. \nJurisdiction \n165. As the Commission explained at length in the Show Cause Order, the issues \npresented in this proceeding implicate both federal and state interests, and their resolution \nwill require the involvement of both federal and state actors, including the Commission, \nstate public utility commissions, and other state and local entities.34°  Recognizing the \ncareful balance that the FPA strikes between federal and state regulation, we make \nseveral findings below, including that: (1) states retain exclusive authority over the \nspecific terms of retail sales, generator siting, the generation mix, and transmissions in \nintrastate commerce; (2) the Commission retains the authority to oversee the terms and \nconditions of generator interconnection to any Commission-jurisdictional distribution \nfacility or transmission facility,341  including for generators that serve or plan to serve \n338  Show Cause Order, 190 FERC ¶ 61,115 at P 3 & n.4 (citation omitted). \n339  Indicated Transmission Owners March 24 Response at 7 n.17. \n340  See Show Cause Order, 190 FERC ¶ 61,115 at P 66. \n341  See infra P 172. \n82 of 515"},{"page":84,"startToken":30930,"endToken":31377,"text":"Document AccessiglaW gkAP?118  _3 gq.CUMerltiiii-jd BeaReA3 18 /J:t.,e Filed: 10/16/2026 \n/  \nDocket No. EL25-49-000, et al. \n- 73 - \nCo-Located Load; and (3) the Commission has the authority to ensure that the rates for \ntransmission service in interstate commerce are just and reasonable. \n166.\nBecause the Commission is a creature of statute, it has jurisdiction only over those \nmatters that Congress has given it the authority to regulate.342  Section 201(b)(1) of the \nFPA gives the Commission jurisdiction over the transmission of electric energy in \ninterstate commerce, the sale of electric energy at wholesale in interstate commerce, and \nall facilities for such transmission or sale of electric energy.343  The FPA reserves to the \nstates authority over any matters not expressly conveyed to the Commission,344  which \nincludes retail sales and wholesale sales not in interstate commerce, as well as the \nfacilities used for the generation and distribution of electricity, except as where otherwise \nprovided.345  The Supreme Court has long held regulation of these matters to be within \nthe states' historical police powers,346  and the Court has observed that the FPA's \njurisdictional divide \"was drawn with meticulous regard for the continued exercise of \nstate power, not to handicap or dilute it in any way.\"347  We adhere to those principles \nhere. \na. \nAreas of Exclusive State Authority \n167.\nWe find that several aspects of Co-Location Arrangements fall squarely within the \njurisdiction of the states. First, states retain exclusive authority over the specific terms of \nretail sales and retail rate design, including how the costs of interstate wholesale sales and \ntransmission of electricity assigned to a wholesale customer are allocated among that \nwholesale customer's retail customers. Although \"a State may not conclude in setting \n342  Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002). \n343  16 U.S.C. § 824(b)(1). \n344  Nat'l Ass'n of Regul. Util. Comm'rs v. FERC, 964 F.3d at 1187 (citing N. Nat. \nGas Co. v. State Corp. Comm'n of the State of Kan., 372 U.S. 84, 91-93 (1963)). \n345  16 U.S.C. § 824(b)(1); see Dayton Power & Light Co. v. FERC, 126 F.4th \n1107, 1129 (6th Cir. 2025). \n346  See, e.g., Munn v. People of State of Ill., 94 U.S. 113 (1876). \n347  Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 384-85 (2015) (discussing the \nanalogous provisions in the Natural Gas Act) (quoting Panhandle E. Pipe Line Co. v. \nPub. Serv. Comm'n of Ind., 332 U.S. 507, 517-18 (1947)); see also Nw. Cent. Pipeline \nCorp. v. State Corp. Comm'n of Kan., 489 U.S. 493, 511 (1989)). \n83 of 515"},{"page":85,"startToken":31377,"endToken":31813,"text":"Doctiment Acces-siAa§C: ?.§2-§§?ili3_ 3 gqcument,i1Ad DE'tae:1§418/p,gte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 74 - \nretail rates that the FERC-approved wholesale rates are unreasonable,\"348  it is within a \nstate's exclusive jurisdiction to determine how those FERC-approved rates are collected \namong the relevant retail consumers, including retail consumers that are Co-Located \nLoad.349  Therefore, states have exclusive jurisdiction over how the costs assigned to \nEligible Customers on behalf of Co-Located Load taking Commission-jurisdictional \ntransmission services — including the new transmission services directed below — are \nallocated to individual retail consumers that are Co-Located Load, just as states have \nexclusive jurisdiction over how to allocate the costs of all Commission-jurisdictional \nrates (including for energy, capacity, and transmission) among retail customers, including \nallocating costs among different classes of retail customers.35°  Regulation of wholesale \nsales that are not in interstate commerce also falls to the states; we agree with \ncommenters who note this distinction.351  We disagree with some parties' claim that \nthere could be a regulatory gap under state law,352  as Co-Located Load that is not served \nby an islanded generator353  may receive some services from the distribution and \ntransmission systems. We also agree with Pennsylvania Commission and OPSI that the \ncommission that regulates each portion of the respective systems has jurisdiction over \nthose services.354 \n168. \nSecond, we affirm the Commission's statement from the Show Cause Order that \nstates retain the exclusive authority through state franchise laws to regulate which entities \nmay make retail sales within their borders, and thus the states determine which entities \n348  Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986). \n349  See, e.g., PIOs April 23 Reply Comments at 42. \n350 Order to Show Cause, 190 FERC ¶ 61,115 at P 68. \n351 See, e.g., OPSI April 23 Reply Comments at 5. \n352 Those parties specifically note concerns where, for example, a single generator \nprovides service to a single customer or one large industrial end-use customer sells \nelectricity to another large industrial end-user within the same complex. See PJM \nMarch 24 Response at 27; PPL April 23 Reply Comments at 7. \n383  A fully islanded generator is one that is engaged in a self-sufficient \narrangement with its load where the load and generation together are both fully \nelectrically isolated from the transmission system. See Farhan Noor et al., Unintentional \nIslanding and Comparison of Prevention Techniques at 90 (2005), \nhttps://ieeexplore.ieee.org/stamp/stamp.jsp?arnumber=1560507&tag=1. \n384  See Pennsylvania Commission April 22 Reply Comments at 4-5; OPSI April 23 \nReply Comments at 5-6. \n84 of 515"},{"page":86,"startToken":31813,"endToken":32255,"text":"Document A„„sicqa§c:  ?§24§8 - 3 PacurnentiiirJa DMe:1018/Pge \n10/16/2026 \nDocket No. EL25-49-000, et al. \n- 75 - \nare legally permitted to provide electricity to retail customers in Co-Location \nArrangements.' Nothing in this order changes who may provide, and bill for, retail \nservice to a Co-Located Load. Furthermore, as OPSI explains, that parties seeking \nclarification of the extent to which a generator's retail sale of energy to Co-Located Load \nis state jurisdictional may file a petition for declaratory order with the relevant state \ncommission.356 \n169.\nThird, we confirm that states have authority over their generation resource mix, \nincluding through their siting authority.357  This authority means that which generating \nfacilities are sited and allowed to serve Co-Located Load is also a question of state \nlaw.358  That is true notwithstanding the fact that PJM's markets might indirectly \ninfluence the resource mix through, for example, capacity market price signals that affect \nresource entry and exit.359 \n170.\nFinally, we decline in this proceeding to comprehensively address jurisdictional \nmatters regarding the interconnection of retail loads served through a Co-Location \nArrangement to the interstate transmission system. As discussed below, we conclude that \nthe Commission has jurisdiction to oversee the interconnection of generating facilities, \nincluding the generators that are used to serve Co-Located Load, to the interstate \ntransmission system, as well as jurisdiction over the provision of transmission service in \ninterstate commerce used by an Eligible Customer to serve Co-Located Load. We find \nthat these determinations are sufficient to resolve the issues in this proceeding. \nTherefore, we establish requirements below that apply to Interconnection Customers \n355  Show Cause Order, 190 FERC ¶ 61,115 at PP 68-69. \n356  OPSI April 23 Reply Comments at 5-6. \n357  See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 238 (D.C. \nCir. 2025) (citing 16 U.S.C. § 824(b)(1)). \n358  See FERC v. Elec. Power Supply Ass'n,577 U.S. 260, 267 (2016) (EPSA) (\"the \nCommission may not regulate . . . retail sales of electricity (i.e., sales directly to users)\"); \nShow Cause Order, 190 FERC ¶ 61,115 at P 69 (\"under the FPA, the states get to \ndetermine which entities are legally permitted to provide electricity to retail customers in \nco-location arrangements\"). \n359  Accord EPSA, 577 U.S. at 281 (\"It is a fact of economic life that the wholesale \nand retail markets in electricity, as in every other known product, are not hermetically \nsealed from each other. To the contrary, transactions that occur on the wholesale market \nhave natural consequences at the retail level. And so too, of necessity, will FERC's \nregulation of those wholesale matters.\"). \n85 of 515"},{"page":87,"startToken":32255,"endToken":32664,"text":"Document Acces s icgla§c:  ?§2§g3_18 - 3 aqcurnentiilAd netNe:iMe/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 76 - \nseeking to serve Co-Located Load as well as Eligible Customers taking interstate \ntransmission service on behalf of Co-Located Load. \nb. \nThe Commission Has Jurisdiction over Generation \nInterconnection  \n171.\nThe Commission retains exclusive jurisdictional authority to ensure that the rates, \ncharges, and classifications for the interstate wholesale sale and transmission of \nelectricity, as well as the practices directly affecting such sale and transmission of \nelectricity, are just and reasonable and not unduly discriminatory or preferentia1.36°  We \nagree with commenters that a generator's interconnection to the interstate transmission \nsystem does not fall outside of the Commission's jurisdiction merely because there is \nCo-Located Load behind the generator's point of interconnection.361  The Commission \nretains exclusive jurisdiction to oversee the interconnection of generating facilities to the \ninterstate transmission system, including where generators serve Co-Located Load. \n172.\nRegarding generation interconnection, the Commission retains exclusive authority \nto regulate the procedures and agreements that apply to the interconnection of a generator \nthat will make wholesale sales, both where the generator interconnects directly to the \ninterstate transmission system and where a generator interconnects to dual-use \ndistribution facilities.362  The standard interconnection procedures and agreements first \nadopted in Order No. 2003 apply when an interconnection customer \"that plans to engage \nin a sale for resale in interstate commerce or to transmit electric energy in interstate \ncommerce\"363  requests interconnection to the facilities of a public utility's transmission \nsystem or distribution system \"that, at the time the interconnection is requested, may be \nused either to transmit electric energy in interstate commerce or to sell electric energy at \nwholesale in interstate commerce pursuant to a Commission-filed Open Access \n36°  16 U.S.C. §§ 824d, 824e; see EPSA, 577 U.S. at 278 (2016) (approving \"a \ncommon-sense construction of the FPA's language, limiting the Commission's \n`affecting' jurisdiction to rules or practices that `directly affect the wholesale rate' \n(cleaned up)). \n361  See Talen April 23 Reply Comments at 8. \n362  See NARUC, 475 F.3d at 1282 (FERC's exercise of jurisdiction \"only over \n`interconnections to a `distribution' facility when the facility is included in a public \nutility's Commission-filed OATT and the interconnection is for the purpose of \nfacilitating a jurisdictional wholesale sale of electric energy' is permissible and not an \nexample of jurisdictional \"boot-strapping\"). \n363  Order No. 2003, 104 FERC ¶ 61,103 at P 804. \n86 of 515"},{"page":88,"startToken":32664,"endToken":33118,"text":"Document Accessiccia§C:gl§g?i18 _ 341CUMerVAd DeaRe:1§73.8/Pg.\n Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 77 - \nTransmission Tariff (OATT).\"364  In particular as to distribution-level interconnections, \nOrder Nos. 2003 and 2006 established what is sometimes referred to as the \"first use\" \ntest, under which the first interconnection to a distribution facility for the purpose of \nmaking wholesale sales is not typically Commission-jurisdictional because the facility is \nnot at the time of the request used to transmit electric energy in interstate commerce or \nsubject to wholesale open access under an OATT.365  This jurisdictional application has \nbeen found to be consistent with the FPA.366  Furthermore, once the generator has \ninterconnected, the Commission retains authority over the generator's wholesale sales in \ninterstate commerce. \nc. \nThe Commission Has Jurisdiction to Ensure that Eligible \nCustomers Taking Service on Behalf of Co-Located Loads \nAre Allocated Costs for Transmission Service  \n173. \nWe affirm that the Commission has exclusive jurisdiction over the provision of \ntransmission service used by an Eligible Customer to serve Co-Located Load, again \n364  Id.; see also Standardization of Small Generator Interconnection Agreements & \nProcs., Order No. 2006, 111 FERC ¶ 61,220, at P 5, order on reh'g, Order No. 2006-A, \n113 FERC ¶ 61,195 (2005), order granting clarification, Order No. 2006-B, 116 FERC \n¶ 61,046 (2006) (\"this Final Rule applies only to interconnections with facilities that are \nalready subject to the Transmission Provider's OATT at the time the Interconnection \nRequest is made\"). \n365  See Order No. 2003, 104 FERC ¶ 61,103 at P 804; Order No. 2006, 111 FERC \n¶ 61,220 at P 481 (explaining that \"only facilities that already are subject to the \nTransmission Provider's OATT are covered by this rule [and that] the Commission is not \nencroaching on the States' jurisdiction\"). The interconnection of a second generator to \nthe same distribution facility for the purpose of engaging in wholesale sales is \njurisdictional, however, because the facilities are already being used to facilitate \nwholesale transactions and are subject to wholesale open access, meaning that it and any \nsubsequent wholesale generators must utilize the Commission-jurisdictional generator \ninterconnection procedures and agreements. Participation of Distributed Energy Res. \nAggregations in Mkts. Operated by Reg'l Transmission Orgs. & Indep. Sys. Operators, \nOrder No. 2222, 172 FERC 1161,247, at P 93 (2020), order on reh'g, Order No. 2222-A, \n174 FERC ¶ 61,197, order on reh'g, Order No. 2222-B, 175 FERC ¶ 61,227 (2021). \n366  See NARUC, 475 F.3d at 1280-82 (\"By establishing standard agreements FERC \nhas exercised its jurisdiction over the terms of those relationships.\") (citing TAPS, \n225 F.3d at 696 (\"FPA § 201 makes clear that all aspects of wholesale sales are subject to \nfederal regulation, regardless of the facilities used.\")). \n87 of 515"},{"page":89,"startToken":33118,"endToken":33556,"text":"DocUment Acces-e-icia4q: gt§g118 _3,4qcumenW-i-Jd Drtae:2018/Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 78 - \nprovided that transmission of electricity is in interstate commerce.367  As part of its \ntransmission authority, the Commission has exercised jurisdiction over the terms of \ncertain interconnections to the transmission system as \"an essential element of \n[t]ransmission [s]ervice\"368  and we agree with commenters who note the same.369  The \nCommission also \"may exercise jurisdiction over generation facilities to the extent \nnecessary to regulate interstate transmission\"37°  and may require \"physical changes\" to \nthose facilities as long as the changes \"bear a close enough relation to [the \nCommission's] exercise of jurisdiction over jurisdictional transactions.\"371  Similarly, \n367  See supra P 171. The Supreme Court has held that transmission facilities \nconnected to the interstate grid operate in interstate commerce, but the presumption that \ntransmission is in interstate commerce will not necessarily hold if transmission-level \nfacilities are not connected to that interstate grid. See New York v. FERC, 535 U.S. at 16 \n(citing FPC v. Fla. Power & Light Co., 404 U.S. 453, 466-67 (1972) (Florida Power)); \nsee also Florida Power, 404 U.S. at 462-63 (\"[The Commission's] alternative assertion \nthat energy commingles in a bus is, in our opinion, sufficient to sustain [the \nCommission's] jurisdiction.\"). See also Market Monitor April 23 Reply Comments at 13. \n368  Order No. 2003-A, 106 FERC ¶ 61,220 at P 698; see NARUC, 475 F.3d \nat 1280 (affirming Order No. 2003 and observing that \"interconnections appear to be \nrelationships between parties with respect to electricity flowing over facilities. . . . By \nestablishing standard agreements [the Commission] has exercised its jurisdiction over \nthe terms of those relationships.\"). The Commission has reiterated this finding \nrepeatedly. Pac. Gas & Elec. Co., 115 FERC ¶ 61,193, at P 36 (2006) \n(\"[I]nterconnection is part and parcel of transmission of electric energy in interstate \ncommerce, and thus interconnection service is part and parcel of jurisdictional \ntransmission service.\"); see also id P 36 n.52 (citing Tenn. Power Co., 90 FERC \n¶ 61,238, at 61,761, reh'g dismissed, 91 FERC ¶ 61,271 (2000)). \n369  See, e.g., Talen April 23 Reply Comments at 4-5 (explaining that the basis of \nthe Commission's authority is that the ISA governing a generator serving Co-Located \nLoad is Commission-jurisdictional). \n37°  TAPS, 225 F.3d at 718; NextEra Energy Res., LLC v. FERC, 118 F.4th 361, \n369 (D.C. Cir. 2024) (holding that an upgrade to a generator's equipment directly affects \nthe transmission of electricity in interstate commerce and is therefore within the \nCommission's jurisdiction). \n371  NARUC, 475 F.3d at 1282. \n88 of 515"},{"page":90,"startToken":33556,"endToken":33988,"text":"Document Accessig a§c: ?gAg?1:18- 3 g C1CUrnerVAd DEAcle:i.§918/P@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 79 - \n\"FERC may regulate electric generating facilities so long as it is addressing a practice \naffecting wholesale rates.\"372 \n174.\nWe acknowledge, as the Supreme Court has recognized, that the boundaries \nbetween federal and state jurisdiction are not hermetically sealed.373  The application of \nthe principles outlined in this order to Co-Location Arrangements depends on the specific \nfacts and circumstances presented in particular situations. We find, however, that the \nchanges to the PJM Tariff that the Commission directs in this order properly draw on the \nCommission's authority under the FPA without infringing on states' authority. \n3. \nShow Cause Findings  \na. \nOverview \n175.\nWe find that PJM's Tariff is unjust and unreasonable because it does not contain \nprovisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions of service that apply to Interconnection Customers serving Co-Located Load \nand Eligible Customers taking transmission service on behalf of Co-Located Load.374  As \nthe Commission explained in the Show Cause Order, the absence of such provisions \nleaves entities unable to determine what steps they must take to effectuate Co-Location \nArrangements of various configurations. Furthermore, this absence creates uncertainty \nthat has resulted in disparate treatment in PJM, where transmission owners have taken \ndifferent approaches to performing the necessary steps that apply to Interconnection \nCustomers seeking to serve Co-Located Load through a Co-Location Arrangement, \nleading to no consistent understanding of entities' responsibilities with respect to their \nplanned Co-Location Arrangements.375  The absence of such provisions also introduces \nthe risk that Co-Located Load may benefit from regulation and black start services \n372  Nat'l Ass 'n of Regul. Util. Comm'rs, 964 F.3d at 1186 n.5; accord La. Pub. \nServ. Comm 'n v. FERC, 522 F.3d 378, 390 (D.C. Cir. 2008) (explaining that \"the \ngenerating facility exception of Section 201(b)(1)\" conferring authority over generation \nfacilities to States \"does not apply where jurisdiction is specifically provided for in \ncertain specified sections of the [Federal Power] Act, including Sections 201 and 206.\"). \n373  EPSA, 577 U.S. at 281. \n374  See, e.g., EPSA/P3 April 23 Reply Comments at 10. \n375  See, e.g., Constellation, Complaint, Docket No. EL25-20-000 (filed Nov. 22, \n2024); Baltimore Gas & Electric Company and PECO Energy Company, Petition for \nDeclaratory Order, Docket No. EL24-149-000 (filed Sept. 30, 2024); Constellation \nApril 23 Reply Comments at 4 n.4 (stating that \"PJM is uniquely situated\" in having an \nunjust and unreasonable tariff absent co-location rules). \n89 of 515"},{"page":91,"startToken":33988,"endToken":34498,"text":"Document -AccedsiAaW gt\".2ggil8 - 3119.curnentiiirJa Daa.qe:19918/Pge Filed: 10/16/2026. \nDocket No. EL25-49-000, et al. \n- 80 - \nwithout contributing to cost recovery for such services. Many parties to this proceeding \nfiled comments supporting the Commission's preliminary finding that PJM's Tariff lacks \nsufficient clarity or consistency as to the rules for Co-Location Arrangements.376  We are \nnot persuaded by PJM's argument that its Tariff remains just and reasonable, because \nwhile PJM asserts that its existing Tariff permits Co-Location Arrangements, PJM \nrecognizes that there is a lack of clarity and consistency in the Tariff regarding the rules \nfor Co-Location Arrangements.377 \n176. First, we find the PJM Tariff unjust and unreasonable because there is a lack of \nsufficient clarity or consistency as to the rates, terms, and conditions of service that apply \nto Interconnection Customers serving Co-Located Load. As such, Interconnection \nCustomers seeking to use their generating facilities to serve Co-Located Load have no \nmeans of knowing the appropriate mechanism for setting forth the terms and conditions \nof Co-Location Arrangements. Moreover, without an Eligible Customer designated to \n376  See Constellation May 8 Answer at 9 (\"In sum, the record in this proceeding \nunequivocally supports the Commission's preliminary finding that the PJM Tariff lacks \nclear co-location rules and is unjust and unreasonable.\"); see also AEU April 23 Reply \nComments at 19 (\"Loads and generators pursuing [C]o-[L]ocation [A]rrangements need \nclarity as to how these arrangements will be studied, and how those studies will be \nevaluated. There must be a level of uniformity and detail outlining study requirements to \nensure regulatory certainty for large loads and new generation and storage resources \nseeking to serve large loads. This level of uniformity is currently lacking in PJM's \ninterconnection procedures and cost allocation methodology . . . .\"); EPSA/P3 April 23 \nReply Comments at 2 (\"EPSA and P3 agree with the Commission that PJM needs to \nestablish tariff provisions and rules to accommodate the array of [C]o-[L]ocated [L]oad \narrangements that will facilitate the timely and effective integration of large loads \nlocating in the region.\"); DCC April 23 Reply Comments at 7 (\". . . [T]he Commission \nshould direct PJM to develop clear, enforceable tariff language that affirms the \npermissibility of multiple co-location configurations, including those where load is \nserved directly from a generation resource located on or near the same site. Tariff clarity \nis essential to reduce unnecessary disputes, avoid case-by-case confusion, and enable \ntransmission providers to process interconnection and load addition requests efficiently \nand predictably.\"). \n377  PJM March 24 Response at 32 (\"Nevertheless, clarifications and enhancements \ncould well be in order given that this is an evolving area and Tariff provisions did not \ncontemplate the type of arrangements at issue in this docket or their implications.\"); id. \nat 35 (\"The extent to which netting [rules under the PJM Tariff] could or should apply to \nco-located data center load is not clear at this time.\"); see also Vistra April 23 Reply \nComments at 11 (arguing that PJM has \"effectively conceded\" that the PJM Tariff does \nnot contain sufficient clarity). \n90 of 515"},{"page":92,"startToken":34498,"endToken":35028,"text":"Document AccessiAa§c:  ?,§2gP18 - 3 Acicumentiiirl DFafie:19118/P@ \nFiled: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 81 - \ntake transmission service on behalf of a Co-Located Load, there is no mechanism for \nPJM to address situations in which a Co-Located Load withdraws energy from the \ntransmission system. As described in Part IV.B.4.a, we therefore direct PJM to file, as \nthe first part of the replacement rate, revisions to the generation interconnection \nprocedures of the Tariff, including to require an Interconnection Customer who will use \nits generating facility to serve Co-Located Load to specify an Eligible Customer who will \ntake transmission service on behalf of the Co-Located Load. We also direct PJM to file \nTariff changes specifying that an Interconnection Customer seeking to serve Co-Located \nLoad using an existing generating facility must bear the costs of all Network Upgrades \nthat PJM finds are necessary to preserve transmission system reliability for existing \ntransmission customers, and that an existing generating facility cannot begin service to a \nCo-Located Load until all required Network Upgrades are in service. This requirement \nwill protect existing transmission customers from transmission reliability risks and from \nbearing the cost of Network Upgrades required for an Interconnection Customer to begin \nserving Co-Located Load. Furthermore, as described in Part IV.B.4.d, we direct PJM to \nrevise its Tariff to clarify that an Interconnection Customer seeking to serve a \nCo-Located Load with a newly interconnecting generating facility may: (1) request \ninterconnection service at a level below its maximum facility output; (2) use existing \nprocedures in the PJM Tariff to accelerate the study of the interconnection service request \nif the request has no cost allocation for Network Upgrades and does not require further \nstudies; (3) request provisional interconnection service; and (4) request Surplus \nInterconnection Service. \n177. Second, we also find that PJM's Tariff is unjust and unreasonable because it does \nnot include transmission services that reflect Eligible Customers378  taking service on \nbehalf of Co-Located Loads that are willing and able to limit their energy withdrawals \nfrom the transmission system under certain conditions. As discussed below, requiring \nEligible Customers taking transmission service on behalf of Co-Located Load to take \nNITS, without the option to instead take the new transmission services set forth in this \norder, would be inefficient. Specifically, for Eligible Customers taking service on behalf \nof Co-Located Loads that do not reserve transmission or take energy from the \ntransmission system but which receive only regulation and black start services, or that \notherwise are willing and able to limit their energy withdrawals from the transmission \nsystem, requiring such Eligible Customers to take NITS on behalf of these Co-Located \nLoads may in some circumstances result in costly and inefficient transmission system \n378  PJM defines Eligible Customer as: \"(i) Any electric utility ... or any person \ngenerating electric energy for sale for resale ... (ii) Any retail customer taking unbundled \ntransmission service pursuant to a state requirement that the Transmission Provider or a \nTransmission Owner offer the transmission service, or pursuant to a voluntary offer of \nsuch service by a Transmission Owner, is an Eligible Customer under the Tariff . . . .\" \nPJM, Intra-PJM Tariffs, OATT, § I.1 Definitions — E-F (41.0.0). \n91 of 515"},{"page":93,"startToken":35028,"endToken":35497,"text":"Document Accessig a§c: gt-d§gii8-3gqcurnentiili-Ja nrage:aWis/Pgte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 82 - \nbuildout that may not be necessary if such Eligible Customers are willing and able to take \na transmission service that requires fewer Network Upgrades to provide, and therefore \nmay result in lower Network Upgrade costs, than would NITS. Moreover, we find that \nPJM's Tariff is unjust and unreasonable because it does not address charges related to \nCo-Located Loads' use of regulation and black start services, which introduces the risk \nthat Co-Located Load may benefit from regulation and black start services without \ncontributing to cost recovery for such services and, thereby, the risk that costs may be \nallocated entirely to other transmission customers and passed through to residential \ncustomers, among others.379  Specifically, the record demonstrates that Co-Located \nLoads, which are synchronized with the PJM transmission system, use regulation and \nblack start services, as explained below. In addition to regulation and black start \nservices, Co-Located Loads that withdraw energy from the transmission system are \ntaking transmission service. \n178. Therefore, as the second part of the replacement rate, we direct PJM to revise its \nTariff to create three new transmission services that reflect that Eligible Customers taking \nservice on behalf of Co-Located Loads are willing and able to limit their energy \nwithdrawals from the transmission system under certain conditions. Specifically, we \ndirect PJM to revise its Tariff to allow Eligible Customers seeking to take NITS on behalf \nof Co-Located Load to take a new interim, non-firm transmission service until all \nNetwork Upgrades necessary to provide the requested NITS are complete. We further \ndirect PJM to offer two other new transmission services—a Firm Contract Demand \ntransmission service and a Non-Firm Contract Demand transmission service380—that an \nEligible Customer can choose to take on behalf of a Co-Located Load instead of taking \nNITS. Specific to these new transmission services, we establish paper hearing \nprocedures to determine the just and reasonable rates, terms, and conditions for such \nservices. \n379  While the replacement rate we establish in Part IV.B.4 applies to Eligible \nCustomers taking transmission service on behalf of Co-Located Load, we intentionally \nrefer at times only to Co-Located Load, for example, when explaining in our Show Cause \nfindings how Co-Located Load uses certain services. \n380 Under this Non-Firm Contract Demand transmission service, we note that an \nEligible Customer on behalf of a Co-Located Load may elect to not reserve any amount \nof transmission service to the extent that the Eligible Customer will not withdraw any \nelectricity from the transmission system. In such a scenario, as discussed below, the \nEligible Customer taking the Non-Firm Contract Demand transmission service on behalf \nof a Co-Located Load will be charged for regulation and black start services, subject to \nthe paper hearing established below. \n92 of 515"},{"page":94,"startToken":35497,"endToken":36022,"text":"Document Accessiccia§c:  4)24cils _ 3Pacumen IF: ilrJ DFAcie:19.?ia/PAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 83 - \n179.\nThird, we find the existing BTMG rules in the PJM Tariff to be unjust and \nunreasonable. As discussed below, under the existing Tariff, loads with BTMG are not \nfully accounted for in resource adequacy planning. As such, the existing BTMG rules \nmay lead to both reliability and resource adequacy risks because PJM, per its Tariff, is \nobligated to serve transmission customers using BTMG but does not consider such \ncustomers in transmission and resource adequacy planning. Thus, as the third part of the \nreplacement rate, we direct PJM to revise its BTMG rules. Recognizing concerns raised \nin the record about the potential impacts on existing BTMG customers of the \nCommission changing PJM's BTMG rules, however, we direct PJM to maintain the \ncurrent BTMG rules for customers that fall below a new MW materiality threshold for \nthe amount of load at a particular electrical location that Network Customers may net \nusing BTMG. We also direct PJM to implement a two-part transition process for retail \nBTMG, as discussed below, including: (1) the establishment of a three-year transition \nperiod; and (2) the ability to grandfather certain entities with existing contracts, as \ndescribed further below. A materiality threshold for all BTMG should reduce the \nreliability and resource adequacy risks that large or increasing BTMG may pose to PJM, \nwhile also allowing for Network Customers to reduce their transmission charges in a \ntransparent, not unduly discriminatory fashion. \n180.\nFinally, because certain aspects of PJM's interconnection procedures do not \nclearly explain how and where they apply to Interconnection Customers seeking to serve \nCo-Located Load, we direct several clarifications to PJM's Tariff regarding \ninterconnection procedures for these customers. In addition, we require PJM to file an \ninformational report on several matters related to PJM's Critical Issue Fast Path (CIFP) \nstakeholder process and PJM's integration of new generation sufficient to serve \nforecasted large load additions within 30 days of the date of issuance of this order. \nb. \nTransmission Service, Regulation and Black Start \n181.\nThe Commission's cost causation principle requires costs to be allocated to those \nwho cause the costs to be incurred and reap the resulting benefits.381  Courts and the \nCommission have acknowledged that adherence to the cost causation principle does not \nrequire that cost allocation methods balance costs and benefits with \"exacting \n381  See S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 87 (D.C. Cir. 2014) (\"[T]he \nCommission's adoption of a beneficiary-based cost allocation method is a logical \nextension of the cost causation principle[;] under that basic tenet, which we have \nrepeatedly embraced, `costs are to be allocated to those who cause the costs to be \nincurred and reap the resulting benefits.\"). See also ICC v. FERC I, 576 F.3d at 476 \n(\"To the extent that a utility benefits from the costs of new facilities, it may be said to \nhave `caused' a part of those costs to be incurred, as without the expectation of its \ncontributions the facilities might not have been built, or might have been delayed.\"). \n93 of 515"},{"page":95,"startToken":36022,"endToken":36493,"text":"Document Acces-±AaC: g,Ap.i18__ 3 aqcument,i1-1-jd Deta,Re:19,h8/pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 84 - \nprecision.\"382  Ultimately, the requirement is met so long as \"all approved rates reflect to \nsome degree the costs actually caused by the customer who must pay them[,]\"383  and this \napportioning is done by ensuring that costs are \"allocated in a manner that is at least \nroughly commensurate with benefits.\"384 \n182.\nThere are significant costs to building, operating, and maintaining the transmission \nsystem to provide, as relevant here, transmission service, regulation service, and black \nstart service, including fixed costs such as wires, poles, transformers, and substations, as \nwell as ongoing maintenance and upgrades necessary to maintain reliability and serve \nload.385  Transmission providers undertake substantial planning and make significant \ninvestments to minimize disruptions on the transmission system that may impact \ngenerators or force generators to go offline.386 \n183.\nThere is significant agreement in the record that Co-Located Loads that are \nsynchronized with the PJM transmission system use and benefit from at least some \nancillary services and may be reasonably charged for such benefits.387  The Commission \n382  Coal. of MISO Transmission Customers v. MISO, 172 FERC ¶ 61,099, at P 83 \n& n.228 (2020) (quoting Midwest ISO Transmission Owners, 373 F.3d at 1369). \n383  Id. P 82 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. \n1992)). \n384  Mun. Energy Agency of Neb. v. Pub. Serv. Co. of Colo., 189 FERC ¶ 61,099, \nat PP 41, 46 (2024) (citation omitted), subsequent history omitted; see also Pub. Serv. \nElec. & Gas Co., 989 F.3d at 13 (explaining that \"although the Commission need not \n`allocate costs with exacting precision,' the costs assessed against a party must bear some \nresemblance `to the burdens imposed or benefits drawn by that party') (quoting Midwest \nISO Transmission Owners, 373 F.3d at 1368-69). \n385  See, e.g., Indicated Transmission Owners March 24 Response at 3. \n386  See, e.g., PJM March 24 Response at 42; ITC, Comments, Docket \nNo. AD24-11, at 5 (filed Dec. 9, 2024). \n387  See Constellation April 23 Reply Comments at 34 (\"[I]t may be appropriate to \ninclude some ancillary service charges, such as regulation and black start . . . .\"); \nConstellation May 8 Answer at 14 (\"To eliminate any debate and move past what always \nhas been a peripheral issue, Constellation would support generator-contingent co-location \nrules that included ancillary service charges as part of a replacement rate.\"); Vistra \nApril 23 Reply Comments at 26 (\"Vistra acknowledges that it may be reasonable to \ncharge a co-location configuration for some ancillary services . . . .\"); ; Advanced Energy \nUnited April 23 Reply Commentsat 19 (\"Ultimately, when large co-located loads come \nonline, they will use some ancillary and other wholesale services, and should pay for the \n94 of 515"},{"page":96,"startToken":36493,"endToken":36958,"text":"Document AccessiA a§e: g zgki, _3  gqcumenOrld D,VAile:1918/pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 85 - \nhas defined ancillary services as part of the costs of transmission services, specifically as \nthose \"that must be offered with basic transmission service under an open access \ntransmission tariff ... [and] needed to accomplish transmission service while maintaining \nreliability within and among control areas affected by the transmission service.\"388  Also, \nas PJM notes, ancillary services \"pass through transmission lines.\"389 \n184. Regulation service is necessary to provide for the continuous balancing of \nresources with load and for maintaining scheduled interconnection frequency at 60 cycles \nper second (60 Hz).39°  The cost of providing regulation service is currently charged or \ncredited to LSEs and wholesale loads based on their pro rata share of the regulation \nrequirements, net of BTMG, for the regulation zone for the hour (but not to be less than \nzero).391  Regardless of whether a Co-Located Load is drawing energy from the \ntransmission system, Co-Located Loads are unlikely to have a perfect load factor,392  and \nit will therefore be necessary for PJM to use regulation service to maintain the power \nbalance between the five-minute intervals of the real-time energy market. Depending on \nthe Co-Location Arrangement, variability in the Co-Located Load may be reflected in the \ngenerator's net output to the transmission system. Any moment-to-moment variability in \nservices as any customer would.\"); PIOs April 23 Reply Comments at 25 (\". . . [C]o-\nlocation arrangements should pay for their share of transmission and ancillary services \ncosts since the transmission system to which co-location arrangements connect deliver \nblackstart and other critical services to ensure reliability for these co-location \narrangements.\"). \n388  City of Holland, Mich. v. Midwest Indep. Transmission Sys. Operator, Inc., \n123 FERC ¶ 61,187, at P 21 (2008) (citing Order No. 888, FERC Stats. & Regs. ¶ 31,036 \nat 31,705). \n389  PJM March 24 Response at 36. \n39°  PJM, Intra-PJM Tariffs, OATT, sched. 3 (6.0.0). \n391  Id. See also PJM Manual 28. Regulation and Frequency Response Service is \naccomplished by committing on-line resources whose output is raised or lowered \n(predominantly through the use of automatic generating control equipment) and by other \nnon-generation resources capable of providing this service as necessary to follow the \nmoment-by-moment changes in load. Each LSE's share of the regulation requirement is \nbased on its total load net of BTMG for the hour (but not to be less than zero). However, \nas discussed below, we find PJM's existing BTMG netting rules unjust and unreasonable. \n392  Load factor refers to \"[t]he ratio of the average load to peak load during a \nspecified time interval.\" U.S. Energy Info. Admin. (EIA), Glossary (last visited \nDec. 2025), https://wwvv.eia.gov/tools/glossary/index.php?id=L. \n95 of 515"},{"page":97,"startToken":36958,"endToken":37383,"text":"Document Accede-igft a§e: ?§IN?il8 _ 3 PaCUmenW-i-Jd neta.qe:I.M.8/Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 86 - \nthe Co-Located Load within real-time market intervals may be absorbed by the \ntransmission system, meaning that unless an Eligible Customer takes transmission service \non behalf of the Co-Located Load, there will be no charges for the benefits that this \nancillary service provides. This variability will exist even if the Co-Located Load takes \nno energy from the transmission system. We therefore find that Eligible Customers \ntaking one of the new transmission services on behalf of Co-Located Load must be \nassessed for regulation service on a gross demand basis at the existing Tariff rate, \nconsistent with the Commission's cost causation principles. \n185. Black start service is the ability of generators to start without an outside electric \nsupply or remain operating when disconnected from the transmission system. The \nrevenue requirements of units providing black start service are recovered from \ntransmission customers based on coincident peak load.393  While parties have noted that \nthe generating facilities of some Interconnection Customers serving Co-Located Load \nmay be able to provide black start service,394  many cannot; and even if the generating \nfacility of an Interconnection Customer can provide black start service, as long as it is \nconnected to the transmission system, black start must be coordinated with the system \noperator to avoid damage to other components of the transmission system.395  Therefore, \nCo-Located Loads that remain connected to the transmission system through an \nInterconnection Customer will benefit from black start service in a manner comparable to \nNetwork Loads. Further, as parties argue, Co-Located Loads rely on black start service \nfor the restoration of the transmission system.396  We .therefore find that Co-Located \nLoads benefit from black start service even if they have zero net energy withdrawals and \nEligible Customers taking one of the new transmission services on behalf of Co-Located \nLoad must be assessed for this service based on gross demand basis at the existing Tariff \nrate. \n393  PJM, Intra-PJM Tariffs, OATT, sched. 6A (16.1.0). \n394  See, e.g., Mainspring April 23 Reply Comments at 11. \n395  See, e.g., PJM's March 24 Response at 42-43. \n396  See, e.g., Indicated Transmission Owners March 24 Response at 13 n.29. See \nalso PJM March 24 Response at 42 (\"The load and generator are connected to and \nsynchronized with the multi-state bulk power system. It is not operating as a micro grid \n(nor can it if the generating facility is a nuclear unit).\"). \n96 of 515"},{"page":98,"startToken":37383,"endToken":37831,"text":"Document Accessigia§q:  gt- g,?118-3Aqcumeq'i ll-Ja \ne•19718/ \nFEed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 87 - \nc. \nBTMG \n186. We find that circumstances have changed since the Commission approved PJM's \nretail BTMG rules such that these rules are no longer just and reasonable.397  PJM \nexplains that the BTMG rules were \"conceived for, and [have] been implemented for, \nsubstantially smaller loads (like a warehouse with solar panels) and not on the scale of \nlarge data centers.\"398  However, large loads, both existing and in the planning stages \nwith PJM, have proliferated in recent years, and PJM has persuasively explained the \nproblems that could occur if Network Customers with large loads were allowed to use the \nexisting BTMG rules in the Tariff.399  For example, PJM explains that \"[a]llowing very \nlarge loads like data centers to net is problematic because loads in this configuration do \nnot carry reserves.\"4°°  Such loads must nevertheless be served, however, allowing them \nto \"lean on the PJM system when the co-located generation is on a full or partial outage \nor if the load exceeds the rating of the co-located generation.\"401  Importantly, PJM's \nexisting BTMG rules do not limit the amount of qualifying load that a Network Customer \nmay net by using BTMG and do not provide any protections against this potential \ntransmission and resource adequacy planning problem or against the costs of maintaining \nsufficient resources to serve these loads being shifted onto other customers.402  We \ntherefore find that PJM's BTMG rules are no longer consistent with cost causation \nprinciples, because large loads configured in a BTMG arrangement with significant \ngeneration will raise cost shifting concerns compared to loads pursuing smaller amounts \nof netting. We find that PJM's existing BTMG rules may lead to both reliability and \n397  See PJM, 107 FERC ¶ 61,113; ISO New England Inc., 173 FERC ¶ 61,198, \nat P 68 (2020) (finding new entrant rules unjust and unreasonable based on changed \ncircumstances). \n398  PJM March 24 Response at 13. \n399  See, e.g., Docket No. AD24-11-000, Large Loads Co-Located at Generating \nFacilities Tr. at 9:2-3 (noting that \"large data centers [] need these significant new \namounts of energy for their business\"); PJM Interconnection, L.L.C., 188 FERC \n¶ 61,200, at P 5 (2024) (\"PJM explains that the [tariff] proposal [to allocate load \nadjustments] was spurred by the recent proliferation of data centers that are contributing \nto large additions of forecasted load concentrated within a specific wholesale metering \narea.\"). \n4\" PJM March 24 Response at 36. \n481  Id. at 13 n.5. \n402 rs \nPJM, Intra-PJM Tariffs, OATT, § III.34.2 Netting of Behind the Meter \nGeneration (0.0.0). \n97 of 515"},{"page":99,"startToken":37831,"endToken":38250,"text":"Docurrient AccesgigAaW ?P2-§@?i.18- 3PAcumenWrld Def3ae:1.9Pis/P@te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 88 - \nresource adequacy risks because PJM, per its Tariff, is obligated to serve transmission \ncustomers using BTMG but does not consider such customers in transmission and \nresource adequacy planning. We clarify that, while the order is limited to Co-Located \nLoads, this finding applies to all Network Load. \n4. \nReplacement Rate \na. \nGeneration Interconnection Procedures, pro forma GIA, \nand Common Service Provisions  \n187.\nWe direct PJM to submit a compliance filing to establish rules for Interconnection \nCustomers serving Co-Located Load. As discussed below, we direct PJM to revise the \ngeneration interconnection procedures of the Tariff, the pro forma Generation \nInterconnection Agreement (GIA),403  and Part I, Common Service Provisions, of the \nTariff, and Attachment O, Appendix 2 of the Tariff \n188.\nFirst, we direct PJM to submit, within 60 days of the date of issuance of this order, \na compliance filing to revise the generation interconnection procedures of the Tariff In \nparticular, we direct PJM to revise its OATT, VIII, Subpart B, section 403 - Application \nRules to add to the list of requirements for a New Service Request that an Interconnection \nCustomer who will use its generating facility to serve Co-Located Load must specify an \nEligible Customer who will take transmission service on behalf of the Co-Located \nLoad.404  As part of that compliance filing, we also direct PJM to submit revisions to the \ngeneration interconnection procedures to specify any operational procedures or data \n403 We note that, as part of reforms to its interconnection process to transition from \na serial first-come, first-served study process to a first-ready, first-served cluster study \napproach, PJM renamed its pro forma ISA to the pro forma GIA. See PJM \nInterconnection, L.L. C., 181 FERC ¶ 61,162 (2022). The new pro forma GIA applies to \ninterconnection requests subject to the transition period rules and the new rules accepted \nin the PJM queue reform.proceeding. Interconnection Customers who executed \ninterconnection agreements prior to the transition period executed an ISA. Accordingly, \nwe refer to both ISAs and GIAs in this order, where applicable. \n404 An Eligible Customer could be, for example, any person generating electric \nenergy for resale or any retail customer taking unbundled transmission service under \ncertain conditions. For the full definition of Eligible Customer, see Part I.C. For a \ndiscussion of how an Eligible Customer may take transmission service on behalf of \nCo-Located Load, see infra P 189 n.407. \n98 of 515"},{"page":100,"startToken":38250,"endToken":38723,"text":"Document Accessicaa§c:  4:42*21:18-3PAcumentii.lAd atICte:19918/Fate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 89 - \nexchange requirements that PJM deems necessary for Co-Location Arrangements to \nremedy our finding that its Tariff lacks sufficient clarity or consistency.' \n189.\nThese Tariff revisions, which will apply to all Interconnection Customers \nrequesting to interconnect their generating facilities to the transmission system and \nseeking to use those facilities to serve Co-Located Load,406  will establish a requirement in \nthe Tariff for the Eligible Customer to be charged for transmission and ancillary services \nthat the Eligible Customer must take on behalf of the Co-Located Load—either NITS or \nthe new transmission services described below in Part IV.B.4.b.iii.407  To the extent that \nan Interconnection Customer wishes to serve Co-Located Load using its generating \nfacility but not identify an Eligible Customer, then the Interconnection Customer may \ntake steps to terminate its generating facility's interconnection to the PJM transmission \nsystem and serve the Co-Located Load fully islanded from PJM's transmission system. \n190.\nSecond, we direct PJM to submit, within 60 days of the date of issuance of this \norder, a compliance filing to revise its pro forma GIA. In particular, we direct revisions \nto OATT, Part IX, Subpart B GIA to specify that an Interconnection Customer that will \nuse its generating facility to serve Co-Located Load must specify an Eligible Customer \nthat will take transmission service on behalf of the Co-Located Load. We find that this \nrevision will ensure that the charges for transmission and ancillary services taken by \nEligible Customers to serve Co-Located Load are appropriately assigned to those Eligible \nCustomers. \n191.\nThird, we direct PJM to submit, within 60 days of the date of issuance of this \norder, a compliance filing to add a new provision to Part I, Common Service Provisions, \n405 For example, PJM explains that \"unique operational procedures and data \nexchange requirements like those proposed in the Susquehanna [Interconnection Service \nAgreement] should be developed and specified\" and that pro forma agreements may \nrequire modification to specify, where applicable, the entities that own any Co-Located \nLoad and contact information at the Co-Located Load for use during emergency and \nnon-emergency situations. PJM March 24 Response at 60-62. \n406 See PJM Interconnection, L.L. C., 189 FERC ¶ 61,078 at P 87 (Susquehanna) \n(\"This [reliance on a generally applicable document for proposed non-conforming \nprovisions] raises questions regarding whether PJM intends to offer these terms to all \nsimilarly situated interconnection customers.\"). \n407 There are several ways that an Eligible Customer could take transmission \nservice on behalf of Co-Located Load. For example, subject to applicable state law, the \nEligible Customer could create a corporate intermediary to serve the Co-Located Load, or \nthe Co-Located Load, acting as an Eligible Customer, could request service from the \nrelevant transmission owner directly. \n99 of 515"},{"page":101,"startToken":38723,"endToken":39222,"text":"Document AccessigPSA: 22Q- \n18-SD \nu ment:Fhla rPaN 9: Mc18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 90 - \nof the Tariff that requires Interconnection Customers with ISAs or GIAs executed, or \nrequested to be filed unexecuted, prior to the effective date of the revised generation \ninterconnection procedures and pro forma GIA directed in this order that wish to add \nCo-Located Load or are currently serving Co-Located Load to publicly notify PJM of \nthat addition and identify the Eligible Customer that will take transmission service on \nbehalf of that Co-Located Load. As discussed further below, that Eligible Customer must \nabide by the terms of the Tariff, including terms regarding transmission service. \n192. As a result of these requirements, an Interconnection Customer that requests to \ninterconnect its generating facility to the PJM transmission system, or whose generating \nfacility is already interconnected to the PJM transmission system, and seeks to serve \nCo-Located Load, or is currently serving Co-Located Load, using its generating facility \nmust specify an Eligible Customer who will take transmission service on behalf of the \nCo-Located Load, thereby ensuring that the Eligible Customer will be the party \nresponsible for executing a transmission service agreement, which will ensure that the \ncharges for transmission and ancillary services are appropriately assigned. \nb. \nTrans mission Services  \n193. As discussed above, PJM's Tariff is unjust and unreasonable because it does not \ncontain provisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions of service that apply to Eligible Customers taking transmission service on \nbehalf of Co-Located Load. Specifically, as above, we find that PJM's Tariff is unjust \nand unreasonable because it does not include transmission services that reflect Eligible \nCustomers taking service on behalf of Co-Located Loads that are willing and able to limit \ntheir energy withdrawals from the transmission system under certain conditions. The \nfollowing discussion relates to the types of transmission service that an Eligible Customer \ntaking transmission service on behalf of a Co-Located Load must select from when it \nrequests the required transmission service. We look to cost causation principles to \ndetermine what constitutes the Eligible Customer's just and reasonable share of \ntransmission system costs and therefore direct a three-part replacement rate based on the \ndegree to which the Eligible Customer on behalf of Co-Located Load takes transmission \nand ancillary services. Specifically, we direct PJM to submit, within 60 days of the date \nof issuance of this order, a compliance filing to modify its Tariff to require that the \nEligible Customer taking transmission service on behalf of a Co-Located Load takes one \nof three transmission services: (1) NITS or a new interim, non-firm transmission service \nwhile Network Upgrades to provide full NITS service are constructed, (2) a new Firm \nContract Demand transmission service, or (3) a new Non-Firm Contract Demand \ntransmission service. As a part of this compliance obligation, PJM must ensure a \ntransmission service agreement that reflects the rates terms, and conditions of these new \ntransmission service options is available to Eligible Customers. \n100 of 515"},{"page":102,"startToken":39222,"endToken":39708,"text":"Document Accessigi \n2A-2-1€1418 -3EKument:Flita EpAg9: iipA 8  / 2  paje Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 91 - \n194. With respect to the new transmission services that we require, we establish paper \nhearing procedures to determine the appropriate rates, terms, and conditions of those \nservices. This Tariff requirement, which will apply to any Eligible Customer taking \ntransmission service on behalf of Co-Located Load, incorporates the existing \ntransmission service structure in the Tariff, which imposes rates, terms, and conditions of \ntransmission service on the Eligible Customer. The Tariff requirements that we establish \napply to the relevant Interconnection Customer taking interconnection service and the \nEligible Customer taking transmission service on behalf of the Co-Located Load. \nEligible Customers, on behalf of the Co-Located Loads that they represent, may choose \nthe transmission services that match their preferred use of the transmission system; \nhowever, they must choose at least one of the required transmission services, and may \ntake a combination of the new Firm Contract Demand and Non-Firm Contract Demand \ntransmission services that we direct herein. \ni. \nNITS \n195.\nFirst, we note that it continues to be just and reasonable for an Eligible Customer \ntaking transmission service on behalf of Co-Located Load to elect, as one of the required \ntransmission services from which the Eligible Customer must choose, to take NITS.408 \nAs discussed further below, NITS provides significant benefits because a NITS customer \ngains the right to be served from the transmission system at any time, and PJM and the \ntransmission owners incorporate NITS load into their transmission planning. However, \nas discussed above, we find that the existing Tariff's BTMG rules are unjust and \nunreasonable. Thus, Eligible Customers that elect to take NITS on behalf of Co-Located \nLoads will not be able to use the existing BTMG rules and must instead take NITS on a \ngross demand basis.\"9  While we find that NITS charged on a gross demand basis is one \njust and reasonable transmission service option for Eligible Customers taking \ntransmission service on behalf of Co-Located Loads, it is not the only option. This order \nestablishes new transmission service options that Eligible Customers taking transmission \nservice on behalf of Co-Located Loads may use if they do not wish to take NITS on a \ngross demand basis. \n196.\nConsistent with our finding that the existing Tariffs BTMG rules are unjust and \nunreasonable, we find that it would be unjust and unreasonable to allow Eligible \nCustomers taking transmission service on behalf of Co-Located Loads to take NITS on a \nnet basis. The Commission has previously found that loads that are able to be served in \n408  Eligible Customers taking NITS on behalf of Co-Located Load may not \ncombine NITS with any of the other transmission services discussed herein. \n409  Eligible Customers taking service on behalf of Co-Located Loads that meet the \nnew criteria discussed below may be able to use the new BTMG rules. \n101 of 515"},{"page":103,"startToken":39708,"endToken":40155,"text":"Dodument Accee-sigPsg 22qq.q-1, 31?p,cument:Flil d rfa'qg9: iipA8/2pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 92 - \npart through NITS and in part through behind-the-meter generation41°  shift costs onto \nother transmission customers.411  Furthermore, the Commission has rejected cost \ncausation arguments made by network customers that sought to lower their load ratio \nshare based on actual use of the transmission system.412  The Commission has explained \nthat \"splitting a discrete load is antithetical to the concept of network service\" because \"a \nload at a discrete point of delivery cannot be partially integrated—it is either fully \nintegrated or not integrated.\"413  In addition, the Commission found that a split system \ncreates the potential for a customer to evade some or all of its load ratio share cost \nresponsibility for network services by using behind-the-meter generation during monthly \npeaks to reduce its load ratio share below its actual, typical monthly peak usage (also \ncalled peak shaving), resulting in a rate that is subsidized by other network customers.414 \nSimilarly, in Order No. 890,415  the Commission refused to require transmission providers \nto allow netting of behind the meter generation against network transmission charges. \nThe Commission explained that its existing policy already provides customers with the \nopportunity to reduce network service costs to the extent a customer is not relying on the \ntransmission system to meet its energy needs (i.e., by taking PTPS instead of NITS).416 \n410 Here we reference behind-the-meter generation more broadly, rather than \nPJM's defined BTMG specifically. \n411  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,259-61. \n412  See, e.g., Amtrak, 171 FERC 1161,237 at P 41. See also PJM, 169 FERC \n¶ 61,041, at P 60 (2019). \n413  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,262. \n414  Id. at 30,260-61. See also East Ky. Power Coop. Inc. v. Louisville Gas & Elec. \nCo./Ky. Utils. Co., 154 FERC ¶ 61,144, at P 60 (2016) (\"[T]he Commission used the \n`behind-meter-generation' language as an example of transmission customers subject to \nthe provision but it did not explicitly exclude . . . other transmission customers from this \nprovision.\"). \n415  Preventing Undue Discrimination and Preference in Transmission Serv., Order \nNo. 890, 118 FERC ¶ 61,119, at P 1619, order on reh'g, Order No. 890-A, 121 FERC \n1161,297 (2007), order on reh'g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on \nreh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, \n129 FERC ¶ 61,126 (2009). \n416  Id. The Commission also explained that it would review alternative \ntransmission provider proposals for behind-the-meter generation treatment on a \ncase-by-case basis. Id. \n102 of 515"},{"page":104,"startToken":40155,"endToken":40655,"text":"Document AccessigPA 22A2-Y1418- PKument:Fl i l d \nilp48/2p2a5te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 93 - \n197.\nRegarding Constellation's argument that it is unduly discriminatory to charge \nEligible Customers taking transmission service on behalf of Co-Located Loads for NITS \non a gross demand basis to the extent it would charge the same rates to customers who \nimpose different costs on the system,417  we reiterate that while Eligible Customers taking \ntransmission service on behalf of Co-Located Loads must take one of the required \ntransmission services, they may take one of the new transmission services instead of \nNITS. Therefore, Eligible Customers taking transmission service on behalf of \nCo-Located Loads that do not wish to be Network Load may seek the alternative \ntransmission services described below. Constellation further argues that charging all \nEligible Customers taking transmission service on behalf of large Co-Located Loads for \nNITS based on a gross demand basis would be unduly discriminatory because it is \ninconsistent with the treatment of BTMG.418  However, we direct changes to PJM's \nexisting BTMG rules, as described below. In doing so, we decline to address \nConstellation's alternative proposals to modify the BTMG provisions.419 \n198.\nThe Network Load that an Eligible Customer designates when taking NITS on \nbehalf of a Co-Located Load will benefit from the transmission system in the same \nmanner as the Network Load of other NITS customers. The Network Load of the \nEligible Customer taking NITS on behalf of a Co-Located Load will gain the right to be \nserved from the transmission system at any time. The Network Load of the Eligible \nCustomer taking NITS on behalf of a Co-Located Load, as any other Network Load, \nwould contribute to the need for costs to be incurred for operation and maintenance of the \ntransmission system, as well as new Network Upgrades to keep the transmission system \nreliable. Moreover, PJM explains, and we agree, that, if Co-Located Load is Network \nLoad, PJM will include the customer's full load in its models for purposes of procuring \ncapacity and will include Co-Located Load that is Network Load in the load forecast for \n417  Constellation April 23 Reply Comments at 31. \n418  Id. at 32-33, 39. \n419  See FirstEnergy Serv. Co. v. FERC, 758 F.3d 346, 353 (D.C. Cir. 2014) (\"The \nstatutory `just and reasonable' standard is the same under section 205 and section 206.\"); \nExxonMobil Oil Corp. v. FERC, 487 F.3d 945, 955 (D.C. Cir. 2007) (\"Under the arbitrary \nand capricious test, our standard of review is `only reasonableness, not perfection.' We \nneed not decide whether the Commission has adopted the best possible policy as long as \nthe agency has acted within the scope of its discretion and reasonably explained its \nactions.\"); New England Power Generators Ass 'n v. ISO New England Inc., 153 FERC \n¶ 61,222, at P 35 (2015) (explaining that, in setting a just and reasonable replacement \nrate, the Commission could accept a party's proposal or \"implement[] its own solution\"). \n103 of 515"},{"page":105,"startToken":40655,"endToken":41142,"text":"Document Acces \n4Aq..418 - 31;19Pu ment:Flild iFaiN9: -.LpA8/2pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 94 - \npurposes of transmission planning.420 Therefore, we find that if an Eligible Customer \ntakes NITS and designates a Co-Located Load as Network Load, the NITS charges an \nEligible Customer incurs on behalf of that Co-Located Load will be at least roughly \ncommensurate with the benefits received. \n199. \nWe disagree with parties who argue that Co-Located Loads should only be \nallowed to take NITS, and that the NITS they must take is on a gross demand basis.421 \nAs discussed further below, we find that the option to take NITS on a gross demand basis \nis just one part of a just and reasonable replacement rate that also includes the \nopportunity for Eligible Customers to take on behalf of Co-Located Loads the new Firm \nor Non-Firm Contract Demand transmission services. As explained below, the record \ndemonstrates that Eligible Customers taking transmission service on behalf of \nCo-Located Loads are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.422  It would be inconsistent with cost \ncausation principles to require Eligible Customers taking transmission service on behalf \nof Co-Located Loads that limit their energy withdrawals to take NITS on a gross demand \nbasis. Rather, Eligible Customers taking service on behalf of Co-Located Loads should \nbe allowed to choose the transmission service that aligns with their use of the \ntransmission system and therefore aligns the charges for service with the benefits \nreceived. Further, we find that requiring an Eligible Customer taking transmission \nservice on behalf of Co-Located Load to take NITS on a gross demand basis would be \ninefficient. Requiring this could necessitate inefficient and costly transmission buildout \nand costs paid by transmission customers that may not be necessary if Eligible Customers \ntaking transmission service on behalf of Co-Located Loads are willing to limit their \nenergy withdrawals and take a transmission service that requires fewer Network \nUpgrades to provide.423 \n42°  PJM March 24 Response at 39 n.64. \n421  See, e.g., NREMC April 23 Reply Comments at 5-6; Indicated Transmission \nOwners March 24 Response at 16-17; Center April 23 Reply Comments at 27. \n422  See infra P 204. \n423  See Antora April 23 Reply Comments at 11-12 (\"Where a customer could have \ninstead taken curtailable transmission service that allows PJM and/or the EDC to curtail \nits load if that service were offered, the failure to provide a service option that \nincorporates load flexibility will directly lead to costs for the interconnecting customer \nthat do not appropriately reflect its flexibility and resulting ability to avoid using high \nvalue energy or grid capacity. And it will lead to increased costs for other customers \nbecause PJM's transmission and interconnection study processes and operating protocols \nwill apply a lack of headroom in its system based on its assumed need to serve the \n104 of 515"},{"page":106,"startToken":41142,"endToken":41632,"text":"Document Access igPSA. 