{"document":{"slug":"rec-20261029-5295","title":"East Kentucky Power Cooperative, Inc. submits Request for Rehearing of the 09/29/2026 Order","issued":"2026-10-29","accession":"20261029-5295","docket":"ER26-3380-001","group":"Rehearing of FERC's PJM Reliability Backstop Procurement order","filer":"East Kentucky Power Cooperative, Inc.","kind":"rehearing request","file":"sources/filings/text/20261029-5295_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261029-5295","tier":"record","sha256":"e72b50ee12dbf29205eb6a9f43be69ab9c907adf9e73fdb296e7dbc65437b902","pages":31,"tokens":10000,"emptyPages":[],"textThemes":["credit","cost","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":246,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-3380-000 \n \n \n) \nEL26-108-00 \n \n \n) \n \nREQUEST FOR REHEARING OF \nEAST KENTUCKY POWER COOPERATIVE, INC. \n \nPursuant to section 313 of the Federal Power Act (“FPA”)1 and Rule 713 of the \nCommission’s Rules of Practice and Procedure,2 East Kentucky Power Cooperative, Inc. \n(“EKPC”) respectfully requests rehearing of the Commission’s order accepting, subject to refund \nand additional proceedings, PJM Interconnection, L.L.C.’s (“PJM”) revisions to its Open Access \nTransmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities \n(“RAA”) establishing the Reliability Backstop Procurement (“RBP”) .3 \nThe Commission erred in accepting aspects of the RBP Proposal without adequately \naddressing EKPC’s cost-causation objections. The Commission did not explain why the existing \nself-supply portfolio of a load-serving entity (“LSE”) may be disregarded in determining the LSE’s \nRBP exposure, or why qualifying offsets need not reduce the obligations of the LSE or the load \nthat supplied them. Nor did it explain whether it accepted PJM’s default allocation to all LSEs in \na zone/area when no state- or Relevant Electric Retail Regulatory Authority (“RERRA”)-\ndetermined allocation is reported or reserved that distinct issue for further proceedings. The \nCommission rejected EKPC’s Fixed Resource Requirement (“FRR”) comparability argument \nwithout adequately addressing the relevance of comparable resource-planning actions by \n \n1 16 U.S.C. § 825l (2018). \n2 18 C.F.R. § 385.713 (2026). \n3 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026) (“Order”)."},{"page":2,"startToken":246,"endToken":514,"text":"2 \nReliability Pricing Model (“RPM”) self-supply LSEs. And, despite setting certain collateral \nelements for paper hearing, the Commission did not adequately address EKPC’s foundational \nobjections to the exposure, quantity, release, and default-allocation methodology underlying the \nLSE collateral requirement. \nAlthough the Commission established paper hearing procedures on cost allocation, \nTransmission Owner exit rules, and LSE collateral requirements, it stated that aside from the issues \nreserved for hearing, “the other aspects of PJM’s RBP proposal are just and reasonable.”4 The \nOrder does not clearly establish whether the independent cost-causation and collateral-\nmethodology objections identified below remain open. To the extent that the Commission rejected \nthose objections or accepted the challenged provisions, EKPC requests rehearing. Alternatively, \nEKPC requests clarification that the paper hearing encompasses those objections and that no \nadverse determination has been made on them. A subsequent section 205 proposal does not resolve \nwhether the Order adequately addressed the framework before the Commission. \nI. \nBackground \nA. \nRBP Proposal \nPJM filed the RBP Proposal on July 31, 2026 as a one-time procurement of new capacity \nfor terms of up to 15 years, beginning no earlier than the 2028/2029 Delivery Year and ending no \nlater than the 2042/2043 Delivery Year.5 At the zone/area level, PJM proposed to allocate the \nInitial RBP Target to Electric Distributor zone/areas based on each zone/area’s pro rata share of \nthe difference in forecasted Load Adjustments between the 2026/2027 and 2028/2029 Delivery \nYears, reduced by qualifying offset capacity and opted-out load, and to fix that allocation for the \n \n4 Order at PP 23-24. \n5 Order at PP 1, 15."},{"page":3,"startToken":514,"endToken":916,"text":"3 \n15-year term.6 At the LSE level, within each zone/area, PJM proposed to allocate costs to LSEs \nbased on a state- or RERRA-determined RBP Obligation (“RBO”) reported by the Electric \nDistributor. If no RBOs are reported, PJM would allocate the zone/area’s RBP Charges to all load \nin the zone/area using each LSE’s ratio share of the Daily Unforced Capacity Obligation under \nRAA, Schedule 8.7 Separately, PJM proposed an LSE collateral requirement equal to an RBP \nCredit Rate of $1.5 million multiplied by committed RBP MW, payable in cash or letter of credit \n45 days before the first Delivery Year, with defaulted RBP Charges reallocated to remaining \nLSEs.8 \nB. \nProtest \nEKPC timely intervened and filed a Protest, supported by the Affidavits of Adam \nBednarczyk and Carl F. Coscia, Ph.D. on August 21, 2026.9 EKPC also filed a Limited Answer \non September 4, 2026,10 and a Second Limited Answer, supported by a Reply Affidavit of Dr. \nCoscia, on September 18, 2026.11 The Commission accepted EKPC’s Answers.12 \nIn proposing the RBP, PJM claimed that the RBP is “a critical safety net designed to \naddress current resource adequacy shortfalls.”13 EKPC shares PJM’s concern about resource \n \n6 Order at P 99 (citing Proposed Tariff, attach. DD, § 18.3(a)). \n7 Order at P 110 (citing Proposed Tariff, attach. DD, § 18.3(b)). \n8 Order at PP 183-84 (citing Proposed Tariff, attach. DD, §§ 18.8, 18.9). \n9 PJM Interconnection, L.L.C., “Protest of East Kentucky Power Cooperative, Inc.,” Docket No. ER26-3380-000 (filed \nAug. 21, 2026) (“Protest”); Affidavit of Adam Bednarczyk, Attachment 1 to Protest (“Bednarczyk Affidavit”); \nAffidavit of Carl F. Coscia, Attachment 2 to Protest (“Coscia Protest Affidavit”). \n10 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and Limited \nAnswer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 4, 2026) (“EKPC September 4 Answer”). \n11 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and Limited \nAnswer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 18, 2026) (“EKPC September 18 Answer”); Reply \nAffidavit of Carl F. Coscia, Attachment 1 to EKPC September 18 Answer (“Coscia Reply Affidavit”). \n12 Order at P 22. \n13 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource \nAdequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”)."},{"page":4,"startToken":916,"endToken":1225,"text":"4 \nadequacy and the reliability challenges facing the PJM region. Fundamentally, however, as EKPC \nexplained in its Protest,14 the RBP is inconsistent with the Commission’s cost-causation principles. \nEKPC has argued and demonstrated, with record evidence, that the RBP fails to “protect LSEs \nwhose existing resource portfolios already support their expected load obligations from incurring \nadditional costs.”15 That risk extends to entities like EKPC “whose supply portfolio contains \nsufficient resources to serve the load underlying PJM’s forecast.”16 \nAs EKPC explained in its Protest, to be just and reasonable and not unduly discriminatory \nor preferential, rates must reflect the cost-causation principle that “all approved rates reflect to \nsome degree the costs actually caused by the customer who must pay them.”17 In its Protest, EKPC \nexplained that rate design decisions must be supported by “substantial evidence.”18 PJM failed to \nprovide any evidence “that allocating costs based on total zonal load obligations bears any \nreasonable relationship to the load growth that caused the shortfall. LSEs with no or minimal large \nload growth may nonetheless be allocated disproportionate costs due to improper accounting of \nthe offsets and opt-outs or the use of the default allocation methodology.”19 The potential for \nsocializing costs across all LSEs, regardless of causation, fails the legal and economic tests of “just \nand reasonable” ratemaking. \n \n14 Protest at 11-12, 18-19, 21, 28-31, 37-39. \n15 Protest at 11. \n16 Protest at 11. \n17 Protest at 30 (quoting KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992)). \n18 Protest at 21 (citing Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1233 (D.C. Cir. 2005) (“Upon applying \nthe usual APA standard, we conclude that the Commission’s approval of the rate design is supported by substantial \nevidence in the record and is not otherwise arbitrary and capricious.”)). \n19 Protest at 21."