{"document":{"slug":"rec-20261104-5209","title":"Preliminary Answer of PJM Interconnection L.L.C. Opposing Fast-Track Processing and Motion for Extension of Time to Answer Exelon Corporation’s 11/03/2026…","issued":"2026-11-04","accession":"20261104-5209","docket":"EL27-11-000","group":"Exelon complaint seeking a prompt PJM capacity auction","filer":"PJM Interconnection, L.L.C.","kind":"answer","file":"sources/filings/text/20261104-5209_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261104-5209","tier":"record","sha256":"2e2b979b70cd5051e005718a9c705960650bb17be488786084a235ed8f36ad91","pages":13,"tokens":3395,"emptyPages":[],"textThemes":["adequacy","procedure"]},"pages":[{"page":1,"startToken":0,"endToken":251,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nExelon Corporation \n \nComplainant, \n \n                        v.  \n \nPJM Interconnection, L.L.C.  \nRespondent. \n \n) \n) \n) \n) \n) \n) \n) \n \n \n \nDocket No. EL27-11-000 \n \n \nPRELIMINARY ANSWER OF PJM INTERCONNECTION L.L.C. OPPOSING \nFAST-TRACK PROCESSING AND  \nMOTION FOR EXTENSION OF TIME TO ANSWER \n \nPursuant to Rules 213, 212 and 2008 of the Federal Energy Regulatory \nCommission’s (“Commission”) Rules of Practice and Procedure,1 PJM Interconnection, \nL.L.C. (“PJM”) respectfully submits this Preliminary Answer to the Complaint Requesting \nFast-Track Processing (“Complaint”) filed by Exelon Corporation (“Exelon”) on \nNovember 3, 2026,2 and moves for an extension of time, through December 21, 2026, to \nsubmit its answer to the Complaint.  This Preliminary Answer only contests the \nComplaint’s request for fast-track processing.  PJM also requests a four-week extension of \ntime to answer the Complaint on the merits.  As discussed further below, the Complaint \nraises complex issues that warrant careful consideration, and PJM is currently devoting \nsignificant resources to ongoing efforts within the PJM Region to develop and file \nsubstantial revisions to multiple PJM governing documents by the end of the year.3  \n \n1 18 C.F.R. §§ 385.213, 385.212 and 385.2008. \n2 Exelon v. PJM, Complaint Requesting Fast Track Processing of Exelon Corporation, Docket No. EL27-11-\n000 (Nov. 3, 2026) (“Complaint”).  \n3 Capitalized terms used herein and not otherwise defined have the meaning used in the Open Access \nTransmission Tariff, the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C., the \nPJM Reliability Assurance Agreement, or the PJM Manuals."},{"page":2,"startToken":251,"endToken":567,"text":"2 \nGranting the requested extension will allow PJM to have a meaningful opportunity to fully \naddress the issues raised in the Complaint, thereby facilitating a complete and well-\ndeveloped record for Commission consideration. \nPJM further requests that the Commission apply the five-day comment period \napplicable to motions for extension of time, such that responses would be due on November \n9, 2026.4  PJM also respectfully requests that the Commission establish the schedule for \nanswering the Complaint as promptly as practicable. \nI. \nPRELIMINARY ANSWER OPPOSING FAST-TRACK PROCESSING \nThe Complaint requests fast-track processing of its Complaint and asks the \nCommission to find that the existing three-year forward procurement period employed in \nPJM’s Reliability Pricing Model is no longer just and reasonable and to replace it with a \n“prompt” auction construct.  However, the Complaint fails to satisfy the stringent standard \nnecessary to justify fast-track processing.  Commission precedent makes clear that fast-\ntrack procedures are generally reserved for comparatively straightforward tariff disputes \nand are not well suited to proceedings involving complex or far-reaching policy issues.5  \nTo qualify for fast-track processing, a complainant must present “a highly credible claim \nand persuasive showing that standard processes will not be capable of resolving the \ncomplaint promptly enough to provide meaningful relief.”6  Because expedited schedules \nimpose a substantial burden on the parties and can strain the Commission’s resources, fast-\ntrack processing is appropriately reserved for only the most limited circumstances. \n \n4 See 18 C.F.R. § 385.213(d)(1)(i) (“If a motion requests an extension of time or a shortened time period for \naction, then answers to the motion to extend or shorten the time period shall be made within 5 days after the \nmotion is filed, unless otherwise ordered.”). \n5 See e.g. Amoco Energy Trading Corp. v. El Paso Natural Gas, 89 FERC ¶ 61,165 (1999). \n6 See Fast Track Procedures, available at https://www.ferc.gov/fast-track-procedures."