22q-A.418 _3qpcument:Flit d EFAg:3143A8/2pa3te Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 95 - \nii. \nInterim, Non-Firm Transmission Service \n200. Co-Located Loads are concerned with the speed to interconnect to the PJM \ntransmission system and begin operation. As a result, these types of loads have sought to \nestablish Co-Location Arrangements with existing generating facilities that can begin \nserving new large Co-Located Loads rapidly.424 In response, and to facilitate more rapid \ninterconnection and operation of Co-Located Loads, PJM and other parties discuss the \ndevelopment of a new transitional service that would allow new Co-Located Load to \nwithdraw electricity from the PJM transmission system earlier than may be otherwise \nachievable if those new Co-Located Loads could only be designated as Network Load \nand served once all of the Network Upgrades necessary to provide the requested NITS \nare complete.425  Therefore, we direct PJM to submit, within 60 days of the date of \nissuance of this order, a compliance filing to create a new interim, non-firm transmission \nservice similar, but not identical, to PJM's proposed option 7. This new interim, \nnon-firm transmission service must allow an Eligible Customer that has requested NITS \non behalf of a Co-Located Load to take non-firm transmission service that can be \ninterrupted until the Network Upgrades necessary to provide NITS are complete and the \nCo-Located Load can be designated as Network Load. We reiterate that this interim, \nnon-firm transmission service should be temporary—only available to Eligible \nCustomers that have requested NITS on behalf of Co-Located Loads that cannot yet be \nreliably served with NITS—and available only until the necessary Network Upgrades are \ncompleted and the Co-Located Load is designated as Network Load. Moreover, this new \nservice would be optional for an Eligible Customer seeking NITS on behalf of a \nCo-Located Load and would only be available to the extent PJM determines that it can \nprovide some level of interim service reliably. Eligible Customers taking this interim, \nnon-firm transmission service on behalf of Co-Located Loads would pay the NITS rate \nfor the new service, as well as ancillary services charges and charges for black start \nservice, but they would not be charged for generation capacity because, as interruptible \nentirety of the Network Load at any given moment, despite the fact that the customer is \ncapable of dispatching down pursuant to PJM and/or EDC instructions. This, in turn, will \ntrigger identification of infrastructure upgrades that could have been avoided . . . .\"); \nConstellation April 23 Reply Comments at 20 (\". . . [A] NITS-only approach to serving \nhyperscale data centers and other large new loads will create a need for massive \ntransmission upgrades and impose billions of dollars of costs on existing \ncustomers . \n.\"). \n424  Show Cause Order, 190 FERC 1161,115 at P 85. \n425  See PJM March 24 Response at 18-19; Mainspring April 23 Reply Comments \nat 13; Constellation April 23 Reply Comments at 55-57; Buckeye April 23 Comments \nat 9. \n105 of 515"},{"page":107,"startToken":41632,"endToken":42096,"text":"Document Accessigi@V; qqA_,418-31d9c ument:Fl it d rpaqg: iip/q8/2pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 96 - \nloads, capacity will not be procured on their behalf until such time as the Network \nUpgrades are in place to serve them. Once the required Network Upgrades to serve the \nfull gross demand are in place, the Co-Located Load would be designated as Network \nLoad and the Eligible Customer would pay on behalf of the Co-Located Load all \nNetwork Load charges. This transmission service may not be combined with the Firm \nContract Demand transmission service or Non-Firm Contract Demand transmission \nservice discussed herein. \n201.\nWe find that this new interim, non-firm transmission service will facilitate the \ntimely provision of transmission service to Eligible Customers taking transmission \nservice on behalf of Co-Located Loads, while preserving reliability for other transmission \ncustomers. As discussed above, the record in this proceeding suggests that a key driver \nof Co-Location Arrangements is delays in new large loads obtaining service through the \ntraditional front-of-the-meter load interconnection process.426  This interim, non-firm \ntransmission service would help to address such delays by allowing an Eligible Customer \nthat has requested to take NITS on behalf of a Co-Located Load to, through this new \ntransmission service, receive an interruptible transmission service before the Network \nUpgrades necessary to designate and serve the Co-Located Load as Network Load are \ncomplete. Eligible Customers taking the interim, non-firm transmission service on behalf \nof Co-Located Loads would avoid paying generator capacity costs in return for their \nwillingness to curtail their withdrawals in advance of emergency conditions (i.e., it will \nbe curtailed before existing firm transmission services and the new Firm Contract \nDemand Transmission Service).427  This willingness to curtail would potentially allow \nthem to obtain service more quickly. As part of the compliance filing ordered above, we \nseek briefing on an appropriate point in emergency operations at which to curtail Eligible \nCustomers taking this new interim, non-firm transmission service on behalf of \nCo-Located Loads; We further note that, when curtailed, Eligible Customers taking this \ntransmission service on behalf of Co-Located Loads may be able to continue to take \nenergy from the Interconnection Customer with which they are co-located if PJM's Tariff \notherwise allows. \n202.\nWe note that, unlike in PJM's proposal in option 7, which would allow Eligible \nCustomers taking transmission service on behalf of Co-Located Loads to receive the \ntransitional service until \"any resource adequacy supply/demand imbalances associated \nwith the large load addition could be addressed,\"428  we instead direct PJM to limit the \ntransitional period to the time needed to complete any Network Upgrades identified in the \n426  Indicated Transmission Owners June 3 Answer, Powers Aff. at 16. \n427  See infra P 208. \n428  PJM March 24 Response at 18-19. \n106 of 515"},{"page":108,"startToken":42096,"endToken":42538,"text":"Document AccessigPSA -2q-Aqq1 8 - 3Q9Cument:Fl i l d  j=1ge:1.971.8/2p-je Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 97 - \nstudy process as necessary to provide the requested NITS. PJM's proposal in option 7 to \nallow the transitional period to continue until any resource adequacy challenges are \naddressed is too broad and not sufficiently detailed to direct as a replacement rate. \n203.\nHowever, as discussed below, we conclude that additional record evidence is \nneeded to set the appropriate replacement rate, i.e., the terms and conditions for the new \ninterim, non-firm transmission service. Thus, we establish a paper hearing and direct \nfurther briefing. \niii. \nFirm Contract Demand and Non-Firm Contract \nDemand Transmission Services  \n204.\nAs the record demonstrates, various potential Co-Location Arrangements may use \nthe transmission system to differing extents. Specifically, parties note that some \nCo-Location Arrangements include system protection facilities that prevent energy \nwithdrawals from the transmission system,429  and parties have demonstrated that some \nCo-Located Loads are willing and able to control their withdrawals from the transmission \nsystem.430  System protection facilities are defined as the equipment, including necessary \nprotection signal communications equipment, required to protect (1) Transmission \nProvider's Transmission System from faults or other electrical disturbances occurring at \nthe Generating Facility, and (2) the Generating Facility from faults or other electrical \nsystem disturbances occurring on Transmission Provider's Transmission System or on \nother delivery systems or other generating systems to which Transmission Provider's \nTransmission System is directly connected:431  Instead of system protection facilities, we \n429  See, e.g., id. at 13-15. \n430  See, e.g., SEIA April 23 Reply Comments at 8 (citing Duke University's \nNicholas Institute for Energy, Environment & Sustainability, Rethinking Load Growth: \nAssessing the Potential for Integration of Large Flexible Loads in US Power Systems, \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-\ngrowth.pdf (Duke Study)); id. (\"Co-located loads with the ability to curtail or shift \ndemand in coordination with generator output or grid constraints should be treated \ndifferently than firm grid-dependent load, as these loads would be capable of reducing \ntheir demand on the grid.\"); Constellation April 23 Reply Comments at 56 (\"The Duke \nStudy identifies the significant benefits to the efficient use of the transmission grid and \nexisting capacity when loads can `temporarily reduce (i.e., curtail) its electricity \nconsumption from the grid during [] peak stress periods.') (quoting Duke Study at 5); \nEDFR April 23 Reply Comments at 9. \n431  Federal Energy Regulatory Commission, Pro forma LGIP, § 1 (Definitions) \n(Aug. 20, 2024), https://www.ferc.gov/media/pro-forma-lgip. See Reform of Generator \nInterconnection Procs. & Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 367 \n107 of 515"},{"page":109,"startToken":42538,"endToken":43023,"text":"Document Accessig#SA: 2A-0,_qti_31;12cument:Flil d  j=)A9: 3'VA 812 Pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 98 - \nwill use in this order the term special protection scheme, also known as a remedial action \nscheme. A special protection scheme is a plan designed to detect abnormal system \nconditions and to automatically take appropriate corrective action, to maintain system \nstability, acceptable system voltages, and acceptable facility loading. Corrective actions, \nas applicable here, may address scenarios such as generator runback or load shedding.432 \n205. As such, PJM and other commenters discuss transmission services that are tailored \nto Co-Located Loads that have protection schemes to limit their energy withdrawals from \nthe system, and that recognize the reduced impact on the transmission system of such \nCo-Location Arrangements as compared to traditional Network Load.433  Parties argue \nthat these services will not require PJM to plan the transmission system to serve these \nCo-Located Loads to the same extent as PJM must plan the transmission system to serve \nNetwork Load, possibly reducing the need for new Network Upgrades.434  Parties further \nargue that Co-Located Loads may be able to receive transmission service faster with use \nof a new, limited transmission service product than they would if they selected NITS, to \nthe extent that providing NITS would require Network Upgrades that the limited \ntransmission service would not.435  We note that, in general, special protection schemes \nallow Eligible Customers on behalf of Co-Located Load to effectively limit their \nwithdrawals from the transmission system.436  For these reasons, in these instances where \n(2018), order on reh'g, Order No. 845-A, 166 FERC ¶ 61,137, order on reh'g, Order \nNo. 845-B, 168 FERC ¶ 61,092 (2019) (discussing system protection facilities in the \ncontext of a generating facility not injecting energy onto the transmission system above \nthe requested level of service). \n432  PJM Manual 07: PJM Protection Standards, Rev. 5 (eff. Sept. 25, 2025) § 17.1. \nWe recognize that PJM's manual currently does not include excess energy withdrawals as \nan abnormal system condition. \n433  See, e.g., PJM March 24 Response at 13-15, 18-19; Glatz and Silverman \nApril 23 Reply Comments at 12-13; Constellation April 23 Reply Comments at 65; \nVistra April 23 Reply Comments at 28. \n434  See Enchanted Rock April 23 Reply Comments at 17. \n435  See Constellation April 23 Reply Comments at 55-56; EPSA/P3 April 23 Reply \nComments at 14. \n436  See Constellation April 23 Reply Comments, Herling Aff. ¶ 23 (\"The \nprotection system, discussed above, is fully redundant and, while it cannot be guaranteed \nto never fail, it is unreasonable to treat the failure of both primary and secondary relay \nsystem facilities following the loss of a generator as anything other than a third \ncontingency. In fact, when I was directing transmission planning for PJM, I cannot think \nof an instance in which we treated such a situation otherwise. In practice, protection \n108 of 515"},{"page":110,"startToken":43023,"endToken":43498,"text":"Document AccessigPSP; 2A-Aq_418 _3Qgcument:Flal d rpaN9: j121A8/2p2aJe Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 102 - \nbecause these Eligible Customers will not be able to reduce their load-ratio share to avoid \npaying transmission costs or capacity costs. Rather, these customers will pay only for the \ncontracted demand, aligning the costs for the Firm Contract Demand transmission service \nthat they take with the benefits they receive. \n212.\nShould the Eligible Customer taking transmission service on behalf of a \nCo-Located Load withdraw energy from the PJM transmission system in excess of the \ncontract demand, for example, due to a special protection scheme failure, we direct PJM \nto apply a penalty rate. The Commission has previously found that transmission \ncustomers should be subject to unreserved use penalties in circumstances where a \ntransmission customer uses transmission service in excess of its reserved capacity or if it \nuses transmission service where it does not have a reservation.443  Further, PJM states that \nit has observed that special protection schemes can fail, which may result in the Eligible \nCustomer taking unreserved service from the transmission system on behalf of the \nCo-Located Load!'\" We direct parties to brief the appropriate penalty charge for a Firm \nContract Demand transmission service customer's unreserved use of the PJM \ntransmission system. We also direct parties to brief the appropriate procedures for PJM \nto curtail Eligible Customers taking the new Firm Contract Demand transmission service \non behalf of Co-Located Loads that withdraw energy in excess of the contract demand \nand any other remedial action that PJM should take to address withdrawals in excess of \nthe contract demand. We also note that, as discussed in the briefing questions below, \nPJM will determine the technical and engineering requirements of special protection \nschemes to help address reliability risks associated with unreserved use of the \ntransmission system. \n213.\nWe find that the new Firm Contract Demand transmission service must have a \nminimum term of one year, similar to NITS.445  However, generation capacity is typically \nprocured three years in advance in PJM. As such, we find that it is just and reasonable \nthat the terms and conditions for taking the new Firm Contract Demand transmission \nservice must prevent transmission customers from switching between the Firm Contract \nDemand and Non-Firm Contract Demand transmission services, i.e., must include an \nanti-toggling mechanism. Otherwise, Eligible Customers taking transmission service on \nbehalf of Co-Located Loads may attempt to switch between the two new transmission \nservices based on expected capacity market conditions. PJM's capacity market includes \nanti-toggling measures, including the \"must-offer\" requirement for existing Capacity \nResources and the five-year minimum commitment for loads seeking to procure their \n443  Order No. 890, 118 FERC ¶ 61,119 at P 834. \n444  PJM March 24 Response at 44. \n445  See PJM, Intra-PJM Tariffs, OATT, § III.29.2 Application Procedures (2.0.0). \n112 of 515"},{"page":111,"startToken":43498,"endToken":43971,"text":"Document AccessigPA 2g'2-18-3PPcument:Flit d ifkgw: ilp/48/ AMe Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 99 - \nthe Co-Location Arrangement includes special protection schemes that limit its energy \nwithdrawals, we find that it is a just and reasonable replacement rate to allow an Eligible \nCustomer taking transmission service on behalf of such load to take and be charged for \nnew types of transmission service that are alternatives, and not equivalent, to NITS. \n206.\nWe therefore direct PJM to develop two new transmission services that must be \navailable to Eligible Customers taking transmission service on behalf of Co-Located \nLoads: (1) Firm Contract Demand transmission service, and (2) Non-Firm Contract \nDemand transmission service. These new transmission services will serve as permanent \nalternatives to existing transmission services, unlike the new interim, non-firm \ntransmission service described above in Part IV.B.4.b.ii, and the new transmission \nservices would not require the Co-Located Load to become Network Load. For the \nEligible Customer taking transmission service on behalf of a Co-Located Load to be \neligible for these new transmission services, the Co-Located Load must be able and \nwilling to prevent or limit its energy withdrawals and must be separately metered from \nthe associated generator. Eligible Customers taking transmission service on behalf of \nCo-Located Loads would also be able to take a combination of Firm Contract Demand \ntransmission service and Non-Firm Contract Demand transmission service. Because firm \ntransmission service contemplates a reservation and regular withdrawal of energy, \nEligible Customers taking transmission service on behalf of Co-Located Loads that will \nnot withdraw energy from the transmission system must take Non-Firm Contract Demand \ntransmission service at 0 MW. \n207.\nThe record assembled to date does not address the appropriate rates, terms, and \nconditions for these new Firm Contract Demand and Non-Firm Contract Demand \ntransmission services. Thus, we direct further briefing to enable the Commission to set \nthe appropriate replacement rate for these services, as discussed below. Among other \ntopics with respect to this pair of new transmission services available to Eligible \nCustomers taking transmission service on behalf of Co-Located Loads, the Commission \ndirects further briefing on whether the rate paid by an Eligible Customer on behalf of a \nCo-Located Load taking only a de minimis amount of the new Firm or Non-Firm \nschemes are regularly employed on the PJM transmission system, and the successful \noperation of such protective systems is a common observance within PJM.\"). Proper \nspecial protection scheme design is also subject to NERC standards to ensure they do not \nintroduce unintentional or unacceptable reliability risks to the system. Remedial Action \nSchemes Reliability Standard, Order No. 837, 160 FERC ¶ 61,071 (2017) (approving \nReliability Standard PRC-012-2). \nAlso, as discussed below, we clarify that PJM's necessary study process assesses \nany special protection scheme that is a part of a Co-Location Arrangement. See infra \nP 227. \n109 of 515"},{"page":112,"startToken":43971,"endToken":44428,"text":"Document Acc„sigt SP; Z-q\"2-\n18-31;;IgCLIMent:FlAd rfaqg:11211C1812pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 100 - \nContract Demand transmission services should reflect not only (i) charges for regulation \nand black start service and (ii) the transmission service charges for that de minimis \namount of service, but also an additional charge reflecting that the Co-Located \nArrangement is physically connected and synchronized to the PJM transmission system \nand, if so, how that additional charge, including a de minimis threshold, should be \ndetermined. \n(a) \nFirm Contract Demand Transmission \nService \n208.\nUnder the new Firm Contract Demand transmission service, Eligible Customers \nwill have the right to request transmission service on behalf of a Co-Located Load up to a \nspecified MW quantity, i.e., the contract demand. The Firm Contract Demand \ntransmission service will have the same reservation and curtailment priority as existing \nfirm transmission services, at the level of the contract demand. However, unlike NITS \ncustomers, the Eligible Customer taking Firm Contract Demand transmission service on \nbehalf of the Co-Located Load is not permitted to withdraw energy from the PJM \ntransmission system beyond the contract demand level.437 \n209.\nEligible Customers taking the new Firm Contract Demand transmission service on \nbehalf of Co-Located Loads will be charged for transmission, ancillary services, and \ncapacity based on the contract demand, with the exception of regulation and black start \nservices.438  As explained above, we agree with parties who argue that all Co-Located \nLoads rely on regulation and black start services to be served regardless of whether they \nare drawing energy from the transmission system,439  and we therefore find that Eligible \n437  We note an Eligible Customer may combine Firm Contract Demand \ntransmission service with Non-Firm Contract Demand transmission service to withdraw, \non an as-available basis, more energy than its firm entitlement. \n438  See, e.g., Constellation April 23 Reply Comments at 66 (\"Ancillary services \nshould be charged on a gross or net load basis for firm and interruptible configurations, as \nrequired to avoid discrimination. For generator-contingent configurations, some charge \nfor regulation or black start service may be appropriate. Energy charges should be \nassessed based on a net injection or withdrawal of the co-located load generator and load \nto the transmission system.\"). \n439  See id. at 34 (\"[I]t may be appropriate to include some ancillary service \ncharges, such as regulation and black start . . . .\"); Vistra April 23 Reply Comments at 27 \n(\"For example, variances in the co-located load, which are seen by the grid as changes in \nthe co-located generator's output, could be viewed as related to the need for regulation \nservice. Co-location configurations with high load variation therefore can be considered \nto use regulation service.\"); ACEG April 23 Reply Comments at 2 (\"Proposed co-located \n110 of 515"},{"page":113,"startToken":44428,"endToken":44902,"text":"Document Accessigi?A 2Q12111.8-3Q9cument:Flitd IEN9:1:121/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 101 - \nCustomers that take the Firm Contract Demand transmission service on behalf of \nCo-Located Loads must be charged for regulation and black start services based on a \ngross demand basis, rather than the contract demand. \n210.\nPJM will only have an obligation to plan for the Network Upgrades necessary to \nserve Eligible Customers taking this new Firm Contract Demand transmission service on \nbehalf of Co-Located Loads at their contract demand. Because PJM will procure \ngeneration capacity on behalf of the Co-Located Load served by Firm Contract Demand \ntransmission service based on their contract demand, we find it is appropriate to charge \nthe relevant Eligible Customer for generation capacity based on the full amount of the \nFirm Contract Demand transmission service.440  We direct parties to brief the appropriate \nrate, terms, and conditions for this new Firm Contract Demand transmission service, \nincluding whether it would be just and reasonable to apply the current zonal firm PTPS \nrates to this new transmission service.\"' \n211.\nWe note that the new Firm Contract Demand transmission service does not raise \nsimilar cost shifting concerns as the split system contemplated in Order No. 888-A.442 \nFirm Contract Demand transmission service customers will be charged based on their \ncontract demand irrespective of usage and therefore will not be able to reduce their \nload-ratio cost responsibility. Further, PJM will only plan the transmission system and \nprocure generation capacity for the contract demand—not for load growth, like it does for \nNITS customers—and PJM will have no obligation to serve the Eligible Customer \nbeyond the contract demand. Therefore, we find that allowing Eligible Customers taking \ntransmission service on behalf of Co-Located Loads to take the new Firm Contract \nDemand transmission service will not cause a cost shift to other transmission customers \nload arrangements do not always function as truly islanded micro grids, and they may \nstill rely on services such as frequency regulation, voltage support, and black start \ncapability.\"). \n440 As noted in Part IV.B.2.a supra, states have exclusive authority over the \nallocation of Commission-jurisdictional costs to retail customers, including retail \ncustomers that are Co-Located Load. Therefore, states have authority over how the costs \nfor Firm Contract Demand transmission service and other services assigned to an Eligible \nCustomer are allocated among individual retail customers. \n441  See PJM, Intra-PJM Tariffs, OATT, sched. 7 (15.0.1). \n442  See Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,259 (\"The concept \nof allowing a `split system' or splitting a discrete load is antithetical to the concept of \nnetwork service. . . . Furthermore, such a split system creates the potential for a customer \nto \"game the system\" thereby evading some or all of its load-ratio cost responsibility for \nnetwork services.\"). \n111 of 515"},{"page":114,"startToken":44902,"endToken":45339,"text":"Document AccessigPSA 2A-2-418-31d9cument:FlA d EFAgp:i121/48/2pAle Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 103 - \nown capacity through the Fixed Resource Requirement alternative. Both measures exist \nto prevent loads or generators from introducing price volatility or exercising market \npower by entering and exiting the market from one year to the next based on projected \nmarket conditions. We direct parties to brief the appropriate mechanism for such a \nfeature, including the appropriate minimum service period and minimum notice period \nfor discontinuing service for the new Firm Contract Demand and Non-Firm Contract \nDemand transmission services. \n(b) \nNon-Firm Contract Demand Transmission \nService \n214.\nAs discussed above, we establish a new Non-Firm Contract Demand transmission \nservice to be offered to Eligible Customers taking service on behalf of Co-Located Loads. \nWe recognize that not all Co-Located Loads will necessarily plan to withdraw energy \nfrom the transmission system on a regular basis. Eligible Customers taking service on \nbehalf of such loads may, however, still seek to withdraw energy from the transmission \nsystem from time to time when transmission capacity is available and not needed by firm \ncustomers. For example, an Eligible Customer could seek a transmission reservation for \na Co-Located Load in advance for the duration of an expected outage of the associated \ngenerator. The new Non-Firm Contract Demand service will provide an option for \nEligible Customers seeking to use the transmission system on behalf of a Co-Located \nLoad in this more limited manner, while still charging customers for regulation and black \nstart services, for the reasons discussed above. \n215.\nWe find that the new Non-Firm Contract Demand transmission service must be \navailable during normal operations and curtailed during emergency operations (i.e., it will \nbe curtailed before existing firm transmission services and the new Firm Contract \nDemand Transmission Service). Under this service, Eligible Customers may reserve \ntransmission service on behalf of a Co-Located Load as needed during normal, \nnon-emergency system operating conditions. Reservations under this service would be \navailable only when there is available transmission capacity, similar to existing non-firm \ntransmission service options in the Tariff. Reservations for this service shall be available \nfor terms ranging from one hour to one month, consistent with the terms available for \nNon-Firm PTPS in the PJM Tariff's\" As noted above, Eligible Customers may use \nNon-Firm Contract Demand transmission service to make use of the transmission system \nabove their Firm Contract Demand transmission service level, if transmission capacity is \navailable. \n446 See PJM,\n \nIntra-PJM Tariffs, OATT, § 14.1 (1.0.0) (\"Non-Firm Point-To-Point \nTransmission Service will be available for periods ranging from one (1) hour to one (1) \nmonth\"). \n113 of 515"},{"page":115,"startToken":45339,"endToken":45806,"text":"Document AccessigP.Sg 2A-A41.8 _3gpcument:FlAd rjpa,p: 3121/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 104 - \n216.\nEligible Customers taking the Non-Firm Contract Demand transmission service on \nbehalf of Co-Located Loads will be charged for transmission and ancillary services on an \nas-reserved contract demand basis, based on the reserved contract demand amount of \ntransmission service (except as noted below). As with the new Firm Contract Demand \ntransmission service, we find that Eligible Customers that take the Non-Firm Contract \nDemand transmission service on behalf of Co-Located Loads use and therefore should be \ncharged for regulation and black start services based on a gross demand basis, rather than \nthe reserved amount of transmission service. As discussed below, we direct parties to \nbrief the appropriate rate, terms, and conditions for this new Non-Firm Contract Demand \ntransmission service, including whether it would be just and reasonable to apply the \ncurrent zonal non-firm PTPS rates to this new service.447 \n217.\nIn addition, similar to the Firm Contract Demand transmission service, should the \nEligible Customer taking the Non-Firm Contract Demand transmission service on behalf \nof the Co-Located Load make unreserved use of the transmission system by withdrawing \nenergy in excess of its transmission service reservation,448  PJM must apply a penalty rate \nin such circumstances. We direct parties to brief the appropriate charge for such a \npenalty, including whether it should be the same as the unreserved use penalty charge \napplicable to the new Firm Contract Demand transmission service. We also direct parties \nto brief the appropriate triggers and procedures for PJM to curtail an Eligible Customer \ntaking the new Non-Firm Contract Demand transmission service on behalf of a \nCo-Located Load when it makes unreserved use of the transmission system by \nwithdrawing energy in excess of its transmission service reservation. \n218.\nThe new Non-Firm Contract Demand transmission service will not include a \ncharge for generation capacity.449  Because it is non-firm transmission service, PJM will \nnot have an obligation to serve Eligible Customers taking this new Non-Firm Contract \nDemand transmission service on behalf of Co-Located Loads; thus, unlike Network \nLoad, Co-Located Loads on whose behalf Eligible Customers are taking Non-Firm \n447  See PJM, Intra-PJM Tariffs, OATT, sched. 8 (14.0.1). \n448  As noted above, Non-Firm Contract Demand transmission service will be \ncurtailed during emergency operations and we request briefing on the appropriate \nprocedures to govern the circumstances under which PJM curtails an Eligible Customer \ntaking Non-Firm Contract Demand transmission service on behalf of a Co-Located Load \nduring emergency procedures. \n449 Regardless, however, we clarify that this option is distinct from Vistra's \nproposal to allow a secondary generator that provides occasional, interruptible backup \nservice to a Co-Located Load to also serve as a Capacity Resource. Vistra April 23 \nReply Comments at 8, 30. \n114 of 515"},{"page":116,"startToken":45806,"endToken":46213,"text":"Document AccessigPS#: 22qA.418 _ Agcu me nt:Fl il d rp@g: j121/4 8/ 2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 105 - \nContract Demand transmission service would not be considered for resource adequacy \nplanning purposes. PJM will also have no obligation to include the Co-Located Loads on \nwhose behalf Eligible Customers take such service in its transmission planning. \niv. \nPaper Hearing on Rates, Terms, and Conditions of \nNew Transmission Services  \n219. As discussed above, additional record evidence is needed to set the appropriate \nreplacement rates, terms, and conditions for the new interim, non-firm transmission \nservice, Firm Contract Demand transmission service, and Non-Firm Contract Demand \ntransmission service. Parties should address the following questions with specificity. \n(1)\nWhat are the appropriate rates, terms, and conditions for the new Firm \nContract Demand transmission service, including whether it would be just and \nreasonable to apply the current zonal firm PTPS charges to this new service \nand whether it would be just and reasonable and consistent with cost causation \nto include charges for any of PJM's administrative services? \n(2)\nWhat are the appropriate rates, terms, and conditions for the new Non-Firm \nContract Demand transmission service, including whether it would be just and \nreasonable to apply the current zonal non-firm PTPS charges to this new \ntransmission service and whether it would be just and reasonable and \nconsistent with cost causation to include charges for any of PJM's \nadministrative services? \n(3)\nAs noted above, a Co-Location Arrangement is synchronized to the \ntransmission system.4\" Should the rate paid by an Eligible Customer on behalf \nof a Co-Located Load taking only the new Non-Firm Contract Demand \ntransmission service that elects to not reserve any amount of that service for a \nperiod of time (e.g., one month) reflect not only charges for regulation and \nblack start services, but also an additional charge given that regulation and \nblack start services could not be provided without the transmission system? If \nso, how should that additional charge be determined? \n(4)\nAs noted above, a Co-Location Arrangement is synchronized to the \ntransmission system.45' Should the rate paid by an Eligible Customer on behalf \nof a Co-Located Load taking only a de minimis amount of the new Firm or \nNon-Firm Contract Demand transmission services reflect not only (i) charges \nfor regulation and black start service and (ii) the transmission service charges \n45\" See also PJM March 24 Response at 42-43. \n451  Id. \n115 of 515"},{"page":117,"startToken":46213,"endToken":46568,"text":"Document AccessigPA qq\"Aq.41.8- ARcument:FlAd EFAgp:1121A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 106 - \nfor that de minimis amount of service, but also an additional charge reflecting \nthat the Co-Location Arrangement is physically connected and synchronized to \nthe PJM transmission system? If so, how should that additional charge be \ndetermined? \n(5)\nWhat is the appropriate penalty charge or other remedial action that PJM \nshould take to address any unreserved use of the PJM transmission system for \nan Eligible Customer taking Firm Contract Demand transmission service on \nbehalf of a Co-Located Load? \n(6)\nWhat is the appropriate penalty charge or other remedial action that PJM \nshould take to address any unreserved use of the PJM transmission system for \nan Eligible Customer taking Non-Firm Contract Demand transmission service \non behalf of a Co-Located Load? \n(7)\nWhat are the appropriate mechanisms for an anti-toggling feature for the \nFirm Contract Demand transmission service, including the appropriate \nminimum service period and minimum notice period for discontinuing or \nmodifying the level of service? \n(8)\nWhat interconnection requirements and operational practices are necessary \nfor special protection schemes to maintain system reliability (e.g. the need for \nfull redundancy of such schemes) in the event that a Co-Located Load itself or \nits associated generator trips offline? \n(9)\nWhat communications, alarm, SCADA452  or other requirements are \nnecessary for PJM to monitor Co-Located Load transmission system demand \nstatus; ensure that relay settings are consistent with special protection scheme \ndesign; and inform system operator action, in order to limit withdrawals from \nEligible Customers on behalf of Co-Located Load that exceed the amount of \nFirm or Non-Firm Contract Demand transmission services? \n(10)\nWhat other eligibility requirements, e.g., interconnection requirements or \noperational practices, are necessary for an Eligible Customer to take Firm \nContract Demand or Non-Firm Contract Demand transmission service on \nbehalf of Co-Located Load? \n452 Supervisory Control and Data Acquisition (SCADA) is a system of remote \ncontrol and telemetry used to monitor and control the transmission system. See NERC \nGlossary of Terms at 42, https://www.nerc.com/globalassets/standards/reliability-\nstandards/glossary_of terms.pdf. \n116 of 515"},{"page":118,"startToken":46568,"endToken":47010,"text":"Document AccessigPW 2AA1.418-4eiKument:Flita raN9:::121A8/2pge Filed: 10/16/2023 \nDocket No. EL25-49-000, et al. \n- 107 - \n(11) \nWhat are the appropriate procedures to govern the circumstances under \nwhich PJM curtails an Eligible Customer taking the interim, non-firm \ntransmission service, Firm Contract Demand transmission service, or \nNon-Firm Contract Demand transmission service on behalf of a Co-Located \nLoad during emergency procedures? In particular, can PJM shed all or a \nportion of a Co-Located Load on whose behalf an Eligible Customer takes \nNon-Firm Contract Demand transmission service while continuing to serve all \nor a portion of a Co-Located Load on whose behalf an Eligible Customer takes \nFirm Contract Demand transmission service? \n220.\nPJM must submit its initial brief in Docket No. EL25-49-000 on or before \nFebruary 16, 2026. The deadline to file responses to PJM's initial brief will be March 18, \n2026, and the deadline to file replies to those responses will be April 17, 2026. \nv. \nBehind the Meter Generation (BTMG) \n221.\nWe next turn to the Tariff's BTMG rules.453  Based on our finding above that \nPJM's BTMG rules are no longer just and reasonable, we direct PJM to revise the Tariff \nto revise the retail BTMG rules. However, we acknowledge that not all loads using \nBTMG are large loads that create the reliability and resource adequacy risks described \nabove. We therefore direct PJM, within 60 days of the date of issuance of this order, to \npropose a new MW threshold for the amount of load at a particular electrical location that \nNetwork Customers may net by using BTMG. Such a threshold should reduce the \nreliability and resource adequacy risks discussed above that large loads may pose to PJM, \nwhile also allowing for Network Customers to reduce their transmission charges in a \ntransparent, not unduly discriminatory fashion. We acknowledge that such a materiality \nthreshold will not eliminate the risk identified in this order, but we find that it will ensure \nthat the risk is limited. Parties will have an opportunity to comment on PJM's proposed \nthreshold before we establish this replacement rate. Although we make no finding in this \norder on a threshold that would be just and reasonable, we note as points of reference that \nPJM requires any generator larger than 10 MW to be individually metered454  and that the \nCommission's definition of a small generator is 20 MW.455 \n453  We clarify that, consistent with the definition in 159,provided above, supra \nP 164, BTMG is not Co-Located Load. \n454  PJM Manual 14G: Generation Interconnection Requests, Rev. 8 (eff. July 26, \n2023), § 1.6.2. \n455  Order No. 2006, 111 FERC ¶ 61,220 at P 1. \n117 of 515"},{"page":119,"startToken":47010,"endToken":47489,"text":"Document Accessigig'SA 4q-2-%q418-3Q9Curnent:Flita rPaqg9:11/§.8/2p2ale Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 108 - \n222.\nWe clarify we do not direct PJM to change its rules for non-retail BTMG.456 \nBecause non-retail BTMG is already capped, the record does not demonstrate a need for \nfurther changes at this time.457  We also recognize concerns raised in the record about the \npotential impacts of the Commission changing PJM's BTMG rules for existing BTMG \ncustomers.458  We thus make several findings and directives about the replacement rate \nbelow that are designed to minimize the impact of this transition on existing BTMG \ncustomers. \n223.\nFirst, we find that it is appropriate to establish a transition period for Network \nCustomers currently using PJM's existing BTMG rules. We thus direct PJM, within \n60 days of the date of issuance of this order, to include in its compliance filing Tariff \nrevisions to allow Network Customers already using the BTMG rules to continue to do so \nfor a transition period of three years, which aligns with the timeline to procure \nreplacement capacity in PJM,459  from the date of issuance of this order. We find that this \napproach reasonably balances concerns about expediently addressing unjust and \nunreasonable rates with concerns from parties that have relied on the existing Tariff. \n224.\nSecond, while the record indicates that parties desire the continued use of the \nexisting Tariff BTMG rules,46°  we acknowledge the possibility that entities may also \nhave contracted for the specific purpose of effectuating a BTMG arrangement. To the \nextent an entity is a party to an existing contract for such a purpose, we find that it is \n456  PJM defines Non-Retail BTMG as BTMG that is \"used by municipal electric \nsystems, electric cooperatives, or electric distribution companies to serve load.\" PJM, \nIntra-PJM Tariffs, OATT, § I.1 Definitions — L-M-N (51.0.1) (defining Non-Retail \nBTMG). \n457  Indicated. Transmission Owners March 24 Response at 28 n.6 (\". . . [T]he total \namount of Non-Retail BTMG in the PJM Region is capped in any specific year and sets a \nmaximum ceiling of 3,000 MW . . . .\"); PJM, Intra-PJM Tariffs, OATT, § III.34.3 \nNetting of Non-Retail Behind the Meter Generation (1.0.0). \n458  See, e.g., AMP April 23 Reply Comments at 10-11; PSE&G May 23 Answer \nat 7. \n459  See PJM, Intra-PJM Tariffs, OATT, attach. DD.5, § 5.4(a) Reliability Pricing \nModel Auctions (10.0.0) (\"The Base Residual Auction shall be conducted in the month of \nMay that is three years prior to the start of such Delivery Year.\"). \n460 See, e.g., PSE&G May 23 Answer at 2 (\"Second, rules adopted by the \nCommission should not adversely impact existing customers in PJM who have BTMG \nand who have long relied upon the netting provisions under the PJM Tariff for purposes \nof paying wholesale grid services . \n.\"). \n118 of 515"},{"page":120,"startToken":47489,"endToken":47929,"text":"Document AccessigRsp; -2q-Aei41.8-3PKumentAil d rfa'qv: j121;218/2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 109 - \nappropriate to grandfather such entity so that it may continue using BTMG for the current \nterm remaining under the existing contract.' We thus direct PJM, within 60 days of the \ndate of issuance of this order, to include in its compliance filing Tariff revisions to \ngrandfather entities with existing contracts for the specific purpose of effectuating a \nBTMG arrangement for the current term remaining under the existing contract. \nc. \nNecessary Study Process462  for Existing Interconnection \nCustomers  \n225.\nBased on our finding above that the PJM Tariff is unjust and unreasonable because \nit lacks sufficient clarity and consistency with respect to the rules for Co-Location \nArrangements, we direct PJM to revise its Tariff to provide sufficient clarity regarding \nthe responsibilities of existing Interconnection Customers seeking to serve Co-Located \nLoad using their generating facilities. \n226.\nFirst, we direct PJM to submit, within 60 days of the date of issuance of this order, \na compliance filing to revise the Tariff to clarify that an existing Interconnection \nCustomer seeking to modify its ISA or GIA to allow its generating facility to serve \nCo-Located Load, including to reflect any reduction in its CIRs, must follow the \nnecessary study process to effectuate such Co-Location Arrangement. Vistra argues that \nthe Commission should require transmission owners to cooperate in the necessary study \nprocess,463  and Indicated Transmission Owners respond that the Commission cannot \nrequire transmission owners to participate in a study process as a prerequisite to \ninterconnecting load.464  Vistra's request is unnecessary. As part of the replacement rate \nin this order, we establish a just and reasonable process to accommodate Co-Location \nArrangements, including by requiring the designation of an Eligible Customer to take \ntransmission service on behalf of a Co-Located Load, and thereby reduce concerns raised \nin the Show Cause Order about how transmission owners approach Interconnection \n461 Cf. ISO New England Inc., 121 FERC ¶ 61,097 (2007) (accepting subject to \ncondition proposal including an option for certain customers with existing agreements for \ngrandfathered treatment); ISO New England Inc., 124 FERC ¶ 61,297 (2008) (approving \nsettlement agreement to implement proposal including grandfathering option). \n462  Necessary studies \"are essentially generator interconnection modification \nstudies.\" PJM March 24 Response at 7. This process is used for changes \"that typically \nhave relatively small MW impacts on [the generator's] ability to deliver less power to the \ngrid than the configuration reflected in an existing service agreement.\" PJM March 24 \nResponse at 47. \n463  Vistra April 23 Reply Comments at 23. \n464  Indicated Transmission Owners June 3 Answer at 23. \n119 of 515"},{"page":121,"startToken":47929,"endToken":48360,"text":"Document AccessigSP:: \n221$_sQpcumentFlild rEqp: ilA.8/2pge Filed: 10/16/2026 \nDocket No:EL25-49-000, et al. \n- 110 - \nCustomers' requests to use their generating facilities to serve Co-Located Load.465  We \nalso clarify that the above-directed requirement is on the Interconnection Customer with \nthe interconnected generating facility that is seeking to modify its ISA or GIA to use that \ngenerating facility to serve Co-Located Load. \n227. \nSecond, we direct PJM to submit, within 60 days of the date of issuance of this \norder, a compliance filing to add to the Tariff a description of the scope of the analysis \nthat it will perform as part of the necessary study process when an Interconnection \nCustomer seeks to use its existing generating facility to serve Co-Located Load, \nconsistent with PJM's discussion of how it conducts necessary studies associated with \nInterconnection Customers seeking to amend their ISAs or GIAs to use existing \ngenerating facilities to serve Co-Located Load, including to reflect any reduction in \nCIRs.466  This should provide additional clarity and transparency regarding the steps that \nPJM and Interconnection Customers are taking to maintain transmission system \nreliability before an existing generating facility can serve Co-Located Load. In response \nto Antora's concerns,467  we require PJM to describe the information that the \nInterconnection Customer must provide about the Co-Located Load for purposes of the \nnecessary study. In response to RMI,468  we clarify that PJM's necessary study process, \nas reflected in the record, assesses any special protection scheme that is a part of a \nCo-Location Arrangement.469  We disagree with parties such as PIOs who claim that the \nnecessary study process is inappropriate for generation interconnection modification to \nserve Co-Located Load. PIOs, for example, claim this process is \"a poor fit,\"47°  but they \ndo not critique PJM's detailed explanation in its Show Cause Response of the scope of its \nstudy. We also believe that the Tariff revisions required as part of this compliance filing \naddress some of the transparency concerns that parties have raised about the use of the \n465  Show Cause Order, 190 FERC ¶ 61,115 at P 75 (\"As such, the record of \nproceedings before the Commission appear to suggest that Transmission Owners are \ntaking different approaches to performing the steps necessary to accommodate a \nco-location arrangement and in the transmission service that they are requiring entities to \ntake.\"). \n466  See PJM March 24 Response at 49, 51-53. \n467  Antora April 23 Reply Comments at 8. \n468 RMI April 23 Reply Comments at 4-5. \n469  PJM March 24 Response at 49. \n470  PIOs April 23 Response at 9. \n120 of 515"},{"page":122,"startToken":48360,"endToken":48842,"text":"Document Acc„sigiV; \n2k2.., \n1 8 -ASTUrnent:Filld DFAV: j122/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 111 - \nnecessary study process, including questions about the scope of the analysis471  and how \nthe necessary study process aligns with other studies.472  To the extent that PJM seeks to \nenhance the necessary study process, including as it gains experience evaluating requests \nfrom Interconnection Customers to modify their interconnection to serve Co-Located \nLoad, PJM may submit such enhancements in an FPA section 205 filing. \n228.\nThird, we direct PJM to submit, within 60 days of the date of issuance of this \norder, a compliance filing to revise the Tariff to indicate that the Interconnection \nCustomer will be responsible for the costs of any modifications or Network Upgrades \nthat are needed as a result of PJM's study of the change to the ISA or GIA to allow the \nexisting generating facility to serve Co-Located Load, including to reflect any reduction \nin CIRs, inclusive of all necessary Network Upgrades. This will clarify that costs \nassociated with such Co-Location Arrangements will not be unfairly shifted to other \ntransmission customers. PJM states that it requires Interconnection Customers to \ncomplete such upgrades before using their generating facilities to serve Co-Located Load \nin practice, but this requirement does not appear to be in the Tariff.473  Therefore, as part \nof this compliance directive, we direct PJM to revise its Tariff to clarify that an existing \ngenerator may not commence service to a Co-Located Load until all required Network \nUpgrades, special protection schemes, and metering are in service. \n229.\nBy directing PJM to revise its Tariff as discussed above, the Tariff will have \nsufficient clarity and consistency to facilitate Co-Location Arrangements in a just and \nreasonable and not unduly discriminatory or preferential manner. We note that we are \ndirecting a longer compliance timeline for PJM to submit these Tariff revisions related to \nInterconnection Customers seeking to serve Co-Located Load using existing generating \nfacilities, compared to the compliance timeline described below related to new generating \nfacilities, in order to expeditiously provide Interconnection Customers clarity on the steps \nthat will be needed to bring new generation online to serve Co-Located Loads. \n230.\nIn accordance with the existing rules for removing Capacity Resource status,474  we \nalso clarify that an existing generating facility may not begin serving Co-Located Load \n471  OPSI April 23 Reply Comments at 3. \n472  Glatz/Silverman April 23 Reply Comments at 7. \n473  PJM March 24 Response at 50 (\"Service to the co-located load pursuant to the \nco-located load configuration may not commence until the necessary PJM \ninterconnection service agreement(s) has been fully executed by the parties, filed with \nand accepted by the Commission, and all required system reinforcements, system \nprotection facilities, and metering are in place.\") (emphasis added). \n474  See PJM, Intra-PJM Tariffs, OATT, attach. DD.6, § 6.6 Offer Requirement for \n121 of 515"},{"page":123,"startToken":48842,"endToken":49311,"text":"Document Accessig:P,,P; qq-A.18-3P9cument:Flild rpaN9: 31248/2p2ale Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 112 - \nthat is not Network Load until it has delisted its CIRs for the portion of the generating \nfacility to be designated to serve any Co-Located Load that is not receiving NITS. In \norder for an existing generator to de-list its CIRs to serve Co-Located Load, the \nInterconnection Customer must revise its ISA or GIA and bear the cost of all required \nsystem upgrades, as noted above. \nd. \nNew Generating Facilities Serving Co-Located Load \n231.\nNext, we discuss several clarifications that we require PJM to make in its Tariff \nwith respect to Interconnection Customers seeking to use new generating facilities to \nserve Co-Located Load. Such revisions are necessary to clarify the steps such \nInterconnection Customers must take to effectuate Co-Location Arrangements in a \nmanner that is just and reasonable and not unduly discriminatory or preferential. \n232.\nFirst, with respect to Interconnection Customers seeking to use new generating \nfacilities to serve Co-Located Load, we direct PJM to submit, within 30 days of the date \nof issuance of this order, a compliance filing to revise section 404.A.2.a.v of its Tariff to \nclarify that PJM shall consider requests for interconnection service below the full \ngenerating capability of the generating facility, so that an Interconnection Customer may \nrequest interconnection service at a level below its maximum facility output to serve \nCo-Located Load. We direct PJM to revise any other Tariff provisions consistent with \nthis directive.475  Consistent with PJM's existing Tariff process, an Interconnection \nCustomer seeking to use its generating facility to serve Co-Located Load will be studied \nat the level of interconnection service requested for the purposes of determining \nInterconnection Facilities, Network Upgrades, and associated costs, but may be subject to \nother studies at the full generating capability of the generating facility to ensure the safety \nand reliability of the transmission system, with the study costs borne by the \nInterconnection Customer.476  This revision will clarify that an Interconnection Customer \nseeking to use a new generating facility to serve a Co-Located Load may request only the \nminimum level of interconnection service it deems necessary to effectuate its \nCo-Location Arrangement. \n233.\nSecond, we direct PJM to submit, within 30 days of the date of issuance of this \norder, a compliance filing to revise its Tariff to clarify that Interconnection Customers \nseeking to use new generating facilities to serve Co-Located Load may use existing \nprocedures to accelerate a new service request if they satisfy the criteria of PJM's Tariff, \nCapacity Resources (3.0.0); PJM March 24 Response at 58. \n475  See Order No. 845, 163 FERC ¶ 61,043 at P 367. \n476  PJM, Intra-PJM Tariffs, OATT, § VIII.C.404.A.2.a.v Introduction (1.0.0). \n122 of 515"},{"page":124,"startToken":49311,"endToken":49785,"text":"Document Access1cP.SA: 2A-A41.8-3Pficument:Flil d rjjaN9: j1248/2p_aje Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 113 - \ni.e., the request has no cost allocation for Network Upgrades and does not require further \nstudies.' \n234.\nThird, we direct PJM to submit, within 30 days of the issuance of this order, a \ncompliance filing to revise the Tariff to clarify that an Interconnection Customer seeking \nto use a new generating facility to serve Co-Located Load may request provisional \ninterconnection service. As the Commission explained in Order No. 845, Interconnection \nCustomers may seek provisional interconnection service when available studies or \nadditional studies as necessary indicate that there is a level of interconnection service that \ncan occur without any additional Interconnection Facilities and/or Network Upgrades, \nand the Interconnection Customer wishes to make use of that level of interconnection \nservice while the facilities required for its full interconnection request are completed.478 \nConsistent with PJM's existing Tariff process, whether PJM grants a request for \nprovisional interconnection service is at PJM's discretion based upon its evaluation and \nthe results of available studies.479  This revision will clarify that an Interconnection \nCustomer that requests provisional interconnection service for a new generating facility \nserving Co-Located Load can enter commercial operation and begin serving the \nCo-Located Load on an expedited basis, provided such provisional interconnection \nservice is available. We also note that an Interconnection Customer may seek provisional \nservice in combination with a request to interconnect at a level below nameplate capacity. \n235.\nFourth, we direct PJM to submit, within 30 days of the date of issuance of this \norder, a compliance filing to revise section 414 of its Tariff to clarify that an \nInterconnection Customer seeking to use a new generating facility to serve Co-Located \nLoad at an existing point of interconnection may request Surplus Interconnection Service, \nif the existing Interconnection Customer at that point of interconnection has made \nSurplus Interconnection Service available. Consistent with PJM's Tariff, Surplus \nInterconnection Service is granted if PJM concludes in its Surplus Interconnection Study \nthat no new Network Upgrades are required to accommodate the new generating \nfacility's output at the designated point of interconnection.480  This revision will clarify \n477  PJM, Intra-PJM Tariffs, 406, OATT Part VIII.C 406 Decision Point I (1.1.0), \n§ 406.A.2 (\"Only New Service Requests that have no cost allocation for Network \nUpgrades and do not require further studies are eligible for acceleration.\"); PJM, \nIntra-PJM Tariffs, 408, OATT Part VIII.C 408 Decision Point II (2.1.0), § 408.A.2.d \n(stating same). \n478  Order No. 845, 163 FERC ¶ 61,043 at P 441. \n479  PJM, Intra-PJM Tariffs, ATTACHMENT O.A2.1.4A, OATT ATTACHMENT \nO.A2.1.4A Other Interconnection Options (2.1.0), § 1.4A.2. \n480 \nIntra-PJM Tariffs, 414, OATT Part VIII.E 414 Surplus Interconnection \n123 of 515"},{"page":125,"startToken":49785,"endToken":50205,"text":"Document Accessigitt; 4-qr2-18-3PPcument:Flitd rFa'qg9:i12_A8/2p-24e Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 114 - \nthat an Interconnection Customer seeking to use a new generating facility to serve \nCo-Located Load has the same opportunity to use Surplus Interconnection Service that is \navailable to other new Interconnection Customers. \n236.\nLastly, we note that PJM requested guidance on its proposed options, including \noption 6.481  Noting that we direct PJM to clarify its Tariff with respect to Interconnection \nCustomers seeking to use a new generating facility to serve Co-Located Load, PJM and \nseveral commenters state that additional Tariff constructs that accelerate interconnection \nstudies for new generation associated with new Co-Located Loads (PJM proposed \noption 6) may be just and reasonable.482  We believe that such constructs may help \naddress concerns raised in this proceeding that increasing amounts of new Co-Located \nLoad seeking to be served by an Eligible Customer faster than equivalent generation can \ncome online may create resource adequacy problems.483  As PJM notes,484  additional load \non the system requires the addition of generators to serve that load reliably, and a process \nwith accelerated interconnection studies for certain generators with Co-Located Load \ncould timely match new load with needed generation. \ne. \nInformational Report \n237.\nWe also are encouraged that, in August 2025, the PJM Board of Managers (PJM \nBoard) initiated the CIFP stakeholder process to address matters that relate to but that are \nbroader than those involving Co-Location Arrangements, and specifically, \"to address the \ndevelopment of reliability-focused solutions to ensure large load additions can continue \nService (1.0.0), § 414.B.2. \n481  See PJM March 24 Response at 5, 33-34, 53. PJM's option 6 refers to \nCo-located load that elects to be Network Load and bring its own generation. \n482 PJM suggests that one possibility could be to enhance existing provisional \ninterconnection service to accelerate in a non-discriminatory manner the ability of new \ngeneration to achieve commercial operation. Id at 17; see also Bloom April 23 Reply \nComments at 2 (arguing that an integrated interconnection approach such as that outlined \nin the Brattle Report attached to Bloom's comments, which \"shares some traits with the \napproach PJM calls New Option 6,\" could significantly accelerate the interconnection \ntimeline). \n483  See, e.g., PJM March 24 Response at 16-17; Market Monitor April 23 Reply \nComments at 11; BrightNight April 23 Reply Comments at 9; Ohio FEA April 23 Reply \nComments at 4-5; AEU April 23 Reply Comments at 14. \n484  PJM March 24 Response at 62. \n124 of 515"},{"page":126,"startToken":50205,"endToken":50685,"text":"Document Ac„„igPSA 2A-A.418-31?Kurnent:FlAd rFaINP:i12..A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 115 - \nto be integrated rapidly and reliably, without causing resource inadequacy.\"485  PJM and \nstakeholders considered a number of potential reforms designed to accommodate large \nload additions in an efficient and reliable manner. In PJM's contemplated expedited \ninterconnection process, for example, generation projects that have a contractual \ncommitment to a new large load, in addition to standalone generation that submits a \nhigher readiness deposit to PJM, would be able to access an expedited interconnection \npathway, so long as they seek to be Capacity Resources, meet a substantial size threshold, \npay a large, non-refundable study deposit, are supported by a state commitment to \nexpedite permitting, and demonstrate three full years of 100% site control, among other \ncriteria. Other reforms considered, and that we highlight here, included, but were not \nlimited to, modifications to PJM's reliability backstop mechanism to expedite PJM's \nability to procure generation capacity on a multi-year basis during instances of resource \nadequacy shortfalls, development of enhanced load forecasting criteria and processes, and \nrules to enable the more efficient utilization of the transmission system by increasing \ndemand flexibility. \n238. Accordingly, we direct PJM to submit in Docket No. EL25-49-000, within 30 days \nof the date of issuance of this order, a detailed informational report486  on the status of the \nproposals considered in the CIFP stakeholder process, including—but not limited to—the \nstatus of the expedited interconnection process to enable shovel-ready generation projects \nto serve PJM more quickly, modifications to PJM's reliability backstop mechanism to \nimprove PJM's ability to respond to acute resource adequacy shortfalls, and the \ndevelopment of enhanced load forecasting487  and demand flexibility measures to assist \nPJM in determining the amount of new capacity that is needed to maintain system \nreliability. The informational report must include a detailed schedule of key milestones, \nsuch as stakeholder or PJM Board votes, that includes the estimated date on which PJM \nexpects to file any such proposals with the Commission. Additionally, as part of this \ninformational report, we direct PJM to identify any problem statements, issue charges, or \nother ongoing stakeholder processes that aim to increase the pace of adding generating \ncapacity in the PJM region. PJM must provide as detailed a schedule as is feasible on the \n485 PJM, Critical Issue Fast Path — Large Load Additions, \nhttps://www.pjm.com/committees-and-groups/cifp-lla (last visited Dec. 5, 2025). \n486 Upon receipt, the Commission will not act on or notice this informational \nfiling. \n487  We note that, on October 20, 2025, PJM submitted a response to \nthen-Chairman Rosner's letter on load forecasting. See supra P 154. PJM should expand \non its response to then-Chairman Rosner in the informational report that we direct here \nby explaining, in detail, any changes or updates to its load forecasting processes that it is \nconsidering. \n125 of 515"},{"page":127,"startToken":50685,"endToken":51122,"text":"Document AccessigPSIV; \nAppument:Fl il d rEN:1.12A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 116 - \ntiming of such initiatives, including updates on the stakeholder process and approximate \ndates of any anticipated filings with the Commission. The informational report also must \nidentify specifically which of these initiatives would support the addition, on an \nexpedited basis, of new generation that is sufficient to serve large loads, like data centers, \nwhile meeting PJM's near-term system resource adequacy needs \n239.\nFinally, given PJM's currently compressed auction schedule, PJM should explain \nthe proposed effective date of any proposal that it intends to file so that the Commission \ncan understand whether any of those proposals could be in place by the 2028/2029 Base \nResidual Auction (BRA) and subsequent BRAs to attract sufficient new generation to \nmaintain regional resource adequacy. \n5. \nPJM Capacity Market, Reliability, and Resource Adequacy \n240.\nThere is also insufficient evidence in the record to find that the existing Tariff \nprovisions governing capacity market rules, reliability, and resource adequacy are unjust \nand unreasonable or unduly discriminatory or preferential. In the Show Cause Order, the \nCommission stated that the Tariff may be unjust and unreasonable and unduly \ndiscriminatory or preferential insofar as it lacks rules necessary to provide PJM with \nsufficient information to perform appropriate analysis to ensure reliable system \noperations given the characteristics of Co-Location Arrangements.488  Commenters \nresponded with concerns, including that Co-Located Load served entirely \nbehind-the-meter will not be accounted for in PJM's planning processes and that \nCo-Located Load could unexpectedly appear online after being previously invisible to \nPJM 489 \n241.\nHowever, as directed herein, Interconnection Customers choosing to serve \nCo-Located Load using their generating facilities will be required to identify an Eligible \nCustomer who will take transmission service on behalf of that Co-Located Load. We \nfind that this requirement should address concerns that Co-Located Load would not be \nvisible to PJM or its transmission owners. We further note that Co-Located Load that \nelects to meet this requirement by taking NITS or the new Firm Contract Demand \ntransmission service through an Eligible Customer will be included in transmission \nplanning and the capacity market.49°  In addition, the Eligible Customer that elects to \ninstead take the Non-Firm Contract Demand transmission service on behalf of \n488  See Show Cause Order, 190 FERC ¶ 61,115 at PP 83-86. \n489  Indicated Transmission Owners April 23 Reply Comments at 13; PPL April 23 \nReply Comments at 10-11; Pennsylvania Commission April 22 Reply Comments at 6. \n490 See PJM March 24 Response at 39 n.64; Indicated Transmission Owners \nMarch 24 Response, attach. A at 17. \n126 of 515"},{"page":128,"startToken":51122,"endToken":51532,"text":"Document AccessigRSAA: 2.2q-2.1\n8- 3?pcument:Flil d rFacw: 31A8/2We Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 117 - \nCo-Located Load agrees that it will be curtailed during emergency operations upon \nPJM's direction, and thus will not be included in transmission planning or in the capacity \nmarket. \n242.\nBecause PJM states that Co-Located Loads that elect to be Network Load may \nparticipate as a demand response resource under PJM's existing Tariff,4\" we find that \nthere is not sufficient evidence to conclude that the existing Tariff is not just and \nreasonable as it relates to the existing demand response rules. We recognize that PJM \nacknowledges that there could be an additional review of the PJM Demand Response \nrules in its stakeholder process,492  which may be further addressed through a future FPA \nsection 205 filing. We also note that the Firm Contract Demand transmission service and \nNon-Firm Contract Demand transmission service we direct in this order will create \nopportunities for Co-Located Loads that do not elect to be Network Load to benefit from \nany ability they have to limit their consumption. \n243.\nRegarding broader resource adequacy and reliability concerns associated with \nmaintaining sufficient generation to serve Co-Located Load, we reiterate that load growth \ngenerally involves resource adequacy and reliability considerations, regardless of whether \nthe new load is Co-Located Load.493  Several commenters, including PJM, acknowledge \nthis fact.494  While the Commission found in the Show Cause Order that the speed at \nwhich Co-Located Load can be added to the transmission system may pose particular \nresource adequacy challenges, especially if Co-Location Arrangements are not \nadequately and transparently reflected in existing resource adequacy planning \nmechanisms,495  there is not sufficient evidence to conclude that additional Tariff changes \nregarding Interconnection Customers electing to use their generating facilities to serve \nCo-Located Load are needed with respect to capacity market rules, reliability, and \nresource adequacy to ensure that the PJM Tariff remains just and reasonable. We \nencourage PJM to continue monitoring capacity market, resource adequacy, and \nreliability issues as they relate to Co-Location Arrangements to evaluate whether \nadditional Tariff changes may be appropriate. \n491  PJM March 24 Response at 19-20. \n492  Id. at 20. \n493  Show Cause Order 190 FERC ¶ 61,115 at P 85. \n494  See, e.g., PJM March 24 Response at 57; Constellation April 23 Reply \nComments at 11, 60-61 (citing Patterson Aff. ¶ 15). \n495  Show Cause Order 190 FERC ¶ 61,115 at P 85. \n127 of 515"},{"page":129,"startToken":51532,"endToken":51949,"text":"Document Accessig.Pir; 22q-Aqq18  _ \nm e n t:F1 d ipaq99:i1A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 118 - \n6. \nMotions \n244.\nIn response to the Motion to Stay, we reject the Joint Parties' request to stay the \nproceeding to allow them to develop through settlement proceedings a new replacement \nrate that establishes the services an Eligible Customer takes on behalf of Co-Located \nLoad and allocates any costs to such Eligible Customer. Because we have established \npaper hearing procedures to determine the just and reasonable rates, terms, and conditions \nfor new transmission services, and directed PJM to make related Tariff revisions on \ncompliance, we deny the Motion to Stay. \n245.