},{"page":5,"startToken":1225,"endToken":1498,"text":"5 \nThe evidence provided by EKPC in the Bednarczyk Affidavit shows that a generalized \nshowing of regional reliability need does not support PJM’s particular rate design.20 As explained \nby Mr. Bednarczyk, the RBP does not “track mitigation measures” or keep costs aligned with the \nparties who create or mitigate the need.21 Existing resources cannot earn RBP revenue, and treating \nthem differently becomes a problem when the Tariff also refuses to count them in deciding who \ncaused the need.22 For self-supply LSEs like EKPC, the question is whether their own resource-\nadequacy actions reduce their RBP exposure.23 As Mr. Bednarczyk explained, self-supply LSEs \nface particular risk if their resource positions are not recognized,24 and crediting offsets only at the \nzonal level weakens incentives for forward procurement.25 And regarding PJM’s proposed default \ncost allocation, by defaulting to Daily Unforced Capacity Obligation, PJM is defaulting to a “broad \ncapacity-allocation metric” that “does not identify the LSEs that created the residual procurement \nneed.”26 Under the proposed default allocation methodology, an LSE whose load growth is \nordinary and whose resources are sufficient bears costs caused by another LSE.27 As explained by \nDr. Coscia, unlike Peak Load Contribution (“PLC”)-based charges, which follow measured load, \nthe RBP Obligation assigns a fixed 15-year quantity based on a forecast that does not fall if the \n \n20 Bednarczyk Affidavit at P 7. \n21 Bednarczyk Affidavit at P 7. \n22 Bednarczyk Affidavit at PP 25-26. \n23 Bednarczyk Affidavit at P 35. \n24 Bednarczyk Affidavit at P 36. \n25 Bednarczyk Affidavit at P 38. \n26 Bednarczyk Affidavit at P 17. \n27 Bednarczyk Affidavit at P 18."},{"page":6,"startToken":1498,"endToken":1812,"text":"6 \nload never appears.28 The Load Adjustment inputs were submitted for planning purposes and were \nnever verified for cost allocation.29 \nDr. Coscia’s Affidavits also addressed the exposure basis and quantity underlying the credit \nand collateral requirements, the interaction with existing PJM credit rules, and the treatment of \ndefaults.30 Proposed Tariff Attachment DD section 18.9(a) requires reallocation of defaulted RBP \nCharges among remaining LSEs responsible for those charges, while application of the defaulting \nLSE’s collateral is permissive.31 Dr. Coscia’s Affidavits separately identify potential residual \nexposure under Operating Agreement section 15.2.2 for Members without an initial RBP \nallocation.32 That concern does not depend on EKPC receiving a zero allocation: it concerns the \nrelationship between the exposure secured, the entities posting collateral, and the entities \npotentially bearing a residual loss.33 \nAs explained by EKPC in its Protest and Answers, EKPC recognizes the urgency of PJM’s \nreliability concerns.34 But the RBP as accepted fails to achieve its objectives in a manner consistent \nwith the requirements of the FPA. The RBP assigns long-term costs and collateral obligations \nthrough a framework that lacks the specificity necessary to be just and reasonable because the RBP \ndoes not sufficiently identify the LSE responsible for causing the capacity shortage, does not \nensure that any offsets or opt-outs follow the entity that secured them, and does not protect LSEs \nwhose existing resource portfolios already support their expected load obligations from incurring \n \n28 Coscia Protest Affidavit at PP 159-61. \n29 Coscia Protest Affidavit at PP 159-61. \n30 See Coscia Reply Affidavit at PP 18-24, 71-73. \n31 See Proposed Tariff, attach. DD, § 18.9(a); Coscia Reply Affidavit at PP 18-24. \n32 See Coscia Protest Affidavit at PP 168-70; Coscia Reply Affidavit at PP 18-24. \n33 See Coscia Reply Affidavit at PP 21-24. \n34 Protest at 10-11. See also EKPC September 18 Answer at 3-4."},{"page":7,"startToken":1812,"endToken":2086,"text":"7 \nadditional costs. The RBP may attempt to address a legitimate reliability need. But simply \nattempting to address a legitimate need is not enough to make the RBP Proposal just and \nreasonable, especially where the resulting costs are not reasonably tied to cost causation. \nC. \nThe Commission’s Order Accepting the RBP Proposal Subject to \nAdditional Proceedings \nIn the Order, the Commission accepted the RBP for filing, suspended it for five months to \nbecome effective February 28, 2027, subject to refund, and established paper hearing procedures \nand an FPA section 206 proceeding in Docket No. EL26-108-000.35 The Commission identified \nthree hearing topics: cost allocation, Transmission Owner exit rules, and LSE collateral \nrequirements.36 It stated that “the other aspects of PJM’s RBP proposal are just and reasonable.”37 \nOn cost allocation, the Commission questioned reliance on Load Adjustments, directed briefing \non updated load forecast information, and “decline[d] to further address arguments raised in the \nprotests related to PJM’s proposed cost allocation method at this time.”38 It separately upheld the \nFRR exclusion and rejected the comparability argument concerning RPM self-supply LSEs.39 On \ncollateral, it upheld seller collateral, questioned LSE collateral, and expressly requested responses \non “(1) what initial RBP Credit Rate is appropriate and (2) whether 45 days before the start of the \ndelivery year is sufficient time for LSEs to post collateral.”40 Those questions do not clearly \nestablish the treatment of the independent allocation and collateral-methodology objections raised \nhere. \n \n35 Order at PP 1, 23-27. \n36 Order at P 24. \n37 Order at P 23. \n38 Order at PP 154-60. \n39 Order at P 151. \n40 Order at PP 203-06."},{"page":8,"startToken":2086,"endToken":2477,"text":"8 \nThe Commission set forth the correct standard by which it must evaluate PJM’s method \nfor allocating RBP costs, explaining that “[u]nder the cost causation principle, all Commission-\njurisdictional rates and charges must ‘reflect to some degree the costs actually caused by the \ncustomer who must pay for them,’”41 and that “costs must be allocated in a manner that is at least \nroughly commensurate with benefits.”42 The Commission explained that it “may approve a given \ncost allocation framework if it ‘has an articulable and plausible reason to believe that the benefits \nare at least roughly commensurate with’ the assigned costs.”43 Although the Commission \narticulated that standard and reserved aspects of cost allocation for further proceedings, it did not \nclearly explain the treatment of EKPC’s distinct LSE-level objections concerning portfolio \nrecognition, offset attribution, and the default allocation. Instead, the Commission addressed the \napplicability of the RBP to FRR Entities, stated that aspects of PJM’s RBP Proposal may not be \njust and reasonable, and set a limited number of issues for additional proceedings.44 The \nCommission failed to address several of the central cost-causation concerns raised by EKPC. \nII. \nStatement of Issues and Specification of Errors \nPursuant to Rules 713(c)(1) and (2), and 203(a)(7),45 EKPC provides the following \nstatement of issues and specification of errors: \n1. \nThe Commission erred by failing to address EKPC’s argument that a self-supply \nLSE’s existing portfolio of resources must be considered. This failure is arbitrary, \ncapricious, not the product of reasoned decision making, and contrary to law. 5 \nU.S.C. § 706(2). See, e.g., Env’t Def. Fund v. FERC, 2 F.4th 953, 967-68 (D.C. Cir. \n2021) (“Thus, the overarching question in this case is whether ‘the Commission’s \ndecisionmaking [wa]s reasoned, principled, and based upon the record.’”) (citation \n \n41 Order at P 150 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); see also Ky. Pub. Serv. \nComm’n v. Am. Elec. Power Serv. Corp., 193 FERC ¶ 61,110 (2025) (Ky. Comm’n)). \n42 Order at P 150. \n43 Order at P 150 (quoting Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)). \n44 Order at PP 2, 150-51. \n45 18 C.F.R. §§ 385.713(c)(1), 385.713(c)(2), 385.203(a)(7) (2026)."