},{"page":3,"startToken":567,"endToken":933,"text":"3 \nThe Complaint makes no such showing.  Exelon offers only a single justification \nfor its request, asserting that fast-track processing would “facilitate a Commission order by \nno later than January 31, 2027, the day before PJM is scheduled to post planning parameters \nfor the 2030/2031 Delivery Year Base Residual Auction.”7  But Exelon never explains why \na Commission order by that date is necessary to preserve meaningful relief.  Nor could it.  \nEven assuming, arguendo, that the Commission were ultimately to conclude that the \nexisting three-year forward capacity market construct is unjust and unreasonable, the \nFederal Power Act provides a mechanism to preserve any potential remedy through the \nestablishment of a refund effective date, including the January 1, 2027 refund effective \ndate requested by Exelon.8  Accordingly, Exelon fails to demonstrate that the \nCommission’s ordinary processes are incapable of providing meaningful relief. \nFast-track processing is particularly inappropriate here because the Complaint \nchallenges a foundational element of PJM’s Reliability Pricing Model.  The issues raised \nby Exelon extend far beyond a discrete tariff interpretation dispute and instead implicate \nfundamental questions regarding several key components of the design and operation of \nPJM’s capacity market.  Evaluation of changes to such rules requires careful consideration \nand input from PJM’s diverse stakeholder body so as to not further exacerbate the resource \nadequacy issues facing the PJM Region.9   \n \n7 Complaint at 5. \n8 See Section 206(b) of the Federal Power Act, 16 U.S.C. 824e(b) (“At the conclusion of any proceeding \nunder this section, the Commission may order refunds of any amounts paid, for the period subsequent to the \nrefund effective date through a date fifteen months after such refund effective date, in excess of those which \nwould have been paid under the just and reasonable rate, charge, classification, rule, regulation, practice, or \ncontract which the Commission orders to be thereafter observed and in force….”). \n9 PJM disagrees with Exelon’s assertion that a prompt auction is just and reasonable on its own without a \nsuite of complementary enhancements needed to produce, in Exelon’s words, “a more durable resource \nadequacy construct that can reliably support the efficient entry and exit of Capacity Resources from the PJM \nRegion . . . .”  Complaint at 6-7."},{"page":4,"startToken":933,"endToken":1178,"text":"4 \nPJM is already evaluating a range of comprehensive reforms to address issues \nrelated to the Reliability Pricing Model.  As part of that effort, PJM recently released its \nPowering Reliability Through Market Design white paper, which identifies three broad \npathways for maintaining long-term resource adequacy and reliability in the PJM region.10  \nSince issuing the paper, PJM has received extensive feedback from stakeholders and other \ninterested parties and is actively evaluating those comments with the objective of \ndeveloping a clear roadmap for market reforms and related Commission filings after a \nstakeholder-informed process. \nIn short, this proceeding presents precisely the type of complex and consequential \nissues for which the Commission has historically declined to employ fast-track \nprocedures.11  Granting Exelon’s request would unnecessarily hinder the ability of PJM \nand other interested stakeholders to develop and present the factual, technical, and policy \nconsiderations focused on holistic solutions which should be relevant to the Commission’s \ndecision.  