\nWe note that Vistra moved for clarification in this proceeding regarding the \nmeaning of Susquehanna by April 16, 2025 so that parties could take the Commission's \nclarification of that order into account when preparing the comments due in this \nproceeding on April 23, 2025. The Commission issued the Susquehanna Rehearing \nOrder on April 10, 2025 in Docket No. ER24-2172-002, including ruling on Vistra's \nmotion in that proceeding seeking clarification of Susquehanna.496  We thus dismiss as \nunnecessary Vistra's pending motion in this proceeding. \n246.\nWe partially grant Constellation's Motion insofar as we adopt the finding in the \nShow Cause Order that the PJM Tariff is unjust and unreasonable and establish a \nreplacement rate. \n247.\nWe disagree with PJM that acting in this proceeding violates applicable case law. \nPJM selectively quotes Cities of Anaheim for the proposition that adjudication should not \nsupplant a pending rulemaking proceeding, but PJM points to no actual court decision \nthat holds that an agency has violated the Administrative Procedure Act on that basis. \nWe also disagree with parties who argue that acting in this proceeding would prejudge \nthe issues raised in the ANOPR proceeding or otherwise be improper. The Commission \nhas discretion as to whether to proceed via adjudication or rulemaking,497  and we find \nthat it is an appropriate exercise of discretion to act on the PJM co-location proceeding \nbefore taking any action in the ANOPR proceeding. \n7. \nConstellation Complaint \n248. In the Show Cause Order, the Commission consolidated the new show cause \nproceeding in Docket No. EL25-49-000 with the complaint filed by Constellation against \nthe PJM Tariff in Docket No. EL25-20-000. As summarized in detail in the Show Cause \n496  Susquehanna, 191 FERC ¶ 61,025. \n497  /V.L.R.B. v. Bell Aerospace Co. Div. of Textron, Inc., 416 U.S. 267, 294 (1974). \n128 of 515"},{"page":130,"startToken":51949,"endToken":52393,"text":"Document AccessigPSA:  2q7Aq18-3PPcument:FlAd ij1@g: 312.748/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 119 - \nOrder,498  Constellation argued that the Tariff is unjust and unreasonable and unduly \ndiscriminatory because it lacks rules for interconnected generators to follow when \nseeking to serve to end-use load co-located with generation behind the meter in a \nconfiguration with system protection facilities to prevent the load from receiving \nelectricity from the transmission system.499  Constellation stated that, in establishing the \nreplacement rate, the Commission should conclude that provisions of the PJM Guidance \nDocument not on file with the Commission (particularly sections 2, 3, 5, and 7) must be \nincorporated into the Tariff under the rule of reason, which will provide certainty to \ngenerators and transmission owners by ensuring that the PJM Guidance Document is \napplied to all interconnected generators seeking to serve Co-Located Load.500 \n249. We grant in part and deny in part the complaint. We grant the complaint insofar \nas we find, as discussed above, that PJM's Tariff is unjust and unreasonable because it \ndoes not contain provisions addressing with sufficient clarity or consistency the rates, \nterms, and conditions of service that apply to Interconnection Customers serving \nCo-Located Load, including generators serving Co-Located Load in a configuration with \nspecial protection schemes to prevent the Co-Located Load from taking energy from the \ntransmission system. We deny the complaint insofar as we direct PJM, as discussed \nabove, to revise the Tariff to establish just and reasonable replacement rates, terms, and \nconditions for Interconnection Customers serving Co-Located Load. The PJM Guidance \nDocument has been rescinded by PJM,501  and it lacked all terms that we find above are \njust and reasonable for Interconnection Customers serving Co-Located Load. \nThe Commission orders: \n(A)\nPJM is hereby directed to submit, within 30 days of the date of issuance of \nthis order, revisions to its Tariff as described in Part IV.B.4.d. \n(B)\nPJM is hereby directed to submit, within 60 days of the date of issuance of \nthis order, revisions to its Tariff as described in Part IV.B.4.a and Part IV.B.4.c. \n(C)\nPJM is hereby directed to submit, within 60 days of the date of issuance of \nthis order, revisions to modify its Tariff to provide that the Eligible Customer taking \ntransmission service on behalf of a Co-Located Load ensure that the Co-Located Load \ntake one of three transmission services: (1) NITS, as modified in the body of this order, \n498  See Show Cause Order, 190 FERC ¶ 61,115 at P 50. \n499  Complaint at 1. \n50°  Id. at 20. \n5\" PJM March 24 Response at 33. \n129 of 515"},{"page":131,"startToken":52393,"endToken":52683,"text":"Document AccessigPSIPr 2A-Aqq1,_3Q9cument:Flil d  jpaqg9: j12.11:18/2pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 120 - \n(2) a new Firm Contract Demand transmission service, or (3) a new Non-Firm Contract \nDemand transmission service, as discussed in Part IV.B.4.b. \n(D)\nPaper hearing procedures are established to evaluate the rates, terms, and \nconditions of the interim, non-firm transmission service, Firm Contract Demand \ntransmission service, and Non-Firm Contract Demand transmission service. \n(E)\nPJM is hereby directed to submit its initial brief in Docket \nNo. EL25-49-000 on or before February 16, 2026. The deadline to file responses to \nPJM's initial brief will be March 18, 2026, and the deadline to file replies to those \nresponses will be April 17, 2026. \n(F)\nPJM is hereby directed to submit, within 60 days of the date of issuance of \nthis order, revisions to the Tariff to: (1) revise the BTMG rules, as discussed in the body \nof this order; (2) propose a new MW threshold for the amount of load that Network \nCustomers may net by using BTMG, as discussed in the body of this order; and \n(3) establish a transition period for Network Customers already using the BTMG rules, as \ndiscussed in the body of this order. \n(G)\nPJM is directed to submit an informational report within 30 days of the date \nof issuance of this order, as discussed in the body of this order. \n(H)\nJoint Parties' motion to stay is hereby denied, as discussed in the body of \nthis order. \n(I)\nVistra's motion for clarification is hereby dismissed, as discussed in the \nbody of this order. \n(J)\nConstellation's motion for expedited action is partially granted, as \ndiscussed in the body of this order. \n130 of 515"},{"page":132,"startToken":52683,"endToken":52757,"text":"Docum„t A„„sigOP; \niq'Aq418-3PPCument:Flild rFa99:i123/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 121 - \n(K) \nThe Constellation complaint in Docket No. EL25-20-000 is hereby granted \nin part and denied in part, as discussed in the body of this order. \nBy the Commission. Commissioner Rosner is concurring with a separate statement \nattached. \nCommissioner Chang is concurring with a separate statement \nattached. \n(SEAL) \nDebbie-Anne A. Reese, \nSecretary. \n131 of 515"},{"page":133,"startToken":52757,"endToken":52993,"text":"Document AccessigisA: 22q-g418-3gpcument:Fl it d rfaN9: i123A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 122 - \nAppendix \nIntervenors  \nAdvanced Energy United (AEU)+ \nAES Corporation* \nAlliant Energy Corporate Services, Inc. \nAllegheny Electric Cooperative, Inc.+ \nAlpha Generation, LLC* \nAmeren Companies502 \nAmerican Clean Power Association \nAmerican Council on Renewable Energy (ACORE)*+ \nAmerican Electric Power Service Corporation (AEP)5°3 \nAmerican Municipal Power, Inc. (AMP)+& \nAmerican Petroleum Institute* \nAmericans for a Clean Energy Grid (ACEG)+ \nAMP Transmission, LLC* \nAntora Energy LLC (Antora)*+ \nAppalachian Voices \nArevon Energy, Inc. \nArkansas Public Service Commission* \nAvangrid, Inc. \nBloom Energy Corporation (Bloom)+ \nBoston Energy Trading and Marketing LLC \nBrightNight Power Marketing, LLC (BrightNight)+ \nBrookfield Renewable Trading and Marketing LP \nBuckeye Power, Inc. (Buckeye)+& \nBusiness Council for Sustainable Energy (BCSE)+A \nCalifornia Department of Water Resources State Water Project \nCalifornia Public Utilities Commission \n5°2  Ameren Services Company, a wholly-owned subsidiary of Ameren \nCorporation, moves to intervene on behalf of its affiliated public utility operating \ncompanies, Ameren Illinois Company, Ameren Transmission Company of Illinois and \nUnion Electric Company d/b/a Ameren Missouri. \n503 AEP moves to intervene on behalf of its affiliates Appalachian Power \nCompany, Indiana Michigan Power Company, Kentucky Power Company, Kingsport \nPower Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian \nTransmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP \nKentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and \nAEP West Virginia Transmission Company, Inc. \n132 of 515"},{"page":134,"startToken":52993,"endToken":53190,"text":"Document Accessig1PA: 2AAq18-3rfVCUMent:F11td EPAP:112348/2P2ale Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 123 - \nCalpine Corporation (Calpine) \nCampbell Energy Advisors, LLC \nCEPM Companies504 \nCenter for Biological Diversity (Center)# \nChevron U.S.A. Inc. (Chevron)+ \nClean Air Task Force (CATF)# \nClean Energy Buyers Association \nClearway Energy Group LLC* \nConsolidated Edison Company of New York, Inc. \nConstellation Energy Generation, LLC (Constellation)& \nConsumers Energy Company \nConsumers' Research+ \nCooperative Energy \nCordelio Services LLC* \nCrete Energy Venture, LLC \nData Center Coalition+ \nDelaware Municipal Electric Corporation, Inc. \nDelaware Public Service Commission (Delaware Commission)*+ \nDominion Energy Services, Inc. \nDTE Electric Company \nEarthjustice \nEast Kentucky Power Cooperative, Inc. \nEast Texas Electric Cooperative, Inc. \nEDF Renewables, Inc. (EDFR)*+ \nEdison Electric Institute (EEI)+ \nElectric Power Supply Association (EPSA)5°5+ \nElectricity Consumers Resource Council (ELCON)+ \nEnchanted Rock, LLC (Enchanted Rock)+ \nEnerwise Global Technologies, LLC (CPower) \nENGIE North America Inc.* (ENGIE)+ \nEnvironmental Defense Fund* \nEolian, LP* \nExelon Corporation \nExus Renewables North America (Exus)# \n504 Hamilton Liberty LLC, Hamilton Patriot LLC, Lakewood Cogeneration, LP, \nEssential Power OPP, LLC, Essential Power Rock Springs, LLC, and Cogentrix Energy \nPower Management, LLC (Cogentrix) comprise CEPM Companies. \n5°5  EPSA submitted joint comments with P3 (EPSA/P3). \n133 of 515"},{"page":135,"startToken":53190,"endToken":53536,"text":"Document Accessig?S#;-  a42-Y1418-3Q9cUrnent:Fhtd IPAg9:1123A8/2PAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 124 - \nFirstEnergy Transmission Companies5°6 \nGoogle Energy LLC \nGoogle LLC \nHamilton Liberty \nIdaho Power Company \nIllinois Attorney General's Office \nIllinois Citizens Utility Board \nIllinois Municipal Electric Agency \nIndiana Office of Utility Consumer Counselor* \nIndicated Transmission Owners507+& \n5°6  First Energy Service Company moves to intervene as agent for its affiliates \nAmerican Transmission Systems, Incorporated, Jersey Central Power & Light Company, \nMid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission \nCompany, The Potomac Edison Company, Monongahela Power Company and \nTrans-Allegheny Interstate Line Company. \n5°7  Indicated Transmission Owners include: AEP on behalf of Appalachian Power \nCompany, Indiana Michigan Power Company, Kentucky Power Company, Kingsport \nPower Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian \nTransmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP \nKentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and \nAEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of \nCleveland, Department of Public Utilities, Division of Cleveland Public Power; City of \nHamilton, OH; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power \nCompany d/b/a Dominion Energy Virginia; Duke Energy Corporation on behalf of its \naffiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy \nBusiness Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; \nExelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and \nElectric Company, Commonwealth Edison Company, Commonwealth Edison Company \nof Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and \nPotomac Electric Power Company; FirstEnergy Service Company, as agent for its \naffiliates American Transmission Systems, Incorporated; Jersey Central Power & Light \nCompany, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian \nTransmission Company, The Potomac Edison Company, Monongahela Power Company \nand Trans-Allegheny Interstate Line Company; Old Dominion Electric Cooperative; PPL \nElectric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric \nCooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc. \nDominion Energy Services did not join in the June 3 Answer or the June 27 Answer. \nDuquesne Light Company did not join in the June 27 Answer. \n134 of 515"},{"page":136,"startToken":53536,"endToken":53785,"text":"Document Accessig-PW -A\"Ael.;18-3P9Purnent:Flild M99:13A8/pate Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 125 - \nIndustrial Energy Consumers of America (IECA)508+ \nInvenergy Renewables LLC and Invenergy Thermal LLC (Invenergy)509+ \nITC Companies510 \nJoint Parties5\" \nKlondike Digital Infrastructure LLC \nLarge Public Power Council \nLee County Electric Cooperative, Inc. \nLincoln Generating Facility, LLC \nLS Power Development, LLC (LS Power) \nMainspring Energy, Inc. (Mainspring)+ \nMaryland Office of People's Counsel (together with New Jersey Division of Rate \nCounsel, Joint Consumer Advocates)*+ \nMaryland Public Service Commission \nMidwest Generation, LLC \nMississippi Public Service Commission \nMonitoring Analytics, LLC, acting in its capacity as the Independent Market Monitor for \nPJM (Market Monitor)+ \nNational Grid \nNational Grid Renewables Development, LLC \nNational Hydropower Association \nNational Rural Electric Cooperative Association \nNational Security Experts512+ \nNatural Resources Defense Council (NRDC)+ \nNebraska Public Power District \nNew Jersey Division of Rate Counsel+ \nNew York State Reliability Council, L.L.C.* \nNextera Energy Transmission MidAtlantic, Inc. (NEET)+ \n508 IECA filed joint comments with the PJM ICC. \n509 Invenergy Renewables LLC and Invenergy Thermal LLC comprise Invenergy. \n51°  International Transmission Company d/b/a ITC Transmission, Michigan \nElectric Transmission Company, LLC, ITC Midwest LLC and ITC Great Plains, LLC \ncomprise ITC companies. \n511  Joint Parties is composed of EPSA, P3, Calpine, Cogentrix, Constellation, and \nLS Power. \n512  National Security Experts is composed of John B. Hashem, Robert G. F. Lee, \nJoseph L. Lengyel, Craig R. McKinley, Benny M. Paulino, Paul Stockton, Chuck Wald, \nand Darryl D. M. Wong. \n135 of 515"},{"page":137,"startToken":53785,"endToken":54053,"text":"Document Accessigsp:: \nrpAg:3123/q8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 126 - \nNorth American Electric Reliability Corporation (NERC)*+ \nNortheast Texas Electric Cooperative, Inc. \nNortheastern Rural Electric Membership Corporation (NREMC)+& \nNorthern Virginia Electric Cooperative, Inc. (NOVEC)+& \nNRG Business Marketing LLC \nOffice of the Ohio Consumers' Counsel \nOhio Federal Energy Advocate (Ohio FEA)+ \nOne Power Company* \nOrange & Rockland Utilities, Inc. \nOrganization of PJM States, Inc. (OPSI)513+\" \nPacific Gas and Electric Company (PG&E)514+ \nPennsylvania Public Utility Commission (Pennsylvania Commission)+^ \nPJM& \nPJM Industrial Customer Coalition (ICC)+ \nPJM Power Providers Group (P3) \nPPL Electric Utilities Corporation (PPL)+ \nPSE&G Companies (PSE&G)515+& \nPublic Citizen, Inc. \nPublic Interest Organizations (PIOs)516+ \n513  OPSI noted that the following of its members support its comments: Delaware \nPublic Service Commission, Public Service Commission of the District of Columbia, \nIllinois Commerce Commission, Indiana Utility Regulatory Commission, Kentucky \nPublic Service Commission, Maryland Public Service Commission, Michigan Public \nService Commission, New Jersey Board of Public Utilities, Public Utilities Commission \nof Ohio, Pennsylvania Commission, Tennessee Public Utility Commission, Virginia State \nCorporation Commission and Public Service Commission of West Virginia. The North \nCarolina Utilities Commission did not join in these comments. \n514  PG&E submitted joint comments with Southern California Edison (together, \nCalifornia Utilities). \n515  Public Service Electric and Gas Company, PSE&G Power LLC and PSE&G \nEnergy Resources & Trade LLC comprise the PSE&G Companies. Comments were filed \nby Public Service Electric and Gas Company. \n516  PIOs is composed of Appalachian Voices, CATF, Earthjustice, EDF, \nPennFuture, and the Sierra Club. Of the PIOs, PennFuture did not move to intervene. \n136 of 515"},{"page":138,"startToken":54053,"endToken":54253,"text":"Document Accessigsp,: 2A-A_418 _ 3pgcument:Fl il d  Mg9: i12.32 8/2Pte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 127 - \nPublic Systems\"' \nRepsol Energy North America Corporation \nRockland Electric Company \nRMI# A \nSan Diego Gas & Electric Company \nShell Energy North America (US), L.P. \nSierra Club \nSilver Run Electric, LLC+ \nSolar Energy Industries Association (SEIA)+ \nSouthern California Edison Company+ \nSouthern Maryland Electric Cooperative, Inc.* \nSustainable FERC Project \nSuzanne Glatz and Abraham Silverman (Glatz and Silverman)+^ \nTalen Energy Corporation (Talen)+& \nThe Dayton Power and Light Company (AES Ohio)+ \nThe Retail Energy Supply Association \nUGI Utilities Inc. \nUnion of Concerned Scientists (UCS)+ \nUnited States Senators518n \nVirginia State Corporation Commission (Virginia Commission)* \nVistra Corp. (Vistra)+& \nVote Solar \nWabash Valley Power Association, Inc. \nWest Virginia Public Service Commission* \n* moved to intervene out-of-time \n+ filed comments or reply comments \n# filed comments out-of-time \n^ filed comments without a notice of intervention or motion to intervene \n& filed an answer \n517  Connecticut Municipal Electric Energy Cooperative, Massachusetts Municipal \nWholesale Electric Company, and Vermont Public Power Supply Authority comprise \nPublic Systems. \n518  United States Senators include Senators Edward J. Markey, Chris Van Hollen, \nElizabeth Warren, Peter Welch, Raphael Warnock, Richard Blumenthal, and Adam B. \nSchiff. \n137 of 515"},{"page":139,"startToken":54253,"endToken":54453,"text":"Document AccessigP \nq-Alq18 _31?gcument:Fl-il d riDa g: 3-123/8,8/2p-Ae Filed: 10/16/2026 \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-000 \nAllegheny Electric Cooperative, Inc. \nEL25-49-001 \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \n138 of 515"},{"page":140,"startToken":54453,"endToken":54739,"text":"Document Accessig0PT; \n\"§.4-18-31;31K UMent:FlAd rPaN9:i123A8/2pge Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n2 \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nAD24-11-000 \nConstellation Energy Generation, LLC \nEL25-20-000 \n(Consolidated) \nv. \nPJM Interconnection, L.L.C. \n(Issued December 18, 2025) \nROSNER, Commissioner, concurring: \n1.\nToday's order directs reforms that deliver a commonsense outcome: if a new large \nload wants to connect directly to a power plant and operate in a way that lowers grid \ncosts, we should let it. If the current rules don't let this work in a way that's fair for \neveryone, we must change those rules to deliver the cost savings that consumers so badly \nneed and ensure reliable electricity for all. Saying no to innovation is not a winning \nstrategy—whether we're trying to win the AI race, bring back American manufacturing, \nor deliver the reliable and affordable energy on which families and small businesses \ndepend. \n2.\nWhile today's outcome is commonsense, like so many Commission policies, the \norder includes a lot of regulatory jargon, which is necessary for technical precision and \nlegal durability. That being the case, I write separately to explain what we are doing and, \nimportantly, why we are doing it. \n3.\nLet's begin by explaining the problem that we are trying to solve. We are trying \nto meet surging demand while upholding two fundamental values that underpin the \n139 of 515"},{"page":141,"startToken":54739,"endToken":55241,"text":"Document AccessigISA:4q-21-8-APPLIMerlt:Filld  LPaqg :  il-A.8/2Me Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 3 \nelectric industry in our country: first, that all customers have a right to receive electric \nservice on a timely basis, and second, that electric service should be reliable and \naffordable for all customers. Given the scale of new large loads putting demand on our \ngrid today, it is clear that fostering both of these values requires intervention. \nUnfortunately, it has become persistently difficult and increasingly expensive to build \nnew grid infrastructure in this country. Because of this, a business-as-usual approach to \nload growth—planning for generation and load separately—will not suffice to timely \nmeet growing demand while also keeping prices reasonable. \n4.\nToday's order helps break the logjam. It directs PJM to establish new pathways \nfor co-location—directly connecting a large load with the power needed to serve it at the \nsame site—and load flexibility that enable large co-located loads to reduce how much \nthey lean on the grid, while ensuring that they pay their fair share. As a result, PJM can \navoid constructing unnecessary transmission upgrades for large loads, reduce strain on \nthe grid, and make power bills cheaper for everyone—including for families and small \nbusinesses. And co-located large loads and generators can get online faster and easier \nthan would otherwise be the case. Grid operators like PJM should allow and encourage \nlarge loads and generators to pursue these time- and cost-saving co-location \narrangements. Here's how we get there. \n5.\nFirst, today's order directs PJM to create two new transmission services, which we \ncall Firm and Non-Firm Contract Demand Transmission Service. These services \nallow a load that is co-located with a generator to contract and pay for service from the \ngrid consistent with the load's actual net withdrawals, while ensuring that the load cannot \ntake more service than the contracted amount. \n6.\nFor example, consider a 1,000 MW data center that co-locates with a new 900 \nMW generator. Under PJM's status quo rules, the data center would be required to take \nthe full 1,000 MW of \"front-of-meter\" transmission service (see Figure 1), despite being \ndirectly connected to the co-located generator. Under today's order, the data center has \ntwo new options: \na. The data center may elect to purchase Firm Contract Demand Transmission \nService if, for example, it plans to take just 100 MW of firm transmission service \nfrom the grid and get the remaining 900 MW of energy it needs from the co-\nlocated generator (see Figure 2). In turn, PJM will plan enough transmission and \nprocure enough capacity to serve only that 100 MW. \nb. The data center may instead elect to purchase Non-Firm Contract Demand \nTransmission Service if, for example, it only plans to pull energy from the grid \ntemporarily while its co-located generator is undergoing scheduled maintenance \n(see Figure 3). When the data center chooses non-firm service, PJM will not plan \nany additional transmission or purchase any capacity to serve that load. \n140 of 515"},{"page":142,"startToken":55241,"endToken":55783,"text":"Document AccesSiII@S\n 2A-A61418-3gccument:FlAd ifiq99:ilAi8/2p2Ve Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 4 \nUnder either new transmission service, the co-located load must uphold its side of the \nbargain by bearing the risk of being curtailed if its usage exceeds what it has contracted \nfor in advance. Therefore, regardless of whether a customer takes the new firm service, \nthe new non-firm service, or some combination of the two, PJM will plan less \ntransmission and procure less generating capacity for the data center, which reduces costs \nfor both the new co-located load and for all other PJM customers and creates the \nopportunity for both the new generator and the new load to get online more quickly. \n7.\nSecond, today's order directs PJM to revise its generator interconnection rules to \nclarify how both new and existing generators may co-locate with load, with a particular \nemphasis on accelerating new generation. \n8.\nFor new generators, the order directs PJM to clarify that a generator may request \na level of service that is consistent with its actual injections to the grid, net of a co-located \nload. Consider the example above, but in reverse. If a new 1,000 MW generator co-\nlocates with a new 900 MW data center, that generator will be allowed to \"reserve\" 900 \nMW to directly serve the data center, and will thus request to inject only 100 MW onto \nthe PJM grid. As a result, new generators with co-located load will need fewer \ntransmission upgrades to access the grid, allowing much-needed electricity to get online \nmore quickly and affordably. Furthermore, the order directs PJM to file these rules for \nnew generator interconnection within 30 days. In sum, these changes will make \n\"bringing your own new generation\" co-located with new load cheaper and faster, \nbenefiting the generator, the large load it will serve, and—critically—all other PJM \ncustomers. \n9.\nFor existing generators, today's order directs PJM to clarify that a generator \ncannot remove its capacity from the grid to serve a co-located load until all transmission \nupgrades needed to maintain reliability are in service, with the costs of those upgrades \nallocated 100% to the existing generator. This means that generators comprising the \nkeystone of today's grid cannot abandon existing customers unless and until those \ngenerators and their large load customers—not other ratepayers—construct the \ntransmission upgrades and incur the costs necessary to maintain reliable service for \neveryone. And under any of the new transmission services, the large load will also pay \nits fair share for any benefits it continues to draw from the grid after the co-location \narrangement is set up. \n10.\nThird, today's order protects existing customers—including families and small \nbusinesses—by directing PJM to assign transmission costs to ensure that a co-located \nload, such as a data center, always pays its fair share. A co-located load that does not \nwithdraw energy from the grid will pay for at least the essential grid services on which it \nstill relies (i.e., regulation and black start services). Meanwhile, a co-located load that \nhas the same right to withdraw energy from the grid as a conventional front-of-meter load \nwill take and pay for the full cost of traditional network transmission service. And for all \n141 of 515"},{"page":143,"startToken":55783,"endToken":56275,"text":"Document Acc„sigtr; \n4qAq418-3gSc urrient:Fhld rf)Ag9:i1448/2p2ale Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 5 \noptions in between, a co-located load will pay a fair rate that is commensurate with its \nactual usage of the grid, protecting other customers from unfair cost shifting and price \nincreases. Unless a load and its generator are completely disconnected from the grid, \nthey will get benefits from the grid—and today's order ensures that they will pay for \nthose benefits. \n11.\nFourth, today's order directs PJM to establish a new interim service (see Figure \n4) to provide a bridge while the infrastructure needed to serve a large load with \ntraditional front-of-meter network transmission service is being built. This interim \nservice leverages speed in the near-term and unlocks the benefits of a full grid connection \nin the long-term. It will allow co-located loads and generators seeking front-of-meter \nservice to access the grid faster than they can today. In exchange for increased speed, \nthese loads will bear the risk of being curtailed when the grid is constrained until the \ntransmission upgrades needed to provide service are constructed. But that doesn't mean \nthat the load will always have to shut down completely during peak periods. Rather, if \nthe co-located load is paired with a new generator, and that generator is still waiting to \nbegin its own front-of-meter service, the load can take service directly from the generator \nin the interim until both \"graduate\" to full, front-of-meter service. This pathway is \nimportant because traditional, front-of-meter network transmission service provides the \nbroadest benefits to both load and generators—a network load can be served by any \ngenerator on the grid, and a network generator can sell its power to any customer on the \ngrid. \n12.\nFifth, today's order encourages further progress on solutions beyond co-location to \nkeep up with growing electricity demand by directing PJM to provide the Commission \nwith a detailed report that describes its ongoing initiatives to reduce both technical and \nfinancial barriers to building new generation and efficiently connect large loads. Given \nPJM's announcement yesterday that its 2027/2028 Base Residual Auction was short of its \nreliability requirement, the solutions enabled by both today's order and PJM's ongoing \ninitiatives to accelerate new generation are immensely important and urgent. The \ninformation PJM will file allows the Commission to monitor PJM's progress and ensure \nthat any further Commission actions on large load issues in the PJM region skate to \nwhere the puck is going. To that end, Secretary Wright recently asked the Commission \nto consider a range of \"potential reforms to ensure the timely and orderly interconnection \nof large loads to the transmission system.\"519  Although the Secretary's initiative is \n519  U.S. Department of Energy, Secretary of Energy, Direction that the \nCommission Initiate Rulemaking Procedures and Proposal Regarding the Interconnection \nof Large Loads Pursuant to the Secretary's Authority Under Section 403 of the \nDepartment of Energy Organization Act (Oct. 23, 2025). \n142 of 515"},{"page":144,"startToken":56275,"endToken":56511,"text":"Document AcceSsiGRSP 2A-2-%qq-1.8-31?Kument:Flil d ERN9:iv,..18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n- 6 \nbroader than both co-location and PJM, I am pleased that today's order makes major \nprogress on the important matters that he referred to the Commission. \n13.\nFinally, all of the Commission's actions in this proceeding respect the long-\nstanding jurisdictional line between federal and state authority provided by Congress and \naffirmed by the Supreme Court. Co-located loads will continue to receive a bill for state-\nregulated retail service just like any other load. Moreover, states retain exclusive \njurisdiction to allocate how the costs of FERC-jurisdictional transmission charges are \ndivided between their retail ratepayers, including co-located loads. The difference \ntoday's order makes is that utilities and load-serving entities will now have access to new \ntransmission service options that will help lower costs for everyone. \n14.\nToday's order is just the next step on important work that the Commission cannot \ndo alone. I encourage all parties to approach today's order, and the path forward that it \ndirects, with an open mind. Durable consensus requires your collective expertise to \nimplement a solution capable of meeting today's challenges, realizing the historic \nopportunity that load growth presents, and delivering the reliable and affordable energy \non which we all depend. Our country deserves no less. \nFor these reasons, I vote to approve today's order. \nDavid Rosner \nCommissioner \n143 of 515"},{"page":145,"startToken":56511,"endToken":56766,"text":"r \nGenerator \n4 \n0 to 900 MW \nAs-available \nPJM Grid \n1000 MW \nAs-available \nFigure 4: New Interim Network Integration Transmission Service \n0 to 900 MW \n• Load & Generator get non-firm \nAs-needed \nservice ASAP, and convert to \nfirm service (Fig. 1) when grid \nupgrades are complete \ntx: O00 \nt= 00 \n• Generator can serve load while \nawaiting grid connection or \nO00 \nLarge Load \nwhen grid is unavailable \nFigure 3: New Non-Firm Contract Demand Transmission Service \n• Load pays for non-firm \ntransmission service on an as-\nreserved basis \n• PJM has no obligation to serve \nload if grid is unavailable  \n• All or portion of the generator \nis devoted to co-located load \nPJM Grid \na Z2)\n 900 MW \nGenerator \n• \n0 to 1000 MW \nAs-available \nO \nL.=  O00  -=-1 \nO c:= 00 \ntz-.  O00  \nLarge Load \nFigure 1: \"Front-of-Meter\" Network Integration Transmission Service \n• PJM plans all transmission and \ngeneration to serve load  \n• Requires more transmission \ninfrastructure and can take \nlonger, but provides the \nbroadest benefits \n900 MW \n=I \nO O00 \nO \n00 \nO00 \nPJM Grid \n1000 MW \nLarge Load \nGenerator \nFigure 2: New Firm Contract Demand Transmission Service \n900 MW \n• Load pays for 100 MW of firm \ntransmission service \n• PJM has no obligation to serve \nO \nO \nO00 \nload above 100 MW \nO \n00 \nO00 \n• All or portion of the generator \nLarge Load \nis devoted to co-located load \n4-\nI. \nPJM Grid \n100 MW \n•\n \nGenerator \nDocument AccessigiSg qq-2.1\n8 _ 31eigcument:Fl i l d rpAp: 31441.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-000, et al. \n7 \nFigures  \n144 of 515"},{"page":146,"startToken":56766,"endToken":56960,"text":"Document A„essigPV; 2q7A.18-3PPPUMent:FlAd DI:AP:1124AB/ 2 -Ale Filed: 10/16/2026 \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nBefore Commissioners: \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-000 \nAllegheny Electric Cooperative, Inc. \nEL25-49-001 \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \n145 of 515"},{"page":147,"startToken":56960,"endToken":57180,"text":"Do6urnent A„„sigsfer; qq418-3g9funient:Flita ifaN9: 31Aq8/2 ge Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n- 2 \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nAD24-11-000 \nConstellation Energy Generation, LLC \nEL25-20-000 \n(Consolidated) \nv. \nPJM Interconnection, L.L.C. \n(Issued December 18, 2025) \nCHANG, Commissioner, concurring: \n1.\nIn today's order, the Commission addresses the rates, terms, and conditions \nthrough which Co-Located Loads may take service from the PJM Interconnection, L.L.C. \n(PJM) system. I write separately to address certain aspects of the Commission's \nproposed replacement rate and highlight the importance of developing a minimum charge \nfor the new transmission services we establish today. \nToday's Order \n2.\nDue to significant delays in PJM's ability to interconnect new generation and load, \nlarge loads, including data centers, have preferred co-location arrangements to expedite \ntheir access to the PJM system. As today's order discusses, PJM's current tariff does not \nprovide adequate clarity for the rules governing co-location arrangements. With today's \n146 of 515"},{"page":148,"startToken":57180,"endToken":57618,"text":"Document Accessig@SA:  214-Aq418-314cument:FlAd d3aqgp: ilitA8/2pAte Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n- 3 \naction, the Commission is providing guidance on how loads and generators may co-\nlocate, including the development of new transmission services that recognize their \nability to limit their energy withdrawals from the transmission system. The responsibility \nfor setting these rules sits with the Commission. As we work together to address this \nissue, we must continue to keep protection of other customers from unnecessary risks and \ncosts at the forefront of our decision making. \n3.\nToday's order represents the first step to developing a package of solutions to \naddress co-location in the PJM footprint. Specifically, by recognizing that controllable \nCo-Located Loads might use less service from the transmission system than traditional \nloads in front of the meter, the order's revised transmission service framework may \nreduce the number of, and costs associated with, future transmission upgrades. The order \nalso helps to clarify how new generation resources may connect to the system on a \nprovisional basis to serve Co-Located Loads. \n4.\nDesigning this new co-location framework highlights an essential component of \nthe overall package: how we protect other customers from adverse reliability impacts and \nunjustified cost shifts. The Commission will ultimately resolve the rates, terms, and \nconditions of these new services following the paper hearing and compliance processes \nwe direct today. As we consider the record, we will assess how those rates, terms, and \nconditions facilitate the efficient interconnection of Co-Located Loads, control \ntransmission costs needed to serve them, and protect other customers against unjustified \ncost shifts. \nNeed for a Minimum Charge \n5.\nOne aspect of the paper hearing is particularly essential to protecting customers \nagainst transmission cost shifts under the new framework established through today's \norder: the need to establish a minimum charge for the Firm and Non-Firm Contract \nDemand transmission services. \n6.\nThe order proposes to establish these two new transmission services for use where \nthe Co-Located Loads can electrically control the amount of energy that they will receive \nfrom the PJM system. As the order explains, all Co-Located Loads are synchronized to \nthe PJM transmission system through their generators. All generators, and as relevant \nhere, all generators that are part of Co-Located Arrangements, rely on the PJM \ntransmission system to operate. Without the PJM grid, Co-Located Loads and their \nassociated generators would be islanded. In today's order, neither of the newly \ndeveloped Contract Demand transmission services requires Co-Located Loads to take any \nspecific quantity of transmission service. In particular, the order contemplates that, under \nthe new Contract Demand transmission services, if the Co-Located Load takes no service, \n147 of 515"},{"page":149,"startToken":57618,"endToken":58096,"text":"Do8iiment Acce6sigisg 2A-g3. 18 _31:39cument:FlAd jj3Ag:31i4./i8/2pAte Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n- 4 \nit would pay only for black start and regulation service.' Because the charges for those \nservices only account for the provision of those discrete ancillary services, they do not \ncontribute to the actual cost of building, operating, or maintaining the grid, or the Co-\nLocated Load's explicit reliance on the PJM system. Black start and regulation service \ncharges are nearly inconsequential.2  Thus, just paying black start and regulation service \ncharges does not constitute the Co-Located Loads paying for their \"fair share\" of the cost \nof maintaining and operating the transmission system. Furthermore, under such a \nscenario, a Co-Located Load would not pay for a portion of PJM's administrative costs, \nwhich are typically included in transmission service rates, even though the Co-Located \nLoad benefits from services provided by PJM. \n7.\nAs a result, absent developing rates that explicitly charge the Co-Located Loads \nfor their synchronization to and reliance on the PJM system, it is possible that a Co-\nLocated Load would not contribute to the costs of operating and maintaining the system. \nSimilarly, if a Co-Located Load takes a de minimis amount of Firm or Non-Firm Contract \nDemand service, it would pay only a minimal amount of system costs. Such scenarios \nwould fail to recognize the benefits Co-Located Loads receive from the grid and risk \nshifting system costs to other customers. Simply put, Co-Located Loads electrically \nconnected to the grid (through a co-located generator) benefit from the system and should \ncover their costs. This is a foundational cost causation principle that the Commission \nmust uphold. \n8.\nIn the paper hearing established in today's order, the Commission seeks comments \non whether the rates, terms, and conditions for these two new transmission services \nshould reflect a minimum charge that recognizes that, without the transmission system, \nthe Co-Located Load and generators could not operate as envisioned. The paper hearing \nalso seeks briefing on how such a charge should be determined3  and whether PJM \nadministrative services charges should be applied to the new services.4  To ensure the \n1  PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 206 (2025). \n2  According to data from the most recent State of the Markets Report by the PJM \nIndependent Market Monitor, regulation and black start services constituted an average of \n$159 million and $47.5 million, respectively, for January through September 2024 and \n2025, while transmission constituted an average of $10.81 billion for those two years. \nSee PJM Independent Market Monitor, 2025 Q3 State of the Markets Report at 18, \nhttps://www.monitoringanalytics.com/reports/PJM_State_of the_Market/2025/2025q3-\nsom-pjm-secl.pdf. \n3  PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at P 219, questions 3 and 4. \n4  Id. questions 1 and 2. \n148 of 515"},{"page":150,"startToken":58096,"endToken":58620,"text":"Document AccessigPV; 2A-A.418-31Acument:Flild rpaqp:i1M.8/2p2kte Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n- 5 \nCommission has a full and complete record on this issue, I encourage commenters to \naddress the following points and questions in their responses to the paper hearing. \n9.\nFirst, a just and reasonable replacement rate for the new transmission services \nshould reflect some form of minimum transmission service charge, which would protect \nother customers against cost shifts resulting from Co-Located Loads that rely upon the \ntransmission system but do not directly or meaningfully contribute to its costs via \ntransmission service payments. This minimum charge would provide a floor to the Co-\nLocated Load's cost responsibilities to pay for a portion of system costs, commensurate \nwith the benefits that the Co-Located Load receives from the system, even where it plans \nto draw little or no energy from that system. I welcome comments on the need for such a \nminimum charge, including, but not limited to: (1) whether a Co-Located Load that is \nsynchronized to the grid but does not meaningfully contribute to transmission system \ncosts violates cost causation principles; and (2) whether such minimum charge is \nnecessary for those that choose to take either the Firm and Non-Firm Contract Demand \ntransmission service. \n10.\nSecond, I welcome comments on both the rate design and the specific costs to be \nincluded in such a minimum charge. For instance, given that all Co-Located Loads rely \non the existence of the PJM grid and are synchronized to it, such loads should pay for at \nleast their fair share of the system's operations and maintenance costs. In addition, I \nwelcome comments as to whether Co-Located Loads should bear responsibility for some \nportion of the capital investments required to ensure the transmission grid continues to \nreliably serve all customers, and if so, the specific calculation of such charges. \nNext Steps and Open Issues  \n11.\nWhile today's order is consequential, it is important that we place it in the proper \ncontext: it addresses a significant but discrete issue in PJM, and sets out services and \nguidance for a commercial model that may only be viable in a limited number of states \nwhere the co-located generator is eligible under state law to serve Co-Located Load. For \nstates where retail loads must be served by the local electric utility, the model \ncontemplated in this order may not apply, and thus it does not necessarily provide a \nreplicable approach for large loads generally. Therefore, the broader challenge of \nreliably, efficiently, and fairly interconnecting large loads and the generation needed to \nserve them remains before the Commission, the states, and industry. \n12.\nFurther, today's order does not address the broader reliability challenges \nimpacting the PJM footprint and its customers. While the order directs PJM to clarify \noptions that exist under its current tariff, it does not address the clogged interconnection \nqueue that has driven the interest in co-location in the first place as a way to expedite \nlarge loads' access to the grid. Solving this foundational problem will require a durable \nfix to the interconnection process that helps resources interconnect at a much more \n149 of 515"},{"page":151,"startToken":58620,"endToken":58944,"text":"Do6ument Access igPsier; 22q-A_418-3PRCument:Fhtd LPaqg9:  125/g 8 / 2pge Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n6 \nefficient pace. As part of solving this problem, PJM must ensure that the transmission \nsystem is built to adequately support the interconnection of new, needed generation. I \nhave a strong preference for durable reforms over one-off fixes.5  Sound investments are \ndriven by good data, comprehensive planning, and disciplined operations. The \nCommission, states, grid planners and operators, and utilities must balance near-term \npressures and incentives with delivering long-term value to the customers we serve. \nBeyond this proceeding, I am concerned about PJM's ability to procure sufficient \nresources to reliably serve both new and existing load. PJM's resource adequacy \nconstruct must deliver clear price signals while being mindful of ratepayer costs. \n13.\nAs we consider further reforms, the Commission's core regulatory principles —\nmost notably open access to the transmission system (including through an efficient \ninterconnection process) — remain the foundation for addressing load growth and related \nchallenges. While reform to existing approaches is likely needed, customers —\nparticularly captive ones — must not bear the cost of a data center-driven infrastructure \nbuildout, and the risks and costs associated with this buildout must not be shifted to small \nbusinesses and residential customers. \nConclusion \n14.\nFollowing the paper hearing and compliance process, the Commission will \ndetermine the just and reasonable replacement rates. This process will consider \ncomments regarding the design of these new transmission services, and how to ensure \nthat other customers are protected against unnecessary risks and costs. As we establish \nnew transmission services, it cannot come at the expense of other ratepayers. I look \nforward to reviewing the record developed in response to today's order while the \nCommission, the states, PJM, and others work to address the broader reliability and \ninterconnection challenges facing the region. \n5  See, e.g., Sw. Pwr. Pool, Inc., 192 FERC ¶ 61,062, at P 3 (2025) (Chang, \nComm'r, concurring). \n150 of 515"},{"page":152,"startToken":58944,"endToken":58978,"text":"Document AccessigP SA :  14-Aq18-31Acument:Flild \nrpa g: 3:125/118/2p2aje Filed: 10/16/2026 \nDocket Nos. EL25-49-000, et al. \n- 7 \nFor these reasons, I respectfully concur. \nJudy W. Chang \nCommissioner \n151 of 515"},{"page":153,"startToken":58978,"endToken":59001,"text":"Doaument AccessigP. SP; 4qq.418-3P9cument:Fhtd. rEqg:1125A.8/2pAte Filed: 10/16/2026 \nDocument Content(s) \nEL25-49-000.docx \n1 \n152 of 515"},{"page":154,"startToken":59001,"endToken":59045,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 153 \nDate Filed: 10/16/2026 \nATTACHMENT B \nPJM Interconnection, L.L.C. et al.; Notice of Denial of Rehearing By \nOperation of Law and Providing for Further Consideration, 194 FERC \n¶ 62,089 (Feb. 20, 2026). \n153 of 515"},{"page":155,"startToken":59045,"endToken":59084,"text":"Case: 26-3621 \nDocument: 1-1 \nPage: 157 \nDate Filed: 10/16/2026 \nATTACHMENT C \nPJM Interconnection, L.L.C. et al.; Order on Rehearing, Clarification, \nCompliance Filing, and Paper Hearings, 195 FERC ¶ 61,209 (June 18, \n2026). \n157 of 515"},{"page":156,"startToken":59084,"endToken":59280,"text":"Document A„„sigi?iP; qq-2016-398Purnent:Flitd ri=1g9:6125A012pAte Filed: 10/16/2026 \n194 FERC ¶ 62,089 \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDocket Nos. EL25-49-002 \n154 of 515"},{"page":157,"startToken":59280,"endToken":59557,"text":"Document AccessigPS : 2A2-V10-3PgPument:FlAd ig@g9:(125i610/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n-2-\nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nAD24-11-001 \nEL25-20-001 \n(Consolidated) \nNOTICE OF DENIAL OF REHEARING BY OPERATION OF LAW AND \nPROVIDING FOR FURTHER CONSIDERATION \n(Issued February 20, 2026) \nRehearing has been timely requested of the Commission's order issued on \nDecember 18, 2025, in this proceeding. PJM Interconnection, L.L.C., 193 FERC \n¶ 61,217 (2025). In the absence of Commission action on a request for rehearing within \n30 days from the date it is filed, the request for rehearing may be deemed to have been \ndenied. 16 U.S.C. § 8251(a); 18 C.F.R. § 385.713 (2025); Allegheny Def. Project v. \nFERC, 964 F.3d 1 (D.C. Cir. 2020) (en banc). \nAs provided in 16 U.S.C. § 8251(a), the requests for rehearing of the above-cited \norder filed in this proceeding will be addressed in a future order to be issued consistent \nwith the requirements of such section. As also provided in 16 U.S.C. § 8251(a), the \nCommission may modify or set aside its above-cited order, in whole or in part, in such \nmanner as it shall deem proper. \nDebbie-Anne A. Reese, \nSecretary. \n155 of 515"},{"page":158,"startToken":59557,"endToken":59580,"text":"D6cunient A„„sigps#:: 2fi)-2-YRAlo _ Appurnent:Fhld rPag9:61.25A012pAte Filed: 10/16/2026 \nDocument Content(s) \nEL25-49-002.docx \n1 \n156 of 515"},{"page":159,"startToken":59580,"endToken":59785,"text":"Document Accessigi SP: 22q'AgA-18 - 3R8P ument :F \nrPaq99:0 5/4812P2% -te Filed: 10/16/2026 \n195 FERC ¶ 61,209 \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nBefore Commissioners: Laura V. Swett, Chairman; \nDavid Rosner, Lindsay S. See, \nJudy W. Chang, and David LaCerte. \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-002 \nAllegheny Electric Cooperative, Inc. \nEL25-49-000 \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \n158 of 515"},{"page":160,"startToken":59785,"endToken":59988,"text":"Document AccessigOA -2Aq18-3Q9c ument:Flil d rpAp:6185/4812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 2 \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nAD24-11-001 \nConstellation Energy Generation, LLC \nEL25-20-001 \n(consolidated) \nv. \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nER26-1479-000 \nORDER ON REHEARING, CLARIFICATION, COMPLIANCE FILING, AND PAPER \nHEARING \n(Issued June 18, 2026) \n1. \nOn December 18, 2025, the Commission issued an order in the show cause \nproceeding in Docket No. EL25-49-000, et al., pursuant to section 206 of the Federal \nPower Act (FPA),' finding PJM Interconnection, L.L.C.'s (PJM) Tariff unjust and \nunreasonable because it does not contain provisions addressing with sufficient clarity or \nconsistency the rates, terms, and conditions of service that apply to generators serving \n1  16 U.S.C. § 824e. \n159 of 515"},{"page":161,"startToken":59988,"endToken":60446,"text":"Dodum„t AccessigPSP; 22q'Agg-18-3Wc Urnent:Flild IF,AgP:6166/C:18/ 2 PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 3 \nCo-Located Load and Eligible Customers taking transmission service on behalf of \nCo-Located Load.2 \n2.\nThe Commission directed PJM to file, within 60 days of the date of issuance of the \norder, a compliance filing to revise its Tariff to set forth specific terms and conditions \nthat an Interconnection Customer in PJM seeking to serve Co-Located Load must follow \nto effectuate a Co-Location Arrangement. In addition, the Commission directed PJM to \nsubmit in its compliance filing revisions to its Tariff to require that the Eligible Customer \ntaking transmission service on behalf of the Co-Located Load takes one of three \ntransmission services: (1) Network Integration Transmission Service (NITS), including a \nnew interim, non-firm transmission service available until all Network Upgrades \nnecessary to provide the requested NITS are complete (Interim NITS), (2) a new Firm \nContract Demand (FCD) transmission service, or (3) a new Non-Firm Contract Demand \n(NFCD) transmission service.3  The Commission established a paper hearing to \ndetermine the just and reasonable rates, terms, and conditions for these new transmission \nservices. \n3.\nThe Commission also found the Behind the Meter Generation (BTMG) rules in the \nTariff to be no longer just and reasonable, and the Commission directed PJM to submit in \nits compliance filing revisions to its Tariff to revise the retail BTMG netting rules and to \nimplement a transition process for existing BTMG participants.4 \n2  PJM Interconnection, L.L. C., 193 FERC ¶ 61,217, at P 2 (2025) (December \nOrder). The December Order defined the Tariff as PJM's Open Access Transmission \nTariff (OATT), the Amended and Restated Operating Agreement of PJM, and the \nReliability Assurance Agreement Among Load Serving Entities in the PJM Region. See \nAppendix for tariff records accepted in this order. \n3  Capitalized terms used but not otherwise defined in this order have the meanings \nascribed to them in the Tariff. \n4  PJM defines BTMG as \"a generation unit that delivers energy to load without \nusing the Transmission System or any distribution facilities (unless the entity that owns \nor leases the distribution facilities has consented to such use of the distribution facilities \nand such consent has been demonstrated to the satisfaction of the Office of the \nInterconnection); provided, however, that [BTMG] does not include: (i) at any time, any \nportion of such generating unit's capacity that is designated as a Generation Capacity \nResource; or (ii) in an hour, any portion of the output of such generating unit that is sold \nto another entity for consumption at another electrical location or into the PJM \nInterchange Energy Market.\" PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions — A-B \n(21.0.0) (defining BTMG). \n160 of 515"},{"page":162,"startToken":60446,"endToken":60871,"text":"Document Access igPs#: 4§)-2-VA18-349cument:Fl i l d ra@gp:jip/18/2pAte Filed. 10/16/2026 \nDocket No. EL25-49-002, et al. \n4 \n4.\nOn January 16, 2026, Exelon and FirstEnergy5  timely filed a request for rehearing \nof the December Order. On January 20, 2026, Industrials6  timely filed a request for \nclarification or, in the alternative, rehearing. On January 20, 2026, Constellation Energy \nGeneration, LLC (Constellation) filed a request for clarification or, in the alternative, \nrehearing. On January 20, 2026, PIOs7  filed a limited request for clarification. On \nJanuary 20, 2026, Joint Partiess  filed a request for clarification. On February 9, 2026, \nAndrew Hinz filed a late request for rehearing. \n5.\nOn February 23, 2026, in Docket No. ER26-1479-000, PJM filed its second \ncompliance filing as directed by the December Order. \n6.\nOn February 23, 2026, in Docket No. EL25-49-000, PJM and the Indicated TOs9 \neach submitted an initial brief to address the Commission's paper hearing questions with \n5  The request for rehearing was filed only by (1) Exelon Corporation (Exelon), on \nbehalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., \nDelmarva Power & Light Company, PECO Energy Company, and Potomac Electric \nPower Company; and (2) FirstEnergy Service Company, as agent for its affiliates \nAmerican Transmission Systems, Incorporated, Jersey Central Power & Light Company, \nMid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission \nCompany, The Potomac Edison Company, Monongahela Power Company and \nTrans-Allegheny Interstate Line Company (collectively, FirstEnergy). \n6  As to the request for clarification or, in the alternative, rehearing, Industrials are \nthe PJM Industrial Customer Coalition (PJM ICC) and the Industrial Energy Consumers \nof America (IECA). \nAs to the request for clarification, PIOs are EarthJustice, Environmental Defense \nFund, and Sierra Club. \n8  As to the request for clarification, Joint Parties are Eolian LP, Antora Energy \nLLC, and Verrus LLC. \n9  We refer to the Indicated PJM Transmission Owners that submitted briefing \njointly in the paper hearing as Indicated TOs. The transmission owners that submitted \nbriefing jointly in the paper hearing are: American Electric Power Service Corporation \non behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power \nCompany, Kentucky Power Company, Kingsport Power Company, Ohio Power \nCompany, Wheeling Power Company, AEP Appalachian Transmission Company, AEP \nIndiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP \nOhio Transmission Company, and AEP West Virginia Transmission Company; The \nDayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on \nbehalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke \n161 of 515"},{"page":163,"startToken":60871,"endToken":61289,"text":"Document AccessigPA 412-Vbq18-3129..Cument:FlAd rFa'qg9:6166A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 5 \nrespect to the new transmission services. On March 25, 2026, and on April 24, 2026, \nparties submitted response briefs and reply briefs, respectively. \n7.\nIn this order, we address the requests for rehearing and clarification of the \nDecember Order, PJM's compliance filing, and the paper hearing on the new \ntransmission services. Pursuant to Allegheny Defense Project v. FERC,1°  the rehearing \nrequests filed in this proceeding may be deemed denied by operation of law. However, \nas permitted by section 313(a) of the FPA,11  we are modifying the discussion in the \nDecember Order and setting aside the order, in part, as discussed below.12  In addition, \nwe are granting, in part, and denying, in part, the requests for clarification. \n8.\nNext, we find that PJM's compliance filing partially complies with the directives \nof the December Order. As such, we accept in part and reject in part PJM's proposed \nTariff revisions, and we direct PJM to file, within 60 days of the date of issuance of this \norder, a further compliance filing. \n9.\nFinally, in response to the record developed in the paper hearing, we establish as \njust and reasonable certain rates, terms, and conditions for the new transmission services \ndirected in the December Order (i.e., Interim NITS, FCD transmission service, and \nNFCD transmission service). We direct PJM to file, within 60 days of the date of \nissuance of this order, a compliance filing to revise its Tariff. We also direct the PJM \ntransmission owners to file, within 60 days of the date of issuance of this order, a \ncompliance filing to revise the Tariff. \nEnergy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, \nInc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon; FirstEnergy; \nPPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland \nElectric Company; and the Southern Maryland Electric Cooperative. \n10  964 F.3d 1 (D.C. Cir. 2020) (en bane). \n11  16 U.S.C. § 8251(a) (\"Until the record in a proceeding shall have been filed in a \ncourt of appeals, as provided in subsection (b), the Commission may at any time, upon \nreasonable notice and in such manner as it shall deem proper, modify or set aside, in \nwhole or in part, any finding or order made or issued by it under the provisions of this \nchapter.\"). \n12  Allegheny Def. Project, 964 F.3d at 16-17. \n162 of 515"},{"page":164,"startToken":61289,"endToken":61468,"text":"Document AccessigPSA 2q-Aggl.8-34@cument:Flild rEN9:61p,A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n6 \nContents \nI. \nBackground \n- 9 -\nA.\nFebruary Order \n- 9 -\nB.\nDecember Order \n- 11 -\nII. \nNotice of Filings and Responsive Pleadings \n- 14 -\nA.\nPJM's Compliance Filing \n- 14 -\nB.\nPaper Hearing on New Transmission Services \n- 15 -\nIII. \nProcedural Matters \n- 16 -\nIV. \nRequests for Rehearing and/or Clarification \n- 18 -\nA. \nJurisdiction \n- 19 -\n1. Sales for Resale in Interstate Commerce \n- 19 -\n2.\nRetail Allocation of Commission-Jurisdictional Rates \n- 20 -\n3.\nRetail BTMG \n- 22 -\n4.\nRetail Backup Service \n- 24 -\nB. \nShow Cause Findings \n- 26 -\n1. Overview, Transmission Service, Regulation and Black Start \n- 26 -\n2.\nRetail BTMG Netting Rules \n- 41 -\n3.\nTransmission Service Options for BTMG \n- 50 -\nC. \nReplacement Rate \n- 52 -\n1. Transmission Services \n- 52 -\n2. Necessary Study Process for Existing Interconnection Customers \n- 87 -\n3. New Generators Serving Co-Located Load \n- 95 -\nD. \nInformational Report \n- 97 -\n1. December Order \n- 97 -\n2.\nRequest for Clarification \n- 98 -\n3.\nDetermination \n- 99 -\nV. \nCompliance \n- 99 -\nA. \nBTMG Rules \n- 99 -\n1. Materiality Threshold \n- 99 -\n2.\nGrandfathering and Transition Period \n 116 - \n163 of 515"},{"page":165,"startToken":61468,"endToken":61641,"text":"Doeument Accessigi Sg 4q-Aq.A18-349..cument:Flil d rpa g9:610/1 8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n7 \n3. QFs and Cogeneration Facilities \n- 121 -\nB. \nTransmission Service \n- 127 -\n1. December Order \n- 127 -\n2. PJM Compliance Filing \n- 129 -\n3.\nPleadings \n- 130 -\n4.\nAnswers \n- 131 -\n5. Determination \n- 132 -\nC. \nNecessary Studies \n- 135 -\n1. December Order \n- 135 -\n2.\nPJM Compliance Filing \n- 136 -\n3.\nPleadings \n- 136 -\n4.\nDetermination \n- 139 -\nD. \nOther \n- 143 -\n1. December Order \n- 143 -\n2.\nRIM Compliance Filing \n- 144 -\n3. Pleadings \n- 147 -\n4.\nAnswers \n- 150 -\n5. Determination \n- 150 -\nE. \nEffective Date \n- 154 -\n1. PJM Compliance Filing \n- 154 -\n2.\nEffective Date Pleadings \n- 154 -\n3. Determination \n- 155 -\nVI. \nPaper Hearing \n- 155 -\nA. \nRates, Terms, and Conditions for Firm and Non-Firm Contract Demand \nTransmission Service \n- 156 -\n1. December Order \n- 156 -\n2. Nature of FCD and NFCD Transmission Services \n- 157 -\n3.\nStudy Process \n- 171 -\n4.\nRates and Charges \n- 179 -\n5.\nOther \n- 193 -\nB. \nAdditional Charge for Eligible Customers Taking FCD and/or NFCD \nTransmission Service \n- 199 -\n1. December Order \n- 199 - \n164 of 515"},{"page":166,"startToken":61641,"endToken":61810,"text":"Document AccessigPV; Z-Q2-VA18-3Q9cument],litd rfi'qg:066A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 8 - \n2.\nInitial Briefs \n- 200 -\n3.\nResponse Briefs \n- 201 -\n4.\nReply Briefs \n- 204 -\n5. Answers \n- 206 -\n6. Determination \n- 207 -\nC. \nInterconnection Requirements and Operational Practices for Necessary Control \nTechnologies and/or Protection Systems \n- 208 -\n1. Initial Briefs \n- 208 -\n2.\nResponse Briefs \n- 209 - \n3. Reply Briefs \n- 211 -\n4.\nAnswer \n- 214 -\n5. Determination \n- 214 -\nD. \nPenalty Charge or Other Remedial Action for New Transmission Services - 218 -\n1. Initial Briefs \n- 218 -\n2.\nResponse Briefs \n- 220 -\n3.\nReply Briefs \n- 223 -\n4.\nAnswer \n- 227 -\n5. Determination \n- 227 -\nE. \nAnti-Toggling Mechanisms for Firm Contract Demand Transmission Service ....-\n237 -\n1. Initial Briefs \n- 237 -\n2.\nResponse Briefs \n- 238 -\n3. Determination \n- 238 -\nF. \nCommunications, Alarm, SCADA, or Other Requirements \n- 240 -\n1. Initial Briefs \n- 240 -\n2.\nResponse Briefs \n- 240 -\n3. Determination \n- 240 -\nG. \nCurtailment Procedures for Interim NITS and Non-Firm Contract Demand \nTransmission Service \n- 241 -\n1. Initial Briefs \n- 241 -\n2.\nResponse Briefs \n- 242 -\n3.\nReply Briefs \n- 243 -\n4.\nAnswers \n- 244 - \n165 of 515"},{"page":167,"startToken":61810,"endToken":62026,"text":"Dodument AccessigIA: Z--2-136g18-341i)Cument:FlAd rpaqg:6156/q8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 9 \n5. Determination \n - 244 \nH. \nRates, Terms, and Conditions for Interim NITS \n - 246 \n1. Initial Briefs \n - 246 \n2. Response Briefs \n - 247 \n3. Reply Briefs \n - 250 \n4. Answers \n - 251 \n5. Determination \n - 252 \nI. \nAnnual Report on New Transmission Services \n - 256 \nJ. Proposed Effective Date \n - 258 \n1. Initial Briefs \n - 258 \n2. Response Briefs \n - 259 \n3. Reply Briefs \n - 262 \n4. Answer \n - 264 \n5. Determination \n - 264 \nK. \nAdditional Arguments \n - 265 \n1. Behind the Meter Generation \n - 265 \n2. Reliability Backstop Auction \n - 265 \n3. Eligible Customer Requirements \n - 267 \n4. Demand Side Pathways \n - 268 \n5. Interconnection \n - 269 \n6. Co-Location Arrangement with Electric Storage Resource \n - 270 \nI. \nBackground \nA. \nFebruary Order \n10. \nIn February 2025, the Commission instituted a new proceeding in Docket \nNo. EL25-49-000 to examine whether the Tariff remains just and reasonable and not \nunduly discriminatory or preferential without provisions addressing with sufficient clarity \nor consistency the rates, terms, and conditions of service that apply to co-location \narrangements.13  The February Order defined Co-Located Load as a \"'configuration [that] \nrefers to end-use customer load that is physically connected to the facilities of an existing \n13  PJM Interconnection, L.L. C., 190 FERC ¶ 61,115, at P 2 (2025) (February \nOrder). \n- \n166 of 515"},{"page":168,"startToken":62026,"endToken":62481,"text":"Document AccessigiqSg 22qAq18-3L2@curnent:Flita rFAil: c166A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 10 - \nor planned Customer Facility on the Interconnection Customer's side of the Point of \nInterconnection to the PJM Transmission System.'\"14  As in the February Order, when \nreferring to both the Co-Located Load and the associated generator, we will use the term \nCo-Location Arrangement. \n11. \nAs explained in the February Order, Co-Location Arrangements are becoming \nincreasingly common in PJM and, since the issuance of the February Order, entities \ncontinue to raise issues involving Co-Location Arrangements with the Commission.15 \nThe Commission set forth, in the February Order, the principles relating to the \nCommission's jurisdiction over the matters relevant to Co-Location Arrangements.16  The \nCommission also made several preliminary findings about the justness and \nreasonableness of the Tariff. First, the Commission found that the Tariff appears to be \nunjust and unreasonable or unduly discriminatory or preferential because it does not \ncontain provisions addressing with sufficient clarity or consistency the rates, terms, and \n14  Id. P 3 & n.4. We note that, in the February Order, the Commission adopted \nthis definition from the Guidance Document that PJM developed on Co-Located Load. \nSee id. PJM rescinded this document pending Commission guidance in this docket. PJM \nMarch 24, 2025 Response at 33. Prior to PJM's transition to its new interconnection \nprocess, PJM used the terms Interconnection Customer and Generation Interconnection \nCustomer. The Tariff defines Generation Interconnection Customer as \"an entity that \nsubmits an Interconnection Request to interconnect a new generation facility or to \nincrease the capacity of an existing generation facility interconnected with \nthe Transmission System in the PJM Region.\" PJM, Intra-PJM Tariffs, OATT, § I.1 \nDefinitions - G - H) (9.0.1) (defining Generation Interconnection Customer). The \nTariff's new rules for generation interconnection, effective January 3, 2023, utilize the \nterms Project Developer and Generation Project Developer. The Tariff defines \nGeneration Project Developer as \"an entity that submits a Generation Interconnection \nRequest to interconnect a new generation facility or to increase the capacity of an existing \ngeneration facility interconnected with the Transmission System in the PJM Region.\" \nPJM, Intra-PJM Tariffs, OATT, § VIII subpt. A 400 (Definitions G) (0.1.0) (defining \nGeneration Project Developer). For simplicity, in this order, and consistent with the \nFebruary Order and December Order, the Commission will use the term Interconnection \nCustomer to refer to both the Tariff definitions of Generation Interconnection Customer \nand Generation Project Developer. \n15  See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,112 (2025) (accepting \nnecessary studies agreement). The February Order consolidated the new show cause \nproceeding with a pending complaint proceeding in Docket No. EL25-20-000 involving \nCo-Located Load. \n16  February Order, 190 FERC ¶ 61,115 at P 66. \n167 of 515"},{"page":169,"startToken":62481,"endToken":62845,"text":"Document AccessigPA qq2-136A18-3R9.cument:FlAd rpAg9:6166/818/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 11 - \nconditions of service that apply to Co-Location Arrangements.\" In addition, the \nCommission preliminarily found that this lack of applicable Tariff provisions raises the \npotential for undue discrimination or preferential treatment.18 \n12.