},{"page":9,"startToken":2477,"endToken":3030,"text":"9 \nomitted); NBCUniversal Media, LLC v. NLRB, 815 F.3d 821, 823 (D.C. Cir. 2016) \n(“NBCUniversal”) (“When an agency’s decision lacks adequate justification \nbecause it is neither logical nor rational, or because it fails to offer a coherent \nexplanation of agency precedent, the judgment under review is wanting for lack of \nreasoned decisionmaking.”). \n2. \nThe Commission erred by failing to address EKPC’s distinct argument that PJM’s \ntreatment of Qualifying RBP Offset UCAP MW reduces the aggregate procurement \ntarget without requiring the offset to reduce the RBO MW, RBP Charges, or \ncollateral obligation of the LSE or load that supplied or sponsored it. To the extent \nthe Commission accepted that treatment, its failure to explain the resulting \nallocation is arbitrary and capricious and contrary to cost-causation principles. \nAlternatively, the Commission failed to clarify that LSE-specific offset attribution \nremains within the paper hearing. 5 U.S.C. § 706(2). See, e.g., Env’t Def. Fund v. \nFERC, 2 F.4th 953, 967-68 (D.C. Cir. 2021); New England Power Generators \nAss’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“It is well established that \nthe Commission must respond meaningfully to the arguments raised before it.”) \n(quoting TransCanada Power Mktg., Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. \n2015)). \n3. \nThe Commission erred by accepting the challenged cost-allocation features without \nadequately applying its cost-causation principles or, alternatively, by failing to \nclarify that those issues remain open for paper hearing. In particular, to the extent \nthe Order accepted the default allocation among LSEs, it did so without explaining \nits consistency with cost causation. The Commission’s failure to provide a reasoned \nexplanation is arbitrary, capricious, not the product of reasoned decision making, \nand contrary to law. 5 U.S.C. § 706(2). See, e.g., N.Y. & Atl. Ry. Co. v. Surface \nTransp. Bd., 635 F.3d 66, 71 (2d Cir. 2011) (“Surface Transp.”) (“An agency also \nacts in an arbitrary and capricious manner if the ‘agency departs from its own \nprecedent without a reasoned explanation.’”) (citation omitted); Greater Boston \nTelevision Corp. v. FCC, 444 F.2d 841, 851-53 (D.C. Cir. 1970) (“Greater \nBoston”) (“An agency’s view of what is in the public interest may change. . . . But \nan agency changing its course must supply a reasoned analysis indicating that prior \npolicies and standards are being deliberately changed, not casually ignored.”) \n(citations omitted); FPL Energy Marcus Hook, L.P. v. FERC, 430 F.3d 441, 448 \n(D.C. Cir. 2005) (“FPL Energy”) (“[W]e can only uphold the Commission’s \ninterpretation if we can ‘discern a reasoned path’ to the decision.”); NBCUniversal, \n815 F.3d at 823 (D.C. Cir. 2016) (“When an agency’s decision lacks adequate \njustification because it is neither logical nor rational, or because it fails to offer a \ncoherent explanation of agency precedent, the judgment under review is wanting \nfor lack of reasoned decisionmaking.”); Motor Vehicle Mfrs. Ass’n of the United \nStates v. State Farm Mut. Ins. Co., 463 U.S. 29, 43 (1983) (“Motor Vehicles”) \n(“[A]n agency rule would be arbitrary and capricious if the agency . . . offered an \nexplanation for its decision that runs counter to the evidence before the agency[.]”). \n4. \nThe Commission failed to engage in reasoned decision making to the extent it \naccepted, or excluded from further examination, the challenged LSE collateral"},{"page":10,"startToken":3030,"endToken":3625,"text":"10 \nmethodology without addressing EKPC’s objections concerning the exposure \nsecured, applicable MW quantity, interaction with Attachment Q and Peak Market \nActivity, reduction and release standards, application of collateral before default \nreallocation, and potential residual exposure under Operating Agreement section \n15.2.2. Alternatively, the Commission failed to clarify that those issues remain open \nfor paper hearing. 5 U.S.C. § 706(2). See, e.g., Surface Transp., 635 F.3d at 71 (“An \nagency also acts in an arbitrary and capricious manner if the ‘agency departs from \nits own precedent without a reasoned explanation.’”) (citation omitted); Greater \nBoston, 444 F.2d 841 at 851-53 (“An agency’s view of what is in the public interest \nmay change. . . . But an agency changing its course must supply a reasoned analysis \nindicating that prior policies and standards are being deliberately changed, not \ncasually ignored.”) (citations omitted); FPL Energy, 430 F.3d at 448 (“[W]e can \nonly uphold the Commission’s interpretation if we can ‘discern a reasoned path’ to \nthe decision.”); NBCUniversal, 815 F.3d at 823 (“When an agency’s decision lacks \nadequate justification because it is neither logical nor rational, or because it fails to \noffer a coherent explanation of agency precedent, the judgment under review is \nwanting for lack of reasoned decisionmaking.”); Motor Vehicles, 463 U.S. at 43 \n(“[A]n agency rule would be arbitrary and capricious if the agency . . . offered an \nexplanation for its decision that runs counter to the evidence before the agency[.]”). \n5. \nThe Commission erred in its determination that there is no undue discrimination \nbetween FRR Entities and RPM LSEs. This determination is arbitrary, capricious, \nand not the product of reasoned decision making. 5 U.S.C. § 706(2). See, e.g., Env’t \nDef. Fund v. FERC, 2 F.4th 953, 967-68 (D.C. Cir. 2021) (“Thus, the overarching \nquestion in this case is whether ‘the Commission’s decisionmaking [wa]s reasoned, \nprincipled, and based upon the record.’”) (citation omitted); Pacific Gas & Elec. \nCo. v. FERC, 306 F.3d 1112, 1115, 1121 (D.C. Cir. 2002) (noting that Commission \n“must be able to demonstrate that it has made a reasoned decision based upon \nsubstantial evidence in the record” and remanding case because reviewed orders \n“provided no explanation as to how or why” the Commission’s conclusion \nproduced necessary outcome); NBCUniversal, 815 F.3d at 823 (“When an agency’s \ndecision lacks adequate justification because it is neither logical nor rational, or \nbecause it fails to offer a coherent explanation of agency precedent, the judgment \nunder review is wanting for lack of reasoned decisionmaking.”). \n6. \nThe Commission erred by failing to meaningfully consider the evidence provided \nin the Bednarczyk and Coscia affidavits. 5 U.S.C. § 706(2). See, e.g., \nSithe/Independence Power Partners, L.P. v. FERC, 165 F.3d 944, 948 (D.C. Cir. \n1999) (“The Commission must be able to demonstrate that it has made a reasoned \ndecision based upon substantial evidence in the record, and the path of its reasoning \nmust be clear.” (quoting Town of Norwood v. FERC, 962 F.2d 20, 22 (D.C. Cir. \n1992) (internal citations and quotations omitted))); Williston Basin Interstate \nPipeline Co. v. FERC, 358 F.3d 45, 48 (D.C. Cir. 2004) (The Commission must \nmake a “reasoned decision based upon substantial evidence in the record.”); Motor \nVehicles, 463 U.S. at 43 (agency decision is arbitrary and capricious if “offer[s] an \nexplanation for its decision that runs counter to the evidence before [it]”); S.C. Pub. \nServ. Auth. v. FERC, 762 F.3d 41, 54 (D.C. Cir. 2014) (The Commission’s findings"},{"page":11,"startToken":3625,"endToken":4057,"text":"11 \nmust be supported by substantial evidence, which means “such relevant evidence \nas a reasonable mind might accept as adequate to support a conclusion.”); BNP \nParibas Energy Trading GP v. FERC, 743 F.3d 264, 270 (D.C. Cir. 2014) (“[W]e \ncannot affirm on the basis of a Commission rationale that fails to respond to critical \narguments raised before the agency.”); New England Power Generators Ass’n, Inc. \nv. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“It is well established that the \nCommission must respond meaningfully to the arguments raised before it.”) \n(quoting TransCanada Power Mktg., Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. \n2015)). \nIII. Request for Rehearing \nUnder the Administrative Procedure Act and federal appellate court precedent, the \nCommission’s decisions will be set aside on appeal if they are “arbitrary, capricious, an abuse of \ndiscretion, or otherwise not in accordance with law,” or “unsupported by substantial evidence.”46 \nFor the Commission to have engaged in reasoned decision-making, it must have examined the \nrelevant data and provided a rational connection between the facts found and the choices made.47 \nIf the Commission “does not provide a rational explanation for its action based on relevant data, \nthen that action is arbitrary and capricious.”48 Here, EKPC, a party aggrieved by the Commission’s \nOrder,49 seeks rehearing of the Order because it is arbitrary and capricious, an abuse of discretion, \nnot based upon substantial evidence in the record, and otherwise contrary to law. \nThe FPA’s just-and-reasonable standard incorporates the cost-causation principle, under \nwhich all approved rates must “reflect to some degree the costs actually caused by the customer \nwho must pay them,” and costs must be allocated in a manner at least roughly commensurate with \n \n46 5 U.S.C. §§ 706(2)(A), 706(2)(E). See also Vistra Corp. v. FERC, 80 F.4th 302, 312 (D.C. Cir. 2023); S.C. Pub. \nServ. Auth. v. FERC, 762 F.3d 41, 55 (D.C. Cir. 2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 528 (D.C. \nCir. 2010). \n47 Motor Vehicle Mfrs. Ass’n v. Motor Vehicles Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983). \n48 La. PSC. v. FERC, 20 F.4th 1, 6-7 (D.C. Cir. 2021) (citing 5 U.S.C. § 706(2)(A) and Motor Vehicle Mfrs. Ass’n, \n463 U.S. at 43)). \n49 See 16 U.S.C. § 825l(a) (party aggrieved by order of Commission may seek rehearing). See also Order at PP 20-22 \n(noting Joint Protestors’ respective interventions and consequent party status in this proceeding)."