The Commission should therefore deny Exelon’s request for fast-track \nprocessing. \nII. \nMOTION FOR EXTENSION OF TIME \nAbsent Commission action, pursuant to Rule 206(f), answers to the Complaint \nwould be due twenty days after the Complaint’s filing date, or November 23, 2026.  PJM \nrespectfully requests that the Commission extend that deadline by four weeks, until \nDecember 21, 2026. \n \n10 PJM, Powering Reliability Through Market Design Paper (May 6, 2026), https://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-\nmarket-design.pdf.  \n11 Amoco Energy Trading Corp., 89 FERC ¶ 61,165 (1999)."},{"page":5,"startToken":1178,"endToken":1456,"text":"5 \nGood cause exists for the requested extension.  First, additional time will permit \nPJM to incorporate into its response the outcome of imminent deliberations by the PJM \nBoard regarding the path forward for the Base Residual Auction for the 2030/2031 \nDelivery Year.  The PJM Board is scheduled to consider these very issues at its November \n17, 2026 meeting, and the PJM Board’s determinations are expected to substantially inform \nPJM’s position regarding the issues raised in the Complaint.  Allowing PJM’s answer to \nreflect the results of those deliberations will provide the Commission with a more complete \nand informed record. Further, following the PJM Board’s deliberations, PJM anticipates \nproviding a timeline that outlines the stakeholder process through which a comprehensive \npackage of capacity market enhancements, along with any associated filing(s), will be \ndeveloped and finalized in PJM’s forthcoming answer. \nSecond, as discussed further below, Exelon has failed to demonstrate any \ncompelling reason for Commission action by the requested January 31, 2027 date.  \nAccordingly, granting a modest four-week extension of the answer deadline will not impair \nthe Commission’s ability to act under section 206 of the Federal Power Act should it \nultimately determine that modifications to PJM’s three-year forward capacity market are \nwarranted.  Rather, the requested extension will ensure that PJM has a meaningful \nopportunity to fully address the complex issues presented in the Complaint and will better \nposition the Commission to consider those issues based on a complete and well-developed \nrecord.   \nA. Legal Consequences Do Not Attach Merely When Planning Parameters Are \nPosted. \n \nExelon’s request for fast-track processing rests entirely on its assertion that the \nCommission should issue an order before PJM posts the planning parameters for the"},{"page":6,"startToken":1456,"endToken":1798,"text":"6 \n2030/2031 Base Residual Auction on January 31, 2027.  Implicit in that argument is the \nsuggestion that Commission action after that date could run afoul of the prohibition against \nretroactive ratemaking.  That suggestion is unfounded. \nBoth the Commission and the courts evaluate retroactivity under the rubric \nestablished by the Supreme Court in Landgraf v. USI Film Products.12  The salient question \nunder Landgraf is at what point in the auction process would a change in the capacity \nauction rules attach new legal consequences.13  As the Supreme Court explained, a rule is \nimpermissibly retroactive where it “would impair rights a party possessed when he acted, \nincrease a party’s liability for past conduct, or impose new duties with respect to \ntransactions already completed.”14  Applying those principles in the capacity market \ncontext, the critical question is not when planning parameters are posted, but when Market \nParticipants take action in reliance on those parameters that carries legal consequences.  \nThose consequences do not arise merely because PJM posts planning parameters.  Rather, \nthey arise when Market Participants submit binding offers into the auction.  Indeed, PJM’s \nOpen Access Transmission Tariff (“Tariff”) already provides express authority to update \nthe planning parameters in certain circumstances.15 \n \n12 Landgraf v. USI Film Products, 511 U.S. 244 (1994).  See Affirmed Energy, LLC v. FERC, 166 F.4th 1070 \n(D.C. Cir. 2026), PJM Power Providers Group v. FERC, 96 F.4th 390, 398-399 (3d. Cir. 2024) (noting that \ncourts routinely apply Landgraf's well-worn retroactivity principles to all sorts of agency actions — including \nFERC’s), and Basin Elec. Power Coop., 177 FERC ¶ 63,020 (2021).  \n13 PJM Power Providers Group v. FERC, 96 F.4th at 398 (quoting Landgraf, 511 U.S. at 269-70, 280). \n14 Landgraf, 511 U.S. at 280. \n15 See e.g. Tariff, Attachment DD, section 5.11(a) (requiring PJM to post “[t]he PJM Region Reliability \nRequirement, and the Variable Resource Requirement Curve for the PJM Region, including the details of \nany adjustments to account for Price Responsive Demand and any associated PRD Reservation Prices”)."},{"page":7,"startToken":1798,"endToken":2124,"text":"7 \nThe Third Circuit’s decision in PJM Power Providers Group v. FERC confirms \nthis distinction.16  There, the court held that a tariff revision approved by the Commission \nduring the conduct of a capacity auction was impermissibly retroactive because PJM had \nalready opened the offer window and Market Participants had submitted binding offers \nbased on the previously posted planning parameters.17  Under those circumstances, the \nCommission’s action altered the legal consequences of conduct that had already occurred, \nthereby “nullif[ying] a legal consequence attached to a past action taken in the Auction.”18  \nSignificantly, the court did not hold that legal consequences attach upon the mere posting \nof planning parameters.  To the contrary, the court’s reasoning focused on the fact that \nMarket Participants had already taken binding action in reliance on those parameters.  The \nprohibition against retroactive ratemaking therefore protects reliance interests that arise \nonce Capacity Market Sellers submit binding offers, not merely expectations that may exist \nbefore any such action occurs.19   \nThis distinction reflects the underlying purpose of the filed-rate doctrine and the \nrule against retroactive ratemaking, which is to promote stability and predictability in \nregulated markets.20  While the posting of planning parameters may inform market \nexpectations, expectations alone do not create vested rights or legal consequences.  As the \n \n16 PJM Power Providers Group v. FERC, 96 F.4th at 399._ \n17 Id. at 402. \n18 Id. at 401. \n19 See ISO New Eng. Inc., 196 FERC ¶ 61,172, at P 43 (2026) (rejecting claim of retroactive rate making and \nexplaining that in the PJM Power Providers decision the court explained that \"retroactive rules alter the past \nlegal consequences of past actions\" and found that that [PJM] tariff change was retroactive “because it altered \nthe legal consequence attached to a past action when it allowed PJM to use a different LDA Reliability \nRequirement than the one it had calculated and posted.”).  \n20 PJM Power Providers Group v. FERC, 96 F.4th at 402."},{"page":8,"startToken":2124,"endToken":2426,"text":"8 \nD.C. Circuit has explained, the rule against retroactive ratemaking “does not protect a \nutility’s expectation that a rate will not change in the future.”21  \nAccordingly, Exelon has failed to demonstrate why Commission action is required \nby January 31, 2027.  The posting of planning parameters, standing alone, does not \nestablish the type of completed transaction or legally consequential market conduct that \nwould later constrain the Commission’s ability to act.  In short, the Commission need not \nadopt an expedited schedule to preserve its authority under section 206 of the Federal \nPower Act to order changes to PJM’s capacity market if it ultimately determines that such \nchanges are warranted. \nB. Market Participants Receive Adequate Prior Notice Upon Establishment of \nthe Refund Effective Date So Any Posted Planning Parameters May Be \nSubject to Revision Under Section 206 of the Federal Power Act \n \nApart from the fact that no legal consequences attach merely upon the posting of \nplanning parameters, Exelon brought this proceeding under section 206 of the FPA.  Under \nthe statutory framework established by Congress, the FPA expressly contemplates that \nrates, rules, and practices subject to a section 206 complaint remain subject to Commission \nreview and potential modification following the establishment of a refund effective date.  \nUpon the filing of a complaint and the establishment of a refund effective date, Market \nParticipants are placed on notice that the challenged rate, term, or condition may ultimately \nbe found unjust and unreasonable and that the Commission may order prospective relief, \nas well as refunds dating back to the refund effective date.22  \n \n21 Louisiana Public Service Commission v. FERC, 10 F.4th 839 (D.C. Cir. 2021) (“the rule against retroactive \nrate making does not protect a utility’s expectation that a rate will not change in the future.”). \n22 16 U.S.C. § 824e(b)."},{"page":9,"startToken":2426,"endToken":2695,"text":"9 \nThe D.C. Circuit recently reaffirmed this principle, explaining that section 206(b) \noperates as a statutory “exception to the filed-rate doctrine’s general prohibition of \nretroactive rate modifications” and authorizes the Commission to provide relief reaching \nback to the refund effective date established upon the filing of a complaint.23  There, the \ncourt emphasized that the refund effective date serves a critical notice function because it \ninforms Market Participants that the challenged tariff provision is subject to potential \nCommission revision and refund liability from that point forward.24  \nThus, even assuming, arguedo, that the legal consequences attach when planning \nparameters are posted, section 206 independently defeats any claim that Commission \naction after that date would constitute impermissible retroactive ratemaking.  The D.C. \nCircuit has expressly rejected the notion that the filed-rate doctrine bars Commission action \nunder section 206 of the FPA.25  That is, Congress specifically authorized the Commission, \nthrough section 206, to modify existing rates and provide refund relief after establishing a \nrefund effective date, thereby placing all affected parties on notice that the challenged rate \nstructure remains provisional pending resolution of the complaint.  To be clear, the \nCommission has historically been reluctant to order refunds with respect to final market \nresults, and PJM has opposed such requests for refund relief.  PJM references the Court’s \ndecision solely to demonstrate that the Commission need not issue an order on the \nunderlying complaint prior to PJM posting the planning parameters. \n \n23 Maryland Office of People's Counsel v. FERC, 164 F.4th 920, 927 (D.C. Cir. 2026) (internal quotation \nmarkets removed). \n24 Id. at 928-30. \n25 Id. at 927."},{"page":10,"startToken":2695,"endToken":2985,"text":"10 \nThe filing of Exelon’s section 206 complaint put Market Participants on notice that \nPJM’s existing capacity market construct challenged by the Complaint may ultimately be \nmodified by Commission order.  Accordingly, once the refund effective date is established, \nstakeholders have legally sufficient notice that the existing rules may be revised and that \nany resulting relief may relate back to that date.  Exelon therefore cannot demonstrate that \nCommission action is required by January 31, 2027, to preserve the Commission’s \nauthority to grant meaningful relief.  For that reason as well, Exelon’s request for fast-track \nprocessing should be denied and the Commission should grant a four-week extension of \ntime to answer Exelon’s complaint. \nC. PJM is Scheduled to Post Planning Parameters By March 1, 2027 for the \n2030/2031 Base Residual Auction. \n \nFurther undermining Exelon’s claim of urgency, the Commission recently accepted \nTariff revisions that require PJM to post the PJM Region Reliability Requirement and the \nLocational Deliverability Area Reliability Requirement by March 1 preceding each Base \nResidual Auction.26  Consistent with that order and the updated Tariff,27 PJM will revise \nits pre-auction schedule and now anticipates posting the planning parameters for the \n2030/2031 Base Residual Auction on or before March 1, 2027.  Accordingly, even if the \nCommission were to conclude that action should be taken before the planning parameters \nfor the 2030/2031 Base Residual Auction are posted, the Commission would have until \nFebruary 28, 2027, rather than January 31, 2027, to act (i.e., four extra weeks).  