\nAs to specific concerns raised regarding Co-Location Arrangements, the \nCommission found that the Tariff may be unjust, unreasonable, unduly discriminatory, or \npreferential because it does not specify the transmission service that Co-Location \nArrangements must take, if any, or otherwise provide a process to ensure that \nCo-Location Arrangements are paying for the benefits they receive from the transmission \nsystem consistent with cost causation principles, which provide that all \nCommission-jurisdictional rates and charges must \"reflect to some degree the costs \nactually caused by the customer who must pay for them,\" and that costs must be allocated \nin a manner that is at least roughly commensurate with the benefits that entity receives.19 \nThe Commission also found that the absence of rates, terms, and conditions of \ninterconnection service specific to Co-Location Arrangements, and, especially regarding \nstudies of the impacts of those arrangements, may render the Tariff unjust and \nunreasonable or unduly discriminatory or preferentia1.2°  Moreover, the Commission \nfound that the absence of rates, terms, and conditions governing the use and sale of \nancillary services and black start services by Co-Location Arrangements may render the \nTariff unjust and unreasonable or unduly discriminatory or preferentia1.21  The \nCommission directed briefing to build a record on these issues as well as a possible \nreplacement rate. \nB. \nDecember Order \n13.\nIn the December Order, the Commission found the Tariff unjust and unreasonable \nbecause it does not contain provisions addressing with sufficient clarity or consistency \nthe rates, terms, and conditions of service that apply to Interconnection Customers \nserving Co-Located Load and Eligible Customers taking transmission service on behalf \n17  Id. P 74. \n18  Id. P 75. \n19  Id. PP 74-78 (citing Midwest ISO Transmission Owners v. FERC, 373 F.3d \n1361, 1368 (D.C. Cir. 2004); Ill. Corn. Comm'n v. FERC, 576 F.3d 470, 476 (7th Cir. \n2009)). \n28  Id. P 79. \n21  Id. P 82. \n168 of 515"},{"page":170,"startToken":62845,"endToken":63236,"text":"Document AccessigPsp,: Z-§,-2yA18 _3Qpcument:Flil d rg'qg: JR 8/ 2  pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 12 - \nof Co-Located Load.22  The Commission explained that the absence of such provisions \nleaves entities unable to determine what steps they must take to effectuate Co-Location \nArrangements and creates uncertainty that has resulted in disparate treatment in PJM \nbecause transmission owners have taken different approaches to performing the necessary \nsteps that apply to Interconnection Customers seeking to serve Co-Located Load through \na Co-Location Arrangement.23  The Commission found that the absence of such \nprovisions also introduces the risk that Co-Located Load may benefit from regulation and \nblack start services without contributing to cost recovery for such services.24 \n14.\nSpecifically, the Commission found the Tariff unjust and unreasonable because \nthere is a lack of sufficient clarity or consistency as to the rates, terms, and conditions of \nservice that apply to Interconnection Customers serving Co-Located Load.25  As part of \nthe replacement rate, the Commission directed PJM to file revisions to the generation \ninterconnection procedures of the Tariff, including to require an Interconnection \nCustomer who will use its generator to serve Co-Located Load to specify an Eligible \nCustomer who will take transmission service on behalf of the Co-Located Load, and \nrevisions to clarify its Necessary Study process.26  The Commission also directed PJM to \nrevise its Tariff to clarify that an Interconnection Customer seeking to serve a \nCo-Located Load with a newly interconnecting generator may: (1) request \ninterconnection service at a level below its maximum facility output; (2) use existing \nprocedures in the Tariff to accelerate the study of the interconnection service request if \nthe request has no cost allocation for Network Upgrades and does not require further \nstudies; (3) request provisional interconnection service; and (4) request Surplus \nInterconnection Service.27 \n15.\nThe Commission also found the Tariff unjust and unreasonable because it does not \ninclude transmission services that reflect Eligible Customers taking service on behalf of \nCo-Located Loads that are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.28  The Commission further found the Tariff \n22  December Order, 193 FERC ¶ 61,217 at P 175. \n23  Id \n24 Id \n25 Id. P 176. \n26  Id. PP 176, 187-192, 225-230. \n27  Id. PP 176, 231-235. \n28  Id. PP 177, 193. \n169 of 515"},{"page":171,"startToken":63236,"endToken":63658,"text":"Dod'uthent Accesgig- STerc Z-Q- gg1 8 - 34gcurnent:Flita \n6l67/C18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 13 - \nunjust and unreasonable because it does not address charges related to Co-Located \nLoads' use of regulation and black start services, which introduces the risk that \nCo-Located Load may benefit from regulation and black start services without \ncontributing to cost recovery for such services and, thereby, the risk that costs may be \nallocated entirely to other transmission customers and passed through to residential \ncustomers, among others.29  The Commission found that NITS charged on a gross \ndemand basis is one just and reasonable transmission service option for Eligible \nCustomers taking transmission service on behalf of Co-Located Loads, but it is not the \nonly option.30  The Commission thus directed PJM to revise its Tariff to create three new \ntransmission services (i.e., Interim NITS, FCD transmission service, and NFCD \ntransmission service) that reflect that Eligible Customers taking service on behalf of \nCo-Located Loads are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.31  Specific to these new transmission \nservices, the Commission established paper hearing procedures to determine the just and \nreasonable rates, terms, and conditions for such services.32 \n16. \nThe Commission also found the existing retail BTMG netting rules in the Tariff to \nbe unjust and unreasonable. PJM's existing Tariff allows load serving entities (LSE) that \nprovide service to loads with qualifying BTMG to reduce their costs by netting output \nfrom BTMG in the calculation of their peak demand for the purpose of determining NITS \ncharges.33  The Commission explained that these retail BTMG netting rules may lead to \nboth reliability and resource adequacy risks because PJM, per its Tariff, is obligated to \nserve transmission customers using BTMG but does not consider such customers' full \ngross load in transmission and resource adequacy planning.34  Thus, the Commission \ndirected PJM to revise its retail BTMG netting rules.35  In recognizing concerns about the \npotential impacts on existing BTMG customers, the Commission directed PJM to \nmaintain the current retail BTMG netting rules for customers that fall below a new MW \nmateriality threshold for the amount of load at a particular electrical location that \nNetwork Customers may net using BTMG and to implement a two-part transition process \n29  Id. P 177. \n3°  Id. PP 195-196. \n31  Id. PP 178, 200-202, 206, 208-218. \n32  Id. PP 178, 194, 203, 207, 219. \n33  Id. P 7. \n34  Id PP 179, 186. \n35  Id. PP 179, 221. \n170 of 515"},{"page":172,"startToken":63658,"endToken":64039,"text":"Document AccessigaV; 22Q-2-VIZ18-31;6ument:Flil d rEN9: W/11812PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 14 - \nfor retail BTMG including: (1) the establishment of a three-year transition period; and \n(2) the ability to grandfather certain entities with existing contracts.36 \nII. \nNotice of Filings and Responsive Pleadings  \nA. \nPJM's Compliance Filing \n17.\nNotice of PJM's compliance filing in Docket No. ER26-1479-000 was published \nin the Federal Register, 91 Fed. Reg. 9849 (Feb. 27, 2026) with interventions and \nprotests due on or before March 16, 2026. \n18.\nTimely motions to intervene were filed by American Forest & Paper Association \n(AF&PA); PJM Industrial Customer Coalition (PJM ICC); Industrial Energy Consumers \nof America (IECA); Monitoring Analytics, LLC, acting in its capacity as the Independent \nMarket Monitor for PJM (Market Monitor); LS Power Development, LLC; Enchanted \nRock, LLC (Enchanted Rock); Illinois Municipal Electric Agency; American Clean \nPower Association; New Jersey Division of Rate Counsel; PJM Power Providers Group; \nAmerican Electric Power Service Corporation; Exelon Corporation; Constellation Energy \nGeneration, LLC (Constellation); Public Citizen, Inc.; East Kentucky Power Cooperative, \nInc.; Clean Energy Buyers Association; Edison Electric Institute; Maryland Office of \nPeople's Counsel (Maryland OPC); EDF Power Solutions, Inc. (EDFps); Solar Energy \nIndustries Association (SEIA); Advanced Energy United (AEU); Buckeye Power, Inc.; \nElectric Power Supply Association; Duquesne Light Company; North Carolina Electric \nMembership Corporation; New Jersey Board of Public Utilities; Appalachian Voices; \nPennsylvania Office of Consumer Advocate; Public Service Electric and Gas Company, \nPSEG Power LLC and PSEG Energy Resources & Trade LLC (collectively, PSEG \nCompanies); Old Dominion Electric Cooperative (ODEC); National Railroad Passenger \nCorporation (Amtrak); Dominion Energy Services, Inc.; Crusoe Energy Systems, Inc. \n(Crusoe); Consolidated Edison Company of New York, Inc.; PPL Electric Utilities \nCorporation (PPL); Rockland Electric Company; Illinois Industrial Energy Consumers; \nAmerican Municipal Power, Inc. (AMP); Grid Reform; Invenergy Renewables LLC and \nInvenergy Thermal LLC (Invenergy); Data Center Coalition (DCC); Eastman Chemical \nCompany (Eastman); Northern Virginia Electric Cooperative, Inc. (NOVEC); Vistra \nCorp. (Vistra); Mainspring Energy; Northeastern REMC; Borough of Chambersburg, \nPennsylvania; Capital Power Corporation; Eolian, L.P. (Eolian); Antora Energy, Inc. \n(Antora); Calibrant Energy (Calibrant); Convergent Energy and Power (Convergent); and \nVerrus, LLC (Verrus). \n19.\nMotions to intervene out of time were filed by Arkon Energy Hannibal and Office \nof the Illinois Attorney General. \n36  Id PP 179, 221, 223-224. \n171 of 515"},{"page":173,"startToken":64039,"endToken":64531,"text":"Document Acces s igi?it; 22QT2-V.A18 - 3Q9ument:Flit d rpAgp: c;l67A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 15 - \n20.\nTimely comments and/or protests were filed by Eastman; EDFps; Digital Power \nNetwork; Vistra; Maryland OPC; AEU/SEIA; Eolian, Antora, Calibrant, Convergent, \nMainspring, and Venus (together, Joint Parties); Calibrant, Antora, Convergent, Eolian, \nand Mainspring (together, BTMG Parties); Invenergy; Energy Artisans, LLC (Energy \nArtisans); DCC; PJM ICC, IECA, AF&PA (collectively, Industrials) and Amtrak \n(Industrials/Amtrak); Digital Power Network; Crusoe; AMP; Appalachian Voices; and \nConstellation. \n21.\nOn April 8, 2026, Constellation filed a motion for leave and supplemental protest \nin this compliance proceeding and in Docket No. ER26-1088-000. On April 14, 2026, \nExelon filed an answer to Constellation's motion. On April 24, 2026, Indicated TOs filed \na motion for leave to answer and answer to certain protests and comments. On May 8, \n2026, the BTMG Parties and Industrials/Amtrak each filed a motion for leave to answer \nand answer the Indicated TOs' April 24 answer. On May 12, 2026, Eastman filed a \nmotion for leave to answer and answer the Indicated TOs' April 24 answer. On June 3, \n2026, Indicated TOs filed a motion for leave to answer and answer. \n22.\nSeveral parties filed briefs for the paper hearing in Docket No. EL25-49-000 and \nfiled these submissions in this compliance proceeding as well. Specifically, in this \ncompliance proceeding: on March 25, 2026, Enchanted Rock filed its reply brief; on \nMarch 26, 2026, Alliance to Save Energy filed comments; and on April 24, 2026, \nEarthjustice filed its reply brief \nB. \nPaper Hearing on New Transmission Services \n23.\nOn February 23, 2026, in Docket No. EL25-49-000, PJM and Indicated TOs each \nsubmitted an initial brief On March 25, 2026, response briefs were submitted by: \nMarket Monitor; Geronimo Power, LLC; AEU/SEIA; Constellation; Eolian, Antora, \nCalibrant, Convergent, Mainspring, Venus, and U.S. Energy Storage Coalition \n(collectively, Joint Co-Location Developers); Vistra; ODEC; Enchanted Rock; Indicated \nTOs; Industrials/Amtrak; NOVEC; DCC; and Alliance to Save Energy (Alliance). On \nApril 24, 2026, reply briefs were submitted by: Earthjustice; ODEC; PJM; Maryland \nOPC; Constellation; Indicated TOs; Joint Co-Location Developers; and \nIndustrials/Amtrak. On May 7, 2026, Enchanted Rock filed a motion for leave to answer \nand answer to PJM's reply brief On May 11, 2026, Constellation filed a motion for \nleave to answer and answer to PJM's and Indicated TOs' reply briefs. On May 21, 2026, \nGeronimo Power filed a motion for leave to answer and answer to PJM's and Indicated \nTOs' reply briefs. On May 28, 2026, Indicated TOs filed a motion for leave to answer \nand answer to various reply briefs and Constellation's May 11 answer. \n24.\nOn December 29, 2025, American Clean Power Association filed a motion to \nintervene out of time in this proceeding. On January 12, 2026, Vitol, Inc. filed a motion \nto intervene out of time in this proceeding. On January 13, 2026, Pennsylvania Office of \n172 of 515"},{"page":174,"startToken":64531,"endToken":64995,"text":"Document AccessigPV; Z-qAq18-31:?Kument:Flild \ne: j67A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 16 - \nConsumer Advocate filed a motion to intervene out of time in this proceeding. On \nJanuary 16, 2026, Voltus, Inc. filed a motion to intervene out of time in this proceeding. \nOn January 16, 2026, Emerald AI submitted comments out-of-time in Docket \nNo. EL25-49-000. On January 26, 2026, Andrew D. Hinz filed a motion to intervene out \nof time and comments. On March 20, 2026, Amtrak and AF&PA each filed a motion to \nintervene out of time in this proceeding. On March 25, 2026, Calibrant, Convergent, \nVenus, and U.S. Energy Storage Coalition filed a motion to intervene out of time in this \nproceeding. \nIII. \nProcedural Matters \n25.\nPursuant to Rule 214 of the Commission's Rules of Practice and Procedure, \n18 C.F.R. § 385.214 (2025), the notices of intervention and timely, unopposed motions to \nintervene in Docket Nos. ER26-1479-000 and EL25-49-000 serve to make the entities \nthat filed them parties to these proceedings. \n26.\nPursuant to Rule 214(d) of the Commission's Rules of Practice and Procedure, \n18 C.F.R. § 385.214(d), we grant the late-filed motions to intervene in Docket \nNos. ER26-1479-000 and EL25-49-000 given these entities' interests in the proceedings, \nthe early stage of the proceedings, and the absence of undue prejudice or delay. \nInterventions in Docket No. EL25-49-000 are prospective only and such entities may not \nchallenge the December Order. \n27.\nWe note that Venus did not intervene until after the December Order. When, as \nhere, late intervention is sought after the issuance of a dispositive order, the prejudice to \nother parties and burden upon the Commission of granting the late intervention may be \nsubstantial. Thus, movants bear a higher burden to demonstrate good cause for granting \nsuch late intervention.37  Venus indicates the proceeding has changed significantly with \nthe initiation of the paper hearing proceeding.38  We do not find this explanation to be \nsufficient to meet the higher burden to show good cause for granting intervention \nfollowing a dispositive order. As discussed above, we grant Venus's motion to intervene \nas-of the filing date (March 25, 2026); however, we dismiss it to the extent Venus joins \nEolian and Antora in the request for clarification of the December Order.39 \n37  PJM Interconnection, L.L.C., 167 FERC ¶ 61,209, at P 24 (2019); PJM \nInterconnection, L.L.C., 157 FERC ¶ 61,193, at P 10 (2016). \n38  Reply Brief of Joint Co-Location Developers and Motion to Intervene \nOut-of-Tome of Calibrant, Convergent, U.S. Energy Storage Coalition, and Venus at 6. \n39  PJM Interconnection, L.L.C., 157 FERC ¶ 61,193 at P 10; Pac. Gas & Elec. \nCo., 100 FERC ¶ 61,097, at P 5 (2002). \n173 of 515"},{"page":175,"startToken":64995,"endToken":65418,"text":"Dodument AccessigissA: qq-Aggis _3ppcument:FlAd EpAg9:616748/2p-Ate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 17 - \n28.\nRule 213(a)(2) of the Commission's Rules of Practice and Procedure, 18 C.F.R. \n§ 385.213(a)(2) (2025), prohibits an answer to a protest or answer unless otherwise \nordered by the decisional authority. We accept the answers submitted in Docket Nos. \nEL25-49-000 and in ER26-1479-000, as well as Constellation's supplemental protest, \nbecause they have provided information that assisted us in our decision-making process. \n29.\nOn February 2, 2026, Constellation filed a motion for leave and answer to Exelon \nand FirstEnergy's request for rehearing. On February 12, 2026, Exelon and FirstEnergy \nfiled an answer in opposition to that motion. On February 19, 2026, the Pennsylvania \nOffice of Consumer Advocate filed a motion for leave to answer and answer in support of \nIndustrials' request for clarification or rehearing.40  On February 5 and March 9, 2026, \nrespectively, Market Monitor and PJM filed answers and motions for leave to answer \nConstellation's request for clarification or rehearing. On February 20 and March 24, \n2026, Constellation filed motions for leave and answers to, respectively, Market \nMonitor's and PJM's answers. Rule 713(d) of the Commission's Rules of Practice and \nProcedure41  prohibits an answer to a request for rehearing.42  Accordingly, we deny these \nmotions and we reject these answers filed by Constellation, Exelon and FirstEnergy, \nPennsylvania Office of Consumer Advocate, Market Monitor, and PJM.43 \n30.\nOn February 9, 2026, Andrew Hinz filed a request for rehearing. Pursuant to \nsection 313(a) of the FPA,44  an aggrieved party must file an application for rehearing \nwithin 30 days after the issuance of the Commission's order; in this case, that deadline is \n40  Pennsylvania Office of Consumer Advocate is not a party to this proceeding \nwith respect to rehearing or clarification of the December Order and therefore may not \nfile an answer to a request for rehearing or clarification. \n41  18 C.F.R. § 385.713(d)(1) (2025). \n42  Id \n43  We note that the Pennsylvania Office of Consumer Advocate's, Market \nMonitor's, and PJM's motions and answers responded to requests for clarification and, in \nthe alternative, rehearing. Because the Commission has discretion in how to characterize \npleadings and examines the substance of pleadings, we construe these pleadings as \nultimately functioning in substance to respond to requests for rehearing and thus treat \nthem as such. Sw. Power Pool, Inc., 182 FERC ¶ 61,083, at P 14 (2023). \n44  16 U.S.C. § 8251(a). \n174 of 515"},{"page":176,"startToken":65418,"endToken":65856,"text":"Document AccessigPSA:  Z%2YR18-3Q9cument:Flit d \nVA8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 18 - \nno later than 5:00 PM U.S. Eastern Time45  on January 19, 2026. Because the 30-day \nrehearing deadline is a statutory requirement, it cannot be waived or extended.\" \nTherefore, we reject Andrew Hinz's request for rehearing as untimely. \nIV. \nRequests for Rehearing and/or Clarification \n31.\nAs discussed further below, we sustain our finding that the Tariff is unjust and \nunreasonable because it does not contain provisions addressing with sufficient clarity or \nconsistency the rates, terms, and conditions of service that apply to Interconnection \nCustomers serving Co-Located Load and Eligible Customers taking transmission service \non behalf of Co-Located Load.47  We also sustain our finding that the Tariff is unjust and \nunreasonable because it does not include transmission services that reflect the willingness \nand ability of an Eligible Customer taking service on behalf of a Co-Located Load to \nlimit its energy withdrawals from the transmission system under certain conditions.48  As \na replacement rate, we continue to direct PJM to establish the new transmission services \ndiscussed in the December Order.\" \n32.\nWe also set aside, in part, the December Order; we find that requiring Eligible \nCustomers taking transmission service on behalf of load with BTMG to take NITS, \nwithout the option to instead take such alternative transmission services, would be unjust \nand unreasonable for the same reasons we made the same finding in the December Order \nwith respect to Eligible Customers taking transmission service on behalf of Co-Located \nLoad. As a replacement rate, we direct PJM to revise its Tariff to extend the new \ntransmission services to Eligible Customers taking service on behalf of load with BTMG. \n45  The Commission's regular business hours end at 5:00 p.m., U.S. Eastern Time. \n18 C.F.R. § 375.101(c) (2025); 18 C.F.R. § 385.2003(c) (2025); FERC, eFiling User \nGuide (May 23, 2024), https://wwvv.ferc.gov/media/efiling-user-guide. \n46  See, e.g., City of Campbell v. FERC, 770 F.2d 1180, 1183 (D.C. Cir. 1985) \n(\"The 30-day time requirement of the [FPA] is as much a part of the jurisdictional \nthreshold as the mandate to file for a rehearing.\"); Bos. Gas Co. v. FERC, 575 F.2d 975, \n977-98, 979 (1st Cir. 1978) (describing identical rehearing provision of Natural Gas Act \nas \"a tightly structured and formal provision\" and holding that \"[n]either the Commission \nor the courts are given any form of jurisdictional discretion\"). \n47  December Order, 193 FERC ¶ 61,217 at P 159. \n48 Id  \n49  Id. P 160. \n175 of 515"},{"page":177,"startToken":65856,"endToken":66192,"text":"Document AccessigPsg q-Q,-23„eR18 _31_299ument:FlAd  yaqg9: 6167/6.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 19 - \n33. \nWe also continue to find that PJM's retail BTMG netting rules are unjust and \nunreasonable.5°  We continue to direct PJM to revise the Tariff's retail BTMG netting \nrules.51  We also set aside, in part, the December Order; we find that it is just and \nreasonable to allow certain cogeneration Qualifying Facilities (QFs) that are Network \nCustomers to be able to net by using BTMG, without being subject to the new materiality \nthreshold, if they demonstrate that they are integrated with load such that, when their \ngenerating facility trips offline, the load follows. \n34. \nWe also continue to direct PJM to clarify its interconnection procedures and \nagreements to ensure that it is clear to both new and existing Interconnection Customers \nhow to interconnect in a Co-Location Arrangement.52 \nA. \nJurisdiction  \n1. \nSales for Resale in Interstate Commerce \na. \nDecember Order  \n35. \nIn the December Order, the Commission found that several aspects of Co-Location \nArrangements fall squarely within the jurisdiction of the states. In particular, the \nCommission affirmed that \"states have authority over their generation resource mix, \nincluding through their siting authority\" and further explained that \"[t]his authority \nmeans that which generating facilities are sited and allowed to serve Co-Located Load is \nalso a question of state law.\"53  In addition, the Commission \"decline[d] in this \nproceeding to comprehensively address jurisdictional matters regarding the \ninterconnection of retail loads served through a Co-Location Arrangement to the \ninterstate transmission system.\"54 \nb. \nRequest for Clarification and/or Rehearing \n36. \nConstellation requests that the Commission clarify that the Commission has \njurisdiction over the wholesale sale of energy by a generator to a retail supplier even if \nthe retail supplier then resells that energy to a Co-Located Load. Constellation states that \n5°  Id P 186. \n51  Id. PP 221-224. \n52  Id P 161. \n53  Id. P 169. \n54  Id. P 170. \n176 of 515"},{"page":178,"startToken":66192,"endToken":66590,"text":"Document A„eseigPsP; 2A,-.qqls-31?gcurnent:Flitd PeN9:j67A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 20 - \nthe December Order is unclear in that it states that \"states have authority over their \ngeneration resource mix, including through their siting authority\" and that \"which \ngenerating facilities are sited and allowed to serve Co-Located Load is also a question of \nstate law.\"55  Constellation explains that generators often do not serve Co-Located Load \ndirectly and instead sell electricity at wholesale to an entity, such as a retail supplier, that \nwill then engage in the ultimate retail sale to the Co-Located Load. In such \ncircumstances, Constellation argues that such sales for resale are exclusively within the \nCommission's jurisdiction.56 \nc. \nDetermination \n37.\nIn response to Constellation's request for clarification or rehearing, we reiterate \nthat, where a generator sells electricity at wholesale in interstate commerce to another \nentity that then resells that electricity at retail to a Co-Located Load, the generator's sale \nfor resale is exclusively within the Commission's jurisdiction.57  Thus, state authority \ndoes not extend to the wholesale sale of energy by a generator to a retail supplier, \nregardless of the specific type of ultimate retail customer. However, as the Commission \nexplained in the December Order, both \"which generating facilities are sited\" and which \ngenerating facilities are \"allowed to serve Co-Located Load\" are \"question[s] of state \nlaw.\"58 \n2. \nRetail Allocation of Commission-J urisdictional Rates \na. \nDecember Order \n38.\nIn the December Order, the Commission held that \"states have exclusive \njurisdiction over how the costs assigned to Eligible Customers on behalf of Co-Located \nLoad taking Commission-jurisdictional transmission services,\" including the new \ntransmission services, \"are allocated to individual retail consumers that are Co-Located \nLoad, just as states have exclusive jurisdiction over how to allocate the costs of all \n55  Constellation Request for Clarification or Rehearing at 6-7 (citing December \nOrder, 193 FERC ¶ 61,217 at P 169) (emphasis in original). \n56  Id. at 6-7 (citing 16 U.S.C. § 824(b)(1); Orangeburg v. FERC, 862 F.3d 1071, \n1086-87 (D.C. Cir. 2017)). \n57  Orangeburg, 862 F.3d at 1086-87 (\"FERC—not state commissions—has \n`exclusive authority to regulate the . . . sale at wholesale of electric energy in interstate \ncommerce.\") (quoting New Eng. Power Co. v. N.H., 455 U.S. 331, 340 (1982)). \n58  December Order, 193 FERC ¶ 61,217 at P 169. \n177 of 515"},{"page":179,"startToken":66590,"endToken":66972,"text":"Dod„„t \nA„„sigPSA\n: 22cfAQA18-3g9cUrnent:Fhtd rPAP:6167/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 21 - \nCommission-jurisdictional rates (including for energy, capacity, and transmission) among \nretail customers, including allocating costs among different classes of retail customers.\"59 \nb. \nRequest for Clarification and/or Rehearing \n39. \nConstellation requests that the Commission clarify that states do not have \nunlimited authority over how to allocate the costs of all Commission-jurisdictional rates \nand that they cannot use their authority over retail allocation to indirectly regulate the \ninterconnection of generators serving Co-Located Load.6°  For example, Constellation \nclaims that a state cannot impose via the exercise of its jurisdiction over retail sales a \nrequirement that attempts to prohibit a transaction that the Commission says is \npermitted.\" Constellation asserts that some utilities have asked their state commission \nfor authority to condition retail service in the state on the load's acceptance of a \nTransmission Security Agreement that calculates its security requirement based on a \ngross NITS rate despite the fact that the Commission has said that other rates must be \nmade available.62  Constellation argues that the December Order is unclear in that it \nprovides that \"states have exclusive jurisdiction over how to allocate the costs of all \nCommission-jurisdictional rates (including for energy, capacity, and transmission) among \nretail customers, including allocating costs among different classes of retail customers.\"63 \nc. \nDetermination \n40. \nIn response to Constellation's request, we deny clarification and sustain the \nDecember Order. In the December Order, the Commission appropriately explained that \n\"states have exclusive jurisdiction over how to allocate the costs of all \nCommission-jurisdictional rates (including for energy, capacity, and transmission) among \nretail customers, including allocating costs among different classes of retail customers.\"64 \nOn the other hand, we note that states \"may not seek to achieve ends, however legitimate, \nthrough regulatory means that intrude on FERC's authority over interstate wholesale \n59  Id. P 167. \n6°  Constellation Request for Clarification or Rehearing at 8 (citing Hughes v. Talen \nEnergy Mktg., LLC, 578 U.S. 150, 164-65 (2016); Nantahala Power & Light Co. v. \nThornburg, 476 U.S. 953, 966 (1986)). \n61  Id \n62  Id \n63  Id at 7 (citing December Order, 193 FERC ¶ 61,217 at P 167). \n64  December Order, 193 FERC ¶ 61,217 at P 167 (emphasis added). \n178 of 515"},{"page":180,"startToken":66972,"endToken":67297,"text":"Document AccessigPS# 2A.Ag18-34Pcument:Flald EPA P: J67/48/ 2p2 te Filed: 10/16/2026 \nDocket No. EL25,49-002, et al. \n- 22 - \nrates . . . .\"65  While Constellation frames its request around the jurisdictional findings in \nthe December Order, Constellation raises a specific matter that is not the subject of and is \notherwise outside the scope of this proceeding, i.e., the terms of transmission security \nagreements. We nonetheless reiterate that: (1) Eligible Customers taking transmission \nservice on behalf of Co-Located Load must have the option to take one of three \ntransmission services, i.e., NITS or Interim NITS, FCD transmission service, or NFCD \ntransmission service;66  and (2) while it remains just and reasonable for an Eligible \nCustomer taking transmission service on behalf of Co-Located Load to take NITS \ncharged on a gross demand basis,67  an Eligible Customer may instead choose to take \nanother transmission service.68 \n3. \nRetail BTMG \na. \nDecember Order \n41. \nIn the December Order, the Commission found that circumstances have changed \nsince the Commission approved PJM's retail BTMG netting rules such that these rules \nare no longer just and reasonable. In particular, the Commission found that PJM's \nexisting retail BTMG netting rules do not limit the amount of qualifying load that a \nNetwork Customer may net by using BTMG and do not provide any protections against \npotential transmission and resource adequacy planning problems or against the costs of \nmaintaining sufficient resources to serve these loads being shifted onto other customers.69 \nThe Commission concluded that PJM's retail BTMG netting rules are no longer \nconsistent with cost causation principles because large loads configured in a BTMG \narrangement with significant generation will raise cost-shifting concerns compared to \nloads pursuing smaller amounts of netting.70 \n65  Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164. \n66  December Order, 193 FERC ¶ 61,217 at P 193. \n67  M P 195. \n68  Id. P 199. \n69  Id. P 186. \n70  Id \n179 of 515"},{"page":181,"startToken":67297,"endToken":67598,"text":"Document AccessigPSP:: 2A-2.1,6A-18 _3Rgcument:Flit d rPa g9:6168/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 23 - \nb. \nRequest for Clarification and/or Rehearing \n42. \nIndustrials argue that the Commission failed to explain and justify its assertion of \njurisdiction over \"retail BTMG that merely offsets retail load.\"71  Industrials contend that \n\"retail BTMG [is not within] the Commission's jurisdiction over the transmission of \nelectric energy in interstate commerce\" because \"[b]y definition, BTMG is produced by a \ngeneration unit `that delivers energy to load without using the Transmission System.'\"72 \nIndustrials assert that the Commission's finding \"necessarily entails piercing the retail \nmeter veil, which serves as the bright-line boundary of the Commission's statutory \nauthority.\"73  Industrials further maintain that the Commission failed to provide a \nwell-reasoned basis for the assertion of jurisdiction over the configurations of retail \ncustomers whose BTMG is not selling wholesale power and is not using the transmission \nsystem.74  Industrials argue that, here, \"retail BTMG involves neither jurisdictional sales \nnor jurisdictional transmission.\"75 \nc. \nDetermination \n43. \nWe disagree with Industrials that the BTMG netting rules are outside of the \nCommission's jurisdiction. Industrials misunderstand the December Order as targeting \nretail sales from BTMG or the delivery of energy from BTMG to load, but this is not the \ncase. The BTMG netting rules instead allow PJM to calculate the charges for \n71  Industrials Request for Clarification or Rehearing at 39. \n72  Id at 40 (citing PJM, Intra-PJM Tariffs, OATT, § I.1 (Definitions — A-B) \n(22.0.0)). \n73  Id \n74  Id at 40-41 (citing Nat'l Ass 'n of Regul. Util. Comm'rs v. FERC, 475 F.3 d \n1277, 1280 (D.C. Cir. 2007); Detroit Edison Co. v. FERC, 334 F.3d 48, 53 (D.C. Cir. \n2003)). \n75  Id at 41-42. \n180 of 515"},{"page":182,"startToken":67598,"endToken":67986,"text":"Document A„e„igP\nSA \nAA41 -18-34P\nument:Flild rPaqiT: jp/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 24 - \ntransmission service in interstate commerce.76  The calculation of such transmission \ncharges is squarely within the Commission's jurisdiction under the FPA.77 \n4. \nRetail Backup Service  \na. \nDecember Order  \n44. \nIn the December Order, the Commission required that PJM modify its Tariff to \nrequire that an Eligible Customer taking transmission service on behalf of a Co-Located \nLoad take one of three transmission services: (1) NITS or Interim NITS; (2) FCD \ntransmission service; or (3) NFCD transmission service.78 \nb. \nRequest for Rehearing \n45. \nExelon and FirstEnergy contend that the Commission's new FCD and NFCD \ntransmission services infringe on state retail authority, asserting that the states, not the \nCommission, have jurisdiction to decide when and in what circumstances retail load will \nbe curtailed, and how utilities should charge and treat retail customers in those \ncircumstances.79  Exelon and FirstEnergy claim that, for example, states might require the \nprovision of backup service to retail customers who lost supply from their contracted \nsupplier, would regulate the distribution system costs associated with such service that \nwould be charged to the retail customer, and would regulate the costs and terms of the \nbackup service.80  Exelon and FirstEnergy assert that the Commission's order appears to \ncreate a new federal construct because it defines the extent and terms of backup service to \n76  PJM, Intra-PJM Tariffs, OATT, § III, § 34.2 (Netting of Behind the Meter \nGeneration) (0.0.0); see December Order, 193 FERC ¶ 61,217 at P 7 (\"[T]he Tariff \nallows load serving entities . . . that provide service to loads with qualifying BTMG to \nreduce their costs by netting output from BTMG in the calculation of their peak demand \nfor the purpose of determining NITS charges.\") (emphasis added). \n77  Orangeburg, 862 F.3d at 1086-87 (\"FERC—not state commissions—has \n`exclusive authority to regulate the transmission . . . of electric energy in interstate \ncommerce.\") (quoting New Eng. Power Co., 455 U.S. at 340); Calpine Corp. v. FERC, \n702 F.3d 41, 50 (D.C. Cir. 2012) (\"[T]he regulation of transmission charges is \nundoubtedly within FERC's jurisdiction . . . .\"). \n78  December Order, 193 FERC ¶ 61,217 at P 193. \n79  Exelon and FirstEnergy Request for Rehearing at 53. \n80 Id. \n181 of 515"},{"page":183,"startToken":67986,"endToken":68440,"text":"Document AccessigP.SP; qq'20§A18-3g€6Urnent:Filtd IPA.99:6168A8/2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 25 - \nretail customers who lose their contracted retail power supplier.8I  Exelon and \nFirstEnergy argue that the Commission's new transmission services lack the limitation in \nthe Commission's wholesale demand response programs, which allow states to prohibit \nretail consumers from participating in wholesale demand response.82 \nc. \nDetermination \n46. \nWe are not persuaded by Exelon and FirstEnergy's assertions that FCD and NFCD \ntransmission services infringe on state retail authority. In the December Order, the \nCommission held that Eligible Customers taking transmission service on behalf of a \nCo-Located Load must have the option to take one of three transmission services: \n(1) NITS or Interim NITS; (2) FCD transmission service; or (3) NFCD transmission \nservice.83  Exelon and FirstEnergy do not explain how FCD and NFCD transmission \nservices define the extent and terms of backup service to retail customers who lose their \ncontracted power supplier and cite no specific aspect of the December Order that does \nso.84  As such, we find that Exelon and FirstEnergy fail to demonstrate that the \nCommission's replacement rate regulates the terms of retail service.\" \n81  Id. at 53, 55. \n82  Id. at 54 (citing FERC v. EPSA, 577 U.S. 260, 275 (2016)). \n83  December Order, 193 FERC ¶ 61,217 at P 193. \n84  FPA section 313(a) requires that an \"application for rehearing shall set forth \nspecifically\" its grounds. 16 U.S.C. § 8251(a) (emphasis added). We follow Commission \npractice, with which courts have agreed, and reject arguments, like this one, on rehearing \nlacking sufficient specificity. PJM Interconnection, L.L.C., 171 FERC ¶ 61,040, at P 22 \n(2020); see also Ind. Util. Regul. Comm'n v. FERC, 668 F.3d 735, 736 (D.C. Cir. 2012); \nLA Storage, LLC, 182 FERC 1161,026, at P 25 & n.75 (2023). \n85  Exelon and FirstEnergy argue that the Commission's new transmission services \nlack the limitation in the Commission's wholesale demand response programs, which \nallows states to prohibit retail consumers from participating in wholesale demand \nresponse. Exelon and FirstEnergy Request for Rehearing at 54 (citing FERC v. EPSA, \n577 U.S. at 275). The considerations that led the Commission to include that \"opt-out\" in \nthe rulemakings that led to Order Nos. 719 and 745, such as a confluence of federal and \nstate jurisdiction with respect to demand response, are not present in this proceeding. \nMoreover, the Commission was not required to include the \"opt-out\" even in those \nrulemakings. See Nat'l Ass 'n of Regul. Util. Comm'rs v. FERC, 964 F.3d 1177, 1187 \n(D.C. Cir. 2020) (\"But because FERC has the exclusive authority to determine who may \n182 of 515"},{"page":184,"startToken":68440,"endToken":68783,"text":"Document AccessigPSK 2A-2-1§g18-349cument:Flild Ifai@v:d43A8, 2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 26 - \nB. \nShow Cause Findings  \n1. \nOverview, Transmission Service, Regulation and Black Start \na. \nDecember Order  \n47. \nAs relevant here, the Commission found in the December Order that the Tariff is \nunjust and unreasonable because it does not contain provisions addressing with sufficient \nclarity or consistency the rates, terms, and conditions of service that apply to \nInterconnection Customers serving Co-Located Load and Eligible Customers taking \ntransmission service on behalf of Co-Located Load. The Commission also found that the \nTariff is unjust and unreasonable because it does not include transmission services that \nreflect Eligible Customers taking service on behalf of Co-Located Loads that are willing \nand able to limit their energy withdrawals from the transmission system under certain \nconditions.86 \nb. \nRequest for Rehearing \n48.\nExelon and FirstEnergy argue that the Commission did not meet its burden under \nFPA section 206 to show that the existing PJM Tariff is unjust and unreasonable.87 \nExelon and FirstEnergy argue that the Commission provides no evidentiary support for \nits finding that the Tariff is unjust and unreasonable because it does not contain \nprovisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions of service that apply to Interconnection Customers serving Co-Located Load \nand Eligible Customers taking transmission service on behalf of Co-Located Load.88 \nExelon and FirstEnergy allege that the Tariff already has provisions explaining how to \nserve load in PJM and the Commission does not even mention them.89 \n49.\nExelon and FirstEnergy dispute that the Constellation Complaint supports the \nCommission's finding of uncertainty.90  Exelon and FirstEnergy contend that the actual \nparticipate in the wholesale markets, the Supremacy Clause—not Order No. 841—\nrequires that States not interfere.\"). \n86  December Order, 193 FERC ¶ 61,217 at P 177. \n87  Exelon and FirstEnergy Request for Rehearing at 13. \n88  Id. at 14 (citing December Order, 193 FERC 4561,217 at P 175). \n89  Id. at 15 (discussing and citing Tariff provisions). \n90  Id. \n183 of 515"},{"page":185,"startToken":68783,"endToken":69223,"text":"Document AccessigSP:: qqA,A18-3Q9cUlTlent:Filtd EPag9:6168/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 27 - \nsituation described in the Constellation Complaint giving rise to the purposed uncertainty \nrevealed that \"any delay resulted from a decision made by Constellation in its attempt to \nbypass retail service requirements and to obtain service in violation of Illinois law.\"91 \nExelon and FirstEnergy argue that, if any clarification was necessary, the Commission \nhas now clarified that Co-Location Arrangements must be properly metered and \ndesignate and involve transmission service to an Eligible Customer. Exelon and \nFirstEnergy allege that service can proceed in an orderly fashion. Exelon and \nFirstEnergy argue that the Commission ignored record evidence that customers' load \nservice requests proceed on a timely basis when customers take service through an \nEligible Customer.92  Exelon and FirstEnergy also maintain that Talen Energy's recent \nchanges to its Co-Location Arrangement with Susquehanna Nuclear, LLC show that the \nTariff works.93 \n50. \nExelon and FirstEnergy next challenge the Commission's finding that the Tariff is \nunjust and unreasonable because it does not include transmission services that reflect that \nan Eligible Customer taking service on behalf of a Co-Located Load that is willing and \nable to limit its energy withdrawals from the transmission system under certain \nconditions.94  Exelon and FirstEnergy allege that there is no evidence that the cost of \nNITS deters service or impacts data center development. Exelon and FirstEnergy also \nargue that there is no evidence to support the Commission's statement that requiring \nNITS could necessitate inefficient and costly transmission buildout and costs paid by \ntransmission customers that may not be necessary if Eligible Customers taking \ntransmission service on behalf of Co-Located Loads are willing to limit their energy \nwithdrawals and take a transmission service that requires fewer Network Upgrades.95 \nExelon and FirstEnergy maintain that charging load on a contract demand basis does not \nchange the physical and engineering impacts of the load.96  Exelon and FirstEnergy \nacknowledge that installing systems to limit grid usage might change system impacts and \nthe need for upgrades, but there is nothing in the record demonstrating that such systems \nare more beneficial for Co-Located Load than other loads or that such systems warrant \n91  Id. at 15-16 (citing Constellation, Docket No. EL25-20-000, Complaint, Ex. 5, \nattach. 1). \n92  Id at 17. \n93  Id. at 17-18 (citing PJM, Docket No. ER24-2172-000, Amended ISA, attach. A, \nSchedule F, Part F.4 (filed June 3, 2024)). \n94  Id. at 18 (citing December Order, 193 FERC ¶ 61,217 at P 159). \n95  Id. at 19 (citing December Order, 193 FERC ¶ 61,217 at P 199). \n96  Id. \n184 of 515"},{"page":186,"startToken":69223,"endToken":69665,"text":"Document Acce„ig@A i'211. 8 - 34@cument:Flita rPAP: c1448/2Date Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 28 - \nthe use of different ratemaking principles for Co-Located Load as compared to other \nloads.97  Exelon and FirstEnergy argue that system impacts may be reduced when a load \nis located near a generator, but that is true whether the load contracts with remote \ngeneration or an abutting generator. Exelon and FirstEnergy assert that the study process \ncan determine how to site to reduce transmission upgrades for the customer using the \ncustomer's gross load. \n51.\nExelon and FirstEnergy argue that the Commission provides no support for its \nstatement that Co-Located Loads may be able to receive transmission service faster with \nuse of a new, limited transmission service product than they would if they selected NITS, \nto the extent that providing NITS would require Network Upgrades that the limited \ntransmission service would not.98  Exelon and FirstEnergy assert that the transmission \nsystem is affected even when no net power is withdrawn from the system.99  Exelon and \nFirstEnergy contend that the Commission endorses an unsound approach by suggesting \nthat loads that do not withdraw from the system can be interconnected on a fast track \nwithout studying physical impacts. \n52.\nExelon and FirstEnergy highlight the Commission's statement that, while the \nCommission finds that NITS charged on a gross demand basis is one just and reasonable \ntransmission service option for Eligible Customer taking transmission service on behalf \nof Co-Located Loads, it is not the only option.100  Exelon and FirstEnergy state that the \nCommission itself acknowledges that the existing service options are feasible and just \nand reasonable, but the Commission merely wants more options. Exelon and FirstEnergy \nargue that when the Commission finds a tariff not unjust and unreasonable under the first \nprong of FPA section 206, as it suggests here, the Commission does not need to set a \nremedy. \n53.\nExelon and FirstEnergy disagree with the Commission's assessment that \nCo-Located Loads merit a different rate based on the combination of transmission system \nburdens and benefits. Exelon and FirstEnergy first state that Co-Located Loads benefit \nfrom regulation and black start, as the Commission recognized.10' Exelon and \nFirstEnergy argue that transmission interconnections provide an avenue for data center \nloads to readily acquire back-up power when co-located generators are not available. \n97  Id. at 19-20. \n98  Id at 20 (citing December Order, 193 FERC ¶ 61,217 at P 205). \n99  Id. at 21. \n100  Id at 22 (citing December Order, 193 FERC ¶ 61,217 at P 195). \n101 Id at 30 (citing December Order, 193 FERC ¶ 61,217 at PP 209, 219). \n185 of 515"},{"page":187,"startToken":69665,"endToken":70086,"text":"Document Acc„sicIPA: 2A-AQq18 -3Q9cUrnent:FlAd rPaqg?:6,168/618/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 29 - \nExelon and FirstEnergy argue that, based solely on these uses of the transmission system, \nCo-Located Loads have no greater claim to preferential rates than other similarly situated \ntransmission customers. Exelon and FirstEnergy argue that the Commission failed to \nconsider the many advantages to Co-Located Loads when they connect to the \ntransmission system. For example, Exelon and FirstEnergy assert that, if the project were \nislanded instead of grid connected, all back-up generation would sit idled when not \nneeded, forgoing significant revenues from selling surplus power into the wholesale \nmarket. Exelon and FirstEnergy also allege that it is very difficult to supply islanded \ngeneration with black start and regulation.m2 \n54.\nExelon and FirstEnergy argue that the Commission failed to respond to arguments \nabout the unique aspects of co-location with nuclear plants. Exelon and FirstEnergy state \nthat a nuclear facility must be interconnected to the grid as a Nuclear Regulatory \nCommission licensing obligation, and thus a Co-Location Arrangement with a nuclear \nunit depends on the grid.'03  Exelon and FirstEnergy assert that, in a Co-Location \nArrangement with a nuclear unit, Co-Located Load depends on services such as \nregulation, voltage support, black start, and other ancillary services delivered over the \ngrid all the time because nuclear units cannot provide these services.104 \nc. \nDetermination \n55.\nOn rehearing, we sustain the Commission's finding in the December Order that \nthe Tariff is unjust and unreasonable!\" First, we continue to find that the Tariff does not \ncontain provisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions of service that apply to Interconnection Customers serving Co-Located Load \n\" 2  Id at 31. \n103 Id at 32-33 (citing Exelon, Docket No. EL25-20-000, Comments, attach. 1, \n11-13, 16)). \n104  Id at 32 (citing Exelon, Docket No. EL25-20-000, Comments, attach. 1, \n¶¶ 14-19)). \n105 December Order, 193 FERC ¶ 61,217 at PP 175-177. As discussed in the \nDecember Order, we continue to find the Tariff also unjust and unreasonable in \nadditional related ways—for example, we continue to find that the Tariff is unjust and \nunreasonable because it does not address charges for black start and regulation service to \nEligible Customers taking transmission service on behalf of Co-Located Load. Id. P 159. \nWe do not interpret Exelon and FirstEnergy, however, to be disputing this finding. \nSeparate portions of this order address our findings in this proceeding that additional \naspects of the Tariff are unjust and unreasonable. \n186 of 515"},{"page":188,"startToken":70086,"endToken":70540,"text":"Document Accessig@g 2A'AqA1.8-3Q@cument:lita rFAV:6143A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 30 - \nand Eligible Customers taking transmission service on behalf of Co-Located Load.10' \nSecond, we continue to find that the Tariff does not include transmission services that \nreflect Eligible Customers taking service on behalf of Co-Located Loads that are willing \nand able to limit their energy withdrawals from the transmission system under certain \nconditions.107 \n56. \nSubstantial evidence supports the Commission's finding that the Tariff lacks \nsufficient clarity as to the rules governing Interconnection Customers serving Co-Located \nLoad and Eligible Customers taking transmission service on behalf of Co-Located \nLoad.108  There is significant support in the record for this finding.109  In particular, PJM \nrecognizes that its Tariff lacks sufficient clarity in this area!\" We also find persuasive \nthe comments in the record from a range of stakeholders reflecting the uncertainty facing \nentities seeking to effectuate Co-location Arrangements within PJM.111 \n1°6 Id P 175. \n1°71d. P 177. \n108  Id PP 175-176. \n1°9  Id. P 176 n.376. \n110 PJM March 24, 2025 Response at 32 (noting that its \"Tariff provisions d[o] not \ncontemplate the type of arrangements at issue in this docket\"); id at 35 (\"The extent to \nwhich netting [rules under the Tariff] could . . . apply to co-located data center load is not \nclear at this time.\"); see also Vistra April 23, 2025 Reply Comments at 11 (arguing that \nPJM has \"effectively conceded\" that the Tariff does not contain sufficient clarity). \n111  See Constellation May 8, 2025 Answer at 3-9 (collecting record support and \nconcluding \"[i]n sum, the record in this proceeding unequivocally supports the . . . \nfinding that the PJM Tariff lacks clear co-location rules\"); AEU April 23, 2025 Reply \nComments at 19 (\"Loads and generators pursuing [C]o-[L]ocation [A]rrangements need \nclarity as to how these arrangements will be studied, and how those studies will be \nevaluated. There must be a level of uniformity and detail outlining study requirements to \nensure regulatory certainty for large loads and new generation and storage resources \nseeking to serve large loads. This level of uniformity is currently lacking in PJM's \ninterconnection procedures and cost allocation methodology . . . .\"); Electric Power \nSupply Association (EPSA)/PJM Power Providers Group (P3) April 23, 2025 Reply \nComments at 2 (\"EPSA and P3 agree with the Commission that PJM needs to establish \ntariff provisions and rules to accommodate the array of [C]o-[L]ocated [L]oad \narrangements that will facilitate the timely and effective integration of large loads \nlocating in the region.\"); DCC April 23, 2025 Reply Comments at 7 (\".. . [T]he \nCommission should direct PJM to develop clear, enforceable tariff language that affirms \n187 of 515"},{"page":189,"startToken":70540,"endToken":70958,"text":"Document AccessigPSg qq-2.-VA-18-349cument:Flibd EPaggp: 6168A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 31 - \n57. \nFurther, there has been significant confusion and dispute over what rules govern \nCo-Location Arrangements in PJM. As the Commission found in the December Order, \nthe absence of clear tariff provisions creates uncertainty that has resulted in disparate \ntreatment of potential Co-Location Arrangements in PJM, where transmission owners \nhave taken different approaches to performing the necessary steps that apply to \nInterconnection Customers seeking to serve Co-Located Load through a Co-Location \nArrangement, leading to no consistent understanding of entities' responsibilities with \nrespect to their planned Co-Location Arrangements.112  Further, in 2024, PJM developed \na now-rescinded \"Guidance Document,\" which included non-binding guidance for \ngenerators and loads seeking to enter into Co-Location Arrangements\"3—further \nsuggesting that PJM's existing Tariff did not provide sufficient clarity resulting in a lack \nof consistent understanding among stakeholders. Indeed, parties have raised varying \ninterpretations of the rules that apply to Co-Location Arrangements across Commission \nproceedings.114 \nthe permissibility of multiple co-location configurations, including those where load is \nserved directly from a generation resource located on or near the same site. Tariff clarity \nis essential to reduce unnecessary disputes, avoid case-by-case confusion, and enable \ntransmission providers to process interconnection and load addition requests efficiently \nand predictably.\"). \n112  December Order, 193 FERC ¶ 61,217 at P 175 & n.375 (citing Constellation, \nComplaint, Docket No. EL25-20-000 (filed Nov. 22, 2024); Baltimore Gas & Electric \nCompany and PECO Energy Company, Petition for Declaratory Order, Docket \nNo. EL24-149-000 (filed Sept. 30, 2024); Constellation April 23, 2025 Reply Comments \nat 4 n.4). \n113  PJM, PJM Guidance on Co-Located Load (Mar. 22, 2024) (updated Apr. 17, \n2024), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-\nguidance-on-co-located-load.pdf. \n114  For instance, an amended ISA to which PPL was a party stated that \"The \nCo-Located Load is not Network Load, and it is intended that the Co-Located Load will \nnever consume capacity and/or energy from the PJM Transmission System.\" PJM \nInterconnection, L.L.C. (Susquehanna), Amended Susquehanna ISA, Docket \nNo. ER24-2172, Schedule F, Part F (filed June 3, 2024); see also, e.g., PJM \nInterconnection, L.L.C., 189 FERC ¶ 61,078, at PP 14, 26 (2024). On the other hand, \nthere are allegations in the record that Exelon has delayed work on Constellation's \nrequests to co-locate load with certain of its generators due to Exelon's concerns that \nsuch requests are not allowed under the Tariff without arranging for wholesale \n188 of 515"},{"page":190,"startToken":70958,"endToken":71340,"text":"Document AccessigPSA:  2AA4516-349cument:Flitd rFas@g9: jd8A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 32 - \n58.\nIn fact, based on our review of the Tariff, the Tariff indeed does not contain \nprovisions specifying the rules governing Co-Location Arrangements.' For instance, \nthe Tariff lacks provisions specifying: the terms and conditions for Interconnection \nCustomers seeking to use their generators to serve Co-Located Load;116  that an \nInterconnection Customer who will use its generator to serve Co-Located Load must \ndesignate an Eligible Customer who will take transmission service on behalf of the \nCo-Located Load;117  the rules governing transmission service—including the rates, terms, \nand conditions of that service—taken by an Eligible Customer on behalf of Co-Located \nLoad;118  and the charges for black start and regulation service to Eligible Customers \ntaking transmission service on behalf of Co-Located Load!\" In sum, due to the absence \nof these provisions, the Tariff lacks sufficiently clear answers to important questions \nabout how to effectuate Co-Location Arrangements. \n59.\nThe finding that the Tariff is unjust and unreasonable due to the lack of sufficient \nclarity is bolstered by several factors. First, the lack of sufficient clarity leaves entities \nunable to determine what steps they can or must take to effectuate or administer \nCo-Location Arrangements of various configurations.12°  Interconnection Customers \nseeking to use their generators to serve Co-Located Load have no means of knowing their \nresponsibilities with respect to serving Co-Location Arrangements and the terms and \nconditions that apply to these arrangements.121  Without an Eligible Customer designated \nto take transmission service on behalf of a Co-Located Load, the Tariff lacks a \nmechanism to address and ensure proper charges for situations in which a Co-Located \nLoad withdraws energy from the transmission system.122  Second, an absence of \ntransmission or retail distribution service. February Order, 190 FERC ¶ 61,115 at PP 51, \n75. \n115  December Order, 193 FERC ¶ 61,217 at P 175. \n\"6  Id P 176. \n\" 7  Id. \n118 \nI d.; see also, e.g., id. P 175. \n119 Id. P 177; see also id PP 159, 181-185. \n120 Id. P 175. \n121  Id. P 176. \n122  Id Indeed, Exelon and FirstEnergy concede that they agree that \"[a]n Eligible \nCustomer serving a co-located load must be designated because it is the Eligible \n189 of 515"},{"page":191,"startToken":71340,"endToken":71795,"text":"Document AccessigPSA:  qq-2-Vg18-3P8cument:Fhtd rEN9: 6169A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 33 - \nsufficient clarity in these circumstances creates regulatory uncertainty, thus undermining \na \"central purpose\" of the FPA—\"predictability.\"I23  Third, the lack of sufficient clarity \nleads here to the potential for undue discrimination, preferential treatment, or otherwise \nunjustifiable disparate conduct. As discussed above, disparate treatment has occurred in \nPJM, where transmission owners have taken different approaches to addressing \nCo-Location Arrangements.124  Finally, the lack of sufficient clarity introduces the risk \nthat costs related to Co-Location Arrangements may not be allocated consistent with cost \ncausation principles because, for instance, Eligible Customers taking transmission service \non behalf of Co-Located Load could benefit from regulation and black start services \nwithout contributing to cost recovery for such services, thus risking that costs may be \nallocated entirely to other transmission customers and passed through to residential \ncustomers, among others.125  In total, these factors are magnified by the facts that \nCo-Location Arrangements are becoming increasingly common in PJM, entities continue \nto raise issues involving Co-Location Arrangements with the Commission,I26  and \nCo-Location Arrangements may include large amounts of load and generation. Given \nthese ramifications and consistent with precedent,127  the Commission appropriately found \nthat the lack of sufficient clarity in the Tariff has rendered it unjust and unreasonable. \nCustomer that seeks and obtains transmission service and pays for it.\" Exelon and \nFirstEnergy Request for Rehearing at 2. \n123  PJM Power Providers Grp. v. FERC, 96 F.4th 390, 401-02 (3d Cir. 2024) \n(describing a central purpose of the filed rate doctrine: predictability). Ensuring \npredictability ultimately supports a primary purpose of the FPA, \"encourag[ing] the \norderly development of plentiful supplies of electricity . . . at reasonable prices.\" Pub. \nUtils. Comm'n of Cal. v. FERC, 367 F.3d 925, 929 (D.C. Cir. 2004) (quoting NAACP v. \nFPC, 425 U.S. 662, 670 (1976); see EPSA, 577 U.S. at 290 (\"The statute aims to protect \n`against excessive prices' and ensure effective transmission of electric power.\" (citations \nomitted)). \n124  December Order, 193 FERC ¶ 61,217 at P 175; February Order, 190 FERC \n¶61,115 atP 75. \n125  December Order, 193 FERC ¶ 61,217 at P 177; see also id. PP 181-185. \n126  Id P 4. \n127  E.g., Invenergy Transmission LLC v. Midcontinent Indep. Sys. Operator, Inc., \n193 FERC ¶ 61,033, at P 53 (2025) (finding tariff unjust and unreasonable because it did \nnot address when and how certain transmission projects are incorporated into a \ntransmission planning model and because existing provisions lacked \"sufficient \nspecificity and certainty\"); PJM Interconnection, L.L.C., 167 FERC 1161,030, at PP 22, \n41, 59 (2019) (\"[W]e find that the PJM Operating Agreement is unjust and unreasonable \n190 of 515"},{"page":192,"startToken":71795,"endToken":72236,"text":"Document Ac„„ig@g 2A-Aqq1.8 - 3P9P-Inlent:Filtd IPa@g9: je9/11812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 34 - \n60.\nNotwithstanding the Commission's findings, Exelon and FirstEnergy argue that \nbecause the Tariff provides for NITS and point-to-point service (PTPS)—with terms \ngoverning them—\"[t]here is no inability to determine how to serve [co-located] load in \nPJM.\"128  Yet, the existence of provisions governing NITS and PTPS does not undermine \nour findings that the Tariff both lacks sufficient clarity and does not contain provisions \nspecifying the rules governing Co-Location Arrangements. The applicability, operation, \nand/or interpretation of the cited general provisions (among others) with respect to \nEligible Customers taking transmission services on behalf of Co-Located Load and \nCo-Location Arrangements are the issues that, in part, give rise to the lack of sufficient \nclarity we target here. \n61.\nNext, Exelon and FirstEnergy respond to the Commission's citation of the \nConstellation Complaint by blaming \"any delay\" giving rise to uncertainty on \nConstellation.129  But this response misunderstands the Commission's reasoning. The \nCommission cited the Constellation Complaint as one piece of evidence to demonstrate \nthat there is \"no consistent understanding\" of the rules governing Co-Location \nArrangements. 130 \n62.\nSimilarly, Exelon and FirstEnergy allege that \"in 2025, [Commonwealth Edison \nCompany] received more than 25 customer service applications for large load service, \nrepresenting new load in excess of 20 GW\" and \"[t]here is no suggestion in the record \nthat any customer is encountering problems with those requests.\"131  Beyond the fact \nthere is no representation that any of those applications relate to Co-Located Load, this \nlimited set of applications before a single Transmission Owner does not demonstrate \nbecause it fails to provide a sufficient level of clarity regarding the permissible \ncomponents of energy market cost-based offers\"); N.Y. Indep Sys. Operator, Inc., \n162 FERC ¶ 61,107, at PP 160, 173 (2018) (\"We find this difference in definitions to be \nunclear and, therefore, unjust and unreasonable\"); Dominion Energy Mktg., Inc., v. ISO \nNew Eng. Inc., 155 FERC ¶ 61,121, at P 17 (2016) (\"We find that [the] existing Tariff is \nunclear as to whether new incremental capacity and existing capacity at the same \ngenerating station must submit a composite offer in order to participate in [a capacity \nauction]. As a result of this lack of clarity, the Tariff fails to provide adequate notice of \nwhat the requirement is and, thus, we find the Tariff is unjust and unreasonable.\"). \n128  Exelon and FirstEnergy Request for Rehearing at 14-15. \n129  Id. at 15-16. \n13°  December Order, 193 FERC ¶ 61,217 at P 175. \n131  Exelon and FirstEnergy Request for Rehearing at 17. \n191 of 515"},{"page":193,"startToken":72236,"endToken":72661,"text":"Document AccessigPfr; 4c)AQA18-3R8..Cument:FlAd rpAg:6169/48/2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 35 - \nsufficient clarity even if those requests \"proceed on a timely basis.i132  As explained \nabove, the Commission continues to be concerned about disparate treatment by different \nTransmission Owners in this context.133 \n63.\nExelon and FirstEnergy also state that in one proceeding pertaining to Co-Located \nLoad, a load and generator entered into a \"front-of-the-meter\" arrangement and thus \n\"conceded that PEW Network Service works . . . and is a service upon which all \ncustomers may rely.\"134  A decision in one proceeding to abandon a Co-Location \nArrangement does not undermine the Commission's finding that there is a lack of \nsufficient clarity related to Co-Location Arrangements writ large (and, in fact, might \nsupport it). \n64.\nFinally, Exelon and FirstEnergy contend that \"No the extent clarification was \nneeded, the Commission has now clarified . . . that these arrangements must be properly \nmetered and must designate and involve transmission service to an Eligible Customer.\"135 \nThis argument is misplaced. Exelon and FirstEnergy's argument that the replacement \nrate should be narrower—that only part of it would be sufficient—should be directed not \nto the finding that the Tariff is unjust and unreasonable but to the determination of a just \nand reasonable replacement rate. Further, the portions of the replacement rate that \nExelon and FirstEnergy reference—requiring proper metering and involving transmission \nservice to an Eligible Customer—do not resolve the Commission's concerns as to a lack \nof sufficient clarity in the Tariff. For example, the Commission found a lack of sufficient \nclarity as to the terms and conditions for Interconnection Customers seeking to use their \ngenerators to serve Co-Located Load.136 \n65.\nWe also continue to find that the Tariff is unjust and unreasonable because it does \nnot include transmission services that reflect Eligible Customers taking service on behalf \nof Co-Located Loads that are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.137  Requiring Eligible Customers taking \n132  Id. \n133  See supra notes 114, 126. \n134  Exelon and FirstEnergy Request for Rehearing at 17-18 (discussing the \nproceedings in Docket Nos. ER24-2172-000 and ER24-2171-001). \n135  Id. at 16-17. \n136  December Order, 193 FERC ¶ 61,217 at P 176. \n137 Id. P 177; see also S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 64-68 (D.C. \nCir. 2014) (explaining that to find a practice unjust and unreasonable, the Commission \nneed not rely on \"empirical evidence\" and can rely on \"reasonable economic \n192 of 515"},{"page":194,"startToken":72661,"endToken":73146,"text":"Document Acce„igPV; 22.A18-1.29cument:Flild JEN9:0,48/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 36 - \ntransmission service on behalf of Co-Located Load to take NITS, without the option to \ninstead take such alternative transmission services, is economically inefficient. Here, the \nrecord demonstrates that some Eligible Customers taking service on behalf of \nCo-Located Loads are willing and able to limit their energy withdrawals. With only the \ncurrent services offered, having found that Eligible Customers taking NITS will be \ncharged based on gross load, prospective Eligible Customers taking transmission service \non behalf of Co-Located Load would have to take a transmission service that does not \nreflect the load's willingness and ability to limit use of the transmission system—which \nis an inefficient result. The Commission has long recognized that providing \ndifferentiated service options can produce more efficient results because customers can \nchoose the service that is most closely tailored to their specific needs, rather than a \none-service-fits-all approach.138  Requiring Eligible Customers taking service on behalf \nof Co-Located Loads to take NITS creates an unacceptable risk of more costly Network \nUpgrades that would be unnecessary if such Eligible Customers were willing and \npermitted to take a transmission service that reflects Co-Located Loads that are willing \npropositions\" \"likely enough to be within the Commission's authority\" and noting that \nthe use of words such as \"might, may, or could\" does not make its determination legally \ndeficient (internal quotation marks omitted)). \n138  See, e.g., Integration of Variable Energy Res., Order No. 764, 139 FERC \n¶ 61,246, at PP 2, 22, order on reh'g & clarification, Order No. 764-A, 141 FERC \n¶ 61,232 (2012), order on clarification & reh'g, Order No. 764-B, 144 FERC ¶ 61,222 \n(2013) (explaining that the Commission sought \"to provide all transmission customers \nthe option of using more frequent transmission scheduling intervals within each operating \nhour, at 15-minute intervals,\" which will allow them \"the flexibility to adjust their \ntransmission schedules, thus limiting their exposure to imbalance charges\" and lead to \n\"more efficient utilization of transmission and generation resources\"); Standardization of \nGenerator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103 \n(2003), order on reh'g, Order No. 2003-A, 106 FERC ¶ 61,220, at P 534, order on reh'g, \nOrder No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh'g, Order No. 2003-C, \n111 FERC ¶ 61,401 (2005), aff'd sub nom. Nat'l Ass 'n of Regul. Util. Comm 'rs v. FERC, \n475 F.3d 1277 (D.C. Cir. 2007) (explaining that \"an Interconnection Customer that elects \nto be studied for Network Resource Interconnection Service has the option also to be \nstudied for Energy Resource Interconnection Service and proceed with Network \nResource Interconnection Service or a lower level Interconnection Service whereby only \ncertain Network Upgrades will be completed\" and finding that \"[t]his option thus allows \nthe Interconnection Customer to avoid having to fund Network Upgrades that it does not \nneed\"). \n193 of 515"},{"page":195,"startToken":73146,"endToken":73603,"text":"n6aufnent Accessigi \nqq-2-13§g-1.8-3P8ument:Filtd rPa,q09:6169/1 8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 37 - \nand able to limit their energy withdrawals.139  We further reiterate that there is support in \nthe record for the foregoing analysis.14° \n66.