},{"page":12,"startToken":4057,"endToken":4405,"text":"12 \nbenefits.50 The Commission must have an “articulable and plausible reason to believe that the \nbenefits are at least roughly commensurate with” the assigned costs.51 Undue discrimination occurs \nwhere similarly situated customers are treated differently without adequate justification.52 Finally, \na filed rate must possess the minimum specificity that the Commission can reasonably require, \nsuch that customers can determine who is responsible for a charge and in what amount.53 \nA. \nThe Commission Erred by Failing to Address EKPC’s Argument That \nIt Is Unjust and Unreasonable for the RBP to Ignore a Self-Supply \nLSE’s Existing Portfolio. \nIn its Protest and Answers, EKPC argued that the RBP should consider a self-supply LSE’s \nexisting portfolio in determining the LSE’s RBP obligations. The Commission failed to address \nthis argument. That failure was arbitrary and capricious, not the product of reasoned decision \nmaking, and contrary to law. \nAs EKPC explained in its Protest, the RBP fails to account for existing resources in an \nLSE’s supply portfolio. The relevant question in evaluating the RBP under the Commission’s cost-\ncausation principle is whether the entity assigned costs as a result of the RBP caused the resource \nadequacy shortfall that the RBP is intended to address and/or whether it benefits from the \nprocurement and associated allocated costs.54 An LSE whose self-supply portfolio fully covers its \nload, including any incremental large load, has not contributed to the resource adequacy gap on \nthat showing.55 Any broader regional benefit does not, without further explanation, justify the \n \n50 KN Energy, 968 F.2d at 1300; Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476-77 (7th Cir. 2009); Old Dominion \nElec. Coop. v. FERC, 898 F.3d 1254, 1260 (D.C. Cir. 2018). See also Order at P 150. \n51 Ill. Com. Comm’n, 576 F.3d at 477. \n52 TranSource, 168 FERC ¶ 61,119 at P 240. \n53 Pub. Utils. Comm’n of Cal. v. FERC, 254 F.3d 250, 255 (D.C. Cir. 2001); Protest at 18-19. \n54 See Protest at 11-12. \n55 Protest at 11-14; 45-47; Bednarczyk Affidavit at PP 25, 31, 61-63."},{"page":13,"startToken":4405,"endToken":4699,"text":"13 \nparticular RBP costs assigned to that LSE. The Commission did not explain why cost causation \ndoes not require PJM to credit a self-supply LSE’s resource position against that LSE’s own RBO, \nRBP Charges, and collateral requirements. \nThis issue is not clearly resolved by the paper hearing questions concerning updated \nzone/area load forecasts.56 Correcting the measurement of load growth does not itself determine \nhow an existing self-supply position affects an LSE’s responsibility in the first instance. To the \nextent that the Order accepted this feature, the Commission must address EKPC’s objections on \nrehearing. If it intended to reserve it, then the Commission should expressly confirm that the \nhearing encompasses existing portfolio recognition. \nThe Commission’s failure to respond to EKPC’s significant, record-supported objections, \nand its reliance on distinctions that do not address the cost-causation question presented, is \narbitrary and capricious and not the product of reasoned decision-making.57 Accepting a rate \ndesign that may require a self-supply LSE to pay for RBP capacity that provides it little or no \nadditional reliability benefit is inconsistent with the requirement that costs be at least roughly \ncommensurate with benefits.58 This outcome also weakens the incentives that the RBP is intended \nto promote and is in tension with the Ratepayer Protection Pledge’s objective of ensuring that new \nlarge loads, not prudently planning LSEs and their existing customers, bear the costs of new \ncapacity.59 \n \n56 See Order at PP 157, 159-60. \n57 Motor Vehicles, 463 U.S. at 43; PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C. Cir. 2005). \n58 Ill. Com. Comm’n, 576 F.3d at 477; Bednarczyk Affidavit at P 34. \n59 See EKPC September 18 Answer at 9-10; Bednarczyk Affidavit at PP 34, 38; Order at P 161."},{"page":14,"startToken":4699,"endToken":5002,"text":"14 \nSection 205 of the FPA requires that “all rules and regulations affecting or pertaining to” \nrates and charges subject to the jurisdiction of the Commission “shall be just and reasonable.”60 \nCourts have consistently required the Commission to use reasoned, principled decision-making in \ndetermining whether rates are just and reasonable. Courts have explained that the Commission \nmust “adequately explain how the evidence it relied on ‘support[ed] the conclusion it reached.’”61 \nAcknowledging but failing to address EKPC’s argument regarding recognizing an LSE’s existing \nsupply portfolio is insufficient to meet this standard. To the extent that the Order accepted the \nchallenged treatment of self-supply portfolios, the Commission should grant rehearing; \nalternatively, it should clarify that this issue remains open for paper hearing. \nB. \nThe Commission Erred by Failing to Address EKPC’s Argument That \nIt Is Unjust and Unreasonable That the Qualifying RBP Offset UCAP \nMW Reduces the Aggregate Procurement Target Without Requiring \nthe Offset to Reduce the RBO MW, RBP Charges, or Collateral \nObligation of the LSE or Load That Supplied or Sponsored It. \nPJM’s treatment of portfolio benefits exposes the central cost-causation defect: qualifying \ncapacity reduces the regional procurement target, but the proposed Tariff does not ensure that the \ncorresponding benefit follows the LSE that supplied it.62 The assertion that RPM-cleared resources \nsupport the pooled regional requirement or that additional capacity may confer regional reliability \nbenefits does not explain why PJM recognizes an LSE’s contribution when reducing the regional \ntarget yet disregards that contribution when determining the LSE’s own RBP Charges and \ncollateral obligation. \n \n60 16 U.S.C. § 824d(a). \n61 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (quoting Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. \nCir. 1985)). \n62 See Protest at 28-31; Bednarczyk Affidavit at PP 34-38."},{"page":15,"startToken":5002,"endToken":5350,"text":"15 \nWhere capacity satisfies PJM’s criteria for Qualifying RBP Offset UCAP MW, the \nproposed Tariff does not require the corresponding reduction to follow the LSE or load that \nsupplied or sponsored it.63 That is an attribution issue, not a request to expand offset eligibility to \nall existing capacity. The Order summarized EKPC’s argument that the proposal “unfairly \nsocializes the benefit of prudent resource planning by LSEs,” but did not resolve whether an offset \nmust reduce the sponsoring LSE’s RBO MW, RBP Charges, and associated collateral obligation.64 \nPJM’s response that pooled benefits are a feature of an RTO does not explain why a targeted \nprocurement may recognize an entity’s contribution when reducing the regional target without \nensuring corresponding recognition in that entity’s own allocation.65 \nMoreover, the assertion that the existence of pooled benefits merit spreading costs to those \nwho are not causing the need for a special resource procurement to an RTO is contrary to the \nCommission’s own standards for recognizing RTOs, and contrary to the cost causation principle \nthat is built into the FPA.  The Commission has not required socialization of costs as a result of \npooling of benefits as a feature of an RTO.  