Exelon’s \nasserted deadline therefore no longer reflects PJM’s anticipated pre-auction schedule for \nposting the planning parameters. \n \n26 PJM Interconnection, L.L.C., Delegated Letter Order, Docket No. ER26-3661-000 (Oct. 30, 2026). \n27 See Tariff, Attachment DD, section 5.10(a)(iv)(B)."},{"page":11,"startToken":2985,"endToken":3153,"text":"11 \nFor this additional reason, granting PJM’s request for a four-week extension of time \nto answer the Complaint, through December 21, 2026, will not prejudice any party, \nconstrain the Commission’s consideration of the issues presented, or otherwise impair the \nCommission’s ability to exercise its authority under section 206 of the Federal Power Act \nshould it ultimately determine that changes to PJM’s capacity market rules are warranted. \nIII. \nCONCLUSION \nFor the reasons set forth herein, PJM respectfully requests that the Commission \ndeny Exelon’s request for fast-track processing.  PJM further requests that the Commission \npromptly grant PJM’s request for an extension of time, through December 21, 2026, to \nanswer the Complaint.  Good cause exists for the requested four-week extension as it will \nafford PJM and other interested parties a meaningful opportunity to review, analyze, and \nrespond to the significant legal, policy, and market-design issues raised by the Complaint.  \nGranting the requested extension will facilitate the development of a comprehensive and \nwell-supported record upon which the Commission can base its determination."},{"page":12,"startToken":3153,"endToken":3320,"text":"12 \n \nFinally, the requested extension will not prejudice any party or impair the \nCommission’s ability to grant relief, if warranted.  As discussed above, the extension has \nno effect on the Commission’s authority under section 206 of the Federal Power Act28 to \nestablish a refund effective date and, if appropriate, order relief in this proceeding.  \nAccordingly, for good cause shown, the Commission should deny Exelon’s request for \nfast-track processing, grant PJM’s motion for an extension of time, and establish December \n21, 2026, as the deadline for answers to the Complaint. \n \nRespectfully submitted,  \n               /s/ Chenchao Lu  \nCraig Glazer \nVice President – Federal Government \nPolicy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 (phone) \n(202) 393-7741(fax) \nCraig.Glazer@pjm.com \n \nChenchao Lu \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n(610) 666-2255 (phone) \n(610) 666-8211 (fax) \nChenchao.Lu@pjm.com \nNovember 4, 2026 \n \nCounsel for \nPJM Interconnection, L.L.C. \n \n \n28 16 U.S.C. § 824e."},{"page":13,"startToken":3320,"endToken":3395,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Audubon, PA., this 4th day of November 2026. \n \n /s/ Chenchao Lu \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n(610) 666-2255 (phone) \n(610) 666-8211 (fax) \nChenchao.Lu@pjm.com \n \nAttorney for  \nPJM Interconnection, L.L.C."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":538,"startToken":0,"endToken":331},{"p":2,"at":538,"title":"I. PRELIMINARY ANSWER OPPOSING FAST-TRACK PROCESSING","method":"printed heading","endPage":4,"endAt":1174,"startToken":331,"endToken":1096},{"p":4,"at":1174,"title":"II. MOTION FOR EXTENSION OF TIME","method":"printed heading","endPage":5,"endAt":1634,"startToken":1096,"endToken":1419},{"p":5,"at":1634,"title":"A. Legal Consequences Do Not Attach Merely When Planning Parameters Are","method":"printed heading","endPage":8,"endAt":711,"startToken":1419,"endToken":2233},{"p":8,"at":711,"title":"B. Market Participants Receive Adequate Prior Notice Upon Establishment of","method":"printed heading","endPage":10,"endAt":756,"startToken":2233,"endToken":2805},{"p":10,"at":756,"title":"C. PJM is Scheduled to Post Planning Parameters By March 1, 2027 for the","method":"printed heading","endPage":11,"endAt":446,"startToken":2805,"endToken":3051},{"p":11,"at":446,"title":"III. CONCLUSION","method":"printed heading","endPage":13,"endAt":0,"startToken":3051,"endToken":3320},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":483,"startToken":3320,"endToken":3395}]}