\nOn rehearing, Exelon and FirstEnergy dispute the Commission's finding that the \nTariff is unjust and unreasonable because it does not include transmission services that \nreflect Eligible Customers taking transmission service on behalf of Co-Located Loads \nthat are willing and able to limit their energy withdrawals from the transmission system \nunder certain conditions.\"1  First, Exelon and FirstEnergy argue that \"there is no \nevidence that the cost of paying for Network Service deters service or has any impact \nwhatsoever on development of data centers\" because \"data center development interest in \nPJM is overwhelming.59142 But the Commission was not required to show that its FPA \nsection 206 step one findings would have a particular effect on data centers. Instead, as \nexplained in the prior paragraph, the Commission's findings relate to economic and other \nharms from a lack of transmission services that reflect Eligible Customers taking service \non behalf of Co-Located Loads that are willing and able to limit their energy withdrawals \nfrom the transmission system.143  In any event, we continue to reason that requiring \nEligible Customers taking transmission service on behalf of Co-Located Load to take \nNITS does have a negative impact relative to transmission services that reflect these \nloads' willingness and ability to limit energy withdrawals. These negative impacts could \ninclude unnecessary Network Upgrade costs, which cause an unjust and unreasonable \nincrease in transmission rates. The assertion that \"development interest\" in data centers \nmay currently be high, or will remain high if Eligible Customers taking transmission \nservice on behalf of Co-Located Loads that are willing and able to limit their withdrawals \nfrom the transmission system are required to take NITS on a gross basis, does not address \nthe counterfactual at issue (i.e., requiring Eligible Customers taking transmission service \non behalf of Co-Located Load to take NITS relative to transmission services that reflect \nthese loads' willingness and ability to limit energy withdrawals). \n67.\nSecond, Exelon and FirstEnergy contend that the Commission has no evidence144 \nto support the risk of \"costly and inefficient transmission system buildout\" under NITS \n139  December Order, 193 FERC ¶ 61,217 at PP 177, 199, 205. \n140  Id. PP 199 & n.423, 205, 434; see also PP 160, 177-178. \n141  Exelon and FirstEnergy Request for Rehearing at 18. \n142  Id at 18-19. \n143  December Order, 193 FERC ¶ 61,217 at P 177. \n144  Exelon and FirstEnergy Request for Rehearing at 19-20 (citing, among other \nthings, December Order, 193 FERC ¶ 61,217 at P 199). \n194 of 515"},{"page":196,"startToken":73603,"endToken":74096,"text":"Document AccessigPV; 2qA C7R18-3Q9curnent:FlAd LFasqg: jegA 8 / 2PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 38 - \ncompared to \"fewer Network Upgrades\" and \"lower Network Upgrade costs\" under an \nalternative service.145  To the contrary, the Commission has provided a robust rationale \nfor this risk, as explained above. Exelon and FirstEnergy state that \"network studies are \nbased on physics and engineering\" so NITS cannot \"impose[] unnecessary transmission \nupgrade costs.\"'\" We agree with the premise that studies are based on physics and \nengineering, but not the conclusion. Many Network Upgrades are caused by the amount \nof MW flow on the transmission system but certain Network Upgrades are not (e.g., they \nmay be caused by stability or voltage-related issues).147  Therefore, as Exelon and \nFirstEnergy concede, under a transmission service designed to reflect load's willingness \nand ability to limit energy withdrawals, \"if the load installs systems aimed at limiting its \nuse of the grid, those might change the system impacts and need for upgrades.\"'\" \nConversely, NITS requires PJM to plan the transmission system to deliver power to \nload, l49  even if that load does not intend to ever withdraw power from the system, which \ncould result in unnecessary Network Upgrades. Exelon and FirstEnergy also claim that \n\"[t]he fact that a load is located near a generator may well reduce system impacts . . . \n145  December Order, 193 FERC ¶ 61,217 at P 177. \n146  Exelon and FirstEnergy Request for Rehearing at 19. \n147  Exelon and FirstEnergy additionally contend that \"even when no net power is \nbeing withdrawn from the system . . . the transmission system is affected and needed by \nthe load—indeed, the Commission agreed with this proposition when it found that co-\nlocated loads do utilize load-following based on gross rather than net load.\" Id at 19-21. \nAgain, we do not find that the need for Network Upgrades is based only on withdrawals; \ninstead, we find that reducing the amount of MW flow can lead to the need for fewer or \nless costly Network Upgrades. The December Order does not promote ignoring impacts \nwhen no net power is being withdrawn. \n148  Id at 19-20. We note that Exelon and FirstEnergy also state that \"the same can \nbe said for similar systems applied to other loads. Nothing in the record [supports] that \nsuch systems are more beneficial for co-located load projects than for any other load [or] \nthe use of different ratemaking principles when such installations are in place. To the \ncontrary, . . . the Commission has consistently rejected arguments that different \nratemaking should be applied even where there are physical limits to the amount of \ntransmission system use.\" Id. We understand these arguments as directed to the \nreplacement rate, and thus we address them below. To the extent they are directed to the \nCommission's FPA section 206 step one finding, we disagree for the same reasons stated \nbelow. \n149 PJM, Intra-PJM Tariffs, OATT, § III, § 28.2 (Transmission Provider \nResponsibilities) (1.0.0). \n195 of 515"},{"page":197,"startToken":74096,"endToken":74562,"text":"Document Accessigl?sg 2A-206,A18 _399curnent:Flil d tpa g9: (-31,9A8, 2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 39 - \nregardless of whether the load has contracted with the generator it abuts, or with remote \ngeneration.\"15°  This assertion ignores the fact that a new transmission service reflecting \nwillingness and ability to limit energy withdrawals could further reduce system \nimpacts-for instance through the \"systems aimed at limiting [the] use of the grid\" that \nExelon and FirstEnergy reference. I51  We similarly disagree with Exelon and \nFirstEnergy's claim that a new transmission service would not \"alter what must be \nstudied in assessing the physics and engineering of any proposed new configuration.\" 52 \nStudies for a customer taking a new transmission service that limits the amount of energy \nthat may be withdrawn would reflect that limitation.153  Such potential transmission \nservice could alter the level of steady-state transmission system usage studied (i.e., the \n\"physics\") and the design of the physical facilities, necessary control technologies, and/or \nprotection systems needed to effectuate that arrangement compared to a traditional \nNetwork Customer (i.e., the \"engineering\"), contrary to Exelon and FirstEnergy's \nassertions. \n68. \nThird, Exelon and FirstEnergy assert that the Commission contradicted itself in \nfinding the Tariff unjust and unreasonable in lacking alternative transmission services \nbecause the Commission also stated that \"`it continues to be just and reasonable for an \nEligible Customer taking transmission service on behalf of Co-Located Load to elect, as \none of the required transmission services from which the Eligible Customer must choose, \nto take NITS.'\"154  The Commission did not find that current set of transmission service \noptions is just and reasonable. Instead, the Commission stated, it continues to be just and \nreasonable for such an Eligible Customer \"to elect\" NITS \"as one of the required \n150 Exelon and FirstEnergy Request for Rehearing at 20. \n151  Id. at 19-20. Exelon and FirstEnergy likewise claim that Co-Location \nArrangements \"will have the same potential benefit regardless of whether there is a \ncontractual supply arrangement with a nearby generator and regardless of whether it pays \nfor transmission service based on net or gross load.\" Id. at 21. This assertion again \nmisses the key distinction. Under a new alternative transmission service reflecting \nwillingness and ability to limit energy withdrawals, there could be fewer or less costly \nNetwork Upgrades if the Eligible Customer can select a lower (but otherwise \nsatisfactory) level of demand. \n152  Id. at 20. \n153  Exelon and FirstEnergy state that \"[t]here is simply no evidence\" for an \nargument that a new transmission service could speed access to service. Id. But the \nCommission's findings are not based on speeding access to service or creating \"fast-track \ninterconnection.\" Id. at 20-21. \n154  Id. at 21-22 (quoting December Order, 193 FERC ¶ 61,217 at P 195). \n196 of 515"},{"page":198,"startToken":74562,"endToken":74987,"text":"Document Acc„sigPsP; 226`0`618-3Wcurnent:Filtd IPA99:616971 8 2PAe Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 40 - \ntransmission services.\"155  But it is unjust and unreasonable for that set of options to lack \nthe alternatives the Commission discussed.156 \n69.\nFourth, Exelon and FirstEnergy argue that the Commission's finding that the \nTariff is unjust and unreasonable because it lacks alternative transmission service options \nmisunderstands the benefits and burdens \"to co-located projects of being interconnected \nto the grid.\"157  The Commission did not find, however, that Co-Located Loads could \nreceive no benefits from or place no burdens on the transmission system. Instead, the \nCommission found that the Tariff was unjust and unreasonable because it did not reflect \nthe features of Co-Location Arrangements that make the existing transmission service \noptions unacceptable.15°  An Eligible Customer taking transmission service on behalf of \nCo-Located Load must be charged for the benefits received from and the burdens placed \non the transmission system—but that does not mean the status quo is not unjust and \nunreasonable. Co-Located Load may be able to reduce the benefits received from and the \nburdens placed on the transmission system if it is willing and able to limit energy \nwithdrawals. We do not dispute, and indeed continue to find, that Co-Located Loads do \nreceive benefits even if they have zero net energy withdrawals, specifically from \nregulation and black start services.159  The Commission's finding that the Tariff is unjust \nand unreasonable does not preclude the recognition of those benefits. \n70.\nFinally, Exelon and FirstEnergy maintain that the Commission's \"finding that the \nexisting PJM Tariff is [unjust and unreasonable] is arbitrary and capricious because the \nCommission failed to consider the unique issues that attend co-location with nuclear \nplants.\"16°  This argument is misplaced. The Commission found that the Tariff is unjust \nand unreasonable for, in part, the two reasons discussed above.16I  In particular, the \nCommission found the Tariff unjust and unreasonable because it does not include an \noption for Eligible Customers on behalf of Co-Located Loads to take transmission \nservices that reflect their willingness and ability to limit their energy withdrawals from \n155  December Order, 193 FERC ¶ 61,217 at P 195 (emphasis added). \n158 Id. P 177. \n157  Exelon and FirstEnergy Request for Rehearing at 30-32; see also id. \n(discussing various benefits and burdens). \n158  December Order, 193 FERC ¶ 61,217 at P 177. \n159  Id. P 185. \n160 Exelon and FirstEnergy Request for Rehearing at 32-33. \n161 December Order, 193 FERC ¶ 61,217 at PP 176, 177. \n197 of 515"},{"page":199,"startToken":74987,"endToken":75392,"text":"Document A„„sigP\nSA qq25\"218-348cu ment.F11td Ii3ag:6169A8/ 2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 41 - \nthe transmission system. The fact that a nuclear generator in a Co-Location Arrangement \nmight be dependent on the transmission system because that nuclear generator cannot \noperate without a robust interconnection to the transmission system, or cannot load \nfollow, does not undermine these core findings. Exelon and FirstEnergy attempt to use \nthese facts to conclude that the Co-Located Load is effectively using the transmission \nsystem in a similar manner to a load served by remote resources. We disagree because, \nregardless of load following, the energy used by the Co-Located Load is provided (at \nleast in part) by its Co-Located Generator, not via the transmission system. Eligible \nCustomers on behalf of Co-Located Loads that are served by a Co-Located Generator \nthat is a nuclear generator should be permitted to take transmission services that reflect \nthat they are willing and able to limit their withdrawals from the transmission system \nunder certain conditions. To the extent a nuclear generator that is part of a Co-Location \nArrangement operates differently than other Co-Located Generators, that is an issue that \nmay be assessed in subsequent study processes, or simply by the nuclear generator itself, \nas the Interconnection Customer (not the Eligible Customer) in determining whether and \nhow to enter into a Co-Location Arrangement. \n2. \nRetail BTMG Netting Rules  \na. \nScope and Adequate Notice  \ni. \nDecember Order  \n71. \nThe Commission found that PJM's retail BTMG netting rules are no longer just \nand reasonable and clarified that this finding applies to all Network Load.162 \nii. \nRequest for Clarification and/or Rehearing \n72. \nCiting the Administrative Procedure Act (APA) and Commission Rule 209, \nIndustrials argue that changes to retail BTMG netting rules are outside the scope of the \nFebruary Order.163  Industrials assert that the February Order set the scope of the \nproceeding and limited it to Co-Located Load and Co-Location Arrangements, thus \nexcluding BTMG. Industrials argue that no part of the February Order included the \npossibility of the Commission's BTMG netting findings in the December Order. \nIndustrials allege there are important distinctions between Co-Location Arrangements \nand BTMG, particularly that a BTMG arrangement is a retail load-modification \n162 Id. P186. \n163  Industrials Request for Clarification or Rehearing at 22 (citing 5 U.S.C. § 706; \n18 C.F.R. § 385.209 (2025)); see also 5U \nU.S.C. § 554. \n198 of 515"},{"page":200,"startToken":75392,"endToken":75746,"text":"Document AccessigPA:  2q-Aegi.8-31?@c ument:FlAd rfasq99: ja9A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 42 - \nconstruct, whereas a Co-Location Arrangement is a wholesale-system-impacting load \nintegration construct.'\" \niii. \nDetermination \n73.\nWe disagree with Industrials that changes to retail BTMG netting rules are beyond \nthe scope of this proceeding because the Commission provided adequate notice as to \nthose changes. \n74.\nUnder the APA, an agency setting a matter for hearing must provide parties with \nadequate notice of the issues that would be considered, and ultimately resolved, at that \nhearing.165  Under Commission Rule 209(b), \"an order to show cause will contain a \nstatement of the matters about which the Commission is inquiring, and a statement of the \nauthority under which the Commission is acting. The statement is tentative and sets forth \nissues to be considered by the Commission.\"'66 \n75.\nWhile Industrials allege that the Commission in the February Order \"set the scope \nof the proceeding to Co-Located Load,\"167  the Commission did no such thing. The \nFebruary Order contains no finding limiting the proceeding's scope to \"Co-Located \nLoad.\" Instead, the February Order also expressly raises, among many other topics, \nrelevant generation configurations16S  and overall addresses issues that attend to load with \non-site or otherwise nearby generation, which logically includes BTMG.'69 \n164  Industrials Request for Clarification or Rehearing at 22-26. \n165  N. Va. Elec. Coop., Inc. v. FERC, 945 F.3d 1201, 1205 (D.C. Cir. 2019); \n5 U.S.C. § 554(b)(3) (establishing notice requirement for adjudications). \n166  18 C.F.R. § 385.209(b). \n167  Industrials Request for Clarification or Rehearing at 22. \n168  February Order, 190 FERC ¶ 61,115 at P 79. \n169  Id. P 76 (discussing concerns related to generation and load being \"likely to use \nor benefit from the transmission system in different ways depending on how they are \nconfigured\" and giving examples such as \"Network Load may co-locate with a generator \nthat is not a grid resource and that either serves the load as an off-grid backup or that \nreduces the Network Load's consumption during peak hours\" (emphasis added)). \n199 of 515"},{"page":201,"startToken":75746,"endToken":76185,"text":"Document AccessigsiP:: 2-A-A6g48 _3Qpcument:Flil d rEN: gp/q.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 43 - \n76.\nIn any event, Industrials themselves acknowledge that the Commission's briefing \nquestions in fact specifically included BTMG.170  In particular, the Commission asked \nparties to address \"how co-located loads are similar to or disparate from other types of \narrangements where load and generation share the same point of interconnection (such as \nBehind the Meter Generation[)].\"171  This question reflects that the Commission would \nconsider BTMG configurations in determining a just and reasonable replacement rate. \nIndustrials contend that the Commission's reference to \"other arrangements\" in this \nquestion shows that retail BTMG and Co-Located Load are distinct concepts, but \nIndustrials' claims are belied by their assertions in their reply comments to the February \nOrder that BTMG configurations and Co-Location Arrangements identically impact the \ntransmission system.I72  And regardless of their similarity, the Commission's briefing \nquestion raises the subject of the treatment of BTMG. Additional briefing questions in \nthe February Order also sufficiently raise the subject of BTMG. The Commission \ndirected parties to submit briefing on transmission services, including potential changes \nto the rates, terms, and conditions of NITS to accommodate Co-Location \nArrangements.173  PJM's retail BTMG netting rules are part of PJM's rates, terms, and \nconditions for NITS.174  Finally, the Commission also asked \"whether portions of the \nGuidance Document may serve as a just and reasonable and not unduly discriminatory or \npreferential replacement rate,\"175  and that document states, \"[i]f the co-located Customer \nFacility elects to be designated as [BTMG], it will be allowed to net the co-located load \ndirectly against the output of the co-located Customer Facility.\"176  We thus find that the \nFebruary Order provided adequate notice that the Commission would consider PJM's \nBTMG netting rules as part of this proceeding. \n77.\nThe record developed in response to the February Order further reflects that \nIndustrials had notice and an opportunity to address changing PJM's retail BTMG netting \n17°  Industrials Request for Clarification or Rehearing at 25. \n171 February Order, 190 FERC ¶ 61,115 at P 88 (briefing question a.iv). \n172 PJM ICC and IECA April 23, 2025 Reply Comments at 9. \n173 February Order, 190 FERC ¶ 61,115 at P 88 (briefing question b.iv). \n174  PJM, Intra-PJM Tariffs, OATT, § III, § 34.2 (Netting of Behind the Meter \nGeneration) (0.0.0). \n175  February Order, 190 FERC ¶ 61,115 at P 88 (briefing question a.iii). \n176 PJM, PJM Guidance on Co-Located Load (Mar. 22, 2024) (updated Apr. 17, \n2024), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-\nguidance-on-co-located-load.pdf. \n200 of 515"},{"page":202,"startToken":76185,"endToken":76635,"text":"Document AccessigPV; 2%Aftg1.8-346cument:Flild  rFas@gp: (4)/118/2pAte Filed 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 44 - \nrules. While Industrials attempt to minimize the briefing questions as \"scarcely \nmention[ing]\" BTMG among a large number of topics in the February Order, PJM \nsubmitted detailed concerns that the retail BTMG netting rules were no longer just and \nreasonable in direct response to the February Order.177  And parties debated the merits of \nPJM's concerns in reply comments.178  All parties, including Industrials, had an \nopportunity to rebut PJM's claims before the Commission could weigh the evidence on \nthis matter. As courts have explained, subsequent briefing on a topic serves as evidence \nof adequate notice as to that topic.'\" \nb. \nWhether PJM's Retail BTMG Rules Are Unjust and \nUnreasonable  \ni. \nDecember Order \n78. \nIn finding that PJM's retail BTMG netting rules are no longer just and reasonable, \nthe Commission explained that circumstances had changed since the Commission \napproved PJM's rules in 2004.180  The Commission stated that PJM explains that the \nBTMG netting rules were \"conceived for, and [have] been implemented for, substantially \nsmaller loads (like a warehouse with solar panels) and not on the scale of large data \n177  PJM March 24, 2025 Response at 34 (\"The co-located load arrangements at \nissue here, large data centers, could be viewed as similar to BTM Generation that \ncurrently exists under PJM's Tariff (as reflected in Ex. A, Option 3). But as explained \nherein, the BTM Generation paradigm does not fit co-location arrangements particularly \nwell because it was not designed with large load co-location in mind.\"); id at 36-37 (\"In \nsum, discussions in the record regarding PJM's BTM Generation rules raise questions \nabout the status of those rules. PJM is open to exploring . . . whether the 20-year-old \nmethod of allocating costs pursuant to the BTM Generation netting rules remains \nconsistent with cost causation principles.\"). \n178  Compare AMP April 23, 2025 Reply Comments at 10 (\"The record provides \nno basis to revisit the current PJM Tariff provisions addressing BTMG.\"), with \nNortheastern Rural Electric Membership Corporation (NREMC) April 23, 2025 Reply \nComments at 5 (\"Additionally, simple netting of generation against load could allow \nthese facilities [i.e., data centers] to avoid most, if not all, costs by netting out to zero as \nthe entire load is supplied by the co-located generator, despite the co-located loads \nreliance and benefit from the grid. This would shift costs and burdens unfairly to other \nusers, violating core principles of just and reasonable ratemaking.\"). \n179  N. Va. Elec. Coop., Inc., 945 F.3d at 1206. \n180 December Order, 193 FERC ¶ 61,217 at P 186 (citing PJM, 107 FERC \n¶ 61,113 (2004) (2004 BTMG Order)). \n201 of 515"},{"page":203,"startToken":76635,"endToken":77099,"text":"Document AccessiglPg 2A-2306,A-1s - 311;9c ument:Fl il d  dpAg:(27,0A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 45 - \ncenters.\"181  However, the Commission stated that large loads, both existing and in the \nplanning stages with PJM, have proliferated in recent years, and PJM has persuasively \nexplained the problems that could occur if Network Customers with large loads were \nallowed to use the existing BTMG netting rules in the Tariff.182  The Commission stated \nthat, for example, PJM explains that \"[a]llowing very large loads like data centers to net \nis problematic because loads in this configuration do not carry reserves.\"183  The \nCommission stated that such loads must nevertheless be served, however, allowing them \nto \"lean on the PJM system when the [BTMG] is on a full or partial outage or if the load \nexceeds the rating of the [BTMG].13184 The Commission emphasized that PJM's existing \nBTMG netting rules do not limit the amount of qualifying load that a Network Customer \nmay net by using BTMG and do not provide any protections against this potential \ntransmission and resource adequacy planning problem or against the costs of maintaining \nsufficient resources to serve these loads being shifted onto other customers.185  The \nCommission found that PJM's BTMG netting rules are no longer consistent with cost \ncausation principles, because large loads configured in a BTMG arrangement with \nsignificant generation will raise cost-shifting concerns compared to loads pursuing \nsmaller amounts of netting. The Commission found that PJM's existing BTMG netting \nrules may lead to both reliability and resource adequacy risks because PJM, per its Tariff, \nis obligated to serve transmission customers using BTMG but does not consider such \ncustomers in transmission and resource adequacy planning. \nii. \nRequest for Clarification and/or Rehearing \n79. \nIndustrials argue that the Commission erred by failing to address prior precedent \non cost causation and failing to demonstrate that the existing BTMG netting rules were \n181  Id. (quoting PJM March 24, 2025 Response at 13). \n182 \n7.\n \nla (citing Docket No. AD24-11-000, Large Loads Co-Located at Generating \nFacilities Tr. at 9:2-3 (noting that \"large data centers [] need these significant new \namounts of energy for their business\"); PJM Interconnection, L.L.C., 188 FERC \n¶ 61,200, at P 5 (2024) (\"PJM explains that the [tariff] proposal [to allocate load \nadjustments] was spurred by the recent proliferation of data centers that are contributing \nto large additions of forecasted load concentrated within a specific wholesale metering \narea.\")). \n183  December Order, 193 FERC ¶ 61,217 at P 186 (quoting PJM March 24, 2025 \nResponse at 36). \n184  Id. (quoting PJM March 24, 2025 Response at 13 n.5). \n185  Id (citing PJM, Intra-PJM Tariffs, OATT, § III, § 34.2 (Netting of Behind the \nMeter Generation) (0.0.0)). \n202 of 515"},{"page":204,"startToken":77099,"endToken":77532,"text":"Document Ac„„igPSP; 2qAqA18-3R9cUrnent:Filtd rEq99:W 912pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 46 - \nunjust and unreasonable.186  Industrials contend that Commission precedent established \nthe \"actual use\" principle, which holds that \"actual use\" of the transmission system is a \njust and reasonable approach for assessing transmission charges that comports with cost \ncausation.187  Industrials argue that the Commission here abandons the \"actual use\" \nprinciple by finding BTMG netting unjust and unreasonable.188  According to Industrials, \nthe December Order also \"creates an unreasonable split between those who manage costs \nby managing load and those who manage costs by investing in generation.\"189  \"In other \nwords,\" Industrials contend, \"the effect of the `gross load' approach is unduly \ndiscriminatory, because it allows `actual use' to govern NITS costs for some (i.e., \nload-only customers), but not for others (i.e., those who have invested in retail \nbehind-the-meter generation).\"190  Industrials acknowledge that \"[i]f standby fees or other \ncharges need to be considered in accordance with cost-causation principles, the \nCommission may explore those,\" but argue that \"eliminating altogether the assessment of \ncharges based on `actual use' is unduly discriminatory and fails to reckon with \nwell-established Commission precedent.\"1\" \n186  Industrials Request for Clarification or Rehearing at 34; see also id. at 5, 19-20. \n187  Id. at 35-36 (citing 2004 BTMG Order, 107 FERC 1161,113, at P 4 (finding \"no \ntransmission or distribution facilities are used to deliver energy from the generating unit \nto the load\"); Occidental Chem. Corp. v. PJM Interconnection, 102 FERC ¶ 61,275, \nat P 14 (2003) (Occidental) (\"Access charges for use of PJM's transmission system \nshould be allocated to network customers based on a network customer's actual use of \nPJM's system, consistent with the principle of cost causation.\"); PJM Interconnection, \nL.L.C., 167 FERC ¶ 61,268, at P 23 (2019) (PJM) (affirming Commission's conclusion in \nOccidental that Network Customers' charges for use of PJM's transmission system \nshould be allocated based on a Network Customer's actual use of PJM's system); ISO \nNew Eng., Inc., 178 FERC 41161,086, at P 51 (2022) (ISO-NE) (finding just and \nreasonable ISO New England Inc.'s proposal to exclude from the Monthly Regional \nNetwork Load served by unregistered BTMG and the portion of the output of a Generator \nAsset that serves load located behind the same retail customer meter and assign Regional \nNetwork Service charges to Network Customers based on each Network Customer's \nactual use of the system)). \n188  Industrials Request for Clarification or Rehearing at 35-37. \n189  Id at 37. \n190  Id. at 37-38. \n191  Id. at 38. \n203 of 515"},{"page":205,"startToken":77532,"endToken":77969,"text":"Document Accessigi@sg 2,Q\"2P-Aii3-3PRcument:Filtd rPAg: gpA_8, 2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 47 - \n80.\nIndustrials argue that the Commission did not develop a sufficient record on which \nto base its determinations on BTMG netting rules in the Tariff.192  Industrials give several \nexamples of \"real-life facility configurations\" that will face substantial harms or be \nundercompensated under a \"gross load\" approach.193  Industrials argue that, without a \nwell-developed record, the Commission may not be able to fully recognize the cost \ncausation implications of the removal of all netting rules. \niii. \nDetermination \n81.\nWe disagree with Industrials that the Commission failed to address prior precedent \nin the December Order or show that PJM's retail BTMG netting rules were unjust and \nunreasonable.194  The Commission in the December Order summarized its decision \napproving PJM's retail BTMG netting rules, including the finding in the 2004 BTMG \nOrder accepting the BTMG netting rules that \"charges for use of PJM's transmission \nsystem should be allocated to network customers based on a network customer's actual \nuse of PJM's system, consistent with the principle of cost causation.\"195  We recognize \nthat the Commission's 2004 BTMG Order relied upon Occidental for the proposition that \nNITS charges should be based on actual use,196  and that, after 2004, the Commission has \nrelied upon Occidental and/or the 2004 BTMG Order to support similar findings.197  But \nthe Commission in the December Order did not find that it is no longer just and \nunreasonable to ever allocate transmission charges based on actual use. Rather, the \nCommission found that PJM's retail BTMG netting rules are no longer consistent with \ncost causation principles for a specific reason, that is, because large loads configured in a \nBTMG arrangement with significant generation will raise cost-shifting concerns \n192  Id at 26; see also id at 6. \n193  Id at 27-31; see also id at 4-5. \n194  Id at 34-38. \n195  December Order, 193 FERC ¶ 61,217 at P 7 (quoting 2004 BTMG Order, \n107 FERC ¶ 61,113 at P 28); Id P 186 (citing 2004 BTMG Order, 107 FERC ¶ 61,113). \n196  2004 BTMG Order, 107 FERC ¶ 61,113 at P 28 (citing Occidental, 102 FERC \n¶ 61,275). \n197  See PJM, 167 FERC ¶ 61,268 at P 23 (discussing Occidental for the \nproposition that the Commission has found that RTOs and transmission owners must \nrecognize load reductions from interruptible load programs in computing billing \ndeterminants); ISO-NE, 178 FERC ¶ 61,086 at P 51 (finding just and reasonable ISO \nNew England's proposal to charge Network Customers based on actual use of the \nsystem). \n204 of 515"},{"page":206,"startToken":77969,"endToken":78412,"text":"Document AccessigRA kAgAi8-34@cument:Flild rENP:g60A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 48 - \ncompared to loads pursuing smaller amounts of netting.198  The Commission thus \nexplained that these PJM retail BTMG netting rules, while previously consistent with \ncost causation principles at the time the Commission approved them, were rendered \nunjust and unreasonable by a change in circumstances. In further support of its finding \nthat these rules are no longer just and reasonable, the Commission found that PJM's \nexisting retail BTMG netting rules may lead to both reliability and resource adequacy \nrisks because PJM, per its Tariff, is obligated to serve transmission customers using \nBTMG but does not consider such customers in transmission and resource adequacy \nplanning.199  The Commission orders relying on actual use principles that Industrials cite \ndo not reflect the problems currently posed in PJM by large loads configured in a BTMG \narrangement.m \n82.\nWe also disagree with Industrials that the Commission did not develop a sufficient \nrecord on which to base its determination in the December Order on PJM's retail BTMG \nnetting rules.201  As discussed above, the Commission adequately supported its findings \nthat PJM's retail BTMG netting rules are no longer just and reasonable. Importantly, the \nCommission relied on evidence submitted by PJM detailing problems that could occur if \nNetwork Customers with large loads were allowed to use the existing retail BTMG \nnetting rules in the Tariff.202  Other parties raised similar concerns in the record.\"3 \n83.\nIndustrials instead raise concerns that the Commission's decision results in \nsignificant economic harm to entities who have used PJM's retail BTMG netting rules \n198 December Order, 193 FERC ¶ 61,217 at P 186. \n189  Id.; see PJM, Intra-PJM Tariffs, OATT, § III, § 34.2 (Netting of Behind the \nMeter Generation) (0.0.0). \n200 See, e.g., ISO-NE, 178 FERC ¶ 61,086 at P 8 (explaining that, decades ago, \nbehind-the-meter generation was typically larger on-site generation connected to \nindustrial load, but since then, behind-the-meter generation has evolved with increasing \namounts of widely distributed behind-the-meter generation that is below 5 MW, such as \nsolar photovoltaic generation). \n201  Industrials Request for Clarification or Rehearing at 26-27. \n202  December Order, 193 FERC ¶ 61,217 at P 186 (\"For example, PJM explains \nthat \"[a]llowing very large loads like data centers to net is problematic because loads in \nthis configuration do not carry reserves.\") (quoting PJM March 24, 2025 Response at 36). \n203 Id.\n \nP 73 (\"NREMC argues that large Co-Located Loads paired with BTMG \npresent significantly greater operational risks than traditional BTMG arrangements \nbecause they lack adequate reserves.\") (citing NREMC April 23 Reply Comments at 5). \n205 of 515"},{"page":207,"startToken":78412,"endToken":78890,"text":"Document Accessigi?SP; qq-AX18-3R99UMent:FlAd \n812\ne\ng,0,6Ate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 49 - \nand the Commission may not have fully recognized the cost causation implications of the \nremoval of all netting rules.204  We find these concerns unpersuasive for several reasons. \nFirst, we believe Industrials' argument concerns how the Commission fashions a \nreplacement rate that determines the extent to which entities may be able to continue to \nrely on netting,205  not to the Commission's finding that the existing rate in PJM is no \nlonger just and reasonable. \n84.\nSecond, as the Commission explained in the December Order in its determination \non transmission services, NITS charges based on gross load for Network Load are \nroughly commensurate with the benefits received because Network Load has the right to \nbe served from the transmission system at any time.206  The Commission's decision to \nrevise PJM's retail BTMG netting rules may increase transmission charges for Network \nCustomers who have used PJM's retail BTMG netting rules, but this change better aligns \nthe benefits and costs for these customers and addresses cost-shifting concerns because it \nreflects the fact that they must be served even when their retail BTMG is on outage.207 \n85.\nThird, as discussed elsewhere in this order, we set aside the December Order in \npart and permit Eligible Customers taking transmission service on behalf of load served \nby BTMG to have the option to take the new transmission services set forth in the \nDecember Order. Therefore, Eligible Customers taking transmission service on behalf of \nload served by BTMG will, at minimum, not be required to take NITS on a gross load \nbasis but will have the option to take and be charged for different transmission services. \n86.\nFourth, we note that Industrials offer six examples involving specific BTMG \narrangements that could be financially harmed by the removal of PJM's retail BTMG \nnetting rules. As discussed above, to the extent these BTMG arrangements are \nfinancially harmed, that implicates the Commission's decision to set a replacement rate \nas to the extent to which such entities may continue to net going forward. Also, as \ndiscussed below, we set aside the December Order in part and direct PJM to exempt \ncertain cogeneration facilities from, revised retail BTMG netting rules where the facilities \nmay be integrated with load such that, when their generator trips offline, the load follows \n(rather than withdrawing energy from the transmission system), as such facilities would \nnot present the cost shift, reliability, or resource adequacy concerns discussed in the \n204 Industrials Request for Clarification or Rehearing at 27. \n2°5  See supra Part IV.C.1.c. \n2°6  December Order, 193 FERC ¶ 61,217 at P 198. \n207  See id. P 186 (finding that PJM's retail BTMG netting rules raise cost-shifting \nconcerns due to large loads configured in BTMG arrangements). \n206 of 515"},{"page":208,"startToken":78890,"endToken":79246,"text":"Document A„„sigPV; 2AACg18-34Pcurnent:Flihd 1J e: g.4);71812PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 50 - \nDecember Order.208  To the extent that any of the facilities discussed in Industrials' six \nexamples could demonstrate that they do not present such concerns, they may fall within \nthe exemption that we direct PJM to submit as part of the compliance filing discussed \nbelow.209 \n87.\nWe also disagree with Industrials that the December Order unduly discriminates \nagainst Network Customers who manage costs by investing in generation as compared to \nNetwork Customers who manage costs by managing load. Undue discrimination \nprohibited by the FPA can occur when similarly situated customers are treated \ndifferently.210 Here, Industrials fail to show that the December Order results in \ndifferential treatment because Network Customers are subject to charges for NITS based \non gross load whether or not they have associated generation, with the exception of the \nmateriality threshold for retail BTMG discussed below. In addition, the December Order \nneither addresses nor limits Network Customers' ability to manage load, whether or not \nthey have associated generation. \n3. \nTransmission Service Options for BTMG \na. \nDecember Order \n88.\nAs explained above, the Commission found that the Tariff is unjust and \nunreasonable because it does not include transmission services that reflect Eligible \nCustomers taking service on behalf of Co-Located Loads that are willing and able to limit \ntheir energy withdrawals from the transmission system under certain conditions.211 \n89.\nThe Commission found that PJM's retail BTMG netting rules were no longer just \nand reasonable, explaining that these rules may lead to both reliability and resource \nadequacy risks because PJM, per its Tariff, is obligated to serve transmission customers \n208 m  \n209 See, e.g., Industrials Request for Clarification or Rehearing at 27 (\"Because the \nmanufacturing process requires steam produced for generation, the bulk of the load can \nremain online only if generation is operational. If the generation goes down, the load will \nlargely cease as well.\"). \n210 Cal. Indep. Sys. Operator Corp., 193 FERC ¶ 61,117, at P 33 (2025). \n211  December Order, 193 FERC ¶ 61,217 at P 193. \n207 of 515"},{"page":209,"startToken":79246,"endToken":79627,"text":"Document AccessigI SA: 4q- obis -3g9curnent:Fiild rijaq99:gbo/e18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 51 - \nusing BTMG but does not consider such customers in transmission and resource \nadequacy planning.212 \nb. \nRequest for Clarification and/or Rehearing \n90. \nIndustrials request clarification that the new transmission services must be made \navailable to Eligible Customers taking transmission service on behalf of load-only \ncustomers with BTMG.213  Industrials argue that Eligible Customers taking transmission \nservice on behalf of load-only customers with BTMG should also be allowed to benefit \nfrom the new transmission services.214 \nc. \nDetermination \n91. \nWe set aside, in part, the December Order. In addition to the finding in the \nDecember Order that the Tariff is unjust and unreasonable as to Eligible Customers \ntaking transmission service on behalf of Co-Located Load, we also find that the Tariff is \nunjust and unreasonable because it does not include transmission services that reflect that \nEligible Customers taking transmission service on behalf of load with BTMG are willing \nand able to limit their energy withdrawals from the transmission system under certain \nconditions. Requiring Eligible Customers taking transmission service on behalf of load \nwith BTMG to take NITS, without the option to instead take such alternative \ntransmission services that reflect their willingness and ability to limit their energy \nwithdrawals, would be unjust and unreasonable for the same reasons we made the same \nfinding with respect to Eligible Customers taking transmission service on behalf of \nCo-Located Load.215  For purposes of this order, then, we use the term Eligible Load to \nrefer to Co-Located Load216  and/or load with BTMG.217  We also direct PJM to file, \nwithin 60 days of the date of issuance of this order, a definition for Eligible Load, or \nother comparable Tariff revisions to implement these directives, and to revise its \ndefinition of BTMG to allow Eligible Customers taking transmission service on behalf of \n212 Id.P186. \n213  Industrials Request for Clarification or Rehearing at 13-14. \n214 Id \n215  See supra Part IV.B.1.c (discussing further the Commission's finding in the \nDecember Order that the Tariff is unjust and unreasonable as to Eligible Customers \ntaking transmission service on behalf of Co-Located Load). \n216  See supra P 10. \n217  See supra note 4. \n208 of 515"},{"page":210,"startToken":79627,"endToken":80000,"text":"Document Ac„ssigPsg 2A-ARA18_349curnent:FlAd rPaN9:goo,48, 2pge Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 52 - \nload with BTMG that are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions to take the new transmission services, \nconsistent with this order. All Eligible Customers taking one of the new transmission \nservices on behalf of Eligible Load will be subject to the requirements discussed below, \nincluding, but not limited to, operational requirements such as necessary control \ntechnologies and/or protection systems as discussed in part VI.C and penalty charges and \nother remedial actions as discussed in part VI.D. \nC. \nReplacement Rate \n1. \nTransmission Services  \na. \nNITS \ni. \nDecember Order  \n92. \nAs relevant here, the Commission found that NITS must be taken on a gross \nbasis.218 \nii. \nRequest for Clarification  \n93.\nPIOs request clarification of the December Order regarding cost allocation issues. \nPIOs argue that, given the unprecedented volume and scale of large load requests, the \nCommission should evaluate whether existing transmission rate designs remain just and \nreasonable. PIOs state that the Commission held in the December Order that Co-Located \nLoad taking NITS would be responsible for costs that are \"roughly commensurate\" with \nbenefits because zonal NITS rates include upgrades and operations and maintenance \ncosts. PIOs argue that this rate design relies on a standard assuming that load growth is \nincremental and widely distributed, however, whereas discrete large-load pockets trigger \nmulti-million dollar reliability solutions.219 \n94.\nPIOs contend that a significant \"payer gap\" can emerge because customers pay \nonly in proportion to billing determinants rather than by the incremental costs that they \ntrigger. PIOs provide the example of a transmission project portfolio approved in the \n2024 Regional Transmission Expansion Plan (RTEP) Window 1 that will cost \n$5.08 billion and state that if a 1,000 MW data center represents 7% of the zone's peak \ndeterminants, it would contribute only $203 million and leave a $4.877 billion gap for \nunrelated regional and zonal customers to pay. PIOs therefore request that the \nCommission clarify how \"roughly commensurate\" cost allocation is evaluated when a \n218  December Order, 193 FERC ¶ 61,217 at P 195. \n219  PIOs Request for Clarification at 7. \n209 of 515"},{"page":211,"startToken":80000,"endToken":80409,"text":"Document Accessigisp; qq-Aeg,18 _3Qacument:Firl d  daN:g..61/C18/2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 53 - \ndiscrete driver's pro-rata contribution is minimal compared to the infrastructure it \nnecessitates. PIOs also argue that the Commission should require PJM and the PJM \ntransmission owners to provide transparent reporting for major projects that compares \nincremental cost causation against pro-rata billing determinant recovery.220 \niii. \nDetermination \n95.\nWe deny the request for clarification.221  In the December Order, the Commission \nfound that NITS must be taken on a gross basis.222  The Commission did not address cost \nallocation for Network Upgrades needed to accommodate NITS (or related reporting \nrequirements) and we decline to do so here, finding those issues to be sufficiently distinct \nfrom the immediate issues in this proceeding and outside the scope of this proceeding. In \nany event, we note that these issues would be better addressed in a separate proceeding in \nwhich a record could be developed on these technical topics.223 \nb. \nNew Transmission Services  \n96.\nIn the December Order, the Commission—having found the Tariff unjust and \nunreasonable because it lacked relevant provisions with sufficient clarity and \ntransmission services that reflect Eligible Customers taking service on behalf of \nCo-Located Loads that are willing and able to limit their energy withdrawals—addressed \na just and reasonable replacement rate.224 \n220  Id at 7-8. \n221  PIOs' request for clarification is titled and presented as a request for \nclarification, id. at 1, and we treat it as such, noting that it does not meet the \nCommission's requirements for requests for rehearing. 18 C.F.R. § 385.713(c)(2); Pub. \nServ. Co. of Colo., 190 FERC ¶ 61,128, at P 24 (2025). \n222  December Order, 193 FERC ¶ 61,217 at P 195. \n223  See Mobil Oil Expl. & Prod. Serv. v. United Distrib. Cos., 498 U.S. 211, \n230-31 (1991) (\"An agency enjoys broad discretion in determining how best to handle \nrelated, yet discrete, issues in terms of procedures.\"); Tenn. Valley Mun. Gas Ass 'n v. \nFERC, 140 F.3d 1085, 1088 (D.C. Cir. 1998) (the Commission has \"broad discretion to \ndetermine when and how to hear and decide the matters that come before it\"); Stowers \nOil & Gas Co., 27 FERC ¶ 61,001, at 61,001 (1984) (\"The Commission, like other \nagencies, is generally master of its own calendar and procedures.\"). \n224  December Order, 193 FERC ¶ 61,217 at P 193. \n210 of 515"},{"page":212,"startToken":80409,"endToken":80787,"text":"Document AccessigiqW 42-YR1 8 - 34@cument.Filtd rEN9:g.61A8/2p,,aje Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 54 - \n97.\nThe Commission directed PJM to submit a compliance filing to modify its Tariff \nto require that the Eligible Customer taking transmission service on behalf of a \nCo-Located Load takes one of three transmission services: (1) NITS or Interim NITS, \n(2) a new FCD transmission service, or (3) a new NFCD transmission service.225  The \nCommission also established paper hearing procedures to determine the appropriate rates, \nterms, and conditions of the new transmission services.226  The Commission stated that \nInterim NITS is a new interim, non-firm transmission service, which allows an Eligible \nCustomer that has requested NITS on behalf of a Co-Located Load to take non-firm \ntransmission service that can be interrupted until the Network Upgrades necessary to \nprovide NITS are complete and the Co-Located Load can be designated as Network \nLoad.227 \n98.\nThe Commission stated that, under the FCD transmission service, Eligible \nCustomers will have the right to request transmission service on behalf of a Co-Located \nLoad up to a specified MW quantity, i.e., the contract demand. The Commission stated \nthat the FCD transmission service will have the same reservation and curtailment priority \nas existing firm transmission services, at the level of the contract demand. However, the \nCommission stated that, unlike Network Customers, the Eligible Customer taking the \nFCD transmission service on behalf of the Co-Located Load is not permitted to withdraw \nenergy from the PJM transmission system beyond the contract demand leve1.228 \n99.\nThe Commission stated that the new NFCD transmission service will be provided \nduring normal operations, on an as-available basis, and curtailed during emergency \noperations (i.e., it will be curtailed before existing firm transmission services and the new \nFCD transmission service). The Commission stated that, under this service, Eligible \nCustomers may reserve transmission service on behalf of a Co-Located Load as needed \nduring normal, non-emergency system operating conditions. The Commission stated that \nreservations under this service would be available only when there is available \ntransmission capacity, similar to existing non-firm transmission service options in the \nTariff  229 \n225 m \n226  M P 194. \n227 Jd. P 200. \n228 Jd. P 208. \n229  /d. P 215. \n211 of 515"},{"page":213,"startToken":80787,"endToken":81186,"text":"Dockiment AccessigP.V; qQ,18-.349curnent:Flild if)Ag:4A 8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 55 - \ni. \nBTMG \n(a) \nRequests for Clarification and/or Rehearing \n100. As to a replacement rate covering Eligible Customers taking transmission service \non behalf of load-only customers with BTMG, Industrials request clarification that the \nnew transmission services must be made available to those customers.23°  Industrials \nargue that Eligible Customers taking transmission service on behalf of load-only \ncustomers with BTMG should also be allowed to benefit from the new transmission \nservices.231 \n(b) \nDetermination \n101.\nAs explained above, we set aside, in part, the December Order and find that the \nTariff is unjust and unreasonable because it does not include transmission services that \nreflect Eligible Customers taking transmission service on behalf of loads with BTMG that \nare willing and able to limit their energy withdrawals from the transmission system under \ncertain conditions. Consistent with this new determination, we now direct PJM to revise \nits Tariff to extend the three new transmission services set forth in the December Order to \nEligible Customers taking service on behalf of load with BTMG that are willing and able \nto limit their energy withdrawals from the transmission system under certain conditions. \n102.\nSpecifically, we direct PJM to submit a compliance filing, within 60 days of the \ndate of this order, to modify its Tariff to require that the Eligible Customer taking \ntransmission service on behalf of Eligible Load takes one of three transmission services: \n(1) NITS or Interim NITS, (2) FCD transmission service, or (3) NFCD transmission \nservice.232  We find that it is just and reasonable for an Eligible Customer taking \ntransmission service on behalf of Eligible Load to elect, as one of the required \ntransmission services from which the Eligible Customer must choose, to take NITS for \nthe same reasons we made that finding with respect to Eligible Customers taking \ntransmission service on behalf of Co-Located Loads.233 \n103.\nEligible Customers, on behalf of the Eligible Loads that they represent, may \nchoose the transmission services that match their preferred use of the transmission \n230 Industrials Request for Clarification or Rehearing at 13-14. \n231m \n232  They must choose at least one of the required transmission services and may \ntake a combination of the FCD and NFCD transmission services. \n233  December Order, 193 FERC ¶ 61,217 at PP 195, 198. \n212 of 515"},{"page":214,"startToken":81186,"endToken":81584,"text":"Document AccessigRSg 2-k2-18-34@cument:Flild jpaqp:g61A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 56 - \nsystem; however, they must choose at least one of the required transmission services, and \nmay take a combination of the FCD and NFCD transmission services. In addition, in \ninstances where load with BTMG includes necessary control technologies and/or \nprotection systems that limit its energy withdrawals, we find that it is a just and \nreasonable replacement rate to allow an Eligible Customer taking transmission service on \nbehalf of Eligible Load to take and be charged for new types of transmission service that \nare alternatives, and not equivalent, to NITS: FCD and NFCD transmission services.234 \nii. \nUndue Discrimination \n(a) \nRequests for Clarification and/or Rehearing \n104.\nExelon and FirstEnergy argue that the Commission granted an undue preference to \nCo-Located Loads in requiring new forms for transmission services.235  Exelon and \nFirstEnergy charge that the Commission failed \"to explain why system protection \nschemes installed in [non-Co-Located Load] configurations would not provide similar \nbenefits and be deserving of preferential rates.\"236  Exelon and FirstEnergy contend that \nthe totality of the burdens and benefits of grid interconnection justify charging \nCo-Located Load the same rate as all other transmission customers. Exelon and \nFirstEnergy assert that the Commission's new transmission service reduces the share of \nembedded costs for Co-Located Loads compared to all other users who receive the same \nbenefits. \n105. Industrials request clarification that the new transmission services must be made \navailable to load-only customers with load flexibility, minimal retail BTMG, or no retail \nBTMG.237  Industrials contend that this clarification would reduce the risk of undue \ndiscrimination because \"[m]any large load customers can curtail their load at key times \nand control the amount of transmission service they use and when they use it.\"238 \nIndustrials also argue that this clarification would avoid potential cost shifts that would \noccur if similarly situated customers were given different options depending only on \nwhether they have small generators on site. Industrials assert that this clarification would \n234  See id. P 205. \n235  Exelon and FirstEnergy Request for Rehearing at 36-39. \n236  Id at 38. \n237  Industrials Request for Clarification or Rehearing at 13 (\"Such an approach \nwould align with the natural gas industry's long history of large gas consumers electing \nhow much service they purchase.\"); see also id. at 6-7. \n238  Id at 14. \n213 of 515"},{"page":215,"startToken":81584,"endToken":82001,"text":"Document A„essigPA 22q-Agg1.8-3g9 Urnent:Flild \ng_61A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 57 - \nextend the optionality of the new transmission services to retail BTMG and load-only \ncustomers.239  Lastly, Industrials argue that this clarification could make the PJM \ntransmission planning process more efficient.24° \n(b) \nDetermination \n106. As an initial matter, we dismiss the argument that the new transmission services \nwould be unduly discriminatory or preferentia1.241  First, we dismiss this argument for \nlack of finality. Rule 713(b) of the Commission's Rules of Practice and Procedure \npermits requests for rehearing \"of any final decision or other final order in a \nproceeding.\"242 A final decision is one that imposes an obligation, denies a right, or fixes \nsome legal relationship as a consummation of the administrative process.243  The \nDecember Order did not make a final decision on the rates, terms, and conditions for the \nnew transmission services.244  Instead, the Commission found that \"additional record \nevidence is needed\" and set these issues for paper hearing procedures.245  Setting a matter \n239  Id. at 14-15. \n24°  Id at 15. \n241  Exelon and FirstEnergy Rehearing Request at 19-20, 30-31, 36-39, 52-53; \nIndustrials Request for Clarification or Rehearing at 13-14. Further, as discussed above, \nwe set aside the December Order, in part, and find in this order that it is just and \nreasonable for Eligible Customers taking transmission service on behalf of load with \nBTMG to take one of three transmission services: (1) NITS or Interim NITS, (2) FCD \ntransmission service, or (3) NFCD transmission service. We therefore do not address \nwhether it would be unduly discriminatory or preferential if the replacement rate were to \nnot allow Eligible Customers taking transmission service on behalf of load with BTMG \nto take those services. \n242  18 C.F.R. § 385.713(b); see also 16 U.S.C. § 8251(a) (stating that parties \n\"aggrieved by an order issued by the Commission in a proceeding . . . may apply for a \nrehearing within thirty days after the issuance of such order\"). \n243  Reliable Automatic Sprinkler Co., Inc. v. Consumer Prod. Safety Comm'n, \n324 F.3d 726, 731 (D.C. Cir. 2003) (\"Final agency action `mark[s] the consummation of \nthe agency's decision making process' and is `one by which rights or obligations have \nbeen determined, or from which legal consequences will flow'\") (quoting Bennett v. \nSpear, 520 U.S. 154, 178 (1997)). \n244  December Order, 193 FERC ¶ 61,217 at P 219. \n245 id. \n214 of 515"},{"page":216,"startToken":82001,"endToken":82520,"text":"Document Accessig@SP; 2q-Aqtql.8-34@ument:Flild ifa'qg:g.61A8/ pate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 58 - \nfor paper briefing \"is interlocutory: it constitutes a procedural step that does not impose \nan obligation, deny a right, or fix some legal relationship as a consummation of the \nadministrative process.\"246  Without a final decision on the rates, terms, and conditions \nfor the new transmission services, it is \"premature\" to argue or evaluate on rehearing \nwhether those as-yet-undeveloped services would be unduly discriminatory.247 At \nbottom, \"the claimed harms are based on speculation regarding potential action that the \nCommission could take, rather than any action the Commission has actually taken.\"248 \nAccordingly, because Commission action is not final and is to be succeeded by further \nCommission action, we dismiss the undue discrimination argument.249 \n107. In any event, we also dismiss the undue discrimination argument for the \nindependent reason that it is outside the scope of this proceeding. This proceeding \naddresses Eligible Customers taking transmission service on behalf of Eligible Load with \nassociated generation, such as through Co-Location Arrangements and BTMG \n246  Algonquin Gas Transmission, LLC, 175 FERC ¶ 61,150, at PP 1, 5-8 (2021); \nsee also Kan. Elec. Power Coop., Inc., 181 FERC ¶ 61,017, at P 10 (2022) (finding that, \nbecause \"the Commission found that its preliminary analysis indicated that the Formal \nChallenge and Complaint raised issues of material fact that could not be resolved on the \nrecord before the Commission and are more appropriately addressed in hearing and \nsettlement judge procedures,\" \"here, Commission action is not final and is to be \nsucceeded by further Commission action,\" thus \"a request for rehearing may be \ndismissed\"); City of Hamilton, Ohio, 82 FERC ¶ 61,349, at 62,359 (1998) (\"Setting this \nmatter for a trial-type hearing does not impose an obligation, deny a right, or fix some \nlegal relationship as a consummation of the administrative process.\"). \n247  Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8; see also, e.g., F.T.C. \nv. Standard Oil Co. of Cal., 449 U.S. 232, 244 n.11 (1980) (Standard Oil) (explaining the \nfact that a \"challenge may be mooted in adjudication warrants the requirement that \n[party] pursue adjudication, not shortcut it\"); MediNatura, Inc. v. Food & Drug Admin., \n998 F.3d 931, 939 (D.C. Cir. 2021); CSX Transp., Inc. v. Surface Transp. Bd., 774 F.3d \n25, 30 (D.C. Cir. 2014) (explaining that it is a \"good sign\" that action is non-final when \nfurther agency processes may eliminate need for review). \n248  Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8. \n249  See, e.g., Cove Mountain Solar, LLC, 179 FERC ¶ 61,179, at P 7 (2022) \n(dismissing, in part, rehearing request on finality grounds because the Commission had \nestablished hearing and settlement judge procedures); Westlands Transmission, LLC, \n177 FERC ¶ 61,175, at P 4 (2021); BridgeTex Pipeline Co., LLC, 164 FERC ¶ 61,111, \nat PP 10-12 (2018); Pac. Gas & Elec. Co., 162 FERC ¶ 61,246, at PP 6-7 (2018); Talen \nEnergy Mktg., LLC, 158 FERC ¶ 61,077, at PP 3-4 (2017). \n215 of 515"},{"page":217,"startToken":82520,"endToken":82977,"text":"Document AccessigPs,er ; qq-Ag-18_39,99ument:FlAd rfa' ..9:,?_61A8/2 p%-te Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 59 - \narrangements.25°  In an order issued concurrently, the Commission is initiating a separate \nshow cause proceeding in Docket No. EL26-67-000 to address, among other things, \nwhether the Tariff remains just and reasonable and not unduly discriminatory or \npreferential without provisions addressing transmission services that reflect flexible large \nloads251  that are willing and able to limit their energy withdrawals from the transmission \nsystem under certain conditions. Accordingly, it is beyond the scope of this \nproceeding—and within the scope of the separate proceeding—to argue that the new \ntransmission services should be extended to Eligible Customers taking transmission \nservice on behalf of flexible large loads. We thus dismiss this argument as outside the \nscope of this proceeding.252  The Supreme Court has made clear that the Commission \n\"enjoys broad discretion in determining how best to handle related, yet discrete, issues in \nterms of procedures.\"253  The Supreme Court has \"expressly approved a[] . . . \nCommission decision to treat [an] issue separately where a different proceeding would \ngenerate more appropriate information and where the agency was addressing the \nquestion\"254—as is true as to the other proceeding. As courts have further recognized, \n\"[w]hile the statute requires the Commission to act upon a finding that rates . . . are unjust \nor unreasonable, it nowhere mandates that having made such a finding with respect to a \ndiscrete issue, the Commission must reopen and reevaluate all other aspects of the filed \nrate.\"255  Here, while the Commission addresses Co-Location Arrangements and BTMG, \nthose findings do not necessitate that the Commission reevaluate transmission services \nthat Eligible Customers take on behalf of other types of load.256 \n250  See, e.g., December Order, 193 FERC ¶ 61,217 at P 2. \n251  Flexible large loads are a subset of large loads that are not co-located with \ngeneration but that are willing and able to limit their use of the transmission system under \ncertain conditions. \n252  See PJM Interconnection, L.L.C., 126 FERC ¶ 61,030, at P 16 (2009); see also \nLa. Pub. Serv. Comm'n v. Entergy Corp., 169 FERC ¶ 61,179, at P 9 (2019); N.Y. Indep. \nSys. Operator, Inc., 127 FERC ¶ 61,042, at P 26 (2009); Union Elec. Co., 113 FERC \n¶ 61,320, at P 8 (2005); Cal. Indep. Sys. Operator Corp., 113 FERC ¶ 61,133, at P 24 \n(2005). \n253  Mobil Oil, 498 U.S. at 230-31; see supra note 226. \n254  Mobil Oil, 498 U.S. at 230-31. \n255  Colo. Off of Consumer Couns. v. FERC, 490 F.3d 954, 956 (D.C. Cir. 2007). \n256  Industrials Request for Clarification or Rehearing at 6-7, 13-14. \n216 of 515"},{"page":218,"startToken":82977,"endToken":83450,"text":"Document AccessigPSg 2A-2§A18-3Q@Cument:Flil d rFa'Np:g.61A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 60 - \n108.\nIn any event, while we dismiss the undue discrimination argument for the reasons \nexplained above, we address the argument below to provide clarification to the parties. \nAs relevant here, Industrials argue that it is unduly discriminatory for \"load-only \ncustomers with load flexibility\" to not be eligible for the new transmission services.257 \nIndustrials contend this creates undue discrimination \"between customers with generation \nand customers without generation,\" who Industrials state \"can curtail their load at key \ntimes and control the amount of transmission service they use and when they use it.\"258 \nWe refer in this subsection to these \"load-only customers with load flexibility,\" as \ndescribed by Industrials, as \"flexible loads.\" \n109.\nThe Commission \"has wide discretion to determine what constitutes undue \ndiscrimination.