For example, an RTO’s market “must provide all \ntransmission customers with efficient price signals that show the consequence of their transmission \nusage decisions.”66 Far from requiring socialization of costs due to the pooling of benefits, the \nregulation mandates that a transmission customer must be able to experience the benefits and the \nharms resulting from its own choices.  That principle is necessary for cost causation as well.  An \narrangement in which a transmission operator such as an RTO is entitled, simply because it is the \ndominant operator in the region, to require region-wide allocation of costs based solely on the \n \n63 See Bednarczyk Affidavit at PP 27-31, 34, 38; Protest at 28-31. \n64 Order at PP 130, 157; Protest at 30-31; Bednarczyk Affidavit at PP 14, 27, 29-30. \n65 See Order at P 133; EKPC September 18 Answer at 16-17. \n66 18 C.F.R. § 35.34(k)(2)(i)."},{"page":16,"startToken":5350,"endToken":5680,"text":"16 \nalleged region-wide sharing of the benefits from a given LSE’s own investments is contrary to \nsection 205. Accordingly, the Commission must reject the RTO’s demand for socialization of costs \nbased on the presumptive pooling of benefits. \nSimilar to the Commission’s failure to address EKPC’s arguments with respect to \nconsideration of an existing self-supply portfolio, the issue of whether Qualifying RBP Offset \nUCAP should follow the LSE or load that sponsored or supplied it is not clearly resolved by the \nCommission’s paper hearing questions.67 Correcting the measurement of load growth does not \nitself determine whether qualifying offsets follow their sponsor. If the Commission intended in its \nOrder to accept this feature, the Commission must address EKPC’s objections on rehearing. \nAlternatively, the Commission should expressly confirm that the hearing encompasses qualifying \noffsets if it intended to reserve this issue. \nThe Commission’s failure to respond to EKPC’s objections is arbitrary and capricious and \nnot the product of reasoned decision-making.68 Accepting a rate design that fails to require an \noffset to reduce costs incurred by the LSE or load that sponsored or supplied it is inconsistent with \nthe requirement that costs be at least roughly commensurate with benefits.69 By failing to ensure \nthat the offset follows the LSE or load, the LSE or load could incur costs of new capacity that it \ndoes not need to meet its own obligations, without a Commission explanation of whether any \nbroader regional benefits are roughly commensurate with those costs. As noted above, such an \noutcome weakens the incentives that the RBP is intended to promote and is in tension with the \nRatepayer Protection Pledge’s objective.70 \n \n67 See Order at PP 157, 159-60. \n68 Motor Vehicles, 463 U.S. at 43; PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C. Cir. 2005). \n69 Ill. Com. Comm’n, 576 F.3d at 477. \n70 See EKPC September 18 Answer at 9-10; Bednarczyk Affidavit at PP 34, 38; Order at P 161."},{"page":17,"startToken":5680,"endToken":5980,"text":"17 \nThe Commission must use reasoned, principled decision-making in determining whether \nrates are just and reasonable and must “adequately explain how the evidence it relied on \n‘support[ed] the conclusion it reached.’”71 Failing to address EKPC’s argument regarding \nattribution of Qualifying RBP Offset UCAP MW is insufficient to meet this standard. To the extent \nthat the Order accepted PJM’s proposed treatment of Qualifying RBP Offset UCAP MW, the \nCommission should grant rehearing; alternatively, it should clarify that this issue remains open for \npaper hearing. \nC. \nThe Commission’s Order Is Arbitrary and Capricious Because It Fails \nto Address PJM’s Proposed Default Cost Allocation. \nThe Order does not clearly resolve the status of PJM’s default allocation of RBP Charges \nand associated collateral obligations to LSEs in an Electric Distributor zone/area based on Daily \nUnforced Capacity Obligation when no RBO is reported.72 The Commission summarized EKPC’s \nobjections to that default allocation and PJM’s purported defense, but made no express \ndetermination on that fallback method.73 At the same time, it accepted the tariff records for filing, \nsuspended them subject to refund and further proceedings, and stated that aspects outside the issues \nspecifically reserved for the paper hearing were just and reasonable.74 If the Commission accepted \nthe default allocation, it did so without explaining why that allocation satisfies cost causation. If it \nreserved the issue, it should clarify that the paper hearing includes the fallback allocation among \nLSEs, not merely the allocation among zone/areas. \n \n71 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (quoting Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. \nCir. 1985)). \n72 Order at P 110 (citing Proposed Tariff, attach. DD, § 18.3(b)). \n73 See Order at PP 119, 123, 157. \n74 Order at PP 23-27."},{"page":18,"startToken":5980,"endToken":6312,"text":"18 \nAs EKPC explained in its Protest, the default allocation “socializes RBP costs across all \nload within the zone – including LSEs serving customer bases that contributed nothing to the \ncapacity shortfall,” violating the principle that costs must be allocated to the entities that cause \nthem.75 PJM offered no evidence that allocating costs based on total zonal load obligations bears \nany relationship to the load growth that caused the shortfall. EKPC explained that, under the \ndefault allocation, all LSEs in a zone/area will be held accountable “regardless of whether they \nserve any large load or contributed to the need for backstop procurement,” and that LSEs cannot \nknow whether they will face the RBO allocation or the default allocation, contrary to the \nrequirement of clear and transparent procedures.76 EKPC’s Protest showed that reliance on a \npreexisting allocation methodology approved in a different context does not justify using that same \nallocation as the default for a fixed, forecast-based 15-year obligation.77 EKPC reiterated that \nPJM’s fallback RBP cost allocation “still spreads RBP costs to load without demonstrating that \nthe charged LSEs caused the procurement need or receive commensurate benefits.”78 \nIn its Order, the Commission found that PJM’s proposed cost allocation to initially assign \nRBP costs to zone/areas, “with the ultimate cost allocation to the LSEs as determined by the state \nand/or RERRA,” may be just and reasonable because it respects state authority.79 That rationale \napplies, however, only where a state or RERRA actually determines an allocation. This \njustification provides no support for the default allocation, which by definition applies when no \nstate or RERRA allocation is reported. Nor does the Commission’s finding that Load Adjustments \n \n75 Protest at 20-21 (citing Old Dominion Elec. Coop., 898 F.3d at 1260); Bednarczyk Affidavit at PP 17-18. \n76 Protest at 17-18. See also Order at P 119. \n77 Protest at 20-21; Coscia Protest Affidavit at PP 158-61. \n78 EKPC September 18 Answer at 3, 7-8. \n79 Order at PP 154, 161."},{"page":19,"startToken":6312,"endToken":6757,"text":"19 \nmay not reasonably capture load growth address the separate question of how costs are allocated \namong LSEs within a zone/area.80 \nIf the Order accepted PJM’s default allocation, the Commission failed to respond \nmeaningfully to significant objections or articulate a rational connection between the allocation \nmetric and responsibility for this procurement. The Commission’s concerns about the upstream \nzone/area allocation do not resolve the separate downstream question of which LSEs should pay \nwhen no RBO is reported.81 The Commission should grant rehearing of any acceptance of the \nfallback method. Alternatively, it should clarify that the method remains open for examination in \nthe paper hearing, including whether allocating a fixed, long-term procurement obligation by Daily \nUnforced Capacity Obligation assigns costs roughly commensurate with the burdens imposed or \nbenefits received by the charged LSEs. \nD. \nThe Commission’s Order Is Arbitrary and Capricious Because It Is \nInconsistent with the Commission’s Cost Causation Principles. \nThe Commission must provide a reasoned explanation for departing from its precedent.82 \nHere, the Commission’s Order does not clearly apply the Commission’s longstanding and well-\nestablished cost-causation principle to the challenged LSE-level allocation features. To the extent \n \n80 Order at PP 154-56. \n81 See Order at PP 153-160; Protest at 17-21; EKPC September 18 Answer at 3, 7-8. \n82 See, e.g., Motor Vehicles, 463 U.S. at 57 (“An agency’s view of what is in the public interest may change, either \nwith or without a change in circumstances. But an agency changing its course must supply a reasoned analysis . . . .”); \nW. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency \nmust provide a reasoned explanation for departing from precedent or treating similar situations differently.”) (quoting \nANR Pipeline Co. v. FERC, 71 F.3d 897, 901 (D.C. Cir. 1995)) (alteration incorporated); MISO Transmission Owners \nv. FERC, 45 F.4th 248, 264 (D.C. Cir. 2022) (“FERC is, of course, entitled to change its mind. But to do so, it must \nprovide a ‘reasoned explanation’ for its decision to disregard ‘facts and circumstances’ that justified its prior choice.”) \n(quoting FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009)); Surface Transp. Bd., 635 F.3d at 71 (“An \nagency also acts in an arbitrary and capricious manner if the ‘agency departs from its own precedent without a reasoned \nexplanation.’”) (internal citation omitted); Greater Boston, 444 F.2d at 851-53 (“An agency’s view of what is in the \npublic interest may change. . . . But an agency changing its course must supply a reasoned analysis indicating that \nprior policies and standards are being deliberately changed, not casually ignored.”) (citations omitted)."},{"page":20,"startToken":6757,"endToken":7096,"text":"20 \nthe Order accepted those features in departure from that principle, the Commission fails to explain \nwhy it departed from that principle. \nThe Commission correctly determined that the relevant legal standard to use in this \nproceeding is its cost-causation principle that requires that all approved rates “reflect to some \ndegree the costs actually caused by the customer who must pay them.”83 As the Commission \nexplained in its Order, “a cost allocation method can satisfy the cost causation principle if the \nCommission ‘has an articulable and plausible reason to believe that the benefits are at least roughly \ncommensurate with’ the allocation of the costs.”84 To the extent the Order accepted the challenged \nLSE-level allocation features rather than reserving them, it must explain their consistency with \nthat standard. \nThe independent defects discussed in Sections III.A, III.B, and III.C above present a \ncommon question: whether the wholesale allocation identifies the burdens imposed on, or benefits \nreceived by, the LSE required to pay. The Order directs further consideration of updated forecast \ninformation, which may improve the allocation among zone/areas. But the use of an updated \nforecast does not by itself justify disregarding an LSE’s resource position, failing to attribute a \nqualifying offset to its sponsor, or allocating costs to all LSEs when no RBO is reported. EKPC \ndoes not demand exact precision or deny that regional procurement may confer broader benefits. \nIt asks the Commission to identify a record-supported basis for finding that those asserted benefits \nare roughly commensurate with the particular costs imposed.85 To the extent that the Order \naccepted these features without that explanation, it departs from the standard the Commission itself \n \n83 Order at P 150 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992), and citing Ky. Pub. Serv. \nComm’n v. Am. Elec. Power Serv. Corp., 193 FERC ¶ 61,110 (2025) (Ky. Comm’n)). \n84 Order at P 150 (quoting Ill. Com. Comm’n, 576 F.3d at 477). \n85 See Order at P 150; Protest at 20-21."},{"page":21,"startToken":7096,"endToken":7378,"text":"21 \narticulated. To the extent that it deferred them, the Commission should confirm that the hearing \nencompasses these LSE-level cost-causation questions rather than only the accuracy of zone/area \nforecasts. \nE. \nThe Commission’s Order Is Arbitrary and Capricious Because It \nFailed to Address All the Issues Properly Raised Regarding Collateral \nRequirements. \nThe Commission correctly found that PJM had not adequately supported its proposed LSE \ncollateral requirement and that the requirement may be unjust and unreasonable.86 Its express \nbriefing questions on collateral requirements, however, identify for paper hearing only the initial \nRBP Credit Rate and whether posting 45 days before the Delivery Year affords sufficient time.87 \nThose questions do not clearly encompass the independent methodological objections EKPC \nraised regarding the proposed collateral requirement. Specifically, the Commission erred in failing \nto determine what exposure is secured, whether gross RBP payment value or net contract-for-\ndifferences exposure is the appropriate basis, what MW quantity applies, and how the requirement \ninteracts with Attachment Q and Peak Market Activity. The Commission also failed to address \nobjective reduction and release standards and the treatment of collateral when an LSE defaults.88 \nAs Dr. Coscia explained, these “matters go to the methodology of the credit requirement rather \nthan to the selection of a replacement figure.”89 The Credit Rate and posting deadline depend on \nthe underlying exposure and methodology. To the extent the Order accepted that methodology or \nexcluded EKPC’s objections from the hearing, its failure to address those predicate issues is \narbitrary and capricious. \n \n86 Order at PP 204-05. \n87 Order at P 206. \n88 See Coscia Reply Affidavit at PP 17-24, 71-73; EKPC September 18 Answer at 12-16. \n89 Coscia Reply Affidavit at P 17."},{"page":22,"startToken":7378,"endToken":7695,"text":"22 \nEKPC highlights here some of the arguments and evidence that it presented about the need \nto resolve the merits of the collateral requirement methodology (which must be done before the \nmechanics of the collateral requirement are addressed in the paper hearing). First, regarding the \ndetermination of the exposure to be secured through the collateral requirement, PJM’s own filing \nreinforces the distinction between gross payment value and the exposure billed through the RBP.  \nIts July 31 transmittal states that “Load Settlement is an inverse of the RBP Credits.”90 In Table 2, \nthe RBP Charge is $2,500 per day on a total resource payment of $12,500 per day, with the \nremaining $10,000 settled through RPM.91 The incremental RBP Charge is therefore the contract-\nfor-differences differential, not the combined gross payment. The collateral methodology must \nexplain why it secures the gross amount rather than the differential payable by load through the \nRBP Charge.92 \nThat distinction also identifies EKPC’s cost-allocation injury. EKPC does not challenge \nthe reliability benefit of capacity that closes the shortfall; instead, EKPC challenges the \nrequirement that load that did not cause the shortfall bear the incremental payment above the RPM \nprice, without a supported cost-causation justification. Moreover, the RBP differential varies with \nthe RPM clearing price in each Delivery Year. A supported collateral methodology must account \nfor that variation over the commitment term rather than treat gross payments as the exposure \nwithout explaining the treatment of the RPM settlement component.93 \nThe methodology also depends on which allocation applies to an LSE and when that \nallocation becomes ascertainable. The Commission should address how the RBO-based and \n \n90 PJM RBP Filing at 83. \n91 PJM RBP Filing at 82-84 & tbl. 2. \n92 See PJM RBP Filing at 79-84; Coscia Reply Affidavit at PP 16-17. \n93 See PJM RBP Filing at 79-84; Proposed Tariff, attach. DD, § 18.5(g); Protest at 21."},{"page":23,"startToken":7695,"endToken":8036,"text":"23 \ndefault allocations determine collateral obligations, the opportunity to review those inputs before \nposting, and the associated liquidity consequences.94 PJM’s September 10 Answer distinguished \nforward RBP exposure from backward-looking Peak Market Activity and offered to remove \nlanguage permitting RBP settlements to enter that calculation.95 That response leaves the question \nwhether the Tariff implements the exclusion and coordinates the RBP requirement with other \napplicable Attachment Q credit requirements; EKPC does not presume that the same exposure \nremains secured twice if the Tariff fully implements the exclusion. PJM also clarified that section \n18.9(a) reallocates defaulted RBP Charges among LSEs already responsible for RBP Charges.96 \nThe remaining question is whether and how Operating Agreement section 15.2.2 could expose \nother Members to residual losses. The Commission should resolve that interaction, including \nwhether collateral must be applied before reallocation, rather than assume that all Members face \ndirect allocation under section 18.9(a).97 \nThese issues remain material regardless of whether an LSE receives an initial RBP \nallocation. An LSE or PJM Member without incremental large-load growth or an initial allocation \nmay still face residual exposure if the governing default provisions permit it, while an allocated \nLSE must be able to identify the exposure and quantity it is required to secure.98 EKPC does not \ncontend that every LSE must post an identical amount. Rather, EKPC contends that differences in \ncollateral burdens must follow a supported measure of exposure and that the resulting default and \nliquidity risks must be addressed. The Commission’s credit standard requires a reasonable balance \n \n94 See Protest at 26-27. \n95 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to Answer and Answer of PJM \nInterconnection, L.L.C.,” at 86 & n. 259 (filed Sept. 10, 2026) (“PJM September 10 Answer”). \n96 PJM September 10 Answer at 67 n.205. See also Coscia Reply Affidavit at PP 19-24. \n97 See Coscia Reply Affidavit at PP 18-24, 71. \n98 See Coscia Protest Affidavit at PP 168-70; Coscia Reply Affidavit at PP 24, 73."},{"page":24,"startToken":8036,"endToken":8394,"text":"24 \nbetween default protection and participants’ flexibility to manage collateral, with requirements \ncorrelated to risk.99 Adjusting a percentage or posting deadline alone cannot establish that balance. \nThe Commission should clarify that the LSE collateral hearing encompasses these \nmethodological issues, including the exposure basis, applicable MW quantity, interaction with \nexisting credit requirements, reduction and release standards, application of collateral, and residual \ndefault exposure.100 To the extent that the Order accepted any of those features or excluded them \nfrom further examination, the Commission should grant rehearing and address EKPC’s supporting \nevidence.  \nPJM’s expected section 205 filing does not absolve the Commission of its obligation to \naddress the arguments and evidence presented to it. EKPC understands that PJM plans to make a \nsection 205 filing on October 29, the date of this rehearing request.101 PJM prepared a presentation \nfor the October 22 Special Members Committee meeting that previews that section 205 filing. The \npresentation describes a Credit Rate of 40% of discounted total RBP payment obligations, \nexclusion of RBP positions and associated RPM MW from Peak Market Activity, and collateral \nbased on generation coming online for the applicable Delivery Year.102 These descriptions are not \noperative tariff revisions, nor do they fully address the arguments and evidence presented by \nEKPC. If the filed Tariff fully implements the stated Peak Market Activity exclusion, the objection \nto collateralizing the same exposure twice must be evaluated in light of that change. The remaining \n \n99 Order at P 205 n.334 (citing PJM Interconnection, L.L.C., 186 FERC ¶ 61,055, at P 29 (2024)). \n100 See Coscia Reply Affidavit at PP 17, 71-73; EKPC September 18 Answer at 12-16. \n101 See PJM Interconnection, L.L.C., “Motion for Abeyance of PJM Interconnection, L.L.C.,” Docket Nos. ER26-\n3380-000, EL26-108-000 (filed Oct. 12, 2026). \n102 PJM Interconnection, L.L.C., Tariff, Section 9.2(b) Stakeholder Consultation of Upcoming 205 Filing on \nReliability Backstop Procurement, at 2, 8–10 (presentation prepared for Special Members Committee meeting, Oct. \n22, 2026), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20261022-\nspecial/item-01---1-tariff-section-92b-stakeholder-consultation-of-upcoming-205-filing-on-reliability-backstop-\nprocurement---presentation.pdf (“October 22 Presentation”)."},{"page":25,"startToken":8394,"endToken":8713,"text":"25 \nimplementation questions are whether the Tariff implements the exclusion, coordinates the RBP \nrequirement with other applicable Attachment Q requirements, and expressly confines the \ncollateral quantity to the applicable in-service MW. A change to the Credit Rate alone does not \nresolve those questions or the gross-versus-differential exposure and residual-default issues raised \nby EKPC in its Protest, Answers, and supporting Affidavits; EKPC seeks a supported \nmethodology, not merely a different initial Credit Rate.103 \nF. \nThe Commission Erred in Its Determination That There Is No Undue \nDiscrimination Between FRR Entities and RPM LSEs. \nThe Commission erred in finding that RPM self-supply LSEs are not similarly situated to \nFRR Entities, and that the RBP is therefore not unduly discriminatory, where both have taken \nmaterially similar planning actions and the Commission identified no cost-causation distinction \njustifying the differential treatment.104 The Commission found that PJM’s exclusion of FRR \nEntities from the RBP was just and reasonable and rejected arguments that the RBP unduly \ndiscriminates against self-supply LSEs that participate in the RPM. It reasoned that FRR load and \ncapacity are removed from RPM while self-supplied capacity is not, and that only FRR Entities \nfully bear the risk of over- or under-supply.105 The Commission therefore determined that the FRR \nexclusion was just and reasonable.106 \nEKPC does not ask the Commission to subject FRR Entities to the RBP. Instead, EKPC \nchallenges the Commission’s failure to explain why comparable resource-planning actions by an \nRPM self-supply LSE receive no corresponding recognition when determining that LSE’s RBP \n \n103 See October 22 Presentation at 8-10; EKPC September 18 Answer at 12-13; Coscia Reply Affidavit §§ V-VI. To \nbe clear, EKPC’s rehearing request addresses the Order and does not prejudge the final section 205 filing. \n104 See 16 U.S.C. § 824d(b); Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 367 (D.C. Cir. 2002). \n105 Order at P 151. \n106 Order at P 151."},{"page":26,"startToken":8713,"endToken":9028,"text":"26 \nexposure.107 The relevant inquiry is not whether FRR Entities and RPM self-supply LSEs are \nidentical in every respect, but whether the differences identified justify the challenged treatment \nunder RBP.108 Both FRR Entities and RPM self-supply LSEs engage in planning to cover their \nload obligations. In that regard, they are similarly situated. But only RPM self-supply LSEs are \nsubject to RBP costs, even though those LSEs have sufficient resources for their load-serving \nobligations (just like FRR Entities). The Commission identified RPM participation and the ability \nto purchase additional capacity or sell excess capacity as distinctions.109 Those distinctions require \nanalysis of whether, and to what extent, an RPM self-supply LSE with sufficient owned or \ncontracted resources contributes to the shortfall or receives benefits commensurate with its \nassigned RBP costs. Excluding FRR Entities because their load and resources are removed from \nRPM does not, without that analysis, explain why an RPM self-supply LSE’s comparable planning \nactions warrant no recognition in its own RBP exposure. As a result, the Commission’s Order runs \nafoul of the FPA section 205(b) prohibition on unreasonable differences in rates among similarly \nsituated customers.110 \nThe Commission’s reliance on FRR Entities’ assumption of over- and under-supply risk \nlikewise requires a connection to the costs at issue.111 EKPC does not deny that RPM participation \nprovides access to pooled capacity. But that access alone does not establish that every self-supply \nLSE caused this incremental procurement need or receives benefits sufficient to justify its \nparticular RBP Charges, collateral burdens, and default exposure.112 The Commission must \n \n107 See Protest at 45-47; Bednarczyk Affidavit at PP 59-60, 64. \n108 See N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018). \n109 Order at P 151. \n110 16 U.S.C. § 824d(b). \n111 See Order at P 151. \n112 See Bednarczyk Affidavit at PP 60-62, 64; Protest at 45-47."