\"259  Discrimination is undue when there is a difference in rates or terms \nbetween similarly situated entities that is not justified by some legitimate factor.26° \n\"[D]istinct operating characteristics\" can render entities not similarly situated.261  Here, a \nrelevant distinct operating characteristic is that Eligible Load has an associated generator \n(Co-Located Generator or BTMG) as part of the Co-Location Arrangement or load \nconfigured with BTMG, and flexible load does not. The presence of these associated \ngenerators is a material factor in analyzing eligibility for the new transmission services. \nWe anticipate, based on the record here, that Eligible Customers taking transmission \n257  Id. at 13-14. \n258  Id. More generally, Industrials argue that the new transmission services should \nbe extended to all transmission customers. Id. Because we dismiss the undue \ndiscrimination argument as nonfinal and outside of scope, we need not address the \nargument that the new transmission services should be extended to all transmission \ncustomers (an even broader, and thus less similar, category). Moreover, we have, in the \nDecember Order and in this order, sufficiently discussed eligibility for the new \ntransmission services, including by explaining that it is not unduly discriminatory to limit \nthe new transmission services to Eligible Customers taking transmission service on \nbehalf of Eligible Load, such that we need not further address extending the services to \nall transmission customers. \n259  Mo. River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019) (citation \nmodified). For purposes of the undue discrimination analysis in this order, when we refer \nto Eligible Customers taking transmission service on behalf of Eligible Load as not \nsimilarly situated to Eligible Customers taking transmission service on behalf of flexible \nload, we are referring to Eligible Customers only insofar as they take transmission \nservice on behalf of specific Eligible Loads or flexible loads. \n260 Sw. Power Pool, Inc., 192 FERC 1161,058, at P 175 (2025). \n261  Sw. Power Pool, Inc., 193 FERC ¶ 61,198, at P 82 (2025). \n217 of 515"},{"page":219,"startToken":83450,"endToken":83938,"text":"Do6urnent Accessigsp; q-q2 g-18 _3112ument:Fl-il d rrAg9: (261/8,8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 61 - \nservices on behalf of Eligible Loads would rely regularly in whole or in part on their \nassociated generators, not on the transmission system, while Eligible Customers taking \ntransmission services on behalf of flexible loads generally would rely entirely on the \ntransmission system, even as they sometimes shift the amount of energy they take. This \ndynamic creates different transmission system usage, which is relevant to transmission \nservices, charges, and planning.262 \niii. \nContract Demand \n(a) \nRequest for Rehearing \n110. Exelon and FirstEnergy argue that the Commission has departed from decades of \nprecedent that NITS is based on the entire gross load of the Network Customer, and the \nCommission failed to adequately explain its departure.263  Exelon and FirstEnergy \nhighlight, for example, the Commission's statement that it would be inconsistent with \ncost causation principles to require Eligible Customers taking transmission service on \nbehalf of Co-Located Loads that limit their energy withdrawals to take NITS on a gross \ndemand basis.264  Exelon and FirstEnergy allege that the Commission recognized that \n262  For the reasons in this Part, we also reject Industrials' request for clarification \non this issue. Industrials Request for Clarification or Rehearing at 13-14. \n263  Exelon and FirstEnergy Request for Rehearing at 22-26 (citing Nat'l R.R. \nPassenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020) (Amtrak); Fla. \nPower & Light, 113 FERC ¶ 61,290 (2005), order on reh'g, 116 FERC ¶ 61,012 (2006), \naff'd, 264 F. App'x 4 (D.C. Cir. 2008) (Florida Power & Light); Idaho Power Co., \n106 FERC ¶ 61,329 (2004) (Idaho Power); Ameren Servs. Co. v. Prairieland Energy Inc., \n131 FERC ¶ 61,125 (2010) (Ameren); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015) \n(APS); Preventing Undue Discrimination & Preference in Transmission Serv., Order \nNo. 890, 118 FERC ¶ 61,119, order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 \n(2007), order on reh'g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh'g, \nOrder No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, \n129 FERC ¶ 61,126 (2009); Promoting Wholesale Competition Through Open Access \nNon-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by \nPub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) \n(cross-referenced at 75 FERC ¶ 61,080), order on reh'g, Order No. 888-A, FERC Stats. \n& Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh'g, Order \nNo. 888-B, 81 FERC ¶ 61,248 (1997), order on reh'g, Order No. 888-C, 82 FERC \n¶ 61,046 (1998), aff'd in relevant part sub nom. Transmission Access Pol'y Study Grp. v. \nFERC, 225 F.3d 667 (D.C. Cir. 2000), aff'd sub nom. N.Y. v. FERC, 535 U.S. 1 (2002). \n264  Exelon and FirstEnergy Request for Rehearing at 28 (citing December Order, \n193 FERC ¶ 61,217 at P 199). \n218 of 515"},{"page":220,"startToken":83938,"endToken":84369,"text":"Document AccessigP.Sir; 2.q-4Qq18-31:Ncumert:Fhtd rpaqp:g.61/4812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 62 - \nthese customers use the transmission system for some services, such as regulation and \nblack start, but for the customer not to use the system for other services makes the \ncustomer partially integrated, contrary to Order No. 888-A.265  Exelon and FirstEnergy \ncontend that the Commission has consistently rejected attempts to create a new third type \nof transmission service by parties whose reasons are exactly the same as the reasons the \nCommission used to justify its decision to establish Contract Demand transmission \nservice based on net load, such as the notion that Co-Located Loads impose less burden \non the grid. Exelon and FirstEnergy argue that the assessment of NITS is not based on \nactual use, that Network Customers pay the full rate but NITS charges are allocated based \non contribution to system peak.266  Exelon and FirstEnergy contend that Network Load \nneeds to be able to call on service regardless of actual usage and utilities have an \nobligation to serve that load. \n(b) \nDetermination \n111. We continue to find that it is just and reasonable to charge for FCD and NFCD \ntransmission services based on the contract demand.267  We disagree with Exelon and \nFirstEnergy's arguments that the Commission erred in not requiring the new FCD and \nNFCD transmission services be charged on a gross load basis and that this decision \nviolates precedent.268  As an initial matter, Exelon and FirstEnergy appear to suggest that \nthe charges for these services would be based \"on actual use\" or \"on net . . . load.\"269  As \nexplained in the December Order, however, transmission customers taking the new FCD \nor NFCD transmission service would \"be charged based on their contract demand \nirrespective of usage.\"27°  We continue to find that this is a just and reasonable alignment \nof costs and benefits.271  In particular, for the new FCD transmission service, because \ntransmission customers taking this service would agree to limit withdrawals to the \n265  Id. at 24. \n266  Id. at 26-29 (citing Indicated TOs June 3, 2025 Answer, Powers Decl.). \n267  December Order, 193 FERC ¶ 61,217 at P 2. \n268  Exelon and FirstEnergy Request for Rehearing at 22-30. \n269 m  \n270  December Order, 193 FERC ¶ 61,217 at PP 211, 216 (\"Eligible Customers \ntaking the [NFCD] transmission service on behalf of Co-Located Loads will be charged \nfor transmission and ancillary services on an as-reserved contract demand basis, based on \nthe reserved contract demand amount of transmission service (except as noted[)].\"). \n271  Id. \n219 of 515"},{"page":221,"startToken":84369,"endToken":84822,"text":"Dodurikent AccesigPSK 22q'2116%18  _ 3Q99u me n t:Fl\nrp~ge:Agq8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 63 - \ncontract demand through the mandatory implementation of necessary control \ntechnologies and/or protection systems, PJM would only plan the transmission system, \nprocure generation capacity, and be obligated to provide transmission service up to that \ncontract demand.272  Similarly, for the new NFCD transmission service, PJM would only \nbe obligated to provide transmission service up to the reserved contract demand when \nthere is sufficient available transmission capacity to provide the requested service.273  If \nthe transmission customers taking the new FCD and NFCD transmission services were \ncharged for that service on a gross load basis, they could be charged for more load than \nPJM is obligated to plan for, procure generation capacity for, or otherwise serve when \ntransmission capacity is available. And—because these customers would be charged \nbased on their contract demand irrespective of usage—they would be unable to avoid \nload-ratio cost responsibility by modifying their load at a particular time.274 \n112. Exelon and FirstEnergy argue that the new contract demand transmission services \nare inconsistent with Commission precedent.275  Exelon and FirstEnergy contend that the \nCommission in the December Order contravened Order No. 888-A, in which the \nCommission rejected the notion of Network Customers \"partially integrat[ing]\" or \n\"splitting a discrete load\" because \"such a split system creates the potential for a \ncustomer to game the system thereby evading some or all of its load-ratio cost \nresponsibility for network services.\"276  We continue to find that the new contract \ndemand transmission services do not violate Order No. 888-A.277  Most simply, Order \nNo. 888-A rejected splitting load between NITS and PTPS at the same point of \ndelivery.278  That kind of splitting between transmission services at the same point of \ndelivery remains barred under the December Order: Eligible Customers also cannot split \n272 Id.; see also id. PP 215-216 (explaining that an Eligible Customer taking NFCD \ntransmission service may reserve service as needed when the service is available, and the \nEligible Customer will be charged on an as-reserved contract demand basis). \n273  Id; see also id. PP 215-216 (explaining that an Eligible Customer taking NFCD \ntransmission service may reserve service as needed when the service is available, and the \nEligible Customer will be charged on an as-reserved contract demand basis). \n274 Id. P 211. \n275  Exelon and FirstEnergy Request for Rehearing at 22-30. \n276  Id at 23-24 (quoting Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 \nat 30,259) (internal quotation marks omitted). \n277  December Order, 193 FERC ¶ 61,217 at P 211. \n278  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,260. \n220 of 515"},{"page":222,"startToken":84822,"endToken":85307,"text":"Document Accessig0Sg 2A-ArRl 8 - 3Q9c ument:Fht d rFi@fie: g.4118/2pAte Filed: 10116/2026 \nDocket No. EL25-49-002, et al. \n- 64 - \nload between NITS and FCD or NFCD transmission service at the same point of delivery. \nFurther, under the new contract demand services, load is neither split nor partially \nintegrated. Instead, load is capped at contract demand and Eligible Customers taking \ntransmission service on behalf of Co-Located Loads are charged for that contract \ndemand, irrespective of usage. Moreover, the rationale underlying Order No. 888-A—\ngaming—is also not present here.279  The new contract demand transmission services will \nhelp avoid a cost shift to other transmission customers because Eligible Customers will \nnot be able to reduce their load-ratio share to avoid paying transmission costs or capacity \ncosts because their amount of FCD transmission service is fixed.28° \n113. Exelon and FirstEnergy further argue that the Commission contravened Order \nNo. 888-A \"[b]ecause the Commission has recognized that the [contract demand \ntransmission service] customers use the transmission system for some services (such as \nload following and black start),\" which would render those customers \"partially \nintegrated.\"28I  We disagree. Receiving ancillary services, such as regulation and black \nstart, does not \"integrate\" a transmission customer into the transmission network—and \nparticularly not in the manner that NITS does. Specifically, Order No. 888-A clarified \nthat a \"request for network service is a request for the integration of a customer's \nresources and loads,\"282  and a PTPS customer is not integrated, as recognized by Order \n279  Id. \n288  December Order, 193 FERC ¶ 61,217 at P 211. We also note that the \nCommission justified its findings in Order No. 888-A by discussing \"several fundamental \noperational problems associated with allowing partial network service.\" Order \nNo. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,260. Those operational problems are not \nraised or present here because neither FCD nor NFCD transmission service are based on \nthe Eligible Customer's load ratio. Further, Exelon and FirstEnergy suggest that the \nDecember Order is inconsistent with Order No. 890. Exelon and FirstEnergy Request for \nRehearing at 25-26 (citing Order No. 890, 118 FERC ¶ 61,119, order on reh'g, Order \nNo. 890-A, 121 FERC ¶ 61,297, order on reh'g, Order No. 890-B, 123 FERC ¶ 61,299 \n(2008), order on reh'g, Order No. 890-C, 126 FERC 1161,228, order on clarification, \nOrder No. 890-D, 129 FERC ¶ 61,126). While they do not cite a particular portion, they \nappear to be referring to a section that reiterates the already discussed portion of Order \nNo. 888-A. Order No. 890, 118 FERC ¶ 61,119 at P 1619 (citing Order No. 888-A, \nFERC Stats. & Regs. ¶ 31,048 at 30,260-61). Our findings as to Order No. 888-A thus \napply to Exelon and FirstEnergy's citation to Order No. 890. \n281  Exelon and FirstEnergy Request for Rehearing at 24. \n282  Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,260. \n221 of 515"},{"page":223,"startToken":85307,"endToken":85759,"text":"Dodument Accessigi SP? 4\"2-Yq.g18-3RP.cument:Flald IFA99-  e?..82,48/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 65 - \nNo. 888-A.283  Nonetheless, PTPS customers pay for and use ancillary services, including \nregulation service. Therefore, whether an Eligible Customer taking transmission service \non behalf of Co-Located Load could receive ancillary services and/or black start service \nhas no bearing on whether it is \"integrated\" as a Network Customer. \n114. Exelon and FirstEnergy also argue that the December Order is inconsistent with \nother Commission precedent.284  These cases do not undermine the December Order. In \nseveral cited cases, Network Customers chose to take NITS and sought to receive the \nbenefits of NITS, specifically the right to withdraw energy from the transmission system \nwhen their own resources were not available, while arguing that they should be charged a \nlower rate based on their usage.285  For example, Amtrak relied on the transmission \nsystem when the nearby generator was not available, and sought to maintain that \narrangement and ability to withdraw energy to meet its gross load at any time, while \npaying NITS.286  Here, the new FCD and NFCD transmission services set up new \nobligations and benefits—as well as charges on that new basis.287  For example, under \n283  Id at 30,259-60 (presenting binary of \"fully integrated or not integrated\"—with \nfull NITS or no NITS, respectively—in opposition to \"partially integrated,\" which would \ninclude NITS and PTPS). \n284  Exelon and FirstEnergy Request for Rehearing at 23-30 (citing Amtrak, \n171 FERC 1161,237, order on reh 'g, 173 FERC 1161,043 (2020); Florida Power & Light, \n113 FERC 1161,290, order on reh g, 116 FERC 1161,012, aff'd, 264 F. App'x 4; Idaho \nPower, 106 FERC ¶ 61,329; Ameren, 131 FERC ¶ 61,125; APS, 151 FERC ¶ 61,191). \n285  E.g., Amtrak, 173 FERC ¶ 61,043 at P 12 (\"What Amtrak seeks to do is carve \nout from network service charges the power supplied by Safe Harbor. Such an outcome \nis impermissible under the PJM Tariff and inconsistent with the nature of NITS.\"). \n286  See id P 13 (rejecting Amtrak's rehearing request and explaining that \"Amtrak \nseeks the ability to select when it will use and pay for NITS (i.e., only when inflows \noccur through PPL's Manor Substation\")). \n287  December Order, 193 FERC ¶ 61,217 at PP 208, 210, 211, 212. Indeed, the \nDecember Order also responds to new circumstances not present in the cited cases—\nnamely, the proliferation of potential Co-Location Arrangements. Even if the cited cases \nwere controlling here, we find these new circumstances would warrant the Commission's \ndecision to charge for FCD and NFCD transmission services based on the contract \ndemand. \n222 of 515"},{"page":224,"startToken":85759,"endToken":86217,"text":"Document AccessigPS#; qq-Aeg18-3R@cument:Fl-Ad IEN9:(W.748/2p2aje Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 66 - \nFCD transmission service, the Eligible Customer can rely on the service only up to the \nlevel of its contract demand.288 \n115. In particular, Exelon and FirstEnergy maintain that the December Order is \ninconsistent with Florida Power & Light, which they characterize as standing for the \nproposition that \"the gross load construct [i]s most appropriate,\" \"even in the case of \nphysical impossibility of serving the entire load.\"289  As an initial matter, there is no \n\"physical impossibility exception\"29°  in the December Order because the new FCD and \nNFCD transmission services are based on legally capped demand, not \"physical \nimpossibility.\"29' Specifically, while in Florida Power & Light the \"physical \nimpossibility\" was a constraint on the transmission system, which prevented the entire \nload from being served by the transmission system,292  no such physical constraint on the \ntransmission system exists for an Eligible Customer taking FCD and/or NFCD \ntransmission service on behalf of a Co-Located Load. Rather, such Eligible Customers \nmay elect to take transmission service at a contract demand level less than the amount of \nthe entire load and commit to limiting their withdrawals from the transmission system to \nthe contract demand level. Regardless, in Florida Power & Light, the Commission only \ndiscussed \"physical impossibility\" in dicta.293  In that discussion, the Commission \n288  Id. We further reiterate that the absence of this type of option is unjust and \nunreasonable. Id. P 177. \n289 E.g., Exelon and FirstEnergy Request for Rehearing at 24-25. \n298  Florida Power & Light, 113 FERC ¶ 61,290 at P 7. \n291  December Order, 193 FERC ¶ 61,217 at PP 208, 210, 211, 212. To the extent \nExelon and FirstEnergy characterize their argument addressed in this Part as directed \ntoward our \"unjust and unreasonable\" findings and not the replacement rate, Exelon and \nFirstEnergy Request for Rehearing at 22-23, we reject this argument based on the same \nsubstantive reasons included in this Part. \n292  Florida Power & Light, 113 FERC ¶ 61,290 at PP 7-8. \n293  Id. The Commission began by generally rejecting the prospect of alternative \nproposals from individual customers because of the potential administrative and undue \ndiscrimination concerns with setting individual-customer-specific rates (but the \nCommission did approve the prospect of alternative proposals from utilities). Id. P 6. In \nother words, the cited adjudications, see, e.g., Exelon and FirstEnergy Request for \nRehearing at 23-25; see also id at 27, are additionally inapposite here to the extent they \ninvolved proceedings where only individual customers that claimed to limit their use of \nthe transmission system sought to alter the rates, terms, and conditions of its transmission \nservice and obtain rates and terms for themselves. \n223 of 515"},{"page":225,"startToken":86217,"endToken":86594,"text":"Document AccessigsA: 4q-A6-,A-18-3c9cument:Filla rPAg9: gEg48/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 67 - \nnonetheless did not even rule out the prospect of considering \"physical impossibility\" in a \nmore generally applicable setting where the impossibility could be administered, verified, \nand backed by technological and legal constructs—rather than on an ad hoc basis due to a \ntransmission customer's mere assertions that it was particularly deserving of a \nspecially-designed and administered service.294 \niv. \nAlleged Alternatives to FCD and NFCD \nTransmission Services  \n(a) \nRequest for Rehearing \n116. Exelon and FirstEnergy contend that the Commission \"fail[ed] to demonstrate that \n[the new transmission services] are just and reasonable\" because there are already \nexisting mechanisms for customers to reduce load or use other generation in order to \nreduce withdrawals.295  Exelon and FirstEnergy maintain that PJM's demand response \nrules are available to Co-Located Loads and the Commission fails to explain why such \nrules are inadequate here. Indeed, Exelon and FirstEnergy assert, the Commission stated \nthat those rules are just and reasonable for Co-Located Loads taking NITS. \n(b) \nDetermination \n117.\nWe do not find Exelon and FirstEnergy's argument availing. The mere fact that \nthere may be preexisting mechanisms in the Tariff to accomplish something (even \nassuming that they are equivalent, which we do not) does not mean that adding an \nadditional mechanism is not just and reasonable. Exelon and FirstEnergy offer no \njustification or citation to support the proposition that having multiple provisions targeted \nat similar objectives is not just and reasonable. \n118.\nFurther, demand response operates differently from the contract demand \ntransmission services. In the first place, demand response is not a transmission service. \nAnd demand response presents a different set of benefits and burdens—NFCD \ntransmission service would be curtailed earlier than demand response resources would be \ncalled on and can be instructed to curtail without any notification (unlike most demand \nresponse resources).296  FCD transmission service, on the other hand, is a firm \ntransmission service with the same curtailment priority as existing firm transmission \n294  Florida Power & Light, 113 FERC ¶ 61,290 at PP 7-8. \n295  Exelon and FirstEnergy Request for Rehearing at 36-37. \n296  December Order, 193 FERC ¶ 61,217 at P 215; see also infra Part VI.G.4. \n224 of 515"},{"page":226,"startToken":86594,"endToken":86964,"text":"Document A„„sigPV; ZAZ*18-34Pcurnent:Flita ?AV:4 748/2We Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 68 - \nservices, at the level of contract demand.297  In addition, PJM would not plan for any \nfuture load growth for either FCD or NFCD transmission service once the contract \ndemand level of each transmission service is established. As to Interim NITS, that \ntransmission service serves a different function than demand response because it allows \nEligible Customers to begin taking a limited, non-firm transmission service on behalf of \nCo-Located Load before the transmission system is capable of reliably providing NITS at \ntheir requested level. \nv. \nProtection Systems  \n(a) \nRequest for Rehearing \n119.\nExelon and FirstEnergy argue that the Commission's emphasis on protection \nsystems is arbitrary and capricious because it is in tension with the Commission's open \naccess policies. Exelon and FirstEnergy assert that generators have an interest in \ndesigning captive arrangements where customers cannot access alternative supply, which \nis contrary to the Commission's open access policies in Order No. 888.298  Exelon and \nFirstEnergy argue that generators will convert their interconnection facilities into \ntransmission assets and then install relay systems that make load captive to its \ngeneration.299  Exelon and FirstEnergy view this arrangement as akin to the problem of \ntransmission owners using their control of transmission facilities to refuse to deliver \nenergy produced by competitors or to deliver competitors' power on less favorable \nterms.300 \n120. Exelon and FirstEnergy argue that the Commission erred in minimizing the fact \nthat protection systems can and have failed.30' Exelon and FirstEnergy point out that the \nCommission recognizes that protection systems fail, and to address this risk, directed \nPJM to apply a penalty rate for the new transmission services. But Exelon and \nFirstEnergy allege that assessing penalties after the fact does not remediate the reliability \nimplications of faulty protection systems. Exelon and FirstEnergy also argue that \nprotection systems \"do not protect the grid from real impacts that occur even when there \n297  December Order, 193 FERC ¶ 61,217 at P 208. \n298  Exelon and FirstEnergy Request for Rehearing at 39-40. \n299  Id. at 40. \n388  Id (citing N.Y. v. FERC, 535 U.S. at 8-9). \n301  Id. at 39-41. \n225 of 515"},{"page":227,"startToken":86964,"endToken":87271,"text":"Document AccessigPSA 22q-AA18  _ 31:29c u men t:Fl \nd \ngA8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 69 - \nis consumption by a co-located customer but no net withdrawal, such as the impacts of \nload and voltage spikes and oscillations.\"3°2 \n(b) \nDetermination \n121.\nWe address both arguments in turn. First, the contemplated use of necessary \ncontrol technologies and/or protection systems is not inconsistent with the Commission's \nopen access policies. Co-Location Arrangements are voluntary. The December Order \ndoes not mandate that any Co-Located Load or Co-Located Generator enter into a \nCo-Location Arrangement. In other words, contrary to Exelon and FirstEnergy's \nassertions, the Commission is not forcing any entity into being a captive customer, as \nthey would have the option to connect to the transmission system and take NITS like any \nother Network Customer. \n122.\nSecond, we dismiss the argument regarding protection system failure and the risks \nthey address for lack of finality.303  The December Order did not make a final decision on \nrequired technology and what appropriate remedies would be for failure of that \ntechnology.304  Instead, the December Order set those issues for paper hearing \nprocedures.3°' In any event, the Commission recognized that protection systems, like \nmany technologies, in rare instances can fail; accordingly, the Commission ordered paper \nbriefing on technical requirements to address reliability risks and remedial actions.306  We \nalso note that it is possible that the remedial actions could remediate the reliability \nimplications of such a failure. Further, whatever risks are not avoided by a facility's \nnecessary control technologies and/or protection systems will be studied in the relevant \nstudy processes. \n3°2  Id at 39. \n3°3  See supra P 106. \n3°4  December Order, 193 FERC ¶ 61,217 at P 177. \n3°5  Id. P 178. \n3°6  Id P 212. \n226 of 515"},{"page":228,"startToken":87271,"endToken":87612,"text":"Document AccessigPV; 2-442-VA18-349cument:FlAd rfasqv:g.w.8/2ppe Filed: 10116/2026 \nDocket No. EL25-49-002, et al. \n- 70 - \nvi. \nBenefits of FCD and NFCD Transmission Services \n(a) \nRequest for Rehearin \n123.\nExelon and FirstEnergy allege that the Commission is wrong to suggest that FCD \nand NFCD transmission services will promote efficiency or change siting.307  Exelon and \nFirstEnergy argue that planning and siting depend on physics and engineering of the grid, \nnot whether transmission service is charged on a gross or net load basis. Exelon and \nFirstEnergy argue that the Commission's decision to require FCD and NFCD \ntransmission services does not change how the study process should work. Exelon and \nFirstEnergy warn that, \"[i]f transmission providers are forced to pretend a 500 MW load \nis only 50 MW, or even that it is zero . . . it will threaten reliability and resource \nadequacy.\"308  Exelon and FirstEnergy maintain that no loads should be taken out of the \nbroader planning process, and there is no support for the suggestion that regional \nplanning needs are reduced because of FCD and NFCD transmission services. Exelon \nand FirstEnergy argue that the Commission's decision on PJM's retail BTMG netting \nrules and the Commission's concerns about resource adequacy and cost shifting cannot \nbe reconciled with the Commission's proposed structure for the new transmission \nservices.309 \n124.\nExelon and FirstEnergy state that the Commission failed to point to any other \ntariff where these new transmission services have been required by the Commission.310 \n(b) \nDetermination \n125. As an initial matter, we dismiss this argument for lack of finality.311  The \nDecember Order did not make a final decision on the rates, terms, and conditions for the \nnew FCD and NFCD transmission services.312  Instead, the Commission found that \n\"additional record evidence is needed\" and set these issues for paper hearing \n307  Exelon and FirstEnergy Request for Rehearing at 47-48. \n3\" Id at 48. \n309  Id. at 48-49. \n310  Id. at 36. \n311  See supra P 106. \n312  December Order, 193 FERC ¶ 61,217 at P 219. \n227 of 515"},{"page":229,"startToken":87612,"endToken":88048,"text":"Document Accessigi?p; 2,q-2q:&18 _31_26)9ument:Fl il d  L'p:(26g8,8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 71 - \nprocedures.313  Without a final decision on the rates, terms, and conditions for the new \nFCD and NFCD transmission services, it is \"premature\" to argue or evaluate on rehearing \nwhether those as-yet-undeveloped services would affect efficiency or siting.314 \n126. In any event, while Exelon and FirstEnergy appear to direct this argument toward \nthe replacement rate, we addressed these topics in our discussion of the Commission's \nFPA section 206 step one finding above. In short, we continue to find that the Tariff is \nunjust and unreasonable because it does not include transmission services that reflect \nEligible Customers taking service on behalf of Co-Located Loads that are willing and \nable to limit their energy withdrawals from the transmission system under certain \nconditions—and that this lack of such transmission services is economically \ninefficient.315  We direct the new FCD and NFCD transmission services as a just and \nreasonable way to address this issue (among others). And, while siting choices can \nreduce the need for Network Upgrades, that fact does not undermine our finding that \nrequiring Eligible Customers taking service on behalf of Co-Located Loads to take NITS \nfor these loads leads to an unacceptable probability of inefficient outcomes by requiring \nmore or more costly Network Upgrades than would potential new FCD and NFCD \ntransmission services.316  We similarly reiterate that the need for many Network \nUpgrades are caused by the amount of MW flow on the transmission system even though \nthe need for certain Network Upgrades are not (e.g., they may be caused by stability or \nvoltage-related issues).317  Therefore, as Exelon and FirstEnergy concede, under a \ntransmission service that reflects willingness and ability to limit energy withdrawals, \"if \nthe load installs systems aimed at limiting its use of the grid, those might change the \nsystem impacts and need for upgrades.\"318  Likewise, while PJM will only plan the \ntransmission system for FCD transmission service based on the level of contract demand \nas a matter of transmission capacity, PJM will still be able to consider the gross load for \nanalyzing certain issues such as stability and short circuit.319 \n313  Id \n314  Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8. \n315  December Order, 193 FERC ¶ 61,217 at P 177. \n316  Id. PP 177, 199, 205. \n317  See Exelon and FirstEnergy Request for Rehearing at 47-48. \n318  Id. at 19-20; see also id. at 48. \n319  December Order, 193 FERC ¶ 61,217 at P 210. \n228 of 515"},{"page":230,"startToken":88048,"endToken":88452,"text":"Document Acc„sigPV; \n4qAqq18 -3999UMent:Filtd gage: \n812 \nto Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 72 - \n127.\nThe Commission's findings related to retail BTMG netting are not inconsistent \nwith the findings related to the new FCD and NFCD transmission services.320  The \nCommission stated that \"the existing BTMG netting rules in the PJM Tariff [are] unjust \nand unreasonable\" because, \"under the existing Tariff, loads with BTMG are not fully \naccounted for in resource adequacy planning.\"321  The Commission explained that \n\"[s]uch loads must nevertheless be served, however, allowing them to lean on the PJM \nsystem when the [BTMG] is on a full or partial outage or if the load exceeds the rating of \nthe [BTMG].\"322  Eligible Customers taking service on behalf of Co-Located Load will \nbe treated differently under FCD and NFCD transmission services—\"PJM will have no \nobligation to serve the Eligible Customer beyond the contract demand.\"323 \n128.\nExelon and FirstEnergy argue that the Commission failed to point to any other \ntariff where these new transmission services have been required by the Commission.324 \nThis argument is irrelevant because the Commission need not point to another FPA \nsection 206 proceeding where the Commission set an identical replacement rate in order \nto set a replacement rate. \nvii. \nReliability and New Transmission Services \n(a) \nRequest for Rehearing \n129.\nExelon and FirstEnergy argue that the Commission overlooked important \nreliability concerns in establishing new transmission services, including that loads impact \nthe system even when there is no net power draw on the system.325  Exelon and \nFirstEnergy assert that gross load is being followed by resources on the grid at all times, \nthus impacting the system. Exelon and FirstEnergy assert that the Commission has not \nexplained how reliability planning should proceed when large loads may be incentivized \nto exceed their contract demand limit for transmission service. Exelon and FirstEnergy \ncontend that the Commission overlooked resource adequacy risks in establishing Interim \nNITS. Exelon and FirstEnergy allege that it is unclear how it will be determined that \nload may be served reliably and the Commission failed to give PJM guideposts to make \n320  See Exelon and FirstEnergy Request for Rehearing at 48-49. \n321  December Order, 193 FERC ¶ 61,217 at P 179. \n322  Id P 186. \n323 1d P 211. \n324  Exelon and FirstEnergy Request for Rehearing at 36; see also id at 27, 29, 35. \n325  Id at 49-51. \n229 of 515"},{"page":231,"startToken":88452,"endToken":88795,"text":"Document Accessig@g 2A2-Vg18-3Q9cument:Flild rj:1@g:ge3A 812We Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 74 - \nprohibit PJM or the transmission owners from performing any particular studies that may \nbe necessary or mandate that the level of contract demand would be the only impact \nstudied. For example, when PJM or the transmission owners consider factors unrelated \nto the contract demand of the Co-Located Load, the December Order did not preclude use \nof the complete dynamic or EMT model of the Co-Located Load, regardless of what level \nor type of transmission service the Eligible Customer has requested. \n132. On Interim NITS, specifically, the Commission established paper hearing \nprocedures on \"What are the appropriate procedures to govern the circumstances under \nwhich PJM curtails an Eligible Customer taking the interim, non-firm transmission \nservice . . . on behalf of a Co-Located Load during emergency procedures?\"332  The \nCommission thus did not make a final decision on this issue either. In any event, the \nCommission stated that said Interim NITS \"would only be available to the extent PJM \ndetermines that it can provide some level of interim service reliably.\"333 \nviii. \nMajor Questions Doctrine \n(a) \nRequest for Rehearing \n133. Exelon and FirstEnergy assert that the Commission's replacement rate violates the \nmajor questions doctrine.334  Exelon and FirstEnergy argue that the Commission has no \nauthority under FPA section 206 to provide unduly preferential treatment to a certain \ncategory of customers, but that the Commission established a replacement rate favoring \nCo-Located Load without reasoned explanation. \n(b) \nDetermination  \n134. We disagree with Exelon and FirstEnergy that the December Order violates the \nmajor questions doctrine. The major questions doctrine applies in certain \"extraordinary \ncases\" involving an agency action that results in a \"transformative expansion\" of its \nauthority—especially over issues of great \"economic and political significance.\"335  In \n332  December Order, 193 FERC ¶ 61,217 at P 219. \n333  Id. P 200. \n334  Exelon and FirstEnergy Request for Rehearing at 52. \n335\n W. Va. v. EPA, 597 U.S. 697, 721, 724 (2022) (citations and quotations \nomitted). \n231 of 515"},{"page":232,"startToken":88795,"endToken":89190,"text":"Document Acce: \n2,6)-206,q18 _39pcument:Fl il d  yaN9:(263iC18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 73 - \nsuch a determination. Exelon and FirstEnergy state that it is unknown how and by what \nstandards load would be curtailed and whether curtailment is an adequate response to the \nneed to follow gross load moment-by-moment, and thus the transmission service options \ncannot be just and reasonable. \n130.\nExelon and FirstEnergy argue that, as to Interim NITS, the Commission has not \naccounted for reliability risks, not knowing when or how curtailments would be \nimplemented, as the Commission has asked for briefing on when Eligible Customers \ntaking this service would be curtailed.326  Exelon and FirstEnergy express concern that \nfuture state legislation may create inconsistencies among Co-Located Load in different \nstates. \n(b) \nDetermination \n131.\nWe dismiss these arguments for lack of finality.327  The December Order did not \nmake a final decision on several issues relevant to this argument.328  Instead, the \nCommission found that \"additional record evidence is needed\" and established paper \nhearing procedures on: the rates, terms, and conditions for the new transmission services; \ninterconnection requirements and operational practices for special protection schemes; \nthe communications, alarm, SCADA,329  or other requirements necessary for PJM to \nmonitor Co-Located Load transmission system demand status, ensure that relay settings \nare consistent with special protection scheme design, and inform system operator action \nin order to limit withdrawals that exceed the amount of contract demand; and the \nprocedures to govern circumstances under which PJM curtails an Eligible Customer \ntaking the three new transmission services.33°  Without a final decision on these issues, it \nis premature to argue or evaluate on rehearing whether the Commission overlooked \nimportant reliability concerns in establishing the new transmission services.331  In any \nevent, as to the new FCD and NFCD transmission services, the December Order did not \n326  Id at 37. \n327  See supra P 106. \n328  December Order, 193 FERC ¶ 61,217 at P 219. \n329  Supervisory Control and Data Acquisition (SCADA) is a system of remote \ncontrol and telemetry used to monitor and control the transmission system. See NERC \nGlossary of Terms 42, https://www.nerc.com/globalassets/standards/reliability-\nstandards/glossary_of terms.pdf. \n33°  December Order, 193 FERC ¶ 61,217 at P 219. \n331  See Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8. \n230 of 515"},{"page":233,"startToken":89190,"endToken":89674,"text":"Document AccessigPSIet; 22qI:o6A18-31:29,9ument:Filtd rPag9: g63A8/2PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 75 - \nsuch \"extraordinary cases,\" courts might \"hesitate before concluding that Congress meant \nto confer such authority.i336 \n135. \nWe conclude that this proceeding is not an \"extraordinary case\" such that the \nDecember Order does not implicate the major questions doctrine. In West Virginia v. \nEnvironmental Protection Agency, the U.S. Supreme Court identified a number of \nindicators that tend to identify a case as extraordinary, none of which are present here. \nFirst, the December Order does not involve a \"transformative expansion\" of the FPA or a \nreimagining of the Commission's long-held interpretation of that statute.337  Instead, the \nCommission acted, as it has previously, by finding that an existing practice was unjust \nand unreasonable and proceeding to establish a just and reasonable replacement rate.338 \nSecond, the December Order does not entail the use of an \"ancillary\" or \"little-used \nbackwater\" statutory provision.339  To the contrary, FPA section 206 is central to the \nCommission's authority over the rates for transmission service in interstate commerce.34° \nThird, the Commission did not in the December Order act outside of the Commission's \ntypical area of \"comparative expertise. 341  Indeed, the Commission's regulation of the \n336  Id. at 721 (citations and quotations omitted). \n337  See id. at 724-25 (finding that an agency's failure to invoke the asserted power \nin the past indicates that the major questions doctrine might apply). \n338  See, e.g., N.Y. v. FERC, 535 U.S. 1 (upholding Commission's exercise of its \nFPA section 206 authority in its landmark Order No. 888, which established the \npro forma OATT and established new transmission services); S.C. Pub. Serv. Auth. v. \nFERC, 762 F.3d 41 (upholding Commission's exercise of its authority under FPA \nsection 206 to remedy deficiencies in existing transmission planning practices). \n339  W. Va. v. EPA, 597 U.S. at 724, 730. \n340 See EPSA, 577 U.S. at 290 (\"ensur[ing] effective transmission of electric \npower\" is one of the \"core objects\" of the FPA\"); /V. Y. v. FERC, 535 U.S. at 7 (\"[Section] \n205 of the FPA prohibited . . . unreasonable rates and undue discrimination with respect \nto any transmission . . . subject to the jurisdiction of the Commission, and [section] 206 \ngave the [Commission] the power to correct such unlawful practices.\") (quotations and \ncitations omitted); Bldg. for the Future Through Elec. Reg'l Transmission Plan. & Cost \nAllocation, Order No. 1920, 187 FERC ¶ 61,068 (2024), order on reh'g and clarification, \nOrder No. 1920-A, 189 FERC ¶ 61,126, at P 175 (2024) (\"FPA section 206 sets forth \ncore Commission regulatory authority to remedy unjust and unreasonable rates, and \npractices affecting rates, for the transmission of electric energy in interstate commerce.\"), \norder on reh'g and clarification, Order No. 1920-B, 191 FERC ¶ 61,026 (2025). \n341  W. Va. v. EPA, 597 U.S. at 729. \n232 of 515"},{"page":234,"startToken":89674,"endToken":89982,"text":"Document AccessigPSA 2PAQ418-399cumentAild  jaq99: ge3A812ppe Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 76 - \nrates, terms, and conditions of transmission service in interstate commerce sits at the core \nof the Commission's expertise.342  Fourth, the December Order does not assert authority \nin a manner of great \"economic and political significance.\"343  Instead, the December \nOrder makes important but discrete changes to the manner in which a subset of \ntransmission customers take and pay for certain transmission services. \n136.\nIn any event, Exelon and FirstEnergy argue that the replacement rate violates the \nmajor questions doctrine only insofar as it exceeds the Commission's jurisdiction or is \nunduly discriminatory or preferentia1.344  As explained above, the replacement rate does \nneither. \nc. \nBTMG  \ni. \nQualifying Facilities  \n(a) \nDecember Order \n137.\nThe Commission directed PJM to revise the Tariff to revise the retail BTMG \nnetting rules.345  The Commission directed PJM to propose a new MW threshold for the \namount of load at a particular electrical location that Network Customers may net by \nusing BTMG but to otherwise phase-in the elimination of netting. Specifically, the \nCommission directed PJM to allow Network Customers already using the retail BTMG \nnetting rules to continue to do so for a transition period of three years.346  Further, the \nCommission directed PJM to grandfather entities with existing contracts for the specific \npurpose of effectuating a BTMG arrangement for the current term remaining under the \nexisting contract.347 \n342  See S.C. Pub. Serv. Auth. v. FERC, 762 F.3d at 49-54 (summarizing the \nCommission's history of reforms to the rates, terms and conditions of interstate \ntransmission service). \n343  W. Va. v. EPA, 597 U.S. at 721. \n344  Exelon and FirstEnergy Request for Rehearing at 52. \n345  December Order, 193 FERC ¶ 61,217 at P 221. \n346  Id. P 223. \n347  Id. P 224. \n233 of 515"},{"page":235,"startToken":89982,"endToken":90373,"text":"Document Accessig:PSP: 2\n2q)QA18.-.3[289urnent:F1.1.1d EPa..g:g.63/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. - \n- 77 - \n(b) \nRequest for Clarification and/or Rehearing \n138. Industrials request clarification on whether cogeneration QFs under the Public \nUtility Regulatory Policies Act of 1978 (PURPA) will be provided access to back-up and \nmaintenance power at just and reasonable rates and be credited for capacity based on the \nreliability of their generating units.348  Industrials contend that many QFs are \ncogeneration facilities, and that strong operational and financial incentives exist for \ncogeneration facilities to operate efficiently. Industrials state that Commission \nregulations require certain QFs to meet specified efficiency standards and thus should be \nencouraged.349  Thus, Industrials argue that many QFs operate with a high capacity factor \nand reliably during transmission peaks. Industrials accordingly seek clarification on \nwhether and how the December Order will apply to cogeneration QFs. Industrials \ncontend that the removal of netting rules will \"directly harm large American \nmanufacturing facilities that have invested substantial resources into developing and \nmaintaining on-site generation.\"3' °  Industrials add that removing netting rules may \ncontradict Commission regulations that require back-up and maintenance services for \ncogeneration QFs. Further, Industrials argue that FCD and NFCD transmission services \ndo not appear to account for forced generation outages. For these reasons, Industrials \nrequest that the Commission clarify that cogeneration QFs are exempt from the \"gross \nload\" approach or that PJM must include a reasonable \"Back-up Power\" transmission \noption that retail BTMG customers, including QFs, can purchase.351 \n(c) \nDetermination \n139.\nAs discussed below, in response to the Industrials' request for clarification, we \nclarify and set aside, in part, the December Order. \n140.\nFirst, we clarify that the December Order's replacement rate does not change any \nobligation under the Commission's PURPA regulations regarding QFs' access to \nsupplementary, back-up, maintenance, and interruptible power. The replacement rate \napplies only to Network Customers' usage of NITS under the Tariff, and nothing in the \nreplacement rate undoes the requirement in 18 C.F.R. § 292.305(b)(1) that, as to QFs, \n\"each electric utility shall provide . . . Supplementary power, Back-up power, \n348  Industrials Request for Clarification or Rehearing at 10; see also id. at 5. \n349  Id. at 11 (citing 18 C.F.R. § 292.205 (2025)). \n350 Id. \n351  Id at 11-13. \n234 of 515"},{"page":236,"startToken":90373,"endToken":90807,"text":"Document Accessig@V; 22q-A4;18- 3Q9cument:FlA d rFai@w: A3A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 78 - \nMaintenance power, and Interruptible power.\"352  While Industrials suggest that \nremoving netting rules may contradict Commission regulations that require back-up and \nmaintenance services for cogeneration QFs, Industrials do not explain how the \nreplacement rate results in Industrials no longer being entitled to back-up and \nmaintenance power under the Commission's regulations. In addition, Industrials do not \nexplain why it is necessary for the Commission to adopt a change to \"credit [QFs] for \ncapacity based on the reliability of their generating units.\"353 \n141.\nSecond, we set aside, in part, the December Order's directive that PJM establish a \nnew MW threshold for the amount of load at a particular electrical location that Network \nCustomers may net by using BTMG.354  We find that it is just and reasonable to allow \ncertain cogeneration QFs that are Network Customers to be able to net by using BTMG, \nand to be exempt from the new MW threshold, as discussed below. In the December \nOrder, the Commission found that PJM's retail BTMG rules are no longer consistent with \ncost causation principles because large loads configured in a BTMG arrangement with \nsignificant generation will raise cost-shifting concerns compared to loads pursuing \nsmaller amounts of netting.355  Moreover, the Commission found that PJM's existing \nretail BTMG rules may lead to both reliability and resource adequacy risks because PJM, \nper its Tariff, is obligated to serve transmission customers using BTMG but does not \nconsider such customers in transmission and resource adequacy planning.356  We find that \nthere is not sufficient reason, and nor do Industrials articulate such a reason on rehearing, \nto believe that these concerns are inapplicable to cogeneration QFs categorically. \n142. However, we recognize, based on the record, that there may be certain industrial \ncogeneration QFs that may be integrated with load such that, when their generator trips \noffline, the load follows (rather than withdrawing energy from the transmission system). \nFor example, as Industrials explain as to certain industrial cogeneration QFs, \"if the \ngenerator goes offline, the load promptly follows because the manufacturing facility \n352  18 C.F.R. § 292.305(b)(1) (2025). \n353  Industrials Request for Clarification or Rehearing at 10. \n354  December Order, 193 FERC ¶ 61,217 at P 221. \n355  Id. P 186. \n356  Id. To the extent the Commission's clarification on this issue conflicts with the \nrequested clarification, we otherwise disagree with Industrials' request to the extent \nIndustrials request rehearing in the alternative. See Industrials Request for Clarification \nor Rehearing at 2. \n235 of 515"},{"page":237,"startToken":90807,"endToken":91165,"text":"Dodument AccesdigPtr; 22Wogg-18-3C9.9Urnent:FlIld IPAP:g 63A8/ 2 P-Ate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 79 - \ncannot function without the steam output from the generation process.\"357  We therefore \ndirect PJM, within 60 days of the date of issuance of this order, to submit on further \ncompliance a process to exempt certain cogeneration QFs from the new retail BTMG \nnetting rules if they demonstrate that they are integrated with load such that, when their \ngenerating facility trips offline, the load follows, and they thus do not present the \nreliability or resource adequacy concerns discussed in the December Order. In \ndeveloping its compliance proposal, PJM must ensure that the requirements for a \ncogeneration QF to make this demonstration are not unduly burdensome. \nii. \nCapacity Obligations  \n(a) \nDecember Order \n143. The Commission found that PJM's existing retail BTMG netting rules may lead to \nboth reliability and resource adequacy risks because PJM is obligated to serve \ntransmission customers using BTMG but does not consider such customers in \ntransmission and resource adequacy planning.358  The Commission directed PJM to \npropose a new MW threshold for the amount of load at a particular electrical location that \nNetwork Customers may net by using BTMG.359  The Commission explained that such a \nthreshold should reduce the reliability and resource adequacy risks that large loads may \npose to PJM, while also allowing for Network Customers to reduce their transmission \ncharges in a transparent, not unduly discriminatory fashion. \n(b) \nRequest for Clarification and/or Rehearing \n144. Industrials seek clarification that the removal of BTMG netting rules will only be \napplicable to transmission and specified ancillary services, not to capacity obligations. \nIndustrials represent that the determination of retail customers' capacity tags is made by \nindividual electric distribution companies and that large industrial and institutional users \nhave a variety of configurations and approaches to meeting their capacity \nrequirements.36°  Industrials contend that the Commission did not analyze the impact of \n357  Industrials Request for Clarification or Rehearing at 11. \n358  December Order, 193 FERC ¶ 61,217 at P 186. \n359  Id. P 221. \n360  Industrials Request for Clarification or Rehearing at 15-16. \n236 of 515"},{"page":238,"startToken":91165,"endToken":91587,"text":"Document AccessigPSA 2Agg18-349c\nurnent:Flita. \ns?-03 A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 80 - \nthe BTMG rule changes on retail customers' capacity obligations or address alternate \ncapacity products that a retail customer with BTMG could elect.36' \n(c) \nDetermination \n145. We deny Industrials' clarification request and sustain the December Order. The \nCommission's determination that PJM's retail BTMG netting rules are no longer just and \nreasonable rested on a finding that PJM's existing retail BTMG netting rules may lead to \nreliability and resource adequacy risks.362  The Commission set a replacement rate to \nreduce the resource adequacy risks identified in the record.363  We recognize that \nrequiring PJM to revise its retail BTMG netting rules may affect capacity obligations,364 \nbut in the absence of this reform, the resource adequacy problems arising from PJM's \nexisting retail BTMG netting rules would persist because PJM remains obligated to serve \ntransmission customers using BTMG but under the existing rules does not consider such \ncustomers in resource adequacy planning.365  As to Industrials' concerns about the impact \nof the retail BTMG netting rule changes on retail customers, we agree with Industrials \nthat the RAA provisions Industrials cite directly apply to LSEs, not retail customers' \ncapacity obligations,366  and we note that, as part of our replacement rate, we established a \ngrandfathering provision such that existing entities may be able to continue netting for \nthe remainder of a contract entered into for the purpose of effectuating a BTMG \narrangement.367  This grandfathering provision may also limit the impacts of the changes \nto PJM's retail BTMG netting rules upon some entities' capacity obligations. In addition, \nas discussed above, we set aside, in part, the December Order and direct PJM to revise its \nTariff to extend the three new transmission services set forth in the December Order to \nEligible Customers taking service on behalf of load with BTMG that are willing and able \nto limit their energy withdrawals from the transmission system under certain conditions. \nThus, Eligible Customers taking transmission service on behalf of load with BTMG that \n361  Id. at 16. \n362  December Order, 193 FERC ¶ 61,217 at P 186. \n363  Id. P 221. \n364  See, e.g., PJM, Intra-PJM Tariffs, RAA, Schedule 8 (Determination of \nUnforced Capacity Obligations) (5.3.0). \n365  December Order, 193 FERC ¶ 61,217 at P 186. \n366  See, e.g., PJM, Intra-PJM Tariffs, RAA, Schedule 8 (Determination of \nUnforced Capacity Obligations) (5.3.0). \n367  December Order, 193 FERC ¶ 61,217 at P 224. \n237 of 515"},{"page":239,"startToken":91587,"endToken":91935,"text":"Document Accesgigi SA '- 1s3oqg-18-3P8curnent:FliLa PaNP: A3,8i8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 81 - \nare willing and able to limit their energy withdrawals from the transmission system under \ncertain conditions may elect to take FCD and/or NFCD transmission service, which could \nreduce capacity obligations in comparison to a BTMG arrangement where the Eligible \nCustomer elects to take NITS.368 \niii. \nUnlawful Taking of Private Property  \n(a) \nDecember Order  \n146. In the December Order, the Commission directed PJM to revise the retail BTMG \nnetting rules in the Tariff.369 \n(b) \nRequest for Clarification and/or Rehearing \n147. Industrials argue that the Commission's BTMG findings effectuate an unlawful \ntaking of private property without providing just compensation, in violation of the Fifth \nAmendment of the United States Constitution. Industrials contend that there is a \"per se \ntaking[]\" because \"the owner is deprived of `all economically beneficial us[e]' of the \nproperty due to the government action.\"37°  Industrials assert that certain manufacturing \nfacilities with on-site generation would be \"completely uneconomic.\"371  Separately, \nIndustrials contend that there is a regulatory taking under the factors outlined in Penn \nCentral Transportation Co. v. New York City.372  In particular, Industrials state that the \nBTMG netting findings will cause, in some instances, devastating economic impacts \"but \nperhaps not total deprivation.\"373  Industrials also argue that the BTMG netting findings \n368  Id. P 211 (\"PJM will only plan the transmission system and procure generation \ncapacity for the contract demand—not for load growth, like it does for NITS customers—\nand PJM will have no obligation to serve the Eligible Customer beyond the contract \ndemand.\"); id. P 218 (\"The new Non-Firm Contract Demand transmission service will \nnot include a charge for generation capacity.\"). \n369  Id. P 221. \n370  Industrials Request for Clarification or Rehearing at 31-32 (quoting Lingle v. \nChevron U.S.A., 544 U.S. 528, 538 (2005)). \n371  Id. at 32 (listing examples). \n372  Id at 33 (citing Penn. Cent. Transp. v. City of IV. Y, 438 U.S. 104, 124 (1978)). \n373  Id. at 33-34. \n238 of 515"},{"page":240,"startToken":91935,"endToken":92323,"text":"Document AccessigPS1P; Z42-VA1E3-34gcurnent:FlAd rfAgp: e7.6314812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 82 - \nupset investment-backed expectations and do not \"promote or facilitate a public program \nor public good to justify the economic interference.\"374 \n(c) \nDetermination \n148. As an initial matter, we dismiss Industrials' argument that the Commission's \nBTMG findings effectuate an unlawful taking of private property for lack of finality.375 \nThe December Order did not make a final decision on the applicability and design of the \nrevised retail BTMG netting rules.376  In particular, the Commission stated that it \"ma[d]e \nno finding in this order on a threshold\" \"for the amount of load at a particular electrical \nlocation that Network Customers may net by using BTMG.\"377  It would thus be \npremature to argue or evaluate on rehearing whether those as-yet-undeveloped retail \nBTMG netting rules effectuate an unlawful taking.378 \n149.\nIn any event, the Commission has an obligation under the FPA to ensure that the \nrates, terms, and conditions of jurisdictional service are just and reasonable. As the \nCommission found in the December Order, circumstances have changed since the \nCommission approved PJM's retail BTMG netting rules such that these rules are no \nlonger just and reasonable.379  The Commission therefore is establishing a just and \nreasonable replacement rate. And, as the Courts have held, in the context of setting rates, \nterms, and conditions for jurisdictional service, what is just and reasonable is not a \ntaking.38°  Instead, in establishing a just and reasonable replacement rate, the Commission \nis balancing the respective rights and obligations of the parties and will determine that \n374  Id. \n375  See supra P 106. \n376  December Order, 193 FERC ¶ 61,217 at P 221. \n377  Id. \n378  Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8. \n379  December Order, 193 FERC ¶ 61,217 at P 186. \n380 See In re Permian Basin Area Rate Cases, 390 U.S. 747, 770 (1968) (\"[T]he \njust and reasonable standard of the Natural Gas Act coincides with the applicable \nconstitutional standards and any rate selected by the Commission from the broad zone of \nreasonableness permitted by the Act cannot properly be attacked as confiscatory.\") \n(punctuation and citations omitted); see also N.Y. Indep. Sys. Operator, Inc., 151 FERC \n¶ 61,075, at P 63 (2015). \n239 of 515"},{"page":241,"startToken":92323,"endToken":92615,"text":"Document Accessig#g \n2-kAg-18-3p@cument:Flild \nrpaqg9:MC18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 83 - \nappropriate replacement rate through the course of the paper hearing and compliance \nproceedings.381 \niv. \nMateriality Threshold \n(a) \nDecember Order \n150. The Commission directed PJM to propose a new MW threshold for the amount of \nload at a particular electrical location that Network Customers may net by using \nBTMG.382  The Commission stated that parties would have an opportunity to comment on \nPJM's proposed threshold before we establish this replacement rate.383 \n(b) \nRequest for Clarification and/or Rehearing \n151. Industrials seek clarification that any retail BTMG materiality threshold \nimplemented will be sufficiently high to permit traditional manufacturers and institutional \ncustomers to continue to net generation, consistent with actual use of the transmission \nsystem.384  Industrials argue that a threshold of at least 200 MW would appropriately \nrecognize the major energy investments most existing industrial and institutional loads \nhave made over decades, consistent with the \"actual use\" principle, without making \n381  N.Y. Indep. Sys. Operator, Inc., 151 FERC ¶ 61,075 at P 63 (citing Jersey Cent. \nPower & Light Co. v. FERC, 810 F.2d 1168, 1191 (D.C. Cir. 1987) (en banc) (Starr, J. \nconcurring) ((\"Unlike garden-variety takings, the requirements of the Takings Clause are \nsatisfied in the rate regulatory setting when justice is done, that is to say the striking of a \nreasonable balance between competing interests.\")); see also supra P 137 (describing the \nmateriality threshold, phase-in, and grandfathering), PP 141-142 (setting aside the \nDecember Order in part to allow certain cogeneration QFs to continue to net). \n382  December Order, 193 FERC ¶ 61,217 at P 221. \n383  Id. \n384  Industrials Request for Clarification or Rehearing at 16. \n240 of 515"},{"page":242,"startToken":92615,"endToken":92937,"text":"Document Accessig@Sg 2A-2-Vt418-3Q@cument:FlA d Ifa'gg:A4A8/2p23-te Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 84 - \nuneconomic their resource adequacy contributions.385  Industrials contend that this \nthreshold would still address the primary concern driven by new large loads.386 \n152. To the extent the Commission does not grant clarification, Industrials argue that \nthe MW materiality threshold, transition period, and grandfathering provision fail to \ncorrect the asserted defects created in the December Order.387  While Industrials \n\"welcome exemptions as helpful,\" they describe those policies as \"the exception that \nproves the rule.\"388  Industrials contend that the threshold could create unintended \nconsequences such as perverse incentives to make on-site generation projects smaller, \nundue discrimination via a bright-line threshold, or a limit that is too low.389  Industrials \nsuggest that, rather than an arbitrary threshold, the Commission should maintain its \ntraditional netting approach but find alternative means to ensure that standby or backup \ncosts are addressed for very large loads. Industrials recommend that if the Commission \npursues a mandatory threshold, it should choose a multi-pronged threshold aligned with \nthe drivers of current transmission demand and the reliability risks posed.39°  Specifically, \nIndustrials argue, the Commission should set the threshold high enough to permit \ntraditional manufacturers and industrial loads to continue netting—such as 200 MW.39' \n385  Id. at 16 & n. 23 (\"We understand that industrial combined heat and power . . . \nunits may, in certain cases, exceed 200 MW. Given the Administration's interest in \nreshoring American manufacturing and the pressing need to keep long-established \ngeneration units economic, 200 MW may be insufficient.\"). \n386  Id at 16-17. \n387  Id at 42. \n388 id \n389  Id at 42-43 (stating also that \"[n]either a MW-based threshold nor a \ngrandfathering provision correct jurisdictional deficiencies\" and the Commission should \n\"find alternative means to ensure that standby or backup costs are addressed for very \nlarge loads\"). \n39°  Id. at 43. \n391  Id. at 43-44. \n241 of 515"},{"page":243,"startToken":92937,"endToken":93379,"text":"Document Accessigi S,9; qq-A6,A18-3Rwument:Flild \ngb4A6/2p2Ve Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 85 - \n(c) \nDetermination \n153.\nAs an initial matter, we dismiss Industrials' argument that any retail BTMG \nmateriality threshold implemented will be insufficiently high for lack of finality.392  The \nDecember Order did not make a final decision on the materiality threshold to be used in \nthe revised the retail BTMG netting rules.393  In particular, the Commission stated that it \n\"ma[d]e no finding in this order on a threshold\" \"for the amount of load at a particular \nelectrical location that Network Customers may net by using BTMG.\"394  It would thus \nbe premature to argue or evaluate on rehearing whether that as-yet-undeveloped retail \nBTMG materiality threshold be insufficiently high.395 \n154.\nIn response to the Industrials' arguments on rehearing regarding the MW \nthreshold, transition period, and grandfathering provision, we continue to find that this \nthree-pronged approach as to a replacement rate is just and reasonable.396  As an initial \nmatter, we note that Industrials primarily take issue with the Commission's decision to \nset a MW threshold, alleging it is arbitrary and may be unduly discriminatory.397  We \ndisagree. We recognize that no threshold may be perfect, but the Commission has \ndiscretion in drawing administrative lines it deems necessary,398  and we continue to \nbelieve that a threshold is not only necessary for the reasons set out in the December \nOrder, but also that we can exercise reasonable discretion to set a threshold consistent \nwith the Commission's intent to reduce the concerns raised by PJM's existing retail \nBTMG netting rules. As the Commission explained in the December Order, \"such a \nthreshold should reduce the reliability and resource adequacy risks [] that large loads may \n392  See supra P 106. \n393  December Order, 193 FERC ¶ 61,217 at P 221. \n394  Id \n395  Algonquin Gas Transmission, 175 FERC ¶ 61,150 at P 8. \n396  December Order, 193 FERC ¶ 61,217 at PP 221-224. \n397  Industrials Request for Clarification or Rehearing at 16-17, 42-43. \n398 See Vonage Holdings Corp. v. FCC, 489 F.3d 1232, 1242 (D.C. Cir. 2007) (\"It \nis true that an agency may not pluck a number out of thin air when it promulgates rules in \nwhich percentage terms play a critical role. When a line has to be drawn, however, the \nCommission is authorized to make a `rational legislative-type judgment.' If the figure \nselected by the agency reflects its informed discretion, and is neither patently \nunreasonable nor `a dictate of unbridled whim,' then the agency's decision adequately \nsatisfies the standard of review.\") (citation and internal quotation marks omitted). \n242 of 515"},{"page":244,"startToken":93379,"endToken":93784,"text":"Document AccessigRSA:  2z421qql 8 - 34cu me nt:F1 1.1  IPAP:g54/1 8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 86 - \npose to PJM, while also allowing Network Customers to reduce their transmission \ncharges in a transparent, not unduly discriminatory fashion.\"399  The Commission also \nacknowledged that such a materiality threshold \"will not eliminate the risk\" identified in \nthe December Order, but found that it \"will ensure that the risk is limited.\"400  As the \nCommission explained in the December Order, an important part of the problem is that \n\"PJM's existing retail BTMG netting rules do not limit the amount of qualifying load that \na Network Customer may net by using BTMG.\"401  We also note that, as discussed \nabove, we set aside, in part, the December Order's elimination of BTMG netting as to \ncertain cogeneration QFs. In addition, we note that above we set aside, in part, the \nDecember Order and extend the three new transmission services set forth in the \nDecember Order to Eligible Customers taking service on behalf of load with BTMG that \nare willing and able to limit their energy withdrawals from the transmission system under \ncertain conditions, thereby providing such customers the option to elect to take a \ntransmission service that matches their preferred use of the transmission system.4°2 \nLastly, we note that, while Industrials suggest the Commission find an alternative \napproach to a mandatory threshold to ensure that standby or backup costs are addressed \nfor \"very large loads,\"403  they fail to support their request with any specificity.404 \n399  December Order, 193 FERC ¶ 61,217 at P 221. \n400 Id. \n4°1  Id. P 186. \n4°2  Id. P 194 (stating that \"Eligible Customers, on behalf of the Co-Located Loads \nthat they represent, may choose the transmission services that match their preferred use of \nthe transmission system\"). \n4°3  Industrials Request for Clarification or Rehearing at 43. \n4°4  FPA section 313(a) requires that an \"application for rehearing shall set forth \nspecifically\" its grounds. 16 U.S.C. § 8251(a) (emphasis added). We follow Commission \npractice, with which courts have agreed, and reject arguments on rehearing, such as this \none, lacking sufficient specificity. PJM Interconnection, L.L.C., 171 FERC ¶ 61,040 \nat P 22; see also Ind Util. Regul. Comm'n, 668 F.3d at 736; LA Storage, LLC, 182 FERC \n¶ 61,026 at P 25 & n.75. \n243 of 515"},{"page":245,"startToken":93784,"endToken":94199,"text":"Document AccessigP Sp;  22PP2-%QA18 - 3R 891-I ment :F ill \nW4418/2 P2Ve Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 87 - \n2. \nNecessary Study Process for Existing Interconnection Customers  \na. \nTreatment of Capacity Interconnection Rights (CIRs) for \nCo-Located Generators  \ni. \nDecember Order \n155. The Commission found that an existing generator may not begin serving \nCo-Located Load that is not Network Load until it has de-listed its CIRs for the portion \nof the generator to be designated to serve any Co-Located Load that is not receiving \nNITS.4°5  A capacity resource's CIRs are rights to inject generation as a Generation \nCapacity Resource into the transmission system at the Point of Interconnection.406 \nii. \nRequest for Clarification and/or Rehearing \n156.\nConstellation argues that the December Order appears to require a capacity \nresource to delist its CIRs even when the capacity resource remains fully capable of \nserving the grid during capacity emergencies.407  Constellation explains that generators \nand Co-Located Load may seek contractual arrangements in which the generator will \nserve the grid rather than the Co-Located Load during a capacity emergency and the \nCo-Located Load will either curtail or rely on backup generation. Constellation claims \nthat it would be inconsistent with PJM's existing rules to require delisting in these \ncircumstances. According to Constellation, PJM's existing rules only require a capacity \nresource entering an external sale to delist its CIRs when the resource \"has a financially \nand physically firm commitment to an external sale of its capacity.'5408 \n157.\nConstellation therefore seeks clarification that the December Order does not \nrequire a capacity resource to delist its CIRs to serve a Co-Located Load that is taking \nNFCD transmission service if PJM can verify that the Co-Located Load has no \ncontractual right to energy from the generator during a capacity emergency and that the \nCo-Located Load has the ability either to curtail or draw on back-up power.4°9 \n4°5  December Order, 193 FERC ¶ 61,217 at P 230. \n406 PJM Interconnection, L.L.C., 168 FERC ¶ 61,155, at P 7 n.15 (2019). \n407 Constellation Request for Clarification or Rehearing at 3 (citing December \nOrder, 193 FERC ¶ 61,217 at P 230). \n4°8  Id. at 4 (quoting PJM, Intra-PJM Tariffs, OATT, attach. DD.6 § 6.6) (emphasis \nin original). \n4°9  Id at 4-5 (referring to \"the ability to (i) interrupt and/or (ii) turn on back-up \ndiesels or other back-up power or draw on batteries when transmission under the \n244 of 515"},{"page":246,"startToken":94199,"endToken":94586,"text":"Document AccessigPsg qq-Aeg -18-349cument:FlAd LPAg?:g04A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 88 - \nConstellation argues that the Commission could require the Co-Located Load to disclose \ninformation regarding its protective relay scheme and its interruptible commitment and \ncould impose penalties on the Co-Located Load for failure to comply with its \ncommitment. \n158.\nTo the extent that the Commission does not grant clarification, Constellation seeks \nrehearing. Constellation argues that requiring a capacity resource to delist its CIRs in \nthese circumstances would be a failure of reasoned decision making.410 Constellation \nalso argues that it would be unduly discriminatory to require a capacity resource serving a \nCo-Located Load to delist for entering into an interruptible commitment but not to \nrequire capacity resources to delist before making other non-firm commitments.41' \niii. \nDetermination \n159.\nWe deny Constellation's request for clarification and sustain the December \nOrder's finding that an existing generator may not begin serving Co-Located Load that is \nnot Network Load until it has delisted its CIRs for the portion of the generator to be \ndesignated to serve any Co-Located Load that is not receiving NITS.412 \n160. Constellation proposes a scenario in which an Eligible Customer taking NFCD \ntransmission service on behalf of Co-Located Load would not be allowed to withdraw \npower from the transmission system during emergency conditions and the Eligible \nCustomer would guarantee that it would further curtail its demand in order to allow the \nCo-Located Generator to provide energy to the system. NFCD transmission service \ngoverns when an Eligible Customer may withdraw energy from the transmission system, \nbut it does not govern the firmness of any bilateral agreement to supply energy between \nthe Co-Located Load and the Co-Located Generator. We understand Constellation's \nscenario to be one in which the Co-Located Load—when relying on the Co-Located \nGenerator—does not schedule its power by relying on FCD or NFCD transmission \nservice. \nnon-firm contract demand service is interrupted and the co-located generator is serving \nthe grid\"). \n410 Id. at 6 (citing Elec. Consumers Res. Council v. FERC, 747 F.2d 1511, 1513-14 \n(D.C. Cir. 1984)). \n411  Id. (citing 5 U.S.C. § 706(2)(A); Consol. Edison of N.Y., Inc. v. FERC, 45 F.4th \n265 (D.C. Cir. 2022)). \n412  December Order, 193 FERC ¶ 61,217 at P 230. \n245 of 515"},{"page":247,"startToken":94586,"endToken":94982,"text":"Dodument AccessigPSA -qr23x6,618-3Q99urnent:Filtd JEN?: W-64 ,618/2p to Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 89 - \n161.\nUnder Constellation's scenario, the Co-Located Generator would not be capable of \nmeeting its entire capacity requirement. In addition to the requirement to perform during \nemergencies, Generation Capacity Resources are required to offer into the Day-Ahead \nMarket throughout the delivery year.413  Constellation's proposal would allow a \nGeneration Capacity Resource to violate this requirement and provide an inferior \ncapacity product (compared to other Generation Capacity Resources) for the same \ncapacity payment. We thus deny Constellation's request for clarification and sustain the \nDecember Order. \n162.\nWe also reject Constellation's argument that Generation Capacity Resources \nengaged in non-firm external bilateral transactions are not required to delist their CIRs \nand are comparable.414  A Generation Capacity Resource engaged in a non-firm external \nbilateral transaction must still make offers into PJM's day-ahead market.415 \nb. \nCost Responsibility for Network Upgrades  \ni. \nDecember Order  \n163. In the December Order, the Commission required PJM to revise its Tariff to \nexpressly indicate that the Interconnection Customer will be responsible for the costs of \nany modifications or Network Upgrades that are needed as a result of PJM's study of the \nchange to the Interconnection Service Agreement (ISA) or Generation Interconnection \nAgreement (GIA) to allow the existing generator to serve Co-Located Load, including to \nreflect any reduction in CIRs, inclusive of all necessary Network Upgrades. The \nCommission found that this change will clarify that costs associated with such \nCo-Location Arrangements will not be unfairly shifted to other transmission customers. \nThe Commission further directed PJM to revise its Tariff to clarify that an existing \ngenerator may not commence service to a Co-Located Load until all required Network \nUpgrades, special protection schemes, and metering are in service.416 \n413  Under the Tariff, a capacity resource is required to offer its Installed Capacity \n(ICAP) equivalent of the resource's cleared Unforced Capacity (UCAP) into the PJM \nenergy markets every day if not on outage or derated. PJM, Intra-PJM Tariffs, OATT, \nattach. K, app. § 1.10 (Scheduling) (46.1.1), § 1.10.1A(d). \n414  Constellation Request for Clarification or Rehearing at 6. \n415 wri• \nIntra-PJM Tariffs, OATT, attach. K, app. § 1.10 (46.1.1), § 1.10.1A(d). \n416  December Order, 193 FERC ¶ 61,217 at P 228; see also id. P 176 \n(summarizing same). \n246 of 515"},{"page":248,"startToken":94982,"endToken":95364,"text":"Document AccessigRA qq-Agg318-34iiscument:Flild rEN?:gb4A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n-90-\nii. \nRequest for Rehearing \n164.\nExelon and FirstEnergy challenge the Commission's directive that an \nInterconnection Customer seeking to serve Co-Located Load using an existing generator \nmust bear the costs of all Network Upgrades.417  Exelon and FirstEnergy contend that the \nCommission has departed, without explanation, from its policy that all transmission \ncustomers share the embedded costs of the transmission system, including Network \nUpgrade costs, consistent with cost causation principles.418  Exelon and FirstEnergy \nassert that this policy is sensible because all loads benefit from the transmission network, \nincluding Co-Located Load. Exelon and FirstEnergy argue that the Commission \nacknowledges that Co-Located Load benefits from the transmission network as a whole \nbecause the Commission found Co-Located Load relies on regulation and black start.419 \nExelon and FirstEnergy contend that regulation and black start cannot be delivered in \nisolation: they depend on diverse resources around the grid transmitting power over \ntransmission lines, on other operating reserves and voltage support services, and on \nNetwork Upgrades. Exelon and FirstEnergy also argue that the December Order is \ninternally inconsistent and discriminatory because it preserves NITS as a just and \nreasonable approach, but the NITS funding model conflicts with the proposed assignment \nof costs to Co-Located Load.42° \n165.\nExelon and FirstEnergy assert that the Commission should not erode its rolled-in \nrate policy and identify several consequences of such erosion.421  First, Exelon and \nFirstEnergy contend that, if Co-Located Loads need only pay for incremental investment, \nthey avoid paying for the broader system on which they depend, resulting in other \ncustomers paying a forced subsidy.422 Exelon and FirstEnergy express concern that, once \na Co-Located Load fulfills its responsibility for funding certain upgrades, prohibitions on \n\"and\" pricing mean the Co-Located Load would not be responsible for further \ntransmission service payments even though the transmission system requires \nmaintenance. Second, Exelon and FirstEnergy argue that the Commission's approach \ncreates challenges akin to those in the generator interconnection space, such as the \npotential for future Co-Located Load customers to trigger significant upgrades, and \n417  Exelon and FirstEnergy Request for Rehearing at 42-43. \n418  Id at 42. \n419  Id. at 43. \n42°  Id. at 44. \n421  Id at 44-47. \n422  Id at 45. \n247 of 515"},{"page":249,"startToken":95364,"endToken":95793,"text":"Document Accessigi SP; qq-2-V?g-18 - 3R9cUrnent:FlAd IPAP: g64 /81812PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 91 - \nincentives for speculative behavior and Point of Interconnection shopping.423  Third, \nExelon and FirstEnergy argue that significant up-front requirements could hinder \neconomic development for Co-Located Load customers that are not data centers. \niii. \nDetermination \n166. We sustain the December Order's requirement that an Interconnection Customer \nwill be responsible for the costs of any modifications or Network Upgrades that are \nneeded to allow the existing generator to serve Co-Located Load, including to reflect any \nreduction in CIRs, inclusive of all necessary Network Upgrades.424  We disagree with \nExelon and FirstEnergy's argument that the Commission created a \"new paradigm\" as to \nInterconnection Customers' cost responsibility for Network Upgrades needed to \naccommodate modifications those customers make to their own generators.425  To the \ncontrary, the Commission directed PJM to revise the Tariff to expressly state that \nInterconnection Customers have this cost responsibility in order to \"clarify that\nthat costs \nassociated with such Co-Location Arrangements will not be unfairly shifted.\"426  In other \nwords, even without this revision to improve the Tariff's clarity, this requirement was the \npreexisting one. The Tariff provides that an Interconnection Customer is responsible for \nthe costs of additions to the Transmission System that are required to accommodate \nmodifications to the generator.427  For example, apart from Co-Location Arrangements, if \nan Interconnection Customer decreased the capacity of a generator due to technological \nchanges at that facility, the Interconnection Customer would be responsible for the costs \nof Network Upgrades needed to accommodate that decrease.428  This requirement \n423  Id at 46. \n424  December Order, 193 FERC ¶ 61,217 at P 228. \n425  Exelon and FirstEnergy Request for Rehearing at 42-47. \n426  December Order, 193 FERC ¶ 61,217 at P 228 (emphasis added). \n427 PJM, Intra-PJM Tariffs, pt. IX, subpt. B, app. 2 (2.0.0), § 3.4(b) (Modification \nCosts) (\"Project Developer shall be responsible for the costs of any additions, \nmodifications, or replacements to the Interconnection Facilities and Transmission Owner \nUpgrades or the Transmission System that are required, in accord with Good Utility \nPractice and/or to maintain compliance with Applicable Laws and Regulations or \nApplicable Standards, in order to accommodate additions, modifications, or replacements \nmade by Project Developer to the Generating Facility or Merchant Transmission Facility \nor to the Project Developer Interconnection Facilities.\"); see also, e.g., id. Attachment O, \nAppendix 2, § 3.4(b) Modification Costs (0.0.0). \n428  Id Part IX.B, Appendix 2, § 3.4(b) Modification Costs (2.0.0). \n248 of 515"},{"page":250,"startToken":95793,"endToken":96245,"text":"Document Access igPsg 22q-Arqg-18 _39Kument:Fl il d rFai@v: g.64/48/22-,Ate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 92 - \nlikewise applies to Interconnection Customers seeking to modify their interconnection to \nserve Co-Located Load if the attendant decrease in energy injected to the transmission \nsystem necessitates Network Upgrades. Accordingly, if the Commission had not directed \nthe revision at issue here, Interconnection Customers would still bear the cost \nresponsibility at issue—the Commission simply acted to improve the clarity of the Tariff \non this topic. Exelon and FirstEnergy thus attack a requirement in the Tariff that the \nCommission approved before this proceeding and that the Commission did not change in \nthis proceeding. \n167.\nFor the same reason, Exelon and FirstEnergy are incorrect in arguing that the \nCommission \"depart[ed] from prior precedent\" with a requirement that \"differs from the \napproach taken in the PJM Tariff.\"429  As explained, the Commission did not change the \npreexisting Tariff regime. In any event, despite their assertion, Exelon and FirstEnergy \ndo not include citations to precedent addressing this topic.43° \n168.\nExelon and FirstEnergy also misunderstand the requirement they criticize. Exelon \nand FirstEnergy characterize the Commission's directive as ordering that \"[C]o-[L]ocated \n[L]oad must self-fund any needed transmission upgrades.\"431  The cost responsibility at \nissue, however, is limited to existing Interconnection Customers and pertains only to the \nspecified Network Upgrades related to their own modifications.432  In short, the \nCommission did not direct that Co-Located Load would self-fund Network Upgrades. \nTheir criticisms of the clarification that the Commission directed to the current Tariff are \nthus flawed. The Commission specifically stated that the requirement to self-fund any \nneeded Network Upgrades was appropriate because when \"an Interconnection Customer \nseek[s] to serve Co-Located Load using an existing generating facility\" \"existing \ntransmission customers\" must be \"protect[ed]\" \"from bearing the cost of Network \nUpgrades required for an Interconnection Customer to begin serving Co-Located \nLoad.\"433  Otherwise, costs could be \"unfairly shifted\" based on the conduct of \n429  Exelon and FirstEnergy Request for Rehearing at 42, 44. \n430  In the relevant section of Exelon and FirstEnergy's rehearing request, they do \ncite several cases and orders that do not address this topic. For example, Exelon and \nFirstEnergy cite Coalition of MISO Transmission Customers v. FERC, 45 F.4th 1004, \n1009 (D.C. Cir. 2022), for a general statement of cost causation principles and they cite \ntwo orders regarding load-ratio share for NITS. Id. at 42-47 & nn.110-111. \n431  Id. at 42. \n432  PJM, Intra-PJM Tariffs, pt. IX, subpt. B, app. 2, (2.0.0), § 3.4(b) (Modification \nCosts). \n433  December Order, 193 FERC ¶ 61,217 at P 176 (emphasis added). \n249 of 515"},{"page":251,"startToken":96245,"endToken":96675,"text":"Document Accessig#ir; 2A-2-18-349curnent:Flild rPA99:g5,c18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n-.93 - \nInterconnection Customers.434  The entity responsible for causing the need for the \nNetwork Upgrade costs is therefore the relevant Interconnection Customer, and Exelon \nand FirstEnergy are incorrect to assert that a \"load pays\" framework should apply here.435 \nIt is the conduct of the Interconnection Customer that triggers the Network Upgrades at \nissue. \n169.\nExelon and FirstEnergy nonetheless contend that \"[C]o-[L]ocated [L]oad should \nbe charged for the benefits it receives from the grid and for the burdens it places upon the \ngrid.\"436  Exelon and FirstEnergy further give the example of the use of regulation and \nblack start services.437  The December Order appropriately addressed such use. The \nDecember Order determined, for example, that Eligible Customers serving Co-Located \nLoads that seek to rely on the transmission system to the same extent as Network \nCustomers will continue to be eligible to take NITS, billed on a gross demand basis; \nEligible Customers can take and pay for the new contract demand transmission services \nthat reflect a Co-Located Load's ability to limit withdrawals from the transmission \nsystem; and Eligible Customers taking transmission service on behalf of Co-Located \nLoad must be assessed charges for regulation and black start services on a gross demand \nbasis, to ensure appropriate cost recovery for such services.438  In sum, the findings we \ndiscuss here related to Interconnection Customer cost responsibility do not disturb the \nCommission's findings addressing appropriate charges for transmission service—an \nobligation on Eligible Customers not Interconnection Customers. \n170.\nExelon and FirstEnergy also argue that the Commission improperly assessed \"cost \ncausation\" because it \"randomly applied\" \"cost responsibility\" \"only to cases where the \nadded load is served through an existing generator interconnection facility.\"439  As \nexplained above, however, the Commission simply applied the existing Tariff. The \n434  Id. P 228. \n435  Exelon and FirstEnergy Request for Rehearing at 43; see also id. at 43-44 \nn.113 (stating that the December Order \"departs from th[e] longstanding approach\" of \n\"rolling the costs of load-driven network upgrades into transmission rates\"). \n436  Id. at 43; see also id. at 45-46; id. at 47 (stating that \"it should not be assumed \nthat large loads will trigger system upgrades with costs in excess of what they would \notherwise contribute to the system if they paid traditional network rates based on their \nload-share ratio\"). \n437  Id at 43. \n438  December Order, 193 FERC ¶ 61,217 at P 160. \n439  Exelon and FirstEnergy Request for Rehearing at 44. \n250 of 515"},{"page":252,"startToken":96675,"endToken":97106,"text":"Document AccessigPV: \nI.8. 349cumentAi l d ig@g?:g.65/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 94 - \nCommission likewise affirmed the allocation of cost responsibility to the parties that \ncause the costs—the Interconnection Customers—who do so through their conduct in \nmodifying their existing arrangement.44°  Accordingly, we disagree with Exelon and \nFirstEnergy's assertion that these costs should instead be spread \"to all network \ncustomers.\" In PJM, the costs of Network Upgrades are directly assigned to the \ninterconnection customer—referred to as participant funding.441 In its Order No. 2003 \ncompliance proceeding, PJM explained that \"the `but for' provisions of the PJM tariff . . . \nrequire an Interconnection Customer to pay 100 percent of the Network Upgrades that \nmust be made for the Interconnection Customer to connect to the PJM grid.\"442  In PJM, \nInterconnection Customers are also responsible for the costs of any changes to the \ntransmission system that are required to accommodate additions, modifications, or \nreplacements made by the Interconnection Customer to the generator or its \ninterconnection facilities.443  The Commission's directive thus adheres to Commission \nprecedent and the Tariff and also does not conflict with (or change) \"the Network Service \nfunding model.\"444 \n171. \nWe also find unavailing the \"several issues\" Exelon and FirstEnergy contend the \nCommission's determination created.445  We find each speculative and unsupported by \nevidence. More specifically, Exelon and FirstEnergy assert that the Commission is \nimproperly accounting for a \"benefit to other customers to include new [C]o-[L]ocated \n[L]oads in the pool of payers for the existing transmission network.\"446  Yet as explained \nabove, the December Order establishes a set of transmission service options that ensures \nthat Eligible Customers taking service on behalf of Co-Located Loads are allowed to \n440 Indeed, Exelon and FirstEnergy acknowledge that \"exiting incumbent \ngenerators\" cause the relevant costs by referring to \"transmission upgrade costs they \ncause by serving [C]o-[L]ocated [L]oad.\" Id. \n441  PJM Interconnection, L.L. C., 108 FERC ¶ 61,025, at P 20 (2004). \n442 Id. P 19. PEVI's current generator interconnection rules include similar \"but \nfor\" provisions. See PJM, Intra-PJM Tariffs, pt. VIII, subpt. C, § 404 (1.0.0), \n§ 404(A)(5) (Cost Allocation for Network Upgrades). \n443  PJM, Intra-PJM Tariffs, pt. IX, subpt. B, app. 2, § 3.4 (2.0.0), § 3.4(b) \n(Modification Costs). \n444  Exelon and FirstEnergy Request for Rehearing at 44. \n445  Id at 45-47 (including argument that the Commission's \"approach creates \nchallenging dynamics like those we have seen in the generator interconnection space\"). \n446  Id. at 45-46. \n251 of 515"},{"page":253,"startToken":97106,"endToken":97426,"text":"Docuinent AccessigPA:  qq2-VA18-3Racument:plild DPaN9: g65A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 95 - \nchoose the transmission service that aligns with their use of the transmission system and \ntherefore aligns the charges for service with the benefits received. Exelon and \nFirstEnergy's conjecture that \"significant up-front requirements could hinder economic \ndevelopment\"447  disregards the voluntary nature of Co-Location Arrangements, which \nreflect an additional opportunity for developers to consider. \n3. \nNew Generators Serving Co-Located Load \na. \nDecember Order \n172. In the December Order, the Commission found that the Tariff is unjust and \nunreasonable because it does not contain provisions addressing with sufficient clarity or \nconsistency the rates, terms, and conditions of service that apply to Interconnection \nCustomers serving Co-Located Load and Eligible Customers taking transmission service \non behalf of Co-Located Load.448  Pertinent to new generators, the Commission directed \nPJM to revise its Tariff to clarify that PJM shall consider requests for interconnection \nservice below the full generating capability of the generator, so that an Interconnection \nCustomer may request interconnection service at a level below its maximum facility \noutput to serve Co-Located Load;449  that Interconnection Customers seeking to use new \ngenerators to serve Co-Located Load may use existing procedures to accelerate a new \nservice request if the request has no cost allocation for Network Upgrades and does not \nrequire further studies;45°  that an Interconnection Customer seeking to use a new \ngenerator to serve Co-Located Load may request provisional interconnection service;451 \nand that an Interconnection Customer seeking to use a new generator to serve Co-Located \nLoad at an existing Point of Interconnection may request Surplus Interconnection \nService, if the existing Interconnection Customer at that Point of Interconnection has \nmade Surplus Interconnection Service available.452 \n447  Id. at 46-47. \n448  December Order, 193 FERC ¶ 61,217 at P 159. \n449  Id. P 232. \n45°  Id. P 233. \n451  Id. P 234. \n452  Id. P 235. \n252 of 515"},{"page":254,"startToken":97426,"endToken":97858,"text":"Document Accessig#V; •A'Aqq18-3P9cUrnent:Flitd \nf--8/2Pe Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 96 - \nb. \nRequest for Clarification  \n173.\nJoint Parties request the Commission clarify that a Co-Located Load may \nnominate a net withdrawal limit in the same manner that it may nominate a net injection \nlimit when requesting new or modifying existing interconnection service.453  Joint Parties \nargue that the Commission found that creating new transmission services is necessary to \nensure that Co-Located Loads pay only for the services they use and to avoid costly and \ninefficient transmission system buildout, and that the same logic \"should compel \ncomplementary reforms to the generator interconnection process, because that process \nalso may evaluate withdrawals from the Co-Located Load and therefore may also \nresult—absent clarification—in `costly and inefficient transmission system buildout.\"454 \nJoint Parties argue that clarification is necessary to realize the Commission's intent of \nensuring that Co-Located Loads do not pay for services that they do not use and do not \ntrigger Network Upgrades that they do not need. Joint Parties explain that, to the extent \nPJM performs interconnection service study steps involving withdrawal assumptions \nfrom both the storage facility and the Co-Located Load, those steps \"must allow the \ninterconnection customer to provide for limits to the injection and withdrawal rights for \nthe generation and co-located load facilities reflecting the proposed integration of those \nfacilities.\"455  Joint Parties clarify that they recommend against the Commission requiring \nCo-Located Load be included in the interconnection study process, as the timing of the \nload interconnection process may not match.456 \n174.\nJoint Parties argue that, without clarification, PJM may assume that the \nCo-Located Load and the charging load of the storage resource create overlapping grid \nimpacts, when both could be managed to limit the overall withdrawal of the resource and \navoid withdrawing energy when doing so would create grid impacts that necessitate \nNetwork Upgrades. Joint Parties explain that, while the December Order recognizes that \n\"co-located resources\" can limit withdrawals and prevent unnecessary transmission \nbuildout, Joint Parties argue the order applies this logic only to transmission service and \nnot interconnection service.457  Joint Parties contend that not applying this logic to \ninterconnection service would reduce the benefits of creating the non-firm transmission \n453  Joint Parties Request for Clarification at 2-3, 5 (citing December Order, \n193 FERC ¶ 61,217 at P 232). \n454  Id at 3 (citing December Order, 193 FERC ¶ 61,217 at P 177). \n455  Id. at 5-6. \n456  Id at 8 n.20. \n457  Id. at 10 (citing December Order, 193 FERC ¶ 61,217 at P 199). \n253 of 515"},{"page":255,"startToken":97858,"endToken":98183,"text":"Document AccessigPsA: -%,.z.36 q-18 _3Q9cument:Flit d \nk5A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 97 - \nservice.458  Joint Parties request that the Commission require PJM to specify what \ninformation about the Co-Located Load is required for the purposes of the new service \nrequest study process, similar to the Commission's requirement about the Necessary \nStudy process, to ensure that PJM does not include overlapping load and energy storage \nwithdrawals.459 \nc. \nDetermination \n175.\nWe deny Joint Parties' request for clarification. Joint Parties' request \nmisconstrues the findings in the December Order that the Tariff is unjust and \nunreasonable because it does not contain provisions addressing with sufficient clarity or \nconsistency the rates, terms, and conditions of service that apply to Interconnection \nCustomers serving Co-Located Load.46°  The December Order did not require PJM to \nintegrate into the interconnection study process operating assumptions of both a \nCo-Located Load and electric storage resources that are part of a Co-Location \nArrangement. PJM has already committed to studying the electric storage resources of \nInterconnection Customers as charging during off-peak periods, consistent with PJM's \nfuel-based dispatch assumptions set forth in its planning criteria.\"' \nD. \nInformational Report  \n1. \nDecember Order  \n176.\nIn the December Order, the Commission directed PJM to submit in Docket \nNo. EL25-49-000, within 30 days of the date of issuance of the December Order, a \ndetailed informational report addressing, among other things \"the development of \nenhanced load forecasting . . . measures to assist PJM in determining the amount of new \ncapacity that is needed to maintain system reliability.\"462 \n455  Id at 9-10. \n459  Id at 8 (citing December Order, 193 FERC ¶ 61,217 at P 227). \n460 December Order, 193 FERC ¶ 61,217 at P 159. \n461  PJM Interconnection, 195 FERC ¶ 61,031, at P 180 (2026) (accepting PJM's \nproposal, in relevant part, in compliance with the Commission's Order No. 2023 \ninterconnection reforms). \n462  December Order, 193 FERC ¶ 61,217 at PP 237-239. \n254 of 515"},{"page":256,"startToken":98183,"endToken":98595,"text":"Document AccessigiPg 2A-2-Vgi 8 - 3Q9c ument:Flil d EpAg9: g.65A. 8 / 2  PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 98 - \n2. \nRequest for Clarification \n177. PIOs request clarification as to how the Commission intends to respond to or \notherwise use information provided in the record regarding PJM's load forecasting \npractices. PIOs further request that any subsequent order from the Commission address \nthe issues raised in the record regarding the continuing and ongoing deficiencies in PJM's \nload forecasting process. PIOs explain that PJM is using these load forecasts as inputs in \nthe upcoming Base Residual Auction and RTEP and argue that, without a specific \nCommission directive, PJM is unlikely to timely resolve issues that PIOs allege exist with \nthe load forecasts.463  PIOs note that the Commission required PJM to provide an \ninformational filing that includes an update regarding the development of \"enhanced load \nforecasting\" and acknowledge that the Commission stated that it \"will not act on or notice \nthis informational [Ming.59464 \n178.\nPIOs note that Commissioner Rosner submitted a letter to PJM about load \nforecasting in September 2025 and take issue with PJM's October 2025 response.465 \nAccording to PIOs, PJM's response to this letter does not require or specify a particular \nmethodology for forecasting large loads, without which PIOs allege that LSEs and \nElectric Distribution Companies will continue to report data with widely varying \naccuracy and that load forecasts will remain uncertain. PIOs also argue that PJM's \nresponse fails to identify a way for PJM to address the double counting of data centers or \nto enable PJM to respond dynamically to significant updates to load forecasts.466 \n179. PIOs contend that recent events have validated their concerns regarding the \naccuracy of PJM's load forecasts. For example, according to PIOs, PJM staff have \nacknowledged that the 2026 forecast would likely reflect a decrease in forecasted load for \nthat time period in light of an update to how PJM implements load adjustments. Given \nthe alleged inaccuracy of PJM's load forecasts, and because PJM uses its load forecasts \nto essentially set the demand curve for capacity obligations, for reliability studies, and to \nsupport the RTEP, PIOs question how these processes remain just and reasonable without \nsignificant revisions to PJM's load forecasting practices.467 \n463  PIOs Request for Clarification at 2-3. \n464  Id at 2 (citing December Order, 193 FERC ¶ 61,217 at P 238 & n.486). \n465  Id at 4-5. \n466  id. \n467  Id at 5-7. \n255 of 515"},{"page":257,"startToken":98595,"endToken":98991,"text":"Document Accessig; gq-230§A18-3P9c ument:FlAd \ng.s5A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 99 - \n3. \nDetermination \n180.\nWe deny the request for clarification. The directive in the December Order to \nPJM to file an informational report that includes load forecasting represents the \nCommission's actions in this proceeding related to load forecasting.468 The Commission \nwill review the informational report in its normal course and remains committed to \nmonitoring PJM's load forecasting. Separately, we note that in the order that we are \nissuing concurrently in Docket No. EL26-67-000, we direct PJM to show cause as to why \nits Tariff remains just and reasonable without sufficiently clear and consistent Tariff \nprovisions that address the application process for requesting transmission service to \nEligible Customers on behalf of large loads and the study procedures for studying the \nprovision of transmission service to Eligible Customers on behalf of large loads, \nincluding a non-refundable application fee and sufficient readiness requirements that \nescalate at distinct phases of the study process to deter duplicative or speculative requests \nfor transmission service (e.g., meaningful milestones and/or financial commitments). \nV. \nCompliance  \nA. \nBTMG Rules  \n1. \nMateriality Threshold  \na. \nDecember Order \n181.\nThe Commission found that PJM's existing retail BTMG netting rules were no \nlonger just and reasonable and directed several changes, including directing PJM to \npropose a new MW threshold for the amount of load at a particular electrical location that \nNetwork Customers may net by using BTMG.469  The Commission found that a \nmateriality threshold would reduce the reliability and resource adequacy risks that large \nloads may pose to PJM, while also allowing for Network Customers to reduce their \ntransmission charges in a transparent, not unduly discriminatory fashion. The \nCommission noted \"as points of reference that PJM requires any generator larger than \n10 MW to be individually metered and that the Commission's definition of a small \ngenerator is 20 MW.\"47° \n468  December Order, 193 FERC ¶ 61,217 at PP 237-239. \n469  Id. P 221. The Commission did not direct PJM to make any changes to its rules \nfor Non-Retail BTMG, finding that the record did not demonstrate the need for changes \ngiven that Non-Retail BTMG is already capped. Id. P 222. \n47°  Id. P 221 (citing PJM Manual 14G: Generation Interconnection Requests, \nRev. 8 (eff. July 26, 2023), § 1.6.2; Standardization of Small Generator Interconnection \n256 of 515"},{"page":258,"startToken":98991,"endToken":99376,"text":"Document AccessigRgg 2A -2-Vgl 8 _ 3Q9cUMent:Flitd \ng 65A81 2 PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 100 - \nb. \nPJM Compliance Filing \n182.\nPJM proposes to modify the existing Tariff definition of BTMG and add a new \ndefinition for Retail BTMG to establish a materiality threshold for Retail BTMG.471  PJM \nexplains that the current Tariff definition of BTMG includes both Retail and Non-Retail \nBTMG, but the Tariff only specifically defines Non-Retail BTMG.472  Therefore, PJM \nproposes to separately define Retail BTMG as BTMG that is used to serve a retail load \nserved by a Network Customer located at the same electrical location, where such \ngeneration has a cumulative nameplate rating of no greater than 50 MW.473  PJM also \nproposes to clarify in the Tariff that Retail BTMG may not be part of a Co-Located Load \nconfiguration. PJM argues that this clarification is necessary \"to avoid unexpected and \nunintended hybrid scenarios mixing BTMG and the new transmission service \nproducts.\"474 \n183.\nPJM states that the proposed materiality threshold, along with other exclusions \ndiscussed below, will avoid the \"unintended consequence of causing Retail BTMG \nresources to prematurely cease operations and discontinue investment in grid-enhancing \nbackup generation,\" which may otherwise impact system reliability.475  PJM argues that a \nlower threshold of 10 or 20 MW would likely exclude Retail BTMG with limited impact \non the transmission system in comparison to Co-Located Load coming online today. \nAgreements & Procs., Order No. 2006, 111 FERC ¶ 61,220, at P 1, order on reh'g, Order \nNo. 2006-A, 113 FERC ¶ 61,195 (2005), order granting clarification, Order No. 2006-B, \n116 FERC ¶ 61,046 (2006)). \n471  Compliance Transmittal at 6-7 (citing December Order, 193 FERC ¶ 61,217 \nat P 179). \n472  Id. at 5-6 (citing PJM, Intra-PJM Tariffs, pt. I, Definitions A-B (24.0.0), Behind \nThe Meter Generation; PJM, Proposed Tariff, PJM, pt. I, Definitions L-M-N (52.0.0), \nNon-Retail Behind The Meter Generation). PJM explains Non-Retail BTMG is BTMG \nused to net load through a distribution system. PJM clarifies that no substantive changes \nare proposed to the Non-Retail BTMG netting rules, but PJM does propose clarifying \nTariff edits to avoid confusion with the new retail BTMG netting rules. Id. at 7, 15-16. \n473  Id. at 7. \n474  Id. at 18. \n475  Id. at 12. \n257 of 515"},{"page":259,"startToken":99376,"endToken":99783,"text":"Document Acc„sigISP:: qq-Aqg1.8 - 3c9curnent:Filla IEN9: g-65 A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 101 - \nPJM also contends that many of the lower MW generators would not be willing to enter \nthe interconnection queue due to age and the potential cost of Network Upgrades.476 \n184.\nPJM also proposes to exclude on-site backup generation at the same electrical \nlocation as the retail load that can only be used to serve such retail load during conditions \nthat may threaten the integrity or reliability of the PJM region or the regional power \nsystem from the 50 MW materiality threshold, arguing that to do otherwise would \ndisincentivize retail customers from installing backup generation that would improve \nreliability.477  PJM notes that the Department of Energy recently issued an order during \nWinter Storm Fern directing PJM to direct backup generation resources to operate before \ntaking certain emergency actions.478  PJM states that exempting backup generation from \nthe materiality threshold will ensure this reliability tool remains available. Finally, PJM \nstates that a materiality threshold based on the size of the generator that may qualify as \nRetail BTMG, rather than the amount of load that may net, establishes a clear and bright \nline for what can continue qualifying as Retail BTMG, given that the size of a load may \nfluctuate.479 \n185. PJM states that, should the Commission not accept PJM's proposal regarding \ngrandfathering, discussed below, PJM requests the Commission to allow a higher interim \ninitial materiality threshold for the start of the transition period to avoid causing Retail \nBTMG to cease operations and exacerbate the resource adequacy issues in PJM.48°  PJM \nstates that, should the Commission take this path, PJM would commit to reviewing \nadditional data on the size and extent of existing Retail BTMG to inform a final \nthreshold. \nc. \nPleadings  \ni. \nSize of Threshold  \n186.\nConstellation argues that PJM's proposed 50 MW materiality threshold for BTMG \nis too high and urges the Commission to either reject it or require modifications to \n476  Id at 12-13. \n477  Id at 13 (citing US Department of Energy, Order No. 202-26-06 (Jan. 26, \n2026), https://www.energy.gov/documents/doe-order-no-202-26-06-pjm). \n478  Id at 13-14 (citing US Department of Energy, Order No. 202-26-06). \n479  Id at 13-14. \n480 Id at 14-15 (noting PJM ICC's request for a 200 MW threshold in PJM ICC's \nRequest for Clarification or Rehearing, Docket No. EL25-49-000, et al., at 44). \n258 of 515"},{"page":260,"startToken":99783,"endToken":100224,"text":"Document Access igf?Sg 42-WA 8-34@cument:Flil d  ERN \ne?-e5/48 /2 PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 102 - \naddress undue discrimination against Co-Located Loads. Constellation argues that this \nthreshold will allow a significant number of loads with BTMG to take advantage of \nunjust and unreasonable netting and include backup generation as offsetting BTMG, but \ndeny such treatment to Co-Located Load, despite there being no physical, technical, or \neconomic reason why a netting construct should apply differently for customers with \nBTMG or with Co-Located Generators. Constellation argues that PJM has not provided \nany explanation for why the proposed threshold is relevant to reducing the reliability and \nresource adequacy risks that large or increasing BTMG may pose to PJM and argues that \nPJM's justifications for the threshold are unsupported.481 \n187. Other parties argue that PJM's proposed threshold is too low.482 \nIndustrials/Amtrak argue that a threshold of at least 200 MW would better capture the \nlarge loads driving reliability and cost-shifting concerns, while maintaining the existing \nretail BTMG netting rules that promote smaller resource adequacy investments, and \navoid economic damage to industrial, institutional, and transportation sectors. \nIndustrials/Amtrak argue that a 200 MW threshold is also appropriate because PURPA \ndefines small generation for non-cogeneration QFs as 80 MW or smaller, meaning large \ngeneration must be greater than 80 MW. Industrials/Amtrak also argue that this threshold \nwould simplify the transition process by eliminating most grandfathering issues and \nbolstering resource adequacy and grid efficiency, thereby avoiding inefficient \ntransmission investment. Industrials/Amtrak argue that a 200 MW threshold would \nrespect the importance of onshoring manufacturing and support Amtrak's operations, \nbecause Amtrak relies on more than 50 MW of retail BTMG, generated at 25 Hz, to \nprovide energy supply and the only black start capability to the south end of Amtrak's \nNortheast Corridor traction power system.483 \n188.\nEnergy Artisans also support a 200 MW materiality threshold.484  Energy Artisans \nargue that, for sites that exceed this higher threshold, the Commission should require \nPJM to use the proposed Interim NITS because it would provide PJM with a \"safety \n481  Constellation Protest and Comments on Compliance Filing at 9-11. \n482  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 9, 25; \nCrusoe Comments on Compliance Filing at 4; Eastman Protest and Comments on \nCompliance Filing at 6; EDFps Comments on Compliance Filing at 4; Energy Artisans \nProtest of Compliance Filing at 1; DPN Comments on Compliance Filing at 4. \n483  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 9, 25, \n31, 33, 39. \n484  Energy Artisans Protest of Compliance Filing at 2. \n259 of 515"},{"page":261,"startToken":100224,"endToken":100639,"text":"Document Accessigi?SP; 'q-A§:g-18-31;29Cument:Flild rFa'q99: (2,6/C18/2pAte Filed: 10/16/2026_ \nDocket No. EL25-49-002, et al. \n- 103 - \nswitch\" to manage reliability during peak emergencies without forcing expensive \nupgrades or disconnection on industrial users. \n189.\nEastman similarly argues that, if the Commission does not maintain netting for \nBTMG facilities like Eastman's Kingsport facility, the Commission must establish a \nthreshold of at least 200 MW on a permanent basis. Eastman explains that its Kingsport \nfacility has generation with a nameplate capacity of 194 MW, but that it cannot withdraw \nthat amount of energy through its interconnection with Kingsport Power and could not \noperate solely on electric power from the grid. Eastman argues that imposing an \narbitrarily low materiality threshold would eliminate the grid benefits that its BTMG \nfacilities have provided.485 \n190.\nIndustrials/Amtrak and Eastman argue that setting the threshold too low will \nincrease costs for many existing loads with BTMG and make a lot of existing BTMG \nuneconomic.486  Industrials/Amtrak argue that even if load with BTMG were to have that \ngeneration participate in the PJM markets, there is no guarantee of that generation \nearning sufficient revenue to make up for the loss of netting, especially as transmission \nupgrades may be required to interconnect the generation. Industrials/Amtrak also argue \nthat setting the threshold too low will force substantial burdens on existing customers to \nbecome Commission-regulated public utilities, secure PJM membership, and undertake \nrelated credit and risk requirements. Moreover, Industrials/Amtrak argue, a low \nthreshold would remove the incentive to operate efficiently and during stressed system \nconditions, as well as create additional work for PJM staff to study BTMG that must \neither go through the interconnection queue or deactivate. Industrials/Amtrak contend \nthat retirement of existing BTMG would increase demand and transmission planning \nneeds in the near term, resulting in higher transmission rates.487  Energy Artisans argue \nthat PJM's proposed 50 MW materiality threshold is an arbitrary cap that ignores the \ncapital-intensive investments made by large-scale industrial facilities.488 \n191.\nIndustrials/Amtrak argue that BTMG can provide benefits to the transmission \nsystem, including reducing large loads on the system, congestion, and transmission \n485  Eastman Protest and Comments on Compliance Filing at 6. \n486  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 7; \nEastman Protest and Comments on Compliance Filing at 6. \n487  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 15, \n25-26, 28. \n488  Energy Artisans Protest of Compliance Filing at 1. \n260 of 515"},{"page":262,"startToken":100639,"endToken":101044,"text":"Document Accessigi@V; 2A \n18-34 ument:FlAd rpaN: g66/11812PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 104 - \nsystem build out, as well as operating during system emergencies.489  EDFps argues that \nBTMG can reduce grid congestion, avoid queue delays, lower Network Upgrade needs, \nand provide economic and community benefits such as tax revenues and jobs.49° \n192.\nCrusoe argues that while the 50 MW threshold aligns with PJM's definition of \nlarge load additions, this threshold is not a bright-line test for what constitutes a \nreliability risk. Crusoe contends that the materiality threshold should be flexible to \naccount for the fact that Co-Location Arrangements can vary significantly and should be \nscaled in proportion to the load served. Crusoe argues that a lower threshold risks forcing \nexisting BTMG resources offline during the transition period, which would increase \nburden on the grid by converting currently netted load into Network Load. Crusoe claims \nthat BTMG arrangements benefit the transmission system by serving load on a \nstreamlined basis, avoiding generator interconnection queue delays, and reducing the \nneed for Network Upgrades.491 \n193.\nEnergy Artisans also contend that the 50 MW materiality threshold is unduly \ndiscriminatory because it establishes a 50 MW nameplate cap for retail BTMG while \nmaintaining a 3,000 MW regional cap for Non-Retail BTMG.492  In the absence of \ndemonstrated negative impacts from existing BTMG configurations, Energy Artisans \nclaim that the 50 MW materiality threshold is a pretext for cost-shifting. \n194. EDFps argues that PJM's proposed 50 MW threshold is arbitrary and will \ndisincentivize large loads from installing their own generation and thereby stifle \ninnovation. EDFps contends that the threshold will instead incentivize the development \nof smaller loads, as well as segmented loads close in proximity to avoid the threshold, \nleading to inefficient and redundant construction of interconnection facilities. EDFps \nnotes that the \"optimal sizing of Retail BTMG\" for an artificial intelligence data center, \nfor example, would be higher than 50 MW and that the threshold would force new large \nloads to develop grid-connected resources instead of BTMG resources.493  EDFps argues \nthat this threshold would result in generation going through the interconnection process \nunnecessarily. \n489  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 6. \n49°  EDFps Comments on Compliance Filing at 2, 4. \n491  Crusoe Comments on Compliance Filing at 4-5. \n492  Energy Artisans Protest of Compliance Filing at 2. \n493  EDFps Comments on Compliance Filing at 4. \n261 of 515"},{"page":263,"startToken":101044,"endToken":101436,"text":"Document A„eesigl.; qCP2f6q1.8 - \nage: g.563.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 105 - \n195.\nEDFps argues the materiality threshold should instead be 100% of the load size at \nthe electrical location, \"combined with operational safeguards and appropriate \ntransmission charges.\"494  Specifically, EDFps proposes that retail BTMG larger than \n50 MW would still be permitted to net generation against load for the purposes of energy \nand capacity market settlements, but would pay transmission and/or distribution network \ncharges on a gross basis.495 \n196.\nDPN similarly argues that PJM's proposal may be too restrictive for digital \ninfrastructure projects, many of which operate at scales well above 50 MW, and that \nbehind-the-meter configurations can provide a viable pathway to speed-to-power. \nAdditionally, DPN argues, the Commission should not require projects to rely on a \nframework that may compound PJM's already significant queue and study delays without \ngreater justification. DPN argues that the Commission should require PJM to better \njustify why 50 MW is the appropriate threshold at this stage and whether a higher \nthreshold, at least on an interim basis, would better accommodate current uncertainty \nwhile PJM and the Commission continue to refine their understanding of large load \nimpacts.496 \n197.\nAEU/SEIA claim that PJM's proposal to require site-located generation to enter \nthe interconnection queue is unjust and unreasonable. AEU/SEIA assert that PJM \nrequires BTMG arrangements that exceed the materiality threshold or do not qualify for \ngrandfather status to transition to a Co-Location Arrangement, which entails pursuing a \nfull interconnection agreement with PJM. AEU/SEIA contend that there is no benefit to \nsubjecting these projects to the standard queue process as they do not require \ndeliverability and will rarely trigger Network Upgrades. AEU/SEIA requests that PJM \nbe encouraged to establish a streamlined, expedited process for resources that do not \nintend to export to the grid, which would allow PJM to maintain visibility while \nminimizing delays for non-exporting resources.497 \nii. \nPJM Proposal to Tie Threshold to Generator \nNameplate Rating \n198.\nSeveral parties urge the Commission to reject PJM's proposal to base the \nmateriality threshold on the amount of generation that can be netted rather than load, \n494  Id at 1-2. \n495  Id. at 4-5. \n496  DPN Comments on Compliance Filing at 4-5. \n497  AEU/SETA Limited Protest of Compliance Filing at 11-13. \n262 of 515"},{"page":264,"startToken":101436,"endToken":101876,"text":"Document Accessig@V; 4Q2-W48 - 349cument:FlAd rpai@p:g6A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 106 - \narguing that this proposal is inconsistent with the December Order.498  BTMG Parties \nargue that the scale of the reduction in load (i.e., what PJM considers and plans for versus \nwhat PJM may actually need to serve) determines whether the potential for resource \nadequacy problems and cost shifts are problematic—not the nameplate of the generation \nused to effect the load reduction.499  Similarly, Industrials/Amtrak argue that nameplate \ncapacity does not necessarily reflect the actual capability of BTMG, such as, for example, \na steam system where the generation output is limited by the steam system's capability.5°° \n199. BTMG Parties further argue that such a nameplate generation-based threshold is \nunjust, unreasonable, and unduly discriminatory because it would also unnecessarily \nconstrain commercial opportunities to serve loads with BTMG without better protecting \nreliability or commensurate reductions in resource adequacy or cost-shift risks and would \ntreat differently BTMGs with similar resource adequacy and cost-shift impacts. BTMG \nParties argue that accepting PJM's proposal would violate notice requirements and that \nthe metering, telemetry, and control capabilities already deployed for existing BTMG \nresources demonstrate that BTMG can reliably comply with the operational requirements \nnecessary to implement a netting-based threshold.501 \n200.\nBTMG Parties argue that, in the alternative, the Commission should require PJM \nto increase its proposed nameplate rating-based materiality threshold for retail BTMG \neligibility to 200 MW to preserve opportunities for load to realize the commercial benefit \nof sizing nameplate generation above the amount of load that a retail customer seeks to \nnet while still achieving the Commission's aim of limiting resource adequacy impacts \nand cost-shift concerns.5°2 \n201.\nAEU/SEIA argue that PJM's proposed threshold is inconsistent with how PJM \nassesses capacity accreditation in the capacity market and lacks the necessary flexibility \nto accommodate resource diversity and hybrid configurations such as storage paired with \nsolar. AEU/SEIA add that there are a number of reasons that, in a BTMG configuration, \nthe generator's nameplate capacity exceeds the customer's netting. AEU/SEIA contend \n498  BTMG Parties Joint Protest of Compliance Filing at 1, 4-5; Industrials/Amtrak \nJoint Protest and Comments on Compliance Filing at 34-35 (citing December Order, \n193 FERC ¶ 61,217 at P 179); AEU/SETA Limited Protest of Compliance Filing at 3. \nSee also Earthjustice Reply Briefing at 24. \n499  BTMG Parties Joint Protest of Compliance Filing at 6. \n500 Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 35. \n501 BTMG Parties Joint Protest of Compliance Filing at 2, 6-12. \n5°2  Id at 2, 12-13. \n263 of 515"},{"page":265,"startToken":101876,"endToken":102269,"text":"Document A„es'sig#SA:  4q-2YA18-3P9cUrnent:FlAd 1130_99: g-56 A8/2pte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 107 - \nthat a reasonable approach would be to permit facilities to exceed 50 MW nameplate \ncapacity provided the customer's netting is limited to 50 MW, and the facility uses \napproved telemetry and automated system controls.503  Appalachian Voices argues that \nPJM's compliance filing is unclear as to whether it will apply the 50 MW materiality \nthreshold to all generation or to each individual generator at a single customer site.504 \n202.\nIndustrials/Amtrak state that, if the Commission opts for a generation-based \nmateriality threshold, they support PJM's proposal on backup generation.505 \nIndustrials/Amtrak explain that emergency backup generation is often sized similarly to \nother on-site generation to function as a full backup power source and provides additional \ngeneration options in emergency conditions, such as the Department of Energy's recent \nstatement regarding the operation of private, behind-the-meter generation during Winter \nStorm Fern.5\" EDFps argues that the Commission should direct PJM to clarify that \nbattery energy storage systems and hybrid systems functioning in a load-following, \nnon-exporting capacity manner during a curtailment event qualify under the \"backup \ngeneration\" exception from the materiality threshold for the revised retail BTMG netting \nrules and can continue to serve the load regardless of their size.507 \niii. \nPJM Proposal to Disqualify Network Customers \nAbove the Materiality Threshold  \n203.\nSeveral parties argue that the Commission should allow netting up to the amount \nof the materiality threshold, rather than disqualifying a customer from netting for any \namount of load if its BTMG exceeds the threshold.508  Industrials/Amtrak argue that this \nallowance would be more consistent with the December Order, reduce discrimination \nconcerns, and avoid incentivizing loads to reduce the size of their generation to ensure \n503 AEU/SEIA Limited Protest of Compliance Filing at 4-5. \n504 Appalachian Voices Limited Protest of Compliance Filing at 4 (citing \nCompliance Transmittal at 11-12). \n5°5  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 10. \n5°6  Id. at 40-41 (citing U.S. Department of Energy, Emergency Order \nNo. 202-26-06). \n5°7  EDFps Comments on Compliance Filing at 8. \n508 Id. at 9, 34; Eastman Protest and Comments on Compliance Filing at 7; Energy \nArtisans Protest of Compliance Filing at 2; EDFps Comments on Compliance Filing at 5. \n264 of 515"},{"page":266,"startToken":102269,"endToken":102656,"text":"Document Access igPSP; 2A-21§A1.8 - 349c ument:FlAd  raqi3: g.66A 8 / 2  p_4;e Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 108 - \nnetting eligibility.'\" Industrials/Amtrak contend that PJM's proposal would distort \ninvestment decisions, produce outcomes disconnected from actual system needs, harm \nresource adequacy, and harm economic development opportunities in PJM.51° \n204.\nEnergy Artisans contend that by rejecting a hybrid BTMG and Co-Location \napproach, under which facilities could net up to the materiality threshold, PJM would \nforce large loads off of BTMG status and onto the grid.5\" EDFps disagrees with PJM \nthat allowing netting up to the amount of the materiality threshold would lead to \nadditional metering costs, noting that grandfathered entities and those below the threshold \nwould not incur any such costs. EDFps also argues that it should be up to individual \nentities whether the additional cost for metering is worth exceeding the threshold. EDFps \nstates that load served by a retail BTMG resource would be required to purchase NFCD \ntransmission service up to the amount covered by the retail BTMG and FCD transmission \nservice for the remainder of the load and could not lean on the system.512 \niv. \nAnswers \n205.\nIndicated TOs argue that PJM's proposed 50 MW materiality threshold strikes the \nappropriate balance between allowing continued use of retail BTMG and limitations to \nensure reliability. Indicated TOs agree with PJM that 50 MW is reasonable because it \naligns with the PJM Board's definition of large load additions, preserves existing \ntreatment for smaller and longstanding retail BTMG arrangements, and avoids sweeping \nin retail customers whose grid impacts are comparatively limited. Indicated TOs argue \nthat PJM reasonably based the threshold on generator size because generator capacity is \nstatic.513 \n206.\nIndustrials/Amtrak argue that the Indicated TOs fail to substantiate their position \nwith any evidence in support of the 50 MW threshold, and do not address any of the \narguments for a 200 MW or greater threshold. Industrials/Amtrak contend that load \nunder 200 MW, particularly industrial and institutional load, is not driving current \n509  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 9-10. \n51°  Id at 36. \n511  Energy Artisans Protest of Compliance Filing at 2. \n512  EDFps Comments on Compliance Filing 2, 6-7. \n513  Indicated TOs April 24 Answer at 2-3. \n265 of 515"},{"page":267,"startToken":102656,"endToken":103109,"text":"Document Accessigsg 2A-2.vg-18 _3p.pcument:Flit d rfa'qg9: gp/q8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 109 - \nreliability challenges.514  Eastman contends that the Indicated TOs' answer \ninappropriately lumps together all industrial BTMG facilities, ignoring that not all loads \nusing BTMG create reliability and resource adequacy risks.515  BTMG Parties argue that \nIndicated TOs' defense of a nameplate-based threshold is non-responsive to the BTMG \nParties' argument because the sole question before the Commission is compliance.516 \nIndicated TOs respond that PJM's 50 MW threshold is reasonable and should be \naccepted.517  Indicated TOs further argue that the Commission did not preclude a \ngeneration-based threshold, as it provided points of reference based on generator size, not \nthe size of the load.518  Indicated TOs lastly allege that parties conflate the two issues of \nthe materiality threshold and the grandfathering provision, and that the need for an \nadequate grandfathering provision is not a convincing reason to increase the size of the \nmateriality threshold. \nd. \nDetermination \n207. \nWe accept in part, and reject in part, PJM's compliance filing with respect to the \nBTMG materiality threshold. Specifically, we accept as just and reasonable PJM's \nproposal to set the materiality threshold at 50 MW and to exclude on-site backup power \nfrom that threshold. However, we reject PJM's proposal to apply the threshold to the \ncumulative nameplate capacity of generation that is used to serve a retail load served by a \nNetwork Customer located at the same electrical location, rather than to the total amount \nof load that can be netted at that electrical location, because this proposal does not \ncomply with the Commission's directives in the December Order.519  We thus direct PJM \nto file, within 60 days of the date of this order, a compliance filing to revise its proposed \ns\" Industrials/Amtrak Answer at 3-4 (citing Industrials/Amtrak Joint Protest and \nComments on Compliance Filing at 25). \n515  Eastman Answer at 2 (citing December Order, 193 FERC ¶ 61,217 at P 107). \n516  BTMG Parties Answer at 2-3. \n517  Indicated TOs June 3 Answer at 3. \n518  Id. at 4. \n519  We therefore reject Proposed Tariff, § I.1 Definitions R-S (Retail Behind The \nMeter Generation) (46.0.0) and § VIII.A 400, Definitions R (Retail Behind The Meter \nGeneration) (7.0.0). We accept Proposed Tariff, § I.1 Definitions A-B (Behind The \nMeter Generation) (24.0.0); § III.34.2 (Netting of Retail Behind the Meter Generation) \n(1.0.0); § 111.34.3 (Netting of Non-Retail Behind The Meter Generation) (2.0.0); § VII.A \n300, Definitions B (Behind The Meter Generation) (2.0.0); and § VIII.A 400, \nDefinitions B (Behind The Meter Generation) (2.0.0). \n266 of 515"},{"page":268,"startToken":103109,"endToken":103606,"text":"Document AccessigPA 2A2-VA18-349cument:Flild E N9: g. tg 8  / 2  p2qte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 110 - \ndefinition of Retail BTMG in its Tariff to permit a Network Customer to net up to \n50 MW of load that it is serving using BTMG at a particular electrical location. \n208.\nIn the December Order, the Commission explained the materiality threshold as \nfollows: \"Such a threshold should reduce the reliability and resource adequacy risks \ndiscussed above that large loads may pose to PJM, while also allowing for Network \nCustomers to reduce their transmission charges in a transparent, not unduly \ndiscriminatory fashion.\"52°  Based on the record here, we find that a threshold of 50 MW \nis just and reasonable and preferable to the 200 MW threshold that some commenters \npropose because a 50 MW threshold will ensure that PJM plans its transmission system \nand procures sufficient capacity resources to serve a greater percentage of the load that, \nin the event that the BTMG that typically serves it is unavailable, PJM would be \nnonetheless obligated to serve. As such, we find that PJM's proposed 50 MW materiality \nthreshold is more likely to help maintain resource adequacy and reliability relative to a \nlarger threshold.52I  Whereas Constellation argues that PJM's proposed materiality \nthreshold of 50 MW is too high and unsupported, we agree with PJM that 50 MW strikes \na reasonable balance between a lower threshold, which may restrict netting more than \nnecessary to respond to resource adequacy concerns, and a higher threshold, which would \nfail to address the resource adequacy concerns identified in the December Order.522 \n209.\nIn response to protesters' concerns that the proposed materiality threshold of \n50 MW is too low and will result in significant economic consequences to existing \nBTMG arrangements,523  we note that the Commission addressed this concern in the \n52°  December Order, 193 FERC ¶ 61,217 at P 221. \n521  See id. P 186 (\"We find that PJM's existing BTMG rules may lead to both \nreliability and resource adequacy risks because PJM, per its Tariff, is obligated to serve \ntransmission customers using BTMG but does not consider such customers in \ntransmission and resource adequacy planning.\"). \n522  See Vonage Holdings Corp. v. FCC, 489 F.3d at 1242; ExxonMobil Gas Mktg. \nCo. v. FERC, 297 F.3d 1071, 1085 (D.C. Cir. 2002) (\"We are generally `unwilling to \nreview line-drawing performed by the Commission unless a petitioner can demonstrate \nthat lines drawn . . . are patently unreasonable, having no relationship to the underlying \nregulatory problem.\") (citations omitted). \n523  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 27-28 \n(alleging economic damage to retail customers); DPN Comments on Compliance Filing \nat 4 (expressing concern that 50 MW risks foreclosing pathways for digital infrastructure \nprojects \"through imposing additional barriers to utilization\"); Eastman Protest and \nComments on Compliance Filing at 6 (\"the proposed threshold would remove the \neconomic benefits that Eastman has relied on to continue operating its BTMG at the \n267 of 515"},{"page":269,"startToken":103606,"endToken":104033,"text":"Document Accessigri \nqq-2.vg-1 _ 31R9.9 umen t:F 1 \nd  EFAg9: gpiel.  / 2  pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 111 - \nDecember Order and established separate mechanisms—a transition period of three years \nfor Network Customers currently using PJM's retail BTMG netting rules and \ngrandfathering for certain entities in a BTMG arrangement—in recognition of the \npotential impacts for existing BTMG customers of a change in the retail BTMG netting \nrules.524  While we recognize the concerns raised in this record that adopting any \nlimitations on netting may have economic consequences for individual Network \nCustomers, we must balance those concerns against the Commission's finding that PJM's \nretail BTMG netting rules are unjust and unreasonable due to the reliability, resource \nadequacy, and cost-shifting concerns they create.525  As discussed above, the materiality \nthreshold primarily serves to reduce reliability and resource adequacy risks that large \nloads may pose to PJM, and we find that PJM's proposed 50 MW materiality threshold \nstrikes a reasonable balance between mitigating those risks and limiting the costs \nassociated with doing so. \n210.\nWe decline to require Eligible Customers seeking NITS on behalf of load with \nBTMG to take Interim NITS for load above the materiality threshold, as Energy Artisans \nrequest. Energy Artisans appear to contemplate taking a combination of Interim NITS \nand NITS at the same Point of Delivery, which is not permitted.526  However, we note \nthat such customers may take Interim NITS, as discussed in Part IV.527 \n211.\nWe also disagree with arguments that the materiality threshold should be higher to \nensure that BTMG resources have an incentive to operate efficiently.528  This concern \nKingsport facilities . . . .\"); Energy Artisans Protest of Compliance Filing at 1 (\"PJM's \nproposal to implement a 50 MW `Materiality Threshold' for Retail BTMG is an arbitrary \ncap that ignores the long-term, capital-intensive investment cycles of large-scale \nindustrial facilities.\"). \n524  December Order, 193 FERC ¶ 61,217 at PP 222-224. \n525 Id. P 186. \n526  Energy Artisans Protest of Compliance Filing at 2 (\"For sites exceeding this \n200 MW threshold, the Commission should direct PJM to utilize the proposed [Interim \nNITS] under the new Part XI of the Tariff.\"). \n527  See supra Part IV.C.1.b.i (extending the three new transmission services set \nforth in the December Order to Eligible Customers taking service on behalf of load with \nBTMG that are willing and able to limit their energy withdrawals from the transmission \nsystem under certain conditions). \n528  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 7, 16, \n25, 32. \n268 of 515"},{"page":270,"startToken":104033,"endToken":104457,"text":"Document Acc„sigRSg 2Aegi 8- 3QgicUMent:FlAd rFai@g9: AE18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 112 - \ndoes not overcome the Commission's finding that large amounts of netted Network Load \npresent reliability and resource adequacy risks. When BTMG operates during peak or \nemergency conditions, it may enhance resource adequacy in the short term by lowering \nthe demand on the system, but when it fails to operate (which, despite any incentive to \noperate, is possible), the result would be that PJM would have an obligation to serve the \nload that such BTMG typically serves without having planned adequate transmission \nfacilities or procured sufficient capacity resources to fulfill that obligation. The \nCommission found that risk unjust and unreasonable in the December Order.529 \n212.\nWe also disagree with Energy Artisans that a 50 MW materiality threshold is \nunduly discriminatory because it establishes a 50 MW cap for Retail BTMG while \nmaintaining a 3,000 MW regional cap for Non-Retail BTMG.53°  The materiality \nthreshold and the cap on Non-Retail BTMG function differently—the Non-Retail BTMG \ncap is a region-wide cap on the amount of load that may net using Non-Retail BTMG,531 \nwhereas the materiality threshold for Retail BTMG is on the amount of load that may net \nat a particular electrical location.532 \n213.\nWe acknowledge EDFps' concern that a 50 MW materiality threshold on Retail \nBTMG could encourage the development of smaller loads combined with smaller \ngenerators, and force new large loads to develop resources interconnected to the \ntransmission system instead of BTMG resources.533  As the Commission explained in the \nDecember Order, the Commission eliminated retail BTMG netting to prevent large loads \nfrom using the retail BTMG netting rules; the Commission agreed with PJM that \nallowing large loads to net is problematic because such loads do not carry reserves and \nare able to rely on the transmission system when the BTMG is not sufficient to meet the \nload.534  EDFps' alternative proposal would not remedy this concern because it would \ncontinue to net BTMG for the purposes of capacity market settlements.535 \n529  December Order, 193 FERC ¶ 61,217 at P 186. \n530 Energy Artisans Protest of Compliance Filing at 2. \n531  See PJM, Intra-PJM Tariffs, OATT, § III, § 34.3 (Netting of Non-Retail Behind \nThe Meter Generation) (1.0.0). \n532  December Order, 193 FERC ¶ 61,217 at P 221. \n533  EDFps Comments on Compliance Filing at 3-4. \n534  December Order, 193 FERC ¶ 61,217 at P 186. \n535  EDFps Comments on Compliance Filing at 4-5. \n269 of 515"},{"page":271,"startToken":104457,"endToken":104945,"text":"Document Adcessigii,-; 2-Actg-18 _3pp_cument:FlAd rj38. g9: A7/0.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 113 - \n214.\nFurther, we find AEU/SEIA's assertion that requiring BTMG arrangements that \nexceed the materiality threshold or do not qualify for grandfather status to transition to a \nCo-Location Arrangement, which entails pursuing an interconnection agreement with \nPJM, is unjust and unreasonable is an untimely request for rehearing of the December \nOrder. In the December Order, the Commission found that PJM's existing retail BTMG \nnetting rules are unjust and unreasonable because they may lead to both reliability and \nresource adequacy risks in PJM.536  The Commission then directed PJM to revise its retail \nBTMG netting rules to establish a new MW materiality threshold for the amount of load \nat a particular electrical location that Network Customers may net using BTMG and to \nimplement a transition process that includes the ability to grandfather certain entities with \nexisting contracts.537  Because AEU/SEIA's assertion challenges the Commission's \nfinding that PJM's existing retail BTMG netting rules are unjust and unreasonable and \nthe related compliance directives—and not whether PJM complied with those \ndirectives—we find that it is an untimely request for rehearing of the December Order \nand dismiss it on that basis.538 \n215.