},{"page":27,"startToken":9028,"endToken":9328,"text":"27 \nexplain why the identified differences are material to those obligations rather than treat the \ndistinction between FRR and RPM participation as dispositive. \nThe temporary suspension of the FRR Commitment Insufficiency Charge further qualifies \nthe Commission’s reliance on FRR Entities’ assumption of supply risk. For the 2025/2026 through \n2028/2029 Delivery Years, no FRR Commitment Insufficiency Charge will be assessed.113 That \nsuspension does not eliminate FRR supply risk throughout an RBP commitment that may run \nthrough 2042/2043; RAA, Schedule 8.1, section D.7 resumes the insufficiency charge beginning \nin 2029/2030.114 EKPC’s comparability argument therefore does not depend on identical risk \nthroughout the term. It rests on the Commission’s failure to explain why comparable planning \nactions that avoid contributing to the shortfall warrant different treatment in assigning RBP \nexposure. \nG. \nThe Commission’s Acceptance of the RBP Is Not Based on Substantial \nEvidence and Therefore Is Arbitrary and Capricious. \nTo the extent that the Order accepted the challenged allocation and collateral features, the \nCommission did not adequately address the evidence supporting EKPC’s objections. A \ngeneralized regional reliability benefit does not itself answer the LSE-specific allocation and \nexposure questions presented here. The Commission erred by failing to meaningfully address \nevidence in the record on cost causation, which was provided by EKPC in its Protest and in the \nBednarczyk and Coscia Affidavits. In the Bednarczyk Affidavit, EKPC provided evidence \nshowing how the RBP “creates cost, credit, collateral, and risk allocation obligations that do not \nconsistently satisfy the principles of transparency, traceability, and cost causation.”115 The \n \n113 RAA, Schedule 8.1, section D.7; EKPC September 18 Answer at 11, n.43. Section D.7 provides that the FRR \nCommitment Insufficiency Charge resumes beginning with the 2029/2030 Delivery Year. \n114 Id. \n115 Bednarczyk Affidavit at P 7."},{"page":28,"startToken":9328,"endToken":9658,"text":"28 \nevidence also shows that the RBP converts what should be a targeted, incremental large-load cost-\ncausation problem into a generalized load-ratio obligation that penalizes self-supply LSEs that \nacted prudently and rewards policies that incentivize inadequate resource planning.116 And Mr. \nBednarczyk shows that the RBP cost allocation process proposed by PJM “does not provide a \ntransparent means for an LSE to assess its wholesale RBP exposure, evaluate the benefits of \nqualifying offsets or opt-outs, understand its related credit obligations, or determine whether its \nactions will make it reliability neutral.”117 Moreover, with respect to the proposed default cost \nallocation method, Mr. Bednarczyk provides evidence that the “Daily Unforced Capacity \nObligation is a broad capacity allocation metric,” and “it does not identify the LSEs that created \nthe residual procurement need.”118 The Commission should address this evidence to the extent it \naccepted the challenged features or clarify that the evidence remains for consideration in the paper \nhearing. \nSimilarly, the Coscia Affidavits address whether the LSE collateral requirement is tied to \nmeasured exposure, whether the same exposure may be secured twice, and how an obligation based \non a default allocation can be determined and reviewed.119 They also identify the interaction \nbetween proposed Tariff Attachment DD section 18.9(a) and Operating Agreement section \n15.2.2.120 PJM’s clarification that section 18.9(a) reallocates defaults among LSEs already paying \nRBP Charges does not resolve the separate question of residual exposure under the Operating \nAgreement.121 That question matters to any PJM Member without an initial RBP allocation and \n \n116 Bednarczyk Affidavit at PP 7, 9, 12, 18. \n117 Bednarczyk Affidavit at P 14. \n118 Bednarczyk Affidavit at P 17. \n119 See Coscia Reply Affidavit at PP 17, 24, 71-73; EKPC September 18 Answer at 12-16. \n120 See Coscia Reply Affidavit at PP 18-24; EKPC September 18 Answer at 12. \n121 See PJM September 10 Answer at 67 n.205, 84 & n.252; Coscia Reply Affidavit at PP 18–24."},{"page":29,"startToken":9658,"endToken":9803,"text":"29 \ndoes not depend on an assumption that the LSE will receive no allocation under revised inputs. \nThe Commission must address whether such residual exposure exists, what collateral secures it, \nand how it is consistent with cost causation. EKPC’s evidentiary objection concerns the absence \nof that analysis, not a prediction of its allocation under a future filing. \nThe Commission is required to address the arguments and evidence presented to it.122 To \nthe extent that the Order accepted the challenged features without addressing that evidence, the \nCommission should grant rehearing and provide a reasoned determination; alternatively, it should \nclarify that these evidentiary issues remain open for paper hearing. \n \n122 See, e.g., BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 270 (D.C. Cir. 2014); New England Power \nGenerators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018)."},{"page":30,"startToken":9803,"endToken":9952,"text":"30 \nIV. Conclusion \nWherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the \nCommission grant rehearing for the reasons discussed herein or, where the Order’s reservation of \nan issue is unclear, clarify that the paper hearing encompasses the independent LSE-level cost-\nallocation, offset-attribution, and collateral-methodology issues identified above without an \nadverse determination on their merits. \n \nRespectfully submitted, \n \n \nDenise R. Foster Cronin \nChief Compliance Officer and Senior Vice \nPresident \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTel.: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \nOn Behalf of \nEast Kentucky Power Cooperative, Inc. \n \n/s/ Daniel E. Frank \n \n \nDaniel E. Frank \nAllison E. S. Salvia \nKelly A. Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTel.: 202-383-0100 \nEmail: danielfrank@eversheds-sutherland.com \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \nCounsel for \nEast Kentucky Power Cooperative, Inc. \n \n \n \n \nDated: October 29, 2026"},{"page":31,"startToken":9952,"endToken":10000,"text":"Certificate of Service \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC this 29th day of October, 2026.  \n/s/ Kelly A. Cuthbertson \n \nKelly A. Cuthbertson"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1142,"startToken":0,"endToken":398},{"p":2,"at":1142,"title":"I. Background","method":"printed heading","endPage":2,"endAt":1158,"startToken":398,"endToken":400},{"p":2,"at":1158,"title":"A. RBP Proposal","method":"printed heading","endPage":3,"endAt":667,"startToken":400,"endToken":628},{"p":3,"at":667,"title":"B. Protest","method":"printed heading","endPage":7,"endAt":277,"startToken":628,"endToken":1856},{"p":7,"at":277,"title":"C. The Commission’s Order Accepting the RBP Proposal Subject to","method":"printed heading","endPage":8,"endAt":1242,"startToken":1856,"endToken":2276},{"p":8,"at":1242,"title":"II. Statement of Issues and Specification of Errors","method":"printed heading","endPage":11,"endAt":648,"startToken":2276,"endToken":3736},{"p":11,"at":648,"title":"III. Request for Rehearing","method":"printed heading","endPage":12,"endAt":486,"startToken":3736,"endToken":4129},{"p":12,"at":486,"title":"A. The Commission Erred by Failing to Address EKPC’s Argument That","method":"printed heading","endPage":14,"endAt":850,"startToken":4129,"endToken":4822},{"p":14,"at":850,"title":"B. The Commission Erred by Failing to Address EKPC’s Argument That","method":"printed heading","endPage":17,"endAt":574,"startToken":4822,"endToken":5765},{"p":17,"at":574,"title":"C. The Commission’s Order Is Arbitrary and Capricious Because It Fails","method":"printed heading","endPage":19,"endAt":928,"startToken":5765,"endToken":6447},{"p":19,"at":928,"title":"D. The Commission’s Order Is Arbitrary and Capricious Because It Is","method":"printed heading","endPage":21,"endAt":211,"startToken":6447,"endToken":7126},{"p":21,"at":211,"title":"E. The Commission’s Order Is Arbitrary and Capricious Because It","method":"printed heading","endPage":25,"endAt":532,"startToken":7126,"endToken":8467},{"p":25,"at":532,"title":"F. The Commission Erred in Its Determination That There Is No Undue","method":"printed heading","endPage":27,"endAt":914,"startToken":8467,"endToken":9162},{"p":27,"at":914,"title":"G. The Commission’s Acceptance of the RBP Is Not Based on Substantial","method":"printed heading","endPage":30,"endAt":4,"startToken":9162,"endToken":9804},{"p":30,"at":4,"title":"IV. Conclusion","method":"printed heading","endPage":31,"endAt":0,"startToken":9804,"endToken":9952},{"p":31,"at":0,"title":"Certificate of Service","method":"printed heading","endPage":31,"endAt":305,"startToken":9952,"endToken":10000}]}