\nHowever, we agree with protesters that PJM's proposal to design the materiality \nthreshold for netting based on whether the \"generation has a cumulative nameplate rating \nof no greater than 50 MW\" fails to comply with the Commission's directive in the \nDecember Order. Specifically, the Commission directed PJM to \"propose a new MW \nthreshold for the amount of load at a particular electrical location that Network \nCustomers may net by using BTMG.\"539  As such, PJM's proposal to instead apply the \nmateriality threshold to the cumulative nameplate capacity of the generation used by a \nNetwork Customer to serve retail load located at the same electrical location is facially \ninconsistent with the December Order. \n216.\nPJM alleges that its proposal to apply its proposed materiality threshold based on \nthe cumulative nameplate capacity of the generation is consistent with or superior to the \nCommission's directive to limit reliability and resource adequacy risks. In particular, \nPJM alleges that its proposal is consistent with the Commission's points of reference to \nvarious generator sizes, as well as the recognition that BTMG is defined as a generation \nunit rather than a load. We find PJM's arguments unpersuasive. While the Commission \n536  December Order, 193 FERC ¶ 61,217 at P 179 (finding that \"the existing \nBTMG rules may lead to both reliability and resource adequacy risks because PJM, per \nits Tariff, is obligated to serve transmission customers using BTMG but does not consider \nsuch customers in transmission and resource adequacy planning\"). \n537  Id. P 179. \n538 Louisville Gas & Elec. Co., 185 FERC ¶ 61,120, at P 39 (2023). \n539  December Order, 193 FERC ¶ 61,217 at P 221 (emphasis added). \n270 of 515"},{"page":272,"startToken":104945,"endToken":105448,"text":"Document AccessigP; 221.8-349cu\nrnent:Flita LFP:gb7A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 114 - \nreferenced examples of generator sizes in the December Order, those examples were in \nreference to an unambiguous threshold for the amount of load that a Network Customer \nmay net.5\" In addition, while BTMG is defined as a generation unit, that fact alone is not \na reason to propose to apply the materiality threshold to a Network Customer based on \nthe amount of generation at the same electrical location rather than applying that \nthreshold to the amount of load that may be netted at that location. Lastly, PJM avers \nthat, whereas load sizes can fluctuate, the nameplate capacity of a generator provides a \nbright line for purposes of qualifying for netting. This argument too is unpersuasive, \nbecause regardless of whether a Network Customer's load increases or decreases over \ntime, the 50 MW materiality threshold we approve today makes clear how much of the \nload at a-single electrical location a Network Customer may net using BTMG. \n217.\nWe also agree with protesters that PJM's interpretation of the December Order as \nprohibiting any netting when a Network Customer exceeds the materiality threshold is \nincorrect.541  PJM supports its interpretation by pointing to the Commission's directive in \nthe December Order that PJM \"maintain the current BTMG rules for customers that fall \nbelow a new MW materiality threshold,\" but PJM reads this language out of context.542 \nRead in full context, the Commission's replacement rate for BTMG in the December \nOrder only involves setting a new materiality threshold \"for the amount of load at a \nparticular electrical location that Network Customers may net by using BTMG,\" which \nthe Commission further stated would \"allow[] for Network Customers to reduce their \ntransmission charges in a transparent, not unduly discriminatory fashion.\"543  Thus, we \nfind that the Commission's directive in the December Order allows for netting of load up \nto the newly established materiality threshold. \n218.\nMoreover, the Commission expressly states that a materiality threshold \"for all \nBTMG should reduce the reliability and resource adequacy risks that large or increasing \n540 Id (\"Although we make no finding in this order on a threshold that would be \njust and reasonable, we note as points of reference that PJM requires any generator larger \nthan 10 MW to be individually metered and that the Commission's definition of a small \ngenerator is 20 MW.\") (footnotes omitted). \n541  Compliance Transmittal 10-11 (\"[T]he proposal is based on an interpretation of \nthe compliance directive that demands an `all or nothing' approach to Retail BTMG \nqualification—meaning that a Retail BTMG cannot both net up to a certain threshold but \nstill potentially have generation and load above that threshold which cannot be net\"); see \nEastman Protest and Comments on Compliance Filing at 7; Industrials/Amtrak Joint \nProtest and Comments on Compliance Filing at 34. \n542  Compare December Order, 193 FERC ¶ 61,217 at P 179, with id. P 221. \n543  Id. P 221 (emphasis added). \n271 of 515"},{"page":273,"startToken":105448,"endToken":105892,"text":"Document AcceesigPSA 2k2VAI.8-39991-Iment:Fhld rPaq99: ?-67A 812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 115 - \nBTMG may pose to PJM.\"544  To use an example similar to that provided by the BTMG \nParties, PJM's proposal would prohibit a Network Customer serving 50.1 MW of load \nusing BTMG from netting any load, but it would allow a Network Customer serving \n50 MW of load using BTMG to net all of that 50 MW of load, even though they have \nvirtually identical resource adequacy impacts on the transmission system.545  We find that \nthis outcome would be unduly discriminatory and conflict with the December Order.546 \nWe also note that protesters persuasively dispute PJM's suggestion that its proposal helps \nload with BTMG avoid incurring significant costs and compliance risks if their \narrangements exceed the materiality threshold.547  We agree with EDFps that Network \nCustomers should decide whether the costs and requirements associated with complying \nwith the revised retail BTMG netting rules are appropriate or cost-effective for their \nbusiness when determining whether to maintain or pursue BTMG arrangements.548 \n219.\nIn response to EDFps' request that the Commission clarify that electric storage \nresources and hybrid resources qualify for the back-up exemption, we note that PJM's \nretail BTMG netting rules do not restrict what resources may qualify as back-up \ngeneration, but instead specify only that the generation must be at the same electrical \nlocation as the retail load and that it can only be used to serve such retail load during \nconditions that may threaten the integrity or reliability of the PJM Region or the regional \npower system.549 \n220.\nAccordingly, we direct PJM to file, within 60 days of the date of issuance of this \norder, a compliance filing to revise its Tariff consistent with the Commission's directive \nin the December Order and our determination here. Specifically, we reject PJM's \n544  Id. P 179. \n545  BTMG Parties Joint Protest of Compliance Filing at 10. \n546  December Order, 193 FERC ¶ 61,217 at P 221 (\"Such a threshold should \nreduce the reliability and resource adequacy risks discussed above that large loads may \npose to PJM, while also allowing for Network Customers to reduce their transmission \ncharges in a transparent, not unduly discriminatory fashion.\"). \n547  See, e.g., BTMG Parties Joint Protest of Compliance Filing at 11 n.20 (\"PJM \ndoes not provide any factual support for these assertions, and these statements do not \nmatch BTMG Parties' experience as developers of BTMG in PJM.\"). \n548  EDFps Comments on Compliance Filing at 7. \n549  Id., pt. VIII, Subpart A, section 400 Definitions R (definition of Retail Behind \nthe Meter Generation) (7.0.0). \n272 of 515"},{"page":274,"startToken":105892,"endToken":106227,"text":"Document AccessigiPg 2A-AltAl8-349cument:Flil d rpAp:g7A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 116 - \nproposed definition of Retail Behind The Meter Generation55°  and direct PJM to submit a \ncompliance filing modifying the Tariff to instead create a materiality threshold that \nallows Network Customers to net from their Network Load up to 50 MW of load served \nby using BTMG at a single electrical location. \n2. \nGrandfathering and Transition Period \na. \nDecember Order \n221. The Commission directed PJM to establish a transition period of three years for \nNetwork Customers currently using PJM's existing retail BTMG netting rules.551  The \nCommission also directed PJM to include in its compliance filing revisions to grandfather \nentities with existing contracts for the specific purpose of effectuating a BTMG \narrangement for the current term remaining under the existing contract.552  The December \nOrder did not direct any changes to Non-Retail BTMG.553 \nb. \nPJM Compliance Filing \n222. \nPJM proposes to modify the existing Tariff definition of BTMG and add a new \ndefinition for Retail BTMG to implement a three-year transition period and provide the \nability to grandfather certain entities with existing contracts.554  Specifically, PJM \nproposes that any existing retail BTMG with a contract that was entered into as of the \ndate of the December Order would be permitted to remain eligible to net against Network \nLoads as Retail BTMG irrespective of the materiality threshold through the term of the \ncontract.555  PJM explains that this proposal could include a wide variety of contracts, \nincluding \"utility contracts, fuel contracts, maintenance contracts, and more.\"556  PJM \n55°  PJM, Proposed Tariff, § I.1 Definitions R-S (Retail Behind The Meter \nGeneration) (46.0.0) and § VIII.A 400, Definitions R (Retail Behind The Meter \nGeneration) (7.0.0). \n551  December Order, 193 FERC ¶ 61,217 at P 223. \n552  Id. P 224. \n553  Id. P 222. \n554  Compliance Transmittal at 6-7 (citing December Order, 193 FERC ¶ 61,217 \nat P 179). \n555  Id. at 8. \n556  Id \n273 of 515"},{"page":275,"startToken":106227,"endToken":106619,"text":"Document AccessigPsne:: qq-Aqq-18 _3R9curnent:Flit d tiDA99: g37/18/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 117 - \nfurther proposes that this exemption would encompass existing renewal or extension \nrights recognized under any existing contracts to \"avoid interference with such reliance \nexpectations upon which investment decisions likely have been made . . . .\"557  PJM \nstates that if the Commission accepts its proposal, it will explore with stakeholders \nwhether manual language should be developed to help elaborate on what types of \nagreements may qualify.558 \nc. \nPleadings  \ni. \nComments  \n223.\nAEU/SEIA ask the Commission to reject PJM's proposal to transition existing \nretail BTMG through December 18, 2028 and instead extend the transition period until \nthe effective date of PJM's compliance filing to avoid harming projects already \nunderway. AEU/SEIA allege that setting the grandfathering date earlier than the \neffective date for the new co-location pathways would leave a problematic gap for \nprojects that were moving forward in good faith and exacerbate uncertainty. AEU/SEIA \nargue that any project \"in process\" as of the transition date should be eligible for \ngrandfathering if it has made significant progress toward completion though not fully \noperational.5' 9  Otherwise, AEU/SEIA allege, PJM's proposal will result in significant \nstranded assets. \n224.\nSimilarly, BTMG Parties argue that the deadlines for the transition period and \ngrandfathering eligibility will exclude retail customers that recently finalized or will \nimminently finalize projects while providing limited system benefit. BTMG Parties \nargue that PJM should be required to instead use the date of a Commission order acting \non PJM's filing, or, at minimum, 180 days from the December 18, 2025 date of the \nCo-Location Order (June 16, 2026), as the date from which the grandfathering and \ntransition period run. BTMG Parties argue that this date would better afford a workable \ntransition for market participants that does not penalize developers for attempting to \ndevelop resources during a historic resource adequacy crisis in PJM.56° \n225.\nAEU/SEIA also ask the Commission to clarify that the types of agreements that \nmay qualify for PJM's proposal include utility interconnection study agreements, \nengineering, procurement, and construction contracts, and any form of binding agreement \n557  Id. at 9. \n558  Id. at 9 n.32. \n559  AEU/SETA Limited Protest of Compliance Filing at 7-9. \n560  BTMG Parties Joint Protest of Compliance Filing at 2-3, 13-16. \n274 of 515"},{"page":276,"startToken":106619,"endToken":107060,"text":"Document AccessigPV; 2AA%q18-349curnent:Flita EFAV: A7A8/2PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 120 - \nd. \nDetermination  \n231.\nWe find that PJM's proposed Tariff revisions comply with the directives in the \nDecember Order.'\" \n232.\nFirst, we find that PJM complies with the directive to revise its Tariff to allow \nNetwork Customers already using the retail BTMG netting rules to continue to do so for \na transition period of three years from the date of issuance of the December Order.572 \nAEU/SEIA and BTMG Parties express concern that such a transition period unfairly \nharms entities that were planning to finalize arrangements in order to use PJM's retail \nBTMG netting rules. But these parties did not seek rehearing of the Commission's \ndecision in the December Order to establish a transition period to minimize the impact on \nexisting BTMG customers. In that order, the Commission explicitly directed PJM to \n\"allow Network Customers already using the BTMG rules to continue to do so for a \ntransition period of three years . . . from the date of issuance of this order.\"573  Thus, we \nfind that AEU/SEIA's and BTMG Parties' arguments constitute untimely requests for \nrehearing of the December Order.574  However, even if these arguments were properly \nbefore us, AEU/SEIA and BTMG Parties offer no suggested transition period to \nencompass certain potential BTMG customers in a manner that would not be arbitrary.575 \n233.\nSecond, we find that PJM complies with the directive to revise its Tariff to \ngrandfather entities with existing contracts that effectuate a BTMG arrangement for the \n571  See PJM, Proposed Tariff, § I.1 Definitions R-S (Retail Behind The Meter \nGeneration) (46.0.0) and § VIII.A 400, Definitions R (Retail Behind The Meter \nGeneration) (7.0.0). \n572  December Order, 193 FERC ¶ 61,217 at P 223; PJM, Compliance Filing, \nattach. B (defining Retail BTMG to provide \"for a transition period through \nDecember 18, 2028\" for Retail BTMG \"used to serve a retail load served by a Network \nCustomer to net load prior to December 18, 2025.\"). \n573  December Order, 193 FERC ¶ 61,217 at P 223. \n574  See, e.g., Louisville Gas & Elec. Co., 185 FERC ¶ 61,120 at P 39; ISO New \nEng. Inc., 132 FERC ¶ 61,098, at P 12 (2010) (\"The Commission has held that requests \nto alter a compliance filing in a manner that differs from the order requiring the \ncompliance filing constitute a collateral attack on the order requiring the compliance \nfiling.\"). \n575  See BTMG Parties Joint Protest of Compliance Filing at 15 (characterizing a \n\"limited class of BTMG developers that were very close to finalizing their projects\"). \n277 of 515"},{"page":277,"startToken":107060,"endToken":107506,"text":"Document Access igRSA 2qX;1 8 - 3Pg'cument:Flild rg@gp:?_67/4812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 118 - \nbetween the load and the BTMG developer.561  Otherwise, AEU/SEIA warn, developers \nface the risk of delay and additional regulatory burdens that could remove projects \nunderway. \n226.\nIndustrials/Amtrak support PJM's proposal to grandfather existing contracts, \nnoting that BTMG customers operate under diverse agreements, some of which renew \nyear to year, which should be eligible for grandfathering. Industrials/Amtrak also argue \nthat grandfathering rules and status should be clear, broadly construed, and easily \nconfirmed for existing BTMG customers to ensure stability and regulatory certainty.562 \n227.\nAEU/SEIA argue that PJM's proposal is unjust and unreasonable because it is not \nclear as to whether grandfathering status applies to the site itself or the generator asset. \nAEU/SEIA suggest that grandfathering the generation while allowing these existing \ncustomers to pursue additional BTMG below the materiality threshold is a logical \nextension of PJM's observation that additions below the materiality threshold would have \nlittle or no impact. AEU/SEIA argue that clarifying that customers with grandfathered \nBTMG have a \"clean slate\" to pursue additional BTMG up to the materiality threshold \nwould also allow existing customers to help address PJM's resource adequacy and \ninfrastructure needs. AEU/SEIA contend that many existing customers have neither the \ndesire nor the economic incentive to pursue co-location and that, for smaller projects, \nPJM's full interconnection process will be too costly and complex.563  Eastman similarly \nrequests that the Commission require PJM's grandfathering provision to apply to BTMG \nfacilities rather than the service agreement. Otherwise, Eastman argues, a BTMG facility \ncould lose its grandfathered status if the relevant service agreement is modified because, \nfor example, the facility was modified to become more efficient.564 \n228.\nIndustrials/Amtrak argue that most BTMG differs from the large loads that the \nCommission addressed in the December Order. Specifically, Industrials/Amtrak argue \nthat BTMG is not new, is not the cause of the changed circumstances, and does not \npresent the reliability risks posed by large, inverter-based loads.565  Further, \nIndustrials/Amtrak contend, new large loads differ from BTMG in that new large loads \ndo not have substantial cogeneration, do not generally operate large motors that can help \n561  AEU/SEIA Limited Protest of Compliance Filing at 7-8. \n562  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 10, 39. \n563  AEU/SEIA Limited Protest of Compliance Filing at 9-11. \n564  Eastman Protest and Comments on Compliance Filing at 7. \n565  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 6-7, \n13; see also Energy Artisans Protest of Compliance Filing at 1. \n275 of 515"},{"page":278,"startToken":107506,"endToken":107892,"text":"Document Accessigisp: qq,Aqg-18 _3Qp_cument:Flil d \n?7,618/2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 119 - \nwith stability on the grid, can turn off and on nearly instantaneously, and can reach sizes \nwell beyond traditional BTMG and the 200 MW threshold proposed by \nIndustrials/Amtrak. Industrials/Amtrak further claim the December Order \"did not find \nthat BTMG rules were unjust and unreasonable as used by manufacturers with \ncogeneration, other QFs (which are size limited under PURPA), or even traditional \n`large' loads with BTMG . . . .39566 \nAnswers  \n229.\nIndicated TOs argue that PJM's materiality threshold should be paired with \ngrandfathering provisions that appropriately recognize that customers have relied on \nretail BTMG netting rules and eliminating such rules could cause financial harm. \nIndicated TOs therefore propose several additions and clarifications to PJM's proposal. \nFirst, Indicated TOs argue that grandfathering treatment should extend to all projects that \nare not yet in service and would have been eligible for retail BTMG treatment, but have \nmade \"substantial progress towards completion.i567  Indicated TOs also argue that the \nexclusion regarding existing contracts should be construed broadly to cover a wide range \nof contracts and recognition of renewal rights in those contracts. Indicated TOs argue \nthat existing retail BTMG arrangements that have been physically in service and \noperating for a significant period of time should be grandfathered to avoid disrupting \nlong-standing arrangements. 568 \n230.\nBTMG Parties and Industrials/Amtrak agree with Indicated TOs that \ngrandfathering should extend to projects that would have been eligible for retail BTMG \ntreatment but for the imposition of the materiality threshold and have made substantial \nprogress toward completion in order to protect the investment-backed expectations of \nPJM customers (and the BTMG developers) and to ensure just and reasonable rates. \nBTMG Parties and Industrials/Amtrak also argue that the existing contract exception \nshould be construed broadly to cover a wide range of contracts.'\" BTMG Parties also \nargue that arrangements that have been physically in service and operating for a \nsignificant period of time should be grandfathered.57° \n566  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 14 \n(emphasis in original). \n567  Indicated TOs April 24 Answer at 3. \n568  Id at 3-4. \n569  BTMG Parties Answer at 2-4; Industrials/Amtrak Answer at 6-7. \n57°  BTMG Parties Answer at 4. \n276 of 515"},{"page":279,"startToken":107892,"endToken":108375,"text":"Document A„essigPSP; 2A r:g-1.8-3R.9CUrnent:Flild rEN9:?-67A.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 121 - \ncurrent term remaining under the existing contract.576  In response to concerns from \nAEU/SEIA and BTMG Parties, we clarify that the Tariff proposal applies to a contractual \narrangement—for which generation used to serve retail load served by a Network \nCustomer to net load is the subject—\"that was in effect as of December 18, 2025.\" \nTherefore, entities with projects that have contractual arrangements \"in place, even if \nthey are not yet fully operational\" by December 18, 2025 may qualify under the Tariff \nproposa1.577  In addition, in response to AEU/SEIA, we clarify that the types of \nagreements that may qualify under PJM's proposal may include engineering, \nprocurement, and construction contracts, and we encourage PJM, as it states in its \ntransmittal, to explore developing language in its manuals on what other types of \nagreements may qualify.578  Moreover, in response to AEU/SEIA and Eastman, who raise \noverlapping concerns about whether grandfathering applies to the generator, we clarify \nthat it does apply to the generator, as the Tariff proposal on grandfathering reflects.579  In \nfurther response to Eastman, parties to an existing BTMG contract could modify the \nagreement to, for example, make the facilities more efficient—provided that the \nmodification is not prohibited by the existing contract and does not fundamentally alter \nthe contractual arrangement that was in effect as of December 18, 2025. And in further \nresponse to AEU/SEIA, we clarify that customers with BTMG within the scope of this \ngrandfathering provision may also avail themselves of the new materiality threshold to \nnet up to 50 MW of load served by a Network Customer because this threshold applies to \na particular electrical location. \n3. \n()Fs and Cogeneration Facilities  \na. \nPJM Compliance Filing \n234. PJM proposes that the new materiality threshold should not apply to any QF over \n50 MW serving as Retail BTMG as of the date of the December Order. PJM \n576  December Order, 193 FERC ¶ 61,217 at P 224; PJM, Compliance Filing, \nattach. B (defining Retail BTMG to include \"any generation used to serve a retail load \nserved by a Network Customer to net load if it is the subject of a contractual arrangement \n(including but not limited to a bilateral agreement or interconnection agreement) that was \nin effect as of December 18, 2025 through the end of the term of such agreement, which \nmay be renewed or extended per the terms of such agreement\"). \n577  AEU/SEIA Limited Protest of Compliance Filing at 7. \n578  Compliance Transmittal at 9 n.32. \n579  PJM, Compliance Filing, attach. B (defining Retail BTMG in part to include \n\"any generation used to serve a retail load served by a Network Customer to net load if it \nis the subject of a contractual arrangement . . .\"). \n278 of 515"},{"page":280,"startToken":108375,"endToken":108758,"text":"Document AccessicIPP; 22q-2-1§A18-349cument:Flitd rfs@v: ?JAB/2 p_e,te Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 122 - \nacknowledges that the December Order does not reference PURPA, yet because the \nDecember Order was issued against the backdrop of PURPA, \"PJM interprets the \nCommission's [grandfathering] compliance directive as allowing the extension of legacy \ntreatment\" to such facilities. PJM states that some of the QFs impacted by this exemption \nare cogeneration facilities that provide economic and energy efficiency benefits.58°  In \nsupport of its proposal, PJM notes that QFs have size limitations and cogeneration QFs \nmust meet efficiency requirements.581  PJM explains that BTMG with existing \ncontractual arrangements or QF status have been in place without any known operational \nissues to date, and so should be allowed to continue netting under their existing \narrangements.582 \nb. \nPleadings  \n235. Industrials/Amtrak argue that QFs should be eligible for retail netting for their full \nload, but the eligibility should not be linked to QF status as of the date of the order.583 \nIndustrials/Amtrak explain that, without retail netting, QFs may be denied the backup \nservice to which they are entitled under PURPA. Industrials/Amtrak argue that for \ncogeneration QFs, \"the BTMG netting construct aligns with their efficient, reliable \nenergy production configurations, matching the intent of Congress and the \n[Commission].\"584  Industrials/Amtrak argue that QFs have stronger operational and \nfinancial incentives to operate reliably and efficiently than other generators and must \nmeet certain efficiency standards. However, Industrials/Amtrak note that many resources \neligible to be QFs have not maintained QF status because PURPA permits the \nCommission to deem certain QFs as having sufficient market access that it removes (for \nthose QFs) the utility's obligation to purchase excess power generated by the QF. \nIndustrials/Amtrak explain that many customers with QFs were required by this status \nchange to secure interconnection service and market-based rate authority to sell excess \nenergy into the PJM markets.585  Industrials/Amtrak argue this \"history should not limit \n58°  Compliance Transmittal at 9-10. \n581  Id. at 10 (citing 16 U.S.C. § 824a-3; 18 C.F.R. § 292.204 (2025)). \n582 m  \n583  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 8, 17. \n584  Id at 8. \n585  Id at 8, 20, 22. \n279 of 515"},{"page":281,"startToken":108758,"endToken":109173,"text":"Document AccessigP.SA: 22q-Aggi8 _3pRcument:Flil d rfAp:gp/q.8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 123 - \nthe ability of retail customers with cogeneration facilities to avail themselves of retail \nBTMG netting for energy production behind the retail meter.\"586 \n236.\nIndustrials/Amtrak argue that the BTMG netting rules ensure QFs have access to \nbackup power to which they are entitled by PURPA, at rates that are not based upon an \nassumption that forced outages or other reductions in electric output by all QFs on the \nsystem will occur simultaneously, during system peak, or both.587  Industrials/Amtrak \ncontend that the FCD or NFCD transmission services would not be sufficient to replace \nnetting, because the FCD transmission service is calculated on the maximum the load \nmight draw from the grid when the QF would only use the system sporadically, and \nNFCD transmission service must be scheduled in advance. Industrials/Amtrak also argue \nthat these services do not align with the costs or risk profile of cogeneration QFs, such \nthat, without netting, QF customers may lose their ability to manage costs even if their \nload and generation are synchronized or they never rely on transmission services, \ncreating a cost-causation gap.588 \n237.\nIndustrials/Amtrak argue that exempting QFs is appropriate and consistent with \nthe goals of the December Order because the Commission did not address PURPA. \nIndustrials/Amtrak also argue that no circumstances have changed with regards to QFs, \nwhich have been operating similarly for decades, and that PJM acknowledges that \nexisting retail BTMG arrangements with QFs have been in place without operational \nissues. Industrials/Amtrak further argue that QFs contribute to resource adequacy and \nreliability because some are limited in their use of the transmission system by the \nintegration between the load and generation.589 \n238.\nEastman argues that the proposed changes to BTMG netting ignore the operational \nrealities of facilities like Eastman's Kingsport facility, which uses its on-site electrical \ngeneration not only to provide electric power but also steam necessary for industrial \nprocesses at the facility. Eastman explains that if the Kingsport facility is unable to \ngenerate power, it also cannot generate steam, which reduces the industrial output and the \nneed for additive power from the grid. Eastman claims that during periods of grid stress, \nthe Kingsport facility is more likely to support the grid than to create operational \n586  Id at 22. \n587  Id at 19. \n588  Id at 20-21. \n589  Id at 17-19, 21. \n280 of 515"},{"page":282,"startToken":109173,"endToken":109558,"text":"Document AccessigIPP; 2721.8.-349cument:Fhla IFAV:43A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 128 - \nInterim NITS may not be combined with the FCD transmission service or NFCD \ntransmission service. \n249.\nWith respect to FCD and NFCD transmission services, the Commission found \nthese services should be permanent transmission services available to Eligible Customers \ntaking transmission service on behalf of Co-Located Load.61°  The December Order \nprovided that the Co-Located Load must be able and willing to prevent or limit its energy \nwithdrawals and must be separately metered from the associated generator. The \nDecember Order also stated that Eligible Customers taking transmission service on behalf \nof Co-Located Loads may take a combination of FCD transmission service and NFCD \ntransmission service, but that Eligible Customers taking transmission service on behalf of \nCo-Located Loads that will not withdraw energy from the transmission system must take \nNFCD transmission service at 0 MW. The Commission also found that Eligible \nCustomers taking either service on behalf of Co-Located Load would be charged for \nregulation and black start services based on gross demand, rather than the reserved \namount of transmission service.\"' \n250.\nThe Commission found that FCD transmission service should have the same \nreservation and curtailment priority as existing firm transmission services at the level of \nthe contract demand and be charged for transmission, ancillary services, and capacity \nbased on the contract demand, with the exception of regulation and black start services.\"' \nThe Commission explained that PJM would only have an obligation to plan for the \nNetwork Upgrades necessary to serve Eligible Customers taking this new FCD \ntransmission service on behalf of Co-Located Loads at their contract demand, and that \nPJM would procure capacity for these customers and should charge them based on their \ncontract demand.613  The Commission further found that FCD transmission service \nshould have a minimum term of one year and that PJM should propose an anti-toggling \nmechanism for Eligible Customers switching between FCD and NFCD transmission \nservices.614 \n251.\nWith respect to NFCD transmission service, the Commission found the service \nshould be available during normal operation and curtailed during emergency operations, \nsimilar to existing non-firm transmission service options. The Commission found the \n610  Id. P 206. \n611  Id PP 209, 216. \n612  Id PP 208-209. \n6131d P 210. \n6141d P 213. \n285 of 515"},{"page":283,"startToken":109558,"endToken":109940,"text":"Document A„essigt?Sc; 2q-AZ418-349cument:Flita rFal@P: A8A 8  / 2 ppe Filed: 10/16/2026 \nDocket No. EL25-49-Q02, et al. \n- 124 - \nconstraints. Therefore, the Commission should allow BTMG facilities like the Kingsport \nfacility to continue to net.59° \nc. \nAnswer \n239.\nIndustrials/Amtrak note that many of the customers impacted by the change in \nBTMG netting rules are QFs under PURPA, subject to efficiency standards (and for \nnon-cogeneration QFs, size limits).591 \nd. \nDetermination \n240.\nConsistent with our determination on rehearing,592  PJM must submit a further \ncompliance filing that includes a process to exempt certain cogeneration QFs from the \nnew retail BTMG netting rules if they demonstrate that they are integrated with load such \nthat, when their generating facility trips offline, the load follows. We therefore reject \nPJM's compliance filing as it relates to QFs. Specifically, we reject PJM's proposal to \nexempt from the materiality threshold all QFs serving as retail BTMG as of the date of \nthe December Order.593  PJM has not demonstrated that all load with BTMG that is either \ndesignated, or eligible to be designated, as a QF is meaningfully distinguishable from \nload with other categories of BTMG for purposes of the concerns and directives \ndiscussed in the December Order. \n241.\nIn the December Order, the Commission found that PJM's retail BTMG netting \nrules could create resource adequacy and reliability risks because PJM is obligated to \nserve transmission customers using BTMG but does not consider such customers in \ntransmission and resource adequacy planning.594  The Commission found that PJM's \nexisting retail BTMG netting rules do not limit the amount of qualifying load that a \nNetwork Customer may net by using BTMG and do not provide any protections against \nthis potential transmission and resource adequacy planning problem or against the costs \nof maintaining sufficient resources to serve these loads being shifted onto other \n590 Eastman Protest and Comments on Compliance Filing at 5, 8. \n591  Industrials/Amtrak Answer at 3, 5-6. \n592  See supra Part IV.C.1.c.i. \n593  Compliance Transmittal at 9; PJM, Proposed Tariff, § I.1 Definitions R-S \n(Retail Behind The Meter Generation) (46.0.0) and § VIII.A 400, Definitions R (Retail \nBehind The Meter Generation) (7.0.0). \n594  December Order, 193 FERC ¶ 61,217 at P 186. \n281 of 515"},{"page":284,"startToken":109940,"endToken":110372,"text":"Document Accessigg;22q-Aqq-18 _3Q9cUrnellt:Flild rjjAg9: W.08A8/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 125 - \ncustomers.595  The Commission did not distinguish in its determination between load \nserved by QFs that are BTMG and load served by other categories of BTMG. \n242.\nPJM argues that some QFs may have economic benefits and are energy efficient, \nbut PJM does not demonstrate that loads served by QFs that are BTMG do not cause the \nconcerns the Commission discussed in the December Order.596  Nor does PJM \ndemonstrate why these loads are not similarly situated to other loads served by other \ncategories of BTMG. \n243.\nPJM also notes that QFs have size limitations and cogeneration QFs must meet \nefficiency requirements.597  However, the Commission in the December Order directed a \nmateriality threshold because netting a smaller amount of load does not raise the same \nlevel of resource adequacy and reliability concerns as netting above the threshold.598 \nPJM does not demonstrate why the materiality threshold should apply differently to load \nserved by QFs that are BTMG and load served by other categories of BTMG. Further, \nefficiency requirements are not unique to QFs—other generators may have efficiency \nrequirements for other reasons or meet similar efficiency targets on their own. PJM has \nnot demonstrated why such requirements are a meaningful consideration in whether to \napply disparate treatment to load served by QFs that are BTMG and load served by other \ncategories of BTMG. Industrials/Amtrak similarly argue that QFs contribute to resource \nadequacy and reliability because some are limited in their use of the transmission system \ndue to the integration between the load and generation.599  However, as \nIndustrials/Amtrak acknowledge, this is only true of some QFs, and above we have \nrecognized that a particular subgroup, cogeneration QFs, warrant different treatment. \n244.\nIndustrials/Amtrak also argue that it is not clear whether QFs will have access to \nthe FCD or NFCD transmission services.6m  As discussed supra, Eligible Customers \ntaking transmission service on behalf of Co-Located Loads, as well as Eligible Customers \ntaking transmission service on behalf of a load with BTMG, may elect to take FCD \n595  Id. \n596  See Compliance Transmittal at 10 (broadly asserting that BTMG arrangements \nwith QF status have been netting within PJM without known operational issues to date). \n597  Compliance Transmittal at 10 (citing 16 U.S.C. § 824a-3; 18 C.F.R. § 292.204). \n598  December Order, 193 FERC ¶ 61,217 at P 221. \n599  Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 18-19, \n21. \n6\"  Id at 20. \n282 of 515"},{"page":285,"startToken":110372,"endToken":110863,"text":"Document AcceSSiII21S \nqq-2-1qA18-3RKument:FlAd EFAv:gtg\n8/2p,ate Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 126 - \nand/or NFCD transmission services.\"' While we acknowledge that Industrials/Amtrak \nalso argue that these new transmission services will not replace netting,602 our \ndetermination herein to allow Eligible Customers taking transmission service on behalf of \nloads with BTMG to take transmission service based on contract demand rather than \nNITS should they so choose could help such Eligible Customers to manage costs if they \ninfrequently rely on transmission service or can reserve needed transmission service in \nadvance (such as when the QF that serves them is on a planned maintenance outage). \n245. Industrials/Amtrak argue that without retail netting, QFs may be denied access to \nbackup service at rates that are not based upon an assumption that forced outages or other \nreductions in electric output by all QFs on the system will occur simultaneously, during \nsystem peak, or both, as required by PURPA. Under the Commission's PURPA \nregulations, the rates at which a host utility provides backup service must be just and \nreasonable and (1) shall not be based upon an assumption (unless supported by factual \ndata) that forced outages or other reductions in output by all QFs on an electric utility's \nsystem will occur simultaneously, or during system peak, or both; and (2) shall consider \nthe extent to which scheduled outages of the QF can be usefully coordinated with \nscheduled outages of the utility's facilities.603  The Commission's directive in the \nDecember Order to PJM to revise its Retail BTMG netting rules implicates the terms of \nthe Tariff for the provision of transmission service, specifically NITS, not back-up \nservice. Therefore, Industrials'/Amtrak's concern regarding backup service appears to \nconflate rates for sales of back-up power and rates for transmission service, rendering the \nconcern misplaced. As is already the case elsewhere, such as in Midcontinent \nIndependent System Operator, Inc. (MISO),6°4  NITS transmission rates in PJM, going \nforward, will be based on gross demand during the system peak. Because this directive \nfrom the December Order has no bearing on the rates at which a host utility provides \nbackup service to QFs, it necessarily does not conflict with the requirement in the \nCommission's PURPA regulations that the rates for such backup service not assume all \nQFs are on forced outage. \n601 See supra Part IV.B.3.c. \n602 Industrials/Amtrak Joint Protest and Comments on Compliance Filing at 20. \n603 18 C.F.R. § 292.305(c). \n604 See Midwest Indep. Transmission Sys. Operator, Inc., 106 FERC ¶ 61,073, \nat P 26 (2004) (\"[MISO]'s proposal to base Network Service charges for delivery of \nstation power on the basis of coincident-peak output is not consistent with its OATT or \nwith Commission precedent. Accordingly, [MISO] should include load served by \nbehind-the-meter generation, including station power load met through \non-site self-supply, in Network Load when it charges for Network Service.\"). \n283 of 515"},{"page":286,"startToken":110863,"endToken":111288,"text":"Document Ac„ssigi Sier; qq-AqA18-312991-Irnent:FlAd rPA99: 4A812pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 127 - \n246.\nWith respect to Eastman's arguments, Eastman appears to reference a \ncogeneration facility, which uses its on-site electrical generation to provide not only \nelectric power but also steam necessary for industrial processes at the facility.605  Because \nwe set aside, in part, the December Order and find that certain cogeneration QFs should \nbe exempted from the replacement rate upon a demonstration that they do not present the \nreliability or resource adequacy concerns discussed in the December Order, Eastman's \nconcern appears to be addressed.606 \nB. \nTransmission Service \n1. \nDecember Order \n247.\nThe Commission directed PJM to modify its Tariff to require that the Eligible \nCustomer taking transmission service on behalf of a Co-Located Load takes one of three \ntransmission services: (1) NITS or Interim NITS, (2) a new FCD transmission service, or \n(3) a new NFCD transmission service.607  The December Order set many of the terms and \nconditions of these services for paper hearing procedures.608 \n248.\nThe December Order stated that Interim NITS must allow an Eligible Customer \nthat has requested NITS on behalf of a Co-Located Load to take non-firm transmission \nservice that can be interrupted until the Network Upgrades necessary to provide NITS are \ncomplete and the Co-Located Load can be designated as Network Load.G09  The \nCommission also found that this service should be temporary, available only to Eligible \nCustomers that have requested NITS on behalf of Co-Located Loads that cannot yet be \nreliably served with NITS and only until the necessary Network Upgrades are completed \nand the Co-Located Load is designated as Network Load. The December Order further \nstated that Interim NITS would be optional for an Eligible Customer seeking NITS on \nbehalf of a Co-Located Load and only available to the extent PJM determines that it can \nprovide some level of interim service reliably. The Commission found that Eligible \nCustomers should pay the NITS rate for this service, as well as ancillary services charges \nand charges for black start service, but they will not be charged for generation capacity \nbecause, as interruptible loads, capacity will not be procured on their behalf until such \ntime as the Network Upgrades are in place to serve them. The Commission clarified that \n605 Eastman Protest and Comments on Compliance Filing at 5. \n606 See supra Part IV.C.1.c.i.c. \n607 December Order, 193 FERC ¶ 61,217 at P 193. \n6°8 Id. P 194. \n\" 9 Id. P 200. \n284 of 515"},{"page":287,"startToken":111288,"endToken":111608,"text":"Document AccessigPA 2A-A64,-18 _ 3gpcument:FlAd rpaqg: 43/q8/ 2 PAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 129 - \nservice should be available for terms ranging from one hour to one month and charged \nbased on as-reserved contract demand.615  The December Order clarified that PJM should \nnot include NFCD transmission service loads in its transmission or resource adequacy \nplanning.616 \n2. \nPJM Compliance Filing \n252.\nPJM clarifies that the compliance filing only includes the organizational Tariff \nchanges needed to implement the Commission's compliance directives regarding creating \nnew transmission services and that the majority of the changes will be determined \nthrough the paper hearing.617  First, PJM submits several \"shell\" Tariff sheets, including a \nnew Part XI governing the new transmission services, new Attachment F-3A for the \nservice agreement for Eligible Customers taking NITS or Interim NITS on behalf of a \nCo-Located Load, and Attachment F-4 for the service agreement for Eligible Customers \ntaking FCD transmission service or NFCD transmission service on behalf of a \nCo-Located Load.618  PJM states that it will file the full text of these sections upon the \nCommission's decision following the conclusion of the paper hearing.619 \n253.\nPJM states that it further proposes modifications to Tariff Part III, governing \nNITS, to clarify that an Eligible Customer taking transmission service on behalf of \nCo-Located Load must take a transmission service or take steps to disconnect the load \nfrom the transmission system.G20  PJM also proposes new language clarifying that an \nEligible Customer taking transmission service on behalf of a Co-Located Load may not \ntake NITS or Interim NITS at the same time as FCD or NFCD transmission service.621 \nFinally, PJM proposes that Co-Located Load that is not served by an Eligible Customer \n6151d. PP 215-216. \n6161d. P 218. \n617 Compliance Transmittal at 18-19. \n618  Id at 19-21. \n619  Id at 21. \n628  Id. at 22. \n621  Id at 22-23. \n286 of 515"},{"page":288,"startToken":111608,"endToken":112008,"text":"Document Accessig@A -AA§A18-346cument:Flild \n?„1A 812 \ne Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 130 - \ntaking transmission service on its behalf \"must take all necessary steps to disconnect \nfrom the Transmission System.\"' \n3. \nPleadings  \n254.\nEDFps supports PJM's proposed framework for the new transmission services.623 \nConstellation requests modifications to PJM's proposed Tariff revisions for Interim \nNITS, including: (1) replacing a load's \"option to seek\" Interim NITS with an \"option to \ntake\"; (2) revising section 28.1 of the Tariff to clarify that Interim NITS is available to \nEligible Customers taking service on behalf of Co-Located Load; and (3) revising \nsection 29.1 of the Tariff to clarify that the required conditions to receive NITS also \napply to Interim NITS.624 \n255.\nCrusoe argues that PJM's proposal in the paper hearing does not answer critical \nquestions such as how the initial contract demand quantity is determined, whether \ncontract demand quantities can be adjusted as Co-Located Load grows in phases, or how \nPTPS interacts with Co-Location Arrangements where both generation and load sit on the \ndeveloper's side of the Point of Change in Ownership.625 \n256.\nCrusoe supports Interim NITS as a workable, near-term solution to allow load to \noperate on the transmission system while a Co-Located Generator and/or retail BTMG is \nstill being built and interconnected.626  Crusoe claims, however, that PJM's proposed \napproach appears to treat a new Co-Located Generator as equivalent to a Network \nResource prior to it receiving such status. On that basis, Crusoe speculates that PJM may \nintend to prevent a Co-Located Generator or retail BTMG from supplying energy to \nCo-Located Load during a grid curtailment event if that load is being served via Interim \nNITS. Crusoe contends that this prohibition would create a disincentive to large load \ncustomers using Interim NITS as an option for speedy interconnection. \n257.\nDCC similarly alleges that PJM's proposal to prohibit customers from relying on a \nCo-Located Generator during curtailment events makes the proposal unworkable and \nwithout practical value. DCC also requests that PJM define the trigger, scope, and \nsequence of Interim NITS curtailment with respect to the operational limits identified in \n622 PJM, Proposed Tariff, Part HI (NITS) (4.0.0). \n623  EDFps Comments on Compliance Filing at 8. \n624  Constellation Protest and Comments on Compliance Filing at 18-19. \n625  Crusoe Comments on Compliance Filing at 8. \n626  Id at 6. \n287 of 515"},{"page":289,"startToken":112008,"endToken":112377,"text":"Document Acces s \n2A,Aeg-18 _ 3112pcument:FlA d rpAg9: A8A8/ 2 pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 131 - \nthe study and should not be able to curtail load for unrelated, broader resource adequacy \nconcerns.627 \n258.\nJoint Parties argue that the Commission should reject PJM's proposed Tariff \nrevisions that preclude retail loads served by BTMG from taking the new transmission \nservices and otherwise limit eligibility for the new transmission services to load that is \nconnecting to a generator with interconnection rights. Joint Parties argue that these retail \nloads are similarly situated to Co-Located Loads in their willingness and ability to limit \ntheir energy withdrawals from the transmission system under certain conditions.628 \n259.\nDCC argues that PJM's proposal does not provide clear timelines for customers to \nbe transitioned from Interim NITS to NITS.629  DCC expresses concern that, without \nclear timelines, Interim NITS could persist indefinitely, creating uncertainty for \ncustomers making long-term investments. \n4. \nAnswers  \n260.\nIndicated TOs argue that the Commission should reject requests to reject or defer \naction on PJM's proposal to limit the new transmission services to Co-Located Load, \nbecause, Indicated TOs contend, the December Order limited such services to Eligible \nCustomers taking transmission service on behalf of Co-Located Load. Indicated TOs \nargue that there is no evidence in the record to support that load-only customers should \nbe entitled to use the new transmission services, which Indicated TOs explain are tied to \ngenerator-specific attributes that load-only customers do not share, such as an associated \ngenerator, separate metering from the generator, and the ability and willingness to \nprevent or limit withdrawals through the Co-Location Arrangement itself.63° \n261.\nIndicated TOs state they do not oppose the requested clarification that Interim \nNITS customers be permitted to continue serving on-site load with a Co-Located \nGenerator during a curtailment event, provided that PJM implements safeguards to ensure \nthat any such operation does not result in unreserved use of the transmission system or \notherwise compromise reliability.63I \n627  DCC Comments on Compliance Filing at 6-7. \n628  Joint Parties Protest of Compliance Filing at 10. \n629  DCC Comments on Compliance Filing at 8. \n630 Indicated TOs April 24 Answer at 6-7. \n631  Id at 7-8. \n288 of 515"},{"page":290,"startToken":112377,"endToken":112843,"text":"Document AccessigPV; Z4-2-VAI.8 -3413c umentAil d rFAii: e4 /E18/2pAe Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 132 - \n262.\nBTMG Parties argue that the record contains ample evidence to support extending \nnew transmission service eligibility to all customers willing and able to limit withdrawals \nfrom the grid, including load-only customers served by BMTG or otherwise able to \nconsume flexibly.632  BTMG Parties contest Indicated TOs' claim that there is absolutely \nno evidence in the record, noting that the Commission relied on Antora's comments \nexplaining that its thermal battery technology provides for an inherently flexible, \nlow-load factor load, whether or not co-located with generation.633  BTMG Parties argue \nthat the ability to inject to the grid is not required to enable a load to limit withdrawals \nfrom the transmission system, and that the Commission should require PJM to tailor new \ntransmission service eligibility more closely to the Commission's justification in issuing \nthe Co-Location Order, namely the willingness and ability to limit withdrawals from the \ntransmission system under specified circumstances.634  BTMG Parties contend that if a \nload is able to meet technology-neutral technical requirements to demonstrate reliable \ncurtailment eligibility, it should be allowed to take the new transmission services. \n5. \nDetermination  \n263.\nWe accept PJM's compliance filing with respect to outlining new transmission \nservices in the Tariff, noting that, as discussed above in Part IV.B.3, we set aside, in part, \nthe December Order and direct PJM to submit further compliance to revise its Tariff to \nextend the three new transmission services set forth in the December Order to Eligible \nCustomers taking service on behalf of load with BTMG that are willing and able to limit \ntheir energy withdrawals from the transmission system under certain conditions.635  We \nfind that PJM complies with the directive in the December Order to modify its Tariff to \nrequire that an Eligible Customer taking transmission service on behalf of Co-Located \nLoad takes one of three transmission services: (1) NITS or Interim NITS, (2) a new FCD \n632  BTMG Parties Answer at 8. \n633  Id. at 5-6 (citing December Order, 193 FERC ¶ 61,217 at P 199). \n634  Id. at 8-9. \n635  Specifically, we accept Proposed Tariff, § III.28.1 (Scope of Service) (2.0.0); \n§ III.29.1 (Conditions Precedent for Receiving Service) (4.0.0); § III.29.2 (Application \nProcedures) (4.0.0); § III.31.6 (Annual Load and Resource Information Update) (4.0.0); \nPart XI (Transmission Services Available for Eligible Customers Taking Service on \nBehalf of Co-Located Loads) (0.0.0); attach. F-3A (Service Agreement for Regional \nNetwork Integration Transmission Service And/or Interim Regional Network Integration \nTransmission Service (For Co-Located Load)) (0.0.0); and attach. F-4 (Service \nAgreement For Contract Demand Transmission Service (For Co-Located Load)) (0.0.0). \n289 of 515"},{"page":291,"startToken":112843,"endToken":113293,"text":"Document AccessigI SA :  q -23.0gA18 - 3129c ument:Flil d rpaqg:gb-9/118/2pAte Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 133 - \ntransmission service, or (3) a new NFCD transmission service.636  We acknowledge \nPJM's statement that it filed on compliance only a limited number of the changes directed \nin the December Order, given the number of issues set to be resolved through the paper \nhearing. \n264.\nHowever, we reject the Tariff provisions proposing that Co-Located Load that is \nnot served by an Eligible Customer taking transmission service on its behalf \"must take \nall necessary steps to disconnect from the Transmission System.\"637  We find this \nprovision duplicative of PJM's proposed changes to Part VIII, Subpart B, \nsection 403(A)(1)(r)(iv), which specify that \"[t]o the extent that a Project Developer \nseeks to serve Co-Located Load using its generating facility but not identify an Eligible \nCustomer, then the Project Developer must terminate its generating facility's \ninterconnection to the Transmission System and serve the Co-Located Load fully \nislanded from the Transmission System.\" \n265.\nWe reject Constellation's request to direct PJM to modify its proposed tariff \nlanguage such that a load has an \"option to take\" Interim NITS instead of an \"option to \nseek\" Interim NITS.638  We acknowledge, as Constellation notes, that the December \nOrder stated that \"[t]his new interim, non-firm transmission service must allow an \nEligible Customer that has requested NITS on behalf of a Co-Located Load to take \nnon-firm transmission service that can be interrupted until the Network Upgrades \nnecessary to provide NITS are complete . . . .\"639  However, the December Order also \nstated that Interim NITS \"would only be available to the extent PJM determines that it \ncan provide some level of interim service reliably.51640 We accept PJM's proposal and \nclarify that Interim NITS is an option but not a right, as it is available to an Eligible \nCustomer taking transmission service on behalf of Co-Located Load only to the extent \nthat PJM determines it can be provided reliably. Constellation appears to request that the \nCommission require PJM to provide Interim NITS regardless of this reliability limitation, \nwhich would not be just and reasonable or consistent with the December Order. We \nreject Constellation's other requested clarifications on the required conditions to receive \nInterim NITS as not required for PJM to comply with the December Order. Further, \nbecause PJM proposes to create a new Tariff section governing Interim NITS, \n636  December Order, 193 FERC ¶ 61,217 at P 193. \n637  PJM, Proposed Tariff, Part III (General) (4.0.0). \n638  Constellation Protest and Comments on Compliance Filing at 18-19. \n639  December Order, 193 FERC ¶ 61,217 at P 200. \n640 Id \n290 of 515"},{"page":292,"startToken":113293,"endToken":113740,"text":"Document AccessigPW 2Q2-11 8 - 3R9cUrnent:Filtd IFA£1:4/118  2paje Filed: 10/16/2026 \nDocket No. EL25-49-002, et al. \n- 134 - \nConstellation has not shown why it is necessary to add details regarding Interim NITS to \nthe existing Tariff sections addressing NITS.\"' \n266.\nIn its comments on the compliance filing, Crusoe makes several misplaced \narguments about the illustrative tariff PJM submitted in the paper hearing.642 Crusoe \nargues that PJM's illustrative tariff does not explain how the initial contract demand \nquantity is determined. It is not clear what Crusoe means, given that the purpose of FCD \nand NFCD transmission services is to allow an Eligible Customer taking service on \nbehalf of Co-Located Load to request a specific contracted amount of transmission \nservice.643  The initial level of transmission service will thus be determined in the first \ninstance by the requesting Eligible Customer. PJM will evaluate those requests pursuant \nto its study process, which we address below.644  Crusoe also argues that PJM does not \nexplain how PTPS interacts with Co-Location Arrangements where both the generator \nand load sit on the Interconnection Customer's side of the Point of Change in Ownership. \nHowever, this arrangement appears to refer to PJM's proposed change to the definition of \nCo-Located Load, which we reject herein.645 \n267.\nCrusoe's request for clarification as to how phased-in load will be treated under \nFCD and NFCD transmission services is addressed below in Part VI.A.2. Crusoe and \nDCC also make arguments about curtailment rules or procedures for Eligible Customers \ntaking Interim NITS on behalf of Co-Located Load, and that issue is addressed below in \nPart VI.G. Finally, comments urging the Commission to reject PJM's compliance filing \nfor failing to make the new transmission services available to Eligible Customers on \nbehalf of non-Co-Located Loads are untimely requests for rehearing. These commenters \nargue for a modification of the December Order, not that PJM has failed to comply with \nit.646  However, we address related arguments on rehearing of the December Order above \nin Parts IV.B.3 and IV.C.1.b.ii. \n641  Compliance Transmittal at 19-20. \n642  Crusoe Comments on Compliance Filing at 8. To accompany its initial brief on \npaper hearing, PJM submitted an illustrative tariff with proposed rates, terms, and \nconditions for the three new transmission services. \n643  See December Order, 193 FERC ¶ 61,217 at PP 208, 216. \n644  See infra Part VI.A.3. \n645  See infra Part V.D.5.a. \n646  See, e.g., ISO New Eng. Inc., 132 FERC ¶ 61,098 at P 12 (\"The Commission \nhas held that requests to alter a compliance filing in a manner that differs from the order \n291 of 515"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":10,"endAt":63,"startToken":0,"endToken":1364},{"p":10,"at":63,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":64,"startToken":1364,"endToken":1516},{"p":11,"at":64,"title":"ATTACHMENT A","method":"printed heading","endPage":15,"endAt":1917,"startToken":1516,"endToken":2793},{"p":15,"at":1917,"title":"I. Background","method":"printed heading","endPage":15,"endAt":1933,"startToken":2793,"endToken":2795},{"p":15,"at":1933,"title":"A. Show Cause Order","method":"printed heading","endPage":18,"endAt":524,"startToken":2795,"endToken":3848},{"p":18,"at":524,"title":"B. Behind the Meter Generation","method":"printed heading","endPage":19,"endAt":935,"startToken":3848,"endToken":4355},{"p":19,"at":935,"title":"C. Eligible Customer","method":"printed heading","endPage":21,"endAt":131,"startToken":4355,"endToken":4865},{"p":21,"at":131,"title":"H. PJM's Answer to Show Cause Order and Responsive Pleadings29","method":"printed heading","endPage":21,"endAt":196,"startToken":4865,"endToken":4875},{"p":21,"at":196,"title":"A. PJM's Options for Co-Location Arrangements","method":"printed heading","endPage":24,"endAt":1944,"startToken":4875,"endToken":6432},{"p":24,"at":1944,"title":"B. General","method":"printed heading","endPage":26,"endAt":449,"startToken":6432,"endToken":6990},{"p":26,"at":449,"title":"C. Jurisdiction","method":"printed heading","endPage":34,"endAt":1849,"startToken":6990,"endToken":10429},{"p":34,"at":1849,"title":"D. Cost Allocation","method":"printed heading","endPage":54,"endAt":1250,"startToken":10429,"endToken":18723},{"p":54,"at":1250,"title":"E. Interconnection Procedures and Cost Allocation","method":"printed heading","endPage":63,"endAt":1371,"startToken":18723,"endToken":22257},{"p":63,"at":1371,"title":"Attachment M-3 was designed for supplemental transmission projects, not load","method":"printed heading","endPage":67,"endAt":2000,"startToken":22257,"endToken":23955},{"p":67,"at":2000,"title":"F. PJM Capacity Market, Reliability, and Resource Adequacy","method":"printed heading","endPage":75,"endAt":1085,"startToken":23955,"endToken":27189},{"p":75,"at":1085,"title":"G. Other Arguments","method":"printed heading","endPage":78,"endAt":1083,"startToken":27189,"endToken":28467},{"p":78,"at":1083,"title":"III. Notice of Show Cause Proceeding and Responsive Pleadings","method":"printed heading","endPage":80,"endAt":631,"startToken":28467,"endToken":29203},{"p":80,"at":631,"title":"IV. Discussion","method":"printed heading","endPage":80,"endAt":648,"startToken":29203,"endToken":29205},{"p":80,"at":648,"title":"A. Procedural Matters","method":"printed heading","endPage":80,"endAt":1521,"startToken":29205,"endToken":29351},{"p":80,"at":1521,"title":"B. Substantive Matters","method":"printed heading","endPage":145,"endAt":1373,"startToken":29351,"endToken":56732},{"p":145,"at":1373,"title":"I. PJM Grid","method":"printed heading","endPage":151,"endAt":1450,"startToken":56732,"endToken":58828},{"p":151,"at":1450,"title":"Conclusion","method":"printed heading","endPage":154,"endAt":65,"startToken":58828,"endToken":59012},{"p":154,"at":65,"title":"ATTACHMENT B","method":"printed heading","endPage":155,"endAt":65,"startToken":59012,"endToken":59056},{"p":155,"at":65,"title":"ATTACHMENT C","method":"printed heading","endPage":164,"endAt":129,"startToken":59056,"endToken":61310},{"p":164,"at":129,"title":"I. Background","method":"printed heading","endPage":164,"endAt":151,"startToken":61310,"endToken":61313},{"p":164,"at":151,"title":"A. February Order","method":"printed heading","endPage":164,"endAt":176,"startToken":61313,"endToken":61317},{"p":164,"at":176,"title":"B. December Order","method":"printed heading","endPage":164,"endAt":202,"startToken":61317,"endToken":61321},{"p":164,"at":202,"title":"II. Notice of Filings and Responsive Pleadings","method":"printed heading","endPage":164,"endAt":258,"startToken":61321,"endToken":61329},{"p":164,"at":258,"title":"A. PJM's Compliance Filing","method":"printed heading","endPage":164,"endAt":293,"startToken":61329,"endToken":61334},{"p":164,"at":293,"title":"B. Paper Hearing on New Transmission Services","method":"printed heading","endPage":164,"endAt":347,"startToken":61334,"endToken":61342},{"p":164,"at":347,"title":"III. Procedural Matters","method":"printed heading","endPage":164,"endAt":380,"startToken":61342,"endToken":61346},{"p":164,"at":380,"title":"IV. Requests for Rehearing and/or Clarification","method":"printed heading","endPage":164,"endAt":437,"startToken":61346,"endToken":61354},{"p":164,"at":437,"title":"A. Jurisdiction","method":"printed heading","endPage":164,"endAt":633,"startToken":61354,"endToken":61381},{"p":164,"at":633,"title":"B. Show Cause Findings","method":"printed heading","endPage":164,"endAt":821,"startToken":61381,"endToken":61408},{"p":164,"at":821,"title":"C. Replacement Rate","method":"printed heading","endPage":164,"endAt":1007,"startToken":61408,"endToken":61432},{"p":164,"at":1007,"title":"D. Informational Report","method":"printed heading","endPage":164,"endAt":1128,"startToken":61432,"endToken":61448},{"p":164,"at":1128,"title":"V. Compliance","method":"printed heading","endPage":164,"endAt":1151,"startToken":61448,"endToken":61451},{"p":164,"at":1151,"title":"A. BTMG Rules","method":"printed heading","endPage":165,"endAt":170,"startToken":61451,"endToken":61498},{"p":165,"at":170,"title":"B. Transmission Service","method":"printed heading","endPage":165,"endAt":333,"startToken":61498,"endToken":61520},{"p":165,"at":333,"title":"C. Necessary Studies","method":"printed heading","endPage":165,"endAt":473,"startToken":61520,"endToken":61539},{"p":165,"at":473,"title":"D. Other","method":"printed heading","endPage":165,"endAt":621,"startToken":61539,"endToken":61560},{"p":165,"at":621,"title":"E. Effective Date","method":"printed heading","endPage":165,"endAt":746,"startToken":61560,"endToken":61577},{"p":165,"at":746,"title":"VI. Paper Hearing","method":"printed heading","endPage":165,"endAt":774,"startToken":61577,"endToken":61581},{"p":165,"at":774,"title":"A. Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand","method":"printed heading","endPage":165,"endAt":1034,"startToken":61581,"endToken":61620},{"p":165,"at":1034,"title":"B. Additional Charge for Eligible Customers Taking FCD and/or NFCD","method":"printed heading","endPage":166,"endAt":250,"startToken":61620,"endToken":61676},{"p":166,"at":250,"title":"C. Interconnection Requirements and Operational Practices for Necessary Control","method":"printed heading","endPage":166,"endAt":506,"startToken":61676,"endToken":61709},{"p":166,"at":506,"title":"D. Penalty Charge or Other Remedial Action for New Transmission Services - 218 -","method":"printed heading","endPage":166,"endAt":881,"startToken":61709,"endToken":61760},{"p":166,"at":881,"title":"F. Communications, Alarm, SCADA, or Other Requirements","method":"printed heading","endPage":166,"endAt":1027,"startToken":61760,"endToken":61779},{"p":166,"at":1027,"title":"G. Curtailment Procedures for Interim NITS and Non-Firm Contract Demand","method":"printed heading","endPage":167,"endAt":152,"startToken":61779,"endToken":61833},{"p":167,"at":152,"title":"H. Rates, Terms, and Conditions for Interim NITS","method":"printed heading","endPage":167,"endAt":337,"startToken":61833,"endToken":61860},{"p":167,"at":337,"title":"I. Annual Report on New Transmission Services","method":"printed heading","endPage":167,"endAt":840,"startToken":61860,"endToken":61927},{"p":167,"at":840,"title":"I. Background","method":"printed heading","endPage":167,"endAt":856,"startToken":61927,"endToken":61929},{"p":167,"at":856,"title":"A. February Order","method":"printed heading","endPage":169,"endAt":1813,"startToken":61929,"endToken":62742},{"p":169,"at":1813,"title":"B. December Order","method":"printed heading","endPage":172,"endAt":292,"startToken":62742,"endToken":63701},{"p":172,"at":292,"title":"II. Notice of Filings and Responsive Pleadings","method":"printed heading","endPage":172,"endAt":342,"startToken":63701,"endToken":63708},{"p":172,"at":342,"title":"A. PJM's Compliance Filing","method":"printed heading","endPage":173,"endAt":1683,"startToken":63708,"endToken":64301},{"p":173,"at":1683,"title":"B. Paper Hearing on New Transmission Services","method":"printed heading","endPage":174,"endAt":725,"startToken":64301,"endToken":64653},{"p":174,"at":725,"title":"III. Procedural Matters","method":"printed heading","endPage":176,"endAt":355,"startToken":64653,"endToken":65475},{"p":176,"at":355,"title":"IV. Requests for Rehearing and/or Clarification","method":"printed heading","endPage":177,"endAt":936,"startToken":65475,"endToken":66009},{"p":177,"at":936,"title":"A. Jurisdiction","method":"printed heading","endPage":184,"endAt":127,"startToken":66009,"endToken":68459},{"p":184,"at":127,"title":"B. Show Cause Findings","method":"printed heading","endPage":210,"endAt":694,"startToken":68459,"endToken":79735},{"p":210,"at":694,"title":"C. Replacement Rate","method":"printed heading","endPage":255,"endAt":1326,"startToken":79735,"endToken":98049},{"p":255,"at":1326,"title":"D. Informational Report","method":"printed heading","endPage":257,"endAt":1265,"startToken":98049,"endToken":98779},{"p":257,"at":1265,"title":"V. Compliance","method":"printed heading","endPage":257,"endAt":1282,"startToken":98779,"endToken":98781},{"p":257,"at":1282,"title":"A. BTMG Rules","method":"printed heading","endPage":286,"endAt":688,"startToken":98781,"endToken":110965},{"p":286,"at":688,"title":"B. Transmission Service","method":"printed heading","endPage":292,"endAt":2727,"startToken